1 Hammarby Sjöstad Kv Lugnvattnet PV-Project: "Lysande" TECHNICAL DESCRIPTION PV System TENDER DOCUMENT Stockholm Created by: Jonas Hedström, Energibanken i Jättendal AB 1

2 Tender document for the purchase of a turn-key PV system for Familjebostäder AB; project "Lysande" at Kv Lugnvattnet in Hammarby Sjöstad, Stockholm Background Familjebostäder (The client) intends to install PV on a multi family building in Kv Lugnvattnet in Hammarby Sjöstad, Stockholm. The name of the project is "Lysande". The four storey high building has 8 apartments with a total area of 536 m 2 and common areas like attic, cellar and staircases of 362 m 2. Solar modules with a total peak power of roughly 25 kw will be installed on the house in essentially two separate installations on different surfaces of the building. (Background to the project is found in Appendix 1) 1. The façade installation (System A): 10 kw peak power is to be installed on the south oriented façade of the building in the form of a lamella structure. System A requires modules specially designed for the current project. 2. The roof installation (System B): 15 kw peak power is to be installed on the west, south and east facing parts of the roof on the building. System B can use standard modules. 1.1 The content of the tender The contract covers delivery, installation and commissioning of the two separated PV systems for "Lysande" including PV modules, a mounting solution for the roof installation (NOTE that the client provides a mounting solution for the lamella structured façade installation) and all electrical parts like inverters, DC- and AC-switches, cables etc. The bid shall also cover all other parts, which are necessary for the total function of the systems. The tender shall also cover the handling-over of the systems covered by documents, training, maintenance recommendations, service agreement and a commissioning protocol issued at the start of the operation. The delivery border between the PV and the electrical contractor is the AC-switch in close connection to inverters, which shall be included in the bid. NOTE that some details concerning delivery borders differs somewhat regarding mounting and electrical installations between System A and System B. 1.2 Codes All electrical installations shall be done according to Swedish codes, which in most cases follow the European standards (EN) and IEC. The mounting methods and material used shall follow the relevant building codes. All parts belonging to the PV system, i.e. PV modules, mounting components, cables etc., that after the installation become parts of the building shall meet all requirements given for the building itself. This refers to water tightness and weather resistance. The bidder shall contact Familjebostäder if there are any questions in this matter. 2. Description of the modules in two systems (A and B) 2.1. Introduction The following description of the two systems is intended to help the tendering company. All measures efficiencies and peak power figures shall be regarded as approximate. The bidder shall use the information provided in the attached drawings. Part 2 of this document is dealing with the modules to be used in the two systems. Mounting solutions are described in part 3 and electrical solutions in part 4. 2

3 2.2 PV modules in the lamella structure in front of the façade (System A) System A consists of a construction in galvanised steel built up half a meter in front of, but attached to the façade. The client is responsible for the design and installation of this framework (Appendix 2.). The modules intended to be used in System A must meet the measures given by the drawings and the following specifications: Figure Schematic drawing of the module to be used in the lamella structure (System A) The cells used in the modules shall be manufactured by poly-crystalline silicon and have a blue appearance The outer dimension of the module shall be mm. The thickness of the module shall be close to 10 mm, based on a laminate with two 4 mm tempered glass sheets plus cells and sufficient encapsulation The holes in the modules shall be made according to measures given by the client in order to make it possible to fit the modules directly to the steel framework The module shall be semitransparent, i.e. manufactured by lamination of separated cells in a transparent encapsulation between two sheets of glass cells with outer dimensions of 100 x 100-mm +/- 5 mm shall be used in each module. In case the bidder intends to use cells with dimensions like 4"x 4" (101,2 x 101,2 mm) the spacing between cells must be reduced from the 20 mm measure given in Appendix 2, according to the increase in cell dimensions in order to obtain a symmetric pattern of the cells in the module) The cells shall be connected in series in two strings with 11 cells in each string These two strings shall be connected in parallel internally in the module in such a way that the plus and minus terminal ends up at the short ends of the module The plus and minus terminal shall be terminated with a red and blue cable respectively, which are to be connected inside the laminate to the internal conductors. Cable area, length and insulation must be sufficient in the present application A by-pass diode shall be integrated in the laminat and connected between the plus and the minus terminal by means of a conductor, which is integrated in the laminate. TABLE A summary of the most important data for the System A modules. The peak power is based on an assumed encapsulated cell efficiency of 14 %. Module type Dimension (l w h) [mm] Module area [m 2 ] Peak Power per module [W] Number of modules Total module area [m 2 ] Peak power System A [kw] System A ,359 30, ,6 9, PV-modules in the roof installation (System B) System B shall be mounted on 3 surfaces on the roof. A condition for this installation is to use modules that are packed as dense as possible on the available surfaces on the roof. In a preliminary design modules with a width of 600 mm have been used in order to fit to the 3

4 distances between the folds in the tinned roof. The bidder can however use standard modules that fit the dimensions in Table as close as possible The colour of the frames and the backing of the modules shall be dark, preferably black The modules shall be manufactured with mono- or poly-crystalline silicon cells with a blue appearance The offered PV modules shall meet the ISPRA guidelines or equal specifications. TABLE Guideline when choosing the System B modules based on a preliminary design. The peak power is calculated on an assumed encapsulated cell efficiency of 14 % and a packing density of cells of 92,9 %, calculated from the outer dimensions of the module. Module type Dimension (l w) [mm] Module area [m 2 ] Peak Power per module [W] Number of modules Total module area [m 2 ] Peak power System B [kw] System B Ca ,72 93, ,7 15,83 3. Mounting 3.1 Introduction More or less detailed mounting solutions for the systems A and B are presented in the construction drawings. The mounting procedures provided in the bid shall consider all relevant aspects needed in order for the systems to fulfil the energy aspects as well as the building criteria; water tightness and weatherproof. 3.2 System A (Dimensions in Appendix 2) The PV modules shall be mounted on the steel construction provided by the client using the four holes in the modules and the threaded bolts, which are welded to steel construction The modules shall be attached with chromium-plated dome shaped nuts The glass shall be protected from cracking when the nuts are tightened by means of rubber washers on both sides of the module. 3.3 System B (Dimensions in Appendix 3 and 4) The tin roof is attached on boards that are nailed on a wooden framework. The distances between the folds in the roof are 600 mm The PV modules in system B shall be mounted with a suitable technique suggested by the bidder. Use preferably elements that can be attached to the folds in the roof. The client must approve the method. Methods that require holes through the roof will not be approved. 4. Electrical installation 4.1. Introduction The actual peak power for each system (A and B) will be based on the type of PV cells used. The necessary DC- and AC-switches will be hosted by the assigned space for the inverters. 4

5 The bid must be provided with information regarding the system voltage (DC) and number and type of inverters to be used. 4.2 Electrical installation - DC General requirements, DC-installation A sufficient number of the PV modules are connected in series to strings ending up in connection boxes. This is preferably done by using double insulated cables and suitable contacts for easy and safe installation. Connections of strings in parallel to module-blocks (if necessary) are done using connection boxes. The use of diodes and over-voltage protection etc is to be decided by the bidder as well as the location of these components. The module strings or blocks, are connected to the inverters using double insulated cables with sufficient thickness. It is recommended to use an UV-proof cable for exposed outdoor use. The cable is to be connected to a DC-switch in close connection to the corresponding inverter. One DCswitch is required for each inverter Electrical installation DC- System A The modules in the lamella structure are not provided with junction boxes or frames The bidder shall suggest a method for the dc-connection of the modules. Connection in series might take advantage of the U-shaped profiles that will be attached vertically and horizontally to the steel construction. These profiles can also be used when it is necessary to continue the series connection on another level in the lamella structure All DC-wiring shall end up in a weatherproof junction box mounted out of reach on the steel construction Another contractor is responsible for the DC connection between the above mentioned junction box and the DC breakers in the space in the cellar assigned to the inverters. The bidder shall connect the DC-cable to the input terminals on the DC breakers Electrical installation DC- System B Follow the information in (Compared to System A, the bidder is responsible for the DC connection between modules and inverters.) The bidder shall suggest a method to connected the modules in series The bidder shall connect the cable between the modules and the inverters The bidder shall suggest a feedthrough for the DC connection between the roof installation and the attic. The client must approve this feedthrough. 4.3 Electrical installation - AC General requirements, AC-installation The inverters shall deliver AC, single-phase, 230 V or three-phase, 400 V The name of the manufacturer, the nominal power and the efficiencies of the inverters shall be included in the bid The efficiencies of the inverter shall be given in the range from % of the nominal power. This specification of efficiency may use data from the manual of the inverter The bid shall include the AC-switches that allow the inverters to be separately disconnected for service without affecting the other inverters. One common ACswitch could be used with automatic fuses for each inverter. Such a solution will provide a correct break point, at the same time providing possibilities to disconnect 5

6 single inverters for service using the automatic fuse as a disconnect switch. The last mentioned suggestion might require a 3-phase AC-switch. The bidder can suggest several small single-phase inverters or one or several 3-phase inverters. In the case of several single-phase inverters it must be demonstrated how they can be symmetrically connected to the 3-phase grid. The delivery interface on the AC-side of the electrical installation is the outlet terminals of the AC-switches. Energy meters shall not be included in the bid AC-installation system A All inverters in system A will be installed in a space in the cellar stated by the client (Appendix 5). Limitations in the outer dimensions for the inverter are given in Appendix 5 and AC-installation system B All inverters in system B will be installed in a space in the attic stated by the client (Appendix 6). Limitations in the outer dimensions for the inverter are given in Appendix 5 and 7. For system B inverters a free wall is reserved with the following rough dimensions: H = 2100 mm, W = 1200 mm and with a free space in front of the wall of 1200 mm. 5. Data monitoring It must be included in the two systems some possibilities to collect operational data and present the produced power and energy on a display, located in the entrance of the building. This PV project will receive demonstration support through an EU-project, which means that some particular conditions regarding monitoring activities have to be considered. Data to be recorded include solar irradiance, ambient and cell temperature, current and voltage on DCside and AC-power to the grid. 5.1 The bid shall present the available options. 6. Documentation A detailed documentation covering all technical parts as well as its function, operation, location of components, maintenance, electrical layout etc, must be included in the bid. 6.1 Detailed drawings of the mounting structures shall be provided. 6.2 Detailed drawings of the electrical layout shall be provided. 6.3 A complete list of all components included in the system shall be provided 6.4 All components shall be well documented. 6.5 A list of all modules and their specific electrical data shall be included (measured peak power, Voc, Isc and IV-curves in addition if possible, handed over as an Excel-file.) 6.6 All modules shall also be marked with a number that also is provided in the list in During the installation of the modules, a drawing shall be produced showing the exact location of every module. 6.8 Operations and maintenance instructions in Swedish shall be delivered. 6.9 Documentation shall be delivered to the client, in 3 copies, one week prior to the start of operation of the two systems. 6

7 7. Installation and commissioning 7.1. Commissioning of the PV installation The commissioning shall include a measurement of the peak power of the two systems A qualified contact person that is present at the commissioning, approved by both he supplier and the client, shall be appointed Before the systems are officially handed over to the client, the function of each of the systems shall be tested and a protocol has to be filled in, showing that everything is working correctly The protocol shall present the result of the calibration measurement of the systems in the form of a power figure in kw, which will be the peak power of the systems It shall be agreed in advance how this can be done using natural sunlight and how deviations in cell temperature, irradiation and solar spectrum, compared to standard test conditions, will be adjusted for Commissioning of other related installations The contact person shall also examine the installations regarding workmanship, the risk of leakage in feedthroughs, electrical safety, documentation quality etc. 8. Service and warranties 8.1 General The bid shall include a proposal for a service contract, describing how the supplier (or someone else appointed by the supplier), in what time and to what cost faults will be corrected. As most problems are related to inverters, the procedure of repairing and exchanging inverters shall be indicated in particular. Will there be spare inverters at any Swedish representative? The bid shall also elaborate the problem with spare modules, due to the project specific modules in system A Components that show malfunction when commissioning the systems shall be replaced or repaired within one month If the cause of a problem cannot be detected by the local service personal, using the given maintenance instructions, than the contractor shall detect the problem In a warranty case, the contractor shall correct the problem within 3 month from the time that the client notified the contractor about the problem. 8.2 System warranty Warranty for the systems A and B shall be 2 years or more The warranty is activated if one of the systems is producing less than 90 % compared to the accepted initial value or if other electrical or mechanical parts of the system are deteriorating in such a way that a risk of operational danger or malfunction is obvious. 8.3 System A module warranty Warranty for the modules in system A shall be 5 years or more The warranty is activated if a system A module is producing less than 90 % compared to the accepted initial value It would be an advantage if the contractor kept a small stock of roughly 10 system A modules, that are expected to be produced in only a small series. If this stock of spare 7

8 modules will be finished, than it shall be negotiated how module deterioration can be made up for by other means. 8.4 System B module warranty Warranty for the modules in system B shall be 20 years or more The warranty is activated if a system B module is producing less than 90 % compared to the accepted initial value. 8.5 Inverter warranty Warranty for the inverters shall be 2 years or more The warranty is activated if the inverter is not working in a normal way. With normal means that it follows the maximum power point of the modules and produces a stable AC-current with conversion efficiency from DC to AC not lower than 90% of what is stated in the inverter documentation. 9. Other 9.1. Local regulations regarding disposal, transportation, parking of vehicles etc shall be followed by the PV-contractor during the installation phase. 9.2 Prices The price shall be given for the whole installation including commissioning and all other items specified in the tender In addition, separate price shall be given for the modules. It is an advantage in this demonstration project that the cost of mounting structures, inverters and other electrical parts are specified in the tender. Also note the display in section All prices shall be given in Euro The earliest possible delivery time shall be presented and conditions for delays and bank guarantees will be discussed during contract negotiations The bidder shall state the installation time, divided in the different activities including the monitoring system. The construction work on the building has already started and the installation of the PV systems will start in April The bidder shall provide a list with relevant reference installations (Building Integrated Photovoltaics, BIPV). 8

9 10. Appendices Appendix 1 Appendix 2 Appendix 3 Appendix 4 Appendix 5 Appendix 6 Appendix 7 Appendix 8 Demonstration project: Familjebostäder AB, Hammarby Sjöstad Kv Lugnvattnet, project Lysande A A30-61-L610 A E62-01-LK09 E60-01-L409 E66-01-L001 E62-55-L Summary In order to simplify the procedure of preparing as well as evaluating the tenders, the most important items have been summarised in the Table 11.1 below. The bidder may specify in each cell marked with the figure "1" or "2" in Table The bidder may specify in each cell marked with the figure "3" in Table 11.1 by adding longer warranty times than what is stated in the text. The bidder may specify the installation time in cells marked with the figure "4" in Table The bidder shall specify, accept and/or suggest in the last column in Table

10 11. Summary of the bid on the PV-installation "Lysande" at Kv Lugnvattnet Component Manufac turer, type, etc Price [Euro] Warran ties [years] Delivery time [weeks] Installa tion time [weeks] Nomin al power [W] Num ber of items Efficien cies [%] Accept all conditions (details in the text regarding colours, warranties, dimensions, efficiencies etc) 1 System A System B Codes Accept or comment? 2.1 PV modules system A PV modules system B Mounting modules system A Mounting modules system B Suggest method DC installation system A Suggest method DC installation system B Suggest method Inverters AC installation system A AC installation system B Monitoring Documentation, System A Documentation, System B Peak power of the system Suggest method 7.2 Inspection of installations Suggest contact person 8 Warranty requirements Accept? 9.1 Local regulations Accept? 9.4 Delayed delivery terms Accept? 9.5 Reference project Reference list 10

Your Sharp system will be supplied with one of the following sets of panels:

Your Sharp system will be supplied with one of the following sets of panels: Sharp3000 3kW Solar System Panel Specifications Your Sharp system will be supplied with one of the following sets of panels: Manufacturer Mono Or Poly Size (Watts) Panels Required To Achieve Minimum 3000

More information

GENERAL INSTALLATION MANUAL FOR EGING PV MODULES

GENERAL INSTALLATION MANUAL FOR EGING PV MODULES GENERAL INSTALLATION MANUAL FOR EGING PV MODULES PLEASE READ THIS MANUAL CAREFULLY BEFORE INSTALLING OR USING THE MODULES. PLEASE PASS ALONG THE ATTACHED USER MANUAL TO YOUR CUSTOMER. 1. INTRODUCTION This

More information

Installation Guide of Sunrise Solartech PV Modules. Term 2013. Contents. Purpose of this guide. General. Safety precaution for installing a solar

Installation Guide of Sunrise Solartech PV Modules. Term 2013. Contents. Purpose of this guide. General. Safety precaution for installing a solar Installation Guide of Sunrise Solartech PV Modules Term 2013 Contents Purpose of this guide General Safety precaution for installing a solar Photovoltaic system Product Identification Mechanical Installation

More information

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting 12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.

More information

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

What are the basic electrical safety issues and remedies in solar photovoltaic installations? What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic

More information

Lease Operations Guide

Lease Operations Guide Lease Operations Guide Table of Contents Table of Contents... 2 GENERAL SAFETY INSTRUCTIONS... 3 HOW DOES MY SOLAR SYSTEM WORK?... 4 System Components... 4 Where does the power go?... 5 What happens if

More information

Section III Schedule of Requirements TECHNICAL SPECIFICATIONS OF THE REQUIRED SYSTEMS

Section III Schedule of Requirements TECHNICAL SPECIFICATIONS OF THE REQUIRED SYSTEMS PART III TECHNICAL SPECIFICATIONS OF THE REQUIRED SYSTEMS I. GENERAL The objective of this specification is to describe a system which uses solar energy to produce electricity. For each site (lot) one

More information

ADDENDUM #1(BID PACKAGE # 3)

ADDENDUM #1(BID PACKAGE # 3) H2Engineering, Inc. 114 East Fifth Avenue Tallahassee, FL 32303 Phone 850.224.7922 Fax 850.224.5876 ADDENDUM #1(BID PACKAGE # 3) To: Jeff Williams From: Peter Lindstrom Co: Leon County Date: October 04,

More information

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings *** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not

More information

Long-term performance of photovoltaic modules Artur Skoczek

Long-term performance of photovoltaic modules Artur Skoczek 1 Long-term performance of photovoltaic modules Artur Skoczek 2 The European Solar Test Installation (ESTI) has the primary objective of providing the scientific and technological basis for a sound and

More information

TECHNICAL SPECIFICATIONS

TECHNICAL SPECIFICATIONS 1. Standards BOS Item / System I ii iii TECHNICAL SPECIFICATIONS Applicable BIS /Equivalent IEC Standards / Applicable MNRE Specifications Standard Description Standard Number Crystalline Silicon Terrestrial

More information

LN240(30)P-3-xxx (230-250W poly)

LN240(30)P-3-xxx (230-250W poly) LN240(30)P-3-xxx (230-250W poly) Why Linuo Modules? 100% EL testing before and after lamination 100% plus tolerance(0-+3%) 100% insured by CHUBB Exceptional performance under low solar irradiance imized

More information

SOLAR MODULES SOLARFLEX Polska Grupa Inwestycje Ekologiczne Sp. z o.o. PRODUCTS LINE of SOLARFLEX Price list

SOLAR MODULES SOLARFLEX Polska Grupa Inwestycje Ekologiczne Sp. z o.o. PRODUCTS LINE of SOLARFLEX Price list SOLAR MODULES SOLARFLEX Polska Grupa Inwestycje Ekologiczne Sp. z o.o. PRODUCTS LINE of SOLARFLEX Price list Nr Indeks Type of modules Set components Peak Power [Pmax] Net price 1 SOLARFLEX 36W Flex flexible

More information

THERMAL CHARACTERISTICS Nominal operating cell temperature(noct) [ C] 48,2±2 48 Temperature coefficient P MPP [%K] -0,41-0,47 Temperature coefficient I SC [%K] 0,05 0,04 Temperature coefficient U OC [%K]

More information

PHOTOVOLTAIC (PV) solar panels. Specification. Electricity - CE & ISO 9000 certified. 83W panel. 180W panel Maximum power:

PHOTOVOLTAIC (PV) solar panels. Specification. Electricity - CE & ISO 9000 certified. 83W panel. 180W panel Maximum power: PHOTOVOLTAIC (PV) solar panels Electricity - CE & ISO 9000 certified Photovoltaic solar panels convert sunlight into useful electricity. ZEDfabric supplies high quality mono-crystalline silicon cell PV

More information

READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY!

READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS MAY VOID YOUR WARRANTY! The main power to any existing system must be disconnected prior to the

More information

PV module safety qualification according to IEC 61730:2004 EN 61730:2007

PV module safety qualification according to IEC 61730:2004 EN 61730:2007 PV module safety qualification according to IEC 61730:2004 EN 61730:2007 TÜV Rheinland Immissionsschutz und Energiesysteme GmbH Renewable Energies January 2009 Version 2009-01-22 Overview The long term

More information

SECTION 13650 Photovoltaic (PV) Glass

SECTION 13650 Photovoltaic (PV) Glass SECTION 13650 Photovoltaic (PV) Glass PART 1 GENERAL 1.01 WORK TO BE PERFORMED A. Provide all labor, materials, tools, and equipment to complete the installation of the PV Glass system. B. Install, equip,

More information

2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE

2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE 2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE PAGE 1 OF 5 This Reference provides a very comprehensive list of aspects of a solar PV installation that could be reviewed, clarifying

More information

Outdoor 33.6W Dual Port Passive Power-over-Ethernet Midspan For External Security Cameras and Wireless Access Points

Outdoor 33.6W Dual Port Passive Power-over-Ethernet Midspan For External Security Cameras and Wireless Access Points Outdoor 33.6W Dual Port Passive Power-over-Ethernet Midspan For External Security Cameras and Wireless Access Points Features SELV Compliant No Detection Passive Injector Gigabit Compatible Full Protection

More information

White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5

White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5 White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code June 2015 Revision 1.5 Shalhevet Bar-Asher; SolarEdge Technologies, Inc. Bill Brooks, PE; Brooks Engineering LLC

More information

46120-F0 Solar Energy Training System

46120-F0 Solar Energy Training System 46120-F0 Solar Energy Training System LabVolt Series Datasheet Festo Didactic en 120 V - 60 Hz 06/2016 Table of Contents General Description 2 List of Equipment 2 List of Manuals 3 Table of Contents of

More information

33.6W Power over Ethernet Waterproof Adapter PoE Plus Single Port Injector for Outdoor Application

33.6W Power over Ethernet Waterproof Adapter PoE Plus Single Port Injector for Outdoor Application 33.6W Power over Ethernet Waterproof Adapter PoE Plus Single Port Injector for Outdoor Application Features Compliant with the IEEE802.3at Standard -40 to +60 C Temperature Range Diagnostic LEDs Full Protection

More information

ATS Overhead Table Shelf System INSTRUCTION MANUAL

ATS Overhead Table Shelf System INSTRUCTION MANUAL ATS Overhead Table Shelf System INSTRUCTION MANUAL ATS Overhead Table Shelf System Instruction Manual Warranty Newport Corporation warrants this product to be free of defects in material and workmanship

More information

Photovoltaic System Overcurrent Protection

Photovoltaic System Overcurrent Protection Photovoltaic System Overcurrent Protection Photovoltaic System Overcurrent Protection Introduction Solar Photovoltaic (PV) systems have, over the last fifty years, evolved into a mature, sustainable and

More information

Photovoltaic Solar Energy Unit EESFB

Photovoltaic Solar Energy Unit EESFB Technical Teaching Equipment Photovoltaic Solar Energy Unit EESFB Products Products range Units 5.-Energy Electronic console PROCESS DIAGRAM AND UNIT ELEMENTS ALLOCATION Worlddidac Member ISO 9000: Quality

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

SHARP SOLAR Frequently Asked Questions for PV Integrators Revised 05/04/2010

SHARP SOLAR Frequently Asked Questions for PV Integrators Revised 05/04/2010 SHARP SOLAR Frequently Asked Questions for PV Integrators Revised 05/04/2010 How do I determine the PTC rating of a module? PTC refers to PVUSA Test Conditions, which were developed to test and compare

More information

BB800 Off-Grid Solar System

BB800 Off-Grid Solar System BB800 Off-Grid Solar System KEY PRODUCT FEATURES Control Box & Charge Controller 1000W of Solar Panels 4x200Ah of SLA Batteries in series 2KW Inverter Output Power Solar Panel & Battery Mounting Our entry

More information

Solar Solutions and Large PV Power Plants. Oscar Araujo Business Development Director - Americas

Solar Solutions and Large PV Power Plants. Oscar Araujo Business Development Director - Americas Solar Solutions and Large PV Power Plants Oscar Araujo Business Development Director - Americas Solar Business of Schneider Electric The Solar Business of Schneider Electric is focused on designing and

More information

Checklist Testing and inspection without interconnection

Checklist Testing and inspection without interconnection Shams Dubai Checklist Testing and inspection without interconnection Version.0 AUGUST 205 TABLE OF CONTENTS Scope...5. PV PLANT AND INSPECTION DATA... 6 2 TESTING EQUIPMENT...7 3 DOCUMENTS... 8 3. Reference

More information

Replacing Fuel With Solar Energy

Replacing Fuel With Solar Energy Replacing Fuel With Solar Energy Analysis by Michael Hauke, RSA Engineering January 22, 2009 The Right Place for Solar Energy Harvesting solar energy at South Pole can reduce the fuel consumption needed

More information

YSmart Technology Co.,Ltd

YSmart Technology Co.,Ltd YSmart Technology Co.,Ltd GWV Series Grid Tie Microinverter User Manual The copyright of this user manual belong to YSmart TechnologyCompany Limited. Without the written permission of the copyright holder,

More information

Solar Kit. Complete solution to optimize your photovoltaic system

Solar Kit. Complete solution to optimize your photovoltaic system Solar Kit Complete solution to optimize your photovoltaic system April 2012 Mounting and selection quick guide On Grid Solar Kit rooftop installation INSTALLATION WITH OVERLAID SUB-STRUCTURE (A.1, A.2)

More information

PERMIT APPLICATION REQUIREMENTS FOR RESIDENTIAL ROOF MOUNTED PHOTOVOLTAIC SYSTEMS

PERMIT APPLICATION REQUIREMENTS FOR RESIDENTIAL ROOF MOUNTED PHOTOVOLTAIC SYSTEMS Butte County Department of Development Services PERMIT CENTER 7 County Center Drive, Oroville, CA 95965 Main Phone (530)538-7601 Permit Center Phone (530)538-6861 Fax (530)538-7785 FORM NO DBP-71 PERMIT

More information

DAVID WILSON LIBRARY

DAVID WILSON LIBRARY DAVID WILSON LIBRARY SOLAR PHOTO-VOLTAIC GENERATOR CLEAN GREEN ELECTRICITY, PRODUCED BY THE SUN TECHNICAL DETAILS Dr Hans Bleijs Department of Engineering University Road, Leicester LE1 7RH Tel. 0116 252

More information

Design qualification and type approval of PV modules

Design qualification and type approval of PV modules Design qualification and type approval of PV modules TÜV Immissionsschutz und Energiesysteme GmbH Test Centre for Energy technologies May 2003 Design qualification and type approval of PV-modules in accordance

More information

SOLAR ELECTRIC MODULE ES-124 & ES-62T Owners Manual and Installation Guide

SOLAR ELECTRIC MODULE ES-124 & ES-62T Owners Manual and Installation Guide SOLAR ELECTRIC MODULE ES-124 & ES-62T Owners Manual and Installation Guide circuit. Reverse connection will damage the module and may result in fire. CAUTIONS Solar electric modules produce DC electricity

More information

Building Integrated Photovoltaic (BIPV)

Building Integrated Photovoltaic (BIPV) Building Integrated Photovoltaic (BIPV) Jan-Willem Tolkamp, International Account Manager BIPV Solar power on buildings' conference, 20th October 2010 see it. feel it Index 1. From PV to BIPV 2. The BIPV

More information

How To Plan Out An Array Of Solar Panels

How To Plan Out An Array Of Solar Panels CITY OF DOWNEY COMMUNITY DEVELOPMENT, BUILDING AND SAFETY 11111 Brookshire Avenue Downey, CA 90241 562.904.7142 (www.downeyca.org) B SECTION 01/01/2011 EFFECTIVE DATE PHOTOVOLTAIC 032 FORM NUMBER 2013

More information

Design qualification and type approval of PV modules acc. to IEC 61215:2005 / IEC 61646:2008

Design qualification and type approval of PV modules acc. to IEC 61215:2005 / IEC 61646:2008 Design qualification and type approval of PV modules acc. to IEC 61215:2005 / IEC 61646:2008 TÜV Rheinland Immissionsschutz und Energiesysteme GmbH Renewable Energies 2009-01-22 January 2009 Design qualification

More information

GUIDELINES FOR INSTALLATION OF AIR CONDITIONING UNITS 174-180 PHILLIP STREET, SYDNEY

GUIDELINES FOR INSTALLATION OF AIR CONDITIONING UNITS 174-180 PHILLIP STREET, SYDNEY GUIDELINES FOR INSTALLATION OF AIR CONDITIONING UNITS 174-180 PHILLIP STREET, SYDNEY July 2008 1.0 SCOPE These guidelines describe the way in which air conditioning units shall be installed or replaced

More information

CSUN Crystalline Silicon PV Module Products Installation Manual (IEC Version)

CSUN Crystalline Silicon PV Module Products Installation Manual (IEC Version) CSUN Crystalline Silicon PV Module Products Installation Manual (IEC Version) ADD.:No.123, Focheng West Road, Jiangning Development Zone, Nanjing, China Code: 211100 TEL. : +86-25-52766666-6530/6728 FAX:

More information

Application Note - How to Design a SolarEdge System Using PVsyst

Application Note - How to Design a SolarEdge System Using PVsyst March 2015 Application Note - How to Design a SolarEdge System Using PVsyst As of version 5.20, PVsyst - the PV system design software - supports the design of SolarEdge systems. This application note

More information

Listed are common requirements that apply to existing solar installations when altered, added to or reconfigured.

Listed are common requirements that apply to existing solar installations when altered, added to or reconfigured. SOLAR ALTERATIONS REQUIREMENTS August 2015 These requirements address typical alterations to solar installations; they cannot address every scenario. In Victoria, an alteration to a solar installation

More information

Cross-beam scanning system to detect slim objects. 100 mm 3.937 in

Cross-beam scanning system to detect slim objects. 100 mm 3.937 in 891 Object Area Sensor General terms and conditions... F-17 Related Information Glossary of terms... P.1359~ Sensor selection guide...p.831~ General precautions... P.1405 PHOTO PHOTO Conforming to EMC

More information

EFFICIENT EAST-WEST ORIENTATED PV SYSTEMS WITH ONE MPP TRACKER

EFFICIENT EAST-WEST ORIENTATED PV SYSTEMS WITH ONE MPP TRACKER EFFICIENT EAST-WEST ORIENTATED PV SYSTEMS WITH ONE MPP TRACKER A willingness to install east-west orientated photovoltaic (PV) systems has lacked in the past. Nowadays, however, interest in installing

More information

Long sensing range. Most suitable for conveyor lines and parking lot applications. 10 m 32.808 ft (Red LED)

Long sensing range. Most suitable for conveyor lines and parking lot applications. 10 m 32.808 ft (Red LED) NX SERIES Compact Multi-voltage Photoelectric Power Supply Built-in Multi-voltage photoelectric sensor usable worldwide Conforming to ow Voltage and EMC Directive Multi-voltage The NX series can operate

More information

Emergency lighting units EM powerled

Emergency lighting units EM powerled M BASIC 1 W Combined emergency lighting Driver 1 4 W Product description Emergency lighting Driver for manual testing SEV for output voltage < 60 V DC ow-profile casing (21 x 30 mm cross-section) 5-year

More information

ANALYSIS 2: Photovoltaic Glass Replacement

ANALYSIS 2: Photovoltaic Glass Replacement ANALYSIS 2: Photovoltaic Glass Replacement Problem Identification Bridgeside II is designed to accommodate 80 percent lab space and 20 percent office space. Laboratory equipment can consume a considerable

More information

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU George CURCANU, Constantin ILINCA, Ilie SBORA ICMET Craiova, Romania, Calea Bucuresti 144, phone:

More information

Solar Power System Installation Manual

Solar Power System Installation Manual Solar Power System Installation Manual Power-Save Energy Co. 3940-7 Broad St. #200 San Luis Obispo, CA 93401 866 297 7192 FOR INSTALLATION PERSONNEL Please read this manual carefully before installing

More information

YINGLI SOLAR PV MODULES Installation and User Manual

YINGLI SOLAR PV MODULES Installation and User Manual YINGLI SOLAR PV MODULES Installation and User Manual Revision Date December 24, 2011 Applicable for IEC certified products This manual applies to photovoltaic modules ( PV modules, also commonly known

More information

FAQs-Main switchboard design criteria

FAQs-Main switchboard design criteria FAQs-Main switchboard design criteria Q: What is the Australian standard for main switchboards? Current Australian standard is AS/NZS 3439.1: 2002 originating from IEC 60439. The new series of standard

More information

TECHNICAL BRIEF. Commercial PV in Australia and New Zealand Using the Enphase Microinverter System

TECHNICAL BRIEF. Commercial PV in Australia and New Zealand Using the Enphase Microinverter System TECHNICAL BRIEF Commercial PV in Australia and New Zealand Using the Enphase Microinverter System 2015 Enphase Energy Inc. All rights reserved May 2015 Table of Contents Commercial PV in Australia and

More information

Type-Tested Power Distribution Board 8PT with Rear Busbars. sivacon

Type-Tested Power Distribution Board 8PT with Rear Busbars. sivacon Type-Tested Power Distribution Board 8PT with Rear Busbars sivacon The Obvious Solution for Global Challenges SIVACON Type-testing is one of today s important issues for low-voltage technology and will

More information

DELIVERING BUSINESS ENERGY GO GREEN AND SAVE MONEY

DELIVERING BUSINESS ENERGY GO GREEN AND SAVE MONEY DELIVERING BUSINESS ENERGY CO M M E R C I A L S O L A R S O LU T I O N S GO GREEN AND SAVE MONEY PAY LESS FOR YOUR ELECTRICITY WHAT YOU SAVE ENERGYAID MODEL HOW YOU GET LOW COST ELECTRICITY Green electricity

More information

Free electricity for your home, offices or factory with solar PV panels

Free electricity for your home, offices or factory with solar PV panels Free electricity for your home, offices or factory with solar PV panels Who we are Easy Being Green helps customers reduce their household s energy consumption by using energy saving products. Easy Easy

More information

Model Number Electrical Compatibility Module Connector Type. M250-60-2LL-S22 60 cell PV module MC-4 Type 2 Locking

Model Number Electrical Compatibility Module Connector Type. M250-60-2LL-S22 60 cell PV module MC-4 Type 2 Locking TECHNICAL BRIEF M250 Microinverter System Installation Planning The M250 Microinverter The Enphase M250 Microinverter is a powerful and efficient grid-tied microinverter. It is compatible with most 60-cell

More information

AJ s Technical Tips: Designing a Small Solar PV System Part IV; Selecting Wires for the System

AJ s Technical Tips: Designing a Small Solar PV System Part IV; Selecting Wires for the System AJ s Technical Tips: Designing a Small Solar PV System Part IV; Selecting Wires for the System A little while back Simon Nyukuri of Kitale wrote to ask me about sizing wires and cables for solar PV systems.

More information

1 GENERAL 4 2 DEFINITIONS 4 3 STANDARDS FOR INSTALLATION 4 4 LICENSING 5. 4.1 Extra Low Voltage (ELV) 5 4.2 Low Voltage (LV) 5

1 GENERAL 4 2 DEFINITIONS 4 3 STANDARDS FOR INSTALLATION 4 4 LICENSING 5. 4.1 Extra Low Voltage (ELV) 5 4.2 Low Voltage (LV) 5 TABLE OF CONTENTS 1 GENERAL 4 2 DEFINITIONS 4 3 STANDARDS FOR INSTALLATION 4 4 LICENSING 5 4.1 Extra Low Voltage (ELV) 5 4.2 Low Voltage (LV) 5 5 DOCUMENTATION 6 6 RESPONSIBILITIES OF ACCREDITED PERSON

More information

BRÖCKSKES D-VIERSEN PV1-F 4,0 mm BRÖCKSKES D-VIERSEN PV1-F 4,0 mm d d 2 2 C VDE-REG.-Nr. 8292 10/2009

BRÖCKSKES D-VIERSEN PV1-F 4,0 mm BRÖCKSKES D-VIERSEN PV1-F 4,0 mm d d 2 2 C VDE-REG.-Nr. 8292 10/2009 d BRÖCKSKES BRÖCKSKES D-VIERSEN D-VIERSEN PV1-F PV1-F 4,0 mm 4,0 2 mm VDE-REG.-Nr. 2 C 8292 10/2009 s - THE COMPANY DIN EN ISO 9001 More than 60 years of experience in temperature measurement and control

More information

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems A. General This Net Metering Standard for Customer-Owned Grid Connected Electric Generating Systems sets forth the

More information

We're with you... solar. Call 1800 332 332 today FOR THE LIFE OF THE SYSTEM YEAR WARRANTY * YEAR OLD BACKED BY CSR BRADFORD CSR A AUSTRALIAN COMPANY

We're with you... solar. Call 1800 332 332 today FOR THE LIFE OF THE SYSTEM YEAR WARRANTY * YEAR OLD BACKED BY CSR BRADFORD CSR A AUSTRALIAN COMPANY We're with you... FOR THE LIFE OF THE SYSTEM 25 YEAR WARRANTY * Electricity prices are predicted to continue to rise in the future. If you're serious about installing energy in your home, look no further

More information

Expedited Permit Process for PV Systems AC Module

Expedited Permit Process for PV Systems AC Module Module The Solar America Board for Codes and Standards (Solar ABCs) Expedited Permit Process provides a means to differentiate systems that can be permitted quickly and easily due to their similarity with

More information

Safety and Installation Instructions for AC Modules

Safety and Installation Instructions for AC Modules Safety and Installation Instructions for AC Modules United States and Canada Contents of this manual are subject to change without notice. For the latest guide please refer to www.sunpower.com/pvinstallguideacmodule

More information

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Project name: Customer: Address, location of the system: Serial number

More information

PV and the Electrical Code Page 1 PV and the Electrical Code

PV and the Electrical Code Page 1 PV and the Electrical Code PV and the Electrical Code Page 1 PV and the Electrical Code Canadian Solar Industries Association (CanSIA) PV and the Electrical Code Page 2 This course was prepared by the Canadian Solar Industries Association

More information

Application Note: String sizing Conext CL Series

Application Note: String sizing Conext CL Series : String sizing Conext CL Series 965-0066-01-01 Rev A DANGER RISK OF FIRE, ELECTRIC SHOCK, EXPLOSION, AND ARC FLASH This Application Note is in addition to, and incorporates by reference, the installation

More information

HORIZONTAL INSTALLATION

HORIZONTAL INSTALLATION THERMO/SOLAR Žiar s.r.o. MANUAL FOR INSTALLATION PV SUPPORTING FRAMES HORIZONTAL INSTALLATION Technical alternation reserved A1410 1 12/2014 CONTENT ORD.NO. PAGE Mounting information 3 Mounting, flat roof

More information

Solar Electric Power System Owner s Manual

Solar Electric Power System Owner s Manual GE Energy Solar Electric Power System Owner s Manual v4.2nmtr Safety...3 Documents...4 Congratulations...5 Principles of Operation...5 Measuring Your Power and Energy...7 Table of Contents Estimating Your

More information

INSTALLATION MANUAL FOR PV MODULES ENGLISH VERSION 01 - SEPTEMBER 2013. www.ldksolar.com

INSTALLATION MANUAL FOR PV MODULES ENGLISH VERSION 01 - SEPTEMBER 2013. www.ldksolar.com INSTALLATION MANUAL FOR PV MODULES ENGLISH VERSION 01 - SEPTEMBER 2013 1 Installation Manual ENGLISH 1. Introduction This manual contains information regarding the safe installation and handling of photovoltaic

More information

Contrast 2 LED. Performance Compactness Complete flexibility NEW

Contrast 2 LED. Performance Compactness Complete flexibility NEW NEW Contrast 2 LED High light output in a compact and discreet design with a wide choice of light effects created using different light distributions and accessories Performance Compactness Complete flexibility

More information

March 14, 2007. Installation of Bay, Bow and Garden Windows

March 14, 2007. Installation of Bay, Bow and Garden Windows March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed

More information

IKS. Profi. Photovoltaic Trainingsystem for vocational and advanced training. Photovoltaik

IKS. Profi. Photovoltaic Trainingsystem for vocational and advanced training. Photovoltaik Photovoltaic Trainingsystem for vocational and advanced training The Solar branch is one of the important growth market of the f u r t u r e. T h e number of jobs g r o w s, t h e d e m a n d o f specialists

More information

A99B Series Temperature Sensors

A99B Series Temperature Sensors FANs 125, 121, 930, 930.5 Product/Technical Bulletin A99 Issue Date 0615 A99B Series Temperature s The A99B Series Temperature s are passive PTC (Positive Temperature Coefficient) sensors. The A99B sensors

More information

Electrical Practices for Construction Work

Electrical Practices for Construction Work 1. Purpose Electrical Practices for Construction Work The purpose of this Code is to provide practical guidance and set minimum safety requirements for electrical practices on all construction sites in

More information

Information sheet. 1) Solar Panels - Basics. 2) Solar Panels Functionality

Information sheet. 1) Solar Panels - Basics. 2) Solar Panels Functionality 1) Solar Panels - Basics A solar cell, sometimes called a photovoltaic cell, is a device that converts light energy into electrical energy. A single solar cell creates a very small amount of energy so

More information

12-Volt Negative Ground Installation Instructions

12-Volt Negative Ground Installation Instructions 12-Volt Negative Ground Installation Instructions For Part Number: 1141, 1164, 1165, 1181 CAUTION!!! Before installing, please read the following important information... 1. The Ignitor is designed for

More information

Solar Photovoltaic (PV) Systems

Solar Photovoltaic (PV) Systems ARTICLE 690 Solar Photovoltaic (PV) Systems INTRODUCTION TO ARTICLE 690 SOLAR PHOTOVOLTAIC (PV) SYSTEMS You ve seen, or maybe own, photocell-powered devices such as night lights, car coolers, and toys.

More information

Prism Solar Installation Manual

Prism Solar Installation Manual This installation manual applies to the following Prism Solar bifacial glass/glass models: B265(L), B260, B255, B250, B245, B200, B150, HB180. IMPORTANT: Read these instructions and the Prism Solar Design

More information

Xenon HID Lighting System

Xenon HID Lighting System Automotive Safety Systems User Installation Manual Preface Specifications Thank you for purchasing NOVABLUE Xenon H.I.D. (High Intensity Discharge) vehicle lighting systems. Before installing this product,

More information

How To Mount An Ecosa Series Solar Panel

How To Mount An Ecosa Series Solar Panel (including PanelClaw ) This Guide is valid in North America only (ETL listed; conforms to UL Standard 1703) PanelClaw is a registered trademark of PanelClaw, Inc. SM-0050revA ELECTRICAL EQUIPMENT CHECK

More information

Dome Security Camera with IR night vision

Dome Security Camera with IR night vision Dome Security Camera with IR night vision EN INSTRUCTION MANUAL 1 Before you begin Limited Warranty Terms & Conditions Swann Communications warrants this product against defects in workmanship and material

More information

Application of photovoltaic s in the building and construction industry as a power generating facility

Application of photovoltaic s in the building and construction industry as a power generating facility Application of photovoltaic s in the building and construction industry as a power generating facility Matthew P. Peloso Science and Technology Business Services LLP 10 Gopeng Street, ICON #34-22 Singapore,

More information

DRM75A 230V 20/100A DIN rail single phase two wire energy meter

DRM75A 230V 20/100A DIN rail single phase two wire energy meter DRM75A 230V 20/100A DIN rail single phase two wire energy meter 1.1 Safety instruction 1.2 Foreword 1.3 Performance criteria 1.4 Specifications 1.5 Basic errors 1.6 Description 1.7 Dimensions 1.8 Installation

More information

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK Pressure monitoring equipment for oil-sf 6 bushings, type GOEK Installation and maintenance guide 5693 827-6 en, Rev. 3, 2002-01-30 This document must not be copied without our written permission, and

More information

Toroidal Conductivity Sensor

Toroidal Conductivity Sensor Instruction Sheet PN 51A-/rev.C June 2012 Toroidal Conductivity Sensor For additional information, please visit our website at www.emersonprocess.com/rosemountanalytical.com SPECIFICATIONS Wetted Materials:

More information

Anti-blackout system for grid connected solar installations (Solsafe concept)

Anti-blackout system for grid connected solar installations (Solsafe concept) Anti-blackout system for grid connected solar installations (Solsafe concept) General description The Solsafe concept is a system which will automatically switch from a grid feeding inverter connected

More information

Solar Power at Vernier Software & Technology

Solar Power at Vernier Software & Technology Solar Power at Vernier Software & Technology Having an eco-friendly business is important to Vernier. Towards that end, we have recently completed a two-phase project to add solar panels to our building

More information

Ontario Electrical Safety Code 25 th Edition/ 2012

Ontario Electrical Safety Code 25 th Edition/ 2012 Ontario Electrical Safety Code 25 th Edition/ 2012 Ted Olechna Director, Codes and Standard Chief Engineer 1 What I Will Cover ESA s role is as the regulator Highlight of 2012 Code changes The Code and

More information

User s Manual Before using the inverter, you need to read and save the safety instructions.

User s Manual Before using the inverter, you need to read and save the safety instructions. User s Manual Before using the inverter, you need to read and save the safety instructions. STI SERIES (STI200, STI300, STI500, STI700, STI1000) Power Frequency Pure Sine Wave Inverter The information

More information

SCHEDULE ' A' TECHNICAL SPECIFICATION FOR 11/22/33KV H.T.XLPE POWER CABLE FOR DISTRIBUTION NETWORK IN MAHARASHTRA (SPECIFICATION NO.

SCHEDULE ' A' TECHNICAL SPECIFICATION FOR 11/22/33KV H.T.XLPE POWER CABLE FOR DISTRIBUTION NETWORK IN MAHARASHTRA (SPECIFICATION NO. SCHEDULE ' A' TECHNICAL SPECIFICATION FOR 11/22/33KV H.T.XLPE POWER CABLE FOR DISTRIBUTION NETWORK IN MAHARASHTRA (SPECIFICATION NO.MM/I/HTXLPE/2006) MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO.LTD.

More information

ADM1TE 5/30A DIN rail single phase two wire energy meter

ADM1TE 5/30A DIN rail single phase two wire energy meter ADMTE 5/30A DIN rail single phase two wire energy meter. Safety instruction.2 Foreword.3 Performance criteria.4 Specifications.5 Basic errors.6 Description.7 Dimensions.8 Installation.9 Operating.0 Troubleshooting.

More information

IXOLAR TM High Efficiency SolarMD.

IXOLAR TM High Efficiency SolarMD. IXOLAR TM High Efficiency SolarMD. Description IXOLAR TM SolarMD is an IXYS product line of Solar Module made of monocrystalline, high efficiency solar cells. The IXOLAR TM SolarMD is an ideal for charging

More information

Vario-Series Accessories

Vario-Series Accessories Accessories and spare parts for GMW analogue panel meters and controllers Current Transformers pages 2-9 Shunt Resistors 10-11 Voltage Dividers 12 Power supply for indicator/controllers 13 Blanking Plates

More information

SOLAR PV SYSTEM MAINTENANCE GUIDE

SOLAR PV SYSTEM MAINTENANCE GUIDE SOLAR PV SYSTEM MAINTENANCE GUIDE GUYANA HINTERLANDS STAND-ALONE SOLAR PV INSTALLATIONS IMPROVING HEALTH FACILITY INFRASTRUCTURE (IHFI) GUYANA CONTRACT NO. EPP-I-00-03-00008-00, TASK ORDER 07 APRIL 2013

More information

245-310 W POWER OUTPUT RANGE

245-310 W POWER OUTPUT RANGE Mono Multi Solutions THE OPTIMIZED SOLUTION COMPTIBLE WITH MOST TRIN MODULES Safer Solar Panel-level disconnect to remotely deactivate modules rc, fire and safety hazard mitigation 245-310 W POWER OUTPUT

More information

Romana Brentgens / photon-pictures.com (2)

Romana Brentgens / photon-pictures.com (2) science & technology inverters test Simple design both inside and out: The results of thermographic imaging were impressive there were only two areas where temperatures were elevated, but they were still

More information

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters 8 Appendix 4 of BS 7671 by Mark Coles Appendix 4, Current-carrying capacity and voltage drop for cables and flexible cords, has seen significant changes with the publishing of BS 7671:2008. This article

More information