New Visual Tools for Load Allocation Analyses: Using STELLA Software for Water Quality Accounting
|
|
|
- Monica O’Brien’
- 9 years ago
- Views:
Transcription
1 New Visual Tools for Load Analyses: Using STELLA Software for Water Quality Accounting Kimberly O. Siemens, Kirk S. Westphal, P.E., Daniel G. Bounds, P.E., D.WRE Kimberly O. Siemens, CDM Plaza East Office Center 330 East Kilbourn Ave, Suite 1219 Milwaukee, WI ABSTRACT STELLA is a visual platform for customized modeling of flow networks and tracking multiple constituents through a water system. STELLA has recently been used as a conservative water quality accounting tool to support total phosphorus (TP) and total suspended solids (TSS) TMDL allocation analyses for a large watershed with multiple reaches and discharge inputs. STELLA was chosen as the tool for this purpose due to its visual presentation of reaches, inputs, and variables, as well as its flexibility. STELLA is essentially an open worksheet in which a user builds a network of flow elements, storage elements, and variables to represent any water system. For this TMDL analysis, the mainstem and tributaries were set up in a model within STELLA, and nonpoint source flows and loads from a previously developed model were incorporated, along with point source flows and loads compiled from existing data. MS4 flows and loads were also entered. The baseline pollutant loads were reduced through a series of reduction factors until concentrations met proposed water quality objectives. As needed, STELLA has also been used to simulate first-order decay or attenuation of total phosphorus in impounded flow networks. STELLA provides a visual feature not available with other modeling platforms. The network constructed for the load allocation analyses has a similar on-screen visual structure to the actual river network and interdependencies between system elements are clearly represented. The visual aspect of STELLA makes for a straightforward explanation of how the model works to public stakeholders. It is easy to visualize how the entire water network is constructed conceptually, how reaches and discharges connect to one another, and how pollutants flow through the system and are mathematically reduced. STELLA was chosen for these analyses because the platform can be used to quickly screen through reduction percentages and identify effective allocations reach by reach by examining resulting in-stream concentrations. The model was set up to include both global and local reduction factors. Global reduction factors are applied universally throughout the entire watershed, while local reduction factors can be applied to each individual reach. For each model run, these reduction factors are easily edited on 466
2 a control interface screen and results can be exported to a spreadsheet for further analysis and load allocation calculations. KEYWORDS TMDL, STELLA, allocation, model, presentation INTRODUCTION STELLA is a visual platform that can be used for customized modeling of flow networks and tracking multiple water quality constituents through a water system. STELLA has recently been used as a conservative water quality accounting tool to support total phosphorus (TP) and total suspended solids (TSS) TMDL allocation analyses for a large watershed with numerous reaches and discharge inputs. In addition to requiring a tool that could aggregate information from multiple sources (water quality models, permit databases, etc.), the analyses required a method to rapidly screen alternative load reductions and estimate appropriate load allocations to meet in-stream TP and TSS targets. STELLA was chosen as the tool for this purpose due to its ability to produce a visual presentation of reaches, inputs, and variables, as well as its flexibility to quickly evaluate the effects of a broad range of management alternatives. STELLA is essentially an open worksheet in which a user builds a network of flow elements, storage elements, and variables to represent a water system. For a TMDL allocation analysis, the mainstem and tributaries can be set up in a model within STELLA. Point and non-point source flows and loads can be entered from raw data or from a previously developed model. MS4 flows and loads can also be entered. Using STELLA, the baseline pollutant loads can be reduced through a series of reduction factors for each load category in each reach, until concentrations meet proposed water quality objectives. STELLA can also been used to simulate first-order decay or attenuation of water quality constituents in impounded flow networks. STELLA provides a visual feature not available with other modeling platforms. A model network constructed a load allocation analyses can have a similar on-screen visual structure to the actual river network, and interdependencies between system elements are clearly represented. The visual presentation aspect of STELLA provides for a straightforward explanation to public stakeholders, including how upstream loads and management decisions propagate downstream. It is easy to visualize how the entire water network is constructed conceptually, how reaches and discharges connect to one another, and how pollutants flow through the system and are mathematically analyzed. STELLA was chosen for these analyses because the platform can be used to quickly screen through reduction percentages and identify effective allocations reach by reach by examining resulting in-stream concentrations, both near-field and far-field. 467
3 The model can be set up to include both global and local reduction factors. Global reduction factors are applied universally throughout the entire watershed, while local reduction factors can be applied to each individual reach. For each model run, these reduction factors are easily edited on a control interface screen and results can be exported to a spreadsheet for further analysis and load allocation calculations. The allocation model is not used to generate new information on pollutant loads or streamflows. Rather, it can be developed as a way to synthesize the routing of existing information through a system and apply simulated load reductions on a reach-by-reach basis. The model can be used to identify load allocations for each reach of a water system. It can also be used to determine load allocations at a downstream endpoint or outlet. MODEL STRUCTURE AND USE A river and its tributaries can be divided into reaches based on the segmentation of a 303(d) list, and additional reaches can be added for river segments not listed on the 303(d) list to represent the entire system. The STELLA structure allows a basic flow network to be developed schematically, and this central network is used to route water through the system of tributaries and mainstem reaches of a river. Parallel networks are then constructed to route pollutants through the system from their point of introduction all the way downstream, or until they are fully attenuated. STELLA is an ideal tool for simulating first order decay dynamics, and can also simulate more complex dynamics if programmed by the user (as one might do with similar programming syntax in a spreadsheet). Even in a conservative allocation analysis, there are many combinations of load allocations that will yield results achieving a water quality target, since most reaches are affected by numerous loads from various sources. Typical allocation methods can be used with STELLA to provide for a sound approach. Figure 1 illustrates the overall model construct for an example water system, containing zoomed in figures to illustrate how pollutants enter each reach and are mathematically reduced, how one reach connects to another, and how the entire water network is constructed conceptually. Total Phosphorus (TP) and Total Suspended Solids (TSS) are shown as example constituents for illustrative purposes. 468
4 Red PS Tot TP PS Red Load 2 NPS Red Load 2 Tot TP Tot Remain Tot Remain TP TP 2 Hydrograph 2 TP 2 Flow 2 Flows 2 Phosphorus Into 1 Reach TSS Red PS PS Red Load 2 NPS Red Load 2 Local TSS TP TSS Flows 2 Hydrograph 2 TSS Red PS TSS Input Flow 2 TP 2 TSS 2 TSS TP 2 TSS 2 TSS TSS TSS TSS TSS TSS TSS TSS TP TSS 2 Representative Reaches Lbs Remov ed TSS TP Red PS TP N N TP TP TP PS Red Load 3 NPS Red Load 3 N TP N N TP N TP N Local TSS TP MS4 3 TSS MS4 3 MS4 Red 3 MS4 Red 3 Flows 3 Hydrograph 3 TP MS4 3 MS4 3 TSS Red PS TSS Input Flow 3 TP 3 TSS 3 TP N TSS N TP 3 TSS 3 N TSS TSS TSS N TSS N N TSS N TSS N TSS TSS N TP N TSS N Figure 1: Example Model Structure Note: Red arrows indicate transfer of information, blue arrows symbolize actual flows of water, or water quality constituents. 469
5 CONCLUSION STELLA is a tool that can be used for a variety of TMDL development and water quality analysis where a visual platform adds value for analysis and presentation purposes. Key benefits of using STELLA are the ability to aggregate information from a variety of sources into a dynamic analytical platform, the functionality to quickly screen through load reduction percentages to identify load allocations, and the ability to help explain how upstream decisions affect the entire flow network. 470
Report for 2003PA14B: Spruce Creek Watershed Keystone Project
Report for 2003PA14B: Spruce Creek Watershed Keystone Project There are no reported publications resulting from this project. Report Follows Abstract: This proposal seeks support for a graduate assistant
Final Report of the Town Owned Lands Improvement Project for the Town of Brentwood, NH
Final Report of the Town Owned Lands Improvement Project for the Town of Brentwood, NH Project Background In November of 2013 the Green Infrastructure for Sustainable Coastal Communities (GISCC) project
Watershed-Wide Modeling for TMDL/MS4 Permit Compliance. Greg Wilson, Barr Engineering
Watershed-Wide Modeling for TMDL/MS4 Permit Compliance Greg Wilson, Barr Engineering Acknowledge City of Golden Valley Eric Eckman Heather Hegi Laura Jester and BCWMC Technical Advisory Committee members
Peter J. Strazdas Associate Vice President, Facilities Management Western Michigan University [email protected]
Peter J. Strazdas Associate Vice President, Facilities Management Western Michigan University [email protected] Mark S. Kieser Principal, Senior Scientist Kieser & Associates, LLC [email protected]
A HYDROLOGIC NETWORK SUPPORTING SPATIALLY REFERENCED REGRESSION MODELING IN THE CHESAPEAKE BAY WATERSHED
A HYDROLOGIC NETWORK SUPPORTING SPATIALLY REFERENCED REGRESSION MODELING IN THE CHESAPEAKE BAY WATERSHED JOHN W. BRAKEBILL 1* AND STEPHEN D. PRESTON 2 1 U.S. Geological Survey, Baltimore, MD, USA; 2 U.S.
Report prepared by: Kelly Hagan and Mark Anderson Grand River Conservation Authority 400 Clyde Road Cambridge ON N1R 5W6
2013 Watershed Overview of Wastewater Treatment Plant Performance Report prepared by: Kelly Hagan and Mark Anderson Grand River Conservation Authority 400 Clyde Road Cambridge ON N1R 5W6 Table of Contents
Chesapeake Bay and Potomac Tidal Monitoring Programs Past, Present and Future
Chesapeake Bay and Potomac Tidal Monitoring Programs Past, Present and Future Bruce Michael Resource Assessment Service Maryland Department of Natural Resources The Future of Water Quality Monitoring in
WATER QUALITY MODELING TO SUPPORT THE ROUGE RIVER RESTORATION
WATER QUALITY MODELING TO SUPPORT THE ROUGE RIVER RESTORATION Edward H. Kluitenberg, P.E., Applied Science, Inc. Gary W. Mercer, P.E., Camp, Dresser and McKee Vyto Kaunelis, Wayne County Department of
Hydrologic Modeling using HEC-HMS
Hydrologic Modeling using HEC-HMS Prepared by Venkatesh Merwade School of Civil Engineering, Purdue University [email protected] April 2012 Introduction The intent of this exercise is to introduce you
Handbook for Developing Watershed Plans to Restore and Protect Our Waters
This document is one chapter from the EPA Handbook for Developing Watershed Plans to Restore and Protect Our Waters, published in March 2008. The reference number is EPA 841-B-08-002. You can find the
REQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS LOWER GREAT MIAMI RIVER NUTRIENT MANAGEMENT PROJECT INTRODUCTION On behalf of a partnership of Water Resource Recovery Facilities (WRRFs) WRRFs and other stakeholders with permitted
WA Department of Ecology Water Quality Issues in the Dungeness Watersheds. Public Information
WA Department of Ecology Water Quality Issues in the Dungeness Watersheds Public Information Water Cleanup Plan for Bacteria in the Lower Dungeness Watershed Total Maximum Daily Load (TMDL) Submittal Report,
Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M.
Fort Dodge Stormwater Master Planning Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Project Location Project Background Flooding History Localized flooding and storm sewer
Permeable Pavement Treatment Capacity
Permeable Pavement Treatment Capacity April 20 2011 This investigation will analyze the pollutant removal capacity of various types of permeable paving techniques. Daniel Sullivan Joseph Fleury Contents
Towards Integrated Water/Watershed Management: Data Strategies. Clay Clifton EcoLayers, Inc.
Towards Integrated Water/Watershed Management: Data Strategies Clay Clifton EcoLayers, Inc. Water environment an Integrated System; one scale is the watershed Historically, management of water resources
User s Manual for the BMPTRAINS Model
User s Manual for the BMPTRAINS Model Prepared By: Marty Wanielista, Mike Hardin, Przemyslaw Kuzlo, and Ikiensinma Gogo-Abite STORMWATER TREATMENT ANALYSIS: STEP 1: Specify pre- and post-development watershed
Flood Mitigation Strategy for the Milwaukee 30 th Street Corridor Redevelopment Program
Flood Mitigation Strategy for the Milwaukee 30 th Street Corridor Redevelopment Program Eric Loucks, P.E., D.WRE Kumar Gali, P.E. June 4, 2015 Outline MMSD Service Area Problem and Challenges Solution
WV Potomac Nutrient Credit Bank and Trade Program. NRCS Conservation Innovation Grant. Final Report
WV Potomac Nutrient Credit Bank and Trade Program NRCS Conservation Innovation Grant Final Report West Virginia Water Research Institute West Virginia University PO Box 6064 Morgantown, WV 26506 September
Locating Point and Non-point Sources of Escherichia coli in the Mechumps Creek Watershed, Hanover County, Virginia
Locating Point and Non-point Sources of Escherichia coli in the Mechumps Creek Watershed, Hanover County, Virginia Report Submitted to the Virginia Department of Environmental Quality Michael S. Fenster
Ginger Paige and Nancy Mesner University of Wyoming Utah State University
Effective Water Quality BMP Monitoring Tools Ginger Paige and Nancy Mesner University of Wyoming Utah State University Overview BMP Monitoring Guidance Document for Stream Systems Lessons learned CEAP
Image source: www.rivers.gov. Visual Data Analytics, LLC
AWRA Spring Specialty AWRA Conference Spring Specialty on GIS Conference and Water on Resources GIS and Water VIII Resources May 13, 2014 Using a Temporal Information System for Visualization and Analysis
HCP Team Meeting. November 18, 2015. icfi.com
HCP Team Meeting November 18, 2015 icfi.com 1 Welcome and Introductions Where are we in the HCP process Hydrology modeling update Native fish survey Fish translocation Finalize covered activities Next
North Branch Chicago River Watershed-Based Plan
North Branch Chicago River Watershed-Based Plan EXECUTIVE SUMMARY In Lake County, the Lake County Stormwater Management Commission (SMC) is responsible for managing Lake County s water resources. The North
City of Lakeland s Wetlands Treatment System An Overview
An Overview In response to more stringent requirements for wastewater discharges in the early 1980 s, the City explored options for the advanced treatment required, with the Wetland Treatment System proving
TITLE: [Name of municipality] Storm Water Abatement Feasibility Study
TITLE: [Name of municipality] Storm Water Abatement Feasibility Study PROBLEM/NEED: [Name of watershed] is an area of [##] acres, surrounding [name of waterbody]. [Name of waterbody] has been assessed
Stormwater Best Management Practices (BMP) Performance Analysis
Stormwater Best Management Practices (BMP) Performance Analysis Revised Document: March 2010 (Original Document: December 2008) Prepared for: United States Environmental Protection Agency Region 1 5 Post
Hydrologic Engineering Techniques for Regional Water Resources Planning
US Army Corps of Engineers Hydrologic Engineering Center Hydrologic Engineering Techniques for Regional Water Resources Planning October 1969 Approved for Public Release. Distribution Unlimited. TP-17
Greater Los Angeles County Region
Attachment 6 Greater Los Angeles County Region IRWM Implementation Grant Proposal Monitoring, Assessment, and Attachment 6 consists of the following items: Monitoring, Assessment, and. The purpose of this
Standards: Human activity has consequences on living organisms and ecosystems. (94412, 94211 )
Minnehaha Creek Restoration Project A Place- Based Environmental Water Study Course: 9 th grade Biology Adapted from Kent Piccott, Minneapolis Public Schools Background: This study was designed with the
. Address the following issues in your solution:
CM 3110 COMSOL INSTRUCTIONS Faith Morrison and Maria Tafur Department of Chemical Engineering Michigan Technological University, Houghton, MI USA 22 November 2012 Zhichao Wang edits 21 November 2013 revised
Accounting for Uncertainty in Offset and Trading Programs
Accounting for Uncertainty in Offset and Trading Programs EPA Technical Memorandum February 12, 2014 Prepared by EPA Region III 1 of 12 CONTENTS Abbreviations and acronyms... 3 Scope... 4 Executive summary...
The International Stormwater BMP Database Part 1: Summary of Database
Land Development Brief: February 2013 The Pennsylvania Housing Research Center The International Stormwater BMP Database Part 1: Summary of Database Katherine L. Blansett, Ph.D., P.E. INTRODUCTION This
Webcast 2: Watershed Treatment Model
Webcast 2: Watershed Treatment Model Welcome to the Webcast To Ask a Question The lower lefthand corner of the screen contains a chat box. Click on the Public tab and type your question in the box and
PowerWorld Simulator
PowerWorld Simulator Quick Start Guide 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 [email protected] http://www.powerworld.com Purpose This quick start guide is intended to
USING DASHBOARDS AND REPORTS V1.0
USING DASHBOARDS AND REPORTS V1.0 2013. SuccessFactors An SAP Company. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means, electronic or mechanical,
ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND
ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND The Rose Creek Watershed (RCW) consists of three planning
IMPROVING SOUTH FORK PEACHTREE CREEK WATERSHED USING THE TRIPLE BOTTOM LINE DEKALB COUNTY, GEORGIA
IMPROVING SOUTH FORK PEACHTREE CREEK WATERSHED USING THE TRIPLE BOTTOM LINE DEKALB COUNTY, GEORGIA David Chastant AUTHORS:DeKalb County, 330 West Ponce De Leon Ave, Decatur, Georgia 30030 REFERENCE:Proceedings
Coldwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration
Draft Photo Documentation Update for Proposition 13 Grant Agreement No. San Diego Region McClellan-Palomar Airport Water Quality Treatment Facility
Draft Photo Documentation Update for Proposition 13 Grant Agreement No. San Diego Region McClellan-Palomar Airport Water Quality Treatment Facility Prepared For: County of San Diego DPW 555 South Overland
case study 7: south east queensland healthy waterways partnership
2 Australia s National Programme of Action for the Protection of the Marine Environment from Land-Based Activities introduction South-east Queensland s marine systems support large populations of dugongs
AUTOMATED SCHEDULING OF OPEN-CHANNEL DELIVERIES: POTENTIAL AND LIMITATIONS
AUTOMATED SCHEDULING OF OPEN-CHANNEL DELIVERIES: POTENTIAL AND LIMITATIONS Robert S. Gooch, P.E., D.WRE 1 Eduardo Bautista, Ph.D. 2 Robert J. Strand 3 ABSTRACT Irrigation and municipal water delivery systems
DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF WATER QUALITY PROTECTION. Policy for Permitting Surface Water Diversions
DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF WATER QUALITY PROTECTION DOCUMENT NUMBER: 362-2000-003 TITLE: Policy for Permitting Surface Water Diversions EFFECTIVE DATE: March 1, 1998 AUTHORITY POLICY:
DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014. Values Statements.
DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014 Values Statements. The Board opposes any new transfers of water from the
Who has Entered Objectives on their 2013 ACES Forms? & Exporting Data to Excel
I. Overview The Dashboard provides instant up-to-date onscreen reports. The following dashboard report will allow you to track the progress of which managers have started entering objectives onto their
Chapter 2 Treatment Facility Menus
Chapter 2 Treatment Facility Menus This chapter identifies the treatment facility menus. The menus in this chapter are as follows: Oil Control Menu, Section 2.1 Phosphorus Treatment Menu, Section 2.2 Enhanced
Estimating Potential Reduction Flood Benefits of Restored Wetlands
Estimating Potential Reduction Flood Benefits of Restored Wetlands Kenneth W. Potter University of Wisconsin Introduction Throughout the summer of 1993 a recurring question was the impact of wetland drainage
Watershed Treatment Model for Urban Watersheds. Neely L. Law Watershed Analyst Center for Watershed Protection
Watershed Treatment Model for Urban Watersheds Neely L. Law Watershed Analyst Center for Watershed Protection Outline Background Primary Loads Secondary Loads Current Management Practices Future Development
2D Modeling of Urban Flood Vulnerable Areas
2D Modeling of Urban Flood Vulnerable Areas Sameer Dhalla, P.Eng. Dilnesaw Chekol, Ph.D. A.D. Latornell Conservation Symposium November 22, 2013 Outline 1. Toronto and Region 2. Evolution of Flood Management
NPDES Permit No. IL0020737. Notice No. SKT:13120601.bah. Public Notice Beginning Date: April 9, 2014. Public Notice Ending Date: May 9, 2014
Public Notice/Fact Sheet Issued By: Notice No. SKT:13120601.bah Public Notice Beginning Date: April 9, 2014 Public Notice Ending Date: May 9, 2014 National Pollutant Discharge Elimination System (NPDES)
WASHINGTON STATE DEPARTMENT OF TRANSPORTATION SUMMARY OF INVENTORY FINDINGS:
WASHINGTON STATE DEPARTMENT OF TRANSPORTATION SUMMARY OF INVENTORY FINDINGS: Spokane River Dissolved Oxygen Total Maximum Daily Load October 15, 2013 Introduction Special Condition S6 of the Washington
The History and Status of Wetland Mitigation Banking and Water Quality Trading
The History and Status of Wetland Mitigation Banking and Water Quality Trading Palmer Hough and Lynda Hall U.S. EPA Office of Wetlands, Oceans & Watersheds Overview Part I: Mitigation Banking Part II:
WATER QUALITY MONITORING AND APPLICATION OF HYDROLOGICAL MODELING TOOLS AT A WASTEWATER IRRIGATION SITE IN NAM DINH, VIETNAM
WATER QUALITY MONITORING AND APPLICATION OF HYDROLOGICAL MODELING TOOLS AT A WASTEWATER IRRIGATION SITE IN NAM DINH, VIETNAM LeifBasherg (1) OlujZejlllJul Jessen (1) INTRODUCTION The current paper is the
Clean Water Services. Ecosystems Services Case Study: Tualatin River, Washington
Viewed broadly, the concept of ecosystem services describes the many resources and services provided by nature. Typically, traditional planning and development practices do not adequately represent the
City of East Lansing CSO Control Facility Evaluation Demonstrative Approach to Meet WQS
City of East Lansing CSO Control Facility Evaluation Demonstrative Approach to Meet WQS Jeff Johnston, East Lansing WWTP Superintendent & Tom Maxwell, P.E., Hubbell, Roth & Clark, Inc. East Lansing CSO