Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM ; Order No.
|
|
|
- Laurence Lambert
- 9 years ago
- Views:
Transcription
1 1
2 2
3 3
4 4
5 Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM ; Order No. 2000) comments regarding Transmission and Generation Maintenance Scheduling 2. Transmission Owners Agreement (TOA) to Organize MISO Appendix E of the TOA states: The MISO shall approve the scheduling of maintenance of all transmission facilities making up the Transmission System and shall coordinate with generation owners, as appropriate, the scheduling of maintenance on generation facilities as set forth in Section VII of this Appendix E. 3. MISO/MAPPCOR Services Agreement Pursuant to an interim extension, MISO currently continues to function as a contracted provider of reliability services to the Mid-Continent Area Power Pool Regional Transmission Committee (MAPPCOR). MISO is responsible for coordinating the scheduling of maintenance for all of the transmission facilities owned by non-miso companies within the Midwest Reliability Organization (MRO) reliability region and for coordinating with Generation Owners to schedule generation facility maintenance per the extended MISO /MAPPCOR Services Agreement. 4. NERC Reliability Standards The Transmission Operations (TOP) Reliability Standards (specifically, TOP-003) Requires coordination between the TOP, GOP and BA with 5
6 respect to outages that could affect Bulk Electric System (BES) reliability [including reactive devices]. Requires each Reliability Coordinator to resolve any scheduling of potential reliability conflicts. Interconnection Reliability Operations and Coordination (IRO) Standards (specifically, IRO-010) Requires RCs to have a documented specification for data and information have a documented specification for data and information to build and maintain models to support Real-time monitoring, Operational Planning Analyses, and Real-time Assessments of its Reliability Coordinator Area to prevent instability, uncontrolled separation, and cascading outages. <<Definitions are provided at the end of this module>> 5
7 MISO is responsible for approving the scheduling of maintenance on all transmission facilities making up the Transmission System and for coordinating with Generation Owners, as appropriate, to schedule maintenance on generation facilities. MISO performs regional transmission and generation outage coordination in order to identify proposed transmission and generation outages that would create unacceptable system conditions and works with the facility owners to create remedial steps to be taken in anticipation of such proposed outages. This is accomplished while minimizing any inconvenience resulting from the involvement of an additional party in the outage review process. BPM-008 describes the MISO transmission and generation outage coordination process, which includes outage scheduling, outage analysis, and outage reporting; this document may be referenced as the BPM throughout this training module. Diagram Transmission and generation entities interact with MISO outage scheduler via the CROW Web, a graphical user interface (GUI), or via CROW s Application Programming Interface (API) which offers data integration via XML. Market Operations [Day-Ahead / Real-Time (DART) functions, Resource Adequacy, Market Settlements, etc..] require current outage information Transmission Outages are posted through OASIS (2308 Planned Outage Report and 2309 Real-Time Outage Report) Reliability Coordinator Information System (RCIS) is available to RCs for incident reporting 6
8 MISO, as the RC, integrates with the NERC System Data Exchange (SDX) application for reporting and managing outage information including Generators, Branches, and Transformers The exchange of outage and load data is performed asynchronously via a web service, utilizing SOAP, hosted by OATI. Access to SDX is achieved by cert/username/password authentication over a secure, private key connection. Data from SDX is provided to the Interchange Distribution Calculator (IDC) for reliability and basecase assessments for the Eastern Interconnection Model 6
9 Internal Coordination and Communications MISO Carmel and St. Paul Operations Engineering (OE) staff coordinate the analysis and approval of all outage schedules. Carmel OEs evaluate outage schedules submitted by MISO members within the ReliabilityFirst Corporation (RFC) and Southeastern Electric Reliability Council (SERC) regions. St. Paul OEs evaluate outage schedules submitted by MISO members and non-miso members within the MRO region and all outages submitted by MISO members in the Southwest Power Pool (SPP) region. Each MISO OE group evaluates the outages assigned to their group and communicates the results of their analysis to the other, as necessary, for review and comment prior to approving the outage schedules. Note: With the successful integration of Entergy into the MISO market and reliability footprint, processes/roles/responsibilities are expected to extend to a new Southern Control Center. Outage Reporting MISO transmission and generation outage schedules are submitted to the SDX on a periodic basis. MISO also downloads non-miso outage schedules from the SDX for use in other MISO processes, in addition to outage coordination. Transmission Outage schedules are available for viewing on OASIS. 7
10 Coordinating with Other Reliability Authorities MISO coordinates transmission and generator outages with other RCs. Outage schedules are normally exchanged with other RCs via the SDX and communication with other RCs is normally performedthrough the MISO Operations Engineering group in order to provide other RCs a single point of contact. Every reasonable effort is made to work with other RCs to reschedule conflicting outages of both parties in order to ensure that regional system reliability is maintained for outages scheduled both within and outside the MISO Reliability Coordinator Area. MISO maintains seams relationships with PJM, SPP, TVA, IESO,and Saskatchewan Power With respect to Outage Coordination, an interregional outage coordination process Defines points-of-contact within the seams parties Defines notification requirements Describes the minimum data/information to be exchanged Establishes procedures for how outage conflicts will be managed and resolved Consistent with NERC reliability criteria 7
11 Outage operations are handled by 3 different groups based on operation day timeline. Outage Coordination 2nd Business day and forward Reviews and approves all Planned outages Coordination of Planned Transmission and Generation Outages Transmission Security Planning Next-day security assessment Performs next day security analysis, plus any outage that has submitted a 24 hours notice Authority over: Next Day Security Plan Next Day, 2-Day and 3-Day Security Studies Contingency Analysis Voltage Stability Analysis on Key interfaces Next Day Report to comply with NERC IRO-004, Reliability Coordination Work with transmission Operators to develop/revise mitigation procedures as necessary (Op Guides) Approve, reschedule or deny urgent and emergency transmission outages Regional Operations Engineers 8
12 Current Operating Day; Emergency and Forced outages, RC support 8
13 Requirements matrix for submitting Generation or Transmission Outages. 9
14 Summary of reporting requirements. 10
15 Generation Outage Priorities types Planned Equipment is known to be operable with little risk of a forced outage As required for preventive maintenance, for troubleshooting, or repairs that are not viewed as urgent work Equipment capacity is upgraded, additional equipment is added or equipment is replaced due to obsolescence Includes periodic overhauls of generation equipment Urgent Equipment is known to be operable, yet carries an increased risk of a forced outage or equipment loss The equipment remains in service until maintenance crews are ready to perform the work Emergency Equipment is to be removed from service by the operator as soon as possible because of safety concerns or increased risk to grid security Forced Equipment is relayed out of service Generation Equipment Request Types Out of Service Equipment is out of service Deration Units that re online and available but with limited total output Economy Units that are offline for economic reasons but available if needed. Used by non-market units only. Note: The following resource types are not included in MISO s Outage Scheduling: 1. Demand Response Resources Type I (DRRs Type I) 11
16 2. Demand Response Resources Type II (DRRs Type II) 3. External Asynchronous Resources (EARs) 11
17 Planned Maintenance Generation Owners (GOs) or Generator Operators (GOPs) must submit Planned Outage schedules A Planned Outage is defined as the scheduled removal from service - in whole or in part - of a Generation Resource for inspection, maintenance or repair with the approval of the MISO in accordance with the Business Practices Manuals. All generation facilities 10 MW for a minimum rolling 24 month period (36 months for nuclear Generator Resources) and updated on a daily basis. Planned outage requests submitted with < 24 month notice will be considered late (36 months for nuclear Generator Resources). Wind Resources should submit outage schedules for facilities < 10MW. Outage Schedules for wind resources are used for wind resource forecast accuracy. If the GO/GOP expects to physically replace the energy needed as a result of the scheduled outage (including non-market generation within MISO reliability footprint), they should provide supporting information with the outage request for the purposes of engineering studies. 12
18 Typically, this would only be for firm energy schedules from external resources or the intention to make internal-to-miso resources must run. If the GO/GOP intends to allow normal market commitment and dispatch to replace the energy that would have been provided by the outaged unit, no physical replacement information is needed. All active outages (Proposed, Submitted, Study, Pre-Approved, Approved, and Implemented status) appearing in the OS are used in the Available Flowgate Capability (AFC) calculation process and posted to the SDX for use in congestion management and regional AFC calculations. The availability of Generation Resources is also determined in the Reliability Assessment Commitment (RAC) by looking at the status of the unit in the OS. In normal operating conditions, if a resource is listed in the OS with an Equipment Request Type of "Out of Service" the unit will be considered unavailable in the RAC analysis. Generation Resources listed in OS with an Equipment Request Type of Deration" would be considered in the RAC analysis. Nuclear Generator Resources MISO has responsibility for honoring Nuclear Plant Operating Agreement (NPOA) or any other applicable procedures or protocols that are mutually agreed upon. This is in accordance with regulatory approved NERC standard NUC-001 to address mutually agreed upon Nuclear Plant Interface Requirements (NPIRs). The NPIRs establish the operating criteria necessary maintain adequate offsite power to the nuclear generating facility. Transmission lines and/or transmission circuit breakers associated with nuclear generating facilities require coordination of outages and maintenance activities which affect the NPIRs. Automatic Voltage Regulator Status The GO/GOP is required to submit an Automatic Voltage Regulator (AVR) status report if the voltage regulation of an on-line generator is not available. This information must be conveyed to MISO RC or OE and must include the unit and the anticipated duration of the AVR unavailability. Reactive reporting for reduced unit AVR capability must also be communicated to MISO RC or OE shift staff. 12
19 The procedure for submission of AVR outages is via CROW; RTO-OP-051 AVR Procedure, defines the complete requirements of AVR status notifications. Note: It is the sole responsibly of the GO/GOP or appointed designee to submit and maintain outage schedules in CROW. MISO will not submit nor maintain outage schedules on behalf of the GO/GOP unless technical reasons prevent the GO/GOP from doing so. It is the Generator Owner or Generator Operator s responsibility to validate accuracy of all data submitted, by them or on their behalf, in the outage scheduler. 12
20 Generation Derates GO/GOPs, must submit a derate outage for all generation facilities when available output is reduced below the unit s capability based upon threshold criteria. A derate threshold is applied to determine if a reduction qualifies for outage submission; any reduction below the Must-Offer requirement, however, must be submitted even if the unit escapes the threshold criteria. <<Refer to BPM-011 Resource Adequacy and Level-2, Manager - Resource Adequacy training for compliance with Must-Offer and Module E>> If a unit s seasonal capability is reduced 10% and > 5MW or 50MW total, a derate outage submission is required. Submission of incremental hourly changes is not necessary; the largest hourly reduction per operating day may be submitted. Example(s): 15MW Unit reduced by 20% = 3MW, [< 5MW] - No Submission required 13
21 100MW Unit reduced by 10% = 10MW, [> 5MW and = 10%] - Submission Required 1000MW Unit reduced by 7% = 70MW, [> 50MW total] - Submission Required A scheduled derate outage due to planned maintenance/system upgrade activities should be submitted as a Planned Outage. Unplanned derates (Emergency/Urgent) are submitted as soon as the derate is identified. Forced events that result in generation derates are submitted as a Forced Outage. Note: Individual outages for each unit must be submitted unless otherwise modeled in MISO s Network Model (i.e. Combined Cycle configuration). Forced Generation Outages A Forced generator Outage is defined as an immediate reduction in output, Capacity or removal from service - in whole or in part - of a Generation Resource by reason of an Emergency or threatened Emergency, unanticipated failure, inability to return on schedule from a Planned Transmission Outage, or other cause beyond the control of the owner or operator of the facility, as specified in the BPM. A reduction in output or removal from service of a Generation Resource in response to changes in market conditions does not constitute a Generator Forced Outage. MISO coordinates with the GO/GOPs to implement schedules for unplanned generation maintenance due to a forced outage. GO/GOPs must contact MISO OEs or the RC to report any equipment limitation, including derates and forced equipment outages. Report must be made as soon as possible after the occurrence of the outage but no later than 30 minutes after the event. Reported information must include the cause of the outage and the expected return to service time (if known) as a schedule submitted through CROW. This must include an estimated end time and must be updated periodically, as necessary. 13
22 Generation Outage Coordination MISO coordinates and assesses the impact of all generator outage schedules in MISO Reliability Coordinator Area. These generation outage schedules are included in all Transmission Outage request studies and in the security studies performed on a regular basis. MISO coordinates with the GO/GOPs to recommend a schedule that maintains system security and minimizes adverse impacts in the available transmission capacity levels and adheres to agreed nuclear plant interface requirements. MISO reviews all existing submitted generation maintenance schedules for generation facilities 10 MW. The review includes analysis of transmission system reliability and any other relevant material effects. MISO will respond within 3 months to all requests submitted on time. In the event of a conflict between planned generation schedules, MISO will request re-scheduling if study results indicate a reasonable expectation of an Emergency, or circumstance that compromise the reliability of the Transmission System: a. The inability to maintain voltage required by nuclear Generation 14
23 Resources, or to meet any other Nuclear Plant Interface Requirement, as defined by NERC, including the provision of offsite power supply b. The inability to maintain the transmission system within system operating limits using normal operating procedures or restore the transmission system to normal operating conditions following a single contingency with the use of normal (non-emergency) operating procedures c. The potential for credible contingencies to significantly affect transmission system reliability of metropolitan areas MISO may suggest possible alternate times for all GO/GOPs to re-schedule the outage in order to maintain network security. Last In/First Out If neither GO/GOP reschedules on a voluntary basis then the outage schedule that was requested last is the first one considered for rescheduling when a conflict arises. Prior to rescheduling an outage, MISO will: a. Attempt to minimize the economic consequences of rescheduling (opportunity costs are excluded) b. Consider physical feasibility c. Coordinate with the affected GO/GOPs If generation outage schedules cannot be moved or changed because doing so would contravene applicable laws, regulations, judicial orders, or where rescheduling is not feasible (voided warranty or equipment damage) MISO will consider the use of existing Operating Guides or the development of new Operating Guides to allow the conflicting outage schedules to continue. Operating Guides to mitigate conflicts between two generator outages that cannot be rescheduled may include Emergency redispatch of generation and Load Shedding provisions. If an Operating Guide cannot be developed to address the generator conflicts, as a last resort, MISO will review the existing Transmission Outage schedules and attempt to identify any Transmission Outage requests that contribute to the problem. If Transmission Outage requests are found, they may be targeted for cancellation or revocation to ensure the system is in a reliable state for the duration of the generation outage schedule. 14
24 Jointly-Owned Generating Units Jointly-Owned Units (JOUs) must be reported appropriately to ensure that the outage is accurately represented in the AFC calculation and security planning process. JOUsthat are pseudo-tied (into, out-of,within) are represented as multiple units based on the ownership share of each owner/operator while JOUs operated using interchange schedules are modeled as a single unit in the operating Balancing Authority Area. <<Refer to Level-2, ManagerNetwork & Commercial Model training for details>> Owner/operators within MISO reliability footprint must report all shares of the JOU. Outage schedules for JOU shares with owners/operators outside MISO Market Footprint are obtained from the NERC SDX interface. 15
25 Non-MISO Market Units Off for Economic Reasons Base load generating units that are off for economic reasons must be reported to the OS. MISO network applications treat these units as offline, but available for dispatch if needed. Outage must be entered as an Economy Equipment Request Type as soon as the condition is identified. The planned start and estimated end times must be entered. The requestor notes must indicate that the unit is offline but available. The recall time must indicate the time needed to bring the unit online. 16
26 Generation Outage Analysis MISO uses Network Applications to analyze a planned generating unit maintenance schedule to determine its effects on, but not limited to: Available Flowgate Capability (AFC) Operating Reserves Security of MISO Reliability Coordinator Area Any other relevant matters Analyses includes power flow, contingency, and stability, to identify: Violation of pre and post-contingent thermal limits Violation of pre and post-contingent voltage limits Violation of pre-determined stability limits Capability for inter-baa transfers If outage analysis indicates unacceptable system conditions, MISO works with the GO/GOP in advance to coordinate the schedule as previously stated. 17
27 MISO Initiated Changes No rescheduling of approved outage requests will be initiated by MISO within 12 months of a generator planned outage (24 months for a nuclear Generation Resource) except when circumstances are due to severe weather or unplanned [urgent, emergency, or forced] outages. MISO may request rescheduling previously accepted outage requests when there is a reasonable expectation of an Emergency or other circumstance that may compromise the reliability of the Transmission System. GO/GOPs are compensated for eligible costs associated with rescheduling a generation outage due to system Emergency conditions. Rescheduled planned outages are eligible for compensation pursuant to Attachment BB of the Tariff provided the outage request was timely submitted or the request was not timely submitted and the request had been accepted. Request for cost recovery due to a rescheduled outage should be submitted to MISO Manager of Transmission Settlements. Documentation that provides justification of the expense, including proof of payment in the amount sought for recovery, should be provided at the time of the request. 18
28 If a request by MISO to reschedule a generator outage request is refused by the GO/GOP, MISO will change the request priority in CROW to Forced if the following conditions apply: The outage request provides less than 1 year advance notice Has not yet been approved Proposed outage causes a scheduling conflict as outlined The Forced outage will be included in the calculation of XEFORd as used to determine the unforced capacity (UCAP) value for the generation resource <<Refer to BPM-011 Resource Adequacy and Level-2, Manager - Resource Adequacy training for UCAP determination calculations>> Changes by Generator Owner/Generator Operator GO/GOPs can modify a previously submitted planned outage at any time up until 12 months prior to the time of the previously scheduled outage for non-nuclear Generation Resources and 24 months prior to the outage for Nuclear Generation Resources. Requests will be analyzed and accepted if the change does not result in a system Emergency condition or other circumstance that may compromise the reliability of the Transmission System. The date the outage change request is received will reset or establish a new outage request queue position. Request for a change prior to the start of an Approved outage: Submit additional request(s) for the time period(s) outside of the original outage window Cancel the original request and submit a new request for the revised outage period Submit a change request via the outage scheduling system Request for a change after the start of an Approved outage (i.e. more time is required to complete maintenance): Must notify MISO as soon as possible to inform of the need for additional time. Can be accomplished by submitting a Scheduled Change Request in CROW. Reason(s) for the potential delay and an estimate of the additional time needed must be included. MISO will review the extension for adverse impacts on system reliability including whether other approved planned requests need to be revoked due to new reliability issues. MISO will coordinate with the GO/GOP regarding any conflicts to the 18
29 outage extension. Any outage change request submitted using the CROW must first be accepted by MISO prior to that change being incorporated into reliability or market functions. Prior to accepting any outage change request, time must be provided to conduct a reliability assessment/study The following response times may be used as a guideline for outage change request submissions: Current day MISO will respond as soon as practical, normally within 4 hour of submitting the request. Current day + 1 MISO will respond as soon as practical, normally within 12 hours or midnight the day prior. Two or more business days in advance of the start date MISO will respond as soon as practical, and within the time period allowed for study of a new outage request. 18
30 Transmission Outage Priorities Planned Equipment is known to be operable with little risk of leading to a forced outage. As required for preventive maintenance, troubleshooting, or repairs that are not viewed as urgent work. Due to needed system improvements such as capacity upgrades, the installation of additional facilities, or the replacement of equipment due to obsolescence. Opportunity Equipment is known to be operable with little risk of leading to a forced outage; however the time line for submission of Planned outage priority has passed. Discretionary Equipment is removed from service for operational reasons such as voltage control, constraint mitigation as identified in an operating procedure, etc.. Urgent Equipment is known to be operable, yet carries an increased risk of a forced outage or equipment loss. The equipment remains in service until maintenance crews are ready to perform the work. Emergency Equipment is to be removed from service by operator as soon as possible because of safety concerns or increased risk to grid security. Forced Equipment is relayed out of service. 19
31 Transmission Outage Equipment Request Types: Out of Service Equipment is out of service. Normally Open Equipment is normally out of service and is identified as normally open in the Network Model. Normally Open request type is used to close (place in service) a normally open facility. Informational Used for outage events that are not covered by one of the other Outage Equipment Requests Types. Not an out of service event. Hot Line Work (HLW) Work is being performed on live or energized equipment. General System Protection Work is being performed on protection systems. Requestor shall specifically identify protection systems out of service and any modification to operation or behavior of system contingencies. 19
32 Criteria for Classification of Facilities The criteria for each class of facilities is detailed in the BPM For purposes of the BPM and this training module, Class I, Class II, and Class III Facilities are those Transmission facilities defined below, and are either: a) a Member s transferred facility or b) a facility for which MISO provides Reliability Coordinator services. Note: MISO does not have functional control over Class IV facilities and they are not subject to MISO RC authority; the classification is included here for information purposes. MISO works with the TOs to develop the Facility class list and any reclassification if studies support a change. The list is reviewed periodically, however, a formal review may be requested by MISO or a TO at any time to ensure that the list is complete and accurate. MISO may add facilities to the class list if studies reveal that the facility s scheduled outage may have an adverse impact on reliability or is in conflict with other outage requests 20
33 Class I Reliability or market impact on transmission system operations, and specifically, if one or more of the following conditions are met: 1. Facility is predicted to cause implementation of MISO Congestion Management Procedure, (i.e., binding constraints in real-time or in day-ahead processes) 2. Facility outage requires unit commitment via the Reliability Assessment Commitment (RAC) process 3. Facility outage is predicted to cause the implementation of TLR procedures 4. Coordinated Flowgates and Reciprocally Coordinated Flowgates (RCF) in MISO RC footprint: Facility is defined as part of the Flowgate (OTDF/PTDF) either as a monitored element or contingent element Facility affects TTC or AFC on the Flowgate 5. Facility is associated with an outage coordination agreement or process with an external MISO party, e.g., IESO, MAPP, SPP, TVA, etc. 6. Facility is a tie point > 100 kv between MISO RC footprint and an external party 7. Facility outage requires an associated mitigation procedure (i.e. Operating Guide / T-Note) 8. Facility outage is associated with an Interconnection Reliability Operating Limit (IROL) or a System Operating Limit (SOL) with wider area impacts 9. Facility outage impacts a Nuclear Plant s Interface Requirement 10. Facility is > 300kV (Excluding non-networked serving local load) kV facilities are not considered Class I, unless specific circumstance necessitate additional time required to coordinate an outage Class II Identified as not having a reliability or market impact on transmission system operations, and specifically, if one or more of the following conditions are met: 1. All 69kV facilities unless determined otherwise 2. Facility is > 100kV (Excluding non-networked serving and/or local load) and does not qualify under any of the Class I criteria Class III Identified as not having a reliability or market impact on transmission system operations, and specifically, if one or more of the following conditions are met: 1. Facility is identified as non-networked serving and/or local load 2. Facility does not qualify under any of the Class I or Class II criteria and MISO has functional control 20
34 Class IV A facility is eligible to become Class IV if all of the following conditions are met. 1. Is a facility for which functional control has not been transferred to MISO per the Transmission Owners Agreement and is a facility within the RC footprint that is not subject to MISO s Reliability Coordinator authority 2. Facility does not qualify under any of the Class I, Class II or Class III criteria. 20
35 Transmission Outage Schedule Requirements Transmission Operators (TOs ) must submit their long-term planned maintenance outage schedules for a minimum of a rolling 1 year period. Must be submitted to MISO as Planned outages and updated daily: All facilities 100 kv or under MISO functional control (including but not limited to transmission lines, transformers, breakers, reactive devises, etc..) Facilities < 100 kv and not under MISO functional control, if they are modeled in MISO s Network Model. These facilities are included in MISO next day security analysis (Class IV). Timetable for submissions: Outage Class I - minimum 14 Calendar Days in advance of the planned start date Class I Outage schedules submitted less than 14 days prior to the start of the outage will not be considered Planned Outages Outage Class II - minimum 7 Calendar Days in advance of the planned start date Outage Class III minimum 48 hours in advance of the planned start date 21
36 Outage Class IV no later than 1400 hours EST the day prior to the outage Note: timetable does not apply to outage request with the priority type of, Opportunity, Urgent, Emergency or Forced If an outage request contains two facilities of different classifications (i.e. Class I and Class II), the outage request will be treated as Outage Class I. All outage requests are evaluated by MISO to determine if the outage would create unreliable system conditions. The request will be scheduled for study with a response time determined by the lead-time of the outage request. All active outage records in CROW are used in the MISO AFC calculation and are posted to the SDX for use in congestion management and regional AFC applications. TOs must make efforts to plan and schedule outages of transmission facilities for periods when the likelihood of adverse system impacts is minimized. For example, non-urgent and non-emergency work (i.e., normal maintenance, construction) would not normally be planned and scheduled by the TOs during Peak periods. In the event that scheduled outages are required during peak system conditions, MISO s evaluation may include study at elevated load levels and varying flow pattern considerations. Outage Conflicts The outage Priority is used to determine the priority of the request with respect to resolving conflicts between outages. During the approval process, the outages are prioritized by type and preference is given to those outages that are considered urgent or Emergency in order to avoid conflicts. When two approved outage schedules are found to jeopardize grid security due to actual system conditions, it may be necessary to cancel a request in order to eliminate the conflict. MISO will work with TOs to eliminate any the conflict; this assistance could include the cancellation and/or rescheduling of the outage or the development of an Operating Guide. Refer to the BPM for an outline of treatment rules for conflicting outages. 21
37 Emergency Outages For emergency transmission maintenance conditions that endanger the safety of employees or the public, may result in damage to electrical facilities or private property. The Transmission Operators must notify MISO as soon as the need is identified. Approval by MISO for emergency maintenance is not required, however an outage schedule for the emergency maintenance must be submitted to MISO as soon as possible. Forced Outages MISO coordinates with the Transmission Operators to implement schedules for unplanned transmission maintenance due to a forced outage. Transmission Operators must contact the MISO RC or OEs to report forced equipment outages as soon as possible after the event is identified. Reported information must include the cause of the outage and the expected return to service time (if known). MISO and the Transmission Operator will develop an associated maintenance schedule for the outage and update the schedule periodically, as necessary. The Transmission Operator must develop an associated schedule for the 22
38 outage and submit the schedule as a forced outage into MISO OS. This must include an estimated end time and must be updated periodically, as necessary. 22
39 Opportunity Outages System Condition Opportunity System condition opportunities are characterized as an opportunity to take a facility out-of-service due to an unexpected change in system conditions/topology that would otherwise not allow the outage to proceed without significant reliability risk or efficient market operation. Examples include: a. An outage or dispatch change of a generating unit resulting in an opportunity outage on one of the transmission outlets to the plant. b. Unanticipated change in an existing outage stop or start times Equipment return to service earlier than anticipated allowing subsequent outages to proceed c. An unexpected transmission or generation outage occurs resulting in an opportunity outage on a transmission element. Evaluation and approval of system condition opportunity outage requests will ensure system reliability is maintained and include factors such as adequate time to process, need for operating guide, market dispatch, external coordination and significance of the opportunity. 23
40 Scheduling Opportunity Scheduling opportunities are characterized as opportunity due to resource availability: a. Crew/Parts/Tools availability, resources become available due to scheduling openings. b. Re-submission of outages left in Proposed status too long, MP must approve and submit the outage or it is automatically withdrawn by the system. c. (If the planned outage submission time frame is passed) d. Low risk repair that may have potential to escalate, preference to perform maintenance earlier if possible. e. (Example: adding gas to a breaker) f. General late submission, not on time for planned status. MISO will analyze scheduling opportunity outage requests as time permits without sacrificing studies required for the outage submittals that were submitted per the specified request time. Requirement of an operating guide, market dispatch or external coordination may be considered as cause for denial of an opportunity outage. 23
41 Systems Protection Work Transmission Operators must submit planned outage schedules to MISO pertaining to status of all Protection and Control Systems when one of the following criteria is met: 1. Transmission and Generation Protection systems: Expected mode of fault clearing when system protection is out of service or modified and would result in additional or multiple facilities taken out of service for a single event (N-1 contingencies are altered) 2. Status change from normal mode of operation for any of the following protection systems that the Transmission Operator owns or operates: Special Protection Schemes (SPS) and/or Remedial Action Systems (RAS) Under Voltage Load Shedding (UVLS) Under Frequency Load Shedding (UFLS) 3. Transmission Operator can submit planned outage schedules of other protection and control system changes as may be deemed necessary to maintain system reliability Outages pertaining to Protection and Control Systems must be submitted to MISO as soon as the outage requirements are determined but no less 24
42 than 48 hours in advance of the outage. MISO will evaluate the impact to the system reliability and an assessment of IROLs and SOLs where there is potential impact. 24
43 Outage Rescheduling Adjustments to start and/or completion times may be necessary due to various reasons as described below. Any change to an outage start/end time or cancellation of an outage that will occur the next day should be made prior to 1100 hrs. EST of the day prior to the scheduled outage start/end date to facilitate reliable and efficient market operations. Changes by Equipment Owner Request for a change prior to the start of an Approved outage: Submit additional request(s) for the time period(s) outside of the original outage window Cancel the original request and submit a new request for the revised outage period Submit a change request via the outage scheduling system To reduce the need for resubmission of an outage due to the widening of the original outage window, Transmission Operators should not consecutively schedule conflicting outages. MISO attempts to coordinate these outages to allow at least 48 hours between such outages to avoid a potential overlap of conflicting outages If the change results in a shorter timeframe being needed the 25
44 requester only needs to notify MISO; no additional approval will be necessary as long as the outage doesn t exceed the originally approved timeframe. Updating the outage information ensures that outages are represented accurately for security analysis and outage coordination. For outages that start late (after the planned start date) or end early (before the planned end date), the equipment owner must promptly contact the MISO RC or OE to report the changes. Once an outage has been Implemented, situations can arise that may require additional time to complete the maintenance. MISO determines if the desired maintenance extension will have an adverse impact on system reliability and/or will cause other approved planned requests to be revoked due to new reliability issues. MISO provides the results of its analysis to the Transmission Operator. The Transmission Operator has the option to: a. Complete the maintenance beyond the previously approved completion date provided there will be no adverse impact on system security and the Operator is willing to compensate other Operators whose approved planned maintenance is revoked by MISO b. Work overtime in order to complete all of the maintenance by the previously approved completion time c. Complete as much of the work as possible and return the facility to service by the previously approved completion time and submit a request to complete the remainder of the work at a later date. Changes Due to New Class 1 Transmission Facility Outage Requests If a planned Class I facility maintenance outage request impacts earlier approved outage requests, MISO will work with the requester who submitted the earlier approved request to determine if adjusting their dates/times is feasible. The equipment operator requesting the planned Class 1 outage is responsible for paying eligible costs incurred as a result of any rescheduled previously approved outage as defined my the MISO tariff. Changes Due to Security or Reliability MISO can revoke any previously approved planned transmission maintenance outage if forced Transmission Outages or other 25
45 circumstances compromise the integrity or reliability of the Transmission System or MISO Reliability Coordinator Area. Transmission Operators are compensated for eligible costs associated with an approved outage of a transmission facility that is revoked due to system security and regional reliability reasons according to MISO Tariff. 25
46 Outage Request Response Times MISO analyzes and responds to Transmission Outage requests submitted to MISO Outage Scheduler within a period of time determined by the leadtime of the request. The response times are: 2 Business Days for outages that have been submitted within two weeks of the start date. 5 Business Days for outages submitted between 2 weeks and 1 month in advance of the start date. 2 weeks for outages submitted between 1 and 3 months in advance of the start date. 3 weeks for outages submitted between 3 and 6 months in advance of the start date. 1 month for outages submitted 6 months or more in advance of the start date. This staggered approach expedites the study of outages that require immediate attention while addressing the need to provide adequate notice for requests that must be planned well in advance of the start date. When additional time is needed to study the transmission maintenance requests and/or prepare special operating procedures, MISO contacts the Transmission Operator within the response window to indicate additional study time is needed or that an Operating Guide is required. 26
47 The following response times may be used as a guideline for outage change request submissions: Current day MISO will respond as soon as practical, normally within 4 hour of submitting the request. Current day + 1 MISO will respond as soon as practical, normally within 12 hours or midnight the day prior. Two or more business days in advance of the start date MISO will respond as soon as practical, and within the time period allowed for study of a new outage request. Any outage change request submitted using the CROW must first be accepted by MISO prior to that change being incorporated into reliability or market functions. Prior to accepting any outage change request, time must be provided to conduct a reliability assessment/study 26
48 MISO Outage Scheduler MISO utilizes the Control Room Operations Window (CROW) application to document all transmission and generation outage schedules. User access is managed by the participant s designated Local Security Administrator (LSA) Generation Owners or Generator Operators only have access to the Generation Resources that they own or operate. Transmission Owners and Operators have access to the transmission equipment they own or operate, and limited access to Generation Resources in their footprint and transmission equipment of surrounding areas. Two methods for submission are available: OS Web Interface Web-based graphical user interface to directly interact with CROW. <<Refer to Level-3, Staff training for CROW and the CROW User s Guide for complete details>> OS XML API Interface Programmatic interface for integrating with CROW trough an XML Web Services interface. <<Refer to Level-3, Staff training for CROW and the 27
49 Outage Scheduler Market Participant Web Services Interface Programming Guide for complete details>> Access to equipment details is based on access rights, which means that Participants and Operators can create an outage schedule request on all equipment for which they have access rights. The outage scheduler is integrated with NERC SDX posting outages to SDX and retrieving external outages on an hourly basis. A planned outage report is posted to MISO OASIS to meet FERC requirements. The planned outage report only contains transmission outage schedules; generation resource outage schedules are not posted. Once an outage has been entered it is available on the report after the next hourly update. Backup Method In the event neither of the two methods above are available for an extended period of time, outage requests/schedules can be submitted to MISO OEs via using the MISO Outage Scheduling Form available to registered users via the MISO Extranet. Appendix B of the BPM provides a sample of the form including the contact address. 27
50 Key Elements to the Outage Scheduling Process The Outage Schedule process employs a workflow from start to finish. Once a request is received either saved as a Proposed request, under the participant s control, or a Submitted request, beginning the MISO internal process each request progresses through the workflow and it s state is promoted or deprecated depending on the process output. Request Actions Initial Request Start of the process. Participants can save the request as Proposed or Submitted Change Request Request modification can be made in the Submitted, Study and Approved status to modify the equipment requested or planned Start/End times. MISO can either approve the change request and leave the outage in its current status or approve the change request and send the outage back to submitted status. Cancellation Request Used to cancel an outage request once the request is beyond the submitted status. Cancel Request is not approved by MISO but is acknowledged. 28
51 Schedule Change Request Used during the Implementation Status to modify Planned End time. Two types are available: The first is Non-Forced where the schedule change is a request; subject to MISO approval. The second is Forced where the schedule change is not avoidable under given circumstance and is only acknowledged by MISO. Process Status Proposed If outage request is saved as Proposed, the outage request remains in the system under full revision control of the Participant until it is approved by the Participant, which changes the status to Submitted. If the outage does not receive Participant approval within 30 days of the planned start date the outage is automatically Withdrawn. A Proposed outage request qualifies for outage queuing in conflict resolution. Submitted Participant places the outage request in Submitted status once they re confident the outage will proceed or request the acceptance response from MISO. Study Once the active study process begins, the MISO changes the outage status to Study. Pre-Approved Pre-Approved status is used to designate outage request that were approved based on long lead studies and may need additional analysis closer to the planned start date or finalization of an Operating Guide. Once the restudy is complete or final operation guide is posted, the outage status is changed to Approved. Requests with Pre-Approved status have the same rights as request with Approved status. Approved If MISO approves the request after the study has been completed, the status changes to Approved. If an emergency outage is submitted, the status immediately becomes Approved. Approved state indicates that the outage request is ready for 28
52 implementation. Implemented Once the actual start time has been entered, indicates the outage is in progress. Request End-States Withdrawn The Participant can withdraw an outage request while it is still in Proposed status. Once in Submitted, Study or an Approved status, the request must be Cancelled. Denied An outage request that is in Study mode can be Denied. If MISO denies the request, the status changes to Denied; a denied outage request can be modified and resubmitted. Denied state indicates that the outage request was not approved for implementation. Cancelled The Cancelled state indicates the outage has been cancelled by the requestor. Cancelled outages can be reinstated by the Participant, provided the planned start of the outage falls within the business rules for lead time submission. Revoked Once an outage request has been Approved, it can be Revoked at any time (i.e., before or during the outage). Recalled An outage that has been implemented can be recalled due to system emergency or conservative operations conditions. Recalled indicates that the outage request had been implemented, but that it was returned without having completed all the necessary work. Completed Once the actual end time has been entered, indicates the outage is no longer in progress. External Outage States (not shown on diagram) <<Outages external to MISO: PJM, TVA, SPP, IESO, etc.>> Active 28
53 Active is only applicable to external outages from the NERC SDX. Active indicates that the request is present in the SDX process. Inactive Inactive is only applicable to an external outage from the NERC SDX. Inactive indicates that the request is no longer present in the SDX process. 28
54 Transmission Outage Analysis and Models Study priority is based on the request type and date and time of the submittal. MISO recognizes the advantages of prioritizing by outage type and gives preference to the more critical outages. MISO Model-on-Demand (MOD) process is the basis for development of (off-line) bus-branch operational planning models. Primary model used for outage analysis. MOD planning model differs from the operational planning model; MOD planning model: System topology is adjusted based on pending MOD projects and equipment in-service dates. Operational Ratings (MISO EMS ratings set) Summer/Winter Ratings seasons used System Load and applicable outages based on NERC SDX data System Interchange and Generation Dispatch is adjusted based on historic operation levels/market patterns MISO utilizes planning and study network applications to analyze planned transmission outage requests. Analysis includes power flow, contingency analysis, and stability analysis, as necessary, to identify: 29
55 Violation of pre and post-contingent thermal limits Violation of pre and post-contingent voltage limits Violation of pre-determined stability limits In General, if outage analysis indicates next-contingency system conditions would be acceptable (i.e., no overloads beyond emergency ratings, excessive or inadequate system voltages, loss of system stability, etc..), MISO approves the request and notifies the requestor. Under certain limited conditions, outage approval may be subject to additional review and analysis to ensure regional security. Multiple contingencies (N-2) or the second next contingency (N-1-1) may be considered during the outage approval analysis. This analysis will be made in conjunction with the transmission operator and reliability coordinator assessment of risk. Analysis of such conditions will be limited to extreme conditions or previously identified scenarios involving cascading events, loss of significant load/generation, nuclear power plant operations, or IROL interfaces. Outage evaluation may also include analysis at elevated Load levels and/or additional sensitivity analysis (e.g., increased transfers to stress interfaces or wind impact analysis) to account for forecast uncertainty. If outage analysis indicates unacceptable system conditions, MISO works with the requestor to develop remedial steps to be taken in advance of such proposed outage. This includes scheduling the outage based on alternate start and end times submitted by the equipment owner, the use of existing Operating Guides, or the development of new Operating Guides. If no remedial steps are possible, MISO normally denies the request and provides an acceptable timeframe in which the maintenance can be performed recognizing the priority of scheduling transmission outage work to maintain transmission system reliability. Note: MISO also performs steady state voltage analysis and voltage stability analysis on certain identified reactive elements. These are elements associated with known voltage problems in MISO Reliability Authority Area and the voltage analysis is done in conjunction with the normal thermal assessment of the outage request. The elements are identified and listed in Transmission Facility Outage Class list. 29
56 Operating Procedures Specific to Outages MISO recognizes the need for procedures to avoid jeopardizing the integrity of the system while continuing to allow maintenance and system improvements to proceed. An outage request analysis that identifies conditions that impact system security would require the submittal of an Operating Guide by the Transmission Operator making the request or development of a Transmission Notification (T-Note) by MISO. Operating Guides Requestors are required to work with MISO staff to develop and/or provide a specific Operating Guide for the maintenance outage. Must be finalized no fewer than three days prior to the outage in order for MISO to review the steps and verify the results of the implementation. If an Operating Guide is not provided in the appropriate amount of time, the outage will be denied and the requestor must make a new request for a later date. Emergency Operating Guides are developed as quickly as possible to mitigate system conditions that arise from unplanned outages or other unanticipated conditions. The Operating Guide is a detailed plan of action that will be implemented in the event of an Emergency condition. 30
57 The details of Operating Guide development, including the minimum required information, is provided in Appendix A of the BPM Standing Operating Guides will be considered for use during a planned outage if the Guide contains sufficient details and the requestor/reviewer verifies the effectiveness of the Guide in addressing the specific outage request during anticipated system conditions of the outage timeframe. Operating Guides for outages that cause Flowgate overloading may be used in determining the System Operating Limit (SOL) that will be used for initiating TLR action. When system conditions necessitate a change in the Operating Guide once an outage has begun, a new Operating Guide will be requested. Any revision to the Operating Guide must be submitted in writing and must represent operating conditions of the current system state. If no revision has been submitted, MISO will continue to operate the system under the present Operating Guide and address TLR issues accordingly. MISO posts Operating Guides that are presently in effect on the Reliability Authority web page found on the MISO extranet. T-Notes T-Notes are a short form of an Operating Guide. When an outage results in unfavorable conditions that can be resolved using the market congestion management procedures, a T-Note may be used in place of an Operating Guide. T-Notes may also be developed to convey known outage conditions that may restrict system access/performance that doesn t otherwise require an Operating Guide. T-Notes are developed by MISO outage coordination engineers in collaboration with the Transmission Operator. Time requirements for development and review T-Notes are the same as for Operating Guides. T-Notes are contained within the outage scheduler as part of the outage schedule details. 30
58 Market Impacts Mitigation for transmission outage impact can include MISO market redispatch, TLR, switching options, and operating guides. Redispatch of non-miso market generators is not typically an option unless provided for under a joint operating agreement and coordinated otherwise. Once an outage has started, any acceptable action to relieve loading is permitted. Action Definitions: Outage Load Equipment outages that directly result in loss of service to end use Load, excluding radially served Load. Load transfers must be noted in the request record. Gen Outlet Reduction Equipment outage leads to requiring Generator output limitation to prevent violation of operating criteria. This outage type only applies to generation with a scheduled commitment. Non-firm TLR Equipment outage requires activation of NERC TLR Level 3 to prevent violation of operating criteria. 31
59 Firm TLR Equipment outage requires NERC TLR Level 5 to avoid violation of operating criteria. Redispatch Action to avoid NERC TLR 4/5 with costs paid for by requestor for maintenance and construction outages. This outage type can include implementation of reliability redispatch for urgent outages. 31
60 Reliability Subcommittee (RSC) The Reliability Subcommittee will provide a forum to discuss issues within the context of the MISO tariff, Transmission Owner Agreement, Amended Balancing Authority Agreement, MISO seams agreements, NERC Reliability Standards, applicable Regional Standards, and other applicable documents for direction on implementation and maintenance of reliability and tariff administration functions at MISO within the MISO footprint and between MISO and adjacent areas. The purpose of the Reliability Subcommittee is for members to advise, guide, and provide recommendations for decision making in areas affecting reliability. Examples include, but are not limited to: Coordination Agreements MISO reliability policies, processes, and procedures NERC Reliability Standards and Standards Development Collaboration MISO s Operational Performance and Reliability Metrics MISO Open Access Transmission and Energy Markets MISO Tariff and Business Practice Manuals Provide support and coordination for Compliance activities Meeting Schedule Meetings generally occur on the 4 th Tuesday and Wednesday of every month Operational Planning Working Group (OPWG) Provides a forum to develop, review, and recommend operational planning practices (e.g. operating studies, outage coordination analyses, seasonal 32
61 assessments, operating guides, operating procedures, etc..) to MISO under the direction of the Reliability Subcommittee (RSC). The OPWG draws upon the collective knowledge of the transmission owners within the MISO reliability footprint and other industry participants providing advice, guidance, and recommendations to MISO staff and the RSC. The purpose is to assist MISO in executing its responsibilities as set forth in the Tariff and TOA. The Operations Working Group - CLOSED (OWG-CLOSED) Provides a forum comprised of operations personnel from MISO and entities in the MISO Reliability Coordination (RC) Area. One of the principal goals for the OWG-CLOSED is to promote the reliability of the bulk electric system (BES) within the MISO RC Area and neighboring areas. This goal is supported by reviewing the evaluation of significant events on the BES presented by the MISO. The evaluation of the events should include analysis to determine the cause of the event, recommendations and lessons learned with implementation of corrective actions. The OWG-CLOSED accepts assignments from the RSC related to reliable operations of RC, Balancing Authority (BA) and Transmission functions and coordinates issues with neighboring entities. The OWG-CLOSED will review, discuss and make proposals to the RSC. Items may include: MISO Procedures related to Real Time Operation (EOP, AOP, NOP & Semi Public) Significant events on the bulk electric system as listed: Exceeding SOL for greater than 30 minutes Exceeding IROL Transmission System Emergency TLR Level 5 Reports Conservative Operations Reliability Directives (MISO and TOP) Maximum Generation Emergency Events NERC EEA Level declarations NERC or Regional Entity (RE) Event Analysis Reports as appropriate Manual Redispatches with Summary Statistics Local Transmission Emergency Load Reduction Events Disturbance Control Standard Events Note: CLOSED meansthatmeetings are restricted to those parties who meet applicable guidelines. All discussions will be in accordance with the antitrust guidelines established by NERC. Calendar of Meetings Meeting schedules, committee charters, and previous meeting materials are available 32
62 on the MISO public web site. 32
63 33
64 34
65 35
66 36
67 37
68 38
69 39
70 40
Generation and Transmission Interconnection Process
PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents
ALCOA POWER GENERATING INC. Long Sault Division. Open Access Transmission Tariff
Alcoa Power Generating Inc. Long Sault Division ALCOA POWER GENERATING INC. Long Sault Division Open Access Transmission Tariff The following sheets reflect all revisions submitted to the Federal Energy
Market Solutions to Loop Flow
Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution
Transmission Function Employees Job Titles and Descriptions 18 C.F.R 358.7(f)(1)
Date of Last Change to the Provided Information August 27 th, 2015 Director, Transmission Operations The employee in this position is responsible for effectively managing the operation of FirstEnergy Utilities
Summary of CIP Version 5 Standards
Summary of CIP Version 5 Standards In Version 5 of the Critical Infrastructure Protection ( CIP ) Reliability Standards ( CIP Version 5 Standards ), the existing versions of CIP-002 through CIP-009 have
DISCUSSION PAPER: Peak Reliability Performance Metrics
DISCUSSION PAPER: Peak Reliability Performance Metrics Executive Summary Performance metrics are critical for any organization in order to encourage improvement, effectiveness and efficiency; to assess
NERC Cyber Security Standards
SANS January, 2008 Stan Johnson Manager of Situation Awareness and Infrastructure Security [email protected] 609-452-8060 Agenda History and Status of Applicable Entities Definitions High Level of
Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055
Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights
Master/Local Control Center Procedure No. 13 (M/LCC 13) Communications Between the ISO and Local Control Centers
Master/LCC Procedure No. 13 - Communications Master/Local Control Center Procedure No. 13 (M/LCC 13) Communications 1. References... 2 2. Background... 3 3. Responsibilities... 3 4. Procedure... 4 4.1
ATTACHMENT G. Network Operating Agreement
ATTACHMENT G Network Operating Agreement 1. PURPOSE OF NETWORK OPERATING AGREEMENT The purpose of this Agreement is to identify contractual requirements related to Network Integration Transmission Service
New Brunswick Electricity Business Rules
New Brunswick Electricity Business Rules Table of Contents Chapter 1 Chapter 2 Chapter 3 Chapter 4 Administration and Participation Transmission Planning and Connections Reliable Operations Billing and
Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering
Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.
When this standard has received ballot approval, the text boxes will be moved to the Guidelines and Technical Basis section of the Standard.
CIP-002-5 Cyber Security BES Cyber System Categorization When this standard has received ballot approval, the text boxes will be moved to the Guidelines and Technical Basis section of the Standard. A.
Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards
Updated July 11, 2013 Job Descriptions Job Title Reports To Job Description TRANSMISSION SERVICES VP Compliance & Standards Develops strategy and business plans for efficient, safe, reliable, regulatorycompliant
Generator Interconnection and Deliverability Study Methodology Technical Paper
Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:
PROCEDURE. Part 3.1: Metering Service Provider (MSP) Registration, Revocation, and Deregistration PUBLIC. Market Manual 3: Metering. Issue 14.
PUBLIC MDP_PRO_0007 PROCEDURE Market Manual 3: Metering Part 3.1: Metering Service Provider (MSP) Registration, Revocation, and Deregistration Issue 14.0 This document provides an overview of the steps
Duke Energy Progress Standards of Conduct Transmission Function Employee Job Titles and Job Descriptions 9/1/13
Duke Energy Progress Standards of Conduct Transmission Function Employee Job Titles and Job Descriptions 9/1/13 Transmission Operations & Planning Carolinas Power System Operations Director Power System
Scope of Restoration Plan
RWG Area Restoration Review Worksheet (10/28/09) EOP-006-02 Directory 8 EOP-005 NYSRG Rule G Text Restoration Plan Requirement R1.Each Reliability Coordinator shall have a Reliability Coordinator Area
Appendix C-2. Entergy Services, Inc. June 8, 2016
Appendix C-2 Preliminary Due Diligence List (Existing Resources) For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016
SOP-RTMKTS.0060.0005 - Test and Approve Operations Software Applications. Contents
SOP-RTMKTS.0060.0005 - Test and Approve Operations Software Applications Contents 1. Objective... 2 2. Background... 2 3. Responsibilities... 3 4. Controls... 4 5. Instructions... 5 5.1 Document Operations
Qualifying Facility Maintenance Outage Scheduling Procedures
I. Applicability The Qualifying Facility ( Maintenance Procedures ) apply to the scheduling of an outage on a QF generating unit as a result of planned maintenance to keep the generating facility in suitable
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Reliability Technical Conference Docket No. AD16-15-000 Prepared Statement of Mark Rothleder on behalf of the California Independent System
FRCC Coordination Procedure. Title: FRCC Reliability Coordinator Contingency Analysis Monitoring Criteria
A. Purpose: The FRCC Reliability Coordinator (RC) Contingency Analysis (CA) application is essential to maintaining the reliability of the FRCC Bulk Electric System. The application has the capability
Section 4: Scheduling Philosophy & Tools
Welcome to the Scheduling Philosophy & Tools section of the PJM Manual for Scheduling Operations. In this section you will find the following information: A description of the PJM OI s scheduling philosophy
Specific amendments to the Capacity Allocation and Congestion Management Network Code
Annex: Specific amendments to the Capacity Allocation and Congestion Management Network Code I. Amendments with respect to entry into force and application The Network Code defines deadlines for several
CIP-010-2 Cyber Security Configuration Change Management and Vulnerability Assessments
CIP-010-2 Cyber Security Configuration Change Management and Vulnerability Assessments A. Introduction 1. Title: Cyber Security Configuration Change Management and Vulnerability Assessments 2. Number:
Electric Field Operations Organization
NSTAR Electric Transmission Function Job Summaries Electric Field Operations Organization Vice President, Electric Field Operations (Transmission) This position has primary responsibility for the planning,
Outage Scheduling Manual
MANUAL 29 Outage Scheduling Manual July 2015 Version: 4.3.1 Effective Date: 07/29/2015 Committee Acceptance: 6/11/2015 OC This document was prepared by: NYISO Energy Market Operations New York Independent
4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s)
A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure
PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement
PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement Asanga Perera Market-to-Market Lead Market Implementation Committee August 12, 2015 Purpose Overview This presentation provides
Rules on Southern Companies Energy Auction Participation
Southern Company Services, Inc. First Revised Sheet No. 20B Superseding Original Sheet No. 20B Rules on Southern Companies Energy Auction Participation 1.0 Participation; Definitions 1.1 Southern Companies
COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011
COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and
GIP. 3.2.3 Net Zero Interconnection Service.
GIP and GIA Energy Displacement Agreement shall mean an agreement between an Interconnection Customer with a commercially operating Generating Facility on the Transmission Provider s Transmission System
-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14
PSEG-Long Island Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA s Radial Distribution Systems -1- PSEG-LI Update of LIPA
THE CONNECTICUT LIGHT AND POWER COMPANY, DBA EVERSOURCE ENERGY TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 20
TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 20 1. Applicability 1A. The following Terms and Conditions shall apply to every registered Electric Supplier authorized to do business within Connecticut
IESO Supply Deliverability Guidelines
PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents
Methodology for Merit Order Dispatch. Version 1.0
Methodology for Merit Order Dispatch Version 1.0 25 th April 2011 TABLE OF CONTENTS 1. OBJECTIVES... 1 2. ROADMAP FOR IMPLEMENTATION... 1 3. DEFINITIONS... 3 4. OPERATIONS PLANNING... 3 4.1. General Considerations...
3. Purpose: To improve the reliability of the Bulk Electric System by requiring the reporting of events by Responsible Entities.
A. Introduction 1. Title: Event Reporting 2. Number: EOP-004-2 3. Purpose: To improve the reliability of the Bulk Electric System by requiring the reporting of events by Responsible Entities. 4. Applicability:
N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS
N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers
Update on Northeast Seams Issues. January 9, 2008 NYISO Management Committee Meeting
Update on Northeast Seams Issues January 9, 2008 NYISO Management Committee Meeting Status of Seams Projects Current Deliverables Project 1. Intra-Hour Transaction Scheduling NYISO and ISO-NE have documented
Virginia Commonwealth University School of Medicine Information Security Standard
Virginia Commonwealth University School of Medicine Information Security Standard Title: Scope: Business Continuity Management Standard for IT Systems This standard is applicable to all VCU School of Medicine
FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003
F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify
Energy Efficiency Measurement & Verification
PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 02 Effective Date: 12/17/2015 Prepared by PJM Forward Market Operations PJM 2015 PJM 2008 Revision, Effective Date: i Table of Contents
How To Use Adobe Software For A Business
EXHIBIT FOR MANAGED SERVICES (2013V3) This Exhibit for Managed Services, in addition to the General Terms, the OnDemand Exhibit, and any applicable PDM, applies to any Managed Services offering licensed
Load Dispatcher (Class Code 5223) Task List
A. Load Dispatching, General Load Dispatcher (Class Code 5223) Task List 1. Prior to work shift speaks to Load Dispatcher(s), reviews hardcopy and computer logs, and looks at the dispatcher's diagram board
PJM LMP Market Overview
PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people
Ms. Rae McQuade President & COO, North American Energy Standards Board
NORTH AMERICAN ENERGY STANDARDS BOARD 801 Travis, Suite 1675 Houston, Texas 77002 Phone: (713) 356-0060 Fax: (713) 356-0067 email: [email protected] Web Site Address: www.naesb.org The Honorable Kimberly
References... 4. Appendices... 5. I. INTRODUCTION... 6 A. Background... 6 B. Standards... 6
ISO New England Operating Procedure No. 14 - Technical Requirements for Generators, Demand Resources, Asset Related Demands and Alternative Technology Regulation Resources Effective Date: January 29, 2015
Alberta Reliability Standard Cyber Security Security Management Controls CIP-003-AB-5
A. Introduction 1. Title: 2. Number: 3. Purpose: To specify consistent and sustainable security management controls that establish responsibility and accountability to protect BES cyber systems against
THIS SERVICE LEVEL AGREEMENT DEFINES THE SERVICE LEVELS PROVIDED TO YOU BY COMPANY.
THIS SERVICE LEVEL AGREEMENT DEFINES THE SERVICE LEVELS PROVIDED TO YOU BY COMPANY. Capitalized terms used herein but not otherwise defined shall have their respective meanings set forth in the End User
CIP 010 1 Cyber Security Configuration Change Management and Vulnerability Assessments
CIP 010 1 Cyber Security Configuration Change Management and Vulnerability Assessments A. Introduction 1. Title: Cyber Security Configuration Change Management and Vulnerability Assessments 2. Number:
Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out
1 2 3 Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out Speaker Notes: Drive-In refers to transactions that originate
BT Assure DoS Mitigation UK
BT Assure DoS Mitigation UK Annex to the Internet Connect UK Schedule Contents A note on we and you... 2 1. Service Summary... 2 2. Service Standard Components... 2 3. Service Options... 2 4. Service Management
PROCEDURE. Part 4.3: Real-Time Scheduling of the Physical Markets PUBLIC. Market Manual 4: Market Operations. Issue 44.
PUBLIC IMP_PRO_0034 PROCEDURE Market Manual 4: Market Operations Part 4.3: Real-Time Scheduling of the Physical Markets Issue 44.0 This procedure provides guidance to Market Participants on the Real-time
ReliabilityFirst CIP Evidence List CIP-002 through CIP-009 are applicable to RC, BA, IA, TSP, TO, TOP, GO, GOP, LSE, NERC, & RE
R1 Provide Risk Based Assessment Methodology (RBAM) R1.1 Provide evidence that the RBAM includes both procedures and evaluation criteria, and that the evaluation criteria are riskbased R1.2 Provide evidence
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
PROCEDURE. Ontario Technical Feasibility Exception PUBLIC. Issue 0.2 IESO_PRO_0680
PROCEDURE PUBLIC IESO_PRO_0680 Ontario Technical Feasibility Exception Issue 0.2 This procedure provides guidance to TFE applicants on the Ontario-adapted NERC Technical Feasibility Exception process.
TERMS AND CONDITIONS
Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator
CURTAILABLE RATE PROGRAM FOR INDIVIDUAL CUSTOMER LOADS
Page 1 of 16 CURTAILABLE RATE PROGRAM FOR INDIVIDUAL CUSTOMER LOADS PROPOSED TERMS AND CONDITIONS January 2015 Page 2 of 16 TABLE OF CONTENTS 1. Definitions... 3 2. Curtailable Load Options... 6 3. Nomination
Change Management Process. June 1, 2011 Version 2.7
Change Management Process June 1, 2011 Version 2.7 Contents Document Control... 3 Overview... 4 Definition of a Change... 5 Description... 5 Objectives... 5 Key Terms & Definitions... 6 Change Management
SOUTH CAROLINA. Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)
SOUTH CAROLINA Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard) 1. Overview: This Standard contains the requirements, in addition
Alberta Reliability Standard Cyber Security System Security Management CIP-007-AB-5
A. Introduction 1. Title: 2. Number: 3. Purpose: To manage system security by specifying select technical, operational, and procedural requirements in support of protecting BES cyber systems against compromise
Energy Management System (EMS) Model Updates and Quality Assurance (QA)
PJM Manual 3A: Energy Management System (EMS) Model Updates and Quality Assurance (QA) Revision: 10 Effective Date: June 25, 2015 Prepared by: Operation Support Division PJM 2015 PJM 2007 Revision 0, Effective
Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure
No. 2310 Table of Contents Purpose... 2 1. Responsibilities... 2 2. Scope/Applicability... 2 2.1 Background... 2 2.2 Scope / Applicability... 2 3. Detail... 3 3.1 Energy Dispatching... 3 3.1.2 Real-Time
THE CONNECTICUT LIGHT AND POWER COMPANY TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 18
TERMS AND CONDITIONS FOR ELECTRIC SUPPLIERS PAGE 1 OF 18 1. Applicability 1A. The following Terms and Conditions shall apply to every registered Electric Supplier authorized to do business within Connecticut
Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC
Appendix A Glossary For 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 Website means the internet website https://spofossil.entergy.com/entrfp/send/2016ellrenewablerfp/index.htm.
GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1
PUBLIC GOT-1 GLOSSARY Glossary of Terms for Capacity Based Demand Response Issue 3.0 This document provides a glossary of terms with definitions used in the Capacity Based Demand Response program. Public
APPENDIX A: SYSTEM OF ASSURANCE OF NET METERING ELIGIBILITY
APPENDIX A: SYSTEM OF ASSURANCE OF NET METERING ELIGIBILITY Sections 1. Purpose... 1 2. Scope... 1 3. Definitions... 1 4. Obtaining a Cap Allocation... 3 5. Duties of the Administrator and Fees... 5 6.
124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Communication Protocols for Public Utilities ORDER NO.
124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G. Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.
BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE
BUSINESS RULES GOVERNING CONTINGENCY RESERVE PROVIDED BY BATCH-LOAD DEMAND RESPONSE This paper describes the issues associated with using Batch-Load Demand Response i resources to provide Contingency Reserve
CIP-003-5 Cyber Security Security Management Controls
A. Introduction 1. Title: Cyber Security Security Management Controls 2. Number: CIP-003-5 3. Purpose: To specify consistent and sustainable security management controls that establish responsibility and
Distributed Generation: Frequently Asked Questions
Distributed Generation: Frequently Asked Questions 1) What is distributed generation (DG)? Generating technologies located close to where the electricity is being used that are connected to the electric
AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233
SA 2507 INTERSTATE POWER AND LIGHT COMPANY E&P AGREEMENT VERSION 1.0.0 EFFECTIVE 3/1/2013 AGREEMENT FOR PRELIMINARY ENGINEERING DESIGN MISO PROJECT J233 Agreement for Preliminary Engineering Design - MISO
An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009
An Overview of the Midwest ISO Market Design Michael Robinson 31 March 2009 The Role of RTOs Monitor flow of power over the grid Schedule transmission service Perform transmission security analysis for
Control Module, Inc. Software Support Plans
Control Module, Inc. Software Support Plans In addition to the resources of the Control Module, Inc. support Web site, the company offers annual support plans to meet your support needs. Each support plan
2016 Santee Cooper Solar Home & Solar Share Home Program Manual
2016-17 2016 Santee Cooper Solar Home & Solar Share Home Program Manual Version 03232016 This Program Manual is intended to serve as a reference for Santee Cooper s residential Customers that are interested
Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS
Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS EVP, Chief Operations Officer, has primary responsibility for the overall planning, operations and control of the transmission
