Overhead lines Asset Management in the Belgian network. S. GERMAIN K. VAN DAM B. RISSE JF. GOFFINET Elia Belgium

Size: px
Start display at page:

Download "Overhead lines Asset Management in the Belgian network. S. GERMAIN K. VAN DAM B. RISSE JF. GOFFINET Elia Belgium"

Transcription

1 21, rue d Artois, F PARIS B2-208 CIGRE 2012 http : // Overhead lines Asset Management in the Belgian network. S. GERMAIN K. VAN DAM B. RISSE JF. GOFFINET Elia Belgium SUMMARY The Belgian Transmission System Operator Elia is accountable to operate overhead lines and underground cables between 30 kv and 380 kv. The overhead electrical network has been built between years 1920 and today with different towers and conductors technologies with a big peak of investments in the years 60 and 70. In some situation the ageing of those equipments can be important and requires their replacements with different priorities in function of the investments possibilities that take into account the political decisions (for instance the integration of the renewable energies), the electrical needs, the financial constraints, etc. To determine those priorities, it is necessary to know the reliability of existing overhead lines. This paper describes the first step of the methodology implementation to determine those priorities by using different technical information. The following steps should be developed: - A briefly description of the problem and the general principle of the methodology will be explained by introducing the probability of failures and the failures consequence to calculate the risk matrix. - To obtain this risk matrix, it is needed to obtain different technical information from the visual inspection, robots inspection, destructive tests, etc. This chapter will describe in broad lines the actually used parameters to determine the two axes. - Finally a small description of the used tool will be described. KEYWORDS Asset Management, Overhead lines, Replacement policy [email protected]

2 1 INTRODUCTION The Belgian Transmission System Operator Elia is accountable to operate overhead lines and underground cables between 30 kv and 380 kv. The overhead electrical network has been built between years 1920 and today with different towers and conductors technologies with a big peak of investments in the years 60 and 70. In some situation the ageing of those equipments can be important and requires their replacements with different priorities in function of the investments possibilities that take into account the political decisions (for instance the integration of the renewable energies), the electrical needs, the financial constraints, etc. To determine those priorities, it is necessary to know the reliability of existing overhead lines. 2 SITUATION OF THE PROBLEM If we look at the age pyramid of the existing overhead lines owned by Elia, we see different parts in this curve: - The start of the curve where the number of overhead lines is limited. - One or more peaks which depend on investments - The end of the curve that corresponds to the obsolescence of the existing equipment (new generation equipments available, etc). The following picture gives an age pyramid for one of the equipment that fit out the existing overhead lines on the Elia electrical network Maintenance ELIA Zone (All) Electrical span 350 Sum of L km Class Electrical span Année_MSI Two situations must be envisaged to determine when the equipment should be replaced: - If we are in the first part of the curve, a technical audit should be made to determine the state of the existing overhead line. Based on this inspection either no work should be needed because the line is in a good state or an important maintenance should be needed to replace the damaged material and in finality to increase the reliability. In this situation, the cost should be included in the investment cost with a limited impact on the investment; 1

3 - If we are in a peak of the curve, the precedent process shouldn t be only used because the financial impact on the investment is very important and probably bigger than the investment capability of the TSO. Another complementary methodology should be developed. 3 USED METHODOLOGY To determine the priority of the investments, Elia has decided to apply the risk matrix at the overhead lines. This risk matrix has two axes: the technical state of the asset (probability of failure) and the consequence (operation, image ) if we loose them. As indicated in the following picture, the determination of the technical state is a combination of different information: ASSETS INSPECTIONS TECHNICAL INFORMATION FAILURES ANALYSE INSPECTIONS ANALYSE PROBABILITY OF FAILURE - The technical information about the overhead lines (age, type of steel, type of towers, type of conductors, ); - The failures analyse (date of the failure, type of failure, type of material concerned, ); - Analyse of the assets based on different visual inspections, audits, destructive analyse, painting maintenance, etc The second axis of the risk matrix is the consequence of the asset failure. The estimation of this axis is based on a combination of different impacts: ELECTRICAL IMPACT SAFETY IMPACT ENVIRONMENTAL IMPACT... CONSEQUENCE OF FAILURE - The importance of the electrical flow through the asset on the electrical network; - In some situation, the breakdown of the asset has a serious impact on the safety (explosion of a porcelain terminal for example); - The environmental impact; - Eventually other information. The estimation of these different elements must be made with a program that collects all information and calculate the different values. So it is important that each asset, that composes the electrical network, has one and only one reference. Indeed, the different information is stored in various data banks (technical data bank, financial data bank, environmental data bank ) and must be compiled asset by asset. 2

4 4 DETERMINATION OF THE RISK MATRIX 4.1 Probability of failures Since 1990, Elia owns an information data bank with all electrical failures observed on the networks 380 kv to 70 kv. For each incident, a technical analyse is made and the results are stored in it. Today, from this data bank, it is possible to extract all failures observed on overhead lines in function of the date, the type of failures (internal cause, meteorological cause, human cause ) and the electrical circuit number. In parallel, since 2005, a data bank with all technical characteristics of overhead lines is being filled in. For each line asset, it is possible to find the commissioning date, the type of used material, the principal characteristics By combination of the two data banks and by using the internal failures it is possible to determine the probability of failure of different equipments (Aluminium-steel conductor, steel tower, concrete pole ) via the Weibull curves. The obtained curves are conformed to the actual knowhow and the field experience. However, if we consider the internal failures, the number of incidents is fortunately very limited. So it is not possible to determine the curve for each section of a conductor family. Besides these curves don t take into account the environmental effect (sea, land ), the chemical aggression To adjust these curves in the future, Elia has started different actions to determine a health index: - During the routine and legal inspections, the agent writes a malfunction report for each observed damages. This report is written directly in a maintenance tool to plan the curative intervention. However this report contains a lot of important technical information that can be used to determine eventually a local problem on a component. To increase the quality of this report and to use directly the observations conclusion in the asset management tool, Elia has started the implementation of standard cards where the following information is available: the type of equipment where it is possible to observe the degradation, the degradation name, the degradation picture, the cause, the risk, the intervention time and if a monitoring of the installation is needed. 3

5 - For the Aluminium-steel conductor, Elia has been measuring for about 20 years the loss of the Zn galvanisation on steel wires without removal of a conductor sample. With this measure, it is possible to classify the different lines from the good to the bad. However, this measure doesn t give technical information on the rust steel and indirectly on the steel section reduction. Today with the evolution of the technology, it is possible to determine the steel section loss and then the residual mechanical tension of the conductor. This methodology enables a better tuning of the lines based on the state of the conductor without removal of a sample. This technology has been tested, for the first time in 2011, on one line and the results are promising. - To follow the evolution of the tower and fitting degradation, the reinforcement of the climbing patrol has been decided two years ago in order to follow the mechanical degradation in the time. For this purpose 10 to 20 % of the towers have been identified as reference towers. If each reference tower is climbed each 5 years, and the same technical points are observed, it is possible to follow the evolution of the mechanical degradation on the time. For each obtained report, a score is given. It is decomposed in 4 levels that translate a severity status: - RED: correspond to a major loss of mechanical and/or electrical characteristics; - ORANGE: correspond to a medium loss of mechanical and/or electrical characteristics; - YELLOW: the first small degradations are observed; - GREEN: the equipment is in a very good state. These scores should be used to determine the health index. 4.2 Consequences The failure of an overhead line in an electrical network can have different consequences in function of its location and the time of failure. To quantify theses consequences in a first time, Elia has decided to determine the following parameters: - Normally the electrical network is dimensioned for the N-1. In consequence, the loss of an overhead line has no consequence for the operation. When a second failure appears, the loss of the first equipment can be important and eventually drives to a switch off of a customer, a city and eventually to a local or global blackout. However the determination of the consequence of the loss of a line is very difficult because it depends on the configuration of the electrical network at one moment. The solution is very difficult and it is for this reason that Elia has standardised the load of each line in function of a maximum load defined. The result of this calculation gives the first consequence. 4

6 - The second used consequence parameter is the impact on the public. Indeed if we observe a failure of a conductor on a road or in a city, the impact on the public is very higher than in a situation where the breakdown is observed on a field. Moreover if during the incident a people is injured the image of the society is impacted. To take it into account, it has been decided to relate the number of crossing with roads and cities with the maximal number of crossing. With these two parameters, it is possible to compute a global consequence for each overhead line. 4.3 Example of a risk matrix When electrical equipment in high voltage, low voltage or power links has reached his expected life time, Elia writes a replacement policy that defines the reasons of the replacement, the condition of the replacement, the financial impact and the duration of this action. In each policy, it is needed to determine the priority of the replacement because the financial capacities are limited. To obtain these equipments classification, the precedent methodology is used and gives a risk matrix. Each point of the following picture corresponds to an overhead line or a part of an overhead line. RISICO MATRIX ß= 5 80% Legende: draadstelnummer - leeftijd (jaar) - geografische lengte (km) - * indien aardkabel 70% 60% 50% Relatieve gevolgschade 40% 30% 20% 10% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Relatieve faalkans The red circle on the picture gives the critical of overhead lines where the risk is above an acceptable risk for the company. This graph gives the priorities for the investments. 5

7 5 ASSET MANAGEMENT TOOL In many situations, the technical needed information is stocked in different data banks (technical data bank, failures data bank, financial data bank, etc) where the information is stocked equipment by equipment. So it is needed a unique identification for each asset that composes the different links, substations, etc. In this situation, it is easy to compile this information to obtain the different components of the risk matrix, for example. Since 3 years, Elia has decided to start the implementation of an asset management tool to manage the different assets those compose the electrical network. Today this program enables the following tasks: - For each asset, this program compiles the different available technical information and gives the basic reports. Those reports must be used to write different documents and to control the data quality by crossing different information. - When the data are compiled, it is possible to estimate the Weibull curve to estimate the expected life time of the asset by using health index. - Another application of this program is the simulation calculation to determine the different components of the risk matrix, the optimal time for the investment, etc - By the using of this tool, it appears that the results are very sensitive to the data quality and should induce bad decisions in some situations. It is for this reason that a specific action is started to increase the data quality via inspection, training of the people, automatic data check, etc. Today, this tool is operational and possesses different methodologies that evolve with the time, with the technology evolution and with evolution of investigations. 6 CONCLUSIONS When the financial resources are limited, it is needed to determine a methodology to find where the money should be the best invested. To reach this goal for the electrical lines and substations, it is needed to determine a risk matrix based on technical information on one side and consequences for the society and the public on the other side. The result is obtained by compilation of much information that comes from one or more data banks. The quality of these data is very important because all errors could lead to a bad investment decision. Finally this methodology is not fixed in the time and may evolve in the future in function of the technical investigation evolution. This asset management is a long-term work. 6

8 BIBLIOGRAPHY [1] Working Group B2.08 CIGRE. Assessment of existing overhead line supports (Technical Brochure 230 June 2003) [2] Working Group B2.15 CIGRE. Life cycle assessment (LCA) for overhead lines (Technical Brochure 265 December 2004) [3] Working Group B2.20 CIGRE. Management of risks due to load-flow increases in transmission OHL (Technical Brochure 385 June 2009) [4] Working Group B2.30 CIGRE. Engineering guidelines relating to fatigue endurance capability of conductor/clamp systems (Technical Brochure 429 October 2010) [5] Working Group B2.33 CIGRE. Working Safely while Supported on Aged Overhead Conductors (Technical Brochure 471 August 2011) [6] Working Group B2.32 CIGRE. Technical Brochure on Evaluation of Aged Fittings (Technical Brochure 477 October 2011) 7

Asset management for power cable systems - Total cost optimization based on the Application of diagnostics -

Asset management for power cable systems - Total cost optimization based on the Application of diagnostics - 21, rue d Artois, F-75008 PARIS B1_212_2012 CIGRE 2012 http : //www.cigre.org Asset management for power cable systems - Total cost optimization based on the Application of diagnostics - T. NISHIKAWA Y.

More information

Overhead lines in Ireland

Overhead lines in Ireland Overhead lines in Ireland The value in Cigré Jarlath Doyle Abstract The main theme of my presentation is to give a brief overview of the valuable information and influence Cigré has and is having on the

More information

Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems

Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems 21, rue d Artois, F-75008 PARIS B1-215 CIGRE 2012 http : //www.cigre.org Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems Mike FAIRHURST (1), Ankit GOWADIA (1),

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,

More information

Living with Electricity Easements

Living with Electricity Easements The Basslink electricity interconnector spans a total of 370 kilometers, from Georgetown in Tasmania, across Bass Straight to Gippsland where it connects with the Victorian electricity grid at Loy Yang.

More information

Server Monitoring Reports for Matrix IT

Server Monitoring Reports for Matrix IT Server Monitoring Reports for Matrix IT Matrix IT Solutions Limited October 2013 Table of Contents 1 Introduction...1 1.1 Overview...1 1.2 All Sites...1 1.3 Percentage Good Analysis...1 1.4 Outage Analysis...1

More information

ELECTRICAL SAFETY RISK ASSESSMENT

ELECTRICAL SAFETY RISK ASSESSMENT ELECTRICAL SAFETY RISK ASSESSMENT The intent of this procedure is to perform a risk assessment, which includes a review of the electrical hazards, the associated foreseeable tasks, and the protective measures

More information

environment briefing02

environment briefing02 PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The

More information

DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2. Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8

DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2. Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8 DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2 Kinds and Uses of Service... 2-1-1 and 2-1-2 Wye Network Area Maps Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8 Transformer Connections

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

Experimental Verification of Advanced Voltage Control for Penetration of PV in Distribution System with IT Sectionalizing Switches

Experimental Verification of Advanced Voltage Control for Penetration of PV in Distribution System with IT Sectionalizing Switches 21, rue d Artois, F-75008 PARIS C6 _113 _2012 CIGRE 2012 http : //www.cigre.org Experimental Verification of Advanced Voltage Control for Penetration of PV in Distribution System with IT Sectionalizing

More information

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4 CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,

More information

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION 1 EFFICIENT ELECTRICAL ENERGY TRANSMISSION

More information

Summary of Electric Transmission Assessment Report

Summary of Electric Transmission Assessment Report Summary of Electric Transmission Assessment Report January 2010 Assessment and Analysis of the State-Of-the-Art High-Voltage Electric Transmission Systems with Specific Focus on High-Voltage Direct Current

More information

Trees and powerlines. Office of the Technical Regulator. sa.gov.au/energysafe

Trees and powerlines. Office of the Technical Regulator. sa.gov.au/energysafe Trees and powerlines Office of the Technical Regulator sa.gov.au/energysafe owerlines are an important part of our everyday lives, bringing electricity to our homes and businesses. egetation needs to be

More information

Brochure Introducing HVDC

Brochure Introducing HVDC Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU George CURCANU, Constantin ILINCA, Ilie SBORA ICMET Craiova, Romania, Calea Bucuresti 144, phone:

More information

Space project management

Space project management ECSS-M-ST-80C Space project management Risk management ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is one of the series of ECSS Standards

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Electromagnetic Induction Experiment

Electromagnetic Induction Experiment In this experiment, the activity will be based on a Phet simulation called Faraday s Electromagnetic Lab, created by a group at the University of Colorado at Boulder. This group has a number of good simulations

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI 1 Vision 2050 An Asset Management Strategy Jaclyn Cantler Manager, Transmission Planning, PHI 2 Agenda Case for Change About Vision 2050 Status Closing System Design Cybersecurity Interface with distributed/dispersed

More information

October Safety Subject

October Safety Subject October Safety Subject Electrical Hazards All electrical equipment should be kept in good repair. Replace defective equipment or have it repaired by a qualified person. Watch for wiring on appliances that

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0

More information

ICM Project Station Infrastructure and Equipment

ICM Project Station Infrastructure and Equipment EB 0 00 Schedule B. ( pages) ICM Project Station Infrastructure and Equipment (THESL) EB 0 00 Schedule B. I EXECUTIVE SUMMARY 0. Project Description Many Municipal Substations (MS) located outside of downtown

More information

2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT

2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT 2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT Contents Overview... 3 1.0 Electric System Reliability... 4 1.1 Annual Reliability Data with Utility Comparisons... 4

More information

Colocation Scenario @ MIX

Colocation Scenario @ MIX Colocation Scenario @ MIX INTRODUCTION This white paper describes the colocation scene for ISPs interested to connect to MIX. The intended audience is network operator peering coordinators that have been

More information

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Centre for Sustainable Electricity and Distributed Generation Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Predrag Djapic and Goran Strbac July 2008 FUNDED BY BERR URN 08/1144

More information

Coupling Effect in Substation Ground Measurements

Coupling Effect in Substation Ground Measurements SERBIAN JOURNAL OF ELECTRICAL ENGINEERING Vol. 9, No. 3, October 2012, 315-324 UDK: 621.316.13.011.2 DOI: 10.2298/SJEE1203315F Coupling Effect in Substation Ground Measurements Alex Farber 1, Boris Katz

More information

LIGHTNING DETECTION IMPROVEMENT FALLS BROUGHT TO ESKOM S TRANSMISSION LINE DESIGN AND FAULT ANALYSIS

LIGHTNING DETECTION IMPROVEMENT FALLS BROUGHT TO ESKOM S TRANSMISSION LINE DESIGN AND FAULT ANALYSIS LIGHTNING DETECTION IMPROVEMENT FALLS BROUGHT TO ESKOM S TRANSMISSION LINE DESIGN AND FAULT ANALYSIS Luthando Peter Faith Mokhonoana Eskom Trans Africa Projects, Midrand Johannesburg South Africa 1 INTRODUCTION

More information

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS Terence Hazel Senior Member IEEE Schneider Electric 38050 Grenoble France Abstract The power requirements for large industrial sites is increasing.

More information

GRID CONNECTION OF POWER GENERATING FACILITIES. FEBEG POSITION Elia WG Belgian Grid (16.09.2011)

GRID CONNECTION OF POWER GENERATING FACILITIES. FEBEG POSITION Elia WG Belgian Grid (16.09.2011) GRID CONNECTION OF POWER GENERATING FACILITIES FEBEG POSITION Elia WG Belgian Grid () FEBEG 2 CONTENT Current developments General principles Integrating new power plants in the grid Grid connection procedure

More information

ELECTRICIAN, LEAD. Job Code Pay Grade 13722 CL14

ELECTRICIAN, LEAD. Job Code Pay Grade 13722 CL14 ELECTRICIAN, LEAD 13722 CL14 Nature of Work This is lead journeyman level electrical work in the installation, alteration, repair and maintenance of electrical systems, fixtures and equipment. The incumbent

More information

Certificate of Registration

Certificate of Registration Certificate of Registration This is to certify that Clancy Docwra Limited Supplier Number: 061973 are now fully registered as a supplier on UVDB for the following products/services 1.4.25 Communication

More information

1.2 Advantages and Types of Prestressing

1.2 Advantages and Types of Prestressing 1.2 Advantages and Types of Prestressing This section covers the following topics. Definitions Advantages of Prestressing Limitations of Prestressing Types of Prestressing 1.2.1 Definitions The terms commonly

More information

V1.8 0 - N ovember 2015. Distribution Network Asset Data Available To Third Parties

V1.8 0 - N ovember 2015. Distribution Network Asset Data Available To Third Parties V1.8 0 - N ovember 2015 Distribution Network Asset Data Available To Third Parties How To Request Data LinesearchBeforeUDig (http://www.linesearchbeforeudig.co.uk) This service is available 24/7 365 days

More information

Measurement, Modeling and Simulation of Capacitor Bank Switching Transients

Measurement, Modeling and Simulation of Capacitor Bank Switching Transients Measurement, Modeling and Simulation of Capacitor Bank Switching Transients Mirza Softić*, Amir Tokić**, Ivo Uglešić*** *Kreka - Dubrave e, Dubrave, Bosnia and Herzegovina (e-mail: [email protected]).

More information

345 kv Brazos Valley Connection Project FAQs

345 kv Brazos Valley Connection Project FAQs 345 kv Brazos Valley Connection Project FAQs Overview 1. Who is CenterPoint Energy Houston Electric, LLC? CenterPoint Energy Houston Electric, LLC (CenterPoint Energy) is an electric utility that maintains

More information

Risk Analysis and Quantification

Risk Analysis and Quantification Risk Analysis and Quantification 1 What is Risk Analysis? 2. Risk Analysis Methods 3. The Monte Carlo Method 4. Risk Model 5. What steps must be taken for the development of a Risk Model? 1.What is Risk

More information

Smart Substation Security

Smart Substation Security Smart Substation Security SmartSec Europe 2014 Amsterdam 29/01/2014 Agenda Context Elia Introduction to the substation environment in Elia Security design and measures in the substation Near and far future

More information

Estimation of electrical losses in Network Rail Electrification Systems

Estimation of electrical losses in Network Rail Electrification Systems Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

Ohm's Law and Circuits

Ohm's Law and Circuits 2. Conductance, Insulators and Resistance A. A conductor in electricity is a material that allows electrons to flow through it easily. Metals, in general, are good conductors. Why? The property of conductance

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

Voltage Detection and Indication by Electric Field Measurement

Voltage Detection and Indication by Electric Field Measurement Voltage Detection and Indication by Electric Field Measurement William McNulty, P.E. Technical Director Voltage Detection and Indication by Electric Field Measurement William McNulty, P.E. HD Electric

More information

Modeling of Transmission Lines

Modeling of Transmission Lines Modeling of Transmission Lines Electric Power Transmission The electric energy produced at generating stations is transported over high-voltage transmission lines to utilization points. The trend toward

More information

The electrical energy produced at the gen

The electrical energy produced at the gen 300 300 Principles of Power System CHAPTER CHAPTER 12 Distribution Systems General 12.1 Distribution System 12.2 Classification of Distribution Systems 12.3 A.C. Distribution 12.4 D.C. Distribution 12.5

More information

PRESTRESSED CONCRETE POLES The Solid Alternative to Wood

PRESTRESSED CONCRETE POLES The Solid Alternative to Wood Prestressed Concrete Utility Poles U-1 PRESTRESSED CONCRETE S The Solid Alternative to Wood Lonestar Prestress concrete poles were developed to meet the expanding need of a supporting structure for; street,

More information

High Voltage. Hazards

High Voltage. Hazards High Voltage Hazards HV Hazards Substations, Overhead Lines, Cables Safety Incidents Requirements for Designers, Constructors Construction Regs 2013 and other Legislation Codes of Practice Other Guidance

More information

Cable Consulting International

Cable Consulting International Cable Consulting International Brian Gregory BSc, CEng, MIEEE, FIEE Technical Director www.cableconsulting.net Alan Williams BSc, CEng, MIEE Senior Consultant 1 FEASIBILITY STUDY for 500 kv AC UNDERGROUND

More information

Parking Guidance System

Parking Guidance System Parking Guidance System The Need: With the development of modern life, the amount of cars is growing rapidly and the difference between cars and parking spaces becomes a problem in the crowded urban areas.

More information

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress

State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress 0611-048-Mep229 12/12/06 6:44 Page 22 State, trends and evolutions of HV/EHV power cables systems and contributions of SC B1 to their ongoing progress Reinhard SCHROTH, Chairman of SC B1 2002-2006 High

More information

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID Tension (kv) Impedance (Ohms) EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID frequency (Hz) Simon DESCHANVRES Yannick VERNAY RTE, CNER, Substations Department t (ms) EMTP-RV Users Group

More information

Quality and Quality Control

Quality and Quality Control 1 Quality and Quality Control INSPECTION Inspection is the most common method of attaining standardisation, uniformity and quality of workmanship. It is the cost art of controlling the product quality

More information

LOW COST MOTOR PROTECTION FILTERS FOR PWM DRIVE APPLICATIONS STOPS MOTOR DAMAGE

LOW COST MOTOR PROTECTION FILTERS FOR PWM DRIVE APPLICATIONS STOPS MOTOR DAMAGE LOW COST MOTOR PROTECTION FILTERS FOR PWM DRIVE APPLICATIONS STOPS MOTOR DAMAGE Karl M. Hink, Executive Vice President Originally presented at the Power Quality 99 Conference ABSTRACT Motor protection

More information

Requirements for the Attachment of Communication Cable Facilities on PPL Poles

Requirements for the Attachment of Communication Cable Facilities on PPL Poles Page 99 of 137 Requirements for the Attachment of Communication Cable Facilities on Replaces: URS-3002 URS-3004 URS-101C-304 A-157649 Page 100 of 137 Reference Notes for Drawings: General 1. The term communication

More information

APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE

APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE APPENDIX D PAGE 1 APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE This appendix is composed of the following three parts: 1. Part I - Guidelines for determining the distribution or wires only assets and activities;

More information

Explaining and avoiding faults Increasing availability

Explaining and avoiding faults Increasing availability Explaining and avoiding faults Increasing availability > Cables > Cable joints > Cable terminals Cables, cable joints, cable terminals Increasing availability A cable breakdown usually means an unexpected

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

Trees and powerlines. Office of the Technical Regulator. Web: sa.gov.au/energysafe Phone: 8226 5500 Email: [email protected]

Trees and powerlines. Office of the Technical Regulator. Web: sa.gov.au/energysafe Phone: 8226 5500 Email: dmitre.otr@sa.gov.au Trees and powerlines Office of the Technical Regulator For more energy information: Web: sa.gov.au/energysafe hone: 8226 5500 Email: [email protected] owerlines are an important part of our everyday

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. [email protected]. [email protected]

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii [email protected] Ethan Boardman [email protected] Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South

Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South Asia Energy Division Asia Clean Energy Forum June 2015

More information

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage

More information

Anomaly Detection in Predictive Maintenance

Anomaly Detection in Predictive Maintenance Anomaly Detection in Predictive Maintenance Anomaly Detection with Time Series Analysis Phil Winters Iris Adae Rosaria Silipo [email protected] [email protected] [email protected] Copyright

More information

Governor s Two-Storm Panel: Distribution Infrastructure Hardening Options and Recommendations

Governor s Two-Storm Panel: Distribution Infrastructure Hardening Options and Recommendations Governor s Two-Storm Panel: Distribution Infrastructure Hardening Options and Recommendations Dana Louth, CL&P VP - Infrastructure Hardening December 14, 2011 0 Topics for today s presentation Review of

More information

Guide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards

Guide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards Guide to the electrical parameter classifications of IEC 60950 and IEC 62368 safety standards Abstract This Guide is an informative listing of selected terms and definitions found in IEC Glossary entry

More information

MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION

MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION REPORT ON NETWORK RELIABILITY ASPECTS OF THE CHOICE LINE VERSUS CABLE FOR

More information

Respecting the environment

Respecting the environment MAIN FEATURE CHAPTER I RESEARCH WITH AN EYE ON THE FUTURE Respecting the environment Low power losses and a lesser visual impact on the landscape make Gas-Insulated Lines (GIL) a very environmentally friendly

More information

Fiat Group Purchasing Supplier Quality SQP User Manual Version 4 September 2008

Fiat Group Purchasing Supplier Quality SQP User Manual Version 4 September 2008 SQP User Guide Version 4 September 2008 Index Topics 1. Access to the System... 2 2. Logon credentials for Iveco Suppliers... 4 3. Access to the system for CNH Users and Suppliers.... 5 4. SQP Main Menu...

More information

Hendrix Spacer Cable

Hendrix Spacer Cable Hendrix Spacer Cable What is Spacer Cable? Covered Conductor Withstands temporary branch contact Eliminates temporary faults Protects wildlife Less clearance issues Compact Configuration Multiple Circuits

More information

PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY

PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY Scope These program criteria apply to programs having titles involving Electrical Engineering Technology including: electrical engineering, electrical

More information

We appreciate your feedback

We appreciate your feedback Publishing date: 23/07/2015 Document title: We appreciate your feedback Please click on the icon to take a 5 online survey and provide your feedback about this document REPORT ON UNIT INVESTMENT COST INDICATORS

More information

EUROPASS CERTIFICATE SUPPLEMENT

EUROPASS CERTIFICATE SUPPLEMENT EUROPASS CERTIFICATE SUPPLEMENT TITLE OF THE DIPLOMA (ES) Técnico en Instalaciones de Telecomunicaciones TRANSLATED TITLE OF THE DIPLOMA (EN) (1) Technician in Telecommunications Installations --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

More information

Market Growth and New Regulations Demand Network Modernization

Market Growth and New Regulations Demand Network Modernization CASE ESB NETWORKS: POLE TOP COMMUNICATION INCREASES EFFICIENCY IN IRELAND Viola s solution for remotely operating pole-top reclosers and switches increases reliability, cuts operating costs and helps to

More information

TABLE OF CONTENTS. I. Introduction 3. II. Contractor Pre-Qualification Criteria 4. III. Procedure for Application of Contractor Pre-Qualification 6

TABLE OF CONTENTS. I. Introduction 3. II. Contractor Pre-Qualification Criteria 4. III. Procedure for Application of Contractor Pre-Qualification 6 Related To FEWA Electricity Network (Transmission & Distribution) Version 1.0 December 2014 TABLE OF CONTENTS Page I. Introduction 3 II. Contractor Pre-Qualification Criteria 4 III. Procedure for Application

More information

Chapter 11 MANAGEMENT CONTROL, REPORTING, INTERNAL AUDIT FUNCTIONS A uniform reporting system in all the subsidiaries allows effective management control and the production of a Group dashboard on a monthly

More information

Comparison between Gas- and Air Insulated Network Concepts with the Life Cycle Cost Method

Comparison between Gas- and Air Insulated Network Concepts with the Life Cycle Cost Method Comparison between Gas- and Air Insulated Network Concepts with the Life Cycle Cost Method Ingo Jeromin, Gerd Balzer, Technische Universität Darmstadt, Jürgen Backes, Richard Huber, EnBW Regional AG Stuttgart

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

Seattle City Light s Asset Management Program

Seattle City Light s Asset Management Program Seattle City Light s Asset Management Program September 25-26, 2012 Agenda Asset Management vs. WAMS Definitions and Distinctions AM Program Budget Status AM Program Major Accomplishments WAMS Budget Status

More information

Electric Power Distribution

Electric Power Distribution Electric Power Distribution A S Pabla Consulting Engineer and Former Chief Engineer Punjab State Electricity Board McGraw-Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New

More information

Study of Lightning Damage Risk Assessment Method for Power Grid

Study of Lightning Damage Risk Assessment Method for Power Grid Energy and Power Engineering, 2013, 5, 1478-1483 doi:10.4236/epe.2013.54b280 Published Online July 2013 (http://www.scirp.org/journal/epe) Study of Lightning Damage Risk Assessment Method for Power Grid

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 60071-2 Third edition 1996-12 Insulation co-ordination Part 2: Application guide This English-language version is derived from the original bilingual publication by leaving out

More information

Lab 3 - DC Circuits and Ohm s Law

Lab 3 - DC Circuits and Ohm s Law Lab 3 DC Circuits and Ohm s Law L3-1 Name Date Partners Lab 3 - DC Circuits and Ohm s Law OBJECTIES To learn to apply the concept of potential difference (voltage) to explain the action of a battery in

More information

Predict the Popularity of YouTube Videos Using Early View Data

Predict the Popularity of YouTube Videos Using Early View Data 000 001 002 003 004 005 006 007 008 009 010 011 012 013 014 015 016 017 018 019 020 021 022 023 024 025 026 027 028 029 030 031 032 033 034 035 036 037 038 039 040 041 042 043 044 045 046 047 048 049 050

More information

Case Study 5 Use of Wind Turbine Technology

Case Study 5 Use of Wind Turbine Technology Case Study 5 Use of Wind Turbine Technology 1. Context Hong Kong relies on an adequate and reliable electricity supply for its economic development. Our electricity needs are met by the two electricity

More information

Application of linear programming methods to determine the best location of concrete dispatch plants

Application of linear programming methods to determine the best location of concrete dispatch plants Application of linear programming methods to determine the best location of concrete dispatch plants Introduction: Carlos Horacio Gómez Junghye Moon University of Illinois Urbana-Champaign I just remember

More information

THE LIGHTNING PROTECTION INTERNATIONAL STANDARD

THE LIGHTNING PROTECTION INTERNATIONAL STANDARD THE LIGHTNING PROTECTION INTERNATIONAL STANDARD Prof.-Dr-Eng. Christian Bouquegneau, Chairman of IEC TC81 (Lightning Protection), Pro-rector of the Faculté Polytechnique de Mons (Belgium) Abstract The

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER

More information

PTU Series Transducer Digital Display Indicator User s Manual

PTU Series Transducer Digital Display Indicator User s Manual PTU Series Transducer Digital Display Indicator User s Manual The Swagelok PTU series digital display indicator is available to mount directly to the Swagelok PTU series transducer to provide local indication

More information