Quantity Takeoff. Dr. Ahmed Elyamany

Size: px
Start display at page:

Download "Quantity Takeoff. Dr. Ahmed Elyamany"

Transcription

1 Quantity Takeoff Dr. Ahmed Elyamany 1

2 Outline Importance of Quantity Takeoff Preparation of Quantity Takeoff Measurement Units Measuring excavation, P.C footings, Beams, Columns, slabs, and stairs. Solved Example 2

3 Quantity Takeoff Quantity takeoff is an activity performed by General Contractors, Subcontractors, Cost Consultants, and Quantity Surveyors as part of the construction process. It involves counting the number of items associated with a particular construction project 3

4 Quantity Takeoff Quantity Takeoff is performed by: General Contractors, Subcontractors, Cost Consultants, Quantity Surveyors Counting the number of items associated with a particular construction project Determining the associated materials and labor costs Preparing an estimate as part of the bidding process. Applied to the pricing process. 4

5 Quantity take-off: Why? Owner perspective: Initial estimate of the project costs at the different stages of the project. Preparing the BOQ as a requirement of the contract documents. Estimating the work done for issuing the contractor payments. Contractor perspective: Pricing different work items. Identifying the needed resources (Labor, Equipment, etc.). Project schedule. Preparing invoices for work done. Subcontractors payments. Review and control of crews production rates. 5

6 Quantity Takeoff The quantity takeoff process is typically done manually using a printout, a pen, and a calculator. 6

7 Quantity Takeoff New Trend is Building Information Modeling (BIM) Provide a solution that generates a set of takeoff elements (counts, measurements, conditions that affect cost) enables estimators to more quickly and more accurately perform takeoff for bidding or pricing. 7

8 Quantity Takeoff Important to specify the type of ; Imported materials Suppliers Equipment Labors Work in project Important to know project budget Important to know activities logic 8

9 Quantity Takeoff Criteria It must be as accurate as possible Should be based on all available engineering and design data. Use of appropriate automation tools is highly recommended. The Quantity Takeoff is an important part of the cost estimate. 9

10 Quantity Takeoff Input Documents Input from the client (task description). Conditions (general, special, supplementary). Drawing and specifications. Addenda. Agreement form. Modifications. 10

11 Quantity Development Guidelines Coordinate the quantity takeoff process and plan with the estimator. Include a list of materials in quantity takeoffs. Utilize a process that easily records the quantity Check scales and dimensions on each drawing sheet. Highlight drawing areas where quantities have been determined to ensure all elements is captured but not double counted. 11

12 Quantity Development Guidelines Consider items that have no material but still require cost, e.g., job office overhead, task setup, training and certifications. Add a certain amount of waste, loss, drop off, or length related to the material purchases for a bulk order. Coordinate with designers if the design appears in error.. 12

13 Takeoff Sheet & Bill Of Quantities Quantity Takeoff Sheet مقايسات كميات Estimated Quantities Actual Quantities Bill Of Quantities (BOQ) مقايسات أعمال تقديرية مقايسات أعمال فعلية مقايسات تثمينية 13

14 Quantity Takeoff Sheet Item Item Unit Quantity Length Dimension Width Height Part Subtraction Addition Total

15 Bill Of Quantities Price Notes Item Item Unit Quantity Unit Total

16 Bill of Quantities classification The Bill of Quantities is classified into the following work groups: Civil works Sanitary works Electrical works Mechanical works 16

17 Bill of Quantities classification Civil works: Earth works: leveling, excavation, backfilling, transportation of excavated soil) Foundation works: plain concrete reinforced concrete piling foundations 17

18 Bill of Quantities classification Civil works: Brick works: Internal brick work External brick work Skelton reinforce concrete: Columns, Beans, Slabs Stairs 18

19 Bill of Quantities classification Civil works: Finishing: Water proofing Staircases Plastering Flooring Painting Metal works: Windows Doors Accessories 19

20 Bill of Quantities classification Sanitary works: Water feeding systems Internal and external plumbing works Finishes of plumbing works Electrical works: Electrical cables Wiring; Accessories Internal connections Mechanical works: Air conditioning systems Elevators 20

21 Work order Items in takeoff sheets are organized in the same construction sequence. Order of items in the same chapter: Items estimated in (m3) Items estimated in (m2) Items estimated in (m) Items estimated in (unit) Items estimated in (ton) Items estimated in (L.S.) 21

22 Measuring Units The units of measurements for civil engineering works are mainly categorized for their: Nature Shape Size and Payments to the contractor. There are a number of standard codes and methods of measurement that are available. 22

23 Measuring Units Cubic meter (m 3 ) Used for items such as: Excavation Backfilling Concrete Brick walls ( 25 cm thick) Square meter (m2) Used for items such as: Brick walls (<25 cm thick) Plastering Flooring Painting 23

24 Measuring Units Linear meter (m) Used for items such as: Pipe lines Canals Stair steps Windows sills Number (unit) Used for items such as: Electric outlets Doors and windows Sanitary fixtures Precast concrete 24

25 Measuring Units Lump sum(l.s.) Item is subcontracted when the contractor does not have enough experience to construct it or there is an item which has a small quantities of many work items such as: Manholes Lifts Some electrical and plumbing works Weight (Ton): Metallic works Reinforcement steel 25

26 Preparation of Quantity Takeoff Check the availability of drawings Check the axis and dimensions Check building levels and link it to structural drawings. Check doors and windows model numbers Check ground water levels 26

27 Preparation of Quantity Takeoff Check architectural against structural drawings Check foundation design and foundation levels Check construction members dimension and reinforcement. Review the contract conditions and specifications 27

28 Formulas Square Rectangle Parallelogram Trapezoid Trapezium 28

29 Formulas Triangles Regular Polygons Circle Parabola Ellipse 29

30 Formulas 30

31 Formulas 31

32 Formulas 32

33 Formulas 33

34 Formulas 34

35 Formulas 35

36 Earth works Excavation Quantities are calculated based on the dimensions of the foundation in plans from the owner perspective. Contractors should consider the excess of material excavated to all for safe operations. Prices differ based on the soil type, deep of excavation, ground water level, site location, shoring system, Equipment used, etc. Unit of measurement is cubic meter (volume). Consider the example in the following slide: 36

37 Earth works Excavation The length of excavation = (4.4 2) 2 = 15.6 m Depth of excavation = 1.8 m Width of excavation = width of plain concrete footing = 1.0 m Volume = = 18.8 m3 37

38 Earth works Backfilling Unit of measurement is cubic meter (volume) Consider the example shown in previous slide, the volume of backfilling could be calculated as follow: Volume of backfilling = excavation concrete brick Volume of concrete = = 6.24 m3 Volume of brick = = m3 Volume of backfilling = 18.8 ( ) = m3 38

39 Earth works Site leveling & Soil transportation Site leveling: Measured in m2 (area) if thickness < 30cm. Measured in m3 (volume) if thickness > 30cm. Soil transportation: Transported soil = Vol. of exc. Vol. of backfilling + additional soil at site Add swelling factor based on the soil type: 5% sandy soil. 15% clayey soil and 25% for demolition material. (owner or contractor) 39

40 Concrete works Plain concrete & Reinforced concrete Plain concrete (PC): Measured in m2 (area) if thickness < 20 cm. Measured in m3 (volume) if thickness 20 cm. Average thickness should be mentioned when measurement is done by area. Reinforced concrete (RC): All RC elements measured by volume (m3) except hollow block slabs measured by area (m2). Domes, cylindrical roofs and shells measured by area in the horizontal projection. 40

41 Concrete works Plain Concrete Footing Quantity of P.C footing = No. of footings for a specific model * length * width * depth Total quantity of P.C footings = summation of P.C footing models RC Footing PC Footing 41

42 Concrete works Ground Beams Quantity of ground beam = No. of ground beams for a specific model * length * width * depth Total quantity of ground beams = summation of ground beam models Ground Beam RC Footing PC Footing 42

43 Concrete works Columns Quantity of columns = No. of columns for a specific model * length * width * height Total quantity of columns = summation of columns models Columns RC Footing PC Footing 43

44 Concrete works Slabs Solid slabs: Quantity of slab = length * width * thickness Flat slab: Quantity of slab = length * width * thickness Beams: Quantity of beam = length * width * height 44

45 Brick works Measured in m2 (by area) if thickness <25 cm. Measured in m3 (by volume) if thickness 25cm. Deduct all openings. Deduct half the area (volume) of arches. Deduct all Concrete elements. Separate item for each brick type 45

46 Stairs Quantity of stairs = inclined length * width * height + stair section area * stair width * No. of stairs stair section area 46

47 Plastering Internal Plaster: Engineering measurement by area (m2). All openings are deducted. All openings sides are added. Inclined slabs are calculated based on their horizontal projection. 47

48 Plastering External plaster: Measured by area (m2). Openings with areas < 4 m2 are kept with deduction. Deduct half the area of the openings 4 m2. Openings with areas < 4 m2 are kept with deduction. Cantilever slabs < 1 m projection not added. Add half the area of cantilever slabs 1 m. 48

49 EXAMPLE 1 Substructure Taking-off List Site preparation Removing trees and shrubs Lifting turf Top soil/removing/preserving Excavation Reduce levels/disposal of excavated material Excavating trenches/disposal of excavated Material/Filling/Surface treatments Concrete Foundations Beds/formwork/damp-proof membrane Masonry Brick walls Forming cavities Filling to cavities 49

50 EXAMPLE 1 Substructure Site levels Top soil cannot be used for backfilling as it would, over time, cause damage to the substructure. The usual default depth for topsoil is 150 mm Next figure is a 5 m grid of a survey of levels taken on a site. The site is required to be reduced to a level of and in order to calculate the volume of excavation required the average level of the site must be determined. This can be easily done by weighting the levels as follows starting at the top left-hand corner of the site (35.90) and working from left to right. 50

51 EXAMPLE 1 Substructure Site levels Level Total Level Total Number of Points = 40 Average site level = / 40 = Reduced level = Average Excavation depth = =

52 Example 5.6m ع ١ ك ٢ ع ١ 15cm 7ɸ10/m 4.8m ك ١ 7ɸ12/m ك ١ A A ع ١ ك ٢ ع ١ 52

53 ك Example سفلي عدل و الكانات 6ɸ8/m الغطاء الخرساني 4ɸ16+ علوي 2ɸ16 ٢.٥ سم 0.3m x 0.5m قطاع الكمرات ك ١ ٢ 0.3m x 0.3m 3.0m قطاع العمود ع ١ ارتفاع العمود ع ١ قطاع السمالت 0.3m x 0.5m منسوب األرض الطبيعية 1.2 m القواعد المسلحة 1m x 1m x 0.4m 53 Section A-A القواعد العادية 1.6m x 1.6m x 0.3m

54 Example It is required to estimate the quantities of the following jobs: (كميات الحفر) Excavation (خرسانة القواعد العادية) Plain Concrete Footings (خرسانة القواعد المسلحة) Reinforced Concrete Footings (خرسانة السمالت) Ground Beams concrete (كميات الردم) Filling (خرسانة األعمدة) Columns concrete (خرسانة البالطة وكمرات السقف) Slab and beams Concrete حديد تسليح البالطة وكمرات ( Reinforcement Slab and beams (السقف 54

55 Excavation 1.6 m 4.8 m 1.2 m 1.6 m.15 m 5.6 m.15 m 1.6 m m 3.7 m

56 Excavation No. Item Unit Number Length Width Depth Total 1 Excavation m

57 PC Concrete Footings No. Item Unit Number Length Width Depth Total 2 PC Concrete m m 0.3 m 1.6 m 57

58 RC Concrete Footings No. Item Unit Number Length Width Depth Total 3 RC Concrete m m 0.4 m 1.0 m 58

59 Ground Beams No. Item Unit Number Length Width Depth Total 4 Ground Beams m m السمالت 4.8 m 4.5 m 0.3 m 0.15 m 5.6 m m 0.3 m 59

60 Filling No. Item Unit Number Length Width Depth Subtotal Total 1 Excavation m PC Concrete m RC Concrete m Ground Beams m Total Concrete m Filling m

61 Columns No. Item Unit Number Length Width Depth Total 6 Columns Concrete m m 3.0 m االعمدة 3.0 m 61

62 Slab & Beams No. Item Unit Number Length Width Depth Total 7 Slab & Beams m m 5.0 m 0.5 m 4.2 m 15 cm 4.8 m 4.5 m 0.3 m m 5.6 m m

63 Take-off Summary Table No. Item Unit Number Length Width Depth Total 1 Excavation m PC Concrete m RC Concrete m Ground Beams m Filling m Columns Concrete m Slab & Beams m Total Concrete

64 ك Reinforcement Takeoff 30cm 0.3m x 0.5m 4ɸ16+ علوي 2ɸ16 قطاع الكمرات ك ١ ٢ سفلي عدل و الكانات 6ɸ8/m الغطاء الخرساني ٢.٥ سم 2.5cm 2.5cm 25cm 7ɸ10/m 7ɸ12/m 50cm 45cm 64

65 Reinforcement Takeoff Unit No. of Length Total Unit Total (kg) bars length Weight Weight 16 upper (beams) lower (beams) long (Slab) short (Slab) stirrup (beams) Total Steel

66 66 Questions?

Quantity Take-off. Quantity Take-off

Quantity Take-off. Quantity Take-off Quantity Take-off Required Information for Cost Estimate Detailed drawings Specifications Available site data Available resource data (labor, material & equipment) Government regulations Applicable owner

More information

CHAPTER 2 QUANTITY TAKE-OFF

CHAPTER 2 QUANTITY TAKE-OFF CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate

More information

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013 How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table

More information

The Task. for. PERI Construction-Exercise 2003

The Task. for. PERI Construction-Exercise 2003 The Task for PERI Construction-Exercise 2003 Entitled to participate all educational institutions for civil engineering and construction management. The work must be based on the outlined project and can

More information

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE...

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE... Starting Guide TABLE OF CONTENTS INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE... 7 ADVANCE CONCRETE USER INTERFACE... 7 Other important

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans Brochure More information from http://www.researchandmarkets.com/reports/2214808/ Repair and Remodeling Estimating Methods. 4th Edition. RSMeans Description: This estimating guide for repair and remodeling

More information

PROJECT COST ESTIMATES & FEASIBILITIES

PROJECT COST ESTIMATES & FEASIBILITIES PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed

More information

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02. L_All_Vocatinal_Ed_Construction Sector: Construction Sr. No Specialisation Page No 1 Construction and Building Technology 02 1 P a g e 2 P a g e VOCATIONAL EDUCATIONAL QUALIFICATION FRAMEWORK (Sector -

More information

HOUSE BUILDING DIGEST

HOUSE BUILDING DIGEST HOUSE BUILDING DIGEST (Construction Specifications-Foundations) Creating Enabling Environment for Affordable Housing for All This is an attempt by BMTPC to provide useful but often ignored information

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

Technical Notes 3B - Brick Masonry Section Properties May 1993

Technical Notes 3B - Brick Masonry Section Properties May 1993 Technical Notes 3B - Brick Masonry Section Properties May 1993 Abstract: This Technical Notes is a design aid for the Building Code Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402-92) and Specifications

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

Requirements for Building Application Submission

Requirements for Building Application Submission THE DEVELOPMENT CONTROL AND PLANNING BOARD P O Box 597 Phone: 869 465-2277 Bladen Commercial Development Fax: 869 465-5842 Basseterre, St. Kitts Email: phyplskb@caribsurf.com To: Architects, Designers

More information

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME National Home Builders Registration Council RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME (14 October 2002) 1 Requirements of the Housing Consumers

More information

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE Sl.No. PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE Description of item Qty Unit Rate Amount 1 Demolishing tile work/cement concrete/( carefully taking out the closet and other

More information

Technical Assignment 2 TABLE OF CONTENTS

Technical Assignment 2 TABLE OF CONTENTS 2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer

More information

Chapter 16. Mensuration of Cylinder

Chapter 16. Mensuration of Cylinder 335 Chapter 16 16.1 Cylinder: A solid surface generated by a line moving parallel to a fixed line, while its end describes a closed figure in a plane is called a cylinder. A cylinder is the limiting case

More information

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab, DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

VOLUME AND SURFACE AREAS OF SOLIDS

VOLUME AND SURFACE AREAS OF SOLIDS VOLUME AND SURFACE AREAS OF SOLIDS Q.1. Find the total surface area and volume of a rectangular solid (cuboid) measuring 1 m by 50 cm by 0.5 m. 50 1 Ans. Length of cuboid l = 1 m, Breadth of cuboid, b

More information

The unit costs are based on the trend line of the 3 low bids for the average quantity.

The unit costs are based on the trend line of the 3 low bids for the average quantity. Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally

More information

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE Autodesk Revit LEARNING PATH FUNDAMENTALS Duration: 3 days Cost: R5 500 (excl VAT) Revit MEP Duration: 3 days Cost: R5 500 (excl VAT) Revit Structure Duration: 3 days Cost: R5 500 (excl VAT) REVIT ADVANCED

More information

Project : CONSTRUCTION OF BUILDING(including electrical and plumbing works) FOR NATIONAL CENTRE FOR SUSTAINABLE COASTAL MANAGEMENT,CHENNAI

Project : CONSTRUCTION OF BUILDING(including electrical and plumbing works) FOR NATIONAL CENTRE FOR SUSTAINABLE COASTAL MANAGEMENT,CHENNAI Project : CONSTRUCTION OF BUILDING(including electrical and plumbing works) FOR NATIONAL CENTRE FOR SUSTAINABLE COASTAL MANAGEMENT,CHENNAI TENDER CLARIFICATIONS- no 3 dated 3rd Oct 13 issued in response

More information

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE 86 :: Certificate in Construction Supervision (CIVIL) 12 ROOF 12.1 INTRODUCTION The structure provided to cover the house surface (floor) is known as roof. For different situation and requirement, it is

More information

LAYING BLOCK AND BRICK

LAYING BLOCK AND BRICK LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct

More information

Aluminium systems profile selection

Aluminium systems profile selection Aluminium systems profile selection The purpose of this document is to summarise the way that aluminium profile selection should be made, based on the strength requirements for each application. Curtain

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION

More information

SOMETIMES the cost of installing a landscape plan

SOMETIMES the cost of installing a landscape plan Pricing the Landscape Plan SOMETIMES the cost of installing a landscape plan can be quite shocking for those not familiar with all the elements of a landscape. When one breaks down the various expenses

More information

Superform Products Ltd.

Superform Products Ltd. TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage 3.3. Evaluation of Building Foundation Damage Basic Terminology: Damage: Destruction, deformation, inclination and settlement of a building foundation caused by an earthquake. Damage grade: Degree of danger

More information

Building Cost Estimates-Beef Related Facilities

Building Cost Estimates-Beef Related Facilities Building Cost Estimates-Beef Related Facilities University of Wisconsin-Extension Beef Team The cost estimates here are ballpark estimates for initial budgeting and decision purposes. It can help in the

More information

Area is a measure of how much space is occupied by a figure. 1cm 1cm

Area is a measure of how much space is occupied by a figure. 1cm 1cm Area Area is a measure of how much space is occupied by a figure. Area is measured in square units. For example, one square centimeter (cm ) is 1cm wide and 1cm tall. 1cm 1cm A figure s area is the number

More information

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY HOWARD COUNTY MARYLAND ARCHITECTURAL DESIGN ACADEMY Architectural Design 1 Introduction / Overview of Course This course will introduce the basic principles

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

1. Concrete: T W L / 27 = Concrete C.Y. Multiply Feet Thickness x Feet Width x Feet Length / 27 = Cubic Yards.

1. Concrete: T W L / 27 = Concrete C.Y. Multiply Feet Thickness x Feet Width x Feet Length / 27 = Cubic Yards. Formulas: Formula Letters: H= Height BCY = Bank Cubic Yards L= Length CCY = Compact Cubic Yards P= Perimeter LCY = Loose Cubic Yards LF = Linear Feet or Lineal Feet BF = Board Foot or Feet SF = Square

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

King Post Wall Information

King Post Wall Information King Post Wall Information DAWSON-WAM specialise in the installation of piled retaining wall systems including steel sheet piling, concrete piled walls and king post walls. This document is our guide to

More information

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number

More information

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL Prepared for: Public Works and Government Services Canada Parliamentary Precinct Branch Prepared by: Halsall Associates 210 Gladstone

More information

Re: Damages to Alaska Building from Legislative Information Office Construction

Re: Damages to Alaska Building from Legislative Information Office Construction 510 L Street Suite 200 Anchorage, AK 99501-1949 (907) 274-22362236 Phone (907) 274-25202520 Fax www.bbfm.com July 22, 2015 Jim Gottstein Alaska Building 406 G Street, Suite 206 Anchorage, AK 99501 Re:

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

Construction Technologies Career Field Pathways and Course Structure

Construction Technologies Career Field Pathways and Course Structure Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry

More information

Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities

Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities At Macau International Airport (RFQ-198) Section 6 Bill of Quantities Bill Nr. 1 Preliminaries Bill Nr. 1 PRELIMINARIES NOTES : (1) The work shall be done during day time and night time according to CAM/ADA

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY GENERAL SPECIFICATIONS These specifications are intended to cover the construction of the

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

SIMULATION PRE-INSTALLATION GUIDELINES CONTRACTOR REQUIREMENTS FOR ROOM PREPARATION

SIMULATION PRE-INSTALLATION GUIDELINES CONTRACTOR REQUIREMENTS FOR ROOM PREPARATION SIMULATION PRE-INSTALLATION GUIDELINES CONTRACTOR REQUIREMENTS FOR ROOM PREPARATION version 1.0_042011 www.foresightsports.com TABLE OF CONTENTS INTRODUCTION 1 COMPONENTS-AT-A-GLANCE 2 SPACE DIMENSIONS

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

Estimating with Microsoft Excel

Estimating with Microsoft Excel Estimating with Microsoft Excel Jay Christofferson Brigham Young University Introduction Almost every construction company has its own computer. It has become a powerful tool for those who use it. The

More information

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within

More information

ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT

ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT GOVERNORATE : DISTRICT : LOCATION : DOHUK SUMEL SUMEL GO code : IRAK GEN ASSENG0 TITLE : Sharia / PHCC / Rehabilitation SO n : SO 03 WPA n : KIR16 0015 Job

More information

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057 Lecturer: Jim Cahill 29 th November 2011 TABLE OF CONTENTS SUMMARY 1 MAIN BODY SECTION

More information

How To Build A Luxury Apartment Complex In London

How To Build A Luxury Apartment Complex In London Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking

More information

WORK SCOPE. Domains in which we work:

WORK SCOPE. Domains in which we work: WORK SCOPE Engineering consulting, technical office, assistance and supervision in industrial works. We specialize in structures, civil works and industrial equipment. Domains in which we work: Industrial

More information

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER NOTICE TO PROPERTY OWNER Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. If your home or business is below

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are: When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory

More information

SUCF PROJECT COST REPORTING GUIDE

SUCF PROJECT COST REPORTING GUIDE SUCF PROJECT COST REPORTING GUIDE State University Construction Fund 353 Broadway / ALBANY, NY 12246 SUCF 900 / 11 Table of Contents Page A. Preface 1 B. Area Takeoff Methodology 1. General 2 2. Net Assignable

More information

Olilo's AEC Design Services. SrinSoft Inc, Partners of

Olilo's AEC Design Services. SrinSoft Inc, Partners of Olilo's AEC Design Services SrinSoft Inc, Partners of Olilo provides design services that include design and analysis, cost estimation, 3D modeling, 2D drafting, conversion from 2D to 2D, quantity take-off,

More information

APPLICANT / CONTACT:_

APPLICANT / CONTACT:_ New Single Family House Permit Application Office Use Only SECTION 1 PERMIT INFORMATION Project Address: (Provide at least one of the following) Please note: it can not be an intersection PROJECT ADDRESS

More information

Uncovered Decks & Porches

Uncovered Decks & Porches Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed

More information

If stepping is required, step at 180mm as seen in this picture.

If stepping is required, step at 180mm as seen in this picture. Cast Foundations to standard building regulations requirements. Foundations must be cast completely level, 600mm wide by 230mm deep for single storey, double storey is not allowed by NHBRC. If stepping

More information

Hanson Building Products. precast basement solutions

Hanson Building Products. precast basement solutions Hanson Building Products precast basement solutions Hanson Building Products Basement Systems Add an extra dimension and combine the inherent flexible, structural and waterproof properties of concrete

More information

BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP"

BILL OF QUANTITY FOR THE WORK OF REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP" Sl. 1 DISMANTLING WORK 1.1 Stripping off worn out plaster (outside and inside) and raking out joints

More information

Section 600 Incidental Construction

Section 600 Incidental Construction Table of Contents 1. Pipe Culverts... 600-1 A. Endwalls, Inlets, Manholes, and Spring Boxes... 600-5 2. Grade Adjustment of Existing Miscellaneous Structures... 600-8 3. Rebuilt Miscellaneous Structures...

More information

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. CI/SfB Tn6 L6813 September 2013 RIW CAVITY DRAIN R20 R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. Other systems are available for specific uses,

More information

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS Module 5 (Lectures 17 to 19) MAT FOUNDATIONS Topics 17.1 INTRODUCTION Rectangular Combined Footing: Trapezoidal Combined Footings: Cantilever Footing: Mat foundation: 17.2 COMMON TYPES OF MAT FOUNDATIONS

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

D Sample Notices to Property Owners, Sample Affidavits, and Other Material D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully

More information

Detailing of Reinforcment in Concrete Structures

Detailing of Reinforcment in Concrete Structures Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

PAVER JOB INFORMATION SHEET

PAVER JOB INFORMATION SHEET PAVER JOB INFORMATION SHEET JOB SITE ADDRESS: Phone # Scheduled Date Directions JOB # OWNERS NAME (S): Phone # (h) (w) GENERAL CONTRACTOR: Contact Phone ARCHITECT: Contact Phone PLANS: Specs Date Pages

More information

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia DESIGN OF SLABS Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia Introduction Types of Slab Slabs are plate elements

More information

FDOT Specifications List

FDOT Specifications List FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...

More information

CONSTRUCTION SUMMARY OF THE PEREIRA HOUSE AT MADOL, VERNA GOA.

CONSTRUCTION SUMMARY OF THE PEREIRA HOUSE AT MADOL, VERNA GOA. CONSTRUCTION SUMMARY OF THE PEREIRA HOUSE AT MADOL, VERNA GOA. On our visit to the house of Conceicao Pereira s house we decided to make many changes that were needed to improve the living conditions of

More information

QS 004 DEPARTMENT OF PUBLIC WORKS REPUBLIC OF SOUTH AFRICA BUILDING COST DATABASE

QS 004 DEPARTMENT OF PUBLIC WORKS REPUBLIC OF SOUTH AFRICA BUILDING COST DATABASE DEPATMENT OF PUBLIC WOKS EPUBLIC OF SOUTH AFICA BUILDING COST DATABASE AUGUST 2012 DEPATMENT OF PUBLIC WOKS EPUBLIC OF SOUTH AFICA BUILDING COST DATABASE POJECT DATA SHEET NOTE Bills of Quantities Stage

More information

Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits

Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits Attachment G-1: Pit Latrine Diagram Fig E.1a: Pit Latrine Fig E.1b: Plan View of Twin Pits Fig E.1c: Section of a water-sealed pan Fig E.1d: 3D view of Overflow Pipe Fig E.1e: 2D view of Overflow Pipe

More information

Simplifying design and construction. Alan Tovey, Director The Basement Information Centre

Simplifying design and construction. Alan Tovey, Director The Basement Information Centre Simplifying design and construction Alan Tovey, Director The Basement Information Centre Simplifying design and construction Grades of construction Construction options Design and waterproofing issues

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides

More information

Gas Meter Clearances and Service Installation Requirements

Gas Meter Clearances and Service Installation Requirements March 2015 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE s Customer Construction Services 1-888-321-7779 or visit PSE.com/CustomerConstruction

More information

Labor Default Settings

Labor Default Settings Labor Default Settings Labor Cost Control Estimate Concrete allows four ways to control labor costs used in the quote. Labor to Material, Labor cost per Cubic Yard and Hours per Job and Piece Work or flat

More information

1. A plane passes through the apex (top point) of a cone and then through its base. What geometric figure will be formed from this intersection?

1. A plane passes through the apex (top point) of a cone and then through its base. What geometric figure will be formed from this intersection? Student Name: Teacher: Date: District: Description: Miami-Dade County Public Schools Geometry Topic 7: 3-Dimensional Shapes 1. A plane passes through the apex (top point) of a cone and then through its

More information

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings CPE Candidate No. 0714108 December 2014 1 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings Table

More information

2. What building projects are exempted? (permit not required)

2. What building projects are exempted? (permit not required) BUILDING AND SAFETY DEPARTMENT 1. What building projects require a permit? Following is a list of projects that require building permits based on Appendix chapter 1 of the California Building Code and

More information

NAHB 1-00-0000 PRODUCT DEFINITION

NAHB 1-00-0000 PRODUCT DEFINITION NAHB Standard Homebuilder Cost Codes Cost Code Description 1-00-0000 PRODUCT DEFINITION 1-01-0000 PREAQUISITION COSTS 1-01-0110 Feasibility Study 1-01-0120 Environmental Impact Study 1-01-0130 Option Fees

More information

Special Use Commercial Properties

Special Use Commercial Properties Contents Overview of Special Use Commercial Properties...3 Understanding Fast Food Restaurants...3 Understanding Gasoline Service Stations...4 Understanding Self-Service Cashier Booths...5 Understanding

More information

Built to Last. Built for Beauty. Good. Solid. Logix. TM

Built to Last. Built for Beauty. Good. Solid. Logix. TM Built to Last. Built for Beauty. Good. Solid. Logix. TM Quality, Value and Service Introducing LOGIX Insulated Concrete Forms. Based on the simple concept of interlocking blocks, LOGIX ICF gives you a

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E)

Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E) Revision: issue 1 Date: 11 June 2014 Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E) 24 th May 2014 Structural Inspection Report Observations

More information

While RS Means is a useful estimating tool, it must be used as intended, coupled with regional knowledge.

While RS Means is a useful estimating tool, it must be used as intended, coupled with regional knowledge. Judicial Branch Capital Construction Program White Paper Courthouse Construction Costs The purpose of this White Paper is to summarize the independent reviews of seven different estimating firms responding