Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project
|
|
|
- Kelly Walters
- 9 years ago
- Views:
Transcription
1 Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Project Example Overview Microsoft Project, in addition to scheduling calculations, can also track resources and consider cases of resource limitations in scheduling project activities. During our last lecture (Lecture 14) on resource allocation, we considered an example project that had a resource limitation. Without resource limitations we found that with a forward and backward pass on the project, it would take 12 days to complete. We can see that a resource limit of 2/day has been imposed in this problem and we found that through a hand calculation that this limitation added an additional 2 days to the project timeline (14 days total). This occurs because after activity A is completed we see that 3 resources per day are required. Before we get into resource allocation we set up MS Project from a blank project by adding the following data: Task Name (Index) Duration Predecessors (Index) A (1) 1 - B (2) 2 A (1) C (3) 2 A (1) D (4) 3 A (1) E (5) 4 B (2) F (6) 5 C (3) G (7) 4 D (4) H (8) 1 E,C (5,3) I (9) 3 G (7) J (10) 1 H,F,I (8,6,9) 1
2 Starting Project So that we can easily count project days, we ll start our project from the 1 st of a 30 day month so that the dates reflect the days. We ll also make Saturdays and Sundays work days for this purpose. Additionally, we ll change the date bars to weeks and days from the start of the project. These steps were outlined in the previous tutorial. 1. Set project start date to April 1 st 2. Define Saturdays and Sundays as work days (change standard calendar) 3. Change calendar bars to time from start of project 4. Add info in table. After we complete these steps our schedule should appear as: Here, we can see that the project is to be completed in 12 days. However, we can also see from the Gantt chart view that there are a number of days (2-8) when 3 activities will be occurring at the same time. Hence, we will require 3 resources on these days. Next, we ll customize the network view but this can be skipped over if necessary. I had challenged myself to try this customization and wanted to document it. 2
3 Project Customization We can also view our network view (View > Network Diagram) to confirm the network is the same as the example. Like many aspects of MS Project, it is very customizable. In fact, we can customize the network view to reflect the information we have in our problem. To do this we ll create a new template for the network view by following: 1. Change to network view (View > Network Diagram) 2. Select Format > Box Styles and the following dialogue box will appear 3. You ll note the Standard data template is in use. Select the button to reveal another dialogue: 3
4 4. Drilling deeper, we now create a new template by selecting the. We ll call this template Event Times and put EST, EFT, LST, LFT in the corners of a 2x3 matrix we set out from the button. From the Choose Cell area we can pull down the field variables we can add to the boxes to assemble the box we need 5. Finally we apply this new template to the Critical and Noncritical box styles from the first dialogue box we encountered in step 2. This produces a network view that compares to our original problem view as: 4
5 Defining Project Resources A resource is traditionally defined as any of the people, equipment, and materials used to complete tasks that make a project. Material resources are differentiated from people and equipment resources, as they are not time dependent. Before we use resources in our activities we must create a resource list. One can follow the wizard from the Tasks menu but most of these steps are not necessary for our simple projects. To create a local resource list for our project change the view to View > Resource Sheet and add a new resource called R1. You ll get an entry as follows: Here, we need to make sure that the Type column is set to Work. This specifies that the people or equipment resource will be utilized while it is assigned and will be prorated across the activity time. We could specify an hourly rate for our resources if we were tracking cost or a lump sum cost each use of the resource. You ll also note the resource can also use its own calendar that might be independent of the standard calendar. Finally, we can specify the maximum number of units for our resource. In this case we have been told in the problem that we have a maximum of 2- resource units per day so we change Max. Units to 200%. There are lots of other ways to add resources to projects and modify them but this seems to be the base method. We can add any number of resources to this list if we are tracking a multi-resource project. These represent pools of resources we can draw from and therefore, have not been allocated for use at this point. 5
6 Allocating Resources Once we have a pool of resources to draw from, we can assign these to various activities. This is done for each activity and can be done in the default Gantt chart view by selecting the resource required from the pull down menu in the Resource Name column. We can also double click on any activity and select the Resource tab from the main Task Information dialogue as follows: If we required more than 100% of a resource for a particular item, we would specify this in the units column of the Task Information or type the information in brackets in the Gantt chart view as R1[200%]. Commas separate multiple resource assignments. For our project each activity uses 1 resource while it is scheduled so each row of the Resource Name column will have an R1 entry. 6
7 Tracking Resources Now that we have assigned resources we can track them to see how they are being allocated on our project. The best way to view resource utilization is through a split window view. Select Window > Split and maintain the Gantt View in the top window. Select the bottom panel and change this view to resource utilization by selecting View > Resource Graph. You should have a view as follows: Here we see that for the resource R1 that we are using 1-unit on days 1, 9-12 while using 3 units for days 2-8. This corresponds to our earlier suspicion of resource over allocation and this over allocation is show by the bars that show the maximum resource availability of 2 units. The red bars indicate days in which the resource is over allocated. Note: if two resources were tracked in the Resource Graph then the scroll bar on the bottom left-side of the plot would be used to scroll through the various resources. Resource Allocation We note here that if we are limited with our resources to 2 units per day then we cannot do the project as we had initially planned. We are forced to delay activities until resources are free to undertake the activity. If we delay critical activities then the end date of the project will be extended. MS Project has a tool for allocating resources to minimize the impact on the project schedule. Before using the resource leveling tool change to top panel to Leveling Gantt view by selecting the top view and selecting View > More Views Select Leveling Gantt. 7
8 You ll notice here that a new column is added in this view called Leveling Delay. There is not much hand leveling we could do with the exception of activity H. If we added a 1 day (elapsed day, eday) to activity H, we would reschedule activity H to day 9 from 8. The result would be a gradual resource reduction as follows: 8
9 If we disregard the 12 day end date of the project, we can reassign the tasks based on resources available. We had undertaken this by hand calculation in class (Lecture 14) using the ELS heuristic rule for deciding upon activities to schedule. The leveling tool in MS Project is initiated by selecting Tools > Level Resources from the top menus. This brings up the following dialogue box: Leveling can be set to occur manually or automatically (I select manual to see the impact of changes I ve made). The project can be leveled over the whole or only parts of the project. The main part of the dialogue is the Resolving overallocations section. In leveling order the heuristic rules for delaying activities are decided. For ID only, activities are assigned based on their ID (1 -> 10 in our example). In standard, the assignment is based on least total float (LTF) and later priority. In Priority, Standard mode, you can assign a priority from 1 -> 1000 in the Task Information dialogue box and this will be first used to select activities. Other options for level ordering constrain the solution to the project end date (1 st option), allows leveling to adjust when a resource works on a task independent of the other resources working on the same task (2 end option), and allows tasks to split (3 ed option). Options 2 and 3 are checked by default. The workflow here is to first clear leveling, change any of the required settings and then reschedule the work with the button. The first result from our example yields a similar result to our hand calculation. However, the result is 15 days rather than 14 days as follows: 9
10 Here you should note the following: The green bars show the result of the previous leveling excise The blue bars show the current leveling result activities The brown lines to the left of the activity are the leveling delay imposed (C,E,F) The blue line to the right of the activities are the free float available (H,I) The indicates a split activity (I) The result of leveling shows that project was extended the project by three days. However, resources on days 13 and 14 could be combined to reduce the schedule by one day. However, this would involve moving activity F back a day and rescheduling other tasks. This can be done by increasing the priority of F in the Task Information dialogue to 520. This is slightly higher then the 500 default level set for other activities. 10
11 If we now re-level the activities, we note that the Leveling Delay for activity F has been reduced from 4 to 3 days and the remaining activities scheduled accordingly. With this change the duration of the project is reduced now to 14 days. This is the same result as was obtained in our hand calculation. We see from the resource graph that the work has been scheduled with maximum of 2 resource units. Given that activities A and J must occur alone, this is optimal result for the resource restriction. 11
12 Reducing Length of Project If we examine the new critical path, we note substantial changes due to resource leveling. This is most often the case. Of course to reduce the duration B,C,E,F or H would require the addition of a new resource. Otherwise the only opportunity to reduce the project duration would be to reduce the durations of the beginning & end activities (A&J) by possibly utilizing 2 resource units on those days to reduce them to 0.5 days each. This would reduce the overall project to 13 days (only 1 greater than the original) and have a constant resource utilization of 2 units. Critical Path with Resource Leveling Critical Path without Leveling Note: Take care when changing the duration of or resources allocated to an activity. Activities become effort driven when resources are utilized. The default setting used is constant units. This means that a unit of resource effort has a constant capacity. If you decrease activity duration more resources are assign or the total effort (work) in the activity is reduced. If you assign more resources, this reduced activity duration or increases work effort. 12
Mastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These
Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.
Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Microsoft Project 2013 Guide to Task and Resource Planning
Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft
Lesson 6 - Managing Resources in a Project Plan
Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional
ELECTRO-MECHANICAL PROJECT MANAGEMENT
CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: [email protected] Page: 1 Electro-mechanical Project Management using MS Project Introduction: When
Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated.
Microsoft Project Pro Steps to completing Project Pro Assignments PART B. (These instructions include all you need to know about adjusting your project in Microsoft Project Pro 2013 and may include instructions
Planning and Managing Projects with Microsoft Project Professional 2013
Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important
Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems
Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems Computer Lab # 1 Time Management (with Microsoft Project 2007) Lab Manual (with master s
Session 6. Microsoft Project. Emanuele Della Valle. http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza
Session 6 Microsoft Project Emanuele Della Valle http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza Credits 2 This slides are largely based on CEFRIEL s slides for PMI Certification and Prof.
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help
PERCEPTION PERT-PAC Using Microsoft Project 2000
PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000
OVERVIEW. Microsoft Project terms and definitions
PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training
NE-50413B Mastering Microsoft Project 2010
NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need
Project Management: Intermediate Microsoft Project 2010
Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project
Microsoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
MSP How to guide session 2 (Resources & Cost)
MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or
Creating a New Project
Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,
Lab 1 Introduction to Microsoft Project
Lab 1 Introduction to Microsoft Project Statement Purpose This lab provides students with the knowledge and skills to use Microsoft Project. This course takes students step-by-step through the features
Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)
Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the
Microsoft Project Activity
Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge
Beginning Microsoft Project
Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND
Planning and Scheduling Your Project Using Microsoft Project 2003
Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering [email protected] Meeting Protocol Agenda Project File Project Calendar Creating
Excel Tutorial. Bio 150B Excel Tutorial 1
Bio 15B Excel Tutorial 1 Excel Tutorial As part of your laboratory write-ups and reports during this semester you will be required to collect and present data in an appropriate format. To organize and
Module A2 Item Activities, Gantt Chart and Utilization Sheet
Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Module 1. Project item activities, Gantt Chart & Utilization Sheet Contents...
technical tips and tricks
technical tips and tricks Document author: Produced by: Displaying a Critical Path Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
Project Management within ManagePro
Project Management within ManagePro This document describes how to do the following common project management functions with ManagePro: set-up projects, define scope/requirements, assign resources, estimate
Microsoft Project 2007 Level 2: Working with Resources and Managing a Project
Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was
Resource Allocation in MS Project
Resource Allocation in MS Project Calendars The project calendar determines the working days and hours available to your project, In addition each resource can have their unique calendars to mark time
How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)
Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open
Microsoft Project 2013
CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a
Instructions for applying data validation(s) to data fields in Microsoft Excel
1 of 10 Instructions for applying data validation(s) to data fields in Microsoft Excel According to Microsoft Excel, a data validation is used to control the type of data or the values that users enter
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects
Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102
Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102 Interneer, Inc. Updated on 2/22/2012 Created by Erika Keresztyen Fahey 2 Workflow - A102 - Basic HelpDesk Ticketing System
MS Project 2007 Quick Guide
MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration
Monthly Payroll to Finance Reconciliation Report: Access and Instructions
Monthly Payroll to Finance Reconciliation Report: Access and Instructions VCU Reporting Center... 2 Log in... 2 Open Folder... 3 Other Useful Information: Copying Sheets... 5 Creating Subtotals... 5 Outlining
IST 195 Lab 12 Introduction to Microsoft Project
IST 195 Lab 12 Introduction to Microsoft Project Microsoft Project is a project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans,
Scheduling Document Creation
Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary
INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS
INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary
The tool also provides an overview of date criteria set against all items within your module.
Date Management Tool What does it do? This tool allows tutors to view in one screen when items are available and change dates attached to more than one content item within a module at the same time. For
Creating a Resource Library
IT Session 3: Resourcing Creating a Resource Library It is possible within the software to include resources as you go on, but it is better to set up a separate resource library and link this to your developing
Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.
2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone
1. INTRODUCTION...2 2. PRODUCT...2. 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2. 3. workbench features...2
Table of Contents 1. INTRODUCTION...2 2. PRODUCT...2 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2 3. workbench features...2 3.1. Project Planning... 2 3.2. Project Tracking... 3 4.
Project Management Quick Reference Guide for MS Project 2010
Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides
MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado
CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado
FAST Travel System. Guide: Creating Expense Reports
FAST Travel System Guide: Creating Expense Reports Purpose: To provide instructions on how to create an Expense Report (ER) in FAST 9.2 Travel module. Definition: Expense Report submission entered into
DESKTOP CLIENT CONFIGURATION GUIDE BUSINESS EMAIL
DESKTOP CLIENT CONFIGURATION GUIDE BUSINESS EMAIL Version 2.0 Updated: March 2011 Contents 1. Mac Email Clients... 3 1.1 Configuring Microsoft Outlook 2011... 3 1.2 Configuring Entourage 2008... 4 1.3.
Scheduling/ Calendar Software Training Manual
In order to enter the Scheduling Software, click on Appointment button on the home page in Clinician Gateway. Once you click on the Appointment button an additional browser page called the Physician s
Earned Value Analysis Exercise
Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)
INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT
LECTURE -01 TO PROJECT MANAGEMENT AND MS PROJECT 2 Objective LEARNING OBJECTIVES To learn Project Management Software and their Application to Civil Engineering Books Microsoft Office Project Step by Step
Project 2010 Introduction
Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery
Project Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
MS Excel. Handout: Level 2. elearning Department. Copyright 2016 CMS e-learning Department. All Rights Reserved. Page 1 of 11
MS Excel Handout: Level 2 elearning Department 2016 Page 1 of 11 Contents Excel Environment:... 3 To create a new blank workbook:...3 To insert text:...4 Cell addresses:...4 To save the workbook:... 5
ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5
Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List
Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa
Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety
Microsoft Expression Web
Microsoft Expression Web Microsoft Expression Web is the new program from Microsoft to replace Frontpage as a website editing program. While the layout has changed, it still functions much the same as
USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS
P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: [email protected] Australia Software
Mastering Microsoft Project 2013
Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals
Using Microsoft Project 2000
Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL
Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet
Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Assistance PSA: Advanced Functionalities Welcome to the Advanced Functionalities
Microsoft Office Access 2007 Basics
Access(ing) A Database Project PRESENTED BY THE TECHNOLOGY TRAINERS OF THE MONROE COUNTY LIBRARY SYSTEM EMAIL: [email protected] MONROE COUNTY LIBRARY SYSTEM 734-241-5770 1 840 SOUTH ROESSLER
Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days
3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: [email protected] Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:
Qualtrics Survey Software. Create an Account
Qualtrics Survey Software Qualtrics is online survey software with the ability to create and distribute surveys, quizzes, and polls. Katz and CBA faculty, staff, and students may create accounts. There
Microsoft Project 70-178 Exam Study Guide
Microsoft Project 70-178 Exam Study Guide Prepared by The Versatile Company for MPUG. www.versatilecompany.com The Versatile Company, 2012. About this Study Guide This guide was developed based upon the
DALHOUSIE NOTES ON PAYROLL EXPENSE DETAIL IN FINANCE SELF SERVICE. QUICK REFERENCE As of September 1, 2015
DALHOUSIE NOTES ON PAYROLL EXPENSE DETAIL IN FINANCE SELF SERVICE QUICK REFERENCE As of September 1, 2015 Quick reference document outlining the basic steps to access the payroll expense detail results
How To Use An Invoice On A Pc Or Macbook
Volume Revolutionary. Online. Cool. Accounting H E A L T H I N N O V A T I O N T E C H O N O L O G I E S, I N C EyeCodeRight v4.0 Tutorial EyeCodeRight 2717 Emerson Ave South Minneapolis, MN 877-370-6906
IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1
IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break
ACCESS 2007. Importing and Exporting Data Files. Information Technology. MS Access 2007 Users Guide. IT Training & Development (818) 677-1700
Information Technology MS Access 2007 Users Guide ACCESS 2007 Importing and Exporting Data Files IT Training & Development (818) 677-1700 [email protected] TABLE OF CONTENTS Introduction... 1 Import Excel
MS Excel Template Building and Mapping for Neat 5
MS Excel Template Building and Mapping for Neat 5 Neat 5 provides the opportunity to export data directly from the Neat 5 program to an Excel template, entering in column information using receipts saved
Tracking Project Progress
L E S S O N 2 Tracking Project Progress Suggested lesson time 45-55 minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the
How To Create A Powerpoint Intelligence Report In A Pivot Table In A Powerpoints.Com
Sage 500 ERP Intelligence Reporting Getting Started Guide 27.11.2012 Table of Contents 1.0 Getting started 3 2.0 Managing your reports 10 3.0 Defining report properties 18 4.0 Creating a simple PivotTable
Mail Merge Creating Mailing Labels 3/23/2011
Creating Mailing Labels in Microsoft Word Address data in a Microsoft Excel file can be turned into mailing labels in Microsoft Word through a mail merge process. First, obtain or create an Excel spreadsheet
Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start
Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and
Working with SQL Server Integration Services
SQL Server Integration Services (SSIS) is a set of tools that let you transfer data to and from SQL Server 2005. In this lab, you ll work with the SQL Server Business Intelligence Development Studio to
Planning and Managing Projects with Microsoft Project Professional 2013
Slides Steps to Enter Duration: 1. In the Duration column of a task, enter a value, and press Enter on your keyboard Important Points: The default time unit is days, so when you enter 5, this becomes 5
Tutorials. If you have any questions, comments, or suggestions about these lessons, don't hesitate to contact us at [email protected].
Tutorials The lesson schedules for these tutorials were installed when you installed Milestones Professional 2010. They can be accessed under File Open a File Lesson Chart. If you have any questions, comments,
Excel 2003: Ringtones Task
Excel 2003: Ringtones Task 1. Open up a blank spreadsheet 2. Save the spreadsheet to your area and call it Ringtones.xls 3. Add the data as shown here, making sure you keep to the cells as shown Make sure
Sage Accpac ERP 5.6A. CRM Analytics for SageCRM I User Guide
Sage Accpac ERP 5.6A CRM Analytics for SageCRM I User Guide 2009 Sage Software, Inc. All rights reserved. Sage, the Sage logos, and all SageCRM product and service names mentioned herein are registered
In this example, Mrs. Smith is looking to create graphs that represent the ethnic diversity of the 24 students in her 4 th grade class.
Creating a Pie Graph Step-by-step directions In this example, Mrs. Smith is looking to create graphs that represent the ethnic diversity of the 24 students in her 4 th grade class. 1. Enter Data A. Open
Gantt Chart/Diagram Excel Template User Guide
Gantt Chart/Diagram Excel Template User Guide Excel-based simple Gantt Chart Template This Excel-based template allows a Gantt chart to be easily and quickly developed. As the project progresses, the chart
Revealing the Secrets of Microsoft Project
2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project
Microsoft Access 2007
How to Use: Microsoft Access 2007 Microsoft Office Access is a powerful tool used to create and format databases. Databases allow information to be organized in rows and tables, where queries can be formed
Project planning with MindGenius
Project planning with MindGenius This workshop looks at using MindGenius for planning and monitoring smaller projects. MindGenius is available free of charge on all University of Brighton staff and student
WebSphere Business Monitor V7.0 Business space dashboards
Copyright IBM Corporation 2010 All rights reserved IBM WEBSPHERE BUSINESS MONITOR 7.0 LAB EXERCISE WebSphere Business Monitor V7.0 What this exercise is about... 2 Lab requirements... 2 What you should
Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands.
Quick Start Guide Microsoft Project 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Quick Access Toolbar Customize this area so your favorite
Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18
Basic Pivot Tables Pivot tables summarize data in a quick and easy way. In your job, you could use pivot tables to summarize actual expenses by fund type by object or total amounts. Make sure you do not
Use Blackboard 9.1 Auto-Submit and Provide a more time accommodation
Use Blackboard 9.1 Auto-Submit and Provide a more time accommodation Blackboard 9.1 introduced a highly requested feature in the tests and quizzes tool the ability to have a time limit enforced on an exam.
Gantt Chart for Excel
Project Management Templates for Excel http://spreadsheetml.com/projectmanagement/ganttchart.shtml Copyright (c) 2009-2010, ConnectCode All Rights Reserved. ConnectCode accepts no responsibility for any
Computer Training Centre University College Cork
Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...
MS Project 2000 Tutorial: Introduction
MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."
QUICK START GUIDE RESOURCE MANAGERS. Last Updated: 04/27/2012
QUICK START GUIDE RESOURCE MANAGERS Last Updated: 04/27/2012 Table of Contents Introduction... 3 Getting started... 4 Logging into Eclipse... 4 Setting your user preferences... 5 Online help and the Eclipse
THE TOP TEN TIPS FOR USING QUALTRICS AT BYU
THE TOP TEN TIPS FOR USING QUALTRICS AT BYU TIP #1: CREATING A SURVEY FROM A COPY AND COLLABORATING ON SURVEYS TIP #2: CREATING AND USING PANELS TIP #3: LIBRARIES AND HOW TO USE THEM TIP #4: BASIC SKIP
ORACLE BUSINESS INTELLIGENCE WORKSHOP
ORACLE BUSINESS INTELLIGENCE WORKSHOP Integration of Oracle BI Publisher with Oracle Business Intelligence Enterprise Edition Purpose This tutorial mainly covers how Oracle BI Publisher is integrated with
I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE
I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE Workshop Information Information Technology Services is happy to provide you with
Basic CPM Calculations
Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.
Microsoft Excel Basics
COMMUNITY TECHNICAL SUPPORT Microsoft Excel Basics Introduction to Excel Click on the program icon in Launcher or the Microsoft Office Shortcut Bar. A worksheet is a grid, made up of columns, which are