1 ESTIMATING PROJECT COST CONTINGENCY A MODEL AND EXPLORATION OF RESEARCH QUESTIONS David Baccarini Department of Construction Management, Curtin University of Technology, PO Box U198, Perth 6845, Western Australia, Australia. The cost performance of building construction projects is a key success criterion for project sponsors. Projects require budgets to set the sponsor s financial commitment and provide the basis for cost control and measurement of cost performance. A key component of a project budget is cost contingency. A literature review of the concept of project cost contingency is presented from which a model for the estimating of project cost contingency is derived. This model is then used to stimulate a range of important research questions in regard to estimating project cost contingency and the measurement of its accuracy. Keywords: cost contingency, project cost performance, project risk management INTRODUCTION The cost performance of construction projects is a key success criterion for project sponsors. Project cost overruns are commonplace in construction (Touran 2003). Cost contingency is included within a budget estimate so that the budget represents the total financial commitment for the project sponsor. Therefore the estimation of cost contingency and its ultimate adequacy is of critical importance to projects. The primarily focus of this paper is a literature review, leading to a tentative model for the concept of project cost contingency. The literature on project cost contingency tends to focus predominately upon the micro-process of estimation. There is no model that sets out a macro perspective to provide a holistic understanding of the estimating process for project cost contingency. A model for project cost contingency, from the perspective of the project, is presented to stimulate the identification of research questions regarding the estimating of project cost contingency and measurement of its accuracy. CONTINGENCY - DEFINITION There are three basic types of contingencies in projects: tolerance in the specification, float in the schedule, and money in the budget (CIRIA 1996). There is no standard definition for contingency as Patrascu (1988:115) observes, "Contingency is probably the most misunderstood, misinterpreted and misapplied word in project execution. Contingency can and does mean different things to different people". Contingency has been defined as the amount of money or time needed above the estimate to reduce the risk of overruns of project objectives to a level acceptable to the organization (PMI 2000: 199) Baccarini, D (2004) Estimating project cost contingency - a model and exploration of research questions. In: Khosrowshahi, F (Ed.), 20th Annual ARCOM Conference, 1-3 September 2004, Heriot Watt University. Association of Researchers in Construction Management, Vol. 1,
2 Baccarini Some authors distinguish between contingency, allowance and management reserve. Allowance is for specific, known but undefined items (Clark and Lorenzoni 1985, Patrascu 1988, Querns 1989, Rad 2002). Management reserve is a provision held by the project sponsor for possible changes in project scope and quality (Wideman 1992). The management reserve should also be expected to cater for extraordinary, unforeseen external risks e.g. currency-exchange fluctuation, force majeure (Yeo 1990). CONTINGENCY - ATTRIBUTES An analysis of the literature identifies the following key attributes of the concept of project cost contingency: Reserve Cost contingency is a reserve of money. A reserve is a provision in the project plan to mitigate cost risk (PMI 2000). Risk and Uncertainty The need and amount for contingency reflects the existence of risk and uncertainty in projects (Thompson and Perry 1992). Contingency caters for events within the defined project scope that are unforeseen (Moselhi 1997, Yeo 1990), unknown (PMI 2000), unexpected (Mak et al 1998), unidentified (Levine 1995), or undefined (Clark and Lorenzoni 1985, Thompson and Perry 1992). Risk Management Contingency is an antidote to risk. There is a range of risk treatment strategies for managing risk in projects such as risk transfer, risk reduction, and financial treatments for retained risks e.g. contingency. So contingency is used in conjunction with other risk treatment strategies. Total Commitment - Cost estimates are prepared and contingencies added in order to indicate the likely total cost of the project. The inclusion of contingencies within a budget estimate means that the estimate represents the total financial commitment for a project. Contingency should avoid the need to appropriate additional funds and reduces the impact of overrunning the cost objective. Project Outcomes - Contingency can have a major impact on project outcomes for a project sponsor. If contingency is too high it might encourage sloppy cost management, cause the project to be uneconomic and aborted, and lock up funds not available for other organisational activities; if too low it may be too rigid and set an unrealistic financial environment, and result unsatisfactory performance outcomes (Dey et al 1994). CONTINGENCY - COVERAGE Contingency caters for two categories of risk - known unknowns and unknown unknowns (PMI 2000, Hillson 1999). Known unknowns are risks that have been identified, analysed and it may be possible to plan for them (PMI 2000). They are identifiable sources of uncertainty (Chapman 2000). Unknown unknowns cannot be managed although they may be addressed them by applying a general contingency based on past experience with similar projects (PMI 2000). So a contingency should be set up to allow for residual unidentified risks not revealed during the risk identification process (Hillson 1999). Unknown unknowns cannot be anticipated and therefore are not manageable and the realisation of some of them is usually inevitable but they exclude risks like the world may end tomorrow (Chapman 2000). 106
3 Project cost contingency It is not only important to understand the factors covered by contingency but also those factors that it is not intended for: Scope changes (Querns 1989, Moselhi 1997). Scope changes occur when what is now expected is materially different from what was previously reasonably expected. Contingency does cover for cost created by scope development i.e. scope remains constant even as the product characteristics are progressively elaborated (PMI 2000); Escalation, which is usually shown as a separate item within the project budget (Querns 1989, Moselhi 1997); unforeseeable major events such as extreme weather, earthquakes, riots, acts of war new government regulations, and economic collapse (Heinze 1996, Moselhi 1997). CONTINGENCY - ESTIMATION A range of estimating techniques is available for calculating project cost contingencysee Table 1. Table 1: Contingency - Estimating methods Contingency Estimating methods References (Examples) 1. Traditional percentage Ahmad 1992, Moselhi Method of Moments Diekmann 1983; Moselhi, 1997, Yeo 1990; 3. Monte Carlo Simulation Lorance & Wendling Factor Rating Hackney 1985, Oberlander & Trost Individual risks expected value Mak, Wong & Picken Range Estimating Curran Regression Merrow & Schroeder 1991; Aibinu & Jagboro Artificial Neural Networks Chen & Hartman 2000; Williams Fuzzy Sets Paek, Lee, & Ock, Controlled Interval Memory Cooper and Chapman 1985; 11. Influence Diagrams Diekmann & Featherman Theory of Constraints Leach Analytical Hierarchy Process Dey, Tabucanon & Ogunlana 1994 Traditional Percentage It is worth briefly describing the long-established percentage approach to estimating contingency because it provides an understanding for the search for alternative estimating methods. Traditionally cost estimates are deterministic [i.e. point estimates for each cost element] based on their most likely value (Mak et al 1998). Contingencies are often calculated as an across-the-board percentage addition on the base estimate, typically derived from intuition, past experience and historical data. The percentage addition method is based on a subjective approach and may consider project characteristics such as type of work, phase of the project, and level of scope definition (Lorance and Wendling 2001). This calculation method is satisfactory for simple projects under stable conditions but is unsuitable for large and complex projects (Newton 1992). A different contingency percentage can be calculated for each major cost element, which reflects that some parts of the project may have greater uncertainty than others 107
4 Baccarini (Ahmad 1992, Moselhi 1997). Each major segment of the estimate is classified in terms of its degree of uncertainty or accuracy and then attracts its own appropriate contingency (Bent and Humphreys 1996). This method is considered more rational and reliable than the simple application of one overall percentage to the total cost because it encourages close examination of each cost area (Moselhi 1997). Traditional Percentage - weaknesses Thompson and Perry (1992:1) observe all too often risk is either ignored or dealt with in an arbitrary way: simply adding a 10% 'contingency' onto the estimated cost of a project is typical". This arbitrary bottom percentage may not be appropriate for the proposed project (Heinze 1996). And it is difficult for the estimator to justify or defend (Newton 1992, Yeo 1990). It is an unscientific approach and a reason why so many projects are over budget (Hartman 2000). Furthermore, allocating a contingency percentage is insufficient unless linked to a confidence level. i.e. the level of probability that the final project cost will be within the estimate including contingencies (Moselhi 1997) There is a tendency to incorporate hidden contingency within the individual cost elements ( padding ) as well as an additional percentage to the total cost (Mak et al 1998). The project manager may not be aware of the padding and therefore will not be able to control this hidden contingency. A padded cost element can become a selffulfilling prophecy as the entire amount is spent unnecessarily to justify the estimate (Hamburger 1994). A percentage addition results in a single-figure prediction of estimated cost which implies a degree of certainty that is not justified (Mak et al 1998). It does not encourage creativity in estimating practice, promoting a routine and mundane administrative approach requiring little investigation and decision making, which may propagate oversights (Yeo 1990, Mak et al 1998). Also, the percentage addition indicates the potential for downside risk. It does not indicate any potential for cost savings and may therefore mask poor project management (Mak et al 1998). It is claimed that contingency is often set too high for low-risk projects and too low for high-risk projects (Mok et al 1997). There is a tendency to overestimate contingency because an underestimated contingency may attract negative comment whilst there is no penalty for overestimation; and to avoid the need to seek additional funds if budgets become overspent (Mak et al 1998). The weaknesses of the traditional percentage addition approach for calculating contingencies has led for a search for a more robust approach as evidenced by the range of estimating methods set out in Table 1. CONTINGENCY - MANAGEMENT Once a contingency fund has been formulated its use must be explicitly identified and controlled. The level of contingency should be constantly monitored and reassessed throughout the project life cycle for appropriateness (CIRIA 1996). Importantly, cost contingency must be used for their intended purpose and not incorrectly used for poor performance (Levine 1995). 108
5 Project cost contingency CONTINGENCY A MODEL Figure 1 set outs a model for the estimating for project cost contingency. The model is for the estimating of contingency by the project sponsor just prior to the commencement of construction phase of building projects. The sponsor has awarded a contract to a building contractor and needs an estimate of the final cost of the project for budgeting purposes. This budget is a combination of the contract sum plus contingency. The key elements of this model are: 1. Contingency is a part of an overall risk management strategy. It is a financial reserve to cater for retained risks. The selection of contingency as a risk treatment strategy leads to the need to estimate the amount of contingency required. 2. There are numerous estimating methods available for project cost contingency ranging from the traditional percentage approach to more sophisticated methods such as Monte Carlo simulation and artificial neural networks. 3. There are several influential variables that affect the estimating process and the amount of estimated contingency (e.g. cognitive bias of the estimator, organisational policies, project size and complexity, and estimator s experience) 4. Contractual variations are the means for altering the contract sum and affecting the actual final cost. The final total amount of variations will be influenced by the contingency management approach e.g. a formal rigorous method that aims to minimize contractual variations is likely to limit the final total value of variations 5. Once a contingency has been estimated it is added to the contract sum to represent the predicted final cost of the project for the sponsor. The actual final cost is the sum of the contract plus contractual variations. The accuracy of the contingency can be measured by comparing the predicted final cost against the actual final cost. 109
6 Baccarini RESEARCH QUESTIONS Using the model in Figure 1, research questions for estimating accurate project cost contingency can be identified. 1. What is the project management community s understanding of the concept of project contingency. There has been little empirical research into the concept of project cost contingency in particular project practitioners understanding of the concept, its intended scope, methods of estimating contingency or the management process for contingency. Despite the ubiquity of cost contingency within project budgets, it has not stimulated a great deal of research interest. However, there has more recently been research into cost contingency (e.g. Mak et al 1998; Aibinu & Jagboro 2002, Williams 2003). One possible reason for this is could be the growing interest in project risk management and the realisation that cost contingency is in fact an important risk management tool. The author is presently finalising a paper into practitioners understanding of project cost contingency. 2. How accurate are cost contingencies? The inclusion of contingencies within a budget estimate for the construction phase of a building project means that this budget represents the total financial commitment for a project. The aim is to estimate a project contingency so that Contract Sum + Contingency = Predicted Final Cost. In effect contingency is catering for variations allowable under the contract between the sponsor and contractor. Research could be undertaken to compare the Predicted Final Cost against the Actual Final Cost to discover the accuracy of contingency estimates. Broadly the smaller the difference between these two costs the more accurate the project cost contingency. This would indicate whether there is a problem is accurately estimating project cost contingency. If contingencies are inaccurate then this could lead to further research questions - see below. 3. Are some contingency estimating methods more accurate than others There are numerous methods for estimating project cost contingency. Research could be undertaken to investigate which if any are more accurate. This would indicate whether the use of certain estimating methods should be encouraged. 4. What variables affect the accuracy of estimating project cost contingency? Research could be undertaken to identify any variables that have a relationship to the accuracy of project cost contingency, for example project size, complexity, type or location. Any variables that do have a relationship might then be used to predict a more accurate project cost contingency; or simply highlight to estimators that when these variables are present there is a need to pay particular consideration to them when estimating contingency. Research could be undertaken to investigate whether any cognitive influences upon the estimator are related to the accuracy of contingency such as risk attitude, cognitive bias (e.g. heuristics) and conscious bias. 5. What effect does the management of project cost contingency have on its accuracy? Once a contingency has been formulated its use must be managed. Research could be undertaken to investigate the nature of the contingency management process and whether the level of management of contingency during the construction process (e.g. level of reporting, formality of policies and procedures) has any relationship with the accuracy of project cost contingency. 110
7 Project cost contingency CONCLUSION The cost performance of construction projects is a key success criterion for project sponsors, which can be measured by comparing project budgets against final cost. Therefore the estimation of cost contingency is an important issue in projects and worthy of research. A literature review of the concept of project cost contingency found no model to represent the elements that play a part in its estimation or the measurement of the accuracy of these estimates. Figure 1 is first attempt known to the author to provide a model for the concept of project cost contingency that can then facilitate the identification of research questions. The author is presently conducting research into some of these questions such as practitioners understanding of the concept of project cost contingency; the estimating accuracy of cost contingency; and the development of a regression model for predicting cost contingency. REFERENCES Ahmad I (1992) Contingency allocation: a computer-aided approach AACE Transactions, 28 June - 1 July, Orlando, F Aibinu A A and Jagboro G.O (2002) The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management, 20, Bent J A and Humphreys K K (1996) Effective project management through applied cost and schedule control. New York: M. Dekker. Chapman C (2000) Project risk management: the required transformations to become project uncertainty management. PMI Research Conference, 2-4 th June, Paris. PMI. Chen D and Hartman F T (2000) A neural network approach to risk assessment and contingency allocation. AACE Transactions, th June, Risk CIRIA (Construction Industry Research and Information Association) (1996) Control of risk: a guide to the systematic management of risk from construction. London: CIRIA Clark F D and Lorenzoni A B (1985). Applied cost engineering. New York: M. Dekker Cooper D F and Chapman C B (1985) Risk analysis of a construction cost estimate. International Journal of Project Management, 3(3), Curran M W (1989) Range Estimating, Cost Engineering, 31(3), Dey P, Tabucanon M T, and Ogunlana S O (1994) Planning for project control through risk analysis, a petroleum pipelaying project. International Journal of Project Management, 12(1), Diekmann J E (1983) Probabilistic estimating: mathematics and applications. Journal of Construction Engineering and Management, 109(3), Diekmann J E and Featherman W D (1998) Assessing cost uncertainty: lessons from environmental restoration projects. Journal of Construction Engineering and Management, 124(6), Hackney J W (1985) Applied contingency analysis. AACE Transactions, B.1-4 Hamburger D (1994) Upper management s leadership role in the contingency planning and control process. PMI Annual Seminar and Symposium, October, Vancouver. PMI. Hartman F T (2000) Don t park your brain outside. Upper Darby PA: PMI. 111
8 Baccarini Heinze K (1996) Cost management of capital projects. New York: M. Dekker Hillson D (1999) Developing effective risk responses. PMI Annual Seminar and Symposium, th October, Philadelphia. PMI Leach L P (2003) Schedule and cost buffer sizing: how to account for the bias between project performance and your model. Project Management Journal, 34(2), Levine H (1995) Risk management for dummies: managing schedule cost and technical risks and contingency. PM Network, October, Lorance R B and Wendling R V (2001) Basic techniques for analysing and presenting cost risk analysis. Cost Engineering, 43(6), Mak S, Wong J and Picken D (1998) The effect on contingency allowances of using risk analysis in capital cost estimating: a Hong Kong case study. Construction Management and Economics, 16, Merrow E W and Schroeder B R (1991) Understanding the costs and schedule of hydroelectric projects, AACE Transactions, June, Seattle, I Mok C K, Rao Tummala V M, and Leung H M (1997) Practices barriers and benefits of risk management process in building services cost estimation. Construction Management and Economics, 15, Moselhi O (1997) Risk assessment and contingency estimating AACE Transactions, 13-16th July, Dallas. DandRM/A Newton S (1992) Methods of analyzing risk exposure in the cost estimates of high quality offices. Construction Management and Economics. 10, Paek J H, Lee Y W and Ock J H (1994) Pricing construction risk: fuzzy set application Journal of Construction Engineering and Management, 119(4), Patrascu A (1988) Construction cost engineering handbook. New York: M. Dekker. PMI [Project Management Institute] (2000) A guide to the project management body of knowledge. Upper Darby PA: PMI. Querns W R (1989) What is Contingency Anyway? AACE Transactions, th June, San Diego. B Rad P F (2002). Project estimating and cost management. Vienna, Va: Management Concepts. Thompson P A and Perry J G (1992). Engineering construction risks. London: Thomas Telford. Touran A (2003) Probabilistic cost estimating with subjective correlations, Journal of Construction Engineering and Management, 119(1), Wideman R M (1992) Project and program risk management: a guide to managing risks and opportunities. Dexel Hill, Pa: PMI. Williams T P (2003) Predicting final cost for competitively bid construction projects using regression models, International Journal of Project Management, 21, Yeo KT (1990) Risks, classification of estimates and contingency management. Journal of Management in Engineering, 6(4),
9 INTRODUCTORY CONTEXT eg: Importance of contingency in construction projects, cost performance as success criterion, lack of empirical research into accuracy of client cost contingency and significant variables that may influence this accuracy OTHER TREATMENTS RISKS IN CONSTRUCTION PROJECTS 1. Known Unknowns 2. Unknown Unknowns CONTRACT TREATMENT contract conditions between client and contractor FINANCIAL TREATMENT CONTINGENCY ESTIMATING TECHNIQUES CONTINGENCY QUANTUM Client contingency for construction phase CONTRACT SUM CONTRACT VARIATIONS ALLOWANCES MANAGEMENT RESERVE Beyond scope of research VARIABLES 1. Project Variables 2. Client Variables 3. Estimating Variables 4. Environmental Variables 5. Organisational Variables 6. Cognitive Variables CONTINGENCY 1. Traditional percentage 2. Method of Moments 3. Monte Carlo Simulation 4. Factor Rating 5. Individual risks expected value 6. Range Estimating 7. Regression 8. Artificial Neural Networks 9. Fuzzy Sets 10. Controlled Interval memory 11 Influence Diagrams PREDICTED FINAL COST ACTUAL FINAL COST ACCURACY OF CONTINGENCY QUANTUM CONTINGENCY MANAGEMENT Figure 1: Model - Sponsor Project Cost Contingency 113
Estimating Project Cost Contingency Beyond the 10% syndrome
Estimating Project Cost Contingency Beyond the 10% syndrome D.Baccarini Faculty of Built Environment, Art & Design, Curtin Univeristy of Technology, Perth, Western Australia ABSTRACT Projects require budgets
Risk Pricing in Construction Tenders How, Who What
Risk Pricing in Construction Tenders How, Who What Marcus Tower and David Bacarini (Department of Construction Management, Curtin University of Technology, Perth, Western Australia ABSTRACT Construction
PROJECT RISK ANALYSIS AND MANAGEMENT
PROJECT RISK ANALYSIS AND MANAGEMENT A GUIDE BY THE ASSOCIATION FOR PROJECT MANAGEMENT (formerly The Association Of Project Managers) Compiled from information provided by members of the Special Interest
The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2
The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2 1 Curtin University of Technology, Perth, Western Australia 2 Broad Construction Services, Perth, Western
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
Capital Adequacy: Advanced Measurement Approaches to Operational Risk
Prudential Standard APS 115 Capital Adequacy: Advanced Measurement Approaches to Operational Risk Objective and key requirements of this Prudential Standard This Prudential Standard sets out the requirements
Extending the Risk Process to Manage Opportunities
Extending the Risk Process to Manage Opportunities Dr David Hillson PMP FAPM MIRM Director of Consultancy, Project Management Professional Learning Limited 7 Amersham Hill, High Wycombe, Bucks HP13 6NS,
Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson
Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced
STAG Technical Database Section 13
Risk and Uncertainty May 2014 Transport Scotland Once printed or downloaded this document is considered to be uncontrolled. For the current version refer to the Scot-TAG section of the Transport Scotland
PROJECT RISK MANAGEMENT - ADVANTAGES AND PITFALLS
1 PROJECT RISK MANAGEMENT - ADVANTAGES AND PITFALLS Kenneth K. Humphreys 1, PE CCE DIF 1 Past Secretary-Treasurer, ICEC, Granite Falls, NC, United States Abstract Proper project decision-making requires
PMI Risk Management Professional (PMI-RMP) Exam Content Outline
PMI Risk Management Professional (PMI-RMP) Exam Content Outline Project Management Institute PMI Risk Management Professional (PMI-RMP) Exam Content Outline Published by: Project Management Institute,
Value Adding Through Appropriate Integrated Risk Insight : Transforming Development Opportunities Into Projects.
Value Adding Through Appropriate Integrated Risk Insight : Transforming Development Opportunities Into Projects. G. J. Hawkins LRMC PTY Ltd, 96 Stanley Street, Nedlands, Western Australia 6009 Tel: +61
Monte Carlo analysis used for Contingency estimating.
Monte Carlo analysis used for Contingency estimating. Author s identification number: Date of authorship: July 24, 2007 Page: 1 of 15 TABLE OF CONTENTS: LIST OF TABLES:...3 LIST OF FIGURES:...3 ABSTRACT:...4
Eliminating Over-Confidence in Software Development Effort Estimates
Eliminating Over-Confidence in Software Development Effort Estimates Magne Jørgensen 1 and Kjetil Moløkken 1,2 1 Simula Research Laboratory, P.O.Box 134, 1325 Lysaker, Norway {magne.jorgensen, kjetilmo}@simula.no
Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry
CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview Sante Torino PMI-RMP, IPMA Level B Head of Risk Management Major Programmes, Selex ES / Land&Naval Systems Division
Best practice cost estimation in land transport infrastructure projects
Australasian Transport Research Forum 2010 Proceedings 29 September 1 October 2010, Canberra, Australia Publication website: http://www.patrec.org/atrf.aspx Best practice cost estimation in land transport
A guide to the water charge (infrastructure) rules: Tier 2 requirements
A guide to the water charge (infrastructure) rules: Tier 2 requirements June 2011 Australian Competition and Consumer Commission 23 Marcus Clarke Street, Canberra, Australian Capital Territory, 2601 Commonwealth
Project Cost Control: The Way it Works By R. Max Wideman
Project Cost Control: The Way it Works By R. Max Wideman 12/21/05 In a recent consulting assignment we realized that there was some lack of understanding of the whole system of project cost control, how
Guideline on loan classification system
Appendix 2 Guideline on loan classification system 1. This guideline sets out the loan classification framework adopted by the Hong Kong Monetary Authority ( HKMA ) for monitoring the asset quality and
Acompany that consistently selects the right projects and
PM.01 How to Create a World Class Project Management Organization Dr. Nick J. Lavingia, PE Acompany that consistently selects the right projects and executes them with excellence can improve return on
COMBINING THE METHODS OF FORECASTING AND DECISION-MAKING TO OPTIMISE THE FINANCIAL PERFORMANCE OF SMALL ENTERPRISES
COMBINING THE METHODS OF FORECASTING AND DECISION-MAKING TO OPTIMISE THE FINANCIAL PERFORMANCE OF SMALL ENTERPRISES JULIA IGOREVNA LARIONOVA 1 ANNA NIKOLAEVNA TIKHOMIROVA 2 1, 2 The National Nuclear Research
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
INT 3 Schedule Risk Analysis
INT 3 Schedule Risk Analysis David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12, 2015 1 Agenda Add uncertainty to the schedule,
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
ScienceDirect. Project Prioritization and Portfolio Performance Measurement in Project Oriented Organizations
Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Scienc es 119 ( 2014 ) 339 348 27 th IPMA World Congress Project Prioritization and Portfolio Performance Measurement
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
An Assessment of Risk Identification in Large Construction Projects in Iran
Journal of Construction in Developing Countries, Supp. 1, 57 69, 2012 An Assessment of Risk Identification in Large Construction Projects in Iran Mehdi Tadayon 1, Mastura Jaafar 1 and Ehsan Nasri 2 Abstract:
Project Governance a board responsibility. Corporate Governance Network
Project Governance a board responsibility Corporate Governance Network November 2015 1 Contents Page Introduction 3 Board responsibilities 3 What is project governance? 4 The boards duties in respect of
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
Capital Works Management Framework
POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset
The consumer purchase journey and the marketing mix model
Dynamic marketing mix modelling and digital attribution 1 Introduction P.M Cain Digital media attribution aims to identify the combination of online marketing activities and touchpoints contributing to
Understanding risk exposure using multiple hierarchies. Introduction
Understanding risk exposure using multiple hierarchies David Hillson PhD PMP FAPM FIRM MCMI FRSA Director, Risk Doctor & Partners Introduction Risk management is recognised as an essential contributor
Teaching Business Statistics through Problem Solving
Teaching Business Statistics through Problem Solving David M. Levine, Baruch College, CUNY with David F. Stephan, Two Bridges Instructional Technology CONTACT: [email protected] Typical
So, What Exactly is Risk Management?
So, What Exactly is Risk Management? By Paul Wielgus, Managing Director, GDS Associates, Inc. Buyers, sellers, and others in the energy business need to understand the risks in this very uncertain environment
Corporate risk register
EXECUTIVE BOARD EB133/10 133rd Session 17 May 2013 Provisional agenda item 7.3 Corporate risk register Organization-wide strategic risk management in WHO Report by the Secretariat 1. This report is submitted
PART B INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS (ICAAP)
Framework (Basel II) Internal Capital Adequacy Assessment PART A OVERVIEW...2 1. Introduction...2 2. Applicability...3 3. Legal Provision...3 4. Effective Date of Implementation...3 5. Level of Application...3
ISO, CMMI and PMBOK Risk Management: a Comparative Analysis
ISO, CMMI and PMBOK Risk Management: a Comparative Analysis Cristine Martins Gomes de Gusmão Federal University of Pernambuco / Informatics Center Hermano Perrelli de Moura Federal University of Pernambuco
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Forecasting cash flow expenditure at pre-tender stage: Case studies in New Zealand construction projects
Forecasting cash flow expenditure at pre-tender stage: Case studies in New Zealand construction projects Andrew Heaps School of Engineering and Advanced Technology, Massey University [email protected]
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL Jan, Shu-Hui Ph.D. Student Construction Engineering & Management Program Department of Civil Engineering National Taiwan University
Risk Review Process Basics
2011 PMOC Annual Meeting FEDERAL TRANSIT ADMINISTRATION Risk Review Process Basics Michael P. Wetherell, PE - Urban Engineers David N. Sillars, PE Sillars Consulting FEDERAL TRANSIT ADMINISTRATION 2011
EST.491. Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies
EST.491 Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies Nicolas Alexander Hall and Sarah Delille, PE ABSTRACT Usually, when a company has a history of successfully planning
Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419
Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419 ABSTRACT David T. Hulett, Ph.D., Hulett & Associates, LLC Michael R. Nosbisch, CCC PSP, Project Time and Cost, Inc. This
THE MAJOR UNCERTAINTY FACTORS AFFECTING IN SOFTWARE COST ESTIMATION
THE MAJOR UNCERTAINTY FACTORS AFFECTING IN SOFTWARE COST ESTIMATION G. Rajkumar 1, Dr.K.Alagarsamy 2 1 Assistant Professor, N.M.S.S.Vellaichamy Nadar College, Madurai, India. 2 Associate Professor, Computer
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.
Project Management in Marketing Senior Examiner Assessment Report March 2013
Professional Diploma in Marketing Project Management in Marketing Senior Examiner Assessment Report March 2013 The Chartered Institute of Marketing 2013 Contents This report contains the following information:
Integrated Risk Management As A Framework For Organisational Success. Abstract
Integrated Risk Management As A Framework For Organisational Success Dr David Hillson PMP FAPM FIRM MCMI Director, Risk Doctor & Partners [email protected], www.risk-doctor.com Abstract Risk management
CCPM: TOC Based Project Management Technique
CCPM: TOC Based Project Management Technique Prof. P.M. Chawan, Ganesh P. Gaikwad, Prashant S. Gosavi M. Tech, Computer Engineering, VJTI, Mumbai. Abstract In this paper, we are presenting the drawbacks
Managing Overall Project Risk. Abstract
Managing Overall Project Risk Dr David Hillson, PMI Fellow, PMP, HonFAPM, FRSA, FIRM, FCMI, CMgr, MIOD The Risk Doctor Partnership, [email protected] Abstract Leading project risk management guidelines
Project Management. Synopsis. 1. Introduction. Learning Objectives. Sections. Learning Summary
Synopsis Project Management 1. Introduction By the time you have completed Module 1 you should understand: what is meant by a project; the concept of project management; how project management can be structured
CFSD 21 ST CENTURY SKILL RUBRIC CRITICAL & CREATIVE THINKING
Critical and creative thinking (higher order thinking) refer to a set of cognitive skills or strategies that increases the probability of a desired outcome. In an information- rich society, the quality
Sri Lanka Accounting Standard -LKAS 11. Construction Contracts
Sri Lanka Accounting Standard -LKAS 11 Construction Contracts -405- Sri Lanka Accounting Standard -LKAS 11 Construction Contracts Sri Lanka Accounting Standard LKAS 11 Construction Contracts is set out
PROJECT RISK MANAGEMENT IN THE QUEENSLAND ENGINEERING CONSTRUCTION INDUSTRY: A SURVEY
Lyons, Terry and Skitmore, Martin (2004) Project risk management in the Queensland engineering construction industry: a survey. International Journal of Project Management 22(1):pp. 51-61. Copyright 2004
THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)
PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities
Project Management Frequently Asked Questions:
Project Management Frequently Asked Questions: Risk Management Version:1.4, November 2008 Inter Agency Policy and Projects Unit Department of Premier and Cabinet What are the benefits of risk management?
NSW Government ICT Benefits Realisation and Project Management Guidance
NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control
Transportation Risk Management: International Practices for Program Development and Project Delivery
Transportation Risk Management: International Practices for Program Development and Project Delivery Sponsored by: In cooperation with: American Association of State Highway and Transportation Officials
Procurement Strategy and Contract Selection
GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works
Project Management. [Student s Name] [Name of Institution]
1 Paper: Assignment Style: Harvard Pages: 10 Sources: 7 Level: Master Project Management [Student s Name] [Name of Institution] 2 Project Management Introduction The project management also known as management
EARNED VALUE ANALYSIS IN THE CONTROL OF PROJECTS: SUCCESS OR FAILURE?
EARNED VALUE ANALYSIS IN THE CONTROL OF PROJECTS: SUCCESS OR FAILURE? Ricardo Viana Vargas, MSc, IPMA-B, PMP Professor Getulio Vargas Foundation (FGV) Brazil Professor Fundação Instituto de Administração
Palisade Risk Conference, 2014
Advanced Risk Management to Improve Cost and Schedule Performance on EPC Projects Risk-Management Best Practices from Nuclear Experience Palisade Risk Conference, 2014 Sola Talabi PhD MBA MSc BSc RMP Project
Integrated Resource Plan
Integrated Resource Plan March 19, 2004 PREPARED FOR KAUA I ISLAND UTILITY COOPERATIVE LCG Consulting 4962 El Camino Real, Suite 112 Los Altos, CA 94022 650-962-9670 1 IRP 1 ELECTRIC LOAD FORECASTING 1.1
Project Evaluation Guidelines
Project Evaluation Guidelines Queensland Treasury February 1997 For further information, please contact: Budget Division Queensland Treasury Executive Building 100 George Street Brisbane Qld 4000 or telephone
Risk Management Policy and Process Guide
Risk Management Policy and Process Guide Status: pending Next review date: December 2015 Page 1 Information Reader Box Directorate Medical Nursing Patients & Information Commissioning Operations (including
The real success factors on projects
International Journal of Project Management 20 (2002) 185 190 www.elsevier.com/locate/ijproman The real success factors on projects Terry Cooke-Davies Human Systems Limited, 4 West Cliff Gardens, Folkestone,
Risk Assessment Worksheet and Management Plan
Customer/Project Name: The Basics There are four steps to assessing and managing risks, and effective risk management requires all four of them. 1. Identify the risks 2. Qualify the risks a. Assess each
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
Project Decision Analysis Process
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
RISK MANAGEMENT STRATEGY AND FRAMEWORK
Uniting Church in Australia Synod of Victoria and Tasmania RISK MANAGEMENT STRATEGY AND FRAMEWORK Prepared by: Synod Risk Management Committee Date Prepared and Issued: February 2010 S:\AdminFinance\EDAF\Risk
How To Account For Construction Contracts In Hong Kong Kongsong Accounting Standard 11
HKAS 11 Issued October 2004Revised March 2010 Hong Kong Accounting Standard 11 Construction Contracts COPYRIGHT Copyright 2011 Hong Kong Institute of Certified Public Accountants This Hong Kong Financial
RISK MANAGEMENT REPORT (for the Financial Year Ended 31 March 2012)
RISK MANAGEMENT REPORT (for the Financial Year Ended 31 March 2012) Integrated Risk Management Framework The Group s Integrated Risk Management Framework (IRMF) sets the fundamental elements to manage
Will Shs 1.5 trillion be well managed? Findings from the performance audit of road works
Will Shs.5 trillion be well managed? Findings from the performance audit of road works. Introduction Poor transport networks are a huge obstacle to economic growth in Tanzania. To address this, significant
Modeling Sewer Pipe Deterioration for Risk Based Planning using a Markov Chain Model. Christopher Pawlowski Shawn Loew
Modeling Sewer Pipe Deterioration for Risk Based Planning using a Markov Chain Model Christopher Pawlowski Shawn Loew August 27, 2014 Asset Management Using Risk Based Planning Limited Funds Unlimited
MATERIAL PURCHASING MANAGEMENT IN DISTRIBUTION NETWORK BUSINESS
MATERIAL PURCHASING MANAGEMENT IN DISTRIBUTION NETWORK BUSINESS Turkka Kalliorinne Finland [email protected] ABSTRACT This paper is based on the Master of Science Thesis made in first half of
STRATEGIC CAPACITY PLANNING USING STOCK CONTROL MODEL
Session 6. Applications of Mathematical Methods to Logistics and Business Proceedings of the 9th International Conference Reliability and Statistics in Transportation and Communication (RelStat 09), 21
Construction Contracts
STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 11 Construction Contracts This version of SB-FRS 11 does not include amendments that are effective for annual periods beginning after 1 January 2015.
Use a Risk Breakdown Structure (RBS) to Understand Your Risks
Use a Risk Breakdown Structure (RBS) to Understand Your Risks David Hillson, PhD, PMP, FAPM, MIRM, MCMI, Director of Consultancy, Management Professional Solutions Limited Introducing the Risk Breakdown
Who should submit the application
Operational risk: Application to use an Advanced Measurement Approach February 2007 1 Contents This document contains Finansinspektionen s requirements regarding the content and structure of an application
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
Challenger Guaranteed Income Fund (For IDPS investors)
Guaranteed Income Fund (For IDPS investors) Product Disclosure Statement (PDS) Dated 27 April 2012 Challenger (ARSN 139 607 122) Responsible Entity Challenger Retirement and Investment Services Limited
Audit Sampling. HKSA 530 Issued July 2009; revised July 2010
HKSA 530 Issued July 2009; revised July 2010 Effective for audits of financial statements for periods beginning on or after 15 December 2009 Hong Kong Standard on Auditing 530 Audit Sampling COPYRIGHT
An Oracle White Paper June 2009. The Benefits of Risk Assessment for Projects, Portfolios, and Businesses
An Oracle White Paper June 2009 The Benefits of Risk Assessment for Projects, Portfolios, and Businesses Executive Overview... 1 Introduction... 1 Why Do Projects Fail?... 3 The Effects of Optimism and
1.20 Appendix A Generic Risk Management Process and Tasks
1.20 Appendix A Generic Risk Management Process and Tasks The Project Manager shall undertake the following generic tasks during each stage of Project Development: A. Define the project context B. Identify