1 CPA Steel Stud Framing Page 1 of 11 STEEL STUD FRAMING General Requirements City of Palo Alto (CPA) Building Inspection Division 285 Hamilton Ave. Inspection Request: Building Division IVR# 302 Revision Date:09/12/12 General Requirements/Checklist for: Commercial Codes Enforced: 2010 CRC, CBC Palo Alto Municipal Code (PAMC) The information provided in this document is general and intended as a guide only. Each project is unique and additional requirements may be enforced as deemed appropriate. APPLICATION CBC 2210 Cold formed steel light-framed construction general design, installation, and construction of structural and non-structural steel framing shall be in accordance with American Iron and Steel Institute (AISI) For additional information and illustrations visit Steel Stud Manufacturers Association SSMA Steel stud walls supporting mechanical equipment or appliances shall be designed for seismic loads in accordance with the California Building Code referenced standard ASCE 7-05 for building components. LIST OF ITEMS UNAPPROVED IN THE CITY OF PALO ALTO Slotted Slip/Deflection Track approved only for wall framing. Slotted Slip/Deflection Track shall not be used for soffits and drop ceiling framing. Hard Screwing not an acceptable alternative Steel studs and other structural members in load bearing walls shall not be spliced. (Runner tracks may be spliced per approved plan or manufacturer s specifications.) Field cuts or notches through the flanges or lips of any structural member not allowed. Damaged members such as cracking in the steel at the bend radius location, and members with scaling of protective coating not allowed. Welding of steel members is not permitted. Exception: Special Inspection by an approved agency for welding and re-coating with a zincrich paint. Punched members shall not be used when unpunched members are specified. Dietrich roll-formed (dimpled) framing materials not approved for structural framing including ceilings and soffits. (See attached manufacturer s information below)

2 CPA Steel Stud Framing Page 2 of 11 STEEL STUD FRAMING INSPECTION (General Requirements) Identification (all framing members) CBC Identification shall be spaced not less than 48 O.C. *Size, type, flange, and thickness. Yield strength of steel Galvanized coating weight Manufacturer s name ICC-ES/ICBO report numbers Steel tracking numbers to identify master coil info. Date and time of production Example of Size, type, flange, and thickness: 362S means: 362=3-5/8 web depth - S= stud or joist C-shape. Other Markers may include: T= track - U= channel or stud no lips - F=furring L= angle or L header - 125= 1-1/4 flange width - 33= steel thickness 20 gage in mills. Steel Stud Framing Code Requirements 2010 CBC section General. The design and installation of structural members and nonstructural members utilized in cold-formed steel light-frame construction shall be in accordance with AISI S200-AISI S230, AISI S100, and 2010 CBC Sections through , as applicable. Manufacturer s installation recommendations and engineering guidelines shall be adhered to. (See CEMCO illustrative examples below) Sill Plate Sill plate anchorage: Shall be in accordance with ICC Evaluation Services Report #1752 and permit reviewed/issued plans/specifications. o Pneumatically driven pins Verify that pin size complies with approved plans (check head markings and values) Verify that pins are fully driven and have a minimum penetration of ¼ through the last material joined. Confirm that pins have protective coating per approved plans. Verify pin spacing is per plans. Wall to foundation connection: Stud blocking inside of wall track at all anchor bolt locations, minimum 6 long with 4 screws in each flange/side, Gage minimum thickness as required for vertical height/span of wall and whether it is bearing or non-bearing. Wall to wood sill connection: Connect track to wood sill with min. 3 x 4 plate with a min. 4 screws to track and 4 nails to wood sill, at the location of anchor bolts. Wall framing Verify that gaps between the end of the stud and the track web are not greater than 1/8. Screw connections (See wall fastening schedule below) Verify screw size, spacing and protective coating complies with approved plans. Verify that screws are fully driven and have a min. penetration of (3) threads through the last member joined with no popped or damaged components. Verify that screws penetrate individual components in the connection without causing separation/gap between the framing members. Wall stud requires one screw at each flange/side.

3 CPA Steel Stud Framing Page 3 of 11 Bracing Requirements (See example illustrations below for blocking, strapping, and bridging methods) Bracing intervals and methods for unsheathed flanges shall be determined by Engineer of record or Manufacturer s recommendations and shall be stated on approved set of plans. Unsheathed flange shall be braced to resist rotation of the framing member when subject to lateral load (i.e. wall hung cabinets, plumbing fixture, heavy cladding materials such as marble, stone or tile) Load bearing walls shall be sheathed on both sides or have approved bracing. Web stiffeners required at all bearing point. Joist Joists shall be located directly over bearing studs, or a load distribution member, such as a track connection, shall be provided at the top of the bearing wall. Web stiffeners and compression blocking shall be provided at reaction points and/or at points of concentrated loads. Verify that continuous track or blocking is provided at joist ends and at each support when not otherwise restrained from rotation. Ceiling Framing Hard metal ceilings in commercial buildings: Verify access opening, light, and access walkways are installed as required for maintenance of all equipment including signs. CMC Interior non-structural composite/ Dimpled (General Requirements) Application: Non-load bearing walls only. Composite wall shall be sheathed both sides with ½ gypsum wallboard for 18 and 33 mil. Composite wall shall be sheathed both sides with 5/8 gypsum wallboard for 43, 54 and 68 mil. Sheathing shall be attached with min. # 6 screws at a max.12 o. c. Corrosion Protection Verify that Load-bearing steel framing is protected with galvanized coating: See recommendations below. Galvanized Coating: Coating Recommended for G60 Indoor application where the environment is relatively dry. G90 Applications where there is a potential for dampness from condensation. Mils to gage conversion table: Mils = Gage 33 = = = = = = 10 Wall fastening schedule: Description of building element Number and size of fasteners Spacing of fasteners Floor joist to track of load-bearing walls 2-No. 8 screws Each joist Wall stud to top or bottom track 2-No. 8 screws Each end of stud, one per flange Structural sheathing to wall studs No. 8 screws per attachment 6 o.c. on edges and 12 o.c. at intermediate supports schedule All the above screw sizes are minimum requirements

4 CPA Steel Stud Framing Page 4 of 11 DIETRICH ROLL-FORMED FRAMING MATERIALS INFORMATION:

5 CPA Steel Stud Framing Page 5 of 11 COMMERCIAL CONCRETE PAN-DECK FASTENING DETAIL (TYP)

6 CPA Steel Stud Framing Page 6 of 11

7 CPA Steel Stud Framing Page 7 of 11

8 CPA Steel Stud Framing Page 8 of 11

9 CPA Steel Stud Framing Page 9 of 11

10 CPA Steel Stud Framing Page 10 of 11

11 CPA Steel Stud Framing Page 11 of 11

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally

More information

PART 1 GENERAL 1.1 SECTION INCLUDES

PART 1 GENERAL 1.1 SECTION INCLUDES J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including

More information

Fig. 2 WALL-TO-WALL PANEL CONNECTIONS CORNER WALL CONNECTION

Fig. 2 WALL-TO-WALL PANEL CONNECTIONS CORNER WALL CONNECTION SIPS SCREWS WITH MINIMUM 1" PENETRATION IN WOOD MEMBER IN SIP WALL PANEL CONNECTED TO @ 24" O.C. MAXIMUM OUTSIDE SKIN EACH SIDE OF FRAMING TYP. AS RECOMMENDED BY FOAM CORE AS EACH SIDE OF FRAMING TYP.

More information

HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES

HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES 101 Retrofits Required. Pursuant to Section 553.844 553.884, Florida Statutes, strengthening of existing site-built,

More information

Chapter 6 ROOF-CEILING SYSTEMS

Chapter 6 ROOF-CEILING SYSTEMS Chapter 6 ROOF-CEILING SYSTEMS Woodframe roof-ceiling systems are the focus of this chapter. Cold-formed steel framing for a roof-ceiling system also is permitted by the IRC but will not be discussed;

More information

GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER

GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER CHAPTER 25 GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER User note: Code change proposals to this chapter will be considered by the IBC Structural Code Development Committee during the 2016 (Group B)

More information

Standard from CSI Part Section Format. 06212 For Wood Framing 05160 For Metal Framing 09226 For Gypsum Sheathing

Standard from CSI Part Section Format. 06212 For Wood Framing 05160 For Metal Framing 09226 For Gypsum Sheathing Standard from CSI Part Section Format. 06212 For Wood Framing 05160 For Metal Framing 09226 For Gypsum Sheathing Specifications for SURE-BOARD Series 200 and 200W Panel for shear PART 1.0 GENERAL 1.01

More information

POST AND FRAME STRUCTURES (Pole Barns)

POST AND FRAME STRUCTURES (Pole Barns) POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:

More information

Discipline: Structural Issued 04-26-06

Discipline: Structural Issued 04-26-06 California Department of General Services. Division of the State Architect. Product Acceptance Report STRUCTURAL SHEAR PANEL SURE-BOARD SERIES 200 PANELS PA-132 Discipline: Structural Issued 04-26-06 This

More information

CONSTRUCTION DETAILS & LOAD DESIGN CHARTS

CONSTRUCTION DETAILS & LOAD DESIGN CHARTS Office and Production 126 New Pace Rd., PO Box 279 Newcomerstown, OH 43832 1-800-446-2188, Fax: 740-498-4184 www.buildwithsips.com CONSTRUCTION DETAILS & LOAD DESIGN CHARTS Table of Contents Description

More information

Seismic Technical Guide

Seismic Technical Guide Technical Document Seismic Technical Guide Hanger Wire Attachment Code Requirements 1 The International Building Code (IBC) defines the requirement for hanger wire and their supports and attachment methods.

More information

Wisconsin Building Products Evaluation

Wisconsin Building Products Evaluation Safety & Buildings Division 201 West Washington Avenue P.O. Box 2658 Madison, WI 53701-2658 Evaluation # 200813-O Wisconsin Building Products Evaluation Material Best Management Standards for Foundation

More information

March 14, 2007. Installation of Bay, Bow and Garden Windows

March 14, 2007. Installation of Bay, Bow and Garden Windows March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed

More information

Design of Cold-Formed Steel Shear Walls

Design of Cold-Formed Steel Shear Walls DESIGN GUIDE 2 Design of Cold-Formed Steel Shear Walls March 1998 The following publication was developed by R.L. Brockenbrough & Associates for the American Iron and Steel Institute (AISI), In the production

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS door frames Engineered product systems INSTALLATION INSTRUCTIONS door frames MINIMALIST DOOR FRAME Fry Reglet Flush Door frames are designed for use with 3 5/8 studs with ½ drywall both sides (4 5/8 throat

More information

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the Chapter 7 PLUMBING AND ELECTRICAL 7.1 Introduction to Plumbing and Electrical Consideration of support services such as plumbing and electrical systems from the preliminary schematics phase through final

More information

THE DOW CHEMICAL COMPANY Issued: August 1, 2008 200 LARKIN CENTER 1605 JOSEPH DRIVE MIDLAND MICHIGAN 48674 (989) 638-8655 www.dowbuildingmaterials.

THE DOW CHEMICAL COMPANY Issued: August 1, 2008 200 LARKIN CENTER 1605 JOSEPH DRIVE MIDLAND MICHIGAN 48674 (989) 638-8655 www.dowbuildingmaterials. ICC EVALUATION SERVICE, INC. EvaluateP InformP Protect Los Angeles Business/Regional OfficeP 5360 Workman Mill RoadP Whittier, CA 90601 (562) 699-0543 phonep (562) 695-4694 fax DIVISION: Section: 6 WOOD

More information

K. D. FRAME ASSEMBLY FOR CLOSED STEEL STUD WALLS...Ins 10. FRAME INSTALLATION DETAILS FOR CLOSED STEEL STUD WALLS...Ins 11

K. D. FRAME ASSEMBLY FOR CLOSED STEEL STUD WALLS...Ins 10. FRAME INSTALLATION DETAILS FOR CLOSED STEEL STUD WALLS...Ins 11 K. D. FRAME ASSEMBLY FOR MASONRY WALLS...........................Ins 2 FRAME INSTALLATION DETAILS FOR MASONRY WALLS......................Ins 3 INSTALLING EXISTING MASONRY WALL ANCHORS IN FRAME..................Ins

More information

GYPSUM BOARD AND PLASTER

GYPSUM BOARD AND PLASTER CHAPTER 25 GYPSUM BOARD AND PLASTER SECTION 2501 GENERAL 2501.1 Scope. 2501.1.1 General. Provisions of this chapter shall govern the materials, design, construction and quality of gypsum board, lath, gypsum

More information

Guidelines for Earthquake Bracing of Residential Water Heaters

Guidelines for Earthquake Bracing of Residential Water Heaters Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)

More information

Guidelines for Earthquake Bracing Residential Water Heaters

Guidelines for Earthquake Bracing Residential Water Heaters Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the

More information

Screw Penetration Testing with the ProSTUD

Screw Penetration Testing with the ProSTUD Screw Penetration Testing with the ProSTUD 24 June 2010 Structural Testing and Research Inc. 498 Eagle St. N., Unit 6 Cambridge, ON, Canada, N3H 1C2 Tel: (519) 653-5255 www.starlabs.ca STaR Technical Report

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

PANELIZED HOME INSTALLATION GUIDELINE

PANELIZED HOME INSTALLATION GUIDELINE PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.

More information

VA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD

VA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD SECTION 09 29 00 GYPSUM BOARD PART 1 - GENERAL 1.1 DESCRIPTION This section specifies installation and finishing of gypsum board, vapor retarder and air and moisture barrrier. 1.2 RELATED WORK A. Installation

More information

LIGHT FLOOR AND WALL FRAMING

LIGHT FLOOR AND WALL FRAMING CHAPTER 1 LIGHT FLOOR AND WALL FRAMING In the normal sequence of construction events, the floor and wall activities follow the completed foundation work. In this chapter, we ll examine established methods

More information

Installation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details

Installation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details D Installation Details D1 General D2 Walls D3 Ceilings D4 Reference D Installation Details D Contents D1 General Installation and Fastening Sequence for Steel Studs D1.1 Fastener Selection D1.3 D2 Walls

More information

SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes seismic restraints and other earthquake-damage-reduction measures for electrical

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-05 40 00 (May 2015) ------------------------ Preparing Activity: NAVFAC Superseding UFGS-05 40 00 (May 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in

More information

A. Structural steel framing members, support members, and struts. B. Baseplates, shear stud connectors, and expansion joint plates.

A. Structural steel framing members, support members, and struts. B. Baseplates, shear stud connectors, and expansion joint plates. DIVISION 5 - METALS Section 05120: Structural Steel...4 Section 05125: Miscellaneous Steel and Metal Fabrications...3 Section 05311: Steel Roof Deck...3 Section 05400: Cold-Formed Metal Framing...7 Section

More information

4. ANCHOR BOLTS AND STRAPS a. ½" anchor bolts shall be embedded 7" into concrete a maximum of 6' on center and 12" from corners and ends of plates.

4. ANCHOR BOLTS AND STRAPS a. ½ anchor bolts shall be embedded 7 into concrete a maximum of 6' on center and 12 from corners and ends of plates. GENERAL CODE REQUIREMENTS (BASEMENTS) 1. FOOTINGS a. Footings shall be below frost line depth (42"). b. For an 8" foundation wall, footings shall be no less than 8" deep and 16" wide. c. Steel reinforcement

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

RESIDENTIAL MASONRY A BEST PRACTICES GUIDE

RESIDENTIAL MASONRY A BEST PRACTICES GUIDE RESIDENTIAL MASONRY A BEST PRACTICES GUIDE Build With Brick Build With Boral CONTENTS BRICK :01 MASONRY CEMENT :03 MASONRY SAND :04 WALL TIES :05 STEEL LINTELS :07 DRAINAGE WALL SYSTEM :09 FLASHING :11

More information

A B U I L D E R, S G U I D E T O S T E E L F R A M E C O N S T R U C T I O N. Steel Framing Guide. s t e e l f r a m i n g. o r g

A B U I L D E R, S G U I D E T O S T E E L F R A M E C O N S T R U C T I O N. Steel Framing Guide. s t e e l f r a m i n g. o r g A B U I L D E R, S G U I D E T O S T E E L F R A M E C O N S T R U C T I O N Steel Framing Guide s t e e l f r a m i n g. o r g STEEL FRAMING GUIDE STEEL FRAMING GUIDE A N E A S Y- T O - U S E G U I D

More information

Repair of Earthquake-Damaged Masonry Fireplace Chimneys SOUTH NAPA EARTHQUAKE RECOVERY ADVISORY

Repair of Earthquake-Damaged Masonry Fireplace Chimneys SOUTH NAPA EARTHQUAKE RECOVERY ADVISORY Repair of Earthquake-Damaged Masonry Fireplace Chimneys SOUTH NAPA EARTHQUAKE RECOVERY ADVISORY Purpose and Intended Audience The August 24, 2014 South Napa Earthquake has again served as a reminder that

More information

Minimizing Water Intrusion Through Roof Vents in High-Wind Regions

Minimizing Water Intrusion Through Roof Vents in High-Wind Regions Minimizing Water Intrusion Through Roof Vents in High-Wind Regions http://www.fema.gov HURRICANE IKE RECOVERY ADVISORY Purpose: To recommend practices for minimizing water intrusion through roof vent systems

More information

Trusted SECTION: 04 HILTI, INC. TULSA, Conformity! ICC-ES Evaluation. not specifically. Copyright 2015

Trusted SECTION: 04 HILTI, INC. TULSA, Conformity! ICC-ES Evaluation. not specifically. Copyright 2015 0 ICC ES Report ICC ES (800) 42 6587 (562) 699 054 www.icc es.orgg 000 Most Widely Accepted and Trusted ESR 2269 Reissued 02/205 This report is subject to renewal 02/207. DIVISION: 0 00 00 CONCRETE SECTION:

More information

RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS

RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS The following guidelines are intended to assist with the permit acquisition process with regard to Plumbing Alterations. Not all information, or additional

More information

Connection Solutions

Connection Solutions Connection Solutions DESIGN BUILD SYSTEM Connection Solutions for Cold formed Steel Construction Complies with; AS/NZS 4600:2005 AISI S100:2007 AS/NZ 1397 ASTM A653 DESIGN & BUILD SYSTEM FRAMECAD Construction

More information

Code Compliant Repair and Protection Guide

Code Compliant Repair and Protection Guide PROFESSIONALS Code Compliant Repair and Protection Guide FOR THE INSTALLATION OF UTILITIES IN WOOD FRAME CONSTRUCTION 800-999-5099 www.strongtie.com CONTENTS Repair and Protection Products... 3 Plumbing/Mechanical

More information

TECHNICAL NOTE. Design of Diagonal Strap Bracing Lateral Force Resisting Systems for the 2006 IBC. On Cold-Formed Steel Construction INTRODUCTION

TECHNICAL NOTE. Design of Diagonal Strap Bracing Lateral Force Resisting Systems for the 2006 IBC. On Cold-Formed Steel Construction INTRODUCTION TECHNICAL NOTE On Cold-Formed Steel Construction 1201 15th Street, NW, Suite 320 W ashington, DC 20005 (202) 785-2022 $5.00 Design of Diagonal Strap Bracing Lateral Force Resisting Systems for the 2006

More information

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)

More information

research report Residential Hip Roof Framing Using Cold-Formed Steel Members RESEARCH REPORT RP06-2 American Iron and Steel Institute

research report Residential Hip Roof Framing Using Cold-Formed Steel Members RESEARCH REPORT RP06-2 American Iron and Steel Institute research report Residential Hip Roof Framing Using Cold-Formed Steel Members RESEARCH REPORT RP06-2 2006 American Iron and Steel Institute Residential Hip Roof Framing Using Cold-Formed Steel Members i

More information

The Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space

The Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space The Stabilizer TM Supplemental support system for sagging beams and floor joists within a crawl space Pre-drilled holes in steel plate allow for connection to beam or floor joists. Benefits Levels and

More information

Mark Cramer Inspection Services, Inc.

Mark Cramer Inspection Services, Inc. Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction

More information

AUTHORIZATION TO MARK

AUTHORIZATION TO MARK AUTHORIZATION TO MARK This authorizes the application of the Certification Mark(s) shown below to the models described in the Product(s) Covered section when made in accordance with the conditions set

More information

ANCHOR: Metal securing device embedded or driven into masonry, concrete, steel or wood.

ANCHOR: Metal securing device embedded or driven into masonry, concrete, steel or wood. CONSTRUCTION TERMINOLOGY ANCHOR: Metal securing device embedded or driven into masonry, concrete, steel or wood. ANCHOR BOLT: Heavy, threaded bolt embedded in the foundation to secure sill to foundation

More information

The better way to build TM. Installation Manual. EXTERIOR WALL SIPs

The better way to build TM. Installation Manual. EXTERIOR WALL SIPs The better way to build TM Installation Manual EXTERIOR WALL SIPs July 2015 EXTERIOR WALL SIPs Installation Manual Table of Contents Topics General Requirements................................... 3 Materials..............................................

More information

H-Stud Area Separation Wall System

H-Stud Area Separation Wall System 12 TH EDITION 09 21 16.33/NGC H-Stud Area Separation Wall System 09 21 16.33 139 H-STUD AREA SEPARATION WALL SYSTEM The fire-protection of gypsum-based Area Separation Walls is demonstrated in dramatic

More information

David C. Barrow Elementary School 100 Pinecrest Drive, Athens, GA 30605

David C. Barrow Elementary School 100 Pinecrest Drive, Athens, GA 30605 David C. Barrow Elementary School 100 Pinecrest Drive, Athens, GA 30605 Winner of the 2014 Cold-Formed Steel Engineers Institute (CFSEI) Design Excellence Award May 2014 The David C. Barrow Elementary

More information

ICC-ES Evaluation Report

ICC-ES Evaluation Report ICC-ES Evaluation Report ESR-2369 Reissued May 1, 2010 This report is subject to re-examination in one year. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council

More information

Featuring TJ Rim Board and TimberStrand LSL

Featuring TJ Rim Board and TimberStrand LSL #TJ-8000 SPECIFIER S GUIDE TRUS JOIST RIM BOARD Featuring TJ Rim Board and TimberStrand LSL Multiple thicknesses, grades, and products to cover all your rim board needs 1¼" Thickness matches lateral load

More information

TYPICAL PATIO COVERS 111

TYPICAL PATIO COVERS 111 City of Laguna Niguel Building Division 30111 Crown Valley Pkwy Laguna Niguel, CA 92677 (949) 362-4360 FAX 362-4369 www.cityoflagunaniguel.org TYPICAL PATIO COVERS 111 PLEASE NOTE: This information Bulletin

More information

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances. Residential Decks Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org

More information

City of San Diego, CWP Guidelines

City of San Diego, CWP Guidelines PART 1 -- GENERAL SECTION 08520-1.1 WORK OF THIS SECTION City of San Diego, CWP Guidelines A. The WORK of this Section includes providing aluminum windows with frames, bracing, glazing attachments, screens,

More information

Superform Products Ltd.

Superform Products Ltd. TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000

More information

6 RETROFITTING POST & PIER HOUSES

6 RETROFITTING POST & PIER HOUSES Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This

More information

Bracing Webs in Trusses that have Dissimilar Configurations

Bracing Webs in Trusses that have Dissimilar Configurations Bracing Webs in Trusses that have Dissimilar Configurations Released April 25, 2006 Issue: Truss Design Drawings (TDD) that are prepared in accordance with ANSI/TPI 1, National Design Standard for Metal

More information

Window Installation Instructions

Window Installation Instructions Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for

More information

Preformed Metal Roofing and Siding

Preformed Metal Roofing and Siding Page -1-1. GENERAL 1.1. Description This specification along with the drawings covers the furnishing of all material, products, equipment, accessories, tools, services, transportation, labor and supervision

More information

Partitioning & Ceiling Product Information

Partitioning & Ceiling Product Information Partitioning & Ceiling Product Information tel + 44 (0) 1384 412448 fax + 44 (0) 1384 4494 email enquiries@drywallsteelsections.co.uk web www.drywallsteelsections.co.uk tel + 44 (0) 1384 412448 fax + 44

More information

CALIFORNIA BUILDING CODE

CALIFORNIA BUILDING CODE CALIFORNIA BUILDING CODE NONSTRUCTURAL DESIGN REQUIREMENTS This section contains portions of the California Building Code which relate to basic minimum nonstructural design requirements for a residence.

More information

STRUCTURAL TESTS AND SPECIAL INSPECTIONS

STRUCTURAL TESTS AND SPECIAL INSPECTIONS CHAPTER 17 STRUCTURAL TESTS AND SPECIAL INSPECTIONS SECTION 1701 GENERAL 1701.1 Scope. The provisions of this chapter shall apply to Class I buildings and shall govern the quality, workmanship and requirements

More information

We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden window unit.

We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden window unit. Important Information for New Construction Installations Attention Installer! We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden

More information

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................

More information

Engineered Wood Foundations

Engineered Wood Foundations Engineered Wood Foundations Emeraldfoundations.com 1 EWF Planning and Installation manual This manual will serve as a guide to planning and installing an Emerald Foundation system. This system is comprised

More information

STANDARD OPEN PATIO COVER

STANDARD OPEN PATIO COVER STANDARD OPEN PATIO COVER BUILDING & SAFETY DIVISION 201 E. LA HABRA BLVD. LA HABRA, CA 90631 62-90-9710 Call Before You Dig 1-800-227-2600 PLEASE NOTE: This information Bulletin is made available to assist

More information

Chapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS.

Chapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS. Austin City Code - Volume II TITLE 25 LAND DEVELOPMENT\CHAPTER 25-12 TECHNICAL CODES\ARTICLE 1: UNIFORM BUILDING CODE\25-12-3 LOCAL AMENDMENTS TO THE BUILDING CODE Chapter 36 - STRAW BALE CONSTRUCTION

More information

Good Craftsmanship Guide. Carpentry and Joinery- Carcassing

Good Craftsmanship Guide. Carpentry and Joinery- Carcassing Good Craftsmanship Guide Carpentry and Joinery- Carcassing Introduction This Good Craftsmanship Guide highlights key problems with the major elements of Carpentry and Joinery - Carcassing, and gives guidance

More information

City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures

City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures SECTION 7201 - PURPOSE The purpose of this appendix chapter is to establish minimum prescriptive standards

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:

More information

Patio Covers / Carports

Patio Covers / Carports Patio Covers / Carports Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed

More information

300mm. 2mm MIN GAP. PLACE 100mm X 100mm. SO THAT IT IS 38mm INTO

300mm. 2mm MIN GAP. PLACE 100mm X 100mm. SO THAT IT IS 38mm INTO INSTALL PEEL & STICK (P&S) GUSSETS WITH PRIMER AS PER MANUFACTURERS INSTRUCTIONS 2mm MIN GAP IN SHEATHING STEP 1 PLACE 100mm X 100mm PIECE OF P&S IN CORNER SO THAT IT IS 38mm INTO THE OPENING EACH WAY

More information

ICC-ES Evaluation Report Reissued September, 2010 This report is subject to re-examination in one year.

ICC-ES Evaluation Report Reissued September, 2010 This report is subject to re-examination in one year. ICC-ES Evaluation Report ESR-2270 Reissued September, 2010 This report is subject to re-examination in one year. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council

More information

Fire Protection. CANADIAN STEEL CONSTRUCTION COUNCIL 201 Consumers Road, Suite 300 Willowdale, Ontario, M2J 4G8. Floor Assembly No.

Fire Protection. CANADIAN STEEL CONSTRUCTION COUNCIL 201 Consumers Road, Suite 300 Willowdale, Ontario, M2J 4G8. Floor Assembly No. BULLETIN No. 28 (a) Fire Protection CANADIAN STEEL CONSTRUCTION COUNCIL 201 Consumers Road, Suite 300 Willowdale, Ontario, M2J 4G8 Floor Assembly No. NRC764-FF22 Fire Endurance Period 1 74 minutes Sound

More information

1/2" CDX PLY W/ 8d @ 6"/ 6"/ 12" 2x ROOF RAFTERS @ 16"OC W/ R-30 BATT. INSUL. (COMMON NAILS)

1/2 CDX PLY W/ 8d @ 6/ 6/ 12 2x ROOF RAFTERS @ 16OC W/ R-30 BATT. INSUL. (COMMON NAILS) TYPE V CONSTRUCTION IS A CLASSIFICATION OF BUILDINGS BY CONSTRUCTION MATERIALS AND METHODS. IT IS THE LEAST RESTRICTIVE PERMITTED BY THE UNIFORM BUILDING CODE AND INCLUDES LIGHT, WOOD-FRAME CONSTRUCTION.

More information

ISO Types 1-6: Construction Code Descriptions

ISO Types 1-6: Construction Code Descriptions ISO 1 Frame (combustible walls and/or roof) Class 1B Buildings where the exterior walls are wood or other combustible materials, including construction where the combustible materials are combined with

More information

REPORT HOLDER: JENWEST ENTERPRISES LLC, DBA ADVANCED CONNECTOR SYSTEMS 321 SOUTH 1240 WEST #15 LINDON, UTAH 84042 EVALUATION SUBJECT:

REPORT HOLDER: JENWEST ENTERPRISES LLC, DBA ADVANCED CONNECTOR SYSTEMS 321 SOUTH 1240 WEST #15 LINDON, UTAH 84042 EVALUATION SUBJECT: 0 ICC ES Report ICC ES (800) 423 6587 (562) 699 0543 www.icc es.org 000 Most Widely Accepted and Trusted ESR 3635 Reissued 04/2016 This report is subject to renewal 04/2018. DIVISION: 03 00 00 CONCRETE

More information

Installation Guide. Bath and Wall Surrounds SERIES 7104 1021861-2-B

Installation Guide. Bath and Wall Surrounds SERIES 7104 1021861-2-B Installation Guide and Wall Surrounds SERIES 7104 1021861-2-B Thank You For Choosing Sterling We appreciate your commitment to Sterling value. Please take a few minutes to review this manual before you

More information

Introduction...COMB-2 Design Considerations and Examples...COMB-3

Introduction...COMB-2 Design Considerations and Examples...COMB-3 SECTION DIRECTORY General Information Introduction...COMB-2 Design Considerations and Examples...COMB-3 Combination Assembly Recommendations and Limitations Composite Configurations...COMB-4 Typical Sealant

More information

SUPER SHED. Indoor shelter for your outdoor tools.

SUPER SHED. Indoor shelter for your outdoor tools. SUPER SHED Indoor shelter for your outdoor tools. Not everyone needs a garden shed. But, if you've no more space on your garage wall for that new leaf rake, if you can't find your potting trowel because

More information

SECTION 05 42 16 COLD-FORMED METAL DECK FRAMING Elevations Steel Deck Framing by Trex

SECTION 05 42 16 COLD-FORMED METAL DECK FRAMING Elevations Steel Deck Framing by Trex (Specifier Note: The purpose of this guide specification is to assist the specifier in correctly specifying cold-formed metal deck framing products and execution. The specifier needs to edit the guide

More information

Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996

Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996 CITY OF SAN JOSE BUILDING DIVISION POLICY Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996 All new and replacement water heaters installed

More information

Clad Direct Glaze Window Installation Instructions

Clad Direct Glaze Window Installation Instructions Clad Direct Glaze Window Installation Instructions Sill flashing and sealing: 2. An overview of the proper flashing sequence is shown in figure 1. Please read entire installation instructions carefully

More information

REDI-EXIT COMMERCIAL FIRE DOOR AND EXTERIOR DOOR KITS INSTALLATION GUIDELINES

REDI-EXIT COMMERCIAL FIRE DOOR AND EXTERIOR DOOR KITS INSTALLATION GUIDELINES REDI-EXIT COMMERCIAL FIRE DOOR AND EXTERIOR DOOR KITS INSTALLATION GUIDELINES Tools Required Tape Measure Hammer Slotted Screw Driver #2 & #3 Philips Screw Driver 3-4 Foot Level 12 Pry Bar Cold Chisel

More information

Installation Instructions

Installation Instructions Installation Instructions READ BEFORE INSTALLING UNIT For Low Profile Window Air Conditioner INSTALLATION WARNINGS AND CAUTION Carefully read the installation manual before beginning. Follow each step

More information

K2 STONE NATURAL VENEER

K2 STONE NATURAL VENEER INTRODUCTION WHAT IS K2 NATURAL THINSTONE VENEER? Natural K2 Stone veneer is real stone, cut 1 inch thick, making it light enough to be installed as a veneer. Sometimes referred to as thin veneer, thin

More information

609 West Rock Road, Radford,VA 24141 540-633-5000 / (fax) 540-731-3712 RECOMMENDED ATTACHMENTS & CONNECTION DETAILS

609 West Rock Road, Radford,VA 24141 540-633-5000 / (fax) 540-731-3712 RECOMMENDED ATTACHMENTS & CONNECTION DETAILS 609 West Rock Road, Radford,VA 24141 540-633-5000 / (fax) 540-731-3712 RECOMMENDED ATTACHMENTS & CONNECTION DETAILS INDEX OF DRAWINGS SECTION A: A-1 = METAL TRACK TO PANEL ATTACHMENT A-2 = WOOD PLATE TO

More information

Requirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited**

Requirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited** PHRC Webinar Series Tuesday, September 9, 2014 1:00 pm Requirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited** Presented by: Bryan Heitzmann Credit(s) earned on completion of

More information

Residential Decks. Planning and Development Services Department

Residential Decks. Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Planning and Development Services Department Residential Decks

More information

usg.com/me USG Middle East, Ltd. Dammam, Saudi Arabia E-mail: info@usgme.com Fax: +966 3 8121029 +966 3 8120995

usg.com/me USG Middle East, Ltd. Dammam, Saudi Arabia E-mail: info@usgme.com Fax: +966 3 8121029 +966 3 8120995 USG Middle East, Ltd. Dammam, Saudi Arabia E-mail: info@usgme.com Fax: +966 3 8121029 +966 3 8120995 Riyadh, Saudi Arabia E-mail: riyadhsales@usgme.com Fax: +966 1 4772734 +966 1 4772734 Jeddah, Saudi

More information

Uncovered Decks & Porches

Uncovered Decks & Porches Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed

More information

Typical Deck Details

Typical Deck Details Fairfax County, Virginia Typical Deck Details Based on the 2012 Virginia Residential Code The design details in this document apply to residential, single-level decks only. Construction cannot deviate

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

Storage Store the siding in a dry and ventilated area. Do not place it directly on the ground. Always cover the siding after a day s work.

Storage Store the siding in a dry and ventilated area. Do not place it directly on the ground. Always cover the siding after a day s work. Installation Guide Before you begin, take the time to read this entire guide to clearly understand the requirements and steps to follow for proper installation. Warning Do not install defective material.

More information

MUNICODE SERVICES LTD.

MUNICODE SERVICES LTD. The Preserved Wood Foundation Guide MUNICODE SERVICES LTD. Prepared by MuniCode Services Ltd. Outline and Restrictions of this Guide The following information required for the construction of Preserved

More information

Steve Brinkman Alain Pinel Realtors 167 S San Antonio Road Los Altos, CA 94022 RE: Foundation Inspection for 162 Del Monte Ave. Los Altos, CA 94022

Steve Brinkman Alain Pinel Realtors 167 S San Antonio Road Los Altos, CA 94022 RE: Foundation Inspection for 162 Del Monte Ave. Los Altos, CA 94022 M G C O N S T R U C T O R S & E N G I N E E R S, I N C. I N S P E C T O R S E N G I N E E R S B U I L D E R S C A L I F O R N I A E N G I N E E R I N G A N D B U I L D I N G L I C E N S E A / B 6 4 2 0

More information

Asphalt Shingle Application Requirements

Asphalt Shingle Application Requirements Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt

More information

8/18/14. Introduction to. Framing. Terminology and Concepts

8/18/14. Introduction to. Framing. Terminology and Concepts 8/18/14 Introduction to Framing Terminology and Concepts Terminology: Framing Level Two points on exactly the same horizontal plane. Square Intersecting lines or faces that form an exact 90 angle. Plumb

More information