1 RL Consulting Project Best Practices for the Application ment Process Prepared by: Rick Leopoldi November 22, 2003 Copyright 2003 RL Information Consulting LLC. All rights reserved. Duplication of this document or extraction of content is strictly forbidden.
2 Overview This paper establishes the essential components for the Requirements Definition and subsequently each Phase within an Application ment project process. This includes the primary steps involved in each Phase, and the necessary packets of information that need to be developed and passed from one Phase to the next. These necessary components, including a high-level summarization checklist of activities, are intended to be depict the guiding, final verification, and sign-off needed to proceed to the next step in the Application ment project process cycle. In essence, the components of each Phase and packet are deliverables that are part of, or needed at, the end of each Phase. Page - 1
3 The following Flowchart depicts the Requirements Definition process that should be done prior to, and as part of the Application ment project process cycle: Requirements Definition with Project Methods Flowchart Determine Project Need Vendor Plan Quality Plan Risk Plan Identify Business End Users and Stakeholders Resource Plan Detail Business Requirements Detail Project Requirements Define Work (WBS) Estimate Effort, Time, Cost, Risk Budget and Schedule Mgt/Exec Committee Page - 2
4 Phase 1: Visioning and Business Planning The purpose of this Phase is to identify the business requirement/need for the potential project. The outcome of this Phase is approving the initial project plan that includes but is not limited to the following activities and deliverables that define: Business need Stakeholders Scope Goals Critical success factors Expected outcomes Needs assessment Costs Phase 1 includes but is not limited to the following: 1) Initial Project Plan in the form of a Work Breakdown Structure (WBS) 2) Phase and Signoff for Technical Team and Business Team 3) Project Vision Statement A high level document to be presented to a and/or Executive Committee 4) Initial CBA a high level description of the benefits and costs for the project 5) Phase Signoff Checklist a document that contains a verification checklist signoff for stakeholders, customers, application development group, business end users for each deliverable in this Phase and the verification and approval to move to the next Phase. Phase 2: Analysis and Design The purpose of this Phase is that the business end users drive the analysis and design in concert with the Application ment project team. The detailed business processes that will be impacted are determined. The outcomes of this Phase are: Commitment from the business units and departments that they will provide to the best of their ability the priority and resources to the development of the business and integration systems in their departments to accept and distribute information from/to the integrated system Page - 3
5 Commitment from the business units and departments responsible for the post implementation systems operations and support with drafts of service level agreements (SLA s) of the business and technical plan that includes but is not limited to the following activities and deliverables that define: Business models Data models Prototypes Costs Schedule Estimated milestones Expected results Phase 2 includes but is not limited to the following: 1) More Detailed Project Plan a follow-on to the Work Breakdown Structure (WBS) that contains more detailed tasks, durations, resources, and expertise levels 2) JAD Decision Document 3) Updated Business and Data Models 4) Business Unit Interface Specification 5) Initial ITSM SLA plan 6) Phase and Signoff for Technical Team and Business Team 7) More Detailed CBA a follow-on to the high level CBA that provides a greater description of the benefits and costs for the Application ment project with qualifications and quantifications for each 8) Phase Signoff Checklist a document that contains a verification checklist signoff for stakeholders, customers, application development group, business end users for each deliverable in this Phase and the verification and approval to move to the next Phase. Phase 3: Application ment and Testing The purpose of this Phase is that the Application ment project team will develop and test the system. The outcomes of this Phase are the demonstration of the application in the test environment and review of test results and the approval to proceed with Operational Testing and Implementation step. Page - 4
6 Phase 3 that includes but is not limited to the following activities and deliverables that defines: 1) A Test Project Plan that contains detailed development and testing tasks, durations, resources, and expertise levels 2) Test Results 3) More detailed IT Service plan that includes Service Level, Incident/Problem, Change, Configuration, Release, Service Continuity, and Performance 4) Step and Signoff for Technical Team and Business Team 5) Finalized CBA a detailed level CBA that provides an in-depth description of the benefits and costs for the Application ment project with qualifications and quantifications for each 6) Phase Signoff Checklist a document that contains a verification checklist signoff for stakeholders, customers, application development group, business end users for each deliverable in this Phase and the verification and approval to move to the next Phase. Phase 4: Operational Testing and Implementation The purpose of this Phase is the system to be deployed is moved to the operational environment for final business end user acceptance testing before implementation for operational use. The outcomes of this Phase are the review and approval of the operational environment test results, to implement, and Implementation. Phase 4 includes but is not limited to the following activities and deliverables that defines: 1) An Implementation Project Plan that contains detailed implementation, deployment, and possible recovery tasks, durations, resources, and expertise levels 2) Disaster Recovery Test Results 3) Further detailed IT Service plan that includes Availability, Capacity, and Financial, and Service Desk 4) Step and Signoff for Technical Team and Business Team 5) Phase Signoff Checklist a document that contains a verification checklist signoff for stakeholders, customers, application development group, business end users for each deliverable in this Phase and the verification and approval to move to the next Phase. Page - 5
7 Phase 5: Post Implementation Operations and Support The infrastructure for this step is defined and approved in the Analysis and Design step. Once the system is deployed to operational use the SLA s are put in place and the IT Service procedures for Change, Release, and Incident/Problem, and Service Continuity management take effect. Phase 5 includes but is not limited to the following activities and deliverables that defines: 1) A template set of Project Plans that contains generic templates for detailed analysis and design tasks, development and testing tasks, implementation and deployment tasks, durations, resources, and expertise levels 2) A Disaster Recovery plan 3) A full IT Service Service Delivery and Service Support methods and best practices 4) Final Project and Signoff for Technical Team and Business Team. This is presented to a or Executive Committee 5) Final Step and Project Signoff Checklist a document that contains a verification checklist signoff for stakeholders, customers, application development group, business end users for each deliverable in this Phase and the verification and the approval for all steps. Page - 6
8 Application ment Project Process Activities PHASE 1: Visioning and Planning Draft Initial Scope and Vision Project Phases with Project Methods Flowchart Mgt/Exec Vision Session Draft Initial Scope and Vision Approve Vision Tech/Bus and SignOff Draft CBA PHASE 2: Analysis and Design Initial WBS Budget and Staff Estimates Draft Project Plan Business Model Data Model Define Requirement Specification Prototype Define Technical and Business Interfaces Determine IT Service Level Requirement Analysis and Design Rept Tech/Bus Tech/Bus Team Reqt Spec Go to Phase 3: ment and Testing Page - 7
9 From Phase 2: Analysis and Design Establish Technical Infrastructure PHASE 3: ment and Testing Migrate to Production Technical Infrastructure PHASE 4: Operational Testing and Implementation Integrated Design Operational Test and Evaluation Technical Infrastructure Install Design and Applications Operational and Cutover Unit Test Tech/Bus and SignOff Unit Test and Evaluation Change PHASE 5: ITSM Post- Implementation Support Processes Unit Test and Cutover Incident/ Problem Tech/Bus and SignOff Release Level Project Plan Overview Project Tasks Service Continuity Financial and Budget Team and Skill Set Detailed Project Plan (Schedule, Resources, Milestones) Risk Plan Configuration Additional ITSM Support Processes Tech/Bus and SignOff Performance/ Capacity Service (Help) Desk Page - 8
IT Services Management Service Brief
IT Services Management Service Brief Release Management Prepared by: Rick Leopoldi May 25, 2002 Copyright 2002. All rights reserved. Duplication of this document or extraction of content is strictly forbidden.
IT Services Management Service Brief
IT Services Management Service Brief Service Continuity (Disaster Recovery Planning) Prepared by: Rick Leopoldi May 25, 2002 Copyright 2002. All rights reserved. Duplication of this document or extraction
IT Service Management
IT Service Management Policy Based IT Service Management White Paper Prepared by: Rick Leopoldi March 23, 2004 Copyright 2001. All rights reserved. Duplication of this document or extraction of content
IT Service Management
RL Consulting IT Service Management Service Outsourcing Questionnaire Prepared by: Rick Leopoldi November 10, 2003 Copyright 2003 RL Information Consulting LLC. All rights reserved. Duplication of this
IT Service Management
RL Consulting IT Service Management Incident/Problem Management Methods and Service Desk Implementation Best Practices White Paper Prepared by: Rick Leopoldi vember 8, 2003 Copyright 2003 RL Information
ID Task Name Time Pred
0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive
44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam
44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION
SAMPLE WORK BREAKDOWN STRUCTURES VARIOUS TYPES OF PROJECT
Applications Development Project Sample WBS Management and support Provide project management Provide quality control Conduct meetings and reviews Materials and supplies Travel and living costs Miscellaneous
Project Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
Project Management Life Cycle (PMLC)
Project Management Life Cycle (PMLC) Page 2 Project Management Life Cycle (PMLC) Introduction PMLC Working Group IT Business Process Management(BPM) IT Project Management Office (PMO) Finance System Support
Education Data Portal ( EDP ) Data Dashboard Solutions
NYSED DATA DASHBOARD SOLUTIONS RFP Attachment 6.8 Statement of Work Template THIS IS STATEMENT OF WORK dated [Date] (the SOW ) to the Contract dated [Date] (the Agreement ) between NEW YORK STATE EDUCATION
SOFTWARE DEVELOPMENT PLAN
SOFTWARE DEVELOPMENT PLAN This document outline is based on the IEEE Standard 1058.1-1987 for Software Project Management Plans. This is the controlling document for managing a software project, and it
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
IT Services Management
IT Services Management A Description of a Service Catalog White Paper Prepared by: Rick Leopoldi June 19, 2002 Copyright 2002. All rights reserved. Duplication of this document or extraction of content
ITSM Tools Operation Continuity Plan Example
ITSM Tools Operation Continuity Plan Example 1 Table of Contents 2 Introduction... 2 3 Invocation... 2 4 Scope... 2 5 Data Dependencies and Considerations... 3 6 Security and Access Considerations... 3
Blend Approach of IT Service Management and PMBOK for Application Support Project
Blend Approach of IT Service and PMBOK for Application Support Project Introduction: This paper addresses the process area, phases and documentation to be done for Support Project using Project and ITSM
Blackhawk Technical College. Information Technology Services. Process Improvement Visioning Document
Blackhawk Technical College Information Technology Services Process Improvement Visioning Document December 12, 2008 Steven Davidson Chief Information Officer Blackhawk Technical College [email protected]
IT Service Management
RL Consulting People Process Technology Organization Integration IT Service Management Change Management Methods and Implementation Best Practices White Paper Prepared by: Rick Leopoldi June 19, 2002 Change
LANDesk Professional Services
LANDesk Professional Services Service Description For G-Cloud Background Drawing upon 25 years of experience, LANDesk today is recognized as a leading provider of systems and endpoint security management,
INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.
What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project
Subject Area 1 Project Initiation and Management
DRII/BCI Professional Practice Narrative: Establish the need for a Business Continuity Plan (BCP), including obtaining management support and organizing and managing the BCP project to completion. (This
IT Service Management. The Role of Service Request Management
RL Consulting IT Service Management The Role of Service Request Management Prepared by: Rick Leopoldi June 1, 2007 Copyright 2001-2007. All rights reserved. Duplication of this document or extraction of
OCCUPATIONAL GROUP: Information Technology. CLASS FAMILY: Security CLASS FAMILY DESCRIPTION:
OCCUPATIONAL GROUP: Information Technology CLASS FAMILY: Security CLASS FAMILY DESCRIPTION: This family of positions provides security and monitoring for the transmission of information in voice, data,
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Validating Enterprise Systems: A Practical Guide
Table of Contents Validating Enterprise Systems: A Practical Guide Foreword 1 Introduction The Need for Guidance on Compliant Enterprise Systems What is an Enterprise System The Need to Validate Enterprise
2003 Patricia Ensworth Page 1
1 1 Sample software development project 2 1.1 Start project 3 1.2 Initiation phase 4 1.2.1 Develop project charter 5 1.2.2 Project charter approved 6 1.3 Planning phase 7 1.3.1 Product activities 8 1.3.1.1
CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS
Chapter 3: Managing Implementation Projects CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Objectives Introduction The objectives are: Describe common problems that occur in implementation projects. Describe
Project Transition Plan
Put your logo here Put your organization name here Project Transition Plan Template Rev. 1.2 November, 2011 Project Transition Plan Project Name: Prepared by: Date (MM/DD/YYYY): Version History (insert
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
An Application of an Iterative Approach to DoD Software Migration Planning
An Application of an Iterative Approach to DoD Software Migration Planning John Bergey Liam O Brien Dennis Smith September 2002 Product Line Practice Initiative Unlimited distribution subject to the copyright.
SCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
How To Implement An Enterprise Resource Planning Program
ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Appeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
IT Project: System Implementation Project Template Description
2929 Campus Drive Suite 250 IT Project: System Implementation Project Template Description Table of Contents Introduction... 2 Project Phases... 3 Initiation & Requirements Gathering Milestone... 3 Initiation
Project Processes. Media Snapshot. Project Management Process Groups
Project Processes PROJECT LIFECYCLE A project normally requires a number of processes. A process is a series of actions directed toward a particular result Project management can be viewed as a number
Re: RFP # 08-X-39202 MOTOR VEHICLE AUTOMATED TRANSACTION SYSTEM (MATRX) FOR MVC ADDENDUM #10
State of New Jersey DEPARTMENT OF THE TREASURY JON S. CORZINE DIVISION OF PURCHASE AND PROPERTY BRADLEY I. ABELOW Governor PURCHASE BUREAU State Treasurer P.O. BOX 230 TRENTON, NEW JERSEY 08625-0230 September
ITIL Deployment Life Cycle
ITIL Deployment Life Cycle 90 Adelaide Street West, Suite 401, Toronto, Ontario, M5H 3V9 www.balardogroup.com Telephone: (416) 410 3554 Fax: (800) 385 9946 Overview The purpose of this document is to provide
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
ITIL. Lifecycle. www.alctraining.com.my. ITIL Intermediate: Continual Service Improvement. Service Strategy. Service Design. Service Transition
Take your ITIL skills to the next level ITIL Lifecycle ITIL Intermediate: Part of the complete ITIL Education Program Advance your career Add value to your organisation Gain credits towards ITIL Expert
This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>.
Guide to Preparing the SOFTWARE PROJECT MANAGEMENT PLAN R. Buckley CSc 190 Senior Project Department of Computer Science - College of Engineering and Computer Science California State University, Sacramento
5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter
Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the
Draft Documents RFP 3.2.4
Draft Documents RFP 3.2.4 In accordance with RFP 3.2.4, CNSI includes the required draft documents in the following order: Work Plan: Team CNSI provides a comprehensive draft Work Plan for the Iowa EHR
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in this Project Scope Statement is implicitly excluded from the project. Create links to referenced documents (e.g., Link_To_ ) by using Insert
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Appendix 2-A. Application and System Development Requirements
Appendix 2-A. Application and System Development Requirements Introduction AHRQ has set up a Distributed Systems Engineering Lab (DSEL) to support all internal development efforts and provide a facility
IT SERVICES MANAGEMENT Service Level Agreements
IT SERVICES MANAGEMENT Service Level Agreements Sample Agreements, Reports, and Checklists White Paper PREPARED BY: RICK LEOPOLDI May 25, 2002 Copyright 2002. All rights reserved. Duplication of this document
7 Practical insights for IT Asset Management
7 Practical insights for IT Asset Management Tauneel McKay Director Swiss Reinsurance Company Ltd Subbarao Chaganty Principal Consultant Infosys Ltd RELATE MANAGE.. Context KNOW. Consolidate the IT Asset
Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases
Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor
ASAP Roadmap. Solution Use. Bill Wood [email protected] (704) 905 5175 http://www.r3now.com
ASAP Roadmap Solution Use Bill Wood [email protected] (704) 905 5175 http://www.r3now.com 704. 905. 5175 [email protected] www.r3now.com http://www.linkedin.com/in/billwood Page 1 of 22 Contents THE
ISO20000: What it is and how it relates to ITIL v3
ISO20000: What it is and how it relates to ITIL v3 John DiMaria; Certified Six Sigma BB, HISP BSI Product Manager; ICT (ISMS,ITSM,BCM) Objectives and Agenda To raise awareness, to inform and to enthuse
Enaxis Consulting Overview
Enaxis Consulting Overview MULTI DIMENSIONAL THINKING October 2009 24 Greenway Plaza Ste 1505 Houston TX 77046 713.881.9494 (o) 713.881.9499 (f) Enaxis Overview We offer the quality of a global firm without
Cisco Unified Contact Center Planning and Design Service
Cisco Unified Contact Center Planning and Design Service Create unique customer experiences for your customers by exploring new possibilities and realizing the full potential of your contact center. Services
Request for Proposal for Application Development and Maintenance Services for XML Store platforms
Request for Proposal for Application Development and Maintenance s for ML Store platforms Annex 4: Application Development & Maintenance Requirements Description TABLE OF CONTENTS Page 1 1.0 s Overview...
Information Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
Migration Planning Guidance (Draft)
Financial Management Line of Business Migration Planning Guidance (Draft) Section 1.1 Overview The purpose of the Migration Planning Guidance document is to help agencies prepare for, and manage, a migration
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
Second Amendment To the HIPAA 5010 and ICD-10 Technical Assistance and Support Services Contract
Second Amendment To the HIPAA 5010 and ICD-10 Technical Assistance and Support Services Contract This second Amendment to Contract Number is effective as of December 12, 2011, between the Iowa Department
Project Lifecycle Management (PLM)
Project Lifecycle Management (PLM) Process or Tool? Why PLM? Project Definition Project Management NEW REQUEST/ INITIATIVES SUPPORT (Quick fixes) PROJECT (Start Finish) ONGOING WORK (Continuous) ENHANCEMENTS
Datalynx Project Delivery Methodology and PCTM Methodology For Legacy Data Cleansing & Migration
Datalynx Project Delivery Methodology and For Legacy Data Cleansing & Migration Title: Datalynx for Migrating Legacy Data Revision: V1.4 Copyright 2014 - Datalynx Pty Ltd. All rights reserved. www.datalynx.com.au
Introduction to Enterprise Project Management
001_0672329212_Intro.qxd 10/1/07 9:42 AM Page 1 Introduction to Enterprise Project Management Throughout this book, you will see that Enterprise Project Management (EPM; also called Enterprise Portfolio
Request for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018
Request for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018 for City of Pitt Meadows Table of Contents Table of Contents... 2 General Information...
SAP ERP Upgrade Checklist Project Preparation
A SAP ERP Upgrade Checklist Project Preparation Upgrade Project Phase Project Preparation Definition From the project perspective the project preparation phase includes: Learning about the new functionality
Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management
Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB51407 Diploma of Project Management First published 2010 ISBN 978-1-74205-511-4 Department of Training and
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
Time Management. Part 2 Work Breakdown Structure (WBS) Review. Richard Boser
Time Management Part 2 Work Breakdown Structure (WBS) Review Richard Boser WBS Planning Process PMBOK WBS is deliverable-oriented grouping of components that organizes and defines the total scope of the
Services Providers. Ivan Soto
SOP s for Managing Application Services Providers Ivan Soto Learning Objectives At the end of this session we will have covered: Types of Managed Services Outsourcing process Quality expectations for Managed
Employing ITSM in Value Added Service Provisioning
RL Consulting People Process Technology Organization Integration Employing ITSM in Value Added Service Provisioning Prepared by: Rick Leopoldi January 31, 2015 BACKGROUND Service provisioning can oftentimes
IT Services Management
IT Services Management Data Management Process White Paper Prepared by: Rick Leopoldi May 25, 2002 Copyright 2002. All rights reserved. Duplication of this document or extraction of content is strictly
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
Annex 9: Technical proposal template. Table of contents
UNFCCC/CCNUCC Page 1 Annex 9: Technical proposal template Table of contents Annex 9... 3 9.1 Technical proposal... 3 9.1.1 Vendor s name... 3 9.2 Engagement model... 3 9.2.1 Type of engagement... 3 9.2.2
PHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
PROJECT PLAN FOR. Project Name Here
PROJECT PLAN FOR Project Name Here Version # DatE Reviewed and Approved for submittal to Executive Sponsor , Project Manager Project Plan Approved for submittal to Executive Sponsor: , Project
Title: DISASTER RECOVERY/ MAJOR OUTAGE COMMUNICATION PLAN
POLICY: This policy is intended to address organizational wide communication executed during a or major IS service outage. When a disaster occurs or when any critical system/infrastructure component is
CDC UNIFIED PROCESS JOB AID
CDC UNIFIED PROCESS JOB AID Independent Verification & Validation Activities Document Purpose This Job Aid is a brief document listing the items to be noted, checked, remembered, and delivered when completing
Project Implementation Process (PIP)
Vanderbilt University Medical Center Project Implementation Process (PIP).......... Project Implementation Process OVERVIEW...4 PROJECT PLANNING PHASE...5 PHASE PURPOSE... 5 TASK: TRANSITION FROM PEP TO
Project Roles and Responsibilities
Project s and This template can be used to define roles and responsibilities Below is a few typical examples of the different types of roles involved in delivering a project and their respective responsibilities.
ITS Projects Systems Engineering Process Compliance Checklist
ITS Projects Systems Engineering Process Compliance Checklist FHWA Final Rule (23 CFR 940) This checklist is to be completed by the MDOT or LPA Project Management Staff. Please refer to the accompanying
Capacity Plan. Template. Version X.x October 11, 2012
Template Version X.x October 11, 2012 This is an integral part of infrastructure and deployment planning. It supports the goal of optimum provisioning of resources and services by aligning them to business
Data Conversion Best Practices
WHITE PAPER Data Conversion Best Practices Thomas Maher and Laura Bloemer Senior Healthcare Consultants Hayes Management WHITE PAPER: Data Conversion Best Practices Background Many healthcare organizations
System/Data Requirements Definition Analysis and Design
EXECUTIVE SUMMARY This document provides an overview of the Systems Development Life-Cycle (SDLC) process of the U.S. House of Representatives. The SDLC process consists of seven tailored phases that help
Criticism of Implementation of ITSM & ISO20000 in IT Banking Industry. Presented by: Agus Sutiawan, MIT, CISA, CISM, ITIL, BSMR3
Criticism of Implementation of ITSM & ISO20000 in IT Banking Industry Presented by: Agus Sutiawan, MIT, CISA, CISM, ITIL, BSMR3 Outline What is IT Service Management What is ISO 20000 Step by step implementation
TERMS OF REFERENCE (TORs) OF CONSULTANTS - (EAG) 1. Reporting Function. The Applications Consultant reports directly to the CIO
TERMS OF REFERENCE (TORs) OF CONSULTANTS - (EAG) Consultant - Enterprise Systems & Applications 1. Reporting Function. The Applications Consultant reports directly to the CIO 2. Qualification and Experience
Optimos Enterprise Helpdesk Automation Solution Case Study
Optimos Enterprise Helpdesk Automation Solution Case Study IT Help Central National Science Foundation Optimos Incorporated 4455 Brookfield Corporate Drive Chantilly, VA 20151 Telephone: (703) 488-6900
CDC UNIFIED PROCESS PRACTICES GUIDE
Purpose The purpose of this document is to provide guidance on the practice called Project Close-Out and to describe the practice overview, requirements, best practices, activities, and key terms related