1 Presentation to the Inland Waterways Users Board Lockport Pool Chicago Sanitary & Ship Canal Illinois Waterway by Gary Loss, P.E. Rock Island District July 13, 2006
2
3
4 Chicago Sanitary and Ship Canal A Landmark Civil Engineering Project North Branch Chicago River Lake Michigan Chicago Lock South Branch Chicago River CSSC Reversing the Chicago River from Lake Michigan to the Illinois River
5 History of the CSSC
6 Authorization History Public Law directed the Department of the Army to implement the provisions of PL97-88, which provided that funds made available to the Corps of Engineers-Civil for O&M of the Illinois Waterway shall be available to operate and maintain the Chicago Sanitary and Ship Canal portion of the Waterway in the interest of navigation. Public Law 98-63, clarified that the CSSC includes the Control Structure and Lock in the Chicago River and other facilities as are necessary to sustain through navigation from Chicago Harbor on Lake Michigan to Lockport on the Des Plaines River.
7 1984 Memorandum of Agreement CSSC operated for sanitary, flood control and navigation purposes. Until 1984, specific responsibilities were vague. MOA executed in 1984 between Department of Army (DA) & Metropolitan Water Reclamation District of Chicago ( MWRD) DA agreed to maintain Controlling Works foundation, piers and dolphins Lockport Lock (including operation) Approach embankment upstream to Controlling Works Powerhouse & Dam gravity (water retaining) structures Concrete guide wall upstream to Damen Ave
8 Chicago Sanitary & Ship Canal (CSSC) on the Illinois Waterway CSSC Des Plaines River Approach Dike 40 Canal Wall Deep Run Creek Lockport Downstream End Of the CSSC
9 Lockport to Brandon Road Lockport Lock & Dam Deep Run Creek Des Plaines River Brandon Road Lock & Dam
10 Illinois Waterway - T.J. O'Brien Lock & Dam 2005 Total Tonnage by Commodity Total Tons: 9,048,078 Waste Material 0.29% Petroleum 5.88% Other 0.39% Manufactured Machines 0.32% Chemical 2.04% Coal 25.82% Chemical Coal Container Crude Material Manufactured Goods 39.51% Container 0.00% Farm Products Manufactured Goods Manufactured Machines Other Petroleum Crude Material 19.88% Waste Material Farm Products 5.86%
11 Illinois Waterway - Lockport Lock & Dam 2005 Total Tonnage by Commodity Total Tons: 16,929,707 Other 0.44% Manufactured Machines 0.40% Petroleum 8.88% Waste Material 0.02% Chemical 10.68% Manufactured Goods 24.83% Farm Products 5.02% Crude Material 34.58% Coal 15.11% Container 0.05% Chemical Coal Container Crude Material Farm Products Manufactured Goods Manufactured Machines Other Petroleum Waste Material
12 Lockport Pool RER MVR prepared a Rehabilitation Evaluation Report for Major Rehab program funding on 5 project features in the Lockport Pool, River Mile 291 to Submitted in March 2004 Approved in November 2004 Five Project Features (per requested funding source) Major Rehabilitation (Rehab/TF) Controlling Works Concrete Canal (Guide) Wall Approach Dike Operations and Maintenance (O&M) Powerhouse Embankment Clearing
13 Lockport Pool Reach Approach Dike Controlling Works Des Plaines River Powerhouse & Dam Canal Wall Lock
14 Approach Dike (Right Descending Bank) Constructed in early 1900 s 4,300 feet in length above the Powerhouse. Acts as high-hazard dam Early CSSC pool raise places canal levels above the core wall top. Constant seepage with chronic sinkhole development.
15 Approach Dike Proposed Concrete Cutoff Wall Recent actions 1992 Sand/bentonite cap installed. Seepage continued foot length of test sheet pile wall installed at location of a major sinkhole. Seepage continues. Rehabilitation Scope Must be done while maintaining navigation & hydropower Concrete seepage cutoff placed via slurry trench $23.6 million (Rehab/TF)
16
17 Joliet Inundation Area Breach Flows Circumvent Upper End of Wall Joliet Wall Brandon Road Dam
18 Lockport Pool Reach Approach Dike Controlling Works Des Plaines River Powerhouse & Dam Canal Wall Lock
19 Concrete Canal Wall (Left Descending Bank) Lockport Pool reach has 399 monoliths, 60 with barge check posts. Acts as a high-head dam with maximum 40- foot head. Serious concerns of structural stability and integrity.
20 Concrete Canal Wall Original Construction 1890 s lower 22 feet, lime cement concrete, 800 psi 1924 upper 15 feet, Portland cement concrete No bond between the 2 parts Rehabilitation Scope Must be done while maintaining navigation and hydropower Pre-cast vertical face panels New horizontal tie-back concrete Rock anchors $87 million in repairs (Rehab/TF) for first 3 miles
21 Lockport Pool Reach Approach Dike Controlling Works Des Plaines River Powerhouse & Dam Canal Wall Lock
22 Controlling Works 1890 s Construction Releases stormwater to Des Plaines River during heavy rainfall Lowers CSSC water levels 5-10 feet within the Lockport Pool. Operated by MWRD MWRD wants to operate remotely.
23 Controlling Works Rehabilitation Scope Concrete repairs, stone work, brick tuck pointing Embankment reshaping, riprap $1.4 million of repairs (Rehab/TF)
24 Lockport Pool Reach Approach Dike Controlling Works Des Plaines River Powerhouse & Dam Canal Wall Lock
25 MWRD Powerhouse Constructed in Powerhouse & Dam Abandoned I&M Canal Lock 48- & 12-foot spillways Powerhouse Operated by MWRD CSSC pool regulation Hydropower
26 MWRD Powerhouse 48-foot spillway Spillway chute concrete is in very poor condition. Used on limited basis to pass debris. MWRD wants to use for routine pool regulation. 12-foot spillway Bulkhead concrete deterioration Rehabilitation Scope No Powerhouse work $1.2 million in spillway concrete replacement (O&M)
27 Embankment Clearing Massive embankment overgrowth Became Corps responsibility in 1984 Impossible to reliably monitor or inspect On MVR Critical O&M Backlog List Rehabilitation Scope Clearing of trees and brush $1.8 million (O&M)
28 Project Cost Summary PROJECT COST SUMMARY Description Major Rehab O&M Total Dam and Powerhouse $ 1,174,500 $ 1,174,500 Concrete Canal Wall $86,940,000 $86,940,000 Approach Dike $23,639,800 $23,639,800 Embankment Clearing $ 1,843,800 $ 1,843,800 Controlling Works $ 1,396,700 $ 1,396,700 Total Project $111,976,500 $ 3,018,300 $114,994,800 BENEFIT:COST RATIOS Concrete wall 1.44 Approach dike 1.20 Controlling works 5.39
29 Screening for Portfolio Risk Analysis (SPRA) July 2005 National Cadre #2 Findings Approach Dike > Inadequate for all 5 Load Cases Concrete Canal Wall > Inadequate for all 5 Load Cases Highest Ranking USACE Navigation Dam from SPRA High economic losses Loss of Life issues indeterminate
30 Lockport Lock & Dam Brandon Road Pool River = Illinois Reach = Reach 1 RS = Legend WS PF 1 Ground Levee 550 Ineff Bank Sta Elevation (ft) Dam Break Water Level Normal Water Level Brandon Road Pool Station (ft)
31 Lockport Pool Dam Break Analyses Feb 2006 Preliminary Review Two scenarios (both with significant impact to navigation): Joliet Walls are not Breached and Brandon Road Dam reacts according to EAP: SDF w/ Breach Flows ~ 3,000 cfs peak flow into Joliet Sunny Day Failure ~ minor flow into Joliet Joliet Walls are Breached or Fails Brandon Road Dam does not react > Joliet Walls could be overtopped. Run-away barges could impact the wall with possible failure. Catastrophic Loss of Life will likely occur.
32 Lockport Lock & Dam Joliet Walls Hickory Creek
33 Brandon Road Pool Towards upstream end of the Joliet Wall (left descending bank)
34 Lockport Pool Recommendations FY 06 FY 07 FY 08 $500k wedge funding for engineering of Approach Dike and Canal Wall rehab. $1.5m wedge funding for engineering of Approach Dike rehab Capability of additional $1.5m additional for continued engineering of Canal Walls rehab. Initiate rehab construction on Controlling Works and Approach Dike FY 09 Initiate rehab construction on Canal Walls
CHICAGO SANITARY AND SHIP CANAL AT LOCKPORT REHABILITATION CASE STUDY. Brant Jones, P.E. 1 Thomas Mack, P.E. 2 Amy Moore, P.E.
CHICAGO SANITARY AND SHIP CANAL AT LOCKPORT REHABILITATION CASE STUDY Brant Jones, P.E. 1 Thomas Mack, P.E. 2 Amy Moore, P.E. 3 ABSTRACT This paper will discuss the unique history and techniques for restoring
Managing Our Water Retention Systems
Managing Our Water Retention Systems 29th Annual USSD Conference Nashville, Tennessee, April 20-24, 2009 Hosted by Corps of Engineers On the Cover Wolf Creek Dam is on the Cumberland River in South Central
US Army Corps of Engineers BUILDING STRONG
Fort Worth District Public Meeting 20 August 2013 US Army Corps of Engineers Lewisville Dam - Authorization Authorized by the River and Harbor Act, approved 2 March 1945 (Public Law 14, 79th Congress,
How to Become a Navy Engineer For $78,000 in USD
Presentation to Associated General Contractors COL Mark Deschenes Commander US Army Corps of Engineers Rock Island District February 2014 US Army Corps of Engineers Rock Island District 78,000 Square Miles
USACE Dam Safety Program Current Approach & Methodology
USACE Dam Safety Program Current Approach & Methodology Siamac Vaghar, PE, MASCE Chief, Geotechnical Engineering Section Dam Safety Program Manager US Army Corps of Engineers New England District Corps
Rehabilitation of Locks on the Kentucky River
Rehabilitation of Locks on the Kentucky River Joshua M. Repp, PE Bergmann Associates Presentation Overview River System History Evolution of Lock and Dams Structures Existing Condition of Structures Lock
Swannanoa River Flood Risk Management Study
Swannanoa River Flood Risk Management Study Measures Evaluated to Reduce Future Flood Damages City of Asheville U.S. Army Corps of Engineers Flooding History Part of the 132 square mile Swannanoa River
Amherst Dam. Michael Juris - Village President Joe Behlen, P.E. WDNR Dam Safety Engineer Gerald Krueger, P.E. AECOM
Amherst Dam Public Informational Meeting Michael Juris - Village President Joe Behlen, P.E. WDNR Dam Safety Engineer Gerald Krueger, P.E. AECOM April 3, 2014 Welcome Michael Juris Village President Introduction
Estabrook Dam A Discussion of Alternatives. Public Scoping Meeting June 5, 2014
Estabrook Dam A Discussion of Alternatives Public Scoping Meeting June 5, 2014 Presenters Kevin Haley, PLA, Milwaukee County Don Pirrung, P.E., PH, AECOM Mike Hahn, P.E., PH, Southeastern Wisconsin Regional
Flood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún
Flood mitigation program for Gatun lake Programa de mitigación de inundaciones del lago Gatún Moffatt & Nichol Engineers 10 de febrero de 2005 Contrato No. 126161 Introducción y Recomendaciones 1 INTRODUCTION
CLIFTY CREEK PLANT MADISON, INDIANA
2015 DAM AND DIKE INSPECTION REPORT GERS-15-018 CLIFTY CREEK PLANT MADISON, INDIANA PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Annual Dam and Dike Inspection
NASHVILLE DISTRICT JETS SAME
NASHVILLE DISTRICT JETS SAME Regional Program Review Savannah, GA 26 June 2014 US Army Corps of Engineers Agenda District Boundaries Cumberland & TN River Systems Major Construction Projects Hydropower/Navigation
STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
USACE Civil Works Infrastructure Investment Trends: Glide-Path to Benign Neglect?
USACE Civil Works Infrastructure Investment Trends: Glide-Path to Benign Neglect? National Waterways Conference Legislative Summit Steven L. Stockton, P.E. Director of Civil Works, U.S. Army Corps of Engineers
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers
Jackson Gulch Outlet Canal Rehabilitation Project
Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County
New Orleans Hurricane Storm Damage Risk Reduction System Tour March 23 24, 2012
New Orleans Hurricane Storm Damage Risk Reduction System Tour March 23 24, 2012 Host: Falcolm E. Hull, Vice President/Technical Expert, ARCADIS, U.S. Inc. Attending: Cherie Coffman, Coastal Projection
How To Rehabilitate A Dam In A Lake Dike
Herbert Hoover Dike Rehabilitation Reach 1 Construction Reaches 2 and 3 Major Rehabilitation Report Briefing Purpose Provide a status update of the HHD rehabilitation project and a description of the upcoming
Watershed Rehabilitation Program in Texas
Watershed Rehabilitation Program in Texas 1 Dams Constructed by Year (nationwide) 700 600 500 PL-566 Pilot/RC&D PL-534 400 300 200 100 0 48 51 54 57 60 63 66 69 72 75 78 81 84 87 90 93 96 99 Year 2 Number
Nashville District Workload for Nashville SAME Professional Development Workshop
Nashville District Workload for Nashville SAME Professional Development Workshop Thomas Cayce, PE Chief, Programs and Project Delivery Branch Nashville District 17 August 2011 US Army Corps of Engineers
Mouth of the Columbia River Jetties Major Rehabilitation Study
Mouth of the Columbia River Jetties Major Rehabilitation Study PNWA Port of Vancouver January 29, 2010 US Army Corps of Engineers Project Overview Background Corps Guidance for Major Rehab Project Alternatives
The City of Ottawa Flood Hazards
The City of Ottawa Flood Hazards The City of Ottawa is located in North Central LaSalle County, approximately 45 miles West of Joliet and 90 miles South of Rockford. The primary water course and sources
RESUME Lee A. Knuppel, P.E.
RESUME Lee A. Knuppel, P.E. OFFICE: EDUCATION: LEE A. KNUPPEL AND ASSOCIATES, Inc. 7770 Cooper Road, Suite 7 Montgomery, Ohio 45242 (513) 793-4222 Graduate: UCLA, Los Angeles, CA M.S. in Civil Engineering,
Moving Small Mountains Vesuvius Dam Rehab
Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,
Understanding the Herbert Hoover Dike Rehabilitation Spillway, Plan 6 and EAA Storage Flow way Alternatives
Understanding the Herbert Hoover Dike Rehabilitation Spillway, Plan 6 and EAA Storage Flow way Alternatives HHD Rehabilitation Public safety is Corps highest priority Analysis of designs to address rehabilitation
Runaway barges damage Marseilles Lock and Dam during 2013 flood on the Illinois River Kenneth R. Olson and Lois Wright Morton
doi:10.2489/jswc.69.4.104a FEATURE Runaway barges damage during 2013 flood on the Illinois Kenneth R. Olson and Lois Wright Morton I n the spring of 2013, the highest floodwater levels in the last 70 years
Inland Marine Transportation System Capital Investment Strategy
Inland Marine Transportation System Capital Investment Strategy Jeanine Hoey, PE, PMP Program Manager 13 April 2010 US Army Corps of Engineers 1 Inland Marine Transportation System (IMTS) Capital Investment
CITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.
Understanding Your An Introduction to the Chicago Area s Combined Sewer Systems
Understanding Your An Introduction to the Chicago Area s Combined Sewer Systems Metropolitan Water Reclamation District of Greater Chicago What is a combined sewer? In a combined sewer system, sanitary
Outlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
Potential Impacts of Hydrofracturing on Dam & Levee Safety
Potential Impacts of Hydrofracturing on Dam & Levee Safety Anita Branch, P.E. Senior Geotechnical Engineer Dam Fort Safety Worth Production District Center, Tulsa SAGEEP, 29 March 2012 29 January 2013
U.S. Army Corps of Engineers Infrastructure Strategies in Texas
U.S. Army Corps of Engineers Infrastructure Strategies in Texas Albert H. Halff 2015 Water Resources Workshop - Dallas Post SAME Robert Slockbower, P.E. Programs Director Southwestern Division 20 July
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
FINAL TECHNICAL MEMORANDUM AWD-00002 FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012
FINAL TECHNICAL MEMORANDUM AWD-00002 FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012 Table of Contents TABLE OF CONTENTS Table of Contents... 1 Executive Summary... 2 1 Objective... 4 2 Study Approach...
Small Dam Hazard Assessment Inventory
Small Dam Hazard Assessment Inventory What would happen if your dam were to fail? This is a question that most dam owners hope they will never have to answer. However it is a question you, as a responsible
HARBOR INFRASTRUCTURE INVENTORIES Chicago Harbor, Illinois
HARBOR INFRASTRUCTURE INVENTORIES Chicago Harbor, Illinois Harbor Location: Chicago Harbor is located on the southwest shore of Lake Michigan in the heart of downtown Chicago, Cook County, Illinois. Authority:
Chapter 4. Flood Control
Chapter 4. Flood Control As noted by their name, flood control measures control floodwaters and keep them from reaching damageable property. They are also called structural measures because they involve
How To Check For Scour At A Bridge
Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
Stormwater Management in Chicago waterways :Basement Flooding and its prevention Kyungmin Kim
Stormwater Management in Chicago waterways :Basement Flooding and its prevention Kyungmin Kim CE 394K GIS in Water Resources - David R. Maidment. Dec 4th 2015 Motivation and Objective Recently, Chicago
Failing Coastal Wood Infrastructure on the Great Lakes
University of Wisconsin Sea Grant Institute Contact Gene Clark [email protected] 715-392-3246 Failing Coastal Wood Infrastructure on the Great Lakes Gene Clark/UW Sea Grant Institute Introduction Many
Small Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C.
Small Dam Repair The Stone Lake Dam Story Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. 29601 1 Historical background of Stone Lake A series of three
Public Law 84-99 and Non-Structural Alternatives to Levee Repairs
Public Law 84-99 and Non-Structural Alternatives to Levee Repairs Presented by: Mr. Jerry A. Skalak, CFM U.S. Army Corps of Engineers Rock Island District and Mr. Tom Oswald Iowa Homeland Security and
PERFORMANCE OF DAMS AND SPILLWAYS 2009 GEORGIA FLOOD. Randall P. Bass, P.E. 1, 2. James R. Crowder, P. Joseph S. Monroe, P.E.
PERFORMANCE OF DAMS AND SPILLWAYS 2009 GEORGIA FLOOD Randall P. Bass, P.E. 1, 2 James R. Crowder, P. Joseph S. Monroe, P.E. 3 ABSTRACT During the latter part of September 2009, the Atlanta metro area received
2010-2011 Contractor of the Year
U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United
6.0 Results of Risk Analyses
6. Results of Risk Analyses A risk analysis of the optimized embankment designs for the Salton Sea restoration project was conducted jointly by Kleinfelder and representatives from Reclamation. A risk
How To Install An Overhead Sewer
Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage
BINGHAMTON FLOOD DAMAGE REDUCTION PROJECT
BINGHAMTON FLOOD DAMAGE REDUCTION PROJECT Department of Environmental Conservation Region 7 Counties: Broome, Cayuga, Chenango, Cortland, Madison, Onondaga, Oswego, Tioga, Tompkins Operated and Maintained
SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER SYSTEMS. Stephen H. Scott 1 and Yafei Jia 2
US-CHINA WORKSHOP ON ADVANCED COMPUTATIONAL MODELLING IN HYDROSCIENCE & ENGINEERING September 19-21, Oxford, Mississippi, USA SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER
FAILURE OF TETON DAM
BACKGROUND ON FAILURE OF TETON DAM Near Rexburg, Idaho June 5, 1976 J. David Rogers, Ph.D., P.E., R.G. Karl F. Hasselmann Chair in Geological Engineering Department of Geological Sciences & Engineering
Greater New Orleans Hurricane & Storm Damage Risk Reduction System
Greater New Orleans Hurricane & Storm Damage Risk Reduction System SLFPA-East Update Col. Robert Sinkler, Commander Hurricane Protection Office July 15, 2010 US US Army Army Corps Corps of of Engineers
Appendix F Benefit-Cost Analysis of Flood Protection Measures
Appendix F Benefit-Cost Analysis of Flood Protection Measures Acronyms used in Appendix F: AA B AA C AA D BC BFE EAD FEMA NED O&M PV RED USACE Average Annual Benefits Average Annual Cost Average Annual
USACE Asset Management Program
USACE Asset Management Program Jose E. Sanchez, P.E. Asset Manager [email protected] Relevant, Ready, Responsive, Reliable 1 Why Asset Management? WE OWN IT Short list 15000 Structures 285000
5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES
5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people
Management of flooding downstream of dams
Management of flooding downstream of dams Attachment to Victoria State Flood Emergency Plan Version 1.0 (6 February 2013) This plan is produced by the Victoria State Emergency Service and Department of
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
Wolf Creek Hydropower Rehabilitation Analysis Report
Wolf Creek Hydropower Rehabilitation Analysis Report David Bishop Kris Atanassov Team Cumberland, September 16, 2015 US Army Corps of Engineers Agenda Overview Water Availability Energy Modeling Preliminary
Gwinnett County NRCS Watershed Dam Rehabilitation Program
Gwinnett County NRCS Watershed Dam Rehabilitation Program Jonathan Semerjian, PE Dept. of Water Resources Stormwater Management Gregg Hudock, PE Golder Associates Sam Fleming, PE Dewberry Presentation
PERFORMANCE OF FLOOD-TESTED SOIL-CEMENT PROTECTED LEVEES. Kenneth D. Hansen, P.E. 1 Dennis L. Richards, P.E. 2 Mark E. Krebs, P.E.
PERFORMANCE OF FLOOD-TESTED SOIL-CEMENT PROTECTED LEVEES Kenneth D. Hansen, P.E. 1 Dennis L. Richards, P.E. 2 Mark E. Krebs, P.E. 3 ABSTRACT Although there were some early projects using soil-cement to
Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa
Review Report and Recommendations for the Remediation of Flood Damage at the Berg River Causeway and the Dam Bypass Channel on Portion of Farms 1646 and 1014, Franschhoek Contact person: Colin Whittemore
Storm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
United States Army Corps of Engineers, Civil Works
United States Army Corps of Engineers, Civil Works Fiscal Year 2013 Federal Program Inventory May 2013 Table of Contents Introduction... 2 Program Inventory... 3 1. Navigation... 3 2. Flood Risk Management...
April 17, 2015 SUMMARY OF SUBJECT MATTER
April 17, 2015 SUMMARY OF SUBJECT MATTER TO: FROM: RE: Members, Subcommittee on Water Resources and Environment Staff, Subcommittee on Water Resources and Environment Hearing on A Review of the President
U.S. Army Corps of Engineers
Walla Walla District U.S. Army Corps of Engineers Hurricane Katrina Response Briefer: Joseph Saxon Today s Briefing U.S. Army Corps of Engineers Mission Events leading up to New Orleans flooding Corp s
Emergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005
Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005 Speakers: Tom Chan, CEO, Global Risk Miyamoto Greg Bates, Principal, Global Risk Consultants Learning Objectives
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
Upper Des Plaines River & Tributaries, IL & WI Feasibility Study
Upper Des Plaines River & Tributaries, IL & WI Feasibility Study Jeffrey Zuercher Project Manager Chicago District February 19, 2014 Study Partnership: US Army Corps of Engineers Agenda Background Study
Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013
Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013 1. Design alternatives for large capital flood projects (basinlevel water retention and Interstate
C O N S U L T A N T S RESUME
C O N S U L T A N T S RESUME Ed Bove, P.E. SUMMARY OF EXPERIENCE Mr. Bove possesses 28 years experience in the civil engineering field. He has been involved with investigation, design, analysis, and quality
SIMPLIFIED INUNDATION MAPS FOR EMERGENCY ACTION PLANS. National Dam Safety Review Board Emergency Action Plan Workgroup
SIMPLIFIED INUNDATION MAPS FOR EMERGENCY ACTION PLANS National Dam Safety Review Board Emergency Action Plan Workgroup EXECUTIVE SUMMARY Development of Emergency Action Plans (EAPs) for all high and significant
A Stream Restoration Case Study in the California Central Coast
International Erosion Control Association Annual Conference 2009, Reno, Nevada Case Study Technical Presentation A Stream Restoration Case Study in the California Central Coast Justin S. Rogers, P.E.,
CHAPTER 2 HYDRAULICS OF SEWERS
CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination
Storm Protection. Storm Protection
Storm Protection Storm Protection About Skyline Steel A premier steel foundation supplier serving the U.S., Canada, Mexico, the Caribbean, Central America, and Colombia markets, Skyline Steel is a wholly-owned
February 4, 2011. [email protected]. Report Recommendations and NIPSCO Responses. 4.3 Maintaining and Controlling Vegetation Growth
February 4, 2011 VIA E-MAIL AND CERTIFIED MAIL #7010 0290 0002 0577 6226 Mr. Stephen Hoffman US Environmental Protection Agency (5304P) 1200 Pennsylvania Avenue, NW Washington, DC 20460 [email protected]
LAKE OKEECHOBEE and THE HERBERT HOOVER DIKE. A Summary of the Engineering Evaluation of Seepage and Stability Problems at the Herbert Hoover Dike.
LAKE OKEECHOBEE and THE HERBERT HOOVER DIKE A Summary of the Engineering Evaluation of Seepage and Stability Problems at the Herbert Hoover Dike. The Good Life Lake Okeechobee and the Herbert Hoover Dike
Oakwood Beach Storm Damage Prevention Project NJDEP-Bureau of Coastal Engineering Glenn Golden, Project Manager U.S. Army Corps Civil Works Programs
Oakwood Beach Storm Damage Prevention Project NJDEP- Glenn Golden, Project Manager U.S. Army Corps Civil Works Programs Branch Dwight Pakan, Project Manager, Philadelphia District The State of New Jersey
Various options are discussed below.these low cost, low impact interventions can also be applied as general erosion control methods.
Week 10 River Hydraulics Rehabilitating Urban Waterways (From http://hubpages.com/hub/river-bank-erosion-control-methods) See also the resources placed on Moodle. Water channels should be viewed as a resource
U.S. Army Corps of Engineers Tulsa District
U.S. Army Corps of Engineers Tulsa District Mike Abate, PMP. Chief, Civil Works Branch, PPMD April 17, 2015 US Army Corps of Engineers Civil Works Mission Water Supply 50% of Corps water supply contracts
Standard Operating Procedures for Flood Preparation and Response
Standard Operating Procedures for Flood Preparation and Response General Discussion Hurricanes, tropical storms and intense thunderstorms support a conclusion that more severe flooding conditions than
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
Reservoir Simulations for the Delaware River Basin Flood of June, 2006
Reservoir Simulations for the Delaware River Basin Flood of June, 2006 Middle Atlantic River Forecast Center State College, PA August 2007 (Revised 9/13/07) Introduction: In the late spring of 2005, the
Storm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.
Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double