Start display at page:

Download "Works Approval Conditions 1 General"

Transcription

1

2

3 Works Approval Conditions 1 General 1.1 Interpretation In the Works Approval, definitions from the Protection Act 1986 apply unless the contrary intention appears In the Works Approval, unless the contrary intention appears: Act means the Protection Act 1986; AS/NZS means the Australian Standard AS/NZS Water Quality Sampling Guidance of the Design of sampling programs, sampling techniques and the preservation and handling of samples; AS/NZS means the Australian Standard AS/NZS Water Quality Sampling Guidance on sampling of waste waters; annual period means the inclusive period from 1 April until 31 March in the following year; CEO means Chief Executive Officer of the Department of Environment Regulation; CEO for the purpose of correspondence means: Manager Licensing (Waste North) Department of Environment Regulation Locked Bag 33 Cloisters Square PERTH WA 6850 Telephone: (08) Facsimile: (08) industry.regulation@der.wa.gov.au; code of practice for the storage and handling of dangerous goods means document titled Storage and handling of dangerous goods: Code of Practice published by the Department of Mines and Petroleum, as amended from time to time; Commissioning means the process of operation and testing that verifies the works and all relevant systems, plant, machinery and equipment have been installed and are performing in accordance with the design specification set out in the works approval application; dangerous goods has the meaning defined in the Dangerous Goods Safety (Storage and Handling of Non-explosives) Regulations 2007; environmentally hazardous material means material (either solid or liquid raw materials, materials in the process of manufacture, manufactured products, products used in the manufacturing process, by-products and waste) which if discharged into the environment from or within the premises may cause pollution or environmental harm. Note: ly hazardous materials include dangerous goods where they are stored in quantities below placard quantities. The storage of dangerous goods above placard quantities is regulated by the Department of Mines and Petroleum; NATA means the National Association of Testing Authorities, Australia; Protection Act 1986 Page 2 of 6 Works Approval: W5763/2014/1 File No: DER2014/ IRLB_TI0674 v2.8

4 NATA accredited means in relation to the analysis of a sample that the laboratory is NATA accredited for the specified analysis at the time of the analysis; Premises means the area defined in the Premises Map in Schedule 1 and listed as the Premises address on page 1 of the Works Approval; Schedule 1 means Schedule 1 of this Works Approval unless otherwise stated; Works Approval means this Works Approval numbered W5763/2014/1 and issued under the Act; and Works Approval Holder means the person or organisation named as the Works Approval Holder on page 1 of the Works Approval Any reference to an Australian or other standard in the Works Approval means the relevant parts of the standard in force from time to time during the term of this Works Approval Any reference to a guideline or code of practice in the Works Approval means the current version of the guideline or code of practice in force from time to time, and shall include any amendments or replacements to that guidelines or code of practice made during the term of this Works Approval. 1.2 General conditions The Works Approval Holder shall construct the works in accordance with the documentation detailed in Table 1.2.1: Table 1.2.1: Construction Requirements 1 Document Parts Date of Document Works Approval Application Form All 18 September 2014 Works Approval Application, Lot 228 Buckleys Road, Broome, Shire of Broome. RES Jeremy Hall, Waste Coordinator Electronic subject: RE: Shire of Broome works approval application liquid waste facility. Dated 20 November 2014 and authored by Jeremy Hall, Waste Coordinator, Shire of Broome All, including Drawings and Appendices 17 September 2014 All 20 November 2014 Note 1: Where the details and commitments of the documents listed in condition are inconsistent with any other condition of this works approval, the conditions of this works approval shall prevail The Works Approval Holder, except where storage is prescribed in section 1.3, shall ensure that environmentally hazardous materials are stored in accordance with the Code of Practice for the Storage and handling of dangerous goods The Works Approval Holder shall undertake commissioning in accordance with the commissioning plan titled Commissioning Plan Liquid Waste Facility Lot 228 Buckleys Road The Works Approval Holder shall commission the Liquid Waste Facility for a period not exceeding 4 months. 1.3 Premises operation There are no specified conditions relating to Premises operation in this section. Protection Act 1986 Page 3 of 6 Works Approval: W5763/2014/1 File No: DER2014/ IRLB_TI0674 v2.8

5 2 Emissions There are no specified conditions relating to emissions in this section. 3 Monitoring The Works Approval Holder shall ensure that: (a) all wastewater sampling is conducted in accordance with AS/NZS and AS/NZS ; and (b) all laboratory samples are submitted to and tested by a laboratory with current NATA accreditation for the parameters being measured. 4 Improvements There are no specified conditions relating to improvements in this section. 5 Information 5.1 Reporting The Works Approval Holder shall submit a compliance document to the CEO, following the construction of the works and prior to commissioning of the same The compliance document shall: (a) certify that the works were constructed in accordance with the conditions of the Works Approval; and (b) be signed by a person authorised to represent the Works Approval Holder and contain the printed name and position of that person within the company The Works Approval Holder shall submit a commissioning report for the Liquid Waste Facility to the CEO within 4 weeks of the completion of commissioning The Works Approval Holder shall ensure the commissioning report includes; (a) (b) (c) (d) a list of any original monitoring reports submitted to the Works Approval Holder from third parties for the commissioning period; a summary of the environmental performance of the Liquid Waste Facility as installed, against the design specification set out in the works approval application; a review of performance against the works approval conditions; and where they have not been met, measures proposed to meet the design specification and/or works approval conditions, together with timescales for implementing the proposed measures. Protection Act 1986 Page 4 of 6 Works Approval: W5763/2014/1 File No: DER2014/ IRLB_TI0674 v2.8

6 5.2 Notification The Works Approval Holder shall ensure that the parameters listed in Table are notified to the CEO in accordance with the notification requirements of the table. Table 5.2.1: Notification requirements Condition or table Parameter Notification requirement Format or form (if relevant) Commencement of commissioning 7 days prior to start None Completion of commissioning 7 days after completion specified Protection Act 1986 Page 5 of 6 Works Approval: W5763/2014/1 File No: DER2014/ IRLB_TI0674 v2.8

7 Schedule 1: Maps Premises map The Premises is shown in the map below. The pink line depicts the Premises boundary. Protection Act 1986 Works Approval: W5763/2014/1 File No: DER2014/ Page 6 of 6 IRLB_TI0674 v2.8

8 Decision Document Protection Act 1986, Part V Proponent: Shire of Broome Works Approval: W5763/2014/1 Registered office: 27 Weld Street BROOME WA 6725 Premises address: Shire of Broome Liquid Waste Facility Reserve Lot 228 Buckleys Road WATERBANK WA 6725 Being Lot 228 on Plan Issue date: Thursday, 26 February 2015 Commencement date: Monday, 2 March 2015 Expiry date: Sunday, 1 March 2020 Decision Based on the assessment detailed in this document the Department of Environment Regulation (DER), has decided to issue a Works Approval. DER considers that in reaching this decision, it has taken into account all relevant considerations and legal requirements and that the Works Approval and its conditions will ensure that an appropriate level of environmental protection is provided. Decision Document prepared by: Carmen Standring Licensing Officer Decision Document authorised by: Steve Checker Manager Licensing Protection Act 1986 Page 1 of 18

9 Contents Contents 2 1 Purpose of this Document 2 2 Administrative summary 3 3 Executive summary of proposal and assessment 4 4 Decision table 6 5 Advertisement and consultation table 15 6 Risk Assessment 16 Appendix A 17 1 Purpose of this Document This decision document explains how DER has assessed and determined the application and provides a record of DER s decision-making process and how relevant factors have been taken into account. Stakeholders should note that this document is limited to DER s assessment and decision making under Part V of the Protection Act Other approvals may be required for the proposal, and it is the proponent s responsibility to ensure they have all relevant approvals for their Premises. Works approval and licence conditions DER has three types of conditions that may be imposed on works approvals and licences. They are as follows; Standard conditions (SC) DER has standard conditions that are imposed on all works approvals and licences regardless of the activities undertaken on the Premises and the information provided in the application. These are included as the following conditions on works approvals and licences: Works approval conditions: , 1.2.1, 1.2.2, and Licence conditions: , , and For such conditions, justification within the Decision Document is not provided. Optional standard conditions () In the interests of regulatory consistency DER has a set of optional standard conditions that can be imposed on works approvals and licences. DER will include optional standard conditions as necessary, and are likely to constitute the majority of conditions in any licence. The inclusion of any optional standard conditions is justified in Section 4 of this document. Non standard conditions (NSC) Where the proposed activities require conditions outside the standard conditions suite DER will impose one or more non-standard conditions. These include both premises and sector specific conditions, and are likely to occur within few licences. Where used, justification for the application of these conditions will be included in Section 4. Protection Act 1986 Page 2 of 18

10 2 Administrative summary Administrative details Application type Activities that cause the premises to become prescribed premises Works Approval New Licence Licence amendment Works Approval amendment Category number(s) 61 Assessed design capacity 2,500 tonnes per annum Application verified Application fee paid Date: 21/11/2014 Date: 11/12/2014 Works Approval has been complied with Yes No N/A Compliance Certificate received Yes No N/A Commercial-in-confidence claim Yes No Commercial-in-confidence claim outcome N/A Is the proposal a Major Resource Project? Yes No Was the proposal referred to the Protection Authority (EPA) under Part IV of the Protection Act 1986? Yes No Is the proposal subject to Ministerial Conditions? Yes No Referral decision No: N/A Managed under Part V Assessed under Part IV Ministerial statement No: N/A EPA Report No: N/A Does the proposal involve a discharge of waste into a designated area (as defined in section 57 of the Protection Act 1986)? Yes No Department of Water consulted Yes No Is the Premises within an Protection Policy (EPP) Area Yes No If Yes include details of which EPP(s) here. Is the Premises subject to any EPP requirements? Yes No If Yes, include details here, eg Site is subject to SO 2 requirements of Kwinana EPP. Protection Act 1986 Page 3 of 18

11 3 Executive summary of proposal and assessment The Shire of Broome has applied to DER for a works approval to construct a category 61 Liquid Waste Facility (LWF) at the Shire of Broome Waste Management Facility (WMF) at Lot 228 Buckleys Road, Broome. The LWF is required to treat grease-trap waste generated within the Shire of Broome. The WMF is a licenced Class II putrescible landfill that has two existing grease-trap waste ponds onsite. However, the WMF is approaching the end of its operational life, and closure of these ponds is required to allow the Shire to fully utilise available void space at the WMF. The Shire is therefore seeking approval to construct a new three tank Bioreactor LWF on the premises. Closure of the old ponds will involve transferring all liquid waste to the new Bioreactor LWF (once commissioned and approved to operate by DER) and conducting sampling and analysis of remnant sludge and pond construction materials (such as embankment walls) to determine appropriate disposal. The Bioreactor system involves three tanks in series that are aerated and automatically dosed with bacteria. Figure 1 shows the layout of the three tank Bioreactor system. The tanks contain anoxic/anaerobic zones and aerobic zones to ensure biological nutrient removal. Each tank acts as a baffle to prevent short circuiting of inflows and retain solids for treatment. Figure 1: Typical layout schematic of the proposed three tank Bioreactor Automated bacteria dosing is applied to tanks 1, 2 and 3. Each tank will contain three industrial micro bubble diffusers set at a sub-surface level approximately 1.3m above the bottom of the tanks. Ambient air supply to all diffusers is via a 3.0kW Side Channel Blower that will supply 3,300L of air per minute to the diffusers in all three tanks. The bacteria product is automatically dosed at programmed times to tanks 1 to 3. The nitrogen cycle bacteria facilitate sufficient levels of aerobic and facultative bacteria in the Bioreactor to process the fats, oils and greases in the wastewater. These bacteria also reduce sludge volumes produced as part of the process. Treated water from the LWF will be used for dust suppression and irrigation onsite. The Shire of Broome is currently conducting rehabilitation trials on the landfill embankments, and it is envisaged that treated water will be suitable for irrigation of revegetated areas. The proposal to construct and operate a three tank Bioreactor LWF at the Shire of Broome WMF has been assessed as presenting a low risk to the environment. Emissions and discharges associated with the proposal have been identified as stormwater, dust, odour and discharges to land. The risk of these emissions, and the proponent s commitments to mitigate such risks, are discussed further in the Decision table below. Protection Act 1986 Page 4 of 18

12 Upon construction of the LWF, the Shire of Broome will be required to submit a construction compliance document and may then commence commissioning of the LWF. A Commissioning Plan has been submitted that details what steps will be taken to ensure the LWF is operating effectively. Commissioning is expected to take four to six weeks and includes: testing automatic dosing and blower systems; introducing liquid waste to the system (to achieve normal operating conditions) and allowing it to be processed through the bioreactor tanks; sampling and analysis of treated wastewater by a NATA certified laboratory; and providing documentary evidence of treated water quality to DER. There will be no discharges of treated wastewater during commissioning; all wastewater will be discharged to the existing grease-trap waste ponds onsite. Once commissioning has demonstrated that the LWF is treating the liquid waste to an acceptable standard, DER will then process an amendment to the Shire of Broome WMF operating licence (L6912/1997/11) to incorporate conditions as recommended in the Decision table and Appendix A below. The amendment will involve conversion of L6912/1997/11 to the new REFIRE format to incorporate existing licence conditions and new conditions relating to operation of the LWF. Protection Act 1986 Page 5 of 18

13 4 Decision table All applications are assessed in line with the Protection Act 1986, the Protection Regulations 1987, DER s Policy Statement - Limits and targets for prescribed premises (2006), and DER s Operational Procedure on Assessing Emissions and Discharges from Prescribed Premises. Where other references have been used in making the decision they are detailed in the decision document. Note: This licence is a non-refire licence. Where applicable, references have been made to the non-refire licence conditions. DECISION TABLE Works Approval / Licence section General conditions Condition number W = Works Approval L= Licence and or NSC Justification (including risk description & decision methodology where relevant) Construction has been included in the works approval requiring the Shire of Broome to commission the LWF in accordance with the Commissioning Plan submitted and has been included to limit the commissioning period of the LWF to four months. Reference documents General provisions of the Protection Act 1986 Existing licence conditions W1(a) W1(c) Operation Emission Description Emission: Stormwater potentially contaminated from spills or leaks of greasetrap waste from the facility. Spills or leaks may occur during transfers, or from rupture / overflow of treatment tanks. Impact: Contamination of surrounding land and surface water drainage systems. Potential impacts on ecology of soils and surface water from the addition of grease and oils. Controls: Stormwater will be directed away from the LWF via contours to reduce the risk of stormwater becoming contaminated during operations. Transfers of liquid waste from truck to tank will not occur during rainy periods. Waste transfers will take place over a hardstand area graded to a drain to capture any spills or leaks during transfers. The drain will comprise a blind sump with grate that will be pumped out prior to and after rain events. The LWF will be fenced off to prevent damage to tanks from vehicles on-site. Application supporting documentation Protection Act 1986 Page 6 of 18

14 DECISION TABLE Works Approval / Licence section Condition number W = Works Approval L= Licence or NSC Justification (including risk description & decision methodology where relevant) Risk Assessment Consequence: Minor Likelihood: Rare Risk Rating: Low Reference documents Regulatory Controls Existing licence conditions W1(a) to W1(c) are in place on the Shire of Broome WMF operating licence to manage stormwater on the premises. Residual Risk Consequence : Minor Likelihood: Rare Risk Rating: Low Emissions general W2 L1.3.1 (REFIRE condition) Descriptive targets and / or limits will be set through the licence, via a licence amendment, to manage odour emissions as well as treated water quality from the LWF, and therefore an regarding recording and investigation of exceedances of limits or targets will be included on the amended licence. N/A Point source emissions to air including monitoring Point source emissions to surface water including W2 and W3 N/A Construction and Operation No significant point source air emissions are expected from the construction or operation of the LWF. No specified conditions relating to point source emissions to air or the monitoring of these emissions are required to be added to the works approval or licence. W2 and W3 N/A Construction and Operation No significant point source emissions to surface water are expected from the construction and operation of the LWF. No specified conditions relating to point source emissions to surface water or the monitoring of these emissions are General provisions of the Protection Act 1986 General provisions of the Protection Act Protection Act 1986 Page 7 of 18

15 DECISION TABLE Works Approval / Licence section Condition number W = Works Approval L= Licence or NSC Justification (including risk description & decision methodology where relevant) monitoring required to be added to the works approval or licence Reference documents Protection (Unauthorised Discharges) Regulations 2004 Point source emissions to groundwater including monitoring Emissions to land including monitoring W2 and W3 N/A Construction and Operation There are no point source emissions to groundwater from the construction or operation of the LWF. No specified conditions relating to point source emissions to groundwater or the monitoring of these emissions are required to be added to the works approval or licence. W2 and W3 N/A Construction There will be no emissions to land during construction of the LWF. All treated wastewater produced during the commissioning period will be discharged to the existing liquid waste ponds, not to land. Monitoring of the discharge will be undertaken in accordance with the submitted Commissioning Plan and discharge to land will only commence once analysis of treated wastewater shows that treatment levels are compliant with National Water quality Management Strategy, Australian Guidelines for Sewerage Systems Effluent Management and once the WMF operating licence has been amended to allow discharges under licence conditions. No specified conditions relating to General provisions of the Protection Act 1986 Protection (Unauthorised Discharges) Regulations 2004 General provisions of the Protection Act 1986 Protection (Unauthorised Discharges) Protection Act 1986 Page 8 of 18

16 DECISION TABLE Works Approval / Licence section Condition number W = Works Approval L= Licence or NSC Justification (including risk description & decision methodology where relevant) emissions to land or the monitoring of such emissions are required to be added to the works approval. Operation DER s assessment and decision making for discharges to land during operation of the LWF are detailed in Appendix A. Reference documents Regulations 2004 Application supporting documentation Fugitive emissions W2 and W3 N/A Construction Emission Description Emission: There is potential for dust emissions during construction of the LWF from minor earthworks and vehicle movements. This is expected to be minimal as the area is already cleared and compacted. Construction involves assembling footings, tanks / screens, pipework, dosing systems and blowers. Impact: Dust emissions can be harmful to human health and the environment. Elevated total suspended particulates (TSP) can impact ambient environmental quality resulting in amenity impacts and can smother vegetation. Particulate matter that is less than 10 (PM 10 ) or 2.5 (PM 2.5 ) micrometres in diameter can be drawn deep into the lungs causing human health impacts.. Nearest sensitive receptor is located 800m west of the premises. Controls: Water carts will be used to minimise dust during construction. Construction phase will be visually monitored by the site supervisor and dust management measures (water cart) will be implemented should visible dust cross the premises boundary. The construction period is expected to be around one month. Risk assessment Consequence: Insignificant Likelihood: Possible Risk rating: Low General provisions of the Protection Act 1986 Protection (Unauthorised Discharges) Regulations 2004 Application supporting documentation Protection Act 1986 Page 9 of 18

17 DECISION TABLE Works Approval / Licence section Condition number W = Works Approval L= Licence or NSC Justification (including risk description & decision methodology where relevant) Regulatory Controls No conditions will be required on the works approval to manage dust. Licence condition A1 exists on operating licence to require the management of fugitive dust emissions from activities on the premises. Reference documents Residual risk Consequence: Insignificant Likelihood: Unlikely Risk rating: Low Licence condition A1 Operation There will be no dust emissions during operation of the LWF. Treated waste water from the LWF will be used for dust suppression as part of the landfill operations, and to irrigate rehabilitated sections of the landfill. The existing licence has conditions requiring monitoring and management of dust emissions from other activities at the site. Odour W2 L2.7.1 (REFIRE condition) N/A Construction There will be no odour emissions during construction of the LWF. No specified conditions relating to odour emissions are required to be added to the works approval. Operation Emission Description Emission: Odour emissions generated from the breakdown of organic matter (grease-trap waste) during processing and when performing waste transfers from truck to tanks. Impact: Nuisance odour emissions may interfere with the amenity, comfort and welfare of people in the local area. Nearest sensitive receptor is located 800m west of the premises. General provisions of the Protection Act 1986 Application supporting documentation Protection Act 1986 Page 10 of 18

18 DECISION TABLE Works Approval / Licence section Condition number W = Works Approval L= Licence or NSC Justification (including risk description & decision methodology where relevant) Controls: Bioreactor tanks will be enclosed. Proponent will monitor Bioreactor tanks daily to ensure the system is operating effectively. Tanks will be cleaned out annually to remove built up sand and grit, however, it is not anticipated desludging will be required due to the nature of the waste stream being processed (grease-trap waste). Reference documents Risk assessment Consequence: Minor Likelihood: Unlikely Risk rating: Low Regulatory Controls An amendment to Licence L6912/1997/11 will be processed to add for the management of odour emissions on the premises. Residual risk Consequence: Minor Likelihood: Unlikely Risk rating: Low Noise W2 N/A Construction and Operation There will be no additional noise emissions generated during construction and operation of the LWF. No specified conditions relating to noise emissions are required to be added to the works approval or the licence. Protection (Noise) Regulations 1997 Application supporting documentation Protection Act 1986 Page 11 of 18

19 DECISION TABLE Works Approval / Licence section Monitoring general Condition number W = Works Approval L= Licence W3.1.1 or NSC Justification (including risk description & decision methodology where relevant) Construction During commissioning of the LWF, the Shire of Broome will inspect the facility daily to check automatic dosing and bubble diffusers to ensure the facility is operating correctly. Laboratory analysis of the treated wastewater will be performed once wastewater levels are sufficient and normal operating conditions are reached. This is estimated to be once the facility achieves the capacity of the bioreactor tanks (45,000L). Parameters to be analysed include Biochemical Oxygen Demand (BOD), ph, Oil and Grease, Total Suspended Solids, Total Dissolved Solids, Total Nitrogen, Total Phosphorus, Sulfate has been included in the works approval to require wastewater sampling to be conducted in accordance with AS/NZS and all laboratory samples to be tested by a laboratory with current NATA accreditation. Reference documents N/A L3.1.1 and Operation During operation of the LWF, the Shire of Broome will be required to analyse the treated wastewater on a quarterly basis to ensure the treatment levels are effective and suitable for discharge to land will be included on the amended licence to require wastewater sampling to be conducted in accordance with AS/NZS and all laboratory samples to be tested by a laboratory with current NATA accreditation will also be included to require quarterly samples be taken at least 45 days apart. Monitoring of inputs and outputs L3.5.1 N/A Operation The Shire of Broome will be required to record and report volumes of liquid waste received at the LWF as well as volumes discharged (irrigated) to land. An will be added to the operating licence requiring the monitoring of inputs at the LWF. N/A Protection Act 1986 Page 12 of 18

20 DECISION TABLE Works Approval / Licence section Process monitoring Condition number W = Works Approval L= Licence or NSC Justification (including risk description & decision methodology where relevant) W3 N/A Construction and Operation No specified conditions relating to process monitoring are required to be added to the licence. Reference documents N/A Ambient quality monitoring Licence condition W3(a) Construction and Operation The existing Licence has conditions requiring the monitoring of groundwater below the landfill to detect any seepage. There are currently four monitoring locations around the landfill. Bores are sampled and analysed regularly for ph, EC, sulphate and a range of metals. The existing monitoring programme is considered sufficient to cover the monitoring of potential groundwater impacts from the LWF. There are no additional ambient quality monitoring conditions required to be added to the licence as a result of the operation of the LWF. General provisions of the Protection Act 1986 Meteorological monitoring W3 N/A Construction and Operation No specified conditions relating to meteorological monitoring are required to be added to the licence. N/A Improvements W4 N/A The proposal to construct a LWF at the Shire of Broome Waste Management Facility is for new infrastructure. As such, there is no requirement for Improvements to be included on the works approval or licence. N/A Information W5.1.1 W5.1.4 Licence condition G9(a) and (b) Construction Standard conditions and will require the submission of the compliance document prior to commissioning has been included in the works approval for the submission of a commissioning report 4 weeks post commissioning outlines information that must be included in the commissioning report. N/A Operation The existing licence requires submission of an Annual Report Protection Act 1986 Page 13 of 18

21 DECISION TABLE Works Approval / Licence section Condition number W = Works Approval L= Licence or NSC Justification (including risk description & decision methodology where relevant) which must include the reporting of any monitoring results required by the licence, assessment of groundwater quality and a summary of complaints. Reporting requirements also include submission of an Annual Audit Compliance Report. Reference documents A licence amendment will be processed to require reporting of volumes of treated effluent discharged to land as well as the results of analysis of treated effluent from the LWF. Licence Duration N/A N/A The proposed works have been assessed as presenting a low risk to the environment. The works approval will be issued for a period of five years. There are no issues that warrant the limiting of the works approval period. N/A Protection Act 1986 Page 14 of 18

22 5 Advertisement and consultation table Date Event Comments received/notes How comments were taken into consideration 22/12/2014 Application advertised in West Australian (or other relevant newspaper) No comments received N/A 9/2/2015 Proponent sent a copy of draft instrument No changes requested N/A Protection Act 1986 Page 15 of 18

23 6 Risk Assessment Note: This matrix is taken from the DER Corporate Policy Statement No Operational Risk Management Table 1: Emissions Risk Matrix Protection Act 1986 Page 16 of 18

24 Appendix A Emissions to land Operations A Bioreactor treatment system with the capacity to treat up to 2,500 tonnes per year will be constructed to treat grease-trap waste received at the Broome WMF. The treated wastewater will be used for dust suppression and irrigated to land as part of rehabilitation activities. Wastewater will be applied by water cart along main roads (unsealed) within the landfill and also on the capped, rehabilitated embankment faces of the landfill. Depth to groundwater has been measured to be from 7.25 to 12.4m below ground level from the five monitoring bores on the premises (in November 2013). The nearest surface water body is a wetland approximately 320m to the north of the WMF. The Shire will discharge treated wastewater to haul roads, stockpiles and faces of the landfill. The effluent discharge quality is anticipated to be consistent with National Water quality Management Strategy, Australian Guidelines for Sewerage Systems Effluent Management (Table 1). Table 1: Treated effluent quality Description Value (mg/l) Australian % of Guideline Guidelines* (mg/l) Biochemical Oxygen Demand (BOD) % Total Suspended Solids (TSS) % Total Dissolved Solids 960 N/A N/A Total Nitrogen (TN) % Total Phosphorus (TP) % Oil and Grease < % *Australian Guidelines for Sewerage Systems Effluent Management ANZECC The entire area of the landfill is around 12ha, and it is estimated that the Shire will discharge treated effluent relatively evenly to at least half of this area throughout the year (6ha). However it should be noted that during the dry season other areas of the landfill may also be irrigated. Soils at the Broome WMF, known as Pindan sands, have been assessed as Risk Category D as per Department of Water s Water Quality Protection Note 22 Irrigation with nutrient-rich wastewater (WQPN 22). Nutrient loading rate calculations show that the Shire will easily comply with annual nutrient loading rates recommended in WQPN 22 when irrigating 2,500 tonnes to land over an area of 6ha on the premises. Table 2 gives the estimated nutrient loading rates for irrigation of treated wastewater from the proposed LWF over a 6ha area. Table 2: Nutrient loading for 6 ha irrigation area Parameter Nitrogen Phosphorus WWTP 2,500 kl / year Irrigation area 6 ha Effluent quality 50 mg/l (worst case) 12 mg/l Nutrient Loading Total 20.8 kg/ha/year 5 kg/ha/year Guideline* 480 kg/ha/year 120 kg/ha/year *WQPN 22 Irrigation with nutrient-rich wastewater (DoW 2008). These guidelines refer to Risk Category D. Emission description Emission: Treated effluent discharged to the landfill and irrigation areas (rehabilitation sites). Impact: Water quality not meeting guidelines. Possible nutrient overloading to irrigation areas, or oily water impacting soils in the area. Protection Act 1986 Page 17 of 18

25 Controls: Quarterly monitoring of quality of treated wastewater to ensure compliance with Australian Guidelines. Regular inspections of the LWF to detect / repair any leaks or blockages and annual clean out of sand and grit build up in tanks. Recording areas irrigated and volumes applied to ensure recommended nutrient loading rates (as per WQPN 22) are met. Risk assessment Consequence: Minor Likelihood: Rare Risk rating: Low Regulatory controls A licence amendment will be processed upon receipt of the construction compliance document to allow discharges to land from the LWF under L6912/1997/11. Quarterly sampling and analysis of treated wastewater will be required under licence conditions. Wastewater treatment target levels and nutrient loading rate limits (based on WQPN 22) will also be included on the amended licence. The Shire of Broome will be required to record and report discharge volumes and the results of quarterly analysis of treated wastewater in the Annual Report. Residual risk Consequence: Insignificant Likelihood: Rare Risk rating: Low Protection Act 1986 Page 18 of 18

Works Approval Conditions 1 General

Works Approval Conditions 1 General Works Approval Conditions 1 General 1.1 Interpretation 1.1.1 In the Works Approval, definitions from the Environmental Protection Act 1986 apply unless the contrary intention appears. 1.1.2 In the Works

More information

LICENCE NUMBER: L8272/2008/2 FILE NUMBER: 2013/000545

LICENCE NUMBER: L8272/2008/2 FILE NUMBER: 2013/000545 WESTERN AUSTRALIA DEPARTMENT OF ENVIRONMENT REGULATION Environmental Protection Act 1986 Licensee: Nationwide Oil Pty Ltd Registered Office: Level 4, 441 St Kilda Road MELBOURNE VIC 3004 ACN: 066 383 364

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

Guidance on applying for approval of installation of a commercial onsite wastewater system

Guidance on applying for approval of installation of a commercial onsite wastewater system Guidance on applying for approval of installation of a commercial onsite wastewater system This factsheet is designed to assist you to complete an Application to construct or install an apparatus for the

More information

Temporary Batch Plants

Temporary Batch Plants Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government

More information

APPENDIX 4. Risk Tables

APPENDIX 4. Risk Tables APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The

More information

Package Treatment Plant Policy and Procedure

Package Treatment Plant Policy and Procedure Package Treatment Plant Policy and Procedure PURPOSE There has been increased interest in the use of package treatment plants for new development proposals in the County. Current review procedures are

More information

a guide for wastewater producers and wastewater treatment plant operators

a guide for wastewater producers and wastewater treatment plant operators Contingency plans April 2007 Contingency Plans a guide for wastewater producers and wastewater treatment plant operators Updated May 2009 * EPA 696/09: This guideline has been provided to help licensees

More information

Understanding Septic Tank Systems

Understanding Septic Tank Systems Understanding Septic Tank Systems Sewage and effluent can contain a variety of human disease-causing microorganisms and parasites. Disease can be spread to humans from this material by direct contact or

More information

31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE

31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE 31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE Edited 21/12/01 Wyong Shire Council has many non sewered areas that

More information

Model operating conditions. ERA 63 Sewage Treatment

Model operating conditions. ERA 63 Sewage Treatment Model operating conditions ERA 63 Sewage Treatment Version history Version Date Description of changes 1 21/05/2014 Original version. 1.1 05/06/2014 Page number correction and error in wording of condition

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes

More information

Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service

Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service Experts Review of Aerobic Treatment Unit Operation and Maintenance Bruce Lesikar Texas AgriLife Extension Service Overview Overview of Aerobic Treatment Units Installing for accessibility to system components

More information

Strategic Environmental Compliance and Performance Review. Industry monitoring. Department of Environment, Climate Change and Water NSW

Strategic Environmental Compliance and Performance Review. Industry monitoring. Department of Environment, Climate Change and Water NSW Strategic Environmental Compliance and Performance Review Industry monitoring Department of Environment, Climate Change and Water NSW Strategic Environmental Compliance and Performance Review Industry

More information

KAWERAU DISTRICT COUNCIL General Bylaw Part 9: On-site Wastewater Disposal Systems (2010)

KAWERAU DISTRICT COUNCIL General Bylaw Part 9: On-site Wastewater Disposal Systems (2010) KAWERAU DISTRICT COUNCIL General Bylaw Part 9: On-site Wastewater Disposal Systems (2010) Kawerau District Council General Bylaw Part 9: On-site Wastewater Disposal Systems (2010) Explanatory Statement

More information

Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills.

Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills. WQ-10 Best Management Practice (BMP) Water Quality Protection Guideline Secondary Containment Design Standards Fuel Storage on Construction Sites According to the EPA, the majority of water pollution in

More information

Improving on-site domestic wastewater treatment systems - West Coast Lagoons Project

Improving on-site domestic wastewater treatment systems - West Coast Lagoons Project Improving on-site domestic wastewater treatment systems - West Coast Lagoons Project West Coast Lagoons Project- Improving Karekare, Piha, North Piha and Te Henga stream water quality Council is offering

More information

TOWNSVILLE WATER Customer Service Standards

TOWNSVILLE WATER Customer Service Standards TOWNSVILLE WATER Customer Service Standards CONTENTS Townsville Water who are we? 3 What is the Customer Service Standard? 3 >> Does the Customer Service Standard apply to me? 3 >> What will Townsville

More information

Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events) 2015

Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events) 2015 Redland City Council Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events) 2015 Redland City Council Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events)

More information

at a disposal site for which a permit has been issued; or

at a disposal site for which a permit has been issued; or Version 1/19 June 2000 INTERPRETATION OF THE DEFINITION OF DISPOSAL SITES WITH REGARD TO THE ISSUING OF PERMITS FOR WASTE INCINERATORS, WASTE MANAGEMENT FACILITIES AND OTHER ALTERNATIVE WASTE DISPOSAL

More information

Shire of Coolgardie. Waste Water Services. Customer Service Charter for. Waste Water Services. Revision One Updated June 2014. Shire of Coolgardie

Shire of Coolgardie. Waste Water Services. Customer Service Charter for. Waste Water Services. Revision One Updated June 2014. Shire of Coolgardie Shire of Coolgardie Waste Water Services Customer Service Charter for Waste Water Services Shire of Coolgardie Irish Mulgar Drive, Kambalda Bayley Street, Coolgardie Revision One Updated June 2014 Postal

More information

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking

More information

APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS.

APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS. Document No: 16-02-12A Issue Date: 09 December 2014 APPLICATION KIT AND GUIDELINES FOR ORGANISATIONS SEEKING TO UNDERTAKE WORKS WITHIN ROAD RESERVE LOW COMPLEXITY WORKS (An approved Traffic Management

More information

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation

Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation Page 1 of 11 Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation This work is copyright. It may be reproduced in whole or in part for study or training purposes

More information

CHAPTER 62-740 PETROLEUM CONTACT WATER

CHAPTER 62-740 PETROLEUM CONTACT WATER CHAPTER 62-740 PETROLEUM CONTACT WATER 62-740.010 Declaration of Intent (Repealed) 62-740.020 Applicability 62-740.030 Definitions 62-740.040 General 62-740.100 Management Practices for Producers of PCW

More information

Ingredion ANZ Pty Ltd

Ingredion ANZ Pty Ltd Ingredion ANZ Pty Ltd 170 Epping Road, Lane Cove, NSW 2066 EPL: 518 Page 1 of 8 1. Purpose and Background POLLUTION INCIDENT RESPONSE The purpose of this Pollution Incident Response Management Plan (PIRMP)

More information

City of Mebane Wastewater Collection and Treatment Facility

City of Mebane Wastewater Collection and Treatment Facility City of Mebane Wastewater Collection and Treatment Facility For the Fiscal Year July 1, 2014 - June 30, 2015 City of Mebane Wastewater Collection and Treatment Facility For the Fiscal Year July 1, 2014

More information

Proposed Terms of Reference for EIA studies

Proposed Terms of Reference for EIA studies 1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

Waste Handling & Disposal

Waste Handling & Disposal Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Improper storage and handling of solid wastes can allow toxic compounds, oils and greases, heavy metals, nutrients, suspended

More information

MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8

MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8 MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8 ONSITE WASTEWATER TREATMENT FACILITIES REGULATION 1. Definitions a. Aggregate means a clean graded hard rock, volcanic rock,

More information

Standard terms and conditions

Standard terms and conditions Standard terms and conditions INTRODUCTION For the provision of a water service (Water Supply, Wastewater and Drainage) Under Section 73(2)(a) of the Water Services Act 2012, landowners may be entitled

More information

Florida Department of Environmental Protection

Florida Department of Environmental Protection Florida Department of Environmental Protection Background Mobile vehicle and equipment washing involves washing at a location where vehicles are based (such as a trucking company, warehouse, bus station,

More information

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF

More information

Public Health (Sewage and Wastewater Treatment and Disposal) Regulations 2014

Public Health (Sewage and Wastewater Treatment and Disposal) Regulations 2014 Public Health (Sewage and Wastewater Treatment and Disposal) Regulations 2014 His Excellency Tom Marsters Queen s Representative Order in Executive Council At Avarua, Rarotonga this day of 2014 Present:

More information

Essential Water. Customer Charter

Essential Water. Customer Charter Essential Water Customer Charter Who is Essential Water? Essential Water is a division of Essential Energy and provides water supply services to over 20,000 people in Broken Hill, Menindee, Sunset Strip

More information

ANNEX 2 Emergency / Pollution Incident Response Plan

ANNEX 2 Emergency / Pollution Incident Response Plan ANNEX 2 Emergency / Pollution Incident Response Plan Volume 5 of 5 Appendix 21.1 Annex 2 EPIRP Page 1 of 9 1 WIND FARM CONSTRUCTION ENVIRONMENTAL EMERGENCY / POLLUTION RESPONSE PLAN... 3 1.1 Policy...

More information

Sustainable Resource Management Ltd

Sustainable Resource Management Ltd 6.0 Predicted nvironmental Impacts 6. Stages and Impacts Considered An nvironmental Impact Analysis has been carried out whereby all the possible environmental, socio economic and health & safety aspects

More information

Paragraph 9 Exemption The reclamation or improvement of land

Paragraph 9 Exemption The reclamation or improvement of land The reclamation or improvement of land 1 INTRODUCTION This document provides guidance, definitions, operational policy and strategy with regard registering a paragraph 9 exemption under Schedule 1 of the

More information

MBJ Environmental Programmes

MBJ Environmental Programmes MBJ Airports Limited Environmental Policy The following is MBJ Airports Limited s (MBJ) Environmental Policy for Sangster International Airport (SIA): Integrate environmental management measures with planning,

More information

SECTION 6 EXISTING WASTEWATER MANAGEMENT SYSTEMS

SECTION 6 EXISTING WASTEWATER MANAGEMENT SYSTEMS SECTION 6 EXISTING WASTEWATER MANAGEMENT SYSTEMS This section will describe the Town s existing wastewater management systems. This includes on-site disposal systems and private collection systems. The

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION

ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION After concession is expired or at the end of its economic life, pipeline network and all associated structures are due for decommissioning

More information

Approval Services Unit

Approval Services Unit Approval Services Construction Management Plan Pro-Forma Commercial Properties Please complete the enclosed form and return to:- By Mail: Approval Services Unit City of Perth Council House 27 St Georges

More information

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES ADDITIONAL STUDIES 7.0 DISASTER MANAGEMENT PLAN It is presumed that the proposed mining process would be designed and engineered with all possible safety measures and standard code of practices. In spite

More information

Operational Audit and. Asset Management System Review. Shire of Coolgardie

Operational Audit and. Asset Management System Review. Shire of Coolgardie Shire of Coolgardie Operational Audit and Asset Management System Shire of Review Dowerin 2011 (Water Services Operating Licence) Water Services Operating Licence (Sewerage and Non-Potable Water) DRAFT

More information

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials E. HAZARDOUS MATERIALS An Environmental Site Assessment Phase I Update was performed on the subject properties by California Environmental Inc. in March 2000 1. This report is included in Appendix E of

More information

Additional Services Agreement. Part 3: Schedule of our requirements

Additional Services Agreement. Part 3: Schedule of our requirements Additional Services Agreement Part 3: Schedule of our requirements Schedule of our requirements Part A Water Services 1 All water services All connections to our water mains, including those used for construction

More information

Outdoor Storage of Raw Materials SC-33

Outdoor Storage of Raw Materials SC-33 Objectives Cover Contain Educate Reduce/Minimize Description Raw materials, by-products, finished products, containers, and material storage areas exposed to rain and/or runoff can pollute stormwater.

More information

A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS

A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS GEORGIA DEPARTMENT OF HUMAN RESOURCES ENVIRONMENTAL HEALTH SECTION A HOMEOWNERS GUIDE TO ON-SITE SEWAGE MANAGEMENT SYSTEMS March 12, 2002 WHAT IS AN ON-SITE SEWAGE MANAGEMENT SYSTEM An on-site sewage management

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site- Specific BMP Plans for projects. plan reviewers will use this checklist to review the Site-Specific

More information

GUIDANCE DOCUMENT FOR PREPARATION AND SUBMISSION OF ENVIRONMENTAL MANAGEMENT PLAN (EMP) 1.0 INTRODUCTION TO GUIDANCE DOCUMENT

GUIDANCE DOCUMENT FOR PREPARATION AND SUBMISSION OF ENVIRONMENTAL MANAGEMENT PLAN (EMP) 1.0 INTRODUCTION TO GUIDANCE DOCUMENT GUIDANCE DOCUMENT FOR PREPARATION AND SUBMISSION OF ENVIRONMENTAL MANAGEMENT PLAN (EMP) A. THE GUIDANCE DOCUMENT 1.0 INTRODUCTION TO GUIDANCE DOCUMENT Environmental Management Plan (EMP) translates the

More information

Asbestos Disposal in the Northern Territory

Asbestos Disposal in the Northern Territory Information on the requirements for the disposal of Asbestos in the Northern Territory Scope These guidance notes have been developed to assist industry, local government, consultants and other relevant

More information

Management of Environmental Risks and Emergencies. Compliance Audit Program

Management of Environmental Risks and Emergencies. Compliance Audit Program Management of Environmental Risks and Emergencies Compliance Audit Program 2012 State of NSW and Environment Protection Authority The State of NSW and the Environment Protection Authority (EPA) are pleased

More information

Basements and Deep Building Construction Policy 2014

Basements and Deep Building Construction Policy 2014 Basements and Deep Building Construction Policy 2014 APPROVAL Council / CEO 27 October 2014 VERSION NO: Version 1.0 TRIM REF: 14/67838 REVIEW 30/10/2019 RESPONSIBLE EXECUTIVE General Manager City Assets

More information

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations SWPPP for Park Operations 2 Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations Bordered by Lake Washington & Lake Sammamish, the City of Bellevue has more than 60 miles of streams,

More information

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT

MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public

More information

On Site Sewage System Maintenance Inspections. March 2011. Building and Development Branch Ministry of Municipal Affairs and Housing

On Site Sewage System Maintenance Inspections. March 2011. Building and Development Branch Ministry of Municipal Affairs and Housing On Site Sewage System Maintenance Inspections March 2011 Building and Development Branch Ministry of Municipal Affairs and Housing Introduction The Building Code Act, 1992 and Building Code (Ontario Regulation

More information

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING 1 TABLE OF CONTENTS 1.0 Introduction and Purpose 3 2.0 Description of Work 3 3.0 Site Supervisor/Foremen Responsibilities 4 4.0 Equipment

More information

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

City of Bakersfield Public Works Department Sewer System Management Plan December 2014 City of Bakersfield Public Works Department Sewer System Management Plan December 2014 C:\Users\hmayberry\Desktop\SEWER SYSTEM MANAGEMENT PLAN 2014.doc 1 Sewer System Management Plan Index: Section 1 Goals

More information

1.3 Wastewater and Ambient Water Quality

1.3 Wastewater and Ambient Water Quality 1.3 Wastewater and Ambient Water Quality Applicability and Approach...25 General Liquid Effluent Quality...26 Discharge to Surface Water...26 Discharge to Sanitary Sewer Systems...26 Land Application of

More information

WASTEWATER TREATMENT OBJECTIVES

WASTEWATER TREATMENT OBJECTIVES WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater

More information

Help protect our special places by maintaining your septic tank

Help protect our special places by maintaining your septic tank Help protect our special places by maintaining your septic tank BC3136 A septic tank guide Help protect our special places Rural Auckland is a special place, but the remoteness also means that many homes

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN FUCHS LUBRICANTS (AUSTRALASIA) PTY LTD 2 HOLLAND STREET WICKHAM NSW POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN ENVIRONMENTAL PROTECTION LICENCE No.10181 Pubic Version DOC REF:ENV228 ISSUE:1 DATE:21.11.13

More information

Summary of Environment and Social Impacts for Activates Associated with Petroleum Refining and the Storage of Petroleum Products

Summary of Environment and Social Impacts for Activates Associated with Petroleum Refining and the Storage of Petroleum Products Sub-sectoral and Social Guidelines Summary of and Social Impacts for Activates Associated with Petroleum Refining and the Storage of Petroleum Products Introduction: The following table should be read

More information

Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009

Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009 APPLICATION FOR ADDITION OF TRANSPORTED WASTES IN WASTEWATER TREATMENT FACILITIES Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009 This application is to be

More information

Application Form 2E. Facilities Which Do Not Discharge Process Wastewater

Application Form 2E. Facilities Which Do Not Discharge Process Wastewater United States Environmental Protection Agency Office of Water Enforcement and Permits Washington, DC 20460 EPA Form 3510-2E Revised August 1990 Permits Division Application Form 2E Facilities Which Do

More information

Spill Prevention, Control and Countermeasure (SPCC) Rule

Spill Prevention, Control and Countermeasure (SPCC) Rule Spill Prevention, Control and Countermeasure (SPCC) Rule Code of Federal Regulations Title 40 CFR Part 112 Training Guide for Oil and Fuel handlers on Farms 1 Purpose of SPCC Rule To prevent oil discharges

More information

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting

More information

SEBENICO ATSI COMPANY OVERVIEW

SEBENICO ATSI COMPANY OVERVIEW Capability Statement SEBENICO ATSI Sebenico ATSI in line with our Aboriginal principles will implement solid processes and good governance to bring together Indigenous and Non indigenous people to work

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan This environmental management plan outlines Red Bus Services objectives and strategies for protecting the environment. This plan sets out how Red Bus Services intends to comply

More information

Slide 1. Enviros Consulting Ltd

Slide 1. Enviros Consulting Ltd Slide 1 Regulation of Waste Management Activities Past, Present and Future! Steve Bell Technical Manager Waste Management Thursday, 26 July 2007 Presentation Aims An insight of where we have come from

More information

WORKING IN CONFINED SPACES GUIDELINES

WORKING IN CONFINED SPACES GUIDELINES WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...

More information

Proposed (Concrete Cutting And Drilling) Environmental Management Plan

Proposed (Concrete Cutting And Drilling) Environmental Management Plan SAMPLE ENVIRONMENTAL MANAGEMENT PLAN This EMP is designed for (Concrete Cutting and drilling), however you may insert your business activities with only minor changes needed. This EMP should become part

More information

SEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank.

SEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank. SEPTIC SYSTEMS Who Has A Septic System? Approximately 30 percent of Connecticut s population is served by on-site subsurface sewage disposal systems (a.k.a. septic systems). This means a large percentage

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN An Environmental Management Plan is prepared for construction phase, post construction phase (commissioning & operation) and for post project

More information

APPENDIX 2A. Shah Deniz Production Sharing Agreement Extract

APPENDIX 2A. Shah Deniz Production Sharing Agreement Extract APPENDIX 2A Shah Deniz Production Sharing Agreement Extract Shah Deniz Production Sharing Agreement Extract ARTICLE 26 - Environmental Protection and Safety 26.1 Environmental Standards Contractor shall

More information

Spill Prevention, Control & Cleanup SC-11

Spill Prevention, Control & Cleanup SC-11 Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Spills and leaks, if not properly controlled, can adversely impact the storm drain system and receiving waters. Due to

More information

Pollution Incident Response Management Plan (PIRMP)

Pollution Incident Response Management Plan (PIRMP) Pollution Incident Response Management Plan (PIRMP) For NSW Ports For Construction of Berth 103 Stage 2 Extension WATERWAY CONSTRUCTIONS PTY LTD ABN 74 061 311 395 Po Box 290, Annandale NSW 2038 TELEPHONE:

More information

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 The Montgomery County Dept. of Environmental Protection, in cooperation with the Dept. of Permitting Services and the Washington

More information

Oasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS

Oasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS Oasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS The evolution continues in decentralised wastewater technology... The Process Decentralised wastewater treatment systems are defined

More information

History of the SPCC Rule

History of the SPCC Rule 2010 SPCC Training SPCC Rule History of the SPCC Rule The SPCC plan is a document required under the clean water act (CWA) It became effective in 1972 and has changed little in 32 years. The rule was formally

More information

NASA Stennis Space Center Environmental Resources Document

NASA Stennis Space Center Environmental Resources Document 16.0 Major Environmental Considerations for Proposed Actions All construction, rocket testing, and operations that may potentially impact environmental media, such as air, water, land, aquatic and biotic

More information

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection

More information

Civil Engineering Sector Labour-Management Health and Safety Committee

Civil Engineering Sector Labour-Management Health and Safety Committee PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION SITES Civil Engineering Sector Labour-Management Health and Safety Committee July 2008 PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION

More information

Company Header POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. For [site name] [EPL number]

Company Header POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN. For [site name] [EPL number] Company Header POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN For [site name] [EPL number] Pollution Incident Response Management Plan for [insert site name] Contents [need to check correct page numbers]

More information

Code of practice for wastewater overflow management

Code of practice for wastewater overflow management Code of practice for wastewater overflow management For further information please contact: Information Officer Environment Protection Authority GPO Box 2607 Adelaide SA 5001 Telephone: (08) 8204 2004

More information

Homeowner s Guide to Maintaining a Sewage Treatment System

Homeowner s Guide to Maintaining a Sewage Treatment System Homeowner s Guide to Maintaining a Sewage Treatment System Warren County Combined Health District 416 South East Street Lebanon, OH 45036 513-695-1220 Sewage Treatment Systems Septic Tank and Soil Absorption

More information

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008 BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008 JBA Prepared by : John Barnett and Associates / SLR Consulting 7 Dundrum Business Park

More information

BY-LAW CONCERNING DISCHARGES AT PURIFICATION WORKS ON THE TERRITORY OF THE URBAN AGGLOMERATION OF MONTRÉAL

BY-LAW CONCERNING DISCHARGES AT PURIFICATION WORKS ON THE TERRITORY OF THE URBAN AGGLOMERATION OF MONTRÉAL VILLE DE MONTRÉAL BY-LAW RCG 08-041 BY-LAW CONCERNING DISCHARGES AT PURIFICATION WORKS ON THE TERRITORY OF THE URBAN AGGLOMERATION OF MONTRÉAL In view of article 17 of the by-law entitled Règlement sur

More information

Minerals Regulatory Guidelines MG5. Guidelines for miners: tailings and tailings storage facilities in South Australia

Minerals Regulatory Guidelines MG5. Guidelines for miners: tailings and tailings storage facilities in South Australia Minerals Regulatory Guidelines MG5 Guidelines for miners: tailings and tailings storage facilities in South Australia Mineral Resources Group Division of Minerals and Energy Resources Primary Industries

More information

The Fuel Storage Tank Regulations 2009

The Fuel Storage Tank Regulations 2009 The Fuel Storage Tank Regulations 2009 October 2009 ED/RO1/015 The Fuel Storage Tank Regulations Issued by: The Regulation and Supervision Bureau for the water, wastewater and electricity sector in the

More information

The Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below:

The Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below: Proposed Terms of Reference for EIA Study Objective: In order to identify the environmental impacts due to construction and operation of the proposed project and associated facilities, a study will be

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information

TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN

TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN 1. GENERAL TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN The main objective of the EIA study is to assess the positive and negative impacts likely to accrue

More information

THIS PAGE INTENTIONALLY LEFT BLANK

THIS PAGE INTENTIONALLY LEFT BLANK THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction

More information

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited

2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited (IV) Proposed Terms of Reference for EIA Studies Project Category Project Proponent Location Paraspani Thermal Power Plant (2x800 MW) Coal based Thermal Power Project A [1(d) Thermal Power Plant 500 MW]

More information

Improper storage of potential pollutants will increase the risk of water pollution that may occur because of spills.

Improper storage of potential pollutants will increase the risk of water pollution that may occur because of spills. WQ-3 Best Management Practice (BMP) Water Quality Protection Guideline Secondary Containment Design and Operation Standards Section 1. Introduction According to the EPA, the majority of water pollution

More information