Greater New Orleans Hurricane & Storm Damage Risk Reduction System
|
|
|
- Trevor Campbell
- 10 years ago
- Views:
Transcription
1 Greater New Orleans Hurricane & Storm Damage Risk Reduction System SLFPA-East Update Col. Robert Sinkler, Commander Hurricane Protection Office July 15, 2010 US US Army Army Corps Corps of of Engineers Engineers
2 1. Public Discussion Rules Agenda 2. USACE Accepted Measures to Inhibit Corrosion 3. Independent External Peer Review (Corrosion and Bending Moment) 4. Settlement Calculation Factors Likely Stopping Point 5. IHNC Storage Capacity 6. Why is the Work Being Expedited? 7. Post Hurricane Storm Surge Damage Repair 8. Design-Life Provided for Back-Up 9. SLFPA-E Construction Execution Team 10. St. Bernard T-Wall Decision 11. Mr. Goin s Comments (Hand-Out) Working Draft 2
3 Public Discussion Rules Will not publicly discuss speculative subsidence, settlement and sea-level rise projections beyond 50- years (will do it privately) Will not publicly discuss speculative performance of a well-maintained system beyond 100-years of age (will do it privately) Will not publicly discuss speculative performance of the 100-year HSDRRS at higher surge levels (will do it privately) Will not publicly discuss speculative performance of HSDRRS resiliency at higher surge levels than 500- yr (will do it privately) Working Draft 3
4 Practice has generally not been to Double Protect USACE Accepted Measures to Inhibit Corrosion Over-sized cross sections of piles (addition of a corrosion allowance). Coal tar epoxy* or other coating. Application of a polyethylene sleeve (on steel pipe piles). Zinc Coating. Electro-chemical (cathodic) protection. Casting in cement, mortar or concrete. All are being used in the HSDRRS! Working Draft *The Current HSDRRS Design Guidelines 4DO NOT Address All!
5 USACE Position on Oversized Steel In some cases an oversized sheet pile section may be specified to provide for the anticipated loss of section resulting from corrosion. o EM , Design of Sheet Pile Walls, Paragraph 9-2.b.(4). Dated 31 March USACE policy on use of an oversized section as an alterative in addressing steel pile corrosion is consistent with other federal and state agencies, as well as private industry design guides. Working Draft 5
6 Current HSDRRS Design Guidelines Do Not Specifically Address Corrosion "5.6.8 Painting Only coal tar epoxy shall be used. Steel sheet, H and Pipe pilings that will be installed in new fill, disturbed materials or fluctuating water tables shall be painted with a coal tar epoxy system. The H-piles and sheet piling shall be painted 3 inches above the stabilization slab and to a 5 ft. minimum below new fill material, disturbed soil or the lowest elevation of fluctuating water tables. Piles exposed in water (i.e. cutoff pilings in breakwaters) shall be coated the full height exposed to water plus a 5 embedment length. Use engineering judgment for final painting requirements." Using accepted methods to address corrosion other than painting with coal tar epoxy is within current HSDRRS Design Guidelines. Working Draft 6
7 St. Bernard H-Pile Dimensions Oversized Steel = More Strength (not drawn to scale) H14X89 (with oversized steel) Depth: 13.8 in. Flange Width: 14.7 in. Flange Thickness: 0.6 in. Web Width: in. Web Thickness: 0.6 in % more crosssectional area than structurally needed in top 5-7 feet! Working Draft 7
8 St. Bernard H-Pile Cross Section Maximum Corrosion Potential Maximum Cross-Sectional Area Required O&M Manual Requires Joint Periodic Inspections of H-Piles Working Draft 8
9 Next Step on Corrosion Follow-up meeting at 2pm today to further discuss way ahead (includes SLFPA-E, OCPR and ERDC experts). Working Draft 9
10 Independent External Peer Review (IEPR) Recommend that the next (future) version of HSDRRS Design Guidelines specifically address: Corrosion Bending Moment All substantive HSDRRS Design Guideline changes do undergo an IEPR. Working Draft 10
11 Settlement Calculation Factors Meets Current HSDRRS Design Criteria Historical data. Soil samples from the foundation tested to determine values for settlement calculations. Computer modeling used to predict settlement over time. Most settlement would occur in the first 15 years after project completion. Many of the levees in St. Bernard Parish are on ground that has already been consolidated to some degree. Working Draft 11
12 H-Piles There is No Hydraulic or Soil Induced Load that Will Break These Piles! Working Draft 12
13 There has Never Been a Documented Case of a Pile Supported T-Wall failure. Working Draft 13
14 Bayou Dupre November 2005 I-Wall Concrete Pile-Founded T-Wall Working Draft 14
15 IHNC Storage Capacity For a 100-yr Storm Surge: Closure elevation: +3 feet Rainfall (10-year, 24 hour event): +0.8 feet Pumping into the basin: +2 feet Overtopping: +1.5 feet Wind setup: +0.5 feet Water elevation of less than 8 feet For a 500-yr storm surge, the IHNC Basin will rise to an elevation of less than 10 feet. The IHNC Basin will be able to safely hold water to the top of the wall, which is at elevation +12 feet at its lowest point. (Hurricane Gustav Elevation) Working Draft 15
16 Why is the Work being Expedited? Operational Deadline: 1 June 2011 The Corps operational goal is to provide [100-yr] level of risk reduction by June 1, (24 Feb 09 Congressional Testimony) Most HSDRRS work is funded by Congress with Flood Control and Coastal Emergency (FCCE) appropriations. Federal expectation is that work will be expedited as if under emergency conditions. A major U.S. Urban Area does not have the Hurricane Storm Surge System its needs. Working Draft 16
17 USACE Authorities and Activities Public Law (Annual Flood Control and Coastal Emergency Appropriations from Congress) Disaster Preparation Emergency Operations Repair any active flood control work Repair any Federally constructed hurricane or shore protection work Rehabilitation Water Assistance Advance Measures Hazard Mitigation Post Hurricane Storm Surge Damage Repair Working Draft 17
18 Design Life for St. Bernard Structures Hydraulics drive the 50-year design elevations used for the structure elevation. Structures will provide one percent storm risk reduction in The 50-year design life is not an indicator of product life span. There is no factor for longevity. The walls and gates will remain structurally sound past the 50-year design life (if properly maintained). Design Corrosion Rate for Most Steel is 100 Years or Greater Working Draft 18
19 Design Life Case Study: IHNC Lock (It is Part of the Mississippi River Levee System) Built in 1923 by the Port of New Orleans. The Lock has exceeded its original 50 Year design life. It s the evolution of the barge industry and the increased sizes of the barge tows, and not the design life, that has resulted in the authorization to replace the Lock. Still in Operation Nearly 90 Years Later! Built on Timber Piles! Working Draft 19
20 Southeast Louisiana Flood Protection Authority East Construction Execution Team Robert Turner Regional Director SLFPA-E Stevan Spencer Chief Engineer SLFPA-E MAJ Hall HPO OIC Marcia St. Martin Executive Director Sewerage & Water Board Joe Becker General Superintendent Sewerage & Water Board John Ashley Branch Chief Pump Station Repairs Cost: >$70 M Contracts: Design-Build 5 Design-Bid-Build: 25 Total: 30 Permanent Pumps Dan Bradley Cost: >$1 B Branch Chief Contracts: Design-Build 2 Permanent Pumps Design-Bid-Build 9 Interim Closure Structures Total: 11 Outfall Canal Walls Storm Proofing Cost: >$250 M Contracts: Design-Bid-Build: 25 Total: 11 Monica Salins Pontchartrain Levee District Carl Anderson Sr. PM Levees Sam Morsie Sr. PM Floodwalls St. Charles Parish Cost: >$150 M Contracts: Design-Bid-Build 16 Total: 16 East Bank Jefferson Parish Cost: >$500 M Contracts: Design-Bid-Build 27 Total: 27 Fran Campbell East Jefferson Levee District Gerry Gillen Orleans Levee District Teresa King Orleans Metro PM CPT Schmidt OIC Sean Brunet Sr. PM Orleans Parish Orleans Metro Cost: >$100 M Contracts: Design-Bid-Build 10 Total: 10 Michael Grzegorzewski Orleans East PM Orleans East Cost: >$700 M Contracts: Design-Bid-Build: 12 Early Contractor Involvement :1 Total: 13 CPT Cali OIC Stuart Williamson Lake Borgne Basin Levee District CPT Wood OIC Harold Daigle Office of Coastal Protection and Restoration Ron Elmer IHNC Sr. PM Chris Gilmore St. Bernard PM St. Bernard Cost: >$1 B Contracts: Design-Bid-Build 3 Early Contractor Involvement 3 Total: 6 > $5 BILLION EXECUTED IN < 5 YEARS INTERNAL WORKING DRAFT AS OF: 13 Jul IHNC Cost: >$1.5 B Contracts: Design-Build 1 Design-Bid-Build 7 Early Contractor Involvement 1 Total: 9
21 St. Bernard T-Wall Decision Earthen levees considered but ruled out for St. Bernard New levee heights: 28 (Approx.) Existing levee heights: Existing width, approx. 300 USACE illustration, not to scale Levee width necessary to meet new, more stringent post-katrina design criteria - approx. 900 Working Draft 21
22 Some T-Wall O&M Cost Savings 75% less mowing (Compared to a Levee) 75% less settlement-related maintenance (borrow material) 2057 elevation without having to address future lifts and future subsidence Less flood side and protected side armoring maintenance Working Draft 22
23 Katrina storm surge elevations were much higher elsewhere along the Gulf Coast. 500-YEAR STILL WATER ELEVATION*: EL YEAR LEVEE ELEVATION: EL +28 HURRICANE KATRINA S STILL WATER ELEVATION* AT THIS LOCATION: EL +18 Top of Floodwall: EL +32 Top of Base Slab: EL YEAR STILL WATER ELEVATION*: EL +18 Top of Stabilization Slab: EL St. Bernard Parish Floodwall, near the IHNC Tie-In (not labeled to scale) *Still water elevation does not include waves 23 Working Draft
24 If Earthen Levees Were Built to Reduce Risk from a year Storm in St. Bernard Parish The expanded footprint would encroach into nearby waterways, and more than 1,450 acres of land would be impacted. Operation and Maintenance costs would be greater. Working Draft Construction would require about 25 million cubic yards of additional borrow material, further driving up the cost. 24 BUILDING STRONG
Greater New Orleans Hurricane and Storm Damage Risk Reduction System
Greater New Orleans Hurricane and Storm Damage Risk Reduction System Mike Park Chief Task Force Hope Mississippi Valley Division U.S. Army Corps of Engineers March 15, 2011 US Army Corps of Engineers BUILDING
GAO HURRICANE KATRINA. Strategic Planning Needed to Guide Future Enhancements Beyond Interim Levee Repairs. Report to Congressional Committees
GAO United States Government Accountability Office Report to Congressional Committees September 2006 HURRICANE KATRINA Strategic Planning Needed to Guide Future Enhancements Beyond Interim Levee Repairs
New Orleans Hurricane Storm Damage Risk Reduction System Tour March 23 24, 2012
New Orleans Hurricane Storm Damage Risk Reduction System Tour March 23 24, 2012 Host: Falcolm E. Hull, Vice President/Technical Expert, ARCADIS, U.S. Inc. Attending: Cherie Coffman, Coastal Projection
New Orleans Hurricane and Storm Damage Risk Reduction System
New Orleans Hurricane and Storm Damage Risk Reduction System Luis A. Ruiz, P.E. Hurricane Protection Office U.S. Army Corps of Engineers August 27, 2009 US Army Corps of Engineers New Orleans Area Hurricane
EXPERT REVIEW PANEL ON GREATER NEW ORLEANS HURRICANE AND STORM DAMAGE RISK REDUCTION SYSTEM DESIGN GUIDELINES: Final Report
EXPERT REVIEW PANEL ON GREATER NEW ORLEANS HURRICANE AND STORM DAMAGE RISK REDUCTION SYSTEM DESIGN GUIDELINES: Final Report May 21, 2014 Produced for and Funded by: Coastal Protection and Restoration Authority
PART 2 NEW ORLEANS DRAINAGE CANALS
PART 2 NEW ORLEANS DRAINAGE CANALS The Old Basin drainage canal was excavated in the 1790s.. This shows the systems of drainage ditches and canals established by 1829, leading to Bayou St. John. Cross
5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES
5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people
Evaluating the Condition of Seawalls/Bulkheads
Volume 2 Evaluating the Condition of Seawalls/Bulkheads By: Coastal Systems International, Inc. Typical bulkhead under construction Seawalls and bulkheads (walls) provide shoreline stabilization for many
STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
TFMA 2015 Spring Conference Dallas, TX. John E. Bourdeau Jr: FEMA Region 6, Risk Analysis Branch
TFMA 2015 Spring Conference Dallas, TX John E. Bourdeau Jr: FEMA Region 6, Risk Analysis Branch Southeastern Louisiana Hurricane Isaac, 2012 Hazard Mitigation, Region 6 DR-4080-LA Figure 3. Hurricane
Comprehensive Recommendations Supporting the Use of the Multiple Lines of Defense Strategy to Sustain Coastal Louisiana 2008 Report (Version I)
Comprehensive Recommendations Supporting the Use of the Multiple Lines of Defense Strategy to Sustain Coastal Louisiana 2008 Report (Version I) This report recommends integrated coastal projects and levee
Release of EC 1110-2-6067 USACE Process for the National Flood Insurance Program (NFIP) Levee System Evaluation. Frequently Asked Questions
Release of EC 1110-2-6067 USACE Process for the National Flood Insurance Program (NFIP) Levee System Evaluation Frequently Asked Questions 1. What does Engineer Circular (EC) 1110-2-6067, USACE Process
U.S. Army Corps of Engineers
Walla Walla District U.S. Army Corps of Engineers Hurricane Katrina Response Briefer: Joseph Saxon Today s Briefing U.S. Army Corps of Engineers Mission Events leading up to New Orleans flooding Corp s
FINAL Environmental Impact Statement (EIS) for the
FINAL Environmental Impact Statement (EIS) for the Mississippi River-Gulf Outlet (MRGO), Louisiana, and Lake Borgne Wetland Creation and Shoreline Protection Project U.S. Army Corps of Engineers New Orleans
The success of the hurricane protection around Chevron s refinery at Pascagoula, MS, during Katrina
The success of the hurricane protection around Chevron s refinery at Pascagoula, MS, during Katrina Dr J.W. van der Meer, Dr C. Cooper, M.J. Warner, H. Adams-Morales and G.J. Steendam Abstract and presentation
Emergency Management THERE WHEN YOU NEED US
Emergency Management THERE WHEN YOU NEED US Disasters can change our lives in an instant. Although emergency preparedness, response and recovery are primarily the responsibilities of states and local communities,
SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
Oakwood Beach Storm Damage Prevention Project NJDEP-Bureau of Coastal Engineering Glenn Golden, Project Manager U.S. Army Corps Civil Works Programs
Oakwood Beach Storm Damage Prevention Project NJDEP- Glenn Golden, Project Manager U.S. Army Corps Civil Works Programs Branch Dwight Pakan, Project Manager, Philadelphia District The State of New Jersey
2010-2011 Contractor of the Year
U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United
US Army Corps of Engineers BUILDING STRONG
Fort Worth District Public Meeting 20 August 2013 US Army Corps of Engineers Lewisville Dam - Authorization Authorized by the River and Harbor Act, approved 2 March 1945 (Public Law 14, 79th Congress,
A New Coastal Engineering Graduate Program
Paper ID #12157 A New Coastal Engineering Graduate Program Dr. Robert W. Whalin, Jackson State University Dr. Robert W. Whalin, Professor of Civil and Environmental Engineering, and Director, Coastal Hazards
Failing Coastal Wood Infrastructure on the Great Lakes
University of Wisconsin Sea Grant Institute Contact Gene Clark [email protected] 715-392-3246 Failing Coastal Wood Infrastructure on the Great Lakes Gene Clark/UW Sea Grant Institute Introduction Many
FINAL TECHNICAL MEMORANDUM AWD-00002 FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012
FINAL TECHNICAL MEMORANDUM AWD-00002 FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012 Table of Contents TABLE OF CONTENTS Table of Contents... 1 Executive Summary... 2 1 Objective... 4 2 Study Approach...
Managing Our Water Retention Systems
Managing Our Water Retention Systems 29th Annual USSD Conference Nashville, Tennessee, April 20-24, 2009 Hosted by Corps of Engineers On the Cover Wolf Creek Dam is on the Cumberland River in South Central
USACE Dam Safety Program Current Approach & Methodology
USACE Dam Safety Program Current Approach & Methodology Siamac Vaghar, PE, MASCE Chief, Geotechnical Engineering Section Dam Safety Program Manager US Army Corps of Engineers New England District Corps
Lockport Pool Chicago Sanitary & Ship Canal Illinois Waterway
Presentation to the Inland Waterways Users Board Lockport Pool Chicago Sanitary & Ship Canal Illinois Waterway by Gary Loss, P.E. Rock Island District July 13, 2006 Chicago Sanitary and Ship Canal A
Storm tide is the water level rise during a storm due to the combination of storm surge and the astronomical tide.
INTRODUCTION TO STORM SURGE Introduction to Storm Surge BOLIVAR PENINSULA IN TEXAS AFTER HURRICANE IKE (2008) What is Storm Surge? Inland Extent Storm surge can penetrate well inland from the coastline.
8 Sub-Basins 26 740 acres. 5 Outflow Locations 29 billion gallon/day capacity. Drainage Basin 1. 17th st. canal. pump st. 12. pump st. 19. pump st.
th st. canal pump st. orleans canal london ave. canal s 0 acres pump st. 9 Outflow Locations 9 billion gallon/day capacity th st canal pump st. orleans canal london ave. canal pump st. 9 to lake ponchartrain
CRS Report for Congress
Order Code RS22285 Updated March 22, 2006 CRS Report for Congress Received through the CRS Web Hurricane-Damaged Drinking Water and Wastewater Facilities: Impacts, Needs, and Response Summary Claudia Copeland
Storm tide is the water level rise during a storm due to the combination of storm surge and the astronomical tide.
INTRODUCTION TO STORM SURGE Introduction to Storm Surge National Hurricane Center Storm Surge Unit BOLIVAR PENINSULA IN TEXAS AFTER HURRICANE IKE (2008) What is Storm Surge? Inland Extent Storm surge can
MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH
MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS COMMUNITY OUTREACH MEETING AGENDA Introductions History of PWSA Actions August 31 Storm Impacts Short
U.S. Naval Academy. Flood Damage Reduction Project Using Structural and Non-Structural Measures
U.S. Naval Academy Flood Damage Reduction Project Using Structural and Non-Structural Measures 3 August 2005 Presentation by Stacey Underwood, U.S. Army Corps of Engineers, Baltimore District Co-Author,
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1
Strategy Name: Reduce Existing Potential for Flood Damages LRSW-S3C1. Develop and implement a program to: Minimize flood damages through the use of structural measures. Minimize flood damages through the
Overview of Deep Mixing at Levee LPV 111, New Orleans, LA
Overview of Deep Mixing at Levee LPV 111, New Orleans, LA Peter Cali 1, PhD, P.E., Bruce Lelong 2, P.E, Donald Bruce 3, PhD, P.E., Stefano Valagussa 4, Jim Beckerle 5, Jim Gardner 6, and George Filz 7,
Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005
Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005 Speakers: Tom Chan, CEO, Global Risk Miyamoto Greg Bates, Principal, Global Risk Consultants Learning Objectives
Review Plan. F-4 Channel Rehabilitation. Tropicana and Flamingo Washes, Clark County, Nevada for Plans and Specification
Review Plan F-4 Channel Rehabilitation Tropicana and Flamingo Washes, Clark County, Nevada for Plans and Specification June 2015 (THIS PAGE LEFT INTENTIONALLY BLANK) Review Plan F-4 Channel Rehabilitation
Storm Protection. Storm Protection
Storm Protection Storm Protection About Skyline Steel A premier steel foundation supplier serving the U.S., Canada, Mexico, the Caribbean, Central America, and Colombia markets, Skyline Steel is a wholly-owned
Rehabilitation of Locks on the Kentucky River
Rehabilitation of Locks on the Kentucky River Joshua M. Repp, PE Bergmann Associates Presentation Overview River System History Evolution of Lock and Dams Structures Existing Condition of Structures Lock
Norfolk Flooding Strategy Update. Presentation to Norfolk City Council March 27, 2012
Norfolk Flooding Strategy Update Presentation to Norfolk City Council March 27, 2012 Presentation Overview The purpose of this presentation is to provide City Council an update on activities carried out
Specification for Pipe Coating Repairs Offshore
Specification for Pipe Coating Repairs Offshore Specification for Pipe Coating Repairs Offshore 1 of 6 Table of Contents 1.0 SCOPE... 3 2.0 REFERENCE DOCUMENTS... 3 3.0 MATERIALS... 3 4.0 EQUIPMENT AND
Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina
Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain
SECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
Structural Damage Due to Floods
Structural Damage Due to Floods By Craig D. Rogers, P.E. The Federal Emergency Management Agency (FEMA) reports that each year approximately 90 percent of all disaster-related property damage results from
Swannanoa River Flood Risk Management Study
Swannanoa River Flood Risk Management Study Measures Evaluated to Reduce Future Flood Damages City of Asheville U.S. Army Corps of Engineers Flooding History Part of the 132 square mile Swannanoa River
CRS Report for Congress
Order Code RS22285 Updated October 19, 2005 CRS Report for Congress Received through the CRS Web Hurricane-Damaged Drinking Water and Wastewater Facilities: Impacts, Needs, and Response Summary Claudia
A Systems Engineering Based Assessment of The Greater New Orleans Hurricane Surge Defense System Using the Multiple Lines-of-Defense Framework
A Systems Engineering Based Assessment of The Greater New Orleans Hurricane Surge Defense System Using the Multiple Lines-of-Defense Framework By Ezra Boyd, Ph.D., Rune Storesund, Ph.D., John Lopez, Ph.D.
REBUILDING BELMAR ABFE FLOOD MAPS &THE REBUILDING PROCESS
REBUILDING BELMAR ABFE FLOOD MAPS &THE REBUILDING PROCESS REBUILDING BELMAR ABFE Maps Preliminary FIRM Maps Flood Insurance Increased Cost of Compliance (ICC) Elevation of Structures Building Permits Acronyms
SSPEED Center Phase III: Developing a Houston- Galveston Area Protection System (H-GAPS)
Center Phase III: Developing a Houston- Galveston Area Protection System (H-GAPS) The Center 6100 Main St., MS317 Houston, Texas 77005 June 2, 2014 DPCAC meeting Center Phase I & II Recap (2009-2014) Phase
GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
Appendix F Benefit-Cost Analysis of Flood Protection Measures
Appendix F Benefit-Cost Analysis of Flood Protection Measures Acronyms used in Appendix F: AA B AA C AA D BC BFE EAD FEMA NED O&M PV RED USACE Average Annual Benefits Average Annual Cost Average Annual
The Army Corps of Engineers and the Flood Risk Challenge
The Army Corps of Engineers and the Flood Risk Challenge Presentation to Association of State Flood Plain Managers Steven L. Stockton, P.E. Director of Civil Works June 12, 2013 US Army Corps of Engineers
Federal Triangle Stormwater Working Group Federal Triangle Floodproofing Seminar BUILDING STRONG SM
Federal Triangle Stormwater Working Group Federal Triangle Floodproofing Seminar Initial Risk Flood Risk = Probability of Flooding x Consequences Zoning Building Codes Outreach Evacuation Planning Risk
C. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona
for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety
Jacksonville Port Authority: Fire and Rescue Marine Fire Station #40, Jacksonville, Florida
Draft Tiered Site-Specific Environmental Assessment Jacksonville Port Authority: Fire and Rescue Marine Fire Station #40, Jacksonville, Florida Port Security Grant Program Project # 2008-GB-T8-K019 November
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers
201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE
STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,
RESUME Lee A. Knuppel, P.E.
RESUME Lee A. Knuppel, P.E. OFFICE: EDUCATION: LEE A. KNUPPEL AND ASSOCIATES, Inc. 7770 Cooper Road, Suite 7 Montgomery, Ohio 45242 (513) 793-4222 Graduate: UCLA, Los Angeles, CA M.S. in Civil Engineering,
Table 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
HURRICANE ISAAC. National Disaster Recovery Framework (NDRF) Long Term Recovery Group (LTRG) Citizens Advisory Committee (CAC)
HURRICANE ISAAC National Disaster Recovery Framework (NDRF) Long Term Recovery Group (LTRG) Citizens Advisory Committee (CAC) 1 ABOUT ST. JOHN THE BAPTIST PARISH Population: 45,924 Cities: LaPlace, Reserve,
1. GENERAL ADVISORY BASE FLOOD ELEVATION (ABFE) QUESTIONS
INTRODUCTION As communities begin to recover from the devastating effects of Hurricane Sandy, it is important to recognize lessons learned and to employ mitigation actions that ensure structures are rebuilt
Capabilities Statement for Project Management Oversight Services. Presented to:
Capabilities Statement for Project Management Oversight Services Presented to: Department of Transportation Federal Transit Administration December 20, 2007 December 20, 2007 Mr. John Bardwell Contracting
Loss-Consistent Categorization of Hurricane Wind and Storm Surge Damage for Residential Structures
Loss-Consistent Categorization of Hurricane Wind and Storm Surge for Residential Structures Carol J. Friedland, P.E., Ph.D. 1, Marc L. Levitan, Ph.D. 2 1 Assistant Professor, Department of Construction
Jefferson Parish Department of Water Emergency Plan
1. Overview Jefferson Parish Department of Water Emergency Plan 1.1. Purpose The purpose of this document is to establish procedures for the Department of Water during natural disasters or terrorist acts.
USACE Civil Works Infrastructure Investment Trends: Glide-Path to Benign Neglect?
USACE Civil Works Infrastructure Investment Trends: Glide-Path to Benign Neglect? National Waterways Conference Legislative Summit Steven L. Stockton, P.E. Director of Civil Works, U.S. Army Corps of Engineers
LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS
Concrete Repairs LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS PART 1 - GENERAL 1.01 DESCRIPTION OF WORK A. The work will occur within the City of Lowell
Outlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
April 17, 2015 SUMMARY OF SUBJECT MATTER
April 17, 2015 SUMMARY OF SUBJECT MATTER TO: FROM: RE: Members, Subcommittee on Water Resources and Environment Staff, Subcommittee on Water Resources and Environment Hearing on A Review of the President
Piers, Wharves & Docks
Piers, Wharves & Docks Exposures and Concerns By: Christopher L. Pesce May 10, 2011 Piers, Wharves & Docks Statistics Why underwriters love to write docks Estimated industry losses for 2010: $30,000,000
Flood Risk Management
Flood Risk Management Value of Flood Risk Management Every year floods sweep through communities across the United States taking lives, destroying property, shutting down businesses, harming the environment
Flood Risk Management
Flood Risk Management Value of Flood Risk Management Value to Individuals and Communities Every year floods sweep through communities across the United States taking lives, destroying property, shutting
Mouth of the Columbia River Jetties Major Rehabilitation Study
Mouth of the Columbia River Jetties Major Rehabilitation Study PNWA Port of Vancouver January 29, 2010 US Army Corps of Engineers Project Overview Background Corps Guidance for Major Rehab Project Alternatives
ORDINANCE NO. 2013 -
ORDINANCE NO. 2013 - AN ORDINANCE OF BREVARD COUNTY, FLORIDA AMENDING CHAPTER 62, LAND DEVELOPMENT REGULATIONS SECTION 62-2891, LOT DRAINAGE, AND CHAPTER 22 BUILDINGS AND BUILDING REGULATIONS, SECTION
How to Become a Navy Engineer For $78,000 in USD
Presentation to Associated General Contractors COL Mark Deschenes Commander US Army Corps of Engineers Rock Island District February 2014 US Army Corps of Engineers Rock Island District 78,000 Square Miles
Flood Mitigation and Management in Bangkok Metropolitan Area
กร งเทพมหานคร Flood Mitigation and Management in Bangkok Metropolitan Area Present By Mr. Kriangkrai Phamornpol Department of Drainage and Sewerage Bangkok Metropolitan Administration 1 Flood Mitigation
SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER SYSTEMS. Stephen H. Scott 1 and Yafei Jia 2
US-CHINA WORKSHOP ON ADVANCED COMPUTATIONAL MODELLING IN HYDROSCIENCE & ENGINEERING September 19-21, Oxford, Mississippi, USA SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
Building Foundation and Structure
Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
Levees in Texas A Historical Perspective
Levees in Texas A Historical Perspective Melinda Luna, PE, 1 T. Lynn Lovell, PE, CFM 2, Joe T. Barrow, P.E. CFM 3, John Ivey, P.E. CFM 4, Jack Furlong, P.E., CFM 5 This paper describes a brief history
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
