MANUAL FOR INTERCONNECTION. Report for supporting the interconnection of rooftop-pv systems in the Philippines.
|
|
|
- Aubrey Marshall
- 9 years ago
- Views:
Transcription
1 Report for supporting the interconnection of rooftop-pv systems in the Philippines
2 Imprint Author Moeller & Poeller Engineering (M.P.E.) GmbH Europaplatz Tübingen, Germany .: [email protected] Web: Version: 12 August 2013 Publisher Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH On behalf of the German Federal Ministry of Economics and Technology (BMWi) Contact Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH Köthener Str. 2, Berlin, Germany Fax: +49 (0) [email protected] Web: Web: This report is part of the Project Development Programme (PDP) South-East Asia. PDP South-East Asia is implemented by the Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH on behalf of the German Federal Ministry of Economics and Technology (BMWi) under the renewables Made in Germany initiative. More information about PDP and about renewable energy markets in South-East Asia can be found on the website This publication, including all its information, is protected by copyright. GIZ cannot be liable for any material or immaterial damages caused directly or indirectly by the use or disuse of parts. Any use that is not expressly permitted under copyright legislation requires the prior consent of GIZ. All contents were created with the utmost care and in good faith. GIZ assumes no responsibility for the accuracy, timeliness, completeness or quality of the information provided.
3
4 Table of Contents 1 Introduction Distribution Companies in the Philippines Low-voltage and Medium-voltage Networks in the Philippines MV-Networks LV-Networks Public LV-Networks Commercial and Industrial LV-networks/LV-loads Grounding Net Metering Rules and Interconnection Standards Purpose and Applicability (Article I) Qualification and Eligibility (Article II) Interconnection Standards (Article III) Compliance Standards Summary of the Net-Metering Interconnection Standards Commercial Arrangements (Article IV) Net Metering Interconnection Standards General Guidelines Application for Interconnection Comments System Parameters Voltage Range of Operation Frequency Range of Operation Power Quality Power Factor Comments System Protection Synchronization Islanding System Grounding Disconnect Device Protective Relays Reclosing Comments Operation and Maintenance Metering i
5 5.7 Testing and Commissioning Impact of Net Metering Rules on the Sizing of PV-Rooftop-Installations Optimal Sizing of Solar Rooftop Installations The Use of Battery Storage Summary References Annex A: Survey of Distribution Companies of the Philippines ii
6 List of Tables Table 1: Distribution Companies in the Philippines... 2 Table 2: Typical MV voltage levels in the Philippines... 4 Table 3: Typical LV-Voltage Levels in the Philippines... 5 Table 4: Minimum Time Requirements for RE to Remain Connected at Different Voltage Ranges Table 5: Minimum Time Requirements for RE to Remain Connected at Different Frequency Ranges. 14 Table 6: Response to abnormal voltage conditions international standards Table 7: Required response to abnormal frequency conditions - international standards Table 8: Interconnection Protective Function Requirements for Inverters according to Table List of Figures Figure 1: 3-phase-4 wire and 2-phase-3-wire ( three-phase ) systems... 4 Figure 2: Typical technologies and voltage levels for public LV-feeders in the Philippines... 5 Figure 3: Typical technologies and voltage levels for supplying commercial/industrial LV-loads in the Philippines... 6 Figure 4: Common grounding scheme of LV-feeders in the Philippines... 7 Figure 5: Workflow of Application Process Figure 6: Typical Single Line Diagram for the protection of Inverter Figure 7: Metering Arrangement Figure 8: Load, generation and residual load profile, Example 1: 2kWp Figure 9: Load, generation and residual load profile, Example 2: 6 kwp Figure 10: Earning in Pesos for one day in function of installed peak capacity Figure 11: Incremental Earning in PHP for one day in function of additionally installed peak capacity22 Currency 1 USD = PHP (August 2013) 1 EUR = PHP (August 2013) Measurement W Watt Wp Watt peak Wh Watt hour kw Kilowatt kwp Kilowatt peak kwh Kilowatt hour MW Megawatt MWp Megawatt peak MWh Megawatt hour GW Gigawatt GWp Gigawatt peak GWh Gigawatt hour iii
7 1 Introduction High end-user tariffs and the support of a net-metering concept will soon initiate a relevant market for rooftop-pv systems in the Philippines. The purpose of this Manual for Interconnection is to provide relevant information about distribution grids in the Philippines for enabling or simplifying the interconnection of rooftop PV-systems in the Philippines. Following a brief survey about distribution grids and distribution network operators, this manual will provide an overview about typical medium-voltage (MV) and low-voltage (LV) network technologies of the Philippines including aspects relating to system grounding. Other sections of this manual give an introduction to the Net Metering Rules [1] and the corresponding Interconnection Standards [2] followed by a brief section relating to the impact that the Net Metering Concept may have on the optimum sizing of rooftop PV-systems. 1
8 2 Distribution Companies in the Philippines Table 1: Distribution Companies in the Philippines Residential Industrial Company Name Franchise area (Cities/Municipalities) Area in km2 customers customers Angeles Electric Corp (AEC) Angeles City 81, Clark Electric Distribution Co. Clark Special Economic Zone (CEDC) Subic Enerzone Subic Bay Freeport Zone 1, Davao Light & Power Co. Davao City, Panabo City/Carmen, Sto. (DLPC) Tomas & Dujali Iligan Light & Power Inc (ILPI) Iligan City 42, Dagupan Electric Corp (DECORP) San Fernando Electric Light & Power Co. (SFELAPCO) Cabanatuan Electric Corp (CELCOR) Cagayan Power & Light Co. (CEPALCO) MERALCO There are various distribution network companies in the Philippines operating distribution grids of various sizes and various areas. Meralco is by far the largest distribution network operator in the Philippines having more the 4.5 million clients and operating the distribution grid of Metro Manila and of some provinces. The distribution companies listed in Table 1 all operate distribution grids that are connected to the main transmission grid of the Philippines. Besides this, there are various grid operators, so-called Electric Cooperatives, operating island networks (networks not connected to the main transmission grid) of various size ranging from a few kw to several MW. The overview according to Dagupan City/Calasiao, Sta. Barbara, San Fabian, San Jacinto & Manaoag City of San Fernando/Floridablanca Cabanatuan City Cagayan de Oro City/Tagoloan, Jassan & Villanueva Metro Manila, the provicens of Rizal, Cavite and Bulacan, and parts of the provinces of Pampanga, Batangas, Laguna and Quezon Table 1 and Annex A is a result of a survey amongst most distribution network operators that has been carried out during a workshop in Manila in November The results of this survey can be summarized as follows: 70, ,000 11, , , ,662,429 9,662 9,337 Cotobato Light & Power Co. Cotobato City (CLPC) Mactan Electric Co. (MECO) Mactan City 68, Tarlac Electric Inc (TEI) Tarlac City 60,571 21, Visayan Electric Co (VECO) Cebu, Mandaue & Talisay/Consolacion, Lilioan, Mnglanilla, Naga & San Fernando 293,323 1, Electricity prices to residential customers range between 5.6 PHP/kWh and 9.5 PHP/kW, which is equivalent to around 0.1 Euro/kWh and 0.18 Euro/kWh (average 2011). Electricity prices to industrial customers range between 6.2 PHP/kWh and 10.5 PHP/kWh (0.12 Euro/kWh and 0.2 Euro/kWh, June 2012). 2
9 Average generation costs range between 2.6 PHP/kWh and 6.5 PHP/kWh (0.05 Euro/kWh and 0.12 Euro/kWh), whereas the average generation cost in 2011 (average over all utilities) was at 4.8PHP/kWh (0.09 Euro/kWh). Only the representatives of Dagupan Electric Corp., Cepalco, Cotubato Light and Power and Veco stated that they had some experience with renewable generation. According to the survey, there is only embedded generation in the grid of Cepalco (1 MW). Only two distribution network operators indicated that they had an interconnection policy in place: Cepalco, adopting the Philippine distribution code and Meralco ( Technical Guidelines of the Interconnection of distributed generation to the Meralco system ) applying to generators >100kW connected to Meralco s subtransmission grids (115 kv and 69 kv) and distribution networks (34.5 kv and 13.8 kv). The result of this survey shows that, despite of the high end-user tariffs, embedded generation in MV and LV networks in the Philippines is still very much at the beginning of its development and that there is still a lot of work to do for implementing codes and procedures for supporting the development of embedded renewable generation in the Philippines. 3
10 3 Low-voltage and Medium-voltage Networks in the Philippines Low-voltage (LV) and medium-voltage (MV) network technologies in the Philippines are widely in line with US-American standards. This includes the network frequency, which is 60 Hz and voltage levels at MV and LV levels. All aspects with regard to electrical installations, safety and design are described in the Philippine Electrical Code (PEC) [11], which has to be considered for all electrical installations. 3.1 MV-Networks Table 2: Typical MV levels in the Philippines Voltage Level Number of Phases Number of Wires Comment 34,5kV 3 4 In Meralco and Cepalco areas 34,5kV 2 3 In Meralco also named "3-phase" 23kV 3 4 Veco, Beneco 20kV 1 2 Cepalco area only (LN of 34,5kV LL) 13,8kV 3 4 Most common MV level 13,2kV 3 4 Standard in Electric Cooperatives 7,96kV 1 2 Cepalco area only (LN of 13,8kV LL) 7,62kV 1 2 Electric Cooperatives (LN of 13,2kV LL) 4,16kV 3 4 Olongapo City only Figure 1: 3-phase-4 wire and 2-phase-3-wire ( three-phase ) systems Public MV-feeders in the Philippines typically operate at 34.5 kv or 13.8 kv. MV-feeders are predominantly three-phase, four wire. The neutral conductor is connected to the star point of the transformer in the substation and solidly earthed. 4
11 In some areas, also two-phase three wire systems can be found (see Figure 1), with distribution transformers being connected in an open delta connection to the HV-side and hence allowing a threephase network at the LV-side. Therefore, these systems are also called three-phase -systems. Electric Cooperatives use 13.2 kv 3-phase, 4-wire as standard distribution technology Single phase, neutral return systems can be found at voltage levels of 20 kv (on LN-voltage of 34.5 V) and 7.96 kv (LN-voltage of 13.8 kv), especially in the area of Cepalco. Most distribution networks in the Philippines are built by overhead lines. For clearing transient faults, automatic reclosing schemes apply, which can lead to short-term interruptions of the underlying LV networks. 3.2 LV-Networks Table 3: Typical LV levels in the Philippines Voltage Level Number of Phases Application industrial/commercial 600Yn/347 3 industrial/commercial industrial/commercial 460Yn/265 3 industrial/commercial 400Yn/230 3 public (underground cables) industrial/commercial 230 1/2 public 115/230 1/2 public public The voltage levels listed in Table 3 represent standard voltage levels of the Philippines according to section of the PEC [11] Public LV-Networks Figure 2: Typical technologies and voltage levels for public LV-feeders in the Philippines 5
12 Most LV networks of Meralco and PEPOA-DUs are according to Configuration A of Figure 2. This type of system corresponds to an American split-phase network, but with the exception that the neutral conductor does not extend to the load. Therefore, both conductors of a Configuration A LV network represent a phase conductor, which is quite unique. Electric Cooperatives predominantly use Configuration B. Here, one of the two conductors is earthed at the transformer side. As in case of Configuration A, the load voltage is equal to 230V but with one conductor being a phase conductor and the other conductor being a neutral conductor. This system corresponds to European standards. Configuration C finally represents a classical 3-wire split phase connection, where both voltage levels, 230V and 115V, are available. As shown for Configuration C in Figure 2, it is possible that the neutral conductor of a LV feeder does not extend to the end of the feeder so that the end point may finally correspond to Configuration A. According to the Distribution Utility Survey [8], the following observations can be made: The large majority of LV-feeders of Meralco and PEPOA are according to Configuration A of Figure 2. In Electric Cooperatives, Configuration B represents the standard configuration for LVfeeders. Typical sizes of MV-LV-transformers are 25 kva or 15 kva supplying between 25 and 40 customers. Typical length of public LV-feeders is around 200m Commercial and Industrial LV-networks/LV-loads Figure 3: Typical technologies and voltage levels for supplying commercial/industrial LV-loads in the Philippines For supplying commercial or industrial loads, the three phase transformers configurations according to Figure 3 are common. 6
13 Depending on the phase, the configuration at the LV-side is equivalent to Configuration A or Configuration B according to Figure 2. It has to be highlighted, that usually only LL-voltages (230 V) shall be used, even if the right transformer in Figure 3 would also allow for a 115V LN-connection Grounding Rules Grounding rules that apply to electrical systems in the Philippines are described in Article 2.50 (Grounding and Bonding) of the PEC [11]. According to a) of the PEC, every non-current carrying metal part of an LV-installation must be connected together and grounded in a manner that: (1) limits the voltage to earth of such equipment (2) establishes an effective ground-fault current path Article defines general safety rules for grounded systems allowing for various options with regard to the use of neutral and earth conductors. Common Practice Figure 4: Common grounding scheme of LV-feeders in the Philippines According to studies carried out by SMA Solar Technology AG the most common LV network technology is Configuration A of Figure 2. In these systems, appliances are with ground wire taken out usually near the 2-prong plug and then connected to ground, such as a water pipe or any means of grounding. Therefore the grounding system of Configuration A can be considered as TT but without neutral conductor (see Figure 4). Due to the fact that water pipes lay underground but not as deep as a conventional grounding electrode, an isolation fault may not go to ground using the grounding wire as another way can have a lower resistance. 7
14 4 Net Metering Rules and Interconnection Standards The general rules for enabling the interconnection of embedded renewable energy source (RE-sources) are described in the so-called Net Metering Rules (RULES ENABLING THE NET-METERING PROGRAM FOR RENEWABLE ENERGY [1]). These rules cover: Purpose Applicability Qualification and Eligibility Inter-Connection Standards Commercial Arrangements 4.1 Purpose and Applicability (Article I) The purpose of the net metering rules, as described in [1] is to Encourage end-users to participate in renewable energy generation. Enable data-gathering for the creation of a knowledge base and hence for improving and optimizing the net metering program. Allow local players to gain experience and the confidence in installing embedded RE-systems for net-metering applications under local conditions. For the time being the net-metering rules only apply to grid connected RE technologies. The ERC can, in consultation with NREB and the electric power industry extend the applicability of these rules to off-grid installations. 4.2 Qualification and Eligibility (Article II) Basically all end-users that intend to install a renewable, distributed energy source and connect it to the grid qualify for the net-metering program. The net-metering program is explicitly limited to renewable energy sources that are installed within the premises of a qualified end-user. Hence, it does not apply to, e.g.: Non-renewable energy sources, such as mini-chp etc. Renewable energy power plants like wind farms or PV-farms that are not installed within the premises of a qualified end-user. 4.3 Interconnection Standards (Article III) This article of the net-metering rules makes provision to the technical rules and standards that need to be considered when installing a RE-generator that participates in the net-metering program Compliance Standards Distributed RE-installations must comply with the following standards: Philippine Electrical Code (PEC) [1], which applies to all electrical installations in the Philippines and defines general installation and safety standards. Distribution Service Open Access Rules (DSOAR) 8
15 Net-metering inter-connection standards, which are listed in Annex A of the net-metering rules (see [2]). The Net-metering inter-connection standards [2] further refer to the Philippine Distribution Code (PDC, [12]), which requires particular consideration with regard to power quality aspects Summary of the Net-Metering Interconnection Standards The Net-Metering Interconnection Standards [2] apply to all distributed generators that comply with the eligibility criteria of the Net Metering Rules (see section 4.2) and that are limited to 100 kw. It is further stated in section 4.3 of the Net-Metering Interconnection Standards that only installations having an installed capacity of less than 100kW will get permission from the distribution utility (DU). Hence, the limitation to 100kW effectively defines another eligibility criterion. The Net-Metering Interconnection Standards [2] are subdivided into the following sections: Overview, Scope and Purposes, Definitions General Guidelines Application for Interconnection System Parameters System Protection Metering Testing and Commissioning Bibliography, Appendix A brief summary of the Net-Metering Interconnection Standards together with some comments and reference to international practice is given in the following sections. A detailed summary and comments related to each article of the Interconnection Standards can be found in section 5 of this document. 4.4 Commercial Arrangements (Article IV) Article IV of the Net Metering Rules contains closes related to the pricing and cost recovery aspects. These clauses include: Aspects relating to the net metering agreement between DU and QE. Pricing methodology Cost recovery of net metering agreements Incremental supply and metering charge Billing Charges RE Certificate Until another set of special rules for the remuneration of net exported electricity has been established, the net electrical energy (generation minus own consumption) is remunerated at the rate of the blended cost of power generation in each DU area. In the case of Meralco, this current rate is currently at about 6 PHP. Cost of RE supply under net-metering agreements shall be included into the DU s total generation cost to be recovered from all DU customers. 9
16 5 Net Metering Interconnection Standards 5.1 General Guidelines (section 4 of [2]) The General Guidelines mainly define areas of responsibility of the Qualified End Unser (QE) and the Distribution Utility (DU). In brief, the main areas of responsibility are: The QE is responsible for design, installation, operation and maintenance of all installations on its property (unless otherwise agreed in the connection agreement) under consideration of the DU s standards. The QE s installation must conform to the PEC [11], PDC [12], DSOAR, other local codes and the Terms and Conditions of Service and Standard Rules and Regulation as approved by ERC. The DU shall conduct inspections, witness calibration and testing of the QE s lines, wires and switches and is entitled to remove the QE s generation from the system at any time for maintenance, test, repair, under emergency conditions or in case of safety concerns. It is not explicitly stated but it can be concluded that the design, installation, operation and maintenance of all installations outside the property of the QE is within the responsibility of the DU. Besides these areas of responsibility, the General Guidelines define that: The requirements of the Interconnection Rules have to be met at the connection point. The DU shall allow RE installations up to 100kW. It is unclear at this stage what rules apply to RE installations with an installed capacity greater than 100 kw. 10
17 5.2 Application for Interconnection (section 5 of [2]) Figure 5: Workflow of Application Process The application process for a RE-installation according to section 5 of the Net Metering Interconnection Standards [2] is illustrated in Figure 5. The process clearly defines the relevant areas of responsibility and the sequence of actions. It further provides details about the documentation to be exchanged and makes reference to other relevant standards and codes, which are not further described in more detail here. 11
18 5.2.1 Comments Generally the application process is clearly described but there are a few aspects that should be considered: Response time for distribution impact study: The process for a RE application defines a response time for the DU for verifying the completeness of an application. However, for the execution of a potentially required distribution impact study, guidelines about maximum acceptable response times are missing. In the case that these impact studies will be required on a regular basis for many applications, this step in the process will represent a serious bottleneck and has the potential to slow down the installation of distributed RE generation in the Philippines considerably. However, it is possible that the DUs of the Philippines will define more detailed processes for the interconnection of RE generation according to the Net Metering Rules and define corresponding response times as part of their internal processes. Approval of compliance with interconnection rules: The process doesn t foresee any formal approval of the conceptual design by the DU. Before the DU will carry out any compliance verification, the QE will have to build the RE-facility. Because no compliance statement is foreseen during the planning phase of a RE project, there is a high risk to the QE that changes/upgrades will be required after the installation has been completed, which can be very costly. In other countries (e.g. Germany), the application process foresees a compliance verification based on the conceptual design of a RE installation. Such compliance verification can either be within the responsibility of the DU or this responsibility can be outsourced to an independent, accredited certification body who, at the same time, takes full liability for this decision. In case of LV installations, it is common practice to submit certificates of conformity for the individual components of a RE facility to the DU for approval. Of course, an on-site inspection for verifying the conformity of the RE installation with the planning documents is always required prior to connection and energization. However, such an inspection cannot lead to a rejection as long as everything has been installed according to the relevant planning documents. For every QE who intends to realize a distributed RE facility in the Philippines, it is highly recommended to seek at least informal approval from the DU based on planning documents for avoiding costly modifications/upgrades of the RE facility after it has been installed or ask for manufacture declarations of conformance with the inter-connection rules of the Philippines (e.g. for PV inverter). 5.3 System Parameters (section 6 of [2]) Section 6 of the Inter-Connection Standards lists a number of main technical performance requirements, especially with regard to: Voltage range of operation Frequency range of operation Harmonics and Flicker Power factor 12
19 voltage in p.u. MANUAL FOR INTERCONNECTION Voltage Range of Operation Table 4: Minimum Time Requirements for RE to Remain Connected at Different Voltage Ranges (Table 1 of [[2]) Voltage in % of Base Voltage Time in s V<30 0,15 V=30 0,60 Linear Interpolation 30<=V<90 between 0,6 and 3,0 seconds 90<=V<=110 Normal Operating Range 110<V<120 1,00 V>=120 0,16 1,3 1,1 0,9 0,7 0,5 0,3 0, , time in s Figure 6: LVRT and HVRT requirement The normal voltage range of operation is defined to be within 90% < V < 110% of nominal voltage. In the case that voltage gets out of the normal range, the RE facility must remain connected as long as voltage stays within the limits according to Table 4, which correspond to the LVRT and HVRT requirement according to Figure 6. 13
20 5.3.2 Frequency Range of Operation Table 5: Minimum Time Requirements for RE to Remain Connected at Different Frequency Ranges (Table 2 of [[2]) Frequency Range in Hz Time >62,4 61,8<F<62,4 58,2<F<61,8 57,6<F<58,2 F<57,6 The frequency range of continuous operation is within 58,2<F<61,83 Hz. For frequencies outside the normal frequency range of operation, the RE facility must automatically disconnect according to the frequency-time settings of Table Power Quality With regard to power quality, the Interconnection Standards make reference to the Philippine Distribution Code [12]. The relevant power quality requirements are: automatic disconnection allowed if so decided by VRE operator 5 minutes Continuous Operation 60 minutes 5s Max. DC-current: 0,5% of rated full load current at the Connection Point Short-term flicker severity: Pst=1, Long-term flicker severity: Plt=0,8 (as specified in section of the PDC [12]. Harmonic current limits: Max. THD of 5% (as defined in section of the PDC [12]). Harmonic voltage limits: Max. THD of 5% (as defined in section of the PDC [12]). As per the PDC, flicker limits at the Connection Point represent total Flicker Limits resulting from all varying loads and generators in the network, not only caused by the RE-installation to be connected. The same applies to harmonic voltage limits Power Factor It is required that the power factor stays above 0.85 lagging. 14
21 5.3.5 Comments Voltage and Frequency Range of Operation Table 6: Response to abnormal voltage conditions international standards (see also [7]) Country Standard international IEC Lower limit upper limit trip time 50% 135% 0.1 s / 0.05 s 85% 110% 2 s Europe EN % 115% 1.5 s / 0.5 s Germany VDE AR-N % 110% 0.1 s Spain RD % 110% 0.5 s Italy DK % 120% 0.2 s / 0.1 s Philippines USA IEEE 1547 South Korea PV 501 0% >120% 0,16 s LVRT 120% 2 s / 1 s 50% 120% 0.16 s 88% 110% 2 s / 1 s 50% 120% 0.16 s 88% 110% 2 s Table 7: Required response to abnormal frequency conditions - international standards (see also [7]) Country Net Metering Voltage monitoring xx% of V nom Lower limit upper limit trip time International IEC Hz + 1 Hz 0.2 s Europe EN Hz + 1 Hz 0.5 s Germany VDE AR-N Hz +1,5 Hz 0,1 s Spain RD 1663/661-2 Hz + 1 Hz 3 s / 0.2 s Italy DK Hz Hz 0.1 s Philippines standard Net Metering Frequency monitoring deviation from fnom - 2,4 Hz +2,4 Hz 5 s/0s - 1,8 Hz + 1,8 Hz 60min/5min USA IEEE Hz Hz 0.16 s South Korea PV Hz Hz 2 s Australia AS Hz + 5 Hz 2 s The required response to abnormal voltage conditions is not in-line with standard international practice (see 6). In previous (draft-) versions of the interconnection rules, the corresponding table defined maximum times to disconnect, hence maximum times for under-/overvoltage protection relays to operate. However, in the final version of the interconnection rules, the corresponding tables have been transformed into requirements defining minimum times for remaining connected in the case of a voltage event. With these now rules, the Net-Metering interconnection rules in the Philippines effectively require LVRT/HVRT capability, which is not in-line with international practice for LV-connected PV systems. 15
22 It is therefore recommended, prior to the installation of solar roof top systems, to clarify with the distribution utility, if they indeed require LVRT/HVRT for LV connected PV systems and which requirements apply for undervoltage protection settings, ie the voltage settings and time to disconnect. The required response to abnormal frequency conditions is in line with corresponding practice in other parts of the world. 5.4 System Protection Section 7 of [2] defines protection and other safety aspects of a RE-installation. This includes: Synchronization Islanding Grounding Disconnect Device Protective Relays Reclosing Synchronization The statements relating to synchronization don t relate to inverter connected RE-sources (see also Table 6 of [2] Islanding The RE installation must be equipped with protection against unintentional islanding that detects islanding conditions and automatically disconnects the RE-installation from the DU s system. Automatic reconnection is allowed if the DU s network is re-energized for several minutes System Grounding System grounding must be in-line with the PEC [11] (see also section of this document) Disconnect Device For safety reasons, the RE-installation must be equipped with a disconnect device for use by the DU as a means of electrically isolate the RE-facility from the DU s network and to establish working clearances for maintenance, safety and system considerations. The disconnect device shall be physically located: within 10 feet from the Connection Point or, if this is not practical, between the RE-facility and the Connection Point The type of disconnect device must Allow for visual indication of the contact s position The handle must be lockable in the open position with a padlock Readily accessible at all times by DU personnel 16
23 5.4.5 Protective Relays For inverter-based RE-facilities (PV), table 6 of [2] applies Table 8: Interconnection Protective Function Requirements for Inverters according to Table 6 of [2] The actual protection arrangement for an inverter, including the disconnect switch is depicted in Fehler! Verweisquelle konnte nicht gefunden werden., which corresponds to Appendix D of [2]. Figure 7: Typical Single Line Diagram for the protection of Inverter (Appendix D of [2]) Reclosing This section of [2] defines that the response of a RE-facility to automatic reclosing actions in MV or LV-networks. The following is required: Immediate disconnection when the system is down Automatic resynchronization after the reclosing devices has reestablished the portion of the system to which the RE-facility is connected Comments Protection and Disconnection requirements defined in in section 7 of [2] are in-line with international standards. 17
24 The requirement to disconnect immediately stated in the Reclosing-section for the case that the system is down is in slight contradiction with the required undervoltage protection settings according to Fehler! Verweisquelle konnte nicht gefunden werden.. With these settings, the system would disconnect with a delay of 0,16s. A requirement for an instantaneous trip because of undervoltage doesn t exist in [2]. 5.5 Operation and Maintenance Section 8 contains some general rules about the QE s obligations with regard to Operation and Maintenance of the RE-facility. 5.6 Metering Figure 8: Metering Arrangement The metering arrangements according to section 9 of [2] are depicted in Fehler! Verweisquelle konnte nicht gefunden werden.7. Essentially, it is required to install the following metering devices: Two uni-directional meters or one bi-directional meter at the connection point that can measure the hourly net-exchange with the system. A generation check meter may be installed for the purpose of recording the hourly RE production for purposes of issuance of RE Certificate, which the DU can use to comply with its RPS requirements. The QE must provide the required space and associated civil works for the location of the metering devices. Meters are owned and operated by a Metering Service Provider (MSP). 18
25 5.7 Testing and Commissioning After completion of installation and before energizing the system, the QE is responsible for carrying out the relevant commissioning tests. The DU has the right to witness these tests and to receive a copy of the test data. Commissioning tests of inverters include: Verification and inspections Production tests: Response to abnormal voltage Response to abnormal frequency Unintentional islanding test Cease-to-energize tests The QE is responsible for installing the required test equipment at the RE facility. Prior to final approval or at any time, the DU reserves the right to carry out protection tests. 19
26 6 Impact of Net Metering Rules on the Sizing of PV-Rooftop-Installations 6.1 Optimal Sizing of Solar Rooftop Installations The optimal sizing of PV rooftop installations in the Philippines will have to consider the following constraints: Available rooftop space Daily and seasonal load variation The value of electricity generated by a solar rooftop facility in the Philippines is equal to the endconsumer tariff (e.g. around 13P/kWh=0.25Euro/kWh in the case of Meralco), as long as the generated power is below the consumed power (net load >0). During all times that generation exceeds load (net load <0, exporting, see dashed area in Figure 10), the value of electricity generated by a solar rooftop facility that exceeds the load drops to the blended generation costs (e.g. 6P=0.115Euro/kWh). When evaluating the earnings resulting from a rooftop PV-installation, the electricity payment without PV installation has to be compared with the electricity payment with PV installation. Therefore, for each hour of the year, the energy consumption resulting from the load and from the residual load has to be calculated for each hour. The resulting time series of kwh/h consumption has to be summed up for obtaining the total annual energy consumption. However, because export and import tariffs are different, two sums have to be calculated for the residual load: Sum of all hourly energies >0 (import) Sum of all hourly energies <0 (export) The resulting imported and exported energies can finally be multiplied with the corresponding import and export tariffs. By comparing the payment with and without PV installation, the return of investment of a rooftop PVfacility can be evaluated. This has been done for one day based on the load and PV-generation profiles according to Figure 9. The installed peak capacity of the PV installation has been increased in steps of 1kWp and the resulting earnings have been calculated (see Figure 11). As Figure 12 shows, the return of investment for additionally installed PV-capacity decreases drastically when the installed capacity exceeds the limit of net export. However, when carrying out this analysis for a complete year, under the consideration of cloudy days and seasonal variations, load variations between week-days and week-ends and seasonal load variations it is expected that the degradation of profitability would not as steep as in Figure 12. For identifying the optimal size of a PV-installation, it is strongly recommended to carry out such a study for a complete year considering: Solar radiation over one or several years Load profile 20
27 However, in contrast to countries with a feed-in tariff that is higher than the end-consumer tariff, as it was the case in Germany until the beginning of 2012, it is expected that the size of PV-installations will be in proportion to the load. Consequently, voltage problems resulting from excessive PV-infeed don t have to be expected. Figure 9: Load, generation and residual load profile, Example 1: 2kWp Figure 10: Load, generation and residual load profile, Example 2: 6 kwp 21
28 800 [P] Earning in Pesos [kwp] Figure 11: Earning in Pesos for one day in function of installed peak capacity 120 [P] Incremental Earning in Pesos [kwp] Figure 12: Incremental Earning in Pesos for one day in function of additionally installed peak capacity 6.2 The Use of Battery Storage For avoiding high exports and low income during times of high PV production and low load, the use of additional battery storage could be a potential option. By storing the energy that is in excess to the load and feeding it into the grid during times of high load and low PV-generation (e.g. in the evening), the value of the generated electricity would increase from export tariff (e.g. 6PHP/kWh) to end-user tariff (e.g. 13PHP/kWh). 22
29 Assuming a battery with a net storage capacity of 3kWh and one load-de-load cycle per (sunny) day, the required cost of corresponding battery storage for making this an economical solution can be calculated: The assumptions are: Net storage capacity: 3kWh 1 load-de-load cycle during a sunny day (3kWh/day) 250 sunny days per year (250 load-de-load cycles per year) Based on these assumptions, there will be around 750kWh of loaded and de-loaded energy per year. The resulting annual income from such battery storage system would be equal to: 13P 6P 5250P Euro I 750kWh 100 A commercially available battery storage system having a net capacity of 3kWh based on Lithium-Ion technology currently costs around 6000 Euro (including inverter). Hence the pay-back period would be in the order of magnitude of 60 years. However, the actual lifetime of a Lithium-Ion battery is currently only in the order of around 15 to 20 years. Consequently, assuming that electricity prices in the Philippines remain constant, costs of batteries would have to drop by at least a factor of three in order to pay its investment back over its lifetime. 23
30 7 Summary This document contains guidelines for planning and installing solar rooftop systems in the Philippines under the Net-Metering Rules and Interconnection Standards, which have become effective in July The guidelines presented in this document include: Overview about distribution companies in the Philippines, including a survey of end-consumer tariffs. Overview about MV and LV network technologies and grounding standards in the Philippines A commented summary of the Net Metering Rules and Interconnection Standards of the Philippines Some recommendations with regard to the sizing of solar rooftop systems. 24
31 References [1] Energy Regulatory Commission of the Philippines: Rules Enabling the Net-Metering Program for Renewable Energy, V.9, 2012 [2] Energy Regulatory Commission of the Philippines: Annex A - Net Metering Interconnection Standards V4, 2012 [3] Energy Regulatory Commission of the Philippines: Annex B Sample Billing Formats and Simulations V2, 2012 [4] Energy Regulatory Commission of the Philippines: Annex C Net Metering Agreement V3, 2012 [5] Markus Pöller: Connecting Solar Rooftops to the Grid Lessons learned from the Workshop on and in Clark/Philippines, [6] Ranulfo Ocampo: Draft Net-Metering Rules, V.9, Presentation from the PEPOA-Workshop on in Clark/Philippines [7] SMA Solar Technology AG: Technical Capabilities of Modern Solar Rooftop Solutions, Presentation from the PEPOA-Worksho on in Clark/Philippines [8] Workshop PEPOA-Connecting Solar Rooftops to the Grid: Distribution Utility Survey, , Clark/Philippines [9] PEPOA: PV Roadmap Development Survey, [10] Juan Pena de Juana/SMA: Input for Manual of Interconnection, from [11] Energy Regulation Commission (ERC): Philippine Electrical Code (PEC) [12] Energy Regulation Commission (ERC); Philippine Distribution Code (PDC), December 2001 [13] Schneider Electric; Planungskompendium Energieverteilung,
32 Annex A: Survey of Distribution Companies of the Philippines 26
33 27
34
NET METERING SUB-CODE. for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana
for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana JANUARY 2015 1 Table of Contents PART A: BACKGROUND... 1 1 Introduction... 1 1.1 Objective... 1 1.2 Status... 1 2
Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid
Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy
Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems
Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission
Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva
Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Issued: August 2009 SIZED UP TO 100 KVA TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Applicability... 1 1.2 Definitions...
POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT
POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT This Power Purchase agreement is entered into at (place).. on this. day of between Electricity Supply Company Limited
FIXED CHARGE: This is a cost that goes towards making the service available, including
ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer
Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns
Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Mehmet H. Cintuglu, [email protected], Armando Altamirano, [email protected] Osama A. Mohammed, [email protected] Energy Systems
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Draft Maharashtra Electricity Regulatory Commission (Net Metering for Rooftop Solar Systems) Regulations, 2015 Electricity Act, 2003 No. MERC / Legal
SPECIFICATION COG-2007
Cleco Power LLC SPECIFICATION COG-2007 FOR PARALLEL OPPERATION OF CUSTOMER-OWNED GENERATION ON CLECO S ELECTRICAL SYSTEM Revised: March 7, 2014 CONTENTS ITEM NO. TITLE PAGE NO. 1.0 Scope 3 2.0 Policy On
TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION. Micro Generation & Small Generation, 3-phase, less than 30 kw
TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION Micro Generation & Small Generation, 3-phase, less than 30 kw i COPYRIGHT 2010 HYDRO ONE NETWORKS INC. ALL RIGHTS RESERVED ii LIMITATION
Session 10: General Overview of Interconnection Standards & Grid Codes for High Penetration PV October 21, 2015 Santiago, Chile
Session 10: General Overview of Interconnection Standards & Grid Codes for High Penetration PV October 21, 2015 Santiago, Chile Michael Coddington National Renewable Energy Laboratory Golden, Colorado,
Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014
1 Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables Bob Yinger Southern California Edison April 15, 2014 Southern California Edison SCE provides power to: Nearly
Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering
Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.
AC COUPLED HYBRID SYSTEMS AND MINI GRIDS
, Michael; Hermes, Matthias SMA Technologie AG Hannoversche Str. 1-5 34266 Niestetal GERMANY E-mail: [email protected] E-mail: [email protected] 1. INTRODUCTION Distributed supply based on renewable
Perspectives for ESS in Germany and Europe legal situation and applications StoREgio energy storage system association
Perspectives for ESS in Germany and Europe legal situation and applications StoREgio energy storage system association Dr. Peter Eckerle Managing Director [email protected] Topics Who is StoREgio?
Rule 5.500 Fast Track Analysis for National Life Insurance Co.
Rule 5.500 Fast Track Analysis for National Life Insurance Co. For a 500 kw Solar array to be located at 155 Northfield Street in Montpelier, Vermont Green Mountain Power Pam Allen Date: 5/31/13 SECTION
NET-METERING REFERENCE GUIDE. How to avail solar roof tops and other renewables below 100 KW in the Philippines. www.renewables-made-in-germany.
NET-METERING REFERENCE GUIDE How to avail solar roof tops and other renewables below 100 KW in the Philippines www.renewables-made-in-germany.com Imprint Editor Markus Dietrich GIZ Consultant, Project
Three phase connection
Three phase connection with SUNNY MINI CENTRAL Contents The inverters of the Sunny Mini Central product family have been especially conceived for their use in threephase feed-in systems. This technical
TERMS AND CONDITIONS
Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator
KERALA STATE ELECTRICITY REGULATORY COMMISSION
KERALA STATE ELECTRICITY REGULATORY COMMISSION Dated 24 th January 2014 NOTICE Notice is hereby given that Kerala State Electricity Regulatory Commission has published the Draft Kerala State Electricity
Connection of micro-generation to the electricity distribution network
Connection of micro-generation to the electricity distribution network Network recommendation YA9:09 Sivu 1(20) CONTENTS INTRODUCTION...3 1. MARKINGS AND DEFINITIONS...3 2. DEFINITION OF MICRO-GENERATION
Electric Power Industry Regulation in the Philippines (Part 2)
Electric Power Industry Regulation in the Philippines (Part 2) Atty. Josefina Patricia A. Magpale-Asirit Commissioner Energy Regulatory Commission September 8, 2015 Kuala Lumpur, Malaysia Regulatory Principles
APPLICATION NOTE USING A MODEL 3060-MS SERIES AS A REGENERATIVE AC SOURCE FOR PV INVERTER TEST APPLICATIONS. Abstract.
USING A MODEL 3060-MS SERIES AS A REGENERATIVE AC SOURCE FOR PV INVERTER TEST APPLICATIONS Abstract This application note describes the necessary procedure to use a standard Pacific Power Source Model
Context: significant penetration of DG = increased risks for system security
Distributed Generation: towards an effective contribution to power system security IEEE Tampa GM 2007: Panel on Impact of Dispersed Generation on Power System structure & security Bruno Meyer Outline Context:
CHANGING THE WORLD WITH COMPELLING IDEAS. German Indian Renewable Energy Dialogue 1st of October 2008
Titel: IBC SOLAR mit starken Ideen die Welt verändern Autor: Ort, 00. Monat 2008 CHANGING THE WORLD WITH COMPELLING IDEAS German Indian Renewable Energy Dialogue 1st of October 2008 2008 IBC SOLAR Agenda
N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS
N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers
Energex. Statement of expected price trends. 1 July 2014 to 30 June 2015. -1-2014/15 Statement of expected price trends
Energex Statement of expected price trends 1 July 2014 to 30 June 2015-1- 2014/15 Statement of expected price trends Version control Version Date Description 1.0 16 June 2013 Published on Energex s website
SUNNY TRIPOWER 5000TL 12000TL
SUNNY TRIPOWER 5000TL 12000TL STP 5000TL-20 / STP 6000TL-20 / STP 7000TL-20 / STP 8000TL-20 / STP 9000TL-20 / STP 10000TL-20 / STP 12000TL-20 NEW available as 10 kva and 12 kva versions Economical Flexible
Accompanying the Philippines on the road toward sustainable energy supply. GIZ s support to renewable energy development in the Philippines
Accompanying the Philippines on the road toward sustainable energy supply GIZ s support to renewable energy development in the Philippines Imprint This publication is by the Deutsche Gesellschaft für Internationale
Earth Fault Detection Basics in Theory
Earth Fault Detection Basics in Theory Author: Dipl.-Ing. Ingo Kühnen Woodward Power Solutions Krefelder Weg 47 47906 Kempen, Germany Kempen, 16.04.2010 Earth_Fault_Detection_20100416.doc page 1 1. Star
General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System
General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System Direction Planification des actifs et expertise de transport February 2011 TABLE OF CONTENTS 1. CONDUCTING
What Matters for Successful Integration of Distributed Generation
What Matters for Successful Integration of Distributed Generation Thomas Ackermann Energynautics GmbH, Germany [email protected] Expert User of DIgSILENT PowerFactory for Power Systems Studies
AUSTIN ENERGY INTERCONNECTION GUIDE FOR CUSTOMER-OWNED POWER PRODUCTION FOR FACILITIES UP TO 10MW A INTERCONNECTION CLASSIFICATIONS...
AUSTIN ENERGY INTERCONNECTION GUIDE FOR CUSTOMER-OWNED POWER PRODUCTION FOR FACILITIES UP TO 10MW TABLE OF CONTENTS PAGE INTRODUCTION... 4 A INTERCONNECTION CLASSIFICATIONS... 5 B. APPLICATION PROCESS
Experimental Verification of Advanced Voltage Control for Penetration of PV in Distribution System with IT Sectionalizing Switches
21, rue d Artois, F-75008 PARIS C6 _113 _2012 CIGRE 2012 http : //www.cigre.org Experimental Verification of Advanced Voltage Control for Penetration of PV in Distribution System with IT Sectionalizing
About us The Challenge Younicos Technology Our Services Business Segments & Projects. Page 3
Contents About us The Challenge Younicos Technology Our Services Business Segments & Projects Page 3 Younicos Company Presentation 2012 About us What we do Founded in 2008, our employees today develop
LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems
LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems A. General This Net Metering Standard for Customer-Owned Grid Connected Electric Generating Systems sets forth the
FIT TIER 2 Application
FIT TIER 2 Application Application Information The below information Auto-Fills from your registration information: Building Permit Application Date: Project Completion Date: Name: Address: City: State:
Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage
Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,
POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends
POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...
Balancing and Reserve Power by PV Plants. Ken Christensen MSEE, BSEE Global Product Manager, SMA Utility-Scale and Hybrid Solutions
Balancing and Reserve Power by PV Plants Ken Christensen MSEE, BSEE Global Product Manager, SMA Utility-Scale and Hybrid Solutions IEEE PES 2014 2 Disclaimer IMPORTANT LEGAL NOTICE This presentation does
Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process
Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering
Kinetic energy recovery on railway systems with feedback to the grid
Kinetic energy recovery on railway systems with feedback to the grid Authors: J.M. ORTEGA, METRO DE BILBAO;S:A: H. IBAIONDO, A. ROMO. INGETEAM TRACTION,S.A. 1. Introduction The increasing concern with
MAKING SOLAR ENERGY COST-EFFECTIVE TODAY IS A SNAP
MAKING SOLAR ENERGY COST-EFFECTIVE TODAY IS A SNAP Dr. James A. White, P.E. Senior Energy Services Engineer Chelan County Public Utility District P.O. Box 1231 Wenatchee, Washington 98807 [email protected]
STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK
STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK This statement is effective from 1 April 2010 This statement is approved by the Gas and Electricity
Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.
Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine
APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution
APPLICATION NOTE Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution INCREASING PV HOSTING WITH EMPOWER TM SOLUTION Executive Summary Distributed solar photovoltaic
Solar Power Plant Design and Interconnection
Solar Power Plant Design and Interconnection Wind & Solar Super Session July 27, 2011 E.H. Camm, S.E. Williams S&C Electric Company Outline Introduction Utility-scale PV power plant Grounding Reactive
SIMULATING HYBRID ENERGY GRIDS IN SMART CITIES FOCUS ON ELECTRIC ENERGY SYSTEMS
Sawsan Henein AIT Austrian Institute of Technology Electric Energy Systems Research Group SIMULATING HYBRID ENERGY GRIDS IN SMART CITIES FOCUS ON ELECTRIC ENERGY SYSTEMS Sustainable Places 2015 Savona,
SCHEDULE FIT TIER 1 AND TIER 2
SHEET NO. 78 Effective October 22, 2010 SCHEDULE FIT TIER 1 AND TIER 2 Feed-In Tariff - Purchases from Tier 1 and Tier 2 Eligible Renewable Energy Generating Facilities A. Availability: This schedule feed-in
Green Power Accounting Workshop: Concept Note For discussion during Green Power Accounting Workshop in Mexico City, May 13th 2011
Introduction As more companies and government organizations prepare greenhouse gas (GHG) inventories that reflect the emissions directly and indirectly associated with their operations, they increasingly
Electrical Shore Connections / Cold Ironing
STANDARD FOR CERTIFICATION No. 2.25 Electrical Shore Connections / Cold Ironing JULY 2014 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version
Interconnection of Generators to EDI s Distribution System
Interconnection of Generators to EDI s Distribution System May 22, 2002 This document sets forth the guidelines for connecting a power producing facility to the Alberta Interconnected Electric System through
Technical Information Short-Circuit Currents Information on short-circuit currents of SMA PV inverters
Technical Information Short-Circuit Currents Information on short-circuit currents of SMA PV inverters Content During grid failures as for example voltage dips, all PV inverters may generate currents that
Advanced Protection of Distribution Networks with Distributed Generators
Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School
Western Australia and the Northern Territory are not connected to the NEM, primarily due to the distance between networks.
Australia has one of the world s longest alternating current (AC) systems, stretching from Port Douglas in Queensland to Port Lincoln in South Australia and across the Bass Strait to Tasmania a distance
Report on the Status of Net Energy Metering In the State of Maryland. Prepared by The Public Service Commission of Maryland
Report on the Status of Net Energy Metering In the State of Maryland Prepared by The Public Service Commission of Maryland Prepared for the General Assembly of Maryland Under Public Utilities Article 7-306(h)
INFORMATION DOCUMENT
INFORMATION DOCUMENT For Design, manufacture, supply, installation and commissioning of different capacity Roof top Solar PV Power projects under Net Metering policy in the state of Punjab. PUNJAB ENERGY
Tetchi Cruz-Capellan Founding President & International Relations Chair Philippine Solar Power Alliance
PV Market & Structure of the Philippine Solar Sector Tetchi Cruz-Capellan Founding President & International Relations Chair Philippine Solar Power Alliance Presentation Outline Overview of the Philippine
RENEWABLE ENERGY INFEED R Herman, M Malengret and CT Gaunt University of Cape Town, South Africa
RENEWABLE ENERGY INFEED R Herman, M Malengret and CT Gaunt University of Cape Town, South Africa Technology and tariffs for renewable energy in-feed at LV and MV Ron Herman : Performance of LV feeders
Earthing Guidance Notes
Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head
Nuclear Power Plant Electrical Power Supply System Requirements
1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, [email protected] Abstract Various regulations and standards require from electrical power system of the
Financial Analysis of Solar Photovoltaic Power plant in India
Financial Analysis of Solar Photovoltaic Power plant in India M. Ganga Prasanna, S. Mahammed Sameer, G. Hemavathi Department of Management Studies MadanapalleInstitute of Technology& Science Post Box No:
Issue 06 / 2015. StoraXe Home & Small Business Battery storage systems for professionals
Issue 06 / 2015 StoraXe Home & Small Business Battery storage systems for professionals Lithium-ion battery storage systems Home & Small Business The StoraXe Home & Small Business product portfolio has
Photovoltaics in Germany Market Development and Perspectives
Photovoltaics in Germany Market Development and Perspectives Matthias Reitzenstein German Solar Industry Association (BSW-Solar) German Solar Industry Association 2 TASK To represent the German solar industry
VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES
VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES C. Schwaegerl*, M.H.J. Bollen, K. Karoui #, A. Yagmur + *Siemens AG, # Tractebel STRI AB
FACT SHEET. NEM fast facts:
(NEM) operates on one of the world s longest interconnected power systems, stretching from Port Douglas in Queensland to Port Lincoln in South Australia and across the Bass Strait to Tasmania a distance
JEA Net Metering Policy Tiers 1-3
Summary The JEA Net Metering Policy is intended to facilitate generation from customer-owned renewable energy sources to offset up to all of the customer s energy requirements. The policy provides system
NETWORK PRICE LIST 2014/2015. Effective 1 July 2014
NETWORK PRICE LIST 2014/2015 Effective 1 July 2014 Document Amendment History Version No. Publication Date Comments 1.0 17 June 2014 AER Approved Pricing 2.0 15 July 2014 Updated Substation and Transformer
Distributed Generation and the Impact on a Distribution System. Brian Lassiter Technical Sales Engineer
Distributed Generation and the Impact on a Distribution System Brian Lassiter Technical Sales Engineer Company Overview Founded in 1989 in Abilene, TX Industry leader in Engineering and Operations Utility
Corona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application
Corona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application DWP s new Solar Partnership Program is available to help offset your investment in a PV system and get you
Audit Report Rottnest Island 2015 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems
ABN 20 009 454 111 Rottnest Island 2015 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems Telephone: +61 8 9260 0003 Fax: +61 8 9225 7447 E-Mail:
PERFORMANCE OF MPPT CHARGE CONTROLLERS A STATE OF THE ART ANALYSIS
PERFORMANCE OF MPPT CHARGE CONTROLLERS A STATE OF THE ART ANALYSIS Michael Müller 1, Roland Bründlinger 2, Ortwin Arz 1, Werner Miller 1, Joachim Schulz 2, Georg Lauss 2 1. STECA ELEKTRONIK GMBH, Mammostr.
ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe
NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3
Fronius IG Plus. The next generation grid-connected PV inverter
Fronius IG Plus The next generation grid-connected PV inverter Maximum energy harvest cloudy or clear The first complete inverter solution. Reliable. Proven. Smart. An outstanding addition to the family:
Main variations of business models for Flexible Industrial Demand combined with Variable Renewable Energy
Innovative Business Models for Market Uptake of Renewable Electricity unlocking the potential for flexibility in the Industrial Electricity Use Main variations of business models for Flexible Industrial
Electric Power Distribution
Electric Power Distribution A S Pabla Consulting Engineer and Former Chief Engineer Punjab State Electricity Board McGraw-Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New
How to regulate self-consumption of electricity produced from PV panels so that it is beneficial to the energy system
How to regulate self-consumption of electricity produced from PV panels so that it is beneficial to the energy system Prof. Bernd Engel Representative of the Board for grid integration European Commission
Technical Requirements for Renewable Energy Systems Connected to the Low Voltage (LV) Network via Inverters
Technical Requirements for Renewable Energy Systems Connected to the Low Voltage (LV) Network via Inverters Specification Number: HPC-9FJ-12-0001-2012 CONTENTS 1 Introduction... 6 1.1 Context... 6 1.2
De Jaeger, Emmanuel ; Du Bois, Arnaud ; Martin, Benoît. Document type : Communication à un colloque (Conference Paper)
"Hosting capacity of LV distribution grids for small distributed generation units, referring to voltage level and unbalance" De Jaeger, Emmanuel ; Du Bois, Arnaud ; Martin, Benoît Abstract This paper revisits
Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer
Size template Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer The average system size has doubled since 2010 Key Network Issues Reverse power on up to 12 off 11 kv feeders
PacifiCorp Original Sheet No. 476 FERC Electric Tariff, Substitute 6 th Rev Volume No. 11 APPENDIX 2 TO SGIP
PacifiCorp Original Sheet No. 476 APPENDIX 2 TO SGIP SMALL GENERATOR INTERCONNECTION REQUEST (Application Form) Transmission Provider: Designated Contact Person: Address: Telephone Number: An Interconnection
KERALA STATE ELECTRICITY REGULATORY COMMISSION
KERALA STATE ELECTRICITY REGULATORY COMMISSION Notification No. 2096/KSERC/CT/2014 Dated, Thiruvananthapuram 10 th June 2014. In exercise of the powers conferred under sections 66, 86 (1) (e) and 181 of
INTEGRAL REMOTE MANAGEMENT SOLUTION cirwatt b series
Communication system for the management of electrical installations INTEGRAL REMOTE MANAGEMENT SOLUTION cirwatt b series MID Approval Technology for energy efficiency PLC Communications (Power Line Communication)
Regulation by the Feed-in Tariff: Experiences from Germany
Solar Power International 08 Panel Technology & Regulation: How to do it Right 16th October 2008, San Diego, California, USA Regulation by the Feed-in Tariff: Experiences from Germany Gerhard Stryi-Hipp
Grid Connected Storage Various Applications Realised with Proven Technologies. Wilhelm van Butselaar Clean Energy Week 2013, Brisbane July 2013
Grid Connected Storage Various Applications Realised with Proven Technologies Wilhelm van Butselaar Clean Energy Week 2013, Brisbane July 2013 Disclaimer IMPORTANT LEGAL NOTICE This presentation does not
Hyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
SDG&E Electric Distribution System Interconnection Handbook. <Revised as of 10/21/2015>
TABLE OF CONTENTS 1 Introduction... 1 1.1 Purposes... 1 1.2 Applicability and Related Tariffs... 1 1.3 Interconnection Agreement Required... 1 1.4 Technical Requirement... 1
Network Price List and Explanatory Notes
Essential Energy Network Price List (Excluding GST) Effective 1 July 2014 Tariff Code Obsolete tariffs on same rate Description Network Energy Energy Energy Energy Energy Energy Energy Peak Shoulder OffPeak
Dakota Energy Cooperative, Inc. POLICY STATEMENT
Dakota Energy Cooperative, Inc. POLICY STATEMENT Subject: Member Owned Small Renewable Energy Policy No. 57 Rate and Interconnection Requirements Issue Date: May 21, 2008 Revised Date: December 16, 2014
Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template
Application Note Application-oriented testing of line differential protection end to end in the field using the corresponding RelaySimTest template Author Jens Baumeister [email protected] Date
EssPro Energy Storage Grid Substation The power to control energy
EssPro Energy Storage Grid Substation The power to control energy EssPro Grid gives you the power to control energy helping to keep smart grids in balance Maximizing the value and performance of energy
ABB central inverters PVS800 100 to 1000 kw
Solar inverters ABB central inverters PVS800 100 to 1000 kw ABB central inverters raise reliability, efficiency and ease of installation to new levels. The inverters are aimed at system integrators and
ENTSO-E Working Draft Network Code on Emergency and Restoration
ENTSO-E Working Draft Network Code on Emergency and Restoration DRAFT FOR THE FOURTH PUBLIC WORKSHOP Notice 22 January 2015 This document reflects the status of the work of Transmission System Operator
SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems
SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems Contents Introduction 3 How solar PV power systems work 4 Solar modules 5 Is solar power
European Distribution System Operators for Smart Grids. Position paper on Electric Vehicles Charging Infrastructure
European Distribution System Operators for Smart Grids Position paper on Electric Vehicles Charging Infrastructure European Distribution System Operators for Smart Grids Position paper on ELECTRIC VEHICLES
What are the basic electrical safety issues and remedies in solar photovoltaic installations?
What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic
Integrating End-User and Grid Focused Batteries and Long-Term Power-to-Gas Storage for Reaching a 100 % Renewable Energy Supply
Integrating End-User and Grid Focused Batteries and Long-Term Power-to-Gas Storage for Reaching a 100 % Renewable Energy Supply M. Hlusiak, Ch. Breyer 7 th International Renewable Energy Storage Conference
Grid Connection of Solar PV Technical and Economical Assessment of Net-Metering in Kenya
Grid Connection of Solar PV Technical and Economical Assessment of Net-Metering in Kenya Authors Georg Hille et al. Michael Franz (ed.) December 2011 Editor Deutsche Gesellschaft für Internationale Zusammenarbeit
NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM
NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM BY AUTHORISED PERSONS Effective from 1 October 2011 to 30 September
PMCS. Integrated Energy Management Solution. Unlock the Full Potential of Power Networks Through Integration. Complete Solution. Informed Decisions
PMCS Integrated Energy Management Solution Unlock the Full Potential of Power Networks Through Integration Power Management Control System (PMCS) is a highly customizable, fully integrated end-to-end Energy
