1 Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Feasibility A guide to feasibility planning for junior mining companies

2

3 Feasibility A guide to feasibility planning for junior mining companies A Norton Rose Fulbright guide

4

5 Contents Summary 04 Introduction 05 Feasibility 07 Other key feasibility considerations 11 Feasibility stage key point summary 15 Contacts 17

6 Feasibility Summary The importance of a robust strategy for the procurement of a mining project, from project inception through to construction implementation, cannot be underestimated. Full consideration of the key procurement issues identified in this guide can often mean the difference between achieving a bankable project with optimal returns for the mining company, and an expensive project failure. 04 Norton Rose Fulbright

7 Introduction Introduction General For junior mining companies in particular, cash is king, but in the race to obtain project finance or other forms of financial backing, we regularly see the key iterative steps and considerations mapped out in this guide either being forsaken or missed. The impact of this for the mining company can be considerable. The need for a strategy The aim of this guide is to explore the key steps in pre-construction planning and evaluation (usually referred to as feasibility), and to look at the common misconceptions as to what the junior mining company (the Sponsor) should be looking to achieve at this stage. Importantly, we will look at the iterative steps usually required to achieve completion of the feasibility stage of a mining project and the common pitfalls that must be avoided along the way. When the feasibility stage of a project is properly executed, the Sponsor will be more likely to be in a position to establish at an early stage, with a degree of certainty, whether or not the economics and general viability of the project stack up. If they don t, the project can be abandoned at the earliest possible point, hopefully before significant amounts of money have been expended. On the assumption that it is established during the feasibility stage that the economics and general viability of the project do stack up, the Sponsor will then go on to consider detailed engineering and construction delivery and importantly how this will be structured to achieve both a bankable and an economically viable project. Norton Rose Fulbright 05

8 Feasibility What do we mean by bankability? The terms bankable or bankability will be used in this guide. Bankability is essentially a view on the robustness of the project structure in terms of it being able to secure for the lenders full repayment of debt outstanding, either through project delivery and operational returns or, in a default scenario, through recourse against the parties responsible for project delivery. The considerations as to bankability will certainly vary from one project to the next, but the lenders will tend to have certain key requirements which must first be met in order to secure internal credit approval and the authority to lend. 06 Norton Rose Fulbright

9 Feasibility Feasibility General Before discussing the feasibility stage of a mining project, it would perhaps first be useful to clarify its purpose and to dispel a few common misconceptions. The purpose of the feasibility stage is to carry out an appropriate level of testing and analysis to establish if a project should be developed through into the detailed engineering and construction stage. It is important to recognise that completion of this study does not, in itself, mean that the Sponsor has an economically viable project. In fact, it can say just the opposite. Furthermore, adding the word bankable before feasibility study does not mean that the project is one that will secure project financing. A bankable feasibility study simply means a report with a sufficient level of accuracy to enable financial institutions to consider feasibility. The decision as to whether to lend will only come following the completion of further and more detailed due diligence. The feasibility study can therefore be seen in several lights. Provided the content is favourable and the report has been produced to the required reporting standards (eg, JORC, NI , SAMREC (as appropriate)) with a recognised international mining consultant or engineering firm standing behind the results, the report may be used for the following purposes: an important and valuable marketing tool which can be used to attract potential equity investors and/or lenders a tool to be used by the Sponsor itself to secure internal board approval for the commitment of equity and capital for the progression to detailed engineering and construction a tool to be used by the Sponsor in order declare a reserve on a new project, as provided by the US Securities and Exchange Commission (SEC) or Norton Rose Fulbright 07

10 Feasibility a tool to be used by Sponsors to satisfy certain pre-listing requirements (eg, the requirements for disclosure of ore reserves in Chapter 18 of the Listing Rules of the Hong Kong Stock Exchange). The common misconception that the production of the final feasibility study will, in itself, either provide the Sponsor with a feasible structure for project delivery and/or secure project financing, often means that fundamental steps are missed or forsaken by Sponsors in pursuit of obtaining the final feasibility report (whatever it may say!). As we will discuss below, this approach may have significant cost implications for Sponsors. Stages of feasibility Sponsors should look to identify issues that may impact on project feasibility at the earliest possible stage. It would be usual therefore for the Sponsor to commission the carrying out of preliminary analysis on the reserve and its economic viability in order to identify key feasibility issues before significant amounts of money are committed to the production of a final feasibility study report. With the cost of a final feasibility study report often running to several million dollars, preliminary analysis can save significant wasted costs later down the line. Below are some of the keys steps typically taken during the feasibility stage of a mining project. As noted, the Sponsor should determine on a project specific basis the appropriateness of each stage of preliminary analysis and/or the requirement for additional stages of analysis both pre and post production of the final feasibility study. Conceptual study The feasibility stage of a project will usually commence with the production of an initial scoping or conceptual study. This conceptual study will typically involve a preliminary evaluation of the project based on initial drilling, industry experience and informed assumptions. The end product will provide a description of the general features of the project, technical factors requiring further investigation and an order of magnitude of likely capital and operating costs, with a usual accuracy of +/- 50 per cent. Whilst this report by no means provides an accurate assessment of feasibility, it can and should be used by the Sponsor to determine whether or not to proceed forward with an exploration program and further engineering work. 08 Norton Rose Fulbright

11 Feasibility Pre-feasibility study If the decision is made, following completion of the conceptual study, to proceed, the next stage in the feasibility process will typically be the completion of a pre-feasibility study. This is the key intermediate step in the assessment of project feasibility. Typically at this stage there will be sufficient drilling and process test work to enable the production of basic engineering. Pre-feasibility will typically involve a determination of mining and milling extraction methods, anticipated product recovery rates and consideration of key environmental and permitting issues. Again, preliminary capital and operating cost estimates will be carried out, this time with a usual accuracy of +/- 30 per cent. There should be focus at this stage on critical issues to be resolved during final feasibility if the decision is subsequently made to continue. Final feasibility study If the results of pre-feasibility are favourable, the Sponsor may choose to move to the final stage in the feasibility process and the production of the feasibility study itself. The feasibility study deliverables will typically include initial mine and plant design, detailed process flow sheets, product recovery estimates, detailed capital and operating cost estimates and an economic model for the project. It would not be unusual also for the feasibility study to present possible financing options. The feasibility study will typically produce capital and operating cost estimates that are accurate to within +/ per cent. Analysis and further investigation Although it would not be unusual for the final feasibility study to identify areas where further investigation may be required, we would typically expect this study to provide sufficient information to enable the Sponsor to make a decision as to whether to move to detailed design and construction or, if the results are not favourable, abandon the project. Whilst the three stage iterative process set out above is typical, it is not a process that should be considered as being set in stone. There may for instance be other intermediate steps that the Sponsor may wish to take before making the decision to commit resource to the further development of a project. Norton Rose Fulbright 09

12 Feasibility It is however essential that the mining company carries out a full appraisal of the results at each stage of an iterative process to take stock and make an informed decision as to whether to continue to the next stage. The key at each stage is to identify problems to be resolved at the next stage and the means by which they may be resolved within the bounds of the economics of the project or (as the case may be) to identify those problems which are insurmountable and which should on reflection deter additional time and money being committed to developing the project in its current form. This process is about drip feeding both time and money into the project at the right time for the right purpose. 10 Norton Rose Fulbright

13 Other key feasibility considerations Other key feasibility considerations The Sponsors role at the feasibility stage Whilst a feasibility study is often produced by an experienced and recognised international engineering consultancy practice, the Sponsor still has a very important role to play if, on the assumption that a reserve may be declared, the feasibility study is to provide a solution that meets the economic expectations of the Sponsor and is acceptable to potential lenders. Whilst controls relating to equipment selection and parameters of affordability should be established under the terms of the consultant s feasibility study appointment, careful monitoring of the progress of the study at fixed milestones will enable the Sponsor at an early stage to pick up on (and ideally resolve) issues that may affect possible financing solutions or go to the affordability of the project. Sponsors should be aware that equipment selection made at feasibility stage may impact on possible financing options, especially in the context of securing export credit agency (ECA) backing. ECAs may provide certain types of financial support and/or political or commercial risk cover to support exports of goods and services from their jurisdiction. However, to secure such support or cover, it will usually be a requirement of the ECA that a fixed minimum value of the relevant support or cover is made up of works and/or services sourced from the ECA s home country (often known as a local content requirement ). Where a Sponsor is looking to secure ECA support, it should look to work closely with the party producing the feasibility study to ensure that plant and equipment selection made at this stage will not be a rigid requirement and that appropriate flexibility and assumptions are provided in, for example, equipment selection proposals and options to account for possible ECA support from various jurisdictions at a later stage in the project. Norton Rose Fulbright 11

14 Feasibility There should ideally be close dialogue between the engineering consultant producing the feasibility study and the Sponsor throughout the final feasibility stage to allow refinement of the study and the assumptions on which it is based. It is also likely that interested lenders will be willing to offer input at this stage. It is advisable for the Sponsor to tap into this resource where available. This interactive process is about pointing the consultant in the right direction to ensure that assumptions on which the final report is based correspond with the expectations of the Sponsor and any potential lenders. This exchange of dialogue must not however be viewed as a means by which the Sponsor can manipulate results to provide an answer they are looking for where a project would not otherwise be feasible. Contracting arrangements Whilst the production of the conceptual study and the pre-feasibility study may be based on more informal terms agreed between the Sponsor and the engineering consultant, or indeed carried out in-house by the Sponsor, the final feasibility study should be completed under the terms of a formal contractual agreement between the relevant parties to ensure that all key requirements of the Sponsor may be achieved. These key requirements will typically include (but not be limited to) the following: the final report to contain all required deliverables and to be produced to the required reporting standards the engineering consultant to stand behind all results in the final study and to be responsible for any errors and/or omissions in the final study (in practice, consultants tend to look to cap their exposure in this regard and appropriate cap levels will be a matter for commercial discussion) the consultant to assign all intellectual property rights in the feasibility study report to the Sponsor, or at least provide an irrevocable licence with a right to grant sublicences (ie, the Sponsor has to consider the possibility that other third parties may wish to rely on or use the report (eg, third party equity investors or potential lenders)) the final report to be completed within a certain time period to meet the Sponsor s overall project programme with appropriate sanctions for delay 12 Norton Rose Fulbright

15 Other key feasibility considerations a right for the Sponsor to review the progress of the report at fixed milestones and to require changes to the scope and/or the assumptions on which it is based. The contract will typically be a form of professional consultancy services contract. The consultant may propose a form of contract but this should be reviewed to ensure that the key requirements of the Sponsor may be achieved. There are also international forms of consultancy agreement that may be employed. For instance, FIDIC has produced a form of professional services agreement (FIDIC White Book) which is often proposed by engineering consultants. It is often the case however that amendments to this form are required in order to achieve an acceptable position for the Sponsor. Legal advice should be taken by the Sponsor in this regard. Design development A fundamental consideration for the Sponsor should be the level of detailed design (if any) being produced at feasibility stage. Whilst a more developed design will permit more accurate capital and operational pricing prior to commencement of construction, the development of detailed design at feasibility stage can (and often does) have a real impact on final construction pricing levels and ultimately bankability. The Sponsor should consider carefully the extent to which a third party contractor would be willing to accept responsibility for design developed by the engineering consultant producing the feasibility study. If the design produced at feasibility stage is conceptual and limited in detail, the Sponsor may have less difficulty in getting the party producing detailed design to accept risk in the accuracy and completeness of the feasibility design. If however the design produced at feasibility stage is more detailed: it will be less likely that a third party contractor will be prepared to accept risk in the earlier design as part of its works delivery obligations or in further development of this earlier design and any resultant split in design responsibility that may transpire may create additional interfaces, which will increase the risk to the Sponsor of time and cost overrun Norton Rose Fulbright 13

16 Feasibility where the Sponsor (and potentially any lenders) look to achieve a continuity of design responsibility from feasibility through to final design and construction in order to reduce interface risk, they may be left to look to either an EPC structure under which the EPC contractor effectively wraps the entire design risk irrespective of the identity of the party producing this design (this will often have a material pricing impact for the Sponsor since it would be usual for risk in third party design to be priced by an EPC contractor on a contingent basis) or an EPCM structure under which the party producing the feasibility study is retained to complete detailed design and to manage works delivery and the procurement of the individual works and supply packages on behalf of the Sponsors. There has been suggestions in the market that an over engineering of the project at feasibility stage has been used as a tactic by engineering companies to eliminate competition prior to the detailed design and construction phase in order to secure EPCM roles on preferred terms (although we would note that we do not have first-hand experience of this ourselves). We have produced a number of further guides which consider in detail the various detailed design and construction delivery structures employed in the mining sector (eg, EPC, EPCM and other hybrids of the two). Clearly, the Sponsor will look to manage design input at feasibility stage to avoid either being: designed into a corner by the party producing any feasibility design or being exposed to either unnecessary design interface risk or material contingent pricing under a wrapped EPC solution. 14 Norton Rose Fulbright

17 Feasibility stage key point summary Feasibility stage key point summary The feasibility stage of a mining project is about the carrying out of an appropriate level of testing and analysis to facilitate the making of an informed decision on whether a project should be developed through into the final engineering and construction stage. The production of a final feasibility study report does not in itself mean that a project is viable or that the project will be one that will attract project finance, it can say just the opposite. If a project is not feasible, from a cost control point of view, Sponsors should be looking to find this out at the earliest possible stage in the process. It is important that Sponsors take a careful and measured approach to the collation of data and information pre-final feasibility in order that an informed decision can be taken as to whether to commit time and resource to the completion of the final feasibility study report. Simply jumping in at the deep end without first carrying out the type of preliminary analysis suggested in this guide can have wasted cost implications for the Sponsors if the project is subsequently deemed not feasible for reasons that should have been identified in the carrying out of initial analysis. In practical terms, the Sponsors should: establish at project inception the series of steps to be taken in order to achieve completion of the feasibility stage of a project and where possible, establish the results and information required at the completion of each step to facilitate the making of a go / don t go decision in terms of whether to commit the time and resource to move to the next stage or to the detailed engineering and construction stage (as the case may be). The Sponsors should select an appropriate form of contract for completion of the final feasibility study to cover key Sponsor requirements. Advice in the regard should be sought from in-house counsel or external legal advisers. Norton Rose Fulbright 15

18 Feasibility If any detailed design is to be developed at feasibility stage, the Sponsors should first consider what impact this will have on the pricing of the detailed design and construction stage of the project and more generally the impact this may have on the achievement of a bankable detailed design and construction contracting structure. The Sponsors should work closely with the relevant engineering consultant and seek input from potential lenders (to the extent available) throughout all stages of feasibility to provide increased certainty that the final deliverables will meet the Sponsor s and any potential lenders expectations. 16 Norton Rose Fulbright

19 Contacts Contacts Martin McCann Global head of mining, infrastructure and commodities Norton Rose Fulbright LLP Tel Mark Berry Partner, London Norton Rose Fulbright LLP Tel Matthew Hardwick Senior associate, London Norton Rose Fulbright LLP Tel Norton Rose Fulbright 17

20 Feasibility

21 Norton Rose Fulbright Norton Rose Fulbright is a global legal practice. We provide the world s pre-eminent corporations and financial institutions with a full business law service. We have more than 3800 lawyers based in over 50 cities across Europe, the United States, Canada, Latin America, Asia, Australia, Africa, the Middle East and Central Asia. Recognized for our industry focus, we are strong across all the key industry sectors: financial institutions; energy; infrastructure, mining and commodities; transport; technology and innovation; and life sciences and healthcare. Wherever we are, we operate in accordance with our global business principles of quality, unity and integrity. We aim to provide the highest possible standard of legal service in each of our offices and to maintain that level of quality at every point of contact. Norton Rose Fulbright LLP, Norton Rose Fulbright Australia, Norton Rose Fulbright Canada LLP, Norton Rose Fulbright South Africa (incorporated as Deneys Reitz Inc) and Fulbright & Jaworski LLP, each of which is a separate legal entity, are members ( the Norton Rose Fulbright members ) of Norton Rose Fulbright Verein, a Swiss Verein. Norton Rose Fulbright Verein helps coordinate the activities of the Norton Rose Fulbright members but does not itself provide legal services to clients. References to Norton Rose Fulbright, the law firm, and legal practice are to one or more of the Norton Rose Fulbright members or to one of their respective affiliates (together Norton Rose Fulbright entity/entities ). No individual who is a member, partner, shareholder, director, employee or consultant of, in or to any Norton Rose Fulbright entity (whether or not such individual is described as a partner ) accepts or assumes responsibility, or has any liability, to any person in respect of this communication. Any reference to a partner or director is to a member, employee or consultant with equivalent standing and qualifications of the relevant Norton Rose Fulbright entity. The purpose of this communication is to provide information as to developments in the law. It does not contain a full analysis of the law nor does it constitute an opinion of any Norton Rose Fulbright entity on the points of law discussed. You must take specific legal advice on any particular matter which concerns you. If you require any advice or further information, please speak to your usual contact at Norton Rose Fulbright. Norton Rose Fulbright LLP NRF /13 (UK) Extracts may be copied provided their source is acknowledged.

22 Law around the world nortonrosefulbright.com

Listed company long-term executive share incentive plans

Listed company long-term executive share incentive plans Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Listed company long-term executive share incentive plans Incentivising

More information

Part 2 Detailed engineering and construction

Part 2 Detailed engineering and construction FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES Part 2 Detailed engineering and construction An essential guide

More information

Tax considerations for US companies offering international equity incentive programmes

Tax considerations for US companies offering international equity incentive programmes Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Tax considerations for US companies offering international equity incentive

More information

Pensions. Duties of employers, trustees and administrators to members: recent Pensions Ombudsman determinations. Briefing. Summary

Pensions. Duties of employers, trustees and administrators to members: recent Pensions Ombudsman determinations. Briefing. Summary Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Pensions Duties of employers, trustees and administrators to members:

More information

Working and ordinarily working in the UK

Working and ordinarily working in the UK Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Working and ordinarily working in the UK Briefing January 2015 Introduction

More information

Asset management. Strategic use of technology and outsourcing to address cost pressures and enhance market position

Asset management. Strategic use of technology and outsourcing to address cost pressures and enhance market position Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Asset management Strategic use of technology and outsourcing to address

More information

Litigation trends. Survey report

Litigation trends. Survey report Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Litigation trends Survey report The 10th Annual Litigation Trends Survey

More information

Big Data and the Internet of Things

Big Data and the Internet of Things Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Big Data and the Internet of Things Protecting rights, controlling

More information

Pensions. Briefing. The PPF Entry Process. Stage 1. Stage 2. December 2011. Summary

Pensions. Briefing. The PPF Entry Process. Stage 1. Stage 2. December 2011. Summary Pensions FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES Briefing The PPF Entry Process December 2011 Summary

More information

MiFID II/MiFIR series

MiFID II/MiFIR series Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare MiFID II/MiFIR series Impact on commodities and commodity derivatives

More information

AIFM Directive. Briefing. The impact on non-eu fund managers of non-eu funds. Introduction. Overview of the AIFMD

AIFM Directive. Briefing. The impact on non-eu fund managers of non-eu funds. Introduction. Overview of the AIFMD AIFM Directive FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES Briefing August 2012 The impact on non-eu fund

More information

China new healthcare reform 2020

China new healthcare reform 2020 Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare China new healthcare reform 2020 Ten things to know Norton Rose Fulbright

More information

How To Get A Listing On The Cenrax Or Cenreo

How To Get A Listing On The Cenrax Or Cenreo Guide to mining projects and mining finance in Canada Financing mining projects Exploration companies without income often look to the equity capital markets to fund on-going exploration. The ramp-up to

More information

CORPORATE FINANCE FINANCIAL INSTITUTIONS ENERGY AND INFRASTRUCTURE. Undertakings. Norton Rose LLP June 2012. PAR-#4041659-v1 1

CORPORATE FINANCE FINANCIAL INSTITUTIONS ENERGY AND INFRASTRUCTURE. Undertakings. Norton Rose LLP June 2012. PAR-#4041659-v1 1 CORPORATE FINANCE FINANCIAL INSTITUTIONS ENERGY AND INFRASTRUCTURE Undertakings Norton Rose LLP June 2012 1 UNDERTAKINGS What is an undertaking? 1 In general terms, an undertaking is simply an enforceable

More information

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework All interested parties Direct Dial: 020 7901 1849 Email: transmissioncompetition@ofgem.gov.uk Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance

More information

Taxation of aircraft financing in Germany

Taxation of aircraft financing in Germany Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Taxation of aircraft financing in Germany Briefing September 2013 1

More information

Registration of foreign loans in Brazil - ROF

Registration of foreign loans in Brazil - ROF Registration of foreign loans in Brazil - ROF - November, 2013 November 2013 2 Registration of Foreign Loans in Brazil - ROF (Registro de Operações Financeiras) The 2014 FIFA World Cup and 2016 Olympics

More information

Compliance issues for pharmaceutical companies in Germany

Compliance issues for pharmaceutical companies in Germany Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Compliance issues for pharmaceutical companies in Germany Ten things

More information

MiFID II/MiFIR series

MiFID II/MiFIR series Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare MiFID II/MiFIR series Trading venues and market infrastructure Briefing

More information

Competition litigation

Competition litigation FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES Competition litigation in the UK Class act Competition litigation

More information

Asset management. Briefing. Establishing an asset management presence in Hong Kong and Singapore. Introduction. Hong Kong

Asset management. Briefing. Establishing an asset management presence in Hong Kong and Singapore. Introduction. Hong Kong Asset management FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES Briefing August 2011 Establishing an asset management

More information

The refinancing of the Fazakerley PFI prison contract

The refinancing of the Fazakerley PFI prison contract Report by the Comptroller and Auditor General The Prison Service The refinancing of the Fazakerley PFI prison contract Ordered by the House of Commons to be printed 26 June 2000 LONDON: The Stationery

More information

Developing a Public-Private Partnership Framework: Policies and PPP Units

Developing a Public-Private Partnership Framework: Policies and PPP Units Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework

More information

Venezuela. Ten things to know when investing by way of debt or equity

Venezuela. Ten things to know when investing by way of debt or equity Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Venezuela Ten things to know when investing by way of debt or equity

More information

Pensions. Briefing. Summary. May 2012

Pensions. Briefing. Summary. May 2012 Pensions FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES Briefing May 2012 High Court considers scope of transferring

More information

Bauhaus Capital Partners

Bauhaus Capital Partners Bauhaus Capital Partners Financial Advisory & Investment Banking Madrid London Bogotá Kiev São Paulo Riyadh Abuja Istanbul Moscow Singapore Hong Kong Miami Bangalore Lagos Mexico City Bauhaus Capital is

More information

Cruise Finance Simon Hartley Partner Norton Rose Fulbright LLP 19 May 2015

Cruise Finance Simon Hartley Partner Norton Rose Fulbright LLP 19 May 2015 Cruise Finance Simon Hartley Partner Norton Rose Fulbright LLP 19 May 2015 Cruise Financing Introduction Background to our involvement (i.e. shipping focus of firm but particular involvement with cruise

More information

London Green Fund Selection of Waste Urban Development Funds IR-893. Questions and Answers

London Green Fund Selection of Waste Urban Development Funds IR-893. Questions and Answers London Green Fund Selection of Waste Urban Development Funds IR-893 Questions and s Question 1. What restriction, if any, will be placed on the waste UDF s ability to re-invest the initial commitment of

More information

InsureTech 2015: Addressing cybersecurity and fraud in the ME insurance industry

InsureTech 2015: Addressing cybersecurity and fraud in the ME insurance industry InsureTech 2015: Addressing cybersecurity and fraud in the ME insurance industry Dino Wilkinson Partner Norton Rose Fulbright (Middle East) LLP 3 February 2015 The growing challenge of cyber risks From

More information

Mega bridge P3 the Detroit River International Crossing (DRIC)/New International Trade Crossing (NITC)

Mega bridge P3 the Detroit River International Crossing (DRIC)/New International Trade Crossing (NITC) Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Mega bridge P3 the Detroit River International Crossing (DRIC)/New

More information

German Stock Corporation Act (Aktiengesetz)

German Stock Corporation Act (Aktiengesetz) Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare German Stock Corporation Act (Aktiengesetz) English translation as

More information

FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES

FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES Nuclear Finance Basics FINANCIAL INSTITUTIONS Offtakers Regulators Developers People International Stakeholders Government Operators Suppliers Public Legacy Managers Financers Insurers 2 NEPIO Government

More information

Moroccan plan for solar energy

Moroccan plan for solar energy Moroccan plan for solar energy FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE AND COMMODITIES TRANSPORT TECHNOLOGY Briefing October 2010 MASEN 500MW Phase One Solar Power Complex at Ouarzazate The Kingdom

More information

How a Hotel Valuation is Undertaken and What a Bank Really Needs from a Valuation

How a Hotel Valuation is Undertaken and What a Bank Really Needs from a Valuation Hotel Valuation How a Hotel Valuation is Undertaken and What a Bank Really Needs from a Valuation This summary paper outlines what is involved in a hotel valuation, and how it can be useful, as well as

More information

Ship finance leasing in China

Ship finance leasing in China Ship finance leasing in China FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES Jonathan Silver Of Counsel, Norton

More information

Cybersecurity and Privacy 2015: Presentation to Institute of International Bankers

Cybersecurity and Privacy 2015: Presentation to Institute of International Bankers Cybersecurity and Privacy 2015: Presentation to Institute of International Bankers Sue Ross Senior Counsel Norton Rose Fulbright US LLP October 27, 2015 Speaker Sue Ross Senior Counsel Norton Rose Fulbright

More information

African Barrick Gold. BMO Global Metals & Mining Conference February 2013

African Barrick Gold. BMO Global Metals & Mining Conference February 2013 African Barrick Gold BMO Global Metals & Mining Conference February 2013 Disclaimer Important Notice This presentation has been provided to you for information purposes only. It does not constitute an

More information

6 STEP 6 - PREPARING THE ACTION PLAN 2

6 STEP 6 - PREPARING THE ACTION PLAN 2 CONTENTS 6 STEP 6 - PREPARING THE ACTION PLAN 2 6.1 USER GUIDE TO THIS STEP 2 6.2 KEY MESSAGES OF THIS STEP 4 6.3 PREPARING THE ACTION PLAN 5 6.4 PRE-FEASIBILITY STUDY 8 6.5 PREPARING AN INVESTMENT PLAN

More information

Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa

Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Overcoming financing challenges for Hydro Power Projects Francois Viljoen, Director, Cresco Project Finance, South Africa Contents Features of Project Finance Challenges posed by Project Finance Risk assessment

More information

Corporate Risk Management Advisory Services FX and interest rate solutions for clients

Corporate Risk Management Advisory Services FX and interest rate solutions for clients Corporate Risk Management Advisory Services FX and interest rate solutions for clients Risk Management: The UBS Warburg approach UBS Warburg has built an outstanding reputation in the management of foreign

More information

THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM. Mr C. A. F. Sweet The South Institute of Mining and Metallurgy

THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM. Mr C. A. F. Sweet The South Institute of Mining and Metallurgy THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM Mr C. A. F. Sweet The South Institute of Mining and Metallurgy The inter-relationship between these parties and the effect

More information

London STOCK EXCHANGE

London STOCK EXCHANGE London STOCK EXCHANGE 16 March 2006 For the attention of the Nominated Advisers/ Finance Directors/ Company Secretaries, all AIM Companies 10 Paternoster Square London EC4M 7LS Telephone 020 7797 1000

More information

Sedgman enters agreement to acquire MDM Engineering

Sedgman enters agreement to acquire MDM Engineering Sedgman Limited [ASX: SDM] ABN 86 088 471 667 Head Office Level 2, 2 Gardner Close Milton QLD 4064 AUSTRALIA Ph: +61 7 3514 1000 Fax: +61 7 3514 1999 Postal Address PO Box 1801 Milton BC QLD 4064 Email:

More information

MiFID II / MiFIR seminar Planning your MiFID II / MiFIR Project. Hannah Meakin, Partner Norton Rose Fulbright LLP 15 October 2014

MiFID II / MiFIR seminar Planning your MiFID II / MiFIR Project. Hannah Meakin, Partner Norton Rose Fulbright LLP 15 October 2014 MiFID II / MiFIR seminar Planning your MiFID II / MiFIR Project Hannah Meakin, Partner Norton Rose Fulbright LLP 15 October 2014 Planning your MiFID II / MiFIR Project Macro themes in your MiFID II / MiFIR

More information

Shared Services Toolkit

Shared Services Toolkit Shared Services Toolkit Shared Services Toolkit Introduction Sharing services is essential if Government is to meet its financial targets. Whether you do this as a group of central or local Government

More information

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 1. INTRODUCTION Financial institutions outsource business activities, functions and processes

More information

Leases Summary of outreach meetings with investors and analysts on proposed accounting by lessees May September 2013

Leases Summary of outreach meetings with investors and analysts on proposed accounting by lessees May September 2013 Introduction 1. This summary outlines the feedback that the IASB and the FASB (the boards) received at meetings with investors and analysts on the lessee accounting proposals included in the Leases Exposure

More information

Italian insurance regulatory updates

Italian insurance regulatory updates Italian insurance regulatory updates Nicolo Juvara (Partner) and Leonardo Gianni (Senior associate) Norton Rose Fulbright Studio Legale 5 September 2013 Regulatory framework innovations Main areas affected

More information

International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies

International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies Sergei Sabanov, PhD, CEng MIMMM Date:10 December 2013 Location: Almaty, Kazakhstan SRK Consulting

More information

Establishing the feasibility of your proposed mining venture

Establishing the feasibility of your proposed mining venture RUPPRECHT, S. Establishing the feasibility of your proposed mining venture. International Platinum Conference Platinum Adding Value, The South African Institute of Mining and Metallurgy, 2004. Establishing

More information

STANDARD LIFE EUROPEAN PRIVATE EQUITY TRUST PLC

STANDARD LIFE EUROPEAN PRIVATE EQUITY TRUST PLC This document is issued by Standard Life European Private Equity Trust PLC (the "Company") and is made available by SL Capital Partners LLP (the AIFM ) solely in order to make certain particular information

More information

Antitrust-approval risks:

Antitrust-approval risks: Financial institutions Energy Infrastructure, mining and commodities Transport Technology and innovation Life sciences and healthcare Antitrust-approval risks: Issues and pitfalls in international M&A

More information

IFRS industry insights

IFRS industry insights IFRS Global Office Issue 2, June 2011 IFRS industry insights Joint arrangements in the energy and resources industry The most significant change will likely be the removal of the option to proportionately

More information

HKAS 27 Consolidated and Separate Financial Statements 1

HKAS 27 Consolidated and Separate Financial Statements 1 HKAS 27 Consolidated and Separate Financial Statements 1 Nelson Lam 1. Scope of HKAS 27 Hong Kong Accounting Standard (HKAS) 27 Consolidated and Separate Financial Statements shall be applied in the preparation

More information

STOCK BASED LOANS. Part of the EC Funding Program

STOCK BASED LOANS. Part of the EC Funding Program Part of the EC Funding Program London 2012 Our Lender specializes in Share Financing, which is also known as a Stock Loan. The Lender has been funding loans in Europe, North America, and the Middle East

More information

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9

NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 A G U I D E T O A I M U K TA X B E N E F I T S 2 AIM Note for Mining, Oil and Gas Companies Contents Introduction 1 Companies to which this Note

More information

NEWSFLASH October 2009

NEWSFLASH October 2009 NEWSFLASH October 2009 INVESTING IN INFRASTRUCTURE IN VIETNAM Vietnam's need for investment in infrastructure to keep pace with and to sustain economic growth has been voiced loudly. To date, the State

More information

From PF1 to PF2: the reform of the Public Private Partnership model in the UK

From PF1 to PF2: the reform of the Public Private Partnership model in the UK From PF1 to PF2: the reform of the Public Private Partnership model in the UK - November, 2013 November, 2013 2 From PFI to PF2: the reform of the Public Private Partnership The British government has

More information

Urban Community Energy Fund Getting your project investment ready

Urban Community Energy Fund Getting your project investment ready Urban Community Energy Fund Getting your project investment ready What is investment readiness, and why does it matter? Investment readiness is when your project is at the right stage to secure a bank

More information

How To Understand The New Financial Regulations In European Law

How To Understand The New Financial Regulations In European Law Seventh Annual MIG seminar: The Impact of MiFID II and EMIR on Commodities Hannah Meakin (Partner) and Cat Blake (Associate) 5 March 2014 Overview MiFID II: What are financial instruments? Additions and

More information

IAS 28 Investments in Associates Impairment of investments in associates in separate financial statements

IAS 28 Investments in Associates Impairment of investments in associates in separate financial statements STAFF PAPER IFRS Interpretations Committee Meeting September 2012 Project IAS 28 Investments in Associates Impairment of investments in associates in separate financial statements CONTACT(S) Leonardo Piombino

More information

alternative finance conference

alternative finance conference alternative finance conference accessing Asian capital through dual listings on the Hong Kong Stock Exchange Paul D. Davis, Partner October 4, 2012 McMillan LLP Vancouver Calgary Toronto Ottawa Montréal

More information

PRESIDIO PARKWAY FINANCIAL PROPOSAL 2.1.2. FINANCIAL PROPOSAL EXECUTIVE SUMMARY GOLDEN LINK PARTNERS

PRESIDIO PARKWAY FINANCIAL PROPOSAL 2.1.2. FINANCIAL PROPOSAL EXECUTIVE SUMMARY GOLDEN LINK PARTNERS 2.1.2. EXECUTIVE SUMMARY The Presidio Parkway Project (the Project ) is a landmark transaction in a high profile location and as the Project is the first transportation P3 in the State, its success is

More information

Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL. XXXXX PPP Unit

Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL. XXXXX PPP Unit Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL XXXXX PPP Unit Chief Executive Officer Job Description: The CEO is tasked with the establishment of a PPP Unit for the Government

More information

LEGG MASON GLOBAL FUNDS PLC Riverside Two Sir John Rogerson s Quay, Grand Canal Dock, Dublin 2, Ireland

LEGG MASON GLOBAL FUNDS PLC Riverside Two Sir John Rogerson s Quay, Grand Canal Dock, Dublin 2, Ireland LEGG MASON GLOBAL FUNDS PLC Riverside Two Sir John Rogerson s Quay, Grand Canal Dock, Dublin 2, Ireland 5 March 2015 THIS DOCUMENT IS IMPORTANT AND REQUIRES YOUR IMMEDIATE ATTENTION. IF YOU ARE IN ANY

More information

CORPORATE FINANCE FINANCIAL INSTITUTIONS ENERGY AND INFRASTRUCTURE. Events of default. Norton Rose LLP June 2012.

CORPORATE FINANCE FINANCIAL INSTITUTIONS ENERGY AND INFRASTRUCTURE. Events of default. Norton Rose LLP June 2012. CORPORATE FINANCE FINANCIAL INSTITUTIONS ENERGY AND INFRASTRUCTURE Events of default Norton Rose LLP June 2012 1 EVENTS OF DEFAULT Events of default in loan agreements 1 Loan agreements normally specify

More information

Brighton and Sussex University Hospital NHS Trust

Brighton and Sussex University Hospital NHS Trust Brighton and Sussex University Hospital NHS Trust Year Ending 31 March 2013 Annual Audit Letter July 2013 Ernst & Young LLP Executive summary Ernst & Young LLP 1 More London Place London SE1 2AF Tel: +44

More information

Measured development Construction and Engineering Training Supplement Guide

Measured development Construction and Engineering Training Supplement Guide Construction and Engineering Training Supplement Guide Welcome Eversheds is the law firm behind some of the world s most ambitious construction and engineering projects. We have one of the biggest teams

More information

Introduction to Warranty and Indemnity Insurance 18 October 2012

Introduction to Warranty and Indemnity Insurance 18 October 2012 Introduction to Warranty and Indemnity Insurance 18 October 2012 Mergers & Acquisitions Insurance Group Adrian Furlonge Assistant Vice President Svetlana Soroka Senior Underwriter Introduction Background

More information

GOING PUBLIC IN CANADA

GOING PUBLIC IN CANADA GOING PUBLIC IN CANADA CASSELS BROCK IN BRIEF Canadian law firm of more than 200 lawyers based in Toronto and Vancouver focused on serving the transaction, advocacy and advisory needs of the country s

More information

Capital Projects. Providing assurance over effective delivery of projects

Capital Projects. Providing assurance over effective delivery of projects Capital Projects Providing assurance over effective delivery of projects Governance and oversight Project Scope and change Reporting and communication Project risk and success factors Delivery Major projects

More information

Course Brochure. New York. Doha

Course Brochure. New York. Doha Course Brochure LONDON New York Dubai Hong Kong Singapore Johannesburg Doha Aberdeen abuja kuala lumpur Table of contents Background page 3 Oil & Gas Faculty pages 5-8 Mining Faculty pages 9-11 Public

More information

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector

More information

Consolidated Financial Statements

Consolidated Financial Statements STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 110 Consolidated Financial Statements This standard applies for annual periods beginning on or after 1 January 2013. Earlier application is permitted

More information

Updating the New Zealand Emissions Trading Scheme: Consultation Document

Updating the New Zealand Emissions Trading Scheme: Consultation Document Updating the New Zealand Emissions Trading Scheme: Consultation Document submission: Updating the New Zealand Emissions Trading Scheme: A Consultation Document 11 May 2012 John Johnston Head of Government

More information

Intellectual Property Litigation Insurance Proposal Form

Intellectual Property Litigation Insurance Proposal Form PROPOSAL FORM Intellectual Property Litigation Insurance Proposal Form Important tice 1. This proposal must be completed in black ink by a partner, principal or director of the firm or company. All questions

More information

Initial Public Offering. Are you ready to float?

Initial Public Offering. Are you ready to float? Initial Public Offering Are you ready to float? What is an IPO? Are you considering listing your company on a stock exchange? In recent times, the phrases listing and floating have been replaced with an

More information

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: The Role of Construction Managers FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: A. Notes on the use of FIDIC in the Middle East B. A Communication

More information

ASPE AT A GLANCE Section 3856 Financial Instruments

ASPE AT A GLANCE Section 3856 Financial Instruments ASPE AT A GLANCE Section 3856 Financial Instruments December 2014 Section 3856 Financial Instruments Effective Date Fiscal years beginning on or after January 1, 2011 1 SCOPE Applies to all financial instruments

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

ASSET FINANCE & LEASING. Delivering expert solutions

ASSET FINANCE & LEASING. Delivering expert solutions ASSET FINANCE & LEASING Delivering expert solutions Delivering expert solutions Winners of the Legal Firm of the Year award LEASING WORLD AWARDS 2014 A MEETING OF MINDS Asset finance is an increasingly

More information

eqube Gaming Limited Condensed Interim Consolidated Financial Statements For the Three and Nine Months Ended November 30, 2015 (Unaudited)

eqube Gaming Limited Condensed Interim Consolidated Financial Statements For the Three and Nine Months Ended November 30, 2015 (Unaudited) Condensed Interim Consolidated Financial Statements For the Three and Nine Months Ended November 30, 2015 Notice to Reader The following interim consolidated financial statements and notes have not been

More information

EDISTON PROPERTY INVESTMENT COMPANY PLC

EDISTON PROPERTY INVESTMENT COMPANY PLC E095\001\EH5977615.4 This document is issued by Ediston Investment Services Limited as alternative investment fund manager of Ediston Property Investment Company plc (the "Company") solely in order to

More information

Real Estate & Mortgage Investment Specialists

Real Estate & Mortgage Investment Specialists Your Real Estate & Mortgage Investment Specialists Private Lending FAQ s 1. Why Should I Invest In A Mortgage? A mortgage is a loan in which real estate or property is used as collateral. When an individual

More information

I N T E R I M R E P O R T 2 0 0 9

I N T E R I M R E P O R T 2 0 0 9 I N T E R I M R E P O R T 2 0 0 9 LETTER FROM THE CEO Leigh A. Hooper, CEO Dear Investor, Thank you for your interest and continued support of Activa Resources AG. The first half of 2009 was very challenging

More information

SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS

SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS SUPERVISORY AND REGULATORY GUIDELINES: PU48-0809 ISSUED: 4 th May 2004 REVISED: 27 th August 2009 GUIDELINES ON MINIMUM STANDARDS FOR THE OUTSOURCING OF MATERIAL FUNCTIONS I. INTRODUCTION The Central Bank

More information

Major Drilling Reports First Quarter Results and Declares Dividend

Major Drilling Reports First Quarter Results and Declares Dividend NEWS RELEASE Major Drilling Reports First Quarter Results and Declares Dividend MONCTON, New Brunswick (September 3, 2014) Major Drilling Group International Inc. (TSX: MDI) today reported results for

More information

MiFID II Academy: Product Governance. Floortje Nagelkerke 12 April 2016

MiFID II Academy: Product Governance. Floortje Nagelkerke 12 April 2016 MiFID II Academy: Product Governance Floortje Nagelkerke 12 April 2016 Introduction Timing: MiFID II / MiFIR 2 July MiFID II and MiFIR entered into force 19 December Level 2 Consultation on technical standards

More information

PROJECT FINANCE UNCDF October 2014 Dar Es Salaam

PROJECT FINANCE UNCDF October 2014 Dar Es Salaam Project Finance PROJECT FINANCE UNCDF October 2014 Dar Es Salaam AGENDA History and Definition Structure of Project Finance Transactions Key Players Milestones Role of Debt in PF transactions Risk Management

More information

Strategic Program Management

Strategic Program Management Governance Assessment Organizational Change Management Strategic Program Management Continuous Improvement Framework Processes Strategy Strategic Program Management Bob Prieto Published by Construction

More information

Internal Audit Report. Chief Executive s Unit. Review of Contract Management

Internal Audit Report. Chief Executive s Unit. Review of Contract Management Internal Audit Report Chief Executive s Unit Review of Contract Management February 2010 CONTENTS 1. BACKGROUND 1 Page 2. AUDIT SCOPE AND OBJECTIVES 1 3. AUDIT APPROACH 1 4. AMENDED PROCESS 2 5. SUMMARY

More information

Patricia McConnell: Will the elimination of operating lease accounting improve financial reporting by lessees?

Patricia McConnell: Will the elimination of operating lease accounting improve financial reporting by lessees? Patricia McConnell: Will the elimination of operating lease accounting improve financial reporting by lessees? 24 June 2010 To address investors concerns about off-balance sheet assets and liabilities

More information

GUYANA GOLDFIELDS INC.

GUYANA GOLDFIELDS INC. Condensed Consolidated Interim Financial Statements (Unaudited, Expressed in United States Dollars) For the Three and Six Months Ended April 30, 2014 Guyana Goldfields Inc. Condensed Consolidated Interim

More information

Introduction to Australian Real Estate Debt Securities

Introduction to Australian Real Estate Debt Securities 1 Introduction Introduction to Australian Real Estate Debt Securities Superannuation fund investors and managers have for a long time invested in real estate as part of their asset allocation in the belief

More information

EMBEDDING BCM IN THE ORGANIZATION S CULTURE

EMBEDDING BCM IN THE ORGANIZATION S CULTURE EMBEDDING BCM IN THE ORGANIZATION S CULTURE Page 6 AUTHOR: Andy Mason, BSc, MBCS, CITP, MBCI, Head of Business Continuity, PricewaterhouseCoopers LLP ABSTRACT: The concept of embedding business continuity

More information

The Family Office Guide. A practical guide to the regulatory issues on setting up and running a family office in the UK

The Family Office Guide. A practical guide to the regulatory issues on setting up and running a family office in the UK The Family Office Guide A practical guide to the regulatory issues on setting up and running a family office in the UK About Taylor Wessing Taylor Wessing is a leading international law firm in Europe,

More information

Cash Flow Overview: Ethanol Plants in 2014-2015. Connie Lindstrom Benchmarking Consultant, Christianson & Associates, PLLP

Cash Flow Overview: Ethanol Plants in 2014-2015. Connie Lindstrom Benchmarking Consultant, Christianson & Associates, PLLP Cash Flow Overview: Ethanol Plants in 2014-2015 Connie Lindstrom Benchmarking Consultant, Christianson & Associates, PLLP 2015 Christianson & Associates, PLLP Data from Biofuels Benchmarking TM Developed

More information

London Borough of Havering. Draft Planning Guidance Note on Affordable Housing. Commuted Sum Payments

London Borough of Havering. Draft Planning Guidance Note on Affordable Housing. Commuted Sum Payments London Borough of Havering Draft Planning Guidance Note on Affordable Housing Commuted Sum Payments May 2016 Affordable housing circumstances where Havering Council will use commuted sum payments to the

More information

Regulatory impact assessment on capital requirements for reverse mortgage loans

Regulatory impact assessment on capital requirements for reverse mortgage loans Regulatory impact assessment on capital requirements for reverse mortgage loans 28 October 2015 2 Agency disclosure statement 1. This Regulatory Impact Statement (RIS) has been prepared by the Reserve

More information

B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org

B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org "INOGATE Technical Secretariat & Integrated Programme in support of the Baku Initiative and the Eastern Partnership energy objectives" Project B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y

More information