Understanding the Auckland electricity network

Size: px
Start display at page:

Download "Understanding the Auckland electricity network"

Transcription

1 Understanding the Auckland electricity network

2 Introduction This presentation describes how electricity reaches homes and businesses in Auckland, with a particular focus on the distribution network run by Vector. Vector is responsible for delivering electricity to 544,513 Aucklanders on behalf of electricity retailers. Vector s network supplies customers from Wellsford in the north, to parts of Papakura in the south. Vector s network is comprised on 18,093 kilometres of overhead lines and underground cables.

3 How electricity reaches Vector s network Sub transmission network Transmission network Power stations Electricity is generated at power stations e.g. Benmore hydro-power. network Electricity is transported from power stations around the country via s transmission network the National Grid to local electricity distribution networks (like Vector). Local electricity distribution networks connect to s transmission network at Grid Exit Points (GXPs). GXPs are large s where the power voltage is reduced from 220kV/110kV transmission voltages for supply into local distribution networks. Grid Exit Points (GXP) (14 in Auckland) Vector network From GXPs power flows into Vector s 110kV/33kV/22kV sub-transmission network and is transported to Vector zone s. High Voltage (HV) network s (107 in Auckland) At zone s, the voltage is further reduced and electricity transported via the High Voltage (HV) network to distribution s. Low Voltage (LV) network s (23,602 in Auckland) s reduce the voltage again and feed electricity into the Low Voltage (LV) network which supplies power directly to customers. NOTE: Some commercial and industrial customers require power at higher voltages and are supplied directly from Vector s sub-transmission or High Voltage (HV) network. (544,513 in Auckland) Vector is responsible for delivering power to 544,513 customers in Auckland from Wellsford in the north to parts of Papakura in the south via its 18,093km network of overhead lines and underground cables.

4 How electricity flows through Vector s Auckland network From Grid Exit Points (GXPs) electricity flows into Vector s sub-transmission network and is transported to zone s. Power stations The voltage is reduced at zone s and supplied to distribution s. From here the voltage is reduced again and supplied into the Low Voltage (LV) lines network which provides power directly to customers. network Grid Exit Point (GXP) Grid Exit Point (GXP) possible possible possible Vector s network design enables use of backfeeding to temporarily restore power supply to customers by supplying power from adjacent areas. This can only be achieved if the power supply allows i.e. demand for power in the area is less than available supply. In some cases, Vector will temporarily switch off customers hot water cylinders to free up electricity for backfeeding. The following slides explain how backfeeding is used.

5 Loss of supply at a GXP Partial loss of power supply at a GXP will not affect the power supply out of the GXP. However, total power loss at a GXP such as through de-energisation will. This causes loss of power to the Vector zone s the GXP supplies, and subsequently to the network that feeds customers from the affected zone s. Power stations network Grid Exit Point (GXP) possible Vector can reconfigure its network to backfeed and liven parts of the affected network. Grid Exit Point (GXP) possible possible

6 Loss of supply at a Vector zone If power supply is lost at one of Vector s zone s, Vector can reconfigure its network to enable backfeeding to liven parts of the affected network. Power stations network Grid Exit Point (GXP) Grid Exit Point (GXP) possible possible active

7 Loss of supply at a Vector distribution If there is a power failure at a Vector distribution the outage will be localised and only affects the customers supplied from the distribution. Power stations is not possible at this localised level (between the distribution and the customers) because there is only a single feed to the customers. network Grid Exit Point (GXP) Grid Exit Point (GXP) possible possible possible

8 Understanding the development of the Penrose GXP

9 How the Penrose GXP has developed The Penrose Grid Exit Point (GXP) was built in the early 1920 s. Building and development around the Penrose GXP from the 1940s onwards, including construction of the Southern motorway bordering the site, has constrained the site from expanding. It has also limited exit routes for Vector s sub-transmission cables. Significant load growth (demand for electricity) in the surrounding areas, and development in the site to meet this demand has added further site constraints. The is built on hard basalt rock which makes alternative corridors difficult to construct.

10 The Penrose GXP The Penrose Grid Exit Point (GXP) is the largest of the 14 connections between s transmission grid and Vector s network. CBD tunnel portal Penrose has two separate switchyards (110kV and 220kV). 33kV switchgear Cables feed: Glen Innes, Newmarket (part), The Drive 110kV switchyard 220kV switchyard Cables feed: Mt Wellington, Westfield (part), Carbine, Sylvia park, McNab (part) CBD 33kV switchyard Cables feed: Remuera, Newmarket (part), St Johns, Orakei, St Heliers Cables feed: McNab (part), Onehunga, Te Papapa, Westfield (part), Rockfield Vector cable corridor in the residential suburbs in the Eastern Bays, Remuera and Epsom, the commercial/retail suburb of Newmarket, and the industrial area through Penrose, Westfield and Mt Wellington are supplied from equipment in the 220 kv switchyard. in the Auckland CBD and neighbouring suburbs are supplied from the 110 kv switchyard via cables installed in Vector s CBD tunnel. There are multiple corridors for Vector s supply cables to exit the Penrose.

11 The Penrose GXP supply area St Heliers Orakei Newmarket Glen Innes Remuera The Drive Penrose GXP St Johns Mt Wellington Rockfield McNab Sylvia Park Onehunga Te Papapa Carbine Westfield GXP Vector zone Vector s sub-transmission cables from s Penrose GXP supply power to 15 Vector zone s in Eastern Auckland, servicing 75,339 customers.

12 Understanding what happened at the Penrose GXP on 4 October 2014

13 Saturday 4 October Electrical fault causes fire at Penrose GXP Saturday 11:21pm An electrical fault in a transition joint in the cable trench at the Penrose GXP caused a fire to start. CBD tunnel portal 33kV switchgear Sunday 2:04am Cables feed: Glen Innes, Newmarket (part), The Drive s remote control system recorded a series of unusual alarms. 110kV switchyard 220kV switchyard Cables feed: Remuera, Newmarket (part), St Johns, Orakei, St Heliers Sunday 2:11am The fire causes cables to start tripping from 2.11am which begins interrupting the power supply to customers. Sunday 2:17am Cables feed: Mt Wellington, Westfield (part), Carbine, Sylvia park, McNab (part) CBD 33kV switchyard Cables feed: McNab (part), Onehunga, Te Papapa, Westfield (part), Rockfield Fire Vector cable corridor A member of the public calls the Fire Service.

14 Sunday 5 October 2:26am-3:32am Getting control of the fire Sunday 2:26am The Fire Service arrive on site. Sunday 3:06am begins de-energising a large proportion of the Penrose GXP to allow safe access for the NZ Fire Service. St Heliers Orakei Newmarket Sunday 3:17am Glen Innes Remuera The Drive Penrose GXP Power supply to 15 Vector zone s is lost as a result of the de-energisation and subsequently 75,339 customers lose power. St Johns Sunday 3:22am The NZ Fire Service enters the switchyard. No site access for Vector or crews until the fire is extinguished. Mt Wellington Rockfield McNab Sunday 3:32am Sylvia Park Onehunga Fire fighting begins and NZ Fire Service start applying foam. Te Papapa Carbine Westfield Power outage Partially restored Power restored

15 Sunday 5 October 9:17am Vector control room begins power restoration via backfeeding Sunday 9:17am Vector s control room restores most of Onehunga and parts of Newmarket using backfeeding. continues with restoration work throughout the day, testing and slowly relivening GXP equipment. St Heliers Orakei Newmarket Sunday 9:57am Glen Innes Remuera The NZ Fire Service hand the site back to and begins inspections and preparing the site for relivening. St Johns Sunday 3:00pm onwards The Drive Penrose GXP partially relivens GXP and Vector is then able to begin the process of relivening its undamaged cables. Mt Wellington Rockfield McNab Power supply is partially restored at s Penrose GXP. Sylvia Park Onehunga Te Papapa Carbine Westfield Power outage Partially restored Power restored

16 Sunday 5 October 6:21pm Relivening the undamaged cables Sunday 6:21pm Vector restores power to seven Vector zone s which are fed from undamaged cables. Nearly half the 75,339 affected customers have their power supply restored. St Heliers Orakei Newmarket Throughout Sunday night, Vector s control room carries out extensive reconfiguration to backfeed supply into affected areas, restoring power to an additional 18,786 customers in St Heliers, Remuera and Mt Wellington. Glen Innes Remuera The Drive Penrose GXP St Johns Mt Wellington Rockfield McNab Sylvia Park Onehunga Te Papapa Carbine Westfield Power outage Partially restored Power restored

17 Monday 6 October 9:06am Restoration work gets underway Monday 9:06am Vector s control room undertakes hot water load controlling in some areas to reduce electrical load to enable additional backfeeding to the affected area. St Heliers Orakei Newmarket A mobile crane arrived onsite to lift cable drums into the yard. Cables were then pulled through the yard along the routes agreed between and Vector and jointing of cables commences. Glen Innes Remuera The Drive Penrose GXP St Johns Mt Wellington Rockfield McNab Repairs to the first two cables are completed early Tuesday morning. Sylvia Park Onehunga Te Papapa Carbine Westfield Crews work continuously to complete repairs. Working conditions over the initial 24 hours of the repair operation were challenging, with periods of severe rain, high wind and hail during Monday night. Power outage Partially restored Power restored

18 Tuesday 7 October 7:41am Restoration work nears completion Tuesday 7:41am Vector continues with cable repair work and re-energisation, restoring additional customers. St Heliers At 7.41am 2,047 customers remain without power. (2.7% of the originally affected customers). Orakei Newmarket Glen Innes Remuera The Drive Penrose GXP St Johns Mt Wellington Rockfield McNab Sylvia Park Onehunga Te Papapa Carbine Westfield Power outage Partially restored Power restored

19 Tuesday 7 October 2:08pm Restoration complete Tuesday 2:08pm Power is restored to all 75,339 affected customers. St Heliers Orakei Newmarket Glen Innes Remuera The Drive Penrose GXP St Johns Mt Wellington Rockfield McNab Sylvia Park Onehunga Te Papapa Carbine Westfield Power outage Partially restored Power restored

20 Vector s response to Penrose outage Vector regrets the disruption to customers during the outage in October Everything was done to ensure the network was repaired as quickly as possible, however, we do understand and acknowledge the impact the outage had on homes and businesses. Immediately after power was restored, and Vector embarked on a thorough investigation including appointing independent international experts to identify the cause, extent and impact of the Penrose fire and subsequent electricity outage. Both parties have also worked collaboratively with the Electricity Authority (EA) to ensure it received the information required to conduct its own separate investigation, and welcomes the EA report on the incident. All incidents provide lessons and the only mistake would be not learning from them. Throughout the internal and external investigations, and Vector s focus has been on identifying and resolving any issues as quickly and thoroughly as possible. The majority of recommendations identified in both the EA and joint and Vector reports have already been completed and progress is well advanced on the remainder. Vector wishes to acknowledge the disruption caused by the Penrose outage by making a Vector service level payment to affected customers. This is a voluntary payment Vector makes available to customers if an outage occurs and power is not restored within Vector s published service levels. This will be available to claim from 2 December.

21 The investigation key learnings While the independent cable expert has concluded that the cause of the fire was rare, we have taken valuable learnings from the incident. We are now focused on finalising implementation of the recommendations to address these: Failures of cable joints installed in air can cause fires, and, if there are a number of cables in close proximity, the collateral damage can have a significant impact on customers; Risk management processes did not identify very low probability risks of events that had not previously occurred on the network; The nature of the incident identified some gaps in current operating practices; The current asset and risk management processes at the physical interface between Vector and s networks must be improved.

22

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas ENERGY NETWORKS ASSOCIATION Electricity Industry EMF Measurement Protocol for High Field Areas Contents 1 Introduction 1.1 Background 1.2 High Field Areas 2 High Field Area - Generation Businesses 2.1

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Customer Charter. Networks. Networks. www.esb.ie

Customer Charter. Networks. Networks. www.esb.ie www.esb.ie Dear Customer ESB has always been committed to putting the needs of our customers first. This is reflected in our 12 Service Guarantees that were first introduced in our Customer Charter some

More information

Powerco Limited Pricing Guide 2015 ANNUAL REPORT 2015

Powerco Limited Pricing Guide 2015 ANNUAL REPORT 2015 ANNUAL REPORT 2015 PRICING GUIDE 2015 1 CONTENTS Introduction Page 03 Who we are Page 04 The Electricity Industry Page 05 Our Pricing Policy Page 08 How Powerco Performs Page 10 Pricing Methodology Page

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

Utilization of Automatic Meter Management in Smart Grid Development

Utilization of Automatic Meter Management in Smart Grid Development Utilization of Automatic Meter Management in Smart Grid Development Elenia Verkko Oy Ville Sihvola Head of Marketing and Sales ville.sihvola@elenia.fi Content of the presentation 1. What is Elenia Verkko

More information

ESB Networks Ltd Statement of Charges

ESB Networks Ltd Statement of Charges ESB Networks Ltd Statement of Charges Revision Date: 9/2014 Revision No.: 11 Document No: DOC-101209-AXR Issued by: ESB NETWORKS LTD Approved by : CER Effective Date: 01/10/2014 Commercial and Renewable

More information

Chapter 1. Network Structures

Chapter 1. Network Structures Chapter 1 Network Structures Definition Standard IEC 60038 defines voltage ratings as follows: Low voltage (): for a phase-to-phase voltage of between 100 V and 1,000 V, the standard ratings are: 400 V

More information

Hydro One Major Incident Report. Operational response and incident review of flooding at Manby and Richview Transformer Stations on July 8, 2013

Hydro One Major Incident Report. Operational response and incident review of flooding at Manby and Richview Transformer Stations on July 8, 2013 Hydro One Major Incident Report Operational response and incident review of flooding at Manby and Richview Transformer Stations on July 8, 2013 1 Toronto Flood, July 8, 2013 On July 8, 2013, the Greater

More information

When power interruptions happen.

When power interruptions happen. When power interruptions happen. We know it s never a good time to have your power go out, so we work all year pruning trees and investing in our system to cut down on problems before they start. Outage

More information

Treasure Valley Electrical Plan

Treasure Valley Electrical Plan Treasure Valley Electrical Plan Community Advisory Committee January 25, 2006 Agenda 10 a.m. Welcome 10:10 a.m. Follow up DSM discussion 10:30 a.m. TVEP CAC process update 10:40 a.m. Transmission Presentation

More information

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2015-16 Electricity Network Tariffs and Charges and Future Price Trends July 2015 Power and Water Corporation 1 Table of Contents 1 Business Characteristics 3 2 2014 Network Price Determination

More information

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...

More information

By Manitoba Hydro, March 4 th 2013

By Manitoba Hydro, March 4 th 2013 Rebuttal to Bipole III Coalition underground cable report Potential Use of Underground Cables for Sections of the Planned 500 kvdc Bipole III Overhead Line in Manitoba By Manitoba Hydro, March 4 th 2013

More information

Improving Reliability for High-Profile Customers

Improving Reliability for High-Profile Customers Improving Reliability for High-Profile Customers By Mark Kimbell Chief Engineer at Murfreesboro Electric Department How important are commercial customers to an electric utility? Are you doing everything

More information

Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions

Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions Owner Name Title Signature Steve White Head of Network Control and Operations Date 16 February 2016 Authoriser Name

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance Annex I To Loughborough University (LU) Facilities Management (FM) Health and Safety Policy High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance 1. Introduction a. These Safety

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

ICM Project Station Infrastructure and Equipment

ICM Project Station Infrastructure and Equipment EB 0 00 Schedule B. ( pages) ICM Project Station Infrastructure and Equipment (THESL) EB 0 00 Schedule B. I EXECUTIVE SUMMARY 0. Project Description Many Municipal Substations (MS) located outside of downtown

More information

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories: Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

Electricity: your entitlement to a reliable supply

Electricity: your entitlement to a reliable supply Electricity: your entitlement to a reliable supply Guaranteed Service Level (GSL) payments explained A guide for Victorian electricity customers Despite the best efforts of Victoria s electricity distributors

More information

SITE CONTRACTOR PROCEDURES

SITE CONTRACTOR PROCEDURES SITE CONTRACTOR PROCEDURES Asset Collection Type B Assets are considered High risk ; the site activities must be in accordance with Graysonline contractor procedures and are to be collected by appointment

More information

Smart Grids. MIECF Conference April 2011

Smart Grids. MIECF Conference April 2011 Smart Grids MIECF Conference April 2011 Introduction Introduction to Ausgrid s Smart Grid Program Overview of the Smart Grid, Smart City initiative Details on each application area for the project Smart

More information

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services SpecialistS IN ELECTRICAL SUPPORT SERVICES TO MINING, UTILITIES & industry Ampcontrol is committed to supporting our customers to maintain efficient

More information

ComEd Grid Renewal Terence R. Donnelly

ComEd Grid Renewal Terence R. Donnelly ComEd Grid Renewal Terence R. Donnelly Executive Vice President and Chief Operating Officer September 23, 2013 COMED S GRID MODERNIZATION VISION ComEd will fulfill the promise of grid modernization for

More information

1.0 APPOINTMENTS 2.0 FIRE RISK ASSESSMENTS

1.0 APPOINTMENTS 2.0 FIRE RISK ASSESSMENTS Fire Risk assessment 1.0 APPOINTMENTS 1.1 Responsible Person. In compliance with the Regulatory Reform (Fire Safety) Order 2005 (FSO) the School s Head, Mrs J M Miles is appointed as the Responsible Person

More information

Underground vs. Overhead Transmission and Distribution

Underground vs. Overhead Transmission and Distribution electric power engineering Underground vs. Overhead Transmission and Distribution Your Power System Specialists June 9, 2009 1 NATIONAL TRENDS Municipalities have passed laws requiring new distribution

More information

Distribution Substation Manual (DSM) Section I - Introduction

Distribution Substation Manual (DSM) Section I - Introduction (DSM) Section I - Introduction March 2007 Document release information Client Project name Western Power Distribution Substation Manual Document number 3463019 Document title Revision status Introduction

More information

How much more electricity do we use in a heatwave?

How much more electricity do we use in a heatwave? January 2015 Heatwaves and electricity supply Heatwaves in Australia normally lead to significant increases in electricity demand. The main reason for this is the increased use of air conditioners over

More information

Fire Risk Assessment Safety Checklist

Fire Risk Assessment Safety Checklist Fire Risk Assessment Safety Checklist This checklist has been prepared to help you comply with The Regulatory Reform Fire Safety Order 2005 What is the Regulatory Reform (Fire Safety) Order 2005? The Regulatory

More information

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage

More information

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

EA Technology (UK) EA Technology (UK) NEDL (UK)

EA Technology (UK) EA Technology (UK) NEDL (UK) Optimising Customer Information and the Fault Management Process D C Newis L Roberts John Barnett EA Technology (UK) EA Technology (UK) NEDL (UK) SUMMARY Electricity companies are under increasing pressure

More information

Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014

Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014 Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014 Customer Data Quality Plan 2015-2020 V1.1 Executive Summary The commencement of Full Retail Contestability in 2004

More information

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This

More information

environment briefing02

environment briefing02 PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES overhead 23/11/04 2:28 PM Page 1 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES ESB Code 9803203 overhead 23/11/04 2:28 PM Page 2 overhead 23/11/04 2:28 PM Page 3 Page 1 of 20

More information

Transmission Business Electrical Incident & Safety Performance Reporting Guide

Transmission Business Electrical Incident & Safety Performance Reporting Guide Transmission Business Electrical Incident & Safety Performance Reporting Guide December 2011 Version 1.0 Energy Safe Victoria PO Box 262 Collins Street West MELBOURNE VIC 8007 AUSTRALIA Telephone (03)

More information

Customer Code of Practice & Security of Supply. Standard Distribution Licence Conditions 8, 9 and 10

Customer Code of Practice & Security of Supply. Standard Distribution Licence Conditions 8, 9 and 10 Customer Code of Practice & Security of Supply Standard Distribution Licence Conditions 8, 9 and 10 (Effective from 26th August 2004) This Code of Practice has been prepared in a form approved by Ofgem

More information

Pricing methodology Electricity distribution network. From 1 April 2014

Pricing methodology Electricity distribution network. From 1 April 2014 Pricing methodology Electricity distribution network From 1 April 2014 Pursuant to: The Electricity Distribution Information Disclosure Determination 2012 1. TABLE OF CONTENTS 1. Table of contents... 2

More information

Does your new building

Does your new building Does your new building need electricity? To save you time and money, talk to us early about your power supply. Our equipment will occupy ground space on your property. You need to consider the size and

More information

Report in respect of. Service Disruption on 9 April 2012

Report in respect of. Service Disruption on 9 April 2012 Report in respect of Service Disruption on 9 April 2012 1. Introduction On 9 April 2012, a power outage occurred in the Shatin Switching Centre, one of three switching centres deployed by SmarTone Mobile

More information

Distributed Generation: Frequently Asked Questions

Distributed Generation: Frequently Asked Questions Distributed Generation: Frequently Asked Questions 1) What is distributed generation (DG)? Generating technologies located close to where the electricity is being used that are connected to the electric

More information

Who is National Grid?

Who is National Grid? Who is National Grid? National Grid is a leading international energy infrastructure business In the UK, our business includes electricity and gas transmission networks and gas distribution networks. We

More information

Safety During Power Restoration. Steve Thompson Emergency Operations Director Alabama Power Company

Safety During Power Restoration. Steve Thompson Emergency Operations Director Alabama Power Company Safety During Power Restoration Steve Thompson Emergency Operations Director Alabama Power Company Safety & Training Responsibilities During Major Outages Staging Area Responsibilities Orientations for

More information

Asset Management Plan

Asset Management Plan 2014 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2014-2024 Network Asset Management Plan (AMP). The 2014 AMP follows on from the

More information

Actual capital expenditure during the current regulatory period. Project summary

Actual capital expenditure during the current regulatory period. Project summary 1 Actual capital expenditure during the current regulatory period. Project summary This document provides a summary of the capital expenditure on large capital projects during the current regulatory period.

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND

UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND FACT SHEET TELEPHONE 0800 327 646 I WEBSITE WWW.FEDFARM.ORG.NZ UNDERGROUND TELECOMMUNICATIONS CABLES ACROSS PRIVATE LAND BACKGROUND The Rural Broadband Initiative envisages substantially improved broadband

More information

One positive experience I've had in the last 24 hours: Exercise today:

One positive experience I've had in the last 24 hours: Exercise today: Name - Day 1 of 21 Sunday, June 29, 2014 3:34 PM journal template Page 1 Name - Day 1 of 21 Sunday, June 29, 2014 3:34 PM journal template Page 2 Name - Day 2 of 21 2:27 PM journal template Page 3 Name

More information

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October Jennifer Woodruff Innovation & Low Carbon Networks Engineer Asset Management Efficient asset management ensures that risk is effectively managed and returns

More information

Journey to Work Patterns in the Auckland Region

Journey to Work Patterns in the Auckland Region Analysis of Census Data for 2001-2013 1 INTRODUCTION... 1 DEFINITIONS OF WORKERS, JOBS AND EMPLOYMENT... 1 2 SCOPE OF THE ANALYSIS... 2 2.1 LEVELS OF ANALYSIS... 2 2.2 DATA INCLUDED IN THE ANALYSIS...

More information

A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES

A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES A Roberts, T Berry, W D Wilson Schneider Electric Ltd, UK SYNOPSIS This paper describes the features of a modern Distribution

More information

Energex Customer Charter. For residential and small business customers

Energex Customer Charter. For residential and small business customers Energex Customer Charter For residential and small business customers Contents 1. The Energex Customer Charter 1 Energex is your electricity distributor 1 Where is the Energex network? 1 Access to information

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

How To Develop A Smart Grid In Elenia

How To Develop A Smart Grid In Elenia GEODE Autumn Seminar in Brighton 12 th of November Utilization of Automatic Meter Management in Smart Grid Development Ville Sihvola Head of Marketing and Sales Elenia Oy Elenia Oy Turnover 220 M Employees

More information

RESTORATION PROCESS. Step 1 Empire s storm restoration team assesses the damage to the system. This assessment allows Empire. = Location of damage

RESTORATION PROCESS. Step 1 Empire s storm restoration team assesses the damage to the system. This assessment allows Empire. = Location of damage RESTORATION PROCESS = Location of damage 6 4 3 POLICE STATION 3 2 8 5 7 2 Step 1 Empire s storm restoration team assesses the damage to the system. This assessment allows Empire to determine if it is necessary

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

City of Buffalo Municipal Electric Utility Energy Emergency Response

City of Buffalo Municipal Electric Utility Energy Emergency Response City of Buffalo Municipal Electric Utility Energy Emergency Response Table of Contents Page 1. Goals 2 2. Types of Energy Emergencies..3 3. Utility Emergency Operating Plans.4 4. Link to General Reliability/Outage

More information

A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines)

A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines) A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines) DOCUMENT NUMBER CLNR-L263 AUTHORS David Miller, Northern Powergrid Duncan Yellen and Daniel Hollingworth,

More information

Asset Management Plan 2012

Asset Management Plan 2012 Asset Management Plan 2012 Period Covered: 1 April 2012 to 31 March 2022 Approved by: Network Waitaki Directors 27 February 2012 Table of Contents 1.0 Summary 5 1.1 Purpose of the Plan 5 1.2 Date Completed

More information

Market Growth and New Regulations Demand Network Modernization

Market Growth and New Regulations Demand Network Modernization CASE ESB NETWORKS: POLE TOP COMMUNICATION INCREASES EFFICIENCY IN IRELAND Viola s solution for remotely operating pole-top reclosers and switches increases reliability, cuts operating costs and helps to

More information

Compliance Noise Monitoring

Compliance Noise Monitoring Monitoring Byron Centre The Manse Road Myocum HEALTH SCIENCE ENVIROMENTAL EDUCATION ENVIRONMENTAL AUDITOR Monitoring Byron Centre The Manse Road Myocum Prepared for: Byron Shire Council Version 1.0 Date:

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

Why build the Silvertown Tunnel?

Why build the Silvertown Tunnel? Why build the Silvertown Tunnel? Over the last 30 years east London has changed with the redevelopment of former industrial areas into major commercial and residential districts. The development of Canary

More information

NETWORK MANAGEMENT STRATEGY

NETWORK MANAGEMENT STRATEGY ABN 85 082 464 622 NETWORK MANAGEMENT STRATEGY DOCUMENT NUMBER: NW-#30065608-V6 DATE: 12 MAY 2011 NW-#30065608-v6-Network_Management_Strategy.DOC Page 1 of 20 This page is intentionally blank. NW-#30065608-v6-Network_Management_Strategy.DOC

More information

NORDEX OFFERS : CONSTRUCTION AND SERVICE OPERATION. Istanbul, 08.11.2012

NORDEX OFFERS : CONSTRUCTION AND SERVICE OPERATION. Istanbul, 08.11.2012 NORDEX OFFERS : TURNKEY PARK CONSTRUCTION AND SERVICE OPERATION Istanbul, 08.11.2012 CUSTOMER FOCUSED ORGANIZATION ORGANIZATIONAL PRINCIPLES NORDEX CUSTOMER ORGANIZATION AND SUPPORT One Responsibility

More information

You can report faults on your Basic Telephone Service to Australian Telephone Networks 24 Hours a Day / 7 Days a week.

You can report faults on your Basic Telephone Service to Australian Telephone Networks 24 Hours a Day / 7 Days a week. AUSTRALIAN TELEPHONE NETWORKS NETWORK FAULT RESTORATION OVERVIEW Australian Telephone Networks Fixed Services (PSTN, ISDN 2, ISDN 10/20/30) are a resale of Telstra s Fixed Line Network. Fault restoration,

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS FEBRUARY 2008 PB POWER PB Power Page i EXECUTIVE SUMMARY General

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

Restoring your electricity safely following a major storm: UK Power Networks response to the storms of 23 & 24 December 2013

Restoring your electricity safely following a major storm: UK Power Networks response to the storms of 23 & 24 December 2013 Restoring your electricity safely following a major storm: UK Power Networks response to the storms of 23 & 24 December 2013 Introduction UK Power Networks is firmly committed to operating a safe and resilient

More information

Brochure Introducing HVDC

Brochure Introducing HVDC Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in

More information

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS Customer Handout Date Aug 2, 2010 Version 1.0 File Name Customer Requirements At Power Substations Document Id Outside Plant Engineering 1 Table Of Contents 1.0

More information

IMPORTANT INFORMATION

IMPORTANT INFORMATION STOXA IMPORTANT INFORMATION May 26-28, 2016 STOXA 10 minutes from Stockholm-Arlanda Airport MOVING IN Exhibition Stands are accessible for installation during the following hours: Monday May 23 Tuesday

More information

SAFETY PERFORMANCE REPORT ON VICTORIAN ELECTRICITY NETWORKS 2014

SAFETY PERFORMANCE REPORT ON VICTORIAN ELECTRICITY NETWORKS 2014 SAFETY PERFORMANCE REPORT ON VICTORIAN ELECTRICITY NETWORKS 2014 JULY 2015 Energy Safe Victoria Safety Performance Report on Victorian Electricity Networks 2014 Page 2 of 143 PREFACE Energy Safe Victoria

More information

EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK

EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK EVALUATION OF ALTERNATIVE BACKUP PROTECTION SCHEMES ON A 66KV DISTRIBUTION NETWORK F. Malone*, P.D. Doyle *ESB International, Ireland fergus.malone@esbi.ie ESB International, Ireland paul.d.doyle@esbi.ie

More information

National Science Foundation Funds Request

National Science Foundation Funds Request University Corporation for Atmospheric Research National Science Foundation Funds Request 1. (NSF USE ONLY) 2. FACILITY NAME & LOCATION 3. PROJECT NAME 4. UCAR TRACKING NUM. NCAR Mesa Lab 15KV FEEDER REPLACEMENT

More information

TRAFFIC MANAGEMENT PLAN

TRAFFIC MANAGEMENT PLAN TRAFFIC MANAGEMENT PLAN For: The construction and operation of a Photovoltaic (PV) Facility in Dabenoris, South Africa Prepared for: Alternative Energy Solutions (Pty) Ltd PO Box 4939 Tygervalley, South

More information

Root-cause analysis, often called RCA, is a way of thinking about how to

Root-cause analysis, often called RCA, is a way of thinking about how to Special Feature by Mark Lautenschlager, P.E. Using Root-Cause Analysis to Find Underlying Causes of Bad Outcomes Root-cause analysis, often called RCA, is a way of thinking about how to fix problems. By

More information

Tech Talk. Smart metering update Successful rollout. Connection Standards newsletter December 2013. Contents. To all Registered Electrical Contractors

Tech Talk. Smart metering update Successful rollout. Connection Standards newsletter December 2013. Contents. To all Registered Electrical Contractors BLEED BLEED Connection Standards newsletter December 2013 Contents Smart metering update Successful rollout Flexible pricing A major benefit of the smart meter program Business flexible pricing New residential

More information

Phase Attribute Identification using GPS Technology

Phase Attribute Identification using GPS Technology Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits

More information

Fire alarm bells (and associated fire detection equipment) are tested on Wednesday mornings between 0830-0845.

Fire alarm bells (and associated fire detection equipment) are tested on Wednesday mornings between 0830-0845. FIRE SAFETY PROCEDURES, ST MARY S CAMPUS MEDICAL SCHOOL BUILDING These notes supplement the Imperial College London Fire Safety Policy and Code of Practice and give details of local fire safety management

More information

Welcome Guide Les Arcs Self Catered

Welcome Guide Les Arcs Self Catered Welcome Guide Les Arcs Self Catered LES ARCS 1800 There are two key agencies handling apartments in Les Arcs 1800 please see your final details email for information on which office is dealing with your

More information

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB BSES, Delhi - Distribution Network improve power quality System design for optimal techno-economic distribution network based on current and future load forecast Analysis of existing sub-transmission and

More information

Power cut. Powering your business is our priority

Power cut. Powering your business is our priority Power cut Powering your business is our priority Contents 2 Preventing power cuts 3 Who are UK Power Networks 4 Plans for your business in case of a power cut 6 My business has lost money 8 Your rights

More information

UCL FIRE RISK ASSESSMENT POLICY& ARRANGEMENTS

UCL FIRE RISK ASSESSMENT POLICY& ARRANGEMENTS Fire Safety Technical Guide UCL FIRE RISK ASSESSMENT POLICY& ARRANGEMENTS 1.0. BACKGROUND 1.1. The Regulatory Reform (Fire Safety) Order (known Fire Safety Order) applies to England and Wales (Northern

More information

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 Disclosure Date 31 March 2015 Start Date (first day) 1 April 2015 Templates for Schedules 11a 13 (Asset Management Plan)

More information

ADMS(Advanced Distribution Management System ) in Smart Grid

ADMS(Advanced Distribution Management System ) in Smart Grid ADMS(Advanced Distribution Management System ) in Smart Grid 柯 佾 寬 博 士 Yi-Kuan Ke, Ph.D. 2014/03/28 Smart Grid Solution Smart Grid Solution Overview Smart Grid Solutions Smart Network Operation - Distribution

More information

Track 1: Managing network assets

Track 1: Managing network assets the agi conference at GIS 2002 A05.2 Track 1: Managing network assets Delivering and realising the benefits of Multi-utility GIS systems for United Utilities Clive Deadman, General Manager, Asset Records,

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

Network Consulting for Power Grid Optimization

Network Consulting for Power Grid Optimization Network Consulting for Power Grid Optimization Project experience in India Network Consulting Competences Page 1 Our worldwide representation Manchester The Hague Denver Schenectady San Diego Houston Mexico

More information