Consumer guidelines for availing Grid connectivity of Solar Rooftop PV systems in BESCOM
|
|
|
- Erik Kennedy
- 9 years ago
- Views:
Transcription
1 Format-16 BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED (Wholly owned Government of Karnataka Undertaking) Consumer guidelines for availing Grid connectivity of Solar Rooftop PV systems in BESCOM (On net-metering basis) Page 1 of 18
2 Introduction Solar energy is a clean, pollution free and renewable source of energy. Karnataka being located between 11 40' and 18 27' North latitude and the geographic position favours the harvesting and development of solar energy. Karnataka state is blessed with about 300 sunny days with good solar radiation of 5.4 to 6.2KWh/square meter/day. On , Karnataka Electricity Regulatory Commission has fixed a tariff of Rs.9.56 per unit (without subsidy) & Rs.7.20/unit (with subsidy) to the Rooftop and Small Solar P.V. plants for the energy generated exceeding the energy consumed during a billing period. The above approved tariff The above approved tariff is applicable to solar power generators entering into power purchase agreements (PPA) on or after and up to other than those where the tariff is discovered through bidding process. The Government of Karnataka has announced the Solar policy on , for Solar P.V. and Solar thermal Power plants including grid connected solar rooftop P.V. systems (under net-metering basis).it is proposed to achieve a minimum of 400 MWs of grid connected Roof Top Solar P.V. Generation projects in the Karnataka State by On , Hon ble Energy minister Sri. D K Shivakumar has launched Solar RTPV programme at corporate office, Bangalore and extended this facility to all the ESCOMS for entire Karnataka State. Grid connected Rooftop Solar Power Plants Fig: A Schematic sketch of a Typical Grid connected Solar Roof Top Photo Voltaic Power Plant. Page 2 of 18
3 Solar PV Cells converts sunlight to generate electricity through a photovoltaic process. In grid connected rooftop or small SPV system, the DC power generated from SPV panel is converted to AC power using power conditioning unit and is fed to the grid either of 11 kv lines or of 415/240 Volt three/ single phase lines. They generate power during the day time which is utilized fully by powering captive loads and feed excess power to the grid as long as grid is available. In case, where solar power is not sufficient due to cloud cover etc., the captive loads are served by drawing power from the grid. The grid-interactive rooftop system can work on net metering basis wherein the utility pays to the power plant on net meter reading basis only. Alternatively two meters can also be installed to major the export and import of power separately. Many such power plants can be installed at the roofs of residential and commercial complex, housing societies, community centers, government organizations, private institutions etc. Ideally, grid interactive systems do not require battery back-up as the BESCOM grid acts as the back-up for feeding excess solar power and vice-versa. However, to enhance the performance reliability of the overall systems, a minimum battery backup of one hour of load capacity is recommended. In grid interactive systems, it has, however to be ensured that in case the grid fails, the solar power has to be fully utilized or stopped immediately feeding to the grid (if any in excess) so as to safe-guard any grid person/technician from getting shock (electrocuted) while working on the grid for maintenance etc. This feature is termed as Islanding Protection. This scheme is only for the Solar Rooftop facility owned, operated and maintained by the consumer(s). Objective of the Programme: To promote the grid connected SPV rooftop and small SPV power generating plants among the residential, community, institutional, industrial and commercial establishments. To mitigate the dependence on fossil fuel based electricity generation and encourage environment friendly Solar electricity generation. To create enabling environment for investment in solar energy sector by private sector, state government and the individuals. To create enabling environment for supply of solar power from rooftops to the grid. To encourage innovation in addressing market needs and promoting sustainable business models and ensures employment opportunities. To provide support to channel partners and potential beneficiaries, within the framework of boundary conditions and in a flexible demand driven mode. To create a paradigm shift needed for commoditization of grid connected SPV rooftop applications. To support consultancy services, seminars, symposia, capacity building, awareness campaigns, human resource development, etc. Page 3 of 18
4 Overview of Solar RTPV Power plants: A solar RTPV Power plant consists of: Solar Panels/Solar PV Modules: These are mounted on the roof of buildings and convert sunlight into Direct Current. Mounting Structures: These Galvanised Steel structures secure the solar panels/pv modules to the roof of your building. Most mounting structures require your roof to be penetrated. If you are worried about water seepage, non-penetrating options are also available Mounting structures should be strong enough to hold your solar panels even at high wind speeds. Inverter :It is an intelligent equipment that converts the generated Direct Current into the Alternating Current which is required for all the electrical appliances through a charge controller. It also regulates battery charging (if required). Balance of Systems (BoS) : All the other components of the solar plant, such as cables, junction boxes, fuses, etc. The size of solar plant you require depends on your requirement of electrical loads,number of kwh (units) you consume and how much Money would you like to earn etc.. The size of solar plant you can install is limited by the extent of shade-free rooftop space available. The expected lifetime of a solar PV plant is 25 years. Incentives Accelerated Depreciation (AD) Accelerated depreciation of 80% is available under the Income Tax act for the Commercial and Industrial rooftop solar PV systems. This can provide significant savings to a SRTPV power plant generator who is a taxable assesse and has sufficient profits against which the depreciation can be charged. Section 32 Of Indian Income Tax Act. Provides Accelerated Depreciation Of 80% of the Invested Capital in To Solar Pv Projects to Professional Companies with Tax Liability. Investors Can Set off Their Tax Liability on the Taxable Income to the tune of 80% in the 1 st Year and subsequently 20% in the 2nd Year. Section 80-IA (sub section 4) of income tax Act, 1961 allows 100% tax waiver on the income generated for any single 10 year period during first 15 years of operational life of a power generation project. The Reserve Bank of India has taken a decision to grant Special Status to the Renewable energy sector, among others, under priority sector for Lending. Page 4 of 18
5 Solar irradiation data of Bangalore City is given below for reference Under Standard test Conditions of 25 degree C of ambient temperature & 1000 Watts/ Square Mts. of solar insolation, the Solar PV Generation is Maximum. For Every 10 degree C rise in ambient temperature, the Solar Generation reduces by about 6%. Bangalore City is blessed with an ideal temperature that ranges between 20 to 30 degree C for most of the time and hence we can expect Maximum Solar Generation in Bangalore City. In Bangalore City, on an annual average, the Solar PV generation would be around 5.26 KWhrs/Square Meter. GENERAL INSTRUCTIONS TO THE APPLICANTS FOR AVAILING SRTPV CONNECTION 1. This scheme is only for the Solar Rooftop facility owned, operated and maintained by the consumer(s). 2. The interested applicants of domestic, commercial, educational institutions, industrial establishments etc., who are consumers of BESCOM can download the Application forms from BESCOM website (Format-1). 3. On-line application: Application can be registered through online, however, after submitting the application in on-line, the applicant shall take a printout of on-line application and approach the AEE of concerned O&M sub-division and pay the prescribed the application fee. Page 5 of 18
6 4. The fee payable are as follows: Sl. No. Capacity of proposed SRTPV system Registration fee Facilitation fee 1. Upto and inclusive of 5.0 kwp Rs.500/- Rs.1000/ Above 5.0 kwp and up to 50 kwp (67 Hp/59 kva) Above 50 kwp (67 Hp/59 kva) and upto 1MWp* Rs.1000/- Rs.2000/- Rs.2000/- Rs.5000/- 1. Note:* For the applicants who obtain subsidy from MNRE, the capacity range is from 1kWp to 500kWp (as per MNRE guidelines. 5. The AEE, C,O&M sub-division is the signing authority for PPA up to sanctioning load upto 50kWp and EE, C, O&M division is the signing authority for PPA of sanctioning load of 50kWp and above. 6. The Content of Power Purchase Agreements, for more than 500kWp, individual approvals have to be obtained from KERC. 7. For applications of loads requesting above 500 kwp to 1 MWp, the draft PPA s from O&M division office will be forwarded to the office to the Office of GM(DSM), Corporate Office, Bescom. GM (DSM), in turn will arrange to forward these PPA s to the KERC for approval on case by case. In this case, the office of GM (DSM) will only act like a facilitator for obtaining approval to the PPAs. 8. The applicant is required to select a reputed system installer to install the SRTPV System, who have experience in design, supply and installation of SRTPV system. 9. After installation of SRTPV system, AEE (Ele,), C, O&M Sub-division, BESCOM is the inspecting authority for SRTPV systems up to and including 10kWp. For above 10kWp SRTPV systems, Chief Electrical Inspectorate, Government of Karnataka is the inspecting authority to meet safety standards. 10. BESCOM shall not be held responsible for any legal disputes between the applicant and SRTPV system installer arising out of the contract. 11. The applicant shall be very careful in selecting and finalising a contract with the System Installer as there is every chance of misleading by some of the System Installers. Hence it is advisable to consider following options before finalising a contract. The applicant may enter in to an agreement with the system Installer: For designing, testing, Supplying, Installing, Commissioning and to maintain for a period of Five years after following all the Safety and Quality of the equipment supplied as per relevant standards. The applicant should see that the System Installer shall guarantee a minimum solar energy generation for a period of Five years. The applicant is advisable to select high efficiency P.V. Modules as their rate of return is Page 6 of 18
7 directly proportional to the no. of units generated/day. Please note this guarantee is not applicable for day to day cleaning of Solar P.V. Modules. It is advisable for the applicant to get a comprehensive Insurance policy against theft/damage/fire/cyclone/riot incidences and also a third party liability insurance against risk of Mechanical/electrical accidents that may happen during installation of solar roof top panels or during maintenance afterwards. The applicant should ensure a clear & complete scope from System Installer in assisting for preparation of drawings, procuring and testing Bi direction Meters, to get approvals from BESCOM/C.E.I. and to have comprehensive maintenance contract for periodical maintenance of P.V. modules, Inverter and other connections or else S.I. will refuse to render appropriate service at a later date. For more information prospective consumers are advised to visit Web sites on Solar energy such as solar mango, bridge to India etc. 12. List of On-grid MNRE approved Channel Partners is available in BESCOM/MNRE website for guidance and it is not mandatory to select one of the MNRE channel partners only. 13. The list of approved vendors for Bi directional meters is available in BESCOM website. 14. Inverters of BESCOM approved manufacturers shall be used. BESCOM is empanelling inverter manufacturers on continuous basis. On , BESCOM has called Expression of Interest (EOI) for Empanelment of Grid-tied Inverter manufacturers for implementation of Solar Roof-top (SRTPV) programme in BESCOM area for a period of one year, which may be extended upto 2 years. The Registration of Empanelment of Grid tied Inverter manufacturers commenced from The list of approved vendors for inverters which meet all required IEC standards are available in BESCOM website. Test reports for the tests conducted as per IS/IEC standards and Technical specifications of SPV system shall be submitted along with Work Completion Certificate as per Format-7 before Commissioning. 15. The Technical, safety, grid connectivity standards to be followed as per the technical standards enclosed with Format 5 and 6 are as below: Page 7 of 18
8 Technical Standards to followed for SRTPV systems BOS Item / System Solar PV modules Grid tied inverters Applicable BIS /Equivalent IEC Standards / Applicable MNRE Specifications Standard Description Standard Number Modules i ii iii Crystalline Silicon Terrestrial PV modules Thin film Terrestrial PV modules Solar PV module safety qualification requirements PV modules to be used in a highly corrosive atmosphere (Coastal area etc,) must qualify Salt Mist IEC 61215/IS14286 IEC IEC (P1 P2) IEC 61701/ IS corrosion Testing Each PV module must use RFID tag which must contain the following information as per MNRE requirements: i. Name of the manufacturer of PV Module ii. Name of the manufacturer of Solar Cells iii. Date of year of manufacture (separately for solar cells and module) iv. Peak wattage, Im, Vm and FF for the module v. Unique Sl. No. and model no. of the module vi. Date and year of obtaining IEC PV module qualification certificate vii. Name of the test lab issuing IEC certificate WARRANTY: PV modules used in solar power system must be warranted for their output peak watt capacity, which should not be less than 90% at the end of 10years and 80% at the end of 25years i* Environmental Testing IEC (1, 2,14,30) / Equivalent BIS Std ii* Efficiency Measurements IEC 61683:1999 Product safety standard IEC (2010) iii IEC (2011) iv Grid Connectivity utility interface IEC 61727:2004 (as per IEEE 519 specifications) Test procedure for islanding IEC or v prevention measures for utility/interconnected PV inverters IEEE 1547 and IEEE * Note: for testing sl. no. i & ii beyond 10KVA self-certification by manufacturers are acceptable in case if the Charge controller is not built-in the inverter, IEC test is required separately vi for Charge controller Electromagnetic compatibility & Electro Magnetic Interference IEC :2007 IEC :2007 IEC :2006 IEC :2006 Page 8 of 18
9 Cables vii Ingress protection i General Test and Measuring Method PVC insulated cables for working voltage upto and including 1100 V and UV resistant for outdoor installation for A.C. cables. (It is suggested to use D.C. rated, UV resistant Photovoltaic cable having plug and play capability cables) IP 65 (for outdoor)/ IP 21 (for indoor) As per IEC IEC / IS 694 IEC / IS 1554 (part I & II) Earthing i Grounding IS 3043: 1986 Switches/ Circuit Breakers/ Connectors Junction Boxes/ Enclosures for Charge Controllers/ Luminaries i i General Requirements Connectors - safety A.C. /D.C. General Requirements IEC Part I,II, III / IS Part I,II, III / EN IP 65 (for outdoor)/ IP 21 (for indoor) As per IEC After installation of SRTPV system, AEE C, O&M Sub-division, BESCOM is the inspection authority for SRTPV systems up to 10kWp and for above 10kWp for applied load, Chief Electrical Inspectorate, Government of Karnataka is the inspecting authority to meet safety standards. 17. The rooftop/terrace must have easy access. 18. The applicant should be the owner of the property or authorized person and Consumer of BESCOM. If the property is in the name of the Company, Trust, Co-operatives / partnership firms, then authorization shall be assigned to a person for correspondence, paperwork, execution of various agreements, etc. Such person must be authorized by the management of the organization. In case of partnership firms, the authorized signatory must be one of the partners, to whom written consent has been given by the other partners. 19. The authorization Format - 1A/1B can be downloaded from the website. 20. If consumer is not willing to avail subsidy, shall furnish self-certification for not availing Capital subsidy. 21. Application registered is not transferable. 22. Net metered energy means: The difference of meter readings of energy injected by the SRTPV system into the grid (export) and the energy drawn from the grid for use by the Prosumer (import) is recorded in the bi-directional meter. 23. Metering: The Applicant has to procure Callibrated bi-directional meter from any of the approved vendors of BESCOM as per CEA guidelines. The vendor list of bi- Page 9 of 18
10 directional meters can be downloaded from BESCOM website. Cost of various capacities of Net Meters of SECURE make and its prices are as below: Sl. No. Capacity Class of Accuracy Description of Type of Bi-directional Meter* Rate in Rs. (inclusive of 14.5% VAT) 1 Up to 5 kws 1.0 S-phase, 2 Wire 2, Above 5 kws to 17.5 kws kws to 50 kws 4 50 kws and above phase, 4 Wire, Whole current phase, 4 Wire, C.T. Operated 0.2s 3-phase, 4 Wire, C.T. Operated 6, , , Note: *All the Meters shall have 60 months of warranty from the date of supply. Cost of meter testing fee to be paid at MT lab is as below (as per SR ): Sl. No. Type of meter Cost of testing fee per meter 1 Bi-directional Single Phase 2 Rs. 200/- wire meter 2 Bi-directional 3 Phase ETV Rs. 1800/- meter 3 ABT feature 3 phase meter Rs. 2400/- At the time of synchronization, the existing metering wiring shall be changed to solar power generation side in presence of AEE/EE, O&M and MT, BESCOM to measure solar generation. Solar meter reading will be taken for solar obligation purpose only and not for billing. The Applicant shall install the meter to read Solar energy of SRTPV system and a bi-directional meter in separate meter boxes along with Bus bar chamber in the same proximity or at a suitable place in the premises accessible for the purpose of reading. The Applicant shall provide check meters when the SRTPV system is more than 20kWp. Procuring CT s separately for the Check Meter are not required as the wiring of main meter shall be used for check meter also. In case of H.T. Installations, Bi-directional meter of 0.2s class of accuracy shall be purchased from BESCOM approved vendors (as per BESCOM approved Technical specifications) and to be fixed at net-metering point in consultation with the EE, MT division. Name and address of the BESCOM approved vendors (Format-15) is available in the BESCOM website Page 10 of 18
11 If the grid connectivity is on L.T. side, the applicant shall arrange to connect Bescom approved L.T. Meter with C.T. s to read solar generation, as approved by E.E. M.T. Division, BESCOM. If the existing meter cubicle is having 2 element system of 2 CTs, 2 PTs and metering with three wire system, it shall be replaced by 3 element system of 3 CTs, 3 PTs and metering with four wire system. 24. In case of L.T. Power Installations, if the proposed capacity of the SRTPV system is higher than 50kWp, then, as per KERC tariff Order, the Applicant/Developer shall provide evacuation facility upto the interconnection point by extending 11KV line and providing the Distribution transformer & protection equipment. The applicant shall use equipment such as Transformer, Conductor etc., from BESCOM approved vendors only. 25. As per CEA guide lines, the applicant/ firm is responsible for planning, design, construction, reliability, protection and safe operation of all the equipment s subject to the regulations for construction, operation maintenance, connectivity and other statutory provisions. 26. The list of documents to be furnished along with the application are: a. Copy of the latest Electricity bill. b. Authorization letter Format-1A in case of Company/Trust/Cooperatives/ Partnership and Format -1B for Partnership firms. c. Copy of the Subsidy sanction letter from MNRE. 27. The Commission decides that, the S.T.U. shall arrange necessary facilities to evacuate power from the interconnection point as below: Sl. System Capacity Voltage level No. 1 Upto inclusive of 5 kwp 240 Volts 2 Above 5 kwp to upto 50 kwp 415 Volts 3 Above 50 kwp* & upto 1MWp 415 Volts /11KV Please note *: In certain cases, the evacuation voltages can either be 415V or 11kV which will be as determined by the Executive Engineer (Ele,) of C,O&M division. In case of clarification, the Executive Engineer (Ele,) shall contact E.E, M.T. Division & GM (DSM), Corporate Office, BESCOM. 28. If the existing power supply of the consumer is of single phase and wishes to apply for three phase SRTPV system, conversion of 1ph to 3ph installation shall be sanctioned from AEE, C, O&M Sub-division before applying. 29. If the Consumer is already having a Three Phase Connection and wish to put up a Single phase Solar roof top Installation, he can do so by procuring a Three Phase Bi-directional Meter at Inter connection point and a single phase energy Meter to read Solar Generation. The single phase uni-directional Meter can be bought at Bescom approved retail Meter outlets. 30. The nodal point of contact for Solar RTPV program shall be the AEE, C, O&M Sub-division, BESCOM. Page 11 of 18
12 31. BESCOM personnel reserve the right to inspect the entire plant routinely at any time as per the distribution code approved by KERC. 32. The consumer shall pay the Electricity tax and other statutory levies, pertaining to SRTPV generation, as levied from time to time. 33. Earthing protection: A minimum of two separate dedicated and interconnected earth electrodes must be used for the earthing of the solar PV system support structure with a total earth resistance not exceeding 5 ohms. (i) Equipment earth (DC) and (ii) System earth (AC) Both equipment earth (DC) and system earth (AC) shall be checked for proper earthing. Equipment earth (DC): All the non-current carrying metal parts such as PV modules, DCDB are bonded together and connected to earth to prevent shocks to the manpower and protection of the equipment. System earth (AC): All the non-current carrying metal parts such as ACDB, Lightening Arresters are bonded together and connected to existing earth. Surge Protection: Surge protection devises (SPD s) shall be provided on the DC side and AC side of the solar system. The DC surge protection devices shall be installed in the DC distribution box adjacent to the solar grid inverter. The AC SPD s shall be installed in the AC distribution box adjacent to the solar grid inverter. The SPD s earthing terminal shall be connected to earth through the above mentioned dedicated earthing system. (The SPD s shall be of Type 2 as per IEC ) Earthing shall be done in accordance IS , provided that earthing conductors shall have a minimum size of 6.0 mm 2 copper wire or 10 mm 2 aluminium wire or 70 mm 2 hot dip galvanized iron flat. Unprotect aluminium or copper-clad aluminium conductors shall not be used for final underground connections to earth electrodes. The earth electrodes shall have a pre-cast concrete enclosure with a removal lid for inspection and maintenance. The entire earthing system shall comprise non-corrosive components. The synchronization of the SRTPV system shall be carried out by the concerned Sub-divisional/Divisional Engineer along with MT staff within 3 working days from the receipt of Work completion Report. Generally, Lightening Arresters need to be provided for the SRTPV buildings which are of more than 15 meters height only. 34. Data monitoring: Online monitoring will be compulsory for all the systems of more than 50kWp capacity. The SRTPV plant parameters such as daily Page 12 of 18
13 generated units are measured shall be transmitted to ALDC, BESCOM using SCADA system through Ethernet Connection and the system Installer should give Link/Password to the AEE OF C,O& M subdivision for monitoring. 35. Regarding any queries/ complaints/ information, the Applicant/ Consumer can contact the AEE, C, O & M Sub-division / Solar help desk at DSM section, Corporate Office, BESCOM. 36. Subsidy: The Applicant can avail MNRE subsidy for Solar rooftop PV systems. If MNRE subsidy is availed subsidy, MNRE guidelines and standards are to be followed, details may be obtained from MNRE website MNRE subsidy may be availed through MNRE approved Channel partners or through KREDL. 37. Dispute Resolution: All the disputes between the SRTPV consumer and BESCOM arising out of or in connection with the agreement shall be first tried to be settled through mutual negotiation. The parties shall resolve the dispute in good faith and in equitable manner. In case of failure to resolve the dispute, either of the parties may approach the Consumer Grievance Redressal Forum (CGRF). Details of CGRF can be obtained from the BESCOM website. 38. The technical specifications stated are subjected to change without notice. 39. Display of caution boards on the Meter Board/Cubicle of SRTPV installation and on pole as stated below: Consumer shall provide Danger Board on the Meter Enclosure. The Section officer shall arrange : To paint One Band of Red Colour of 6 around the pole (at about 8 feet height from the Ground Level), below it, One Band of Orange coloured Radium paint of 6 around the pole, duly writing R.R. No. with pre fixing the letters of SRTPV in Black coloured paint. 40. Applicability of Wheeling and Banking Charges and Cross Subsidy Charges: The KERC has decided not to levy any Wheeling and Banking Charges and Cross Subsidy Charges on the Solar generators who sell electricity on Open access within the state. Procedure for Availing SRTPV Connection 1. The Applicant shall submit the filled-in Application along with the necessary documents either Online/Offline to jurisdictional O&M, Sub-division office, BESCOM and pay required registration fee. 2. If Offline application (In-person) is received, the AEE shall assist applying it Online. Page 13 of 18
14 3. On submission of Application form to concerned AEE, Sub-divisional office, will perform general screening and register the application with acknowledgment to the Applicant. 4. After revenue verification, the Application shall be sent to concerned Section officer / Executive Engineer, C, O&M BESCOM as per delegation of powers for Technical feasibility report. 5. In case of L.T. Power Installations, if the proposed capacity of the SRTPV system is higher than 50kWp, then, as per KERC tariff Order, the Applicant/Developer shall provide evacuation facility upto the interconnection point by extending 11KV line and providing the Distribution transformer & protection equipment. The applicant shall use equipment such as Transformer, Conductor etc., from BESCOM approved vendors only 6. The Assistant Executive Engineer, C, O&M BESCOM, as per delegation of powers, shall accord Approval to all the L.T. Installations up to a capacity of 50kWp as per Format The Executive Engineer, C, O&M Division BESCOM as per delegation of powers shall accord Approval to all the H.T. Installations of 50kWp and above the capacity as per Format After completion of installation work of SRTPV system, the work completion report Format-6C is to be submitted by Applicant to AEE/EE, C,O&M, BESCOM along with the following documents: i. Facilitation fee of Rs.1000/- upto 5kWp, Rs.2000/- for above 5.0 kwp and upto 50 kwp and Rs.5000/- for above 50 kwp and upto 1MWp shall be paid and enclose the copy of receipt. ii. Copy of the Single Line Drawing of the SRTPV System indicating all the Safety aspects of Grid Connectivity. iii. Approved drawings and approval for Commissioning from Chief Electrical Inspectorate (CEI), GoK (for capacity above 10kWp). iv. Test Certificate of bi-directional meter from MT division, BESCOM. v. Test reports for the tests conducted as per IS/IEC standards and Technical specifications of SPV system shall be submitted along with Work Completion Certificate as per Format-7 before Commissioning. vi. Copy of Power Purchase Agreement on Rs.200/- Non judicial stamp paper with BESCOM. vii. Facing sheet of Bank pass book containing details of Name of the Bank, Type of account, Account No, Name of the Branch, IFSC code etc., The maximum time frame for completion of installation work in all respect by the applicant is 180 days. 9. AEE, O&M, BESCOM is the Inspecting authority of Safety procedures upto 10 kwp and for applied loads above 10 kwp, Chief Electrical Inspectorate, Department of Electrical Inspectorate, GoK is the Inspecting authority to meet safety standards. Page 14 of 18
15 10. Signing of Power Purchase Agreement: After completion of SRTPV installation work, the consumer has to enter into a Power Purchase agreement with BESCOM on Rs.200/- Non judicial stamped paper. Format of PP Agreement can be downloaded from BESCOM website The PP agreement shall be signed before Commissioning and Synchronizing. As per delegation of powers, the AEE of C, O&M sub-divisions are authorised to sign PPA upto 50kWp. As per delegation of powers, EE of C, O&M divisions are authorised to sign PPA of 50kWp and above. PP Agreements of more than 500kWp, individual approvals have to be obtained from KERC through GM (DSM), Corporate Office, BESCOM. 11. Submission of work completion report: The Applicant/System installer of SRTPV system shall submit the following documents along with work completion report as per Format 7 to the approving authority (C, O&M, and AEE/EE of BESCOM): a. Approved drawing and approval letter for commissioning the SRTPV system by CEI of DEI, GoK. b. Specification sheets of all equipments and manufacturer s test reports and test certificate of modules and inverters. c. Test certificates of bi-directional meter from MT division, BESCOM. d. Undertaking of MNRE subsidy Sanction letter or self-declaration Certificate for not availing MNRE subsidy (Format-1C). e. Details of facilitation fee paid. f. Power Purchase Agreement on Rs.200/- Non judicial stamp paper. 12. After verification of all documents and completion reports submitted by the Applicant, AEE/EE will issue sanction letter for testing and commissioning of SRTPV system. 13. The testing, commissioning and synchronization of the SRTPV system shall be carried out by the concerned Sub-divisional/Divisional Engineer along with MT staff/section Officer (To asses the SRTPV Load, the Capacity of Inverter or P.V.Module whichever is Low,shall be considered). 14. During the period of synchronization of the SRTPV system with BESCOM grid, the BESCOM personnel shall inspect, calibrate and seal the bi-directional meter. 15. The AEE/Section Officer shall record G.P.S. Co-ordinates of all the SRTPV Installations in the Work Completion report submitted by the applicant and System Installer (Format 7) which will be helpful to map all the serviced installations at a later date. Page 15 of 18
16 16. The A.E.E. of C, O&M, after commission, shall take a photograph of the Solar R.T.P.V. power plant, retain one copy along with the service docket and shall mail copy to the GM, DSM, Corporate Office, BESCOM. 17. The concerned AEE/EE C, O&M will issue for synchronization certificate to the applicant of the SRTPV system after synchronization and commissioning. 18. Billing and Payment: The consumer shall receive a monthly net import/export bill indicating either net export to the grid or net import from the grid. Import - means energy supplied by the BESCOM grid. Export - means energy delivered to the BESCOM grid. The meter reader has to capture present reading of Uni-directional meter provided at solar side. Solar side meter reading is used only for MIS report (to measure the quantum of generation) and shall not be used for billing purpose. The meter reader has to capture both import & export energy and other billing parameters recorded by the bi-directional meter. In case of net import bill, the consumer shall pay the same as per existing tariff. In case, the export energy is more than the import, AEE, C,O&M subdivision will arrange for the energy exported as per the KERC approved tariff through NEFT. The tariff for injecting surplus energy by rooftop installation will be as per the prevailing tariff determined by KERC from time to time. At present the tariff is Rs.9.56 per unit for installations without subsidy and Rs.7.20 per unit for installations with subsidy Minimum charges/electricity dues/statutory levies, if any, shall be adjusted against the energy purchase bill. The amount payable by the BESCOM to the Seller for energy injected to the BESCOM grid (excluding self-consumption) during the billing period becomes due for payment, which shall be settled within 30 days from the date of meter reading and credited to the bank account through NEFT. 19. Display of caution boards on the Meter Board/Cubicle of SRTPV installation and on pole are as specified. 20. Please Note: The terms and conditions are subjected to change without Notice. Page 16 of 18
17 Billing Installation and Commissioning Applicant & S.I. Submits C.R. Utility Review Process Application Process Flow Chart of Interconnection Process Applicant downloads the application Formats and Guidelines to Consumers from the website: Yes Applicant submits the Application form on line duly attaching copy of electricity bill, Photo and necessary Certificates Registration fee shall be paid at C, O&M Sub-division. If Offline application is received, AEE shall convert it into online format AEE will issue approval letter Format-5 for L.T.Installations & EE will issue approval letter Format- 6 for H.T. installations. After installation of SRTPV Power plant, Applicant submits pays facilitation fee, procures Bi-directional meter & gets tested at MT division and submits test reports along with bank pass book details, AEE/EE of C,O&M will sign PP Agreement with consumer &submits Work completion report and request to commission it in Format-7. Not Ok Applicant & S.I. shall undertake corrective measures and apply Utility shall provide suggestions and reasons for failure At the request of Applicant (Format-7), Commissioning & synchronizing will be conducted by AEE/EE C, O&M Div,&, AEE/EE, MT div after testing SRTPV system Not Ok Ok If the rooftop facility fails to clear the Commissioning test File will be sent to Revenue section in O&M Sub-division for Billing. Issues Certificate of synchronization to applicant (Format-8A) Page 17 of 18
18 Single Line Diagram of Rooftop Facility DC Fuse DC surge protection device DC disconnect Switch DC to AC Grid tied Inverter Manual disconnect Switch Solar PV array DC combiner box DC distribution box Uni-directional meter Solar Meter Distribution Network BESCOM Grid Bi-directional Meter Net Meter Consumer Distribution Panel AC disconnect Switch AC surge Protection device To consumer Loads AC distribution box
Format - 17 GUIDELINES FOR ON-GRID SOLAR RTPV PROGRAMME (ON NET- METERING BASIS) FOR BESCOM OFFICERS
Format - 17 GUIDELINES FOR ON-GRID SOLAR RTPV PROGRAMME (ON NET- METERING BASIS) FOR BESCOM OFFICERS 1. Introduction: Solar energy is a clean, pollution free and renewable source of energy. Karnataka being
TECHNICAL SPECIFICATIONS
1. Standards BOS Item / System I ii iii TECHNICAL SPECIFICATIONS Applicable BIS /Equivalent IEC Standards / Applicable MNRE Specifications Standard Description Standard Number Crystalline Silicon Terrestrial
POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT
POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT This Power Purchase agreement is entered into at (place).. on this. day of between Electricity Supply Company Limited
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Draft Maharashtra Electricity Regulatory Commission (Net Metering for Rooftop Solar Systems) Regulations, 2015 Electricity Act, 2003 No. MERC / Legal
INFORMATION DOCUMENT
INFORMATION DOCUMENT For Design, manufacture, supply, installation and commissioning of different capacity Roof top Solar PV Power projects under Net Metering policy in the state of Punjab. PUNJAB ENERGY
KERALA STATE ELECTRICITY REGULATORY COMMISSION
KERALA STATE ELECTRICITY REGULATORY COMMISSION Notification No. 2096/KSERC/CT/2014 Dated, Thiruvananthapuram 10 th June 2014. In exercise of the powers conferred under sections 66, 86 (1) (e) and 181 of
LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems
LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems A. General This Net Metering Standard for Customer-Owned Grid Connected Electric Generating Systems sets forth the
Financial Analysis of Solar Photovoltaic Power plant in India
Financial Analysis of Solar Photovoltaic Power plant in India M. Ganga Prasanna, S. Mahammed Sameer, G. Hemavathi Department of Management Studies MadanapalleInstitute of Technology& Science Post Box No:
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tamil Nadu Version: April 2014
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tamil Nadu Version: April 2014 Scope and Purpose These Guidelines for grid-connected small scale (rooftop) solar PV systems have
SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems
SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems Contents Introduction 3 How solar PV power systems work 4 Solar modules 5 Is solar power
File No. 5/22/2013-14/RT Ministry of New and Renewable Energy Grid Connected Rooftop Solar Power Division *****
File No. 5/22/2013-14/RT Ministry of New and Renewable Energy Grid Connected Rooftop Solar Power Division ***** Block 14, CGO Complex Lodhi Road, New Delhi-110003 Dated: 18.09.2015 Subject: Operational
A. 5MWp SPV Plant at Khimsar, Rajasthan. B. 5MWp SPV Plant Installed Technologies. D. 5MWp SPV Plant Challenges. E. 5MWp SPV Plant - Performance
An overview & Performance Analysis of 5 MWp Solar PV Plant at Khimsar, Rj Rajasthan Reliance Industries Limited June 2, 2011 July 2010 Contents A. 5MWp SPV Plant at Khimsar, Rajasthan B. 5MWp SPV Plant
Frequently Asked Questions SOLAR ENERGY:
Frequently Asked Questions SOLAR ENERGY: Why should I have Solar Power? There are lots of reasons that make installing Solar Power Generation worthwhile: Environmental Green advantages Zero carbon emissions
KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF
KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Shri. K.J.Mathew, Chairman Shri. C. Abdulla, Member Shri. M.P.Aiyappan, Member Petition No. CT/SOLAR JNNSM/KSERC/2010 August 4,
KERALA STATE ELECTRICITY REGULATORY COMMISSION
KERALA STATE ELECTRICITY REGULATORY COMMISSION Dated 24 th January 2014 NOTICE Notice is hereby given that Kerala State Electricity Regulatory Commission has published the Draft Kerala State Electricity
32/1/2013-14/PVSE(Part-II) Ministry of New and Renewable Energy SPV Off Grid Division
Annexure-A 32/1/2013-14/PVSE(Part-II) Ministry of New and Renewable Energy SPV Off Grid Division Scheme: Installation of 10,000 nos. of solar photovoltaic water pumping systems for irrigation purpose implemented
What are the basic electrical safety issues and remedies in solar photovoltaic installations?
What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic
FIXED CHARGE: This is a cost that goes towards making the service available, including
ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer
Solar Power Plants FAQs
Solar Power Plants FAQs Solar Power industry in India is gaining more and more prominence with each passing day. The domestic/off-grid industry is picking up speed too. Owing to the queries we are receiving
Listed are common requirements that apply to existing solar installations when altered, added to or reconfigured.
SOLAR ALTERATIONS REQUIREMENTS August 2015 These requirements address typical alterations to solar installations; they cannot address every scenario. In Victoria, an alteration to a solar installation
Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems
Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission
RENEWABLE ENERGY SUBSTATIONS SOLAR PHOTOVOLTAIC AND WIND POWER. tgood.com. Energy. Fast.
RENEWABLE ENERGY SUBSTATIONS SOLAR PHOTOVOLTAIC AND WIND POWER tgood.com Energy. Fast. TGOOD is a world leading manufacturer of prefabricated renewable energy substations PRODUCT CONCEPT ENVIRONMENTAL
12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting
12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.
White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5
White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code June 2015 Revision 1.5 Shalhevet Bar-Asher; SolarEdge Technologies, Inc. Bill Brooks, PE; Brooks Engineering LLC
ANALYSIS 2: Photovoltaic Glass Replacement
ANALYSIS 2: Photovoltaic Glass Replacement Problem Identification Bridgeside II is designed to accommodate 80 percent lab space and 20 percent office space. Laboratory equipment can consume a considerable
Using the sun to generate electricity
Using the sun to generate electricity Image source: http://www.globalsolarcenter.com/files/2009/04/commercial-solar.jpg Solar panels information sheet What are the benefits? How does it work? What is the
G.O.MS.No. 8 Dated 12.02.2015 Read the following:-
GOVERNMENT OF ANDHRA PRADESH ABSTRACT ENERGY, INFRASTRUCTURE & INVESTMENT DEPARTMENT - Development of Solar Power in Andhra Pradesh Andhra Pradesh Solar Power Policy, 2015 Orders Issued. ------------------------------------------------------------------------------------------------------------
SOLAR TECHNOLOGY CHRIS PRICE TECHNICAL SERVICES OFFICER BIMOSE TRIBAL COUNCIL
SOLAR TECHNOLOGY CHRIS PRICE TECHNICAL SERVICES OFFICER BIMOSE TRIBAL COUNCIL SOLAR TECHNOLOGY Photovoltaics Funding Options Solar Thermal Photovoltaics 1. What are they and how do they work? 2. The Solar
SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings
*** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not
PHOTOVOLTAIC (PV) solar panels. Specification. Electricity - CE & ISO 9000 certified. 83W panel. 180W panel Maximum power:
PHOTOVOLTAIC (PV) solar panels Electricity - CE & ISO 9000 certified Photovoltaic solar panels convert sunlight into useful electricity. ZEDfabric supplies high quality mono-crystalline silicon cell PV
Request for Proposals for Photovoltaic System Installation
Request for Proposals for Photovoltaic System Installation Presented by: Prepared by: Location: Contact: Date: Capitol Hill Housing Foundation Bonneville Environmental Foundation, Renewable Energy Group
PHOTOVOLTAIC SYSTEM DESIGN AND INSTALLATION From the pre-feasibility study to the commissioning
FEBRUARY, 2011 PHOTOVOLTAIC SYSTEM DESIGN AND INSTALLATION From the pre-feasibility study to the commissioning [email protected] www.a-sunenergy.com FEBRUARY, 2011 TABLE OF CONTENT PROJECT OVERVIEW
ENERGY SOLUTIONS RESIDENTIAL STORAGE BATTERY SYSTEM
ENERGY SOLUTIONS RESIDENTIAL STORAGE BATTERY SYSTEM MAKING SMART TOWNS, BUILDING SMART COMMUNITIES WHY PANASONIC? RESIDENTIAL STORAGE BATTERY SYSTEM The next evolution in solar energy solutions. Panasonic
Solar Matters III Teacher Page
Solar Matters III Teacher Page Solar Powered System - 2 Student Objective Given a photovoltaic system will be able to name the component parts and describe their function in the PV system. will be able
REQUEST FOR PROPOSALS SOLAR POWER PURCHASE AGREEMENT (PPA)
ISSUE DATE: July 24, 2015 REQUEST FOR PROPOSALS SOLAR POWER PURCHASE AGREEMENT (PPA) Proposals will be received until 2:00 P.M. Monday, August 24, 2015 for furnishing the services described herein. Email
Solar Solutions and Large PV Power Plants. Oscar Araujo Business Development Director - Americas
Solar Solutions and Large PV Power Plants Oscar Araujo Business Development Director - Americas Solar Business of Schneider Electric The Solar Business of Schneider Electric is focused on designing and
Solar power Availability of solar energy
Solar Energy Solar Energy is radiant energy produced in the sun as a result of nuclear fusion reactions. It is transmitted to the earth through space by electromagnetic radiation in quanta of energy called
Ministry of New and Renewable Energy. Jawaharlal Nehru National Solar Mission SOLAR PHOTOVOLTAIC WATER PUMPING SYSTEMS (2015-16)
Ministry of New and Renewable Energy Jawaharlal Nehru National Solar Mission SOLAR PHOTOVOLTAIC WATER PUMPING SYSTEMS (2015-16) I. INTRODUCTION A Solar Photovoltaic (SPV) Water Pumping System consists
KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001
KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001 Present: Shri M.R.Sreenivasa Murthy Chairman Shri Vishvanath Hiremath Shri K. Srinivasa
2016 Santee Cooper Solar Home & Solar Share Home Program Manual
2016-17 2016 Santee Cooper Solar Home & Solar Share Home Program Manual Version 03232016 This Program Manual is intended to serve as a reference for Santee Cooper s residential Customers that are interested
SHARP SOLAR Frequently Asked Questions for PV Integrators Revised 05/04/2010
SHARP SOLAR Frequently Asked Questions for PV Integrators Revised 05/04/2010 How do I determine the PTC rating of a module? PTC refers to PVUSA Test Conditions, which were developed to test and compare
Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme
Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme This agreement made at on this day of two thousand between M/s. (Renewable Energy Generator name and address) hereinafter
Application of photovoltaic s in the building and construction industry as a power generating facility
Application of photovoltaic s in the building and construction industry as a power generating facility Matthew P. Peloso Science and Technology Business Services LLP 10 Gopeng Street, ICON #34-22 Singapore,
Pilot Scheme of MNRE for Large Scale Grid Connected Roof Top Solar Power Generation
Pilot Scheme of MNRE for Large Scale Grid Connected Roof Top Solar Power Generation Solar Energy Corporation of India (A Govt. of India Enterprise) NBCC Plaza, Tower-1, 4 th Floor, Pushp Vihar Sector-V,
CHANGING THE WORLD WITH COMPELLING IDEAS. German Indian Renewable Energy Dialogue 1st of October 2008
Titel: IBC SOLAR mit starken Ideen die Welt verändern Autor: Ort, 00. Monat 2008 CHANGING THE WORLD WITH COMPELLING IDEAS German Indian Renewable Energy Dialogue 1st of October 2008 2008 IBC SOLAR Agenda
Solar Panel Installations
Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.
CUTES Solar Power System
Solar Power System Solar power systems provide a continuous, reliable power solution that's easily deployed, cost-effective and requires little maintenance. Solar Power Systems are complete, fully integrated
Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014
Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014 Table of Contents 1- PREAMBLE - 1 2- OBJECTIVES - 1 3- OPERATIVE PERIOD - 1 4- IMPLEMENTATION PLAN - 2 5- ELIGIBLE ENTITIES - 2 6- TARGETS
Corona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application
Corona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application DWP s new Solar Partnership Program is available to help offset your investment in a PV system and get you
Energy Depot GmbH PRODUCT AND APPLICATION GUIDE. Total Monitoring Solution for PV. Delivering Solutions for Energy Management
Energy Depot GmbH Delivering Solutions for Energy Management PRODUCT AND APPLICATION GUIDE Total Monitoring Solution for PV SOLAR LOGGER & ANALYSIS DC STRING MONITORING Residential Comprehensive Solar
How To Plan Out An Array Of Solar Panels
CITY OF DOWNEY COMMUNITY DEVELOPMENT, BUILDING AND SAFETY 11111 Brookshire Avenue Downey, CA 90241 562.904.7142 (www.downeyca.org) B SECTION 01/01/2011 EFFECTIVE DATE PHOTOVOLTAIC 032 FORM NUMBER 2013
Application Bulletin 103 - NEC Reference Guide for SolarBridge-Enabled AC Module Installers
9229 Waterford Centre Dr. Bldg C, Suite 110 Austin, Tx 78758 Application Bulletin 103 - NEC Reference Guide for SolarBridge-Enabled AC Module Installers Current Version: 13 AC Modules are a new product
Solar Power Frequently Asked Questions
General information about solar power 1. How do I get solar power? Solar Power Frequently Asked Questions Many companies install solar power systems including some electricity retailers. It is worth comparing
NOTICE OF INTENT Department of Revenue Policy Services Division. Income Tax Credits for Wind or Solar Energy Systems (LAC: 61:I.
NOTICE OF INTENT Department of Revenue Policy Services Division Income Tax Credits for Wind or Solar Energy Systems (LAC: 61:I.1907) Under the authority of R.S. 47:287.785, R.S. 47:295, R.S. 47:1511, and
may be prescribed by the Government, under the provisions of the sub section (1) of section 127 of the Act;
MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. CONDITIONS OF SUPPLY BASED ON THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (ELECTRICITY SUPPLY CODE & OTHER CONDITIONS OF SUPPLY) REGULATIONS,
FAQs-Main switchboard design criteria
FAQs-Main switchboard design criteria Q: What is the Australian standard for main switchboards? Current Australian standard is AS/NZS 3439.1: 2002 originating from IEC 60439. The new series of standard
AMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5
AMFA-27 AMFA-29 Operator s Manual & Installation Instructions Rev. 2.5 Date: 17 July, 2010 Permanently-connected, utility Interactive, single-phase, inverters Model AMFA-27 WIND TURBINE INVERTER (240 VAC
TELANGANA SOLAR POWER POLICY 2015
TELANGANA SOLAR POWER POLICY 2015 1 GLOSSARY COD CII GoTS GoI MNRE MoP NCE NOC NSM PCB PPA PV R&D REC RPPO RLDC SGST SLDC SPC SPP SPV SRP Scheduled Commercial Operations Date Confederation of Indian Industry
SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE
SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE for solar energy management LEATEC Delivering Solutions for Energy Management SOLAR ENERGY DATA CENTER BUILDING 4 to8 String Monitoring with 0.% Accuracy
Performance Assessment of 100 kw Solar Power Plant Installed at Mar Baselios College of Engineering and Technology
Performance Assessment of 100 kw Solar Power Plant Installed at Mar Baselios College of Engineering and Technology Prakash Thomas Francis, Aida Anna Oommen, Abhijith A.A, Ruby Rajan and Varun S. Muraleedharan
CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN
CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN 5.1 Introduction So far in the development of this research, the focus has been to estimate the available insolation at a particular location on the earth s surface
Support Information for Solar Power Generation Regulation of JERC & Suggestive Power Purchase Agreement.
Support Information for Solar Power Generation Regulation of JERC & Suggestive Power Purchase Agreement. Technical and interconnection requirements The Project Developers shall adhere to the National &
Ontario Electrical Safety Code 25 th Edition/ 2012
Ontario Electrical Safety Code 25 th Edition/ 2012 Ted Olechna Director, Codes and Standard Chief Engineer 1 What I Will Cover ESA s role is as the regulator Highlight of 2012 Code changes The Code and
Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : [email protected] [email protected]
Draft ver2 Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : [email protected] [email protected] 1 TABLE OF CONTENTS S.No Contents Page No 1. PREAMBLE 3 2. OBJECTIVES 3 3. OPERATIVE
CHAPTER 4: TECHNICAL CHARACTERISTICS OF SOLAR FARM
CHAPTER 4: TECHNICAL CHARACTERISTICS OF SOLAR FARM 4.1 PRINCIPLE OF ELECTRICITY PRODUCTION FROM SOLAR IRRADIANCE Solar irradiance from the sun can provide an invaluable source of energy. Solar energy is
Installation Guide of Sunrise Solartech PV Modules. Term 2013. Contents. Purpose of this guide. General. Safety precaution for installing a solar
Installation Guide of Sunrise Solartech PV Modules Term 2013 Contents Purpose of this guide General Safety precaution for installing a solar Photovoltaic system Product Identification Mechanical Installation
AUTOMATIC TRANSFER SWITCH. Changeover Type from 250A to 2500A
AUTOMATIC TRANSFER SWITCH Changeover Type from 250A to 2500A Table of Contents Preamble 1.1 Theoretical base 1.2 Selection the size of automatic transfer switch 1.3 Automatic transfer switch components
Karnataka Electricity Regulatory Commission. Discussion note on
Karnataka Electricity Regulatory Commission Discussion note on Draft KERC (Forecasting, Scheduling, Deviation settlement and related matters for Wind and Solar Generation sources) Regulations, 2015. 1.0.
all that you want to know About Rajasthan Solar Energy
all that you want to know bout Rajasthan Solar Energy Policy, 2014 General 01 Registration Land Timelines Fee & Charges 06 08 11 13 all that you want to know bout Rajasthan Solar Energy Policy, 2014 Rajasthan
Application Note: Modbus/RS485 Wiring for Conext Core XC Series Inverters
Application Note: Modbus/RS485 Wiring for Conext Core XC Series Inverters AP-XC-025 Revision B DANGER RISK OF ELECTRIC SHOCK, EXPLOSION, ARC FLASH, AND FIRE This Application Note is in addition to, and
Solar Energy Opportunities for the Australian Nursery Industry
Solar Energy Opportunities for the Australian Nursery Industry Introduction Solar energy is a freely available source of renewable energy that is suitable for utilisation at almost all locations in Australia.
Photo Kirklees IS SOLAR ENERGY FOR ME? A guide to going solar
Photo Kirklees IS SOLAR ENERGY FOR ME? A guide to going solar WHY SOLAR? Economics Solar energy can reduce bills, earn you money and protect you from rising energy prices. Solar is a free source of energy
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.2010 In the matter of : Determination of generic levellised generation
PERMIT APPLICATION REQUIREMENTS FOR RESIDENTIAL ROOF MOUNTED PHOTOVOLTAIC SYSTEMS
Butte County Department of Development Services PERMIT CENTER 7 County Center Drive, Oroville, CA 95965 Main Phone (530)538-7601 Permit Center Phone (530)538-6861 Fax (530)538-7785 FORM NO DBP-71 PERMIT
SOLAR PV INFORMATION. January, 2015
January, 2015 SOLAR PV INFORMATION Thank you for the opportunity to present you with information about Solar Photovoltaic (PV) Energy Systems in the East Texas area. This document will give you a brief
Solar Power HourSM. Solar educa on for your community.
Solar Power HourSM Solar educa on for your community. 1 Contents About. 1 Commonly Asked Questions.. 2-3 The Solar Site Assessment.. 3-4 Selecting a Solar Installer. 5-7 Certified Installers by State.
To whom application is to be filed
SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED 6-1-50, Corporate Office/Mint Compound/Hyderabad 063. www.tssouthernpower.com, email:[email protected] As per TELANGANA SOLAR POWER POLICY
ADDENDUM #1(BID PACKAGE # 3)
H2Engineering, Inc. 114 East Fifth Avenue Tallahassee, FL 32303 Phone 850.224.7922 Fax 850.224.5876 ADDENDUM #1(BID PACKAGE # 3) To: Jeff Williams From: Peter Lindstrom Co: Leon County Date: October 04,
Guideline for Energy Efficient Electrical systems for building. Presentation by TERI
Guideline for Energy Efficient Electrical systems for building Presentation by TERI Objective of study The study highlights how BBMP can implement energy efficiency measures in building in co-ordination
Consumer guide. be brighter. actewagl.com.au/solar [email protected] 13 14 93
be brighter. Consumer guide. Your guide on how solar works, how much you can save on your electricity bills and how to choose the right provider and system for you. actewagl.com.au/solar [email protected]
AC Coupling of Inverters for Grid Tied PV Systems
AC Coupling of Inverters for Grid Tied PV Systems AC Coupling with Conext s, Xantrex GT Inverters, and Conext TX Inverters Application Note 976-0240-01-01 Rev B DANGER RISK OF FIRE, ELECTRIC SHOCK, EXPLOSION,
Solar technology. A guide to solar power at utility scale. in Africa
Solar technology A guide to solar power at utility scale in Africa About solar power Solar electricity is generated using a free and abundant energy source the sun. In a single hour, the sun transmits
The Solar Power Specialists. Elm Park House, Elm Park Court, Pinner, Middlesex, HA5 3NN Solutions House, Unit A19, 20 Heron Road, Belfast, BT3 9LE
The Solar Power Specialists GB: 0845 64 39 772 NI: 0845 50 40 444 Email: [email protected] Visit: www.metartecsolar.com Elm Park House, Elm Park Court, Pinner, Middlesex, HA5 3NN Solutions House,
Solar Kit. Complete solution to optimize your photovoltaic system
Solar Kit Complete solution to optimize your photovoltaic system April 2012 Mounting and selection quick guide On Grid Solar Kit rooftop installation INSTALLATION WITH OVERLAID SUB-STRUCTURE (A.1, A.2)
Solar Power at Vernier Software & Technology
Solar Power at Vernier Software & Technology Having an eco-friendly business is important to Vernier. Towards that end, we have recently completed a two-phase project to add solar panels to our building
TECHNICAL BRIEF. Commercial PV in Australia and New Zealand Using the Enphase Microinverter System
TECHNICAL BRIEF Commercial PV in Australia and New Zealand Using the Enphase Microinverter System 2015 Enphase Energy Inc. All rights reserved May 2015 Table of Contents Commercial PV in Australia and
Solar Power for Agriculture and Our Experiences at the Middlesex County EARTH Center Rutgers Cooperative Extension William T. Hlubik Agricultural and Resource Management Agent Rutgers Cooperative Extension
DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015
DRAFT 31.3.2015 KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 The Kerala State Electricity Regulatory Commission hereby publishes
ALL STAR ELECTRIC COMPANY 10,000 Trumbull SE, Suite #F Albuquerque, NM 87123 (505) 856-1010 voice & fax NM License 21880 www.allstarelec.
ALL STAR ELECTRIC COMPANY 10,000 Trumbull SE, Suite #F Albuquerque, NM 87123 (505) 856-1010 voice & fax NM License 21880 www.allstarelec.com On-Site Power System Specialists: Photovoltaics, Wind Turbine
Technology Fact Sheet for Mitigation
Technology Fact Sheet for Mitigation Solar PV systems (>1MW) i Technology: Solar PV systems (>1MW) Sector : Energy Subsector : Technology characteristics Introduction Solar photovoltaic, or simply photovoltaic
Connecting to the network information pack Version 2
Connecting to the network information pack Version 2 Updated: Contents 1.0 What is a new connection or connection alteration?... 3 2.0 Connection enquiry... 3 3.0 Connection application... 3 3.1 Processing
We're with you... solar. Call 1800 332 332 today FOR THE LIFE OF THE SYSTEM YEAR WARRANTY * YEAR OLD BACKED BY CSR BRADFORD CSR A AUSTRALIAN COMPANY
We're with you... FOR THE LIFE OF THE SYSTEM 25 YEAR WARRANTY * Electricity prices are predicted to continue to rise in the future. If you're serious about installing energy in your home, look no further
Initiatives by TEDA and
Initiatives by TEDA and Tamil Nadu Solar Policy 2012 1 POWER SECTOR AT A GLANCE (AS ON 30.09.12) INDIA TAMIL NADU Nuc2% Nuc3% RES 12% Hydro 19% RES 44% Thermal 41% Thermal 67% Hydro 12% Thermal Hydro 138806.18
Distributed Generation: Frequently Asked Questions
Distributed Generation: Frequently Asked Questions 1) What is distributed generation (DG)? Generating technologies located close to where the electricity is being used that are connected to the electric
Marketing Methodology of Solar PV Power Packs
Marketing Methodology of Solar PV Power Packs Somasekhar. G, Bharathi.G, and GirijaEureka.M* Department of Management Studies Madanapalle Institute of Technology & Science Post Box No: 14, Angallu, Madanapalle-
What is Solar? The word solar is derived from the Latin word sol (the sun, the Roman sun god) and refers to things and methods that relate to the sun.
What is Solar? The word solar is derived from the Latin word sol (the sun, the Roman sun god) and refers to things and methods that relate to the sun. What is the solar industry? The solar industry is