PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement

Size: px
Start display at page:

Download "PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement"

Transcription

1 PJM Seams Update: Day-Ahead M2M Revisions to MISO- PJM Joint Operating Agreement Asanga Perera Market-to-Market Lead Market Implementation Committee August 12, 2015

2 Purpose Overview This presentation provides an informational update on projected MISO-PJM Joint Operating Agreement (JOA) revisions Key Takeaway PJM intends to file a MISO-PJM JOA enhancement by August 31, 2015 This enhancement is designed to accommodate MISO-PJM Day-Ahead (DA) Firm Flow Entitlement (FFE) exchange implementation 2

3 Background In the Joint and Common Markets (JCM) efforts, MISO and PJM have been discussing an initiative to exchange FFEs in DA This initiative will enhance RTOs DA M2M coordination practices and their Real- Time (RT) M2M settlement payments According to the JOA provisions, currently for projected M2M Flowgates, RTOs limit each others market flows to their FFEs RTOs have discovered that there could be an opportunity to exchange unused FFEs in a DA basis for targeted M2M Flowgates in an attempt to: Minimize Joint Bid Production Cost - Overall savings to RTOs Minimize Real-time M2M payments Improve FTR funding 3

4 JOA ICP Revisions for DA JOA Interregional Coordination Process (ICP) section 4 describes the steps to perform the DA FFE exchange However, the current language could be enhanced to: Provide flexibility and clarity in executing this protocol Provide consistency between the DA and RT M2M settlement calculations 4

5 Flexibility and Clarity JOA ICP Revisions for DA Flexibility, Clarity and Consistency ICP Section 4 requires this protocol to be utilized infrequently, since the term infrequently is vague and since the RTOs would like to utilize this protocol in a flexible manner, RTOs plan to remove this provision ICP Section 4.1 requires this protocol to be executed prior to 08:00 EST and 10:00 EST on the day before the operating day, since the RTOs DA market execution timeline could be revised in the future, RTOs would like to introduce flexibility to this provision by removing explicit time requirements Instead of explicit times, RTOs will introduce a requirement for FFE exchange request to occur an hour prior to DA bidding deadline 5

6 Clarity JOA ICP Revisions for DA Flexibility, Clarity and Consistency RTOs have agreed to cancel the FFE exchange agreement under certain circumstances RTOs will only exchange FFEs if the Flowgate Shadow Price is below a certain threshold defined by the requesting RTO If the RTOs realize that the FFE request cannot be achieved below the requesting RTO s defined threshold, RTOs will cancel the FFE exchange This cancelation would occur within an hour of RTOs DA clearing process RTOs are introducing a new provision to ICP section 4.1 to clarify this agreement 6

7 JOA ICP Revisions for DA Flexibility, Clarity and Consistency Consistency ICP Section 4.2 defines the DA M2M settlement equation, this equation is utilizing terms that are inconsistent with the terms utilized to define RT M2M equation defined in ICP Section 3.2 In an attempt to introduce consistency between the DA and RT M2M settlement equations, RTOs plan to revise ICP Section 4.2 7

8 Next Steps PJM intends to file the JOA ICP enhancements with FERC by 8/31/2015 requesting an effective date of 9/30/2015 8

9 Appendix A JOA Revisions 9

10 ICP Section 4 Revisions Flexibility and Clarity 4 Day-Ahead Energy Market Coordination The Day-Ahead energy market coordination focuses primarily on ensuring that the Day-Ahead scheduled flows on all M2M Flowgates are limited to no more than the Firm Flow Entitlements for each RTO. When system conditions can accommodate the change, either RTO may request that the Day-Ahead flow limit be raised above its Firm Flow Entitlement. Normally, this protocol will be utilized infrequently and only when the need for additional congestion relief assistance is predictable on a Day-Ahead basis. 10

11 ICP Section 4.1 Revisions Flexibility 4.1 Day-Ahead Energy Market Coordination Procedures An M2M Flowgate limit exception is a request to alter the M2M Flowgate limits, as described above, that will be modeled in the Day- Ahead markets and/or the Day-Ahead reliability analysis. The following procedure will apply for designating M2M Flowgate limit exceptions: 1. Prior to 0800 EST on the day before the Operating Day, iif the Requesting RTO identifies a need to utilize more of an M2M Flowgate than it is entitled, it may request the Responding RTO to lower its Day-Ahead Market limit below its Firm Flow Entitlement by a specified amount and for a specified range of hours. The Requesting RTO must request the adjustment from the Responding RTO as soon as possible but not later than one hour prior to the Responding RTO s deadline for submitting bids and offers in the day-ahead market. 2. If the Responding RTO agrees to provide the limit reduction, it will communicate the approved amount to the Requesting RTO by 1000 ESTas soon as possible but not later than to the Requesting RTO s deadline for submitting bids and offers in the Day-Ahead Market. 3. The Requesting RTO may increase its limit on the M2M Flowgate by the agreed upon and specified amount and for the specified range of hours. 4. Either Party may rescind the agreement up to one hour after the Responding RTO s deadline for submitting bids and offers in the day-ahead market. 11

12 ICP Section 4.1 Revisions Consistency 4.2 Day-Ahead Energy Market Settlements The Day-Ahead payment for the RTO that is requesting congestion relief will be calculated as follows: Requesting RTO Payment to Responding RTO = Approved Day-Ahead Adjustment for M2M Flowgate * Responding RTOs M2M Flowgate constraint shadow price. Payment = Approved MW *Transmission Constraint Shadow Price in Responding RTOs Dispatch Solution 12

13 Appendix B Reference to JCM Benefits Analysis 13

14 DA FFE Exchange Benefits Example Breed_Wheatland 345 flo Jefferson_Rockport 765 Flowgate for 1/11/2013 $1.2 million RT JOA Settlement between MISO and PJM On average, PJM s Real Time Market Flow is 198 MW more than PJM s FFE On average, MISO s Real Time Market Flow is 152 MW less than MISO s FFE What happens when RTOs exchange FFEs using the DA FFE exchange protocol? 14

15 DA FFE Exchange Benefits Example 20MW Exchange (MISO -> PJM) 15

16 DA FFE Exchange Benefits Example 60% of MF-FFE Exchange (MISO -> PJM) 16

17 Reference to JCM slides for DA FFE Exchange Benefits 17

Firm Flow Entitlement on M2M Flowgates Readers' Guide. Last Updated: February 01, 2016 Version: 4.0

Firm Flow Entitlement on M2M Flowgates Readers' Guide. Last Updated: February 01, 2016 Version: 4.0 Firm Flow Entitlement on M2M Flowgates Readers' Guide Last Updated: February 01, 2016 Version: 4.0 1 Table of Contents 1 DISCLAIMER...3 2 INTRODUCTION...3 3 GLOSSARY OF TERMS...3 4 FFE FILE...3 4.1 DESCRIPTION...

More information

Market Solutions to Loop Flow

Market Solutions to Loop Flow Market Solutions to Loop Flow Robert Pike Director, Market Design New York Independent System Operator Business Issues Committee September 9, 2009 1 Agenda Background Recommendation Next Steps Solution

More information

PJM LMP Market Overview

PJM LMP Market Overview PJM LMP Market Overview Andrew Ott Senior Vice President, Markets June 10, 2010 PJM as Part of the Eastern Interconnection 6,038 substations KEY STATISTICS PJM member companies 600+ millions of people

More information

Convergence Bidding Tutorial & Panel Discussion

Convergence Bidding Tutorial & Panel Discussion Convergence Bidding Tutorial & Panel Discussion CAISO June 13, 2006 Joe Bowring PJM Market Monitor www.pjm.com Convergence Basics Day-Ahead Market basics Day-Ahead and Real-Time Market interactions Increment

More information

Two Settlement - Virtual Bidding and Transactions

Two Settlement - Virtual Bidding and Transactions Two Settlement - Virtual Bidding and Transactions (Fall 2009) PJM 2009 2009 PJM 1 Agenda Two-Settlement Overview Two-Settlement Features & System Two-Settlement Business Rules Two-Settlement Data Requirements

More information

Presentation for The National Commission for Energy State Regulation of Ukraine

Presentation for The National Commission for Energy State Regulation of Ukraine Presentation for The National Commission for Energy State Regulation of Ukraine Todd Keech Laura Walter PJM Interconnection June 17, 2014 What is PJM? 1 What is PJM? ISO RTO Map Part of Eastern Interconnection

More information

PJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013

PJM Overview of Markets. Georgian Delegation PUCO Office April 11, 2013 PJM Overview of Markets Georgian Delegation PUCO Office April 11, 2013 1 Agenda Introduction Energy Markets Locational Marginal Pricing - LMP Two Settlement - Day Ahead / Real time Ancillary Services Capacity

More information

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure No. 2310 Table of Contents Purpose... 2 1. Responsibilities... 2 2. Scope/Applicability... 2 2.1 Background... 2 2.2 Scope / Applicability... 2 3. Detail... 3 3.1 Energy Dispatching... 3 3.1.2 Real-Time

More information

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations

PJM Overview and Wholesale Power Markets. John Gdowik PJM Member Relations PJM Overview and Wholesale Power Markets John Gdowik PJM Member Relations PJM s Role Ensures the reliability of the high-voltage electric power system Coordinates and directs the operation of the region

More information

PI.'s"'1-SlttlllIl. bstili

PI.'s'1-SlttlllIl. bstili PI.'s"'1-SlttlllIl. bstili Market Implementation linda J. Clarke Strategist PJM Market Design y Supports many options for energy traders. balanced bilateral transactions (Le. scheduling coordinator) with

More information

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D.

The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. The Power Market: E-Commerce for All Electricity Products By Edward G. Cazalet, Ph.D., and Ralph D. Samuelson, Ph.D. Why not use the Web to buy and sell transmission rights at prices derived from bids

More information

Convergence Bidding Stakeholder Conference Call

Convergence Bidding Stakeholder Conference Call Convergence Bidding Stakeholder Conference Call Margaret Miller Senior Market Design & Policy Specialist Convergence Bidding Stakeholder Conference Call August 13, 2009 Agenda 1:00 1:15 - Plan for Stakeholder

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Independent Market Monitor for PJM v. PJM Interconnection, L.L.C. ) ) ) ) ) ) Docket No. EL14- -000 COMPLAINT AND MOTION TO CONSOLIDATE

More information

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out

Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out 1 2 3 Key Take Away : There are 4 types of MISO transmission transactions : 1) Drive- In, 2) Drive-Within, 3) Drive-through, and 4) Drive-Out Speaker Notes: Drive-In refers to transactions that originate

More information

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009

An Overview of the Midwest ISO Market Design. Michael Robinson 31 March 2009 An Overview of the Midwest ISO Market Design Michael Robinson 31 March 2009 The Role of RTOs Monitor flow of power over the grid Schedule transmission service Perform transmission security analysis for

More information

Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England

Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England Business Models for Transactive Energy in the Wholesale Market December 5, 2012 1:30 p.m. to 3:30 p.m. Irving, Texas Robert Burke, Principal Analyst ISO New England About ISO New England (ISO) Not-for-profit

More information

Interjurisdictional Energy Trading. IESO Training

Interjurisdictional Energy Trading. IESO Training Interjurisdictional Energy Trading IESO Training Revised: January, 2014 Introduction to Interjurisdictional Energy Trading AN IESO TRAINING PUBLICATION This document has been prepared to assist in the

More information

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional

More information

Generation and Transmission Interconnection Process

Generation and Transmission Interconnection Process PJM Manual 14A Generation and Transmission Interconnection Process Revision: 18 Effective Date: January 28, 2016 Prepared by Planning Division Generation Interconnection Department PJM 2016 Table of Contents

More information

Update on Northeast Seams Issues. January 9, 2008 NYISO Management Committee Meeting

Update on Northeast Seams Issues. January 9, 2008 NYISO Management Committee Meeting Update on Northeast Seams Issues January 9, 2008 NYISO Management Committee Meeting Status of Seams Projects Current Deliverables Project 1. Intra-Hour Transaction Scheduling NYISO and ISO-NE have documented

More information

Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No.

Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No. 1 2 3 4 Responsibility for Outage Coordination is designated by 4 key artifacts: 1. FERC Order 2000 FERC Order 2000 (Docket No. RM99-2-000; Order No. 2000) comments regarding Transmission and Generation

More information

Multi-Faceted Solution for Managing Flexibility with High Penetration of Renewable Resources

Multi-Faceted Solution for Managing Flexibility with High Penetration of Renewable Resources Multi-Faceted Solution for Managing Flexibility with High Penetration of Renewable Resources FERC Technical Conference Increasing RT & DA Market Efficiency Through Improved Software June 24 26, 2013 Nivad

More information

How To Understand The Benefits Of The French Power Market Plan

How To Understand The Benefits Of The French Power Market Plan Why Did the US (Mostly) Go With LMP? Benefits of Flow Based Allocation Benjamin F. Hobbs EPRG, University of Cambridge, UK DoGEE, Johns Hopkins University, USA Market Surveillance Committee, California

More information

Section 4: Scheduling Philosophy & Tools

Section 4: Scheduling Philosophy & Tools Welcome to the Scheduling Philosophy & Tools section of the PJM Manual for Scheduling Operations. In this section you will find the following information: A description of the PJM OI s scheduling philosophy

More information

Robust Adaptive Topology Control

Robust Adaptive Topology Control Robust Adaptive Topology Control Mladen Kezunovic, PI Texas A&M University Kory W. Hedman, Co-PI Arizona State University January 14-15, 2015 System Integration Robust Adaptive Topology Control (RATC)

More information

Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT

Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT Optimizing Wind Generation in ERCOT Nodal Market Resmi Surendran ERCOT Chien-Ning Yu ABB/Ventyx Hailong Hui ERCOT FERC Conference on Increasing Real-Time and Day-Ahead Market Efficiency through Improved

More information

Real-time Security-Constrained Economic Dispatch and Commitment in the PJM : Experiences and Challenges

Real-time Security-Constrained Economic Dispatch and Commitment in the PJM : Experiences and Challenges Real-time Security-Constrained Economic Dispatch and Commitment in the PJM : Experiences and Challenges Simon Tam Manager, Markets Coordination PJM Interconnection June 29, 2011 1 Real Time and Day Ahead

More information

How To Settle Day Ahead Energy, Loss, And Loss For A Day Ahead Market

How To Settle Day Ahead Energy, Loss, And Loss For A Day Ahead Market Settling the Day-Ahead Market Charge Codes included in this training: 6011, 6800, 6700, 6301. EXTERNAL Customer Services Page 1 of 45 Disclaimer All information contained in this document is provided for

More information

Aliso Canyon Gas-Electric Coordination. Straw Proposal

Aliso Canyon Gas-Electric Coordination. Straw Proposal Aliso Canyon Gas-Electric Coordination Straw Proposal April 15, 2016 Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 4 3. Background... 5 3.1. Aliso Canyon Impact... 5

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Price Formation in Energy and ) Docket No. AD14-14-000 Ancillary Services Markets Operated ) By Regional Transmission Organizations

More information

Wind Power and Electricity Markets

Wind Power and Electricity Markets PO Box 2787 Reston, VA 20195 Phone: 703-860-5160 Fax: 703-860-3089 E-mail: [email protected] Web: www.uwig.org Wind Power and Electricity Markets A living summary of markets and market rules for wind energy

More information

Virtual Transactions in the PJM Energy Markets

Virtual Transactions in the PJM Energy Markets PJM Interconnection October 12, 2015 This page is intentionally left blank. PJM 2015 www.pjm.com i P age Table of Contents Executive Summary... 1 Background... 3 Synopsis of the Virtual Transactions...

More information

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market CALIFORNIA ISO Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market Prepared by the Department of Market Analysis California Independent System Operator September 1999 Table of Contents Executive

More information

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Four Corners) Scheduling. Operating Procedure

Table of Contents. Purpose. Eldorado Intertie and System (Eldorado- Four Corners) Scheduling. Operating Procedure Table of Contents Purpose... 1 1. Limits, Ratings, & Effectiveness Factors... 2 2. Contingency Operations... 2 2.1 Transmission Lines Outages... 2 2.2 APS Terminal Equipment Outages... 2 2.3 SCE Terminal

More information

Preliminary Project Description

Preliminary Project Description Auxiliary Market Products Additional Capacity Zones The NYISO and stakeholders are developing the rationale in 2010 for creating additional capacity zones, identified as a recommendation in the 2009 State

More information

Enabling 24/7 Automated Demand Response and the Smart Grid using Dynamic Forward Price Offers

Enabling 24/7 Automated Demand Response and the Smart Grid using Dynamic Forward Price Offers Enabling 24/7 Automated Demand Response and the Smart Grid using Dynamic Forward Price Offers Presented to ISO/RTO Council by Edward G. Cazalet, PhD The Cazalet Group [email protected] www.cazalet.com 650-949-0560

More information

Introduction to the Integrated Marketplace

Introduction to the Integrated Marketplace The information, practices, processes and procedures outlined and contained in this publication are the intellectual property of Southwest Power Pool, Inc. and are protected by law. This publication or

More information

Performance Metrics. For Independent System Operators And Regional Transmission Organizations

Performance Metrics. For Independent System Operators And Regional Transmission Organizations Performance Metrics For Independent System Operators And Regional Transmission Organizations A Report to Congress In Response to Recommendations of the United States Government Accountability Office April

More information

Ms. Rae McQuade President & COO, North American Energy Standards Board

Ms. Rae McQuade President & COO, North American Energy Standards Board NORTH AMERICAN ENERGY STANDARDS BOARD 801 Travis, Suite 1675 Houston, Texas 77002 Phone: (713) 356-0060 Fax: (713) 356-0067 email: [email protected] Web Site Address: www.naesb.org The Honorable Kimberly

More information

PAC7 Customer Specific Procedure

PAC7 Customer Specific Procedure PAC7 Customer Specific Procedure Table of contents 1. Procedure... 3 Call Services... 3 Day-Ahead (DA) Scheduling Process Pre DAM... 3 Hour Ahead (HA) Scheduling Process... 5 Real-Time Scheduling... 5

More information

Generator Optional. Timeline including the next steps. A practical example. Potential benefits of OFA? Key implications. How might OFA work?

Generator Optional. Timeline including the next steps. A practical example. Potential benefits of OFA? Key implications. How might OFA work? Generator Optional Firm Access Rights Australian Energy Market Commission announces terms of reference for detailed design work On the 6 March 2014, the Australian Energy Market Commission (AEMC) released

More information

Consistency of Energy-Related Opportunity Cost Calculations

Consistency of Energy-Related Opportunity Cost Calculations Consistency of Energy-Related Opportunity Cost Calculations Bhavana Keshavamurthy Market Implementation Committee 03/14/2012 PJM 2012 www.pjm.com 1 P a g e This page is intentionally left blank. PJM 2012

More information

FI/RU electricity exchange area setup

FI/RU electricity exchange area setup FI/RU electricity exchange area setup Daily routines at Nord Pool Spot Time (CET) Action 9:30 Transmission capacities published on NPS web Daily at 9:30 CET the relevant TSOs submit the available transmission

More information

Operator Initiated Commitments in RTO and ISO Markets

Operator Initiated Commitments in RTO and ISO Markets Price Formation in Organized Wholesale Electricity Markets Docket No. AD14-14-000 Staff Analysis of Operator Initiated Commitments in RTO and ISO Markets December 2014 For further information, please contact:

More information

Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC

Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Appendix A Glossary For 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 Website means the internet website https://spofossil.entergy.com/entrfp/send/2016ellrenewablerfp/index.htm.

More information

Winter Impacts of Energy Efficiency In New England

Winter Impacts of Energy Efficiency In New England Winter Impacts of Energy Efficiency In New England April 2015 Investments in electric efficiency since 2000 reduced electric demand in New England by over 2 gigawatts. 1 These savings provide significant

More information

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and

More information

Uplift in RTO and ISO Markets

Uplift in RTO and ISO Markets i Staff Analysis of Uplift in RTO and ISO Markets August 2014 For further information, please contact: William Sauer Office of Energy Policy and Innovation Federal Energy Regulatory Commission 888 First

More information

A Guide to Inform Institutions about Participation in PJM s Demand Response Programs

A Guide to Inform Institutions about Participation in PJM s Demand Response Programs A Guide to Inform Institutions about Participation in PJM s Demand Response Programs John Soden & Robin Aldina Dr. Dalia Patiño-Echeverri, Advisor May 2013 Masters Project submitted in partial fulfillment

More information

Nodal Exchange Contract Specifications

Nodal Exchange Contract Specifications Nodal Exchange Contract Specifications Monthly Day Ahead On-Peak Power Contract Specification Cash Settled Financial On-Peak Power. Financial On-Peak, [PJM/NYISO/MISO/MISO-RTO/ISO- NE/CAISO/ERCOT] [Nodal

More information

Status of Demand Response in Europe. Jessica Stromback, Smart Energy Demand Coalition EPFL Lausanne Switzerland Sept 10 th, 2015

Status of Demand Response in Europe. Jessica Stromback, Smart Energy Demand Coalition EPFL Lausanne Switzerland Sept 10 th, 2015 Status of Demand Response in Europe Jessica Stromback, Smart Energy Demand Coalition EPFL Lausanne Switzerland Sept 10 th, 2015 The Smart Energy Demand Coalition (SEDC) is an European Industry Association

More information

Demand Response Programs: Lessons from the Northeast

Demand Response Programs: Lessons from the Northeast Demand Response Programs: Lessons from the Northeast Charles Goldman E. O. Lawrence Berkeley National Laboratory [email protected] Mid Atlantic Demand Response Initiative Meeting Baltimore MD December

More information

Review of PJM s Market Power Mitigation Practices in Comparison to Other Organized Electricity Markets

Review of PJM s Market Power Mitigation Practices in Comparison to Other Organized Electricity Markets Review of PJM s Market Power Mitigation Practices in Comparison to Other Organized Electricity Markets Prepared for PJM Interconnection, LLC Prepared by James D. Reitzes Johannes P. Pfeifenberger Peter

More information

ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014

ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014 ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014 Grid Operations & Planning Summary March 2014 Operations The peak demand of 54,549 MW on March 3 rd was greater than the mid-term

More information

Energy Management System (EMS) Model Updates and Quality Assurance (QA)

Energy Management System (EMS) Model Updates and Quality Assurance (QA) PJM Manual 3A: Energy Management System (EMS) Model Updates and Quality Assurance (QA) Revision: 10 Effective Date: June 25, 2015 Prepared by: Operation Support Division PJM 2015 PJM 2007 Revision 0, Effective

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Coordination between Natural Gas and Electricity Markets Docket No. AD12-12-000 Prepared Statement of Brad Bouillon on behalf of

More information

124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Communication Protocols for Public Utilities ORDER NO.

124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Communication Protocols for Public Utilities ORDER NO. 124 FERC 61,317 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G. Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.

More information

process is usually performed with an additional SCUC and has been the natural fit for the use of wind power forecasts. Currently, however, since this

process is usually performed with an additional SCUC and has been the natural fit for the use of wind power forecasts. Currently, however, since this Impact of Variable Renewable Energy on US Electricity Markets By J.C. Smith, Stephen Beuning, Henry Durrwachter, Erik Ela, David Hawkins, Brendan Kirby, Warren Lasher, Jonathan Lowell, Kevin Porter, Ken

More information

The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in

The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in 17.1 LBMP Calculation Method The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by either the Real-

More information

Workshop B. 11:15 a.m. to 12:30 p.m.

Workshop B. 11:15 a.m. to 12:30 p.m. Workshop B Advanced Energy Management Tools: Benefitting from the Competitive Electricity Marketplace Beyond the Fixed Rate & Key Issues to Understand when Comparing Electricity Quotes 11:15 a.m. to 12:30

More information

Demand Response Review

Demand Response Review Demand Response Review Presented to: AESO Presented by: Johannes Pfeifenberger and Attila Hajos March 2011 Copyright 2011 The Brattle Group, Inc. www.brattle.com Antitrust/Competition Commercial Damages

More information

Dynamic Thermal Ratings in Real-time Dispatch Market Systems

Dynamic Thermal Ratings in Real-time Dispatch Market Systems Dynamic Thermal Ratings in Real-time Dispatch Market Systems Kwok W. Cheung, Jun Wu GE Grid Solutions Imagination at work. FERC 2016 Technical Conference June 27-29, 2016 Washington DC 1 Outline Introduction

More information

Comparison of Market Designs

Comparison of Market Designs Public Utility Commission of Texas Comparison of Market Designs Market Oversight Division Report Project 26376, Rulemaking Proceeding on Wholesale Market Design Issues in the Electric Reliability Council

More information