1 Pole Guying More Complicated Than Meets the Eye NRECA TechAdvantage 2014 Presented by Jason Settle, P.E.
2 Pole Guying Strength of components NESC vs. RUS Guy Factor Grounding 2
3 Pole Guying Purpose Support fully loaded design tension of conductors Applied wind and ice load 3
4 The Components of a Guyed Structure Guy Attachment Guy Attachment Height Guy Pole Anchor Guy Lead 4
5 The strength of the guy-anchor assembly is dependent on: Strength of the guy wire de-rated to 90% of the RBS (NESC Table 261-1) Strength of the guy attachment including the bolt and washer Strength of the anchor and rod Holding power of the soil in which the anchor is installed Only as Strong as the Weakest component 5
6 Guy Hardware 6
7 Thimble-eye Bolt 7
8 Johnny Ball & Guy Strain Insulator 8
9 Guy Wire Strength Data 9
10 RUS Guy Assemblies & Strength Assembly Item Material E1.1 E1.1L E1.2 b Bolt, machine 5/8 (12,400 lbs) 3/4 (18,350 lbs) None d Washer, curved 3 square (7,800 lbs) v Guy attachment Standard (6,600 lbs) y Guy wire 3/8 SM (6,255 lbs) 4 square (14,200 lbs) Heavy Duty (8,500 lbs) 3/8 HS steel (9,720 lbs) None 90% of guy wire 7/16 SM (8,415 lbs) Total Guy Strength 6,255 lbs 8,500 lbs 8,415 lbs 10
11 11
12 RUS Standard Washer Allowed Load RUS standards allow no more than 910 pounds per square inch of compression for washers on wood poles and crossarms. 12
13 13
14 14
15 RUS Standard Distribution Anchor Assemblies Anchor Type Expanding Screw (Power Installed) RUS Designation Maximum Holding Power (lbs)* F1.8 8,000 F ,000 F ,000 F2.8 8,000 F ,000 F ,000 *Maximum Holding Power based on installation in Class 5 Soil 15
16 Types of Soils for Anchor Placement Class Description Soil Class Descriptions 1 Solid rock 2 Dense sand, hard silts, course gravel 3 Compact clay & gravel mixed, shale, hardpan 4 Compacted sand, clay-pan, compacted gravel 5 Loose sand, gravel & clay, compacted course sand 6 Clay loam, damp clay, compacted fine sand, loose course sand 7 Silt loam, loose sand fines, wet clay, miscellaneous fill 8 Swamp, saturated loam, marshland 16
17 Expansion Anchors Rating (pounds) 6,000 8,000 10,000 12,000 Item Anchor Rod F1.6 F1.8 F1.10 F1.4 x Anchor Rod 5/8 x 7 5/8 x 7 N/A N/A Thimble Eye x Anchor Rod N/A N/A 3/4 x 8 3/4 x 8 Twin Eye z Anchor (sq. in.)
18 Expansion (Bust) Anchors Un-expanded Anchor Expansion Tool Illustration courtesy of Hubble Power Systems (Chance) 18
19 Screw Anchors Single Helix Double Helix Illustration courtesy of Hubble Power Systems (Chance) 19
20 20
21 Spacing of Anchors 5 feet 5-ft for standard duty 8-ft for heavy duty 21
22 Guying Situations Change in conductor size New wire sagged against old wire Line angles Dead-ends Grade B Crossings Spans that exceed the ruling span by 150% Long crossings 22
23 Guy & Anchor Selection Depend on: Horizontal pull at the guy attachment Guy resultant tension in the down guy Soil type in which the anchor is installed Available materials and assemblies 23
24 Standard Guy and Anchor Assemblies Guys Anchors E1.1 ( 6,255 lbs) F1.6 (6,000 lbs) E1.1L (8,500 lbs)* F1.8 (8,000 lbs) E1.2 (9,720 lbs)* F1.10 (10,000 lbs) * 3/8 HS steel 24
25 Guy & Anchor Grade of Construction RUS requires Minimum Grade C on distribution Must match highest Grade of construction on pole Transmission underbuild Grade B Railroad, Limited Access Hwy Grade B 25
26 Type of Guy Loads Transverse Forces acting perpendicular to the line Wind blowing on ice loaded conductors Tension in the wire Longitudinal Forces acting parallel to the line Maximum loaded design tension 26
27 Deadend Guying Calculations Tension A,B,CΦ Height Neutral Height Guy Height (Hg) Guy Lead (Lg) 27
28 Dead-end guying Gh = Mt/Hg Gh = Horizontal pull at guy attachment Mt = Sum of moments due to tension in the wire Hg = Average guy attachment height NESC construction grade = C NESC loading district = Light Primary cond. = 1/0 ACSR 6/1, Neutral cond. = 2 ACSR 7/1 Pole height and class = 40 ft, Class 4, SYP Pole-top assembly = C5.71L (RUS Assembly) 28
29 *NESC Load factors for deadend guyed structures defined in Rule 250B Type of Loading Grade B Grade C Crossing Elsewhere Transverse wind Transverse wire tension Longitudinal load at dead-ends *Adapted from NESC Table 253-1, 2012 Edition 29
30 *NESC Load factors for Extreme Weather when applicable Type Loading Rule 250 C Extreme Wind Grade B Crossing Grade C Elsewhere Wind Loads All other loads Rule 250D Extreme ice with concurrent wind *Adapted from NESC Table 253-1, 2012 Edition Applied to NESC 250B load if a structure or its supported facilities exceed 60 feet above ground or water. 30
31 Transverse Wind Load for 1-ft of Conductor Conductor Physical Data Transverse Wind Name Size/Strand Dia. (in) RBS (lb) Light (lb/ft) Medium (lb/ft) Heavy (lb/ft) Sparate Raven Penguin Merlin 2 ACSR 7/1 1/0 ACSR 6/1 4/0 ACSR 6/1 336 ACSR 18/
32 Step 1: Moment Due to Tension (Mt) Mt = Σ(Dt Hc Ft) Mt = Moment due to tension in the wire DT = Fully loaded design tension DT = 50% RBS 1/0 ACSR = 0.50(4,380 lbs) = 2,190 lbs 2 ACSR = 0.50(3,640 lbs) = 1,820 lbs Hc = Height of conductor above grade (RUS C5.71L) Ft = NESC wire tension load factor = 1.10 (grade C) 32
33 Step 1: Moment due to tension (Mt) Wire DT(lb) x Hc (ft) x Ft (ft) = Mt(ft-lb) A-phase 2190 x 32.5 x 1.10 = 78,293 B-phase 2190 x 32.5 x 1.10 = 78,293 C-phase 2190 x 32.5 x 1.10 = 78,293 Neutral 1,820 x 28.5 x 1.10 = 57,057 Σ(Dt Hc Ft) = 291,936 Mt = 291,936 ft-lbs 33
34 Step 2: Horizontal Pull (Gh) Gh Mt Hg Hg = Height of guy attachment = ft (RUS drawing C5.71L) Mt = 291,936 ft-lbs Gh = 291,936/31.75 = 9,195 Gh = 9,195 lbs 34
35 Guy Resultant or Total Guy Load (Gr) Gr Gh Lg 2 Lg Hg 2 Gr = Guy resultant tension (lbs) Gh = Horizontal pull at guy attachment (lbs) Hg = Height of guy attachment (ft) Lg = Guy lead length (ft) 35
36 Guy Resultant for Example 1 (Equation Method for 1:1 Guy Lead) Gr Gh Lg 2 Lg Hg 2 Gr 9, lbs Total Guy Load (Gr) = 13,004 lbs 36
37 Guy Factors Gf Lg2Hg2 Lg Hg Gf = Guy Factor Lg = Guy lead length Hg = Guy attachment height Lg 37
38 Guy Factors Gf Gf Gf 15 1 to 1 2 to 3 1 to
39 Guy Resultant for Example 1 (Guy Factor Method) Gr Gh * Gf 1:1 Guy Lead Gr 9,195* ,001lbs 2:3 Guy Lead Gr 9,195* ,579 lbs 1:2 Guy Lead Gr 9,195* ,560 lbs 39
40 Guy Leads Specify and stake adequate guy leads Not based on truck setup Short guy leads can cause Significant increase in total guy load Pole buckling due to the vertical component of guy tension Buckling Guy Lead 40
41 Pole Buckling Short Guy Leads Small Pole Class Heavy Wire Tension Specify a larger class pole 41
42 Guy Factors Guy Lead (ft) Guy Attachment Height (ft) # # # # # # # #
43 43
44 Clearance from Guys to Other Conductors Adapted from NESC Table Bare Guy Wire Insulator Link Secondary and Neutral 6 inches 4.5 inches 12 kv Primary 6 inches 4.5 inches 25 kv Primary 10 inches 7.5 inches 44
45 Code Violation! 45
46 Grounding Anchor Guys and Span Guys Rule 215C2 All anchor guys and span guys shall be effectively grounded. Only EXCEPTION is to use a guy insulator Fiberglass guy strain insulators Johnny Balls used in the past Eliminated EXCEPTION for triplex service conductors Guys on secondary poles must be grounded Big change for many utilities Per Bulletin 1724E-153 RUS considers it to be nonstandard construction when guy wires are not effectively grounded. 46
47 RUS Use of Insulator Links RUS calls for insulator links on 12 kv systems when there is less than 15 inches of wood separating guy attachment and phase associated hardware. RUS also calls for the lower portion of the guy to be grounded. Thus it meets the requirements of 215C2 Insulator link used for two reasons 1. Increase BIL on the structure 2. Provide for increased spacing between phase conductors and ground conductors as one means of providing safety to lineman. 47
48 Guy on secondary pole must be grounded Guy must be grounded or have guy strain insulator 48
49 Grounded Guy Grounded guy near to phase associated hardware Susceptible to flashover from lightning Solution 1. Lower guy RUS says 18 inches 2. Install guy insulator Still ground the lower part of the guy Guy Attachment 49
50 Guy Insulator Link Common mistake is to assume the guy insulator link must extend past lower conductors Not a NESC requirement To achieve BIL goals 18 inches is long enough To achieve working space Some use 36 inches 50
51 Span Guys Span guy is grounded at structure At stub pole Grounding jumper from span guy to down guy RUS requires grounding nut in anchor eye 51
52 52
53 Pole Guying Verify/Know your material/inventory. Be careful of short guy leads RUS - insulate and ground Questions? 53
V.A PJM Design and Application of Overhead Transmission Lines 69kV and Above
V.A PJM Design and Application of Overhead Transmission Lines 69kV and Above These design criteria have been established to assure acceptable reliability of the bulk transmission system facilities. These
More informationRequirements for the Attachment of Communication Cable Facilities on PPL Poles
Page 99 of 137 Requirements for the Attachment of Communication Cable Facilities on Replaces: URS-3002 URS-3004 URS-101C-304 A-157649 Page 100 of 137 Reference Notes for Drawings: General 1. The term communication
More informationGUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
More informationSystem. Stability. Security. Integrity. 150 Helical Anchor
Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More informationSchedule-4(A3) Page 1 of 5. Specification No.: JPL/KWTL/A3 (Package-A3) To: Bidder's Name & Address
Specification : JPL/KWTL/A3 (Package-A3) Page 1 of 5 Tower Package (Package-A3) for 400 kv D/C (Quad Bundle) Karcham Wangtoo Abdullapur Line Part III associated with Karcham Wangtoo HEP Transmission System
More informationTransmission Foundations. helical piles and guy anchors for transmission structures. www.hubbellpowersystems.com
Transmission Foundations helical piles and guy anchors for transmission structures www.hubbellpowersystems.com Grid locked on your transmission job? Instant Foundation helical piles go places concrete
More informationWhen power interruptions happen.
When power interruptions happen. We know it s never a good time to have your power go out, so we work all year pruning trees and investing in our system to cut down on problems before they start. Outage
More informationComprehensive Design Example 2: Foundations for Bulk Storage Facility
Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently
More informationPRESTRESSED CONCRETE POLES The Solid Alternative to Wood
Prestressed Concrete Utility Poles U-1 PRESTRESSED CONCRETE S The Solid Alternative to Wood Lonestar Prestress concrete poles were developed to meet the expanding need of a supporting structure for; street,
More informationFigure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate
Addendum HELICAL PULLDOWN Micropile (HPM) Introduction The HPM is a system for constructing a grout column around the shaft of a standard Helical Screw Foundation (see Figure A1). To begin the process,
More informationCONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION
Page 1 of 11 ****This Standard Supercedes BECo CS2.13-2.3 & ComElectric OH Construction Manual, System Grounding Section, drawings CGND, GRDSUM, and C2**** 1.0 Bill of Materials GROUNDING AND BONDING POLE-MOUNTED
More informationStability. Security. Integrity.
Stability. Security. Integrity. PN #MBHPT Foundation Supportworks provides quality helical pile systems for both new construction and retrofit applications. 288 Helical Pile System About Foundation Supportworks
More informationReport on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars
Report on Wind Resistance of Signs supported by Glass Fiber Reinforced Concrete (GFRC) Pillars Prepared for US Sign and Fabrication Corporation January, 2006 SUMMARY This study found the attachment of
More informationAERIAL FIBER OPTIC CABLE PLACEMENT
Installation Practice IP003 Aerial Fiber Optic Cable Placement Rev.-June 2000 Page 1 of 6 AERIAL FIBER OPTIC CABLE PLACEMENT CONTENTS PARAGRAPH SCOPE...1 GENERAL PRECAUTIONS...2 GENERAL DESCRIPTION OF
More informationBUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE Toll Free Telephone Numbers Residential Services 800.454.3853 Commercial Services 800.653.5307 Utility Locating Company N.C. 800.632.4949 S.C. 888.721.7877
More informationENCE 4610 Foundation Analysis and Design
This image cannot currently be displayed. ENCE 4610 Foundation Analysis and Design Shallow Foundations Total and Differential Settlement Schmertmann s Method This image cannot currently be displayed. Strength
More information1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona
for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety
More informationTECHNICAL MEMORANDUM
TECHNICAL MEMORANDUM OCS Requirements TM 3.2.1 Prepared by: Signed document on file 09 July 09_ Xavier de Vimal Checked by: Signed document on file 10 July 09_ Richard Schmedes Approved by: Signed document
More informationThe minimum reinforcement for the stem wall is the placement of:
PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20
More informationEngineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.
TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may
More informationload on the soil. For this article s examples, load bearing values given by the following table will be assumed.
How Many Piers? By Gary Collins, P.E. A clear-cut guide to helical pier spacing Introduction Helical pier spacing is not an exact science. How many does it take to support a structure adequately or repair
More informationPlease check with your local inspection authority for any additional requirements before installation.
Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be
More informationSUPPLEMENT TO SPECIFICATIONS FOR ELECTRICAL INSTALLATIONS
SUPPLEMENT TO SPECIFICATIONS FOR ELECTRICAL INSTALLATIONS PRIMARY METER POLE ELECTRIC SYSTEM BULLETIN No. 753 JUNE 1993, 2 ND PRINTING APRIL 2002 (Supersedes issue dated March 1983 and incorporates Nov.
More informationInstallation Instructions Hustler 6-BTV Trap Vertical
Installation Instructions Hustler 6-BTV Trap Vertical ASSEMBLY 1. Check the package contents against the parts list on page 2. 2. WARNING. Installation of this product near power lines is dangerous. For
More informationActivity 2.3b Engineering Problem Solving Answer Key
Activity.3b Engineering roblem Solving Answer Key 1. A force of 00 lbs pushes against a rectangular plate that is 1 ft. by ft. Determine the lb lb pressure in and that the plate exerts on the ground due
More informationEMERGENCY HOME PROTECTION. Homeowner's Guide for Emergency Flood Control. Contents INTRODUCTION
EMERGENCY HOME PROTECTION Homeowner's Guide for Emergency Flood Control Contents Discussion or Section Page Number Introduction 3 Potential Flooding Periods 4 General Rules and Control Aids 5,6 Sandbags
More informationInternational Greenhouse Company
Greenhouse Foundation Design As with any building, a good solid foundation is crucial for the long term durability and functionality of your greenhouse. A weak foundation will cause your greenhouse to
More informationHendrix Spacer Cable
Hendrix Spacer Cable What is Spacer Cable? Covered Conductor Withstands temporary branch contact Eliminates temporary faults Protects wildlife Less clearance issues Compact Configuration Multiple Circuits
More informationDigital Energy ITI. Instrument Transformer Basic Technical Information and Application
g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER
More information5/1/2013. Topics. The challenge is to better maintain native characteristics of soils during and after construction
PIN Foundations Topics Applications Design and Construction Flow Control Credits www.pinfoundations.com Copyright 2008, Pin Foundations, Inc. Curtis Hinman WSU Extension Faculty, Watershed Ecologist chinman@wsu.edu
More informationPUMP JACK SYSTEM AND ACCESSORIES
Pump Jack Model # 2200 A low cost, easy to operate, safe, portable scaffolding built of rugged steel. It's perfect for shingling, siding, sheathing, insulating, painting, building, roofing, home repair
More informationIRRIGATION PUMPING Table of Contents - Section 900
IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS
More informationSECTION 16402 UNDERGROUND ELECTRIC SERVICE
SECTION 16402 UNDERGROUND ELECTRIC SERVICE PART 1 GENERAL 1.1 SUMMARY A. Description of System 1. Furnish all labor, materials, and equipment for below grade work external to buildings as required, and
More informationSpool Tie. RUS Accepted NOMENCLATURE GENERAL RECOMMENDATIONS. 11-40 (440) 461-5200 inquiries@preformed.com www.preformed.com
Spool Tie NOMENCLATURE RUS Accepted IDENTIFICATION TAPE SIX COLOR CODE TIE TUBE Tie Assembly: A Spool Tie Assembly consists of one metal tie component plus tie tube. Tie Tube: Each Spool Tie is supplied
More informationScrew Thread Design. Rev. 3-4-09
Screw Thread Design Screw Thread Fundamentals A screw thread is defined as a ridge of uniform section in the form of a helix on either the external or internal surface of a cylinder. Internal threads refer
More informationVertical Break Parallel (VBP) / Vertical Break Slant (VBS)
August, 2009 Vertical Break Parallel (VBP) / Vertical Break Slant (VBS) Type VBPA (Aluminum) / Type VBPC (Copper) Type VBSA (Aluminum) / Type VBSC (Copper) PASCOR Air Break Switch Technology PASCOR offers
More informationTS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING
TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET
More informationResidential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
More informationPOLE MOUNT SYSTEM-3 INSTALLATION
1 May 2014 POLE MOUNT SYSTEM-3 INSTALLATION The Pole Mount System-3 is an easy to install and flexible system designed to allow ONE SYSTEMS loudspeaker products to be mounted to pole structures. The only
More informationSTANDARD OPEN PATIO COVER
STANDARD OPEN PATIO COVER BUILDING & SAFETY DIVISION 201 E. LA HABRA BLVD. LA HABRA, CA 90631 62-90-9710 Call Before You Dig 1-800-227-2600 PLEASE NOTE: This information Bulletin is made available to assist
More informationThe Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space
The Stabilizer TM Supplemental support system for sagging beams and floor joists within a crawl space Pre-drilled holes in steel plate allow for connection to beam or floor joists. Benefits Levels and
More informationTransmission Silicone Insulators Line Post 69 kv to 161 kv
K-LINE INSULATORS LIMITED Catalogue T-LP Transmission Silicone Insulators Line Post 69 kv to 161 kv ISO9001 SAI GLOBAL FILE No. 000117 Transmission Silicone Insulators Line Post Today transmission lines
More informationINSTALLATION INSTRUCTIONS HUSTLER 4-BTV, 5-BTV TRAP VERTICAL WARNING INSTALLATION OF THIS PRODUCT NEAR POWER LINES IS DANGEROUS
INSTALLATION INSTRUCTIONS HUSTLER 4-BTV, 5-BTV TRAP VERTICAL WARNING INSTALLATION OF THIS PRODUCT NEAR POWER LINES IS DANGEROUS FOR YOUR SAFETY, FOLLOW THE INSTALLATION DIRECTIONS GENERAL DESCRIPTION:
More informationHow to Design Helical Piles per the 2009 International Building Code
ABSTRACT How to Design Helical Piles per the 2009 International Building Code by Darin Willis, P.E. 1 Helical piles and anchors have been used in construction applications for more than 150 years. The
More information6 RETROFITTING POST & PIER HOUSES
Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This
More informationPOLE MOUNT SYSTEM EX-3 INSTALLATION
May 2014 POLE MOUNT SYSTEM EX-3 INSTALLATION The Pole Mount System EX-3 is an easy to install and flexible system designed to allow ONE SYSTEMS loudspeaker systems to be mounted to pole structures. The
More informationEZ-48-3AB-125-35 Weather Station Mounting Tripod and Mast
EZ-48-3AB-125-35 Weather Station Mounting Tripod and Mast EZ-125-35M 35 Mast Extension (Optional) EZ-125-SK Stake Kit (Optional) EZ-46-3 Tar Pad Kit (Optional) EZ-GWA Guy Wire Kit (Optional) Ambient Weather
More informationBy SP Partners, LLC. www.rainbowatticstair.com INSTALLATION GUIDE. Prestige
By SP Partners, LLC www.rainbowatticstair.com INSTALLATION GUIDE Prestige IMPORTANT READ THIS FIRST Inspect stair for any damage prior to installation. Stair is NOT to be installed while home is under
More informationMOBILE HOME SERVICE REQUIREMENTS GAS
ELECTRIC AND GAS 1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL 4.0 REFERENCE MATERIAL 5.0 TYPICAL UNDERGROUND UTILITY LAYOUT 6.0 METER PAD DETAILS 7.0 GENERAL INSTALLATION PROCEDURES 8.0 PEDESTAL SPECIFICATIONS
More informationVeri*Lite Silicone Rubber Line Post Insulators for 15-69kV Applications
Veri*Lite Silicone Rubber Line Post Insulators for 15-69kV Applications Section 2-1 2 Warranty - Material Hubbell Power Systems, Inc. warrants all products sold by it to be merchantable (as such term is
More informationShaft- Mounted Speed Reducers
Torque Arm Design Considerations for Todd R. Bobak has worked in the gear industry for 15 years. He has held positions in technical service, design and development, and quality assurance. He is a product
More informationC O N V E Y O R C O M P O N E N T S C H A I N S B E L T S B E A R I N G S
C O N V E Y O R C O M P O N E N T S C H A I N S B E L T S B E A R I N G S January 2009 Issue 6 Valu Guide Brackets The Ultimate in Adjustability and Cost Savings Valu Guide brackets are part of a family
More informationRating when used as a weight carrying hitch without spring bars:
BOLT-TOGETHER WEIGHT DISTRIBUTING HITCH SYSTEM Rating when used as a weight distributing hitch with spring bars: Part Number 48051 4805 48053 48054 Max Tongue Weight 550 Ibs. 750 Ibs. 1000 Ibs. 1400 lbs.
More informationThe Verdura Wall check with your local building department
The Verdura Wall The Verdura Wall by Soil Retention Products, Inc of Carlsbad, California can be constructed as a gravity retaining structure or a geosynthetic reinforced segmental retaining wall, depending
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks
More informationMarch 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
More informationDynamic Load Testing of Helical Piles
Dynamic Load Testing of Helical Piles ANNUAL KANSAS CITY SPECIALTY SEMINAR 2014 JANUARY 10, 2014 Jorge Beim JWB Consulting LLC Pile Dynamics, Inc. Main Topics Brief description of the Dynamic Load Test
More informationDISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2. Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8
DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2 Kinds and Uses of Service... 2-1-1 and 2-1-2 Wye Network Area Maps Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8 Transformer Connections
More informationCeiling Mounted Folding Attic Ladders Installation Instructions
Ceiling Mounted Folding Attic Ladders Installation Instructions WARNING Before you start installing your new Louisville Ceiling Mounted Folding Attic Ladder, you must read and understand the following:
More information758 Heavy-duty Ratchet Guy Wire Cutter
INSTRUCTION MANUAL 758 Heavy-duty Ratchet Guy Wire Cutter Read and understand all of the instructions and safety information in this manual before operating or servicing this tool. Register this product
More informationTrundle Bed Plans (For Use Under Twin or Full-Size Standard Length Beds)
Bunk Beds Unlimited Trundle Bed Plans (For Use Under Twin or Full-Size Standard Length Beds) On the following pages we have included all of the necessary drawings and requirements for a Modified twin-size
More informationHelical Pier Foundation System U.S. Patents 5,011,336; 5,120,163; 5,213,448
Helical Pier Foundation System U.S. Patents 5,011,336; 5,120,163; 5,213,448 Technical Manual Contents Helical Pier Foundation System History Research and Development Advantages Theory of Foundation Anchor
More informationPOST AND FRAME STRUCTURES (Pole Barns)
POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:
More informationSECTION 02845 GUARDRAILS
SECTION 02845 GUARDRAILS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals necessary and repair, replace or install all types of guardrails as specified herein
More informationDesign of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges
7.7 Truss bridges Fig. 7.21 some of the trusses that are used in steel bridges Truss Girders, lattice girders or open web girders are efficient and economical structural systems, since the members experience
More information1 Town of Lyons Electrical Distribution System Design Standards
Town of Lyons Electrical Distribution System Material and Design INDEX 6.1 Design Criteria 6.11 Submissions 6.1.2 Method 6.1.3 Criteria 6.2 Specifications 6.2.1 Scope 6.2.2 General Requirements 6.2.3 Materials
More informationType of Force 1 Axial (tension / compression) Shear. 3 Bending 4 Torsion 5 Images 6 Symbol (+ -)
Cause: external force P Force vs. Stress Effect: internal stress f 05 Force vs. Stress Copyright G G Schierle, 2001-05 press Esc to end, for next, for previous slide 1 Type of Force 1 Axial (tension /
More informationc. Borehole Shear Test (BST): BST is performed according to the instructions published by Handy Geotechnical Instruments, Inc.
Design Manual Chapter 6 - Geotechnical 6B - Subsurface Exploration Program 6B-2 Testing A. General Information Several testing methods can be used to measure soil engineering properties. The advantages,
More informationALLOWABLE LOADS ON A SINGLE PILE
C H A P T E R 5 ALLOWABLE LOADS ON A SINGLE PILE Section I. BASICS 5-1. Considerations. For safe, economical pile foundations in military construction, it is necessary to determine the allowable load capacity
More informationCOMMERCIAL CONDUIT RULES AND REGULATION
Electric Engineering Division COMMERCIAL CONDUIT RULES AND REGULATION S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies\Residential 1805 NE 30th Ave., Bldg. 400 Ocala, FL 34470-4875
More informationRPS - sales@rpssolar.com - 858 755 4505-12478 San Bruno Cove, San Diego, CA 92130
RPS - sales@rpssolar.com - 858 755 4505-2478 San Bruno Cove, San Diego, CA 9230 SWH Solar Mount Rail R-MR-SW-SR-0.5, R-MR-SW-SR-2, R-MR-SW-SR-4, R-MR-SW-SR-4B, R-MR-SW-SR-7 Part No. MR-SW-SR-0.5, MR-SW-SR-2,
More informationSteel Bridge Design E90 Project Proposal
Steel Bridge Design E90 Project Proposal 12/5/07 Abstract We propose to design and construct a steel bridge to the specifications and constraints governing the 2008 ASCE/AISC Steel Bridge Competition.
More informationTransmission Foundations Case History : Helical piles Hydro One Networks Inc.
Transmission Foundations Case History : Helical piles Hydro One Networks Inc. www.hubbellpowersystems.com Late in 2008, an aerial patrol discovered three 500kV towers with partially-collapsed foundations
More informationResidential Foundations and Basements
Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article
More informationLAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
More informationNew construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations
from New construction foundations don t have to be a headache. The CHANCE Helical Pier Foundation System gives you the performance of concrete without the drawbacks and liabilities of driven piles and
More informationMobile Home Pre-Inspection Checklist
Mobile Home Pre-Inspection Checklist TWO (2) STEP INSPECTION PROCESS STEP ONE: CALL FOR THE FIRST INSPECTION WHEN THESE ITEMS ARE COMPLETE. 1. Septic tank installed and plumbing complete. (SEE PLUMBING
More informationElectrical Service Guidelines
Electrical Service Guidelines Middle Tennessee Electric Membership Corporation Revised: May 23, 2013 MTEMC's Electrical Guidelines TABLE OF CONTENTS Right-of-Way Clearance Guide 3 MTEMC Requirements 4
More informationMAST ARMS & POLES. Ornamental Pole Top & Bases
Ornamental Pole Top & Bases Pelco s decorative pole top and bases help make the traffic signal aesthetically pleasing to the eye. Available for various pole diameters and multiple finish options. Ornamental
More informationQuick fix for frost heave:
Quick fix for frost heave: HELICAL PILES Megan Milbradt Civil Engineer Basin Electric Power Shane Vasbinder Civil Engineer Basin Electric Power Concrete piers were 6 inches to 2 feet out of the ground.
More informationAdditions and Alterations
Additions and Alterations Addition and alteration construction is a miscellaneous grouping of home improvement and renovation projects that are generally geared toward the enhancement of an existing principal
More informationTYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE
TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE A. GENERAL NOTES: Service entrance line and load conductors, conduit straps, weatherhead, lock nuts, bushings, connectors, and
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More information3M Mobile SkyWalk Series Horizontal Lifeline Product Return Form
3M Mobile SkyWalk Series Horizontal Lifeline Product Return Form THIS FULLY COMPLETED DOCUMENT MUST BE INCLUDED WITH EACH RETURN SHIPMENT IN ORDER FOR CREDIT TO BE ISSUED. ALL CREDITS WILL BE ISSUED TO
More informationBuilding Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County
Building Permit Application Packet The purpose of Building Codes is to establish the minimum requirements to safe guard the public health, safety and general welfare through structural strength, means
More informationSTEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13
STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13 (See Supplemental Instructions for trailers with heavy duty round footplates and/or Power Leveling Systems) PHONE SUPPORT
More informationHi*Lite XL Transmission Insulators
Hi*Lite XL Transmission Insulators Section 261 26 A NOTE: Because Hubbell has a policy of continuous product improvement, we reserve the right to change design and specifications without notice. Copyright
More informationGUY-GRIP Dead-end NOMENCLATURE GENERAL INFORMATION SAFETY CONSIDERATIONS 19-2. (440) 461-5200 inquiries@preformed.com www.preformed.
GUY-GRIP Dead-end NOMENCLATURE Cross-over Marks*: (A) Indicate starting point for application on smaller diameter fittings described on the reverse side of this page. (B) Indicates alternate starting point
More informationAerial Fibre Optics. Complete One Stop Solution for Aerial Fibre Optics. OPGW Cable and Fittings for OPGW
Complete One Stop Solution for OPGW Cable and Fittings for OPGW 53, Justice Chandra Madhav Road, Kolkata - 700020. India. Phone: 91-33-24748575 / 7565 Fax: 91-33-2476-1955 Email: sales@supremeco.com Website:
More informationANTENNA PARTS CATALOG
ANTENNA PARTS CATALOG Maco Antennas 302 S. East St. Mt. Carroll, IL 61053 www.macoantennas.net 815-244-3500 www.antennapartsoutlet.com SCREWS / BOLTS PART SIZE LENGTH DESCRIPTION PRICE S21 10-24 1/2" Machine
More informationMERCHANTS METALS SECTION 32 31 13 ARMORLINK ALUMINIZED CHAIN LINK FENCE AND GATES 2014!
MERCHANTS METALS SECTION 32 31 13 ARMORLINK ALUMINIZED CHAIN LINK FENCE AND GATES 2014 PART 1 GENERAL 1.1 RELATED DOCUMENTS A. DIVISION 01 - GENERAL REQUIREMENTS: Drawings, quality, product and performance
More informationThis mount uses concrete parking bumpers and a Davis tripod to create a mounting solution for nonpenetrable
NON-PENETRATING FLAT ROOF MOUNT Application Note 18 For Any Davis Weather Station Installed on a Mounting Tripod Introduction This application note describes various mounting solutions for non-penetrable
More informationPTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE
FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances
More informationSERIES ASM NEOPRENE/EPMD FLANGED SINGLE SPHERE CONNECTOR CONNECTORS. Pressures to 225 PSIG (15.51 barg) Temperatures to 230ºF (110ºC)
APPLICATIONS Process Industry Weak Acids Alkalies Compressed Air Pulp & Paper MODELS ASM - Flanged Connection OPTIONS Control Rods Oil & Gas Water & Waste Pump suction & discharge Sea water Chemical lines
More informationTECHNICAL NOTE Lining of Casings with SaniTite HP Pipe
TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,
More informationSECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such
More informationCONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST
CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST 1 Permeability is a measure of the ease in which water can flow through a soil volume. It is one of the most important geotechnical parameters. However,
More informationATS Overhead Table Shelf System INSTRUCTION MANUAL
ATS Overhead Table Shelf System INSTRUCTION MANUAL ATS Overhead Table Shelf System Instruction Manual Warranty Newport Corporation warrants this product to be free of defects in material and workmanship
More information