THE MAJOR UNCERTAINTY FACTORS AFFECTING IN SOFTWARE COST ESTIMATION
|
|
|
- Josephine Neal
- 10 years ago
- Views:
Transcription
1 THE MAJOR UNCERTAINTY FACTORS AFFECTING IN SOFTWARE COST ESTIMATION G. Rajkumar 1, Dr.K.Alagarsamy 2 1 Assistant Professor, N.M.S.S.Vellaichamy Nadar College, Madurai, India. 2 Associate Professor, Computer Centre, Madurai Kamaraj University, Madurai, India. ABSTRACT The majority of uncertainty factors that caused major problems were operational in the sense that they invoked problems that are normally within the responsibility of the Software Project Management. Each project will have a different capacity for uncertainty. This is a measure of how much uncertainty the project can tolerate. Accurate software cost and schedule estimations are essential especially for large software projects. However, once the required efforts have been estimated, little is done to recalibrate and reduce the uncertainty of the initial estimates. Uncertainties in estimates of resource requirements for future systems arise from many sources. One of the top reasons for the failures is inadequate or inconsistent application of proven project Uncertainty methods. All projects have some uncertainties. Most practitioners agree that improved estimation practices and processes have changed the uncertainty scale. This paper reviews the numbers of Uncertainty factors involved in the software cost estimation, which interact with each other. Keywords: Software Project Management, Uncertainty Factors, Managing Uncertainty. INTRODUCTION The accuracy of cost estimation result is important in any software development project. The crucial question in software development project is how to complete a project in specific time, budget and resources. A major part of the failure can be due to a lack of understanding of the software development process and the effect of that method used in the project plan, schedule and cost estimates. Organizations and individuals have studied a number of projects that have both succeeded and failed and some common factors emerge. Major projects by nature are usually more complex and contain more risk elements than other projects. Careful attention must be provided when preparing cost estimates for major projects. Costs should be determined for uncertainties within an estimate. All elements of the project must be reduced to a cost that can be accounted and budgeted. There should be a disciplined and comprehensive method of assessing and reassessing project risk and uncertainty. Most importantly, however all estimates have uncertainty. This paper discusses on Uncertainty factors in software development project. SOURCE OF UNCERTAINTY Uncertainty is the indefiniteness or variance of an event. The [1] Major sources of uncertainty in cost analysis of future system and force structure proposals may be classified in various ways. The variations arise for number of reasons. All projects have some uncertainties. For example Differences in Individual cost analysts, Errors in Cost estimating relationships, Errors in basic data and so on. THE MOST COMMON REASONS FOR PROJECT UNCERTAINTY The following list has been inspired by actual mistakes encountered in real-world systems projects. 1. MANAGEMENT 419
2 G Rajkumar et al, Int.J.Computer Technology & Applications,Vol 4 (3), objectives, while planning is the detailed formulation of the projects strategy in time, cost, quality, and quantity. The design provides an account of the project in its entirely, while the plan is largely limited to the operational perspective. Uncertainty factors related to the design of projects. The problems related to inappropriate components had to do with lack of training, maintenance, too sophisticated or ambitious components, etc. In this section we consider what might be done to develop a management uncertainty approach which encompasses all forms of project related uncertainty. Top management commitment is the factor that determines the tipping point between potential success and failure when developing and implementing business continuity management projects and systems. The term 'uncertainty management' [2]it implies more than just a combined consideration of threats and opportunities. Rather, the term implies a more fundamental purpose of exploring and understanding the origins of project uncertainty before seeking to manage it, with no preconceptions about what is desirable or undesirable. Key concerns are understanding where and why uncertainty is important in a given project context, and where it is not. The Management Problem occurs in all the stages of the Software 3. COMMUNICATION The communication problems [5] are a major factor in the delay and failure of software projects. Requirements descriptions are necessarily uncertain. The specification documentation may be so large that no member of the software team has read it all. In this situation, Uncertainty Factors 2% MANAGEMENT 11% 23% PROJECT DESIGN COMMUNICATION 9% STAFF EXPERIENCE 2% FUNDING PROBLEMS USER S RESPONSE 14% PRICE CHANGES 21% TECHNICAL FACTORS 5% 7% 6% development project. 2. PROJECT DESIGN Design is associated with the conceptual framework [3] that constitutes the project and establishes its main characteristics and RESOURCES OTHERS misunderstandings and conflicting views are rife. Software projects suffer serious breakdowns in co-ordination and communication throughout their development life cycle. We present some of the causes for the breakdown of communication during the requirements engineering phase of software 420
3 development projects. The communication attributes [6] provide information about whether the matter of concern should and has been communicated between the sender and the receiver. In software development, coordination and communication within and across organizational boundaries throughout the software development cycle are acknowledged as critical factors for success, especially when software is developed on a large scale. 4. STAFF EXPERIENCE Staff weaknesses had to do with qualifications of staff, the experience of expatriate personnel, lack of commitment, turn-over of qualified staff, etc. Planning and preparation had to do with the availability and quality of detailed plans of operation. [4] The projecting company had experience with the solution of similar problems. The project team did not experience any significant personnel losses or transfer during the project s development. 5. FUNDING PROBLEMS Delay is one of the [7] most serious problems in the completion of a project. Delay is common in projects and its extent varies considerably from project to project. Some projects are only a few days behind schedule; some are delayed by over a year. Thus, delay is costly for both owner and contractor. To the owner, a delay means loss of potential revenue; a delay means increased costs in overhead. The Financial issues are Payment issues, Cash flow issues, financial resource issues and Market issues. Financial-related delays are mainly due to poor cash flow management, followed by late payment, insufficient financial resources, and financial market instability. 6. USER RESPONSES Computer users have rapidly increased in both number and diversity. They [8] include managers, accountants, engineers, home makers, teachers, scientists, health care workers, insurance adjusters, salesmen, and administrative assistants. Many of these people work on tasks that rapidly vary on a yearly, monthly, or even daily basis. End users usually do not have training in professionals' programming languages, formal development processes, or modeling and diagramming notations. Moreover, end users often lack the time or motivation to learn these traditional techniques, since end users usually write code in order to achieve a short or medium-term goal rather than to create a durable software asset that will produce a continuing revenue stream. Consequently, supporting End user requires providing appropriate tools, social structures, and development processes that are highly usable, quickly learned, and easily integrated into domain practice. 7. RESOURCES One must seek to optimize the [9] knowledge and experience gain from the information gathered (its relevance, accuracy and suitability), in relation to the investments made to gather it (the time and money spent). The following describes various methods of gathering data and information. The reasonably priced and straight-forward ones should be preferred. In cases where the more complex and expensive methods must be used, one should evaluate critically which one(s) will be most appropriate. The approach taken by an external organization which is just starting up work in a new partner country will naturally differ from that of a local organization which is already established and in operation. Sources of information are survey reports, Government Official, 421
4 UNCERTAINTY UNCERTAINTY IN DIFFERENT S S NGO Personal, Community members, etc., 8. PRICE CHANGES Pricing [11] must take into account broader organizational, economic, political and business considerations, such as Market opportunity, Financial Health, Requirements etc., Therefore, there may not be a simple relationship between the price to the customer for the software and the development costs. Because of the organizational considerations involved, project pricing should involve senior management, as well as software project managers. 9. TECHNICAL FACTORS The task was technically demanding. Under most circumstances regulatory cost estimates ignore the possibility of technological progress. As noted, regulators often have an obligation to identify a means for firms to meet the regulation, a requirement that seemingly precludes the projection or extrapolation of future costs or the expectation of cost declines. Technical change is, after all, notoriously difficult to predict; all we can say with some confidence, based on historical experience, is that the cost of compliance will decline, but we cannot say at what rate. Special consideration is given to soft or human-related factors in software engineering that are often not analyzed with equal detail as more technical factors. Choosing the right proper tool is important in cost estimation process. The right proper tool produce an accurate results. The traditional common tool used in estimating the cost is spreadsheet or Microsoft Excel and Microsoft Project. The biggest challenge in using the traditional method is the level of accuracy. Software development communities faced difficulty to achieve high accuracy in producing cost estimation result. Therefore, many studies have been done to develop automated tool for cost estimation process. However, no one claimed their proposed tool can produce accurate result. HOW TO MANAGE UNCERTAINTY? Uncertainty has no independent existence; it is not an object which can be identified, trapped and eliminated like a virus invading the living organism of our project. Uncertainty [12] naturally arises out of complex situations and is therefore an integral part of most projects. Each project will have a different capacity for uncertainty. This is a measure of how much uncertainty the project can tolerate. High risk projects, that is, typically novel projects which are pursuing ambitious goals where it is accepted that the 422
5 likelihood of failure is high, will have a high capacity for uncertainty. The usual response of industry to these challenges is to manage uncertainty using a framework in the figure 1. RECOGNIZE ANALYSE MINIMIZE RECTIFY uncertainty and how they become overlapped in time and iterated across. Each step has an overlap with the next and may require individuals to return to previous steps to make updates or to consider new uncertainties that had not been previously identified. EMPIRICAL RESULTS Hypothesis Statement: To reduce the cost challenges in cost estimation over uncertainty factors that arises in the project and program planning. If arises, how to manage uncertainty factors in software cost estimation. To evaluate or prove the Hypothesis statement CHI-SQUARE Testing is implemented. The chi-square formula used on these data is = (O - E) 2 /E Where, O is the Observed Frequency in each category E is the Expected Frequency in the corresponding category Figure 1 Managing Uncertainty df is the "degree of freedom" (n-1) The usual response of industry to these [13] challenges is to manage uncertainty using a framework in the above figure. The figure illustrates flow of the activities within the cost estimation managing CAUSES / S REQUIRE MENT ANALYS IS is Chi Square Uncertainty Matrix is framed phases over uncertainty factors matrix entries are defined as, DESIG N PHAS E IMPLEM ENTATIO N TESTIN G MAINT ENANC E MANAGEMENT PROJECT DESIGN COMMUNICATION STAFF EXPERIENCE FUNDING PROBLEMS USER S RESPONSE RESOURCES PRICE CHANGES TECHNICAL UNCERTAINTY MATRIX FACTORS OTHERS 1 423
6 1 If the uncertainty factor occur in the phase. 0 If the Uncertainty factor does not occur in the phase. X table value (45) = Actual value of Uncertainty Matrix is Thus the hypothesis statement is proved. CONCLUSION They have been several issues raised regarding uncertainty. It is proposed that a formal definition and methodology is required to improve the integrity of future projects. Clear distinction between uncertainty and process complexity must be made to reduce the level of project complexity and lack of understanding. A method to identify uncertainties in a simpler fashion that will allow those with little experience to complete the tasks in the time allocated without too much involvement form experienced staff members. This paper review the numbers of Uncertainty factors are involved in the software cost estimation and some of which interact with each other. By managing uncertainty we can recognize the problems in causes then it can be analysed. The analysed problem should be minimized and rectified. REFERENCES [1] Paul.F.Dienemann, Estimating Cost Uncertainty Using Monte Carlo Techniques, The RAND Corporation. [2] Stephen Ward and Chris Chapman, Project Uncertainty Management as A Desirable Future, School of Management, University of Southampton, Highfield, Southampton SO17 1BJ. [3] Knut Samset, Project management in a high uncertainty Situation, Norwegian University of Science and Technology. [4] Dov Dvir, Thomas Lechler, Plans are nothing, changing plans is everything: the impact of changes on project success. [5] Amer Al-Rawas and Steve Easterbrook, Communication Problems in Requirements Engineering: A Field Study. [6] Joakim Pernstal, Robert Feldt, Tony Gorschek and Dan Floren, Communications Problems in Software Development A Model and its Industrial Application. [7] Hamzah Abdul-Rahman, Chen Wang, Roshana Takim and Szemin Wong, Project Schedule influenced by Financial Issues: Evidence in construction Industry. [8] Margaret M.Burnett and Christopher Scaffidi, End-User Development. [9] Dr.Anne Touwen, Hand Book for Projects: Development Management and Fundraising. [10] Winston Harrington, Richard D.Morgenstern and Peter Nelson.On the Accuracy of Regulatory Cost Estimates. [11] Sommerville, Software Engineering, Seventh Edition, Low Price Edition. [12] David Cleden and Gower, Managing Project Uncertainty Uncertainty in Project and Programme Plans. [13] Erkoyuncu J.A, Roy. R, Shehab.E, Wardle.P, Uncertainty challenges in service cost estimation for product service systems in the aerospace and defence industries 424
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
Better decision making under uncertain conditions using Monte Carlo Simulation
IBM Software Business Analytics IBM SPSS Statistics Better decision making under uncertain conditions using Monte Carlo Simulation Monte Carlo simulation and risk analysis techniques in IBM SPSS Statistics
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
Impact of Uncertainty Factors in Cost Estimation Substantiation through Normal Distribution Curve
G. Rajkumar et al, International Journal of Computer Science and Mobile Computing Vol. Issue. 9, September- 13, pg. 139-15 Available Online at www.ijcsmc.com International Journal of Computer Science and
Assessing the Appropriate Level of Project, Program, and PMO Structure
PMI Virtual Library 2011 Daniel D. Magruder Assessing the Appropriate Level of Project, Program, and PMO Structure By Daniel D. Magruder, PMP Executive Summary Does your organization have in-flight projects
PUBLIC ACCOUNTANTS COUNCIL HANDBOOK
PUBLIC ACCOUNTANTS COUNCIL HANDBOOK Adopted by the Public Accountants Council for the Province of Ontario: April 17, 2006 PART I: PROFESSIONAL COMPETENCY REQUIREMENTS FOR PUBLIC ACCOUNTING PART II: PRACTICAL
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
Lowering business costs: Mitigating risk in the software delivery lifecycle
August 2009 Lowering business costs: Mitigating risk in the software delivery Roberto Argento IBM Rational Business Development Executive Valerie Hamilton IBM Rational Solution Marketing Manager and Certified
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview Sante Torino PMI-RMP, IPMA Level B Head of Risk Management Major Programmes, Selex ES / Land&Naval Systems Division
Project Management Process
Project Management Process Description... 1 STAGE/STEP/TASK SUMMARY LIST... 2 Project Initiation 2 Project Control 4 Project Closure 5 Project Initiation... 7 Step 01: Project Kick Off 10 Step 02: Project
META DATA QUALITY CONTROL ARCHITECTURE IN DATA WAREHOUSING
META DATA QUALITY CONTROL ARCHITECTURE IN DATA WAREHOUSING Ramesh Babu Palepu 1, Dr K V Sambasiva Rao 2 Dept of IT, Amrita Sai Institute of Science & Technology 1 MVR College of Engineering 2 [email protected]
pm4dev, 2007 management for development series Introduction to Project Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2007 management for development series Introduction to Project Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage
Metadata-Based Project Management System. A Case Study at M-Files Corporation. Iulia Adomnita
Metadata-Based Project Management System. A Case Study at M-Files Corporation Iulia Adomnita University of Tampere School of Information Sciences Computer Science M.Sc. Thesis Supervisors: Timo Poranen,
PROJECT RISK ANALYSIS AND MANAGEMENT
PROJECT RISK ANALYSIS AND MANAGEMENT A GUIDE BY THE ASSOCIATION FOR PROJECT MANAGEMENT (formerly The Association Of Project Managers) Compiled from information provided by members of the Special Interest
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
The State of Data Security Intelligence. Sponsored by Informatica. Independently conducted by Ponemon Institute LLC Publication Date: April 2015
The State of Data Security Intelligence Sponsored by Informatica Independently conducted by Ponemon Institute LLC Publication Date: April 2015 Ponemon Institute Research Report The State of Data Security
RECRUITERS PRIORITIES IN PLACING MBA FRESHER: AN EMPIRICAL ANALYSIS
RECRUITERS PRIORITIES IN PLACING MBA FRESHER: AN EMPIRICAL ANALYSIS Miss Sangeeta Mohanty Assistant Professor, Academy of Business Administration, Angaragadia, Balasore, Orissa, India ABSTRACT Recruitment
Effective Software Verification for Medical Devices
STERLINGTECH AND KLOCWORK WHITE PAPER NOVEMBER 2009 Effective Software Verification for Medical Devices Achieving compliance and meeting productivity goals with static analysis In addition to producing
Access Governance. Delivering value. What you gain. Putting a project back on track for success
What you gain Risk-managed access Having a second line of defence to identify what needs to be controlled and who owns it lowers your operational costs, while taking a risk-based approach ensures greater
OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.
OTC 12979 Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. Copyright 2001, Offshore Technology Conference This paper was prepared for
University of Huddersfield Repository
University of Huddersfield Repository Hajjaji, Mufeed, Denton, Paul and Jackson, Steve The effectiveness of using project management tools and techniques for delivering projects Original Citation Hajjaji,
Checklist for Operational Risk Management
Checklist for Operational Risk Management I. Development and Establishment of Comprehensive Operational Risk Management System by Management Checkpoints - Operational risk is the risk of loss resulting
FUNBIO PROJECT RISK MANAGEMENT GUIDELINES
FUNBIO PROJECT RISK MANAGEMENT GUIDELINES OP-09/2013 Responsible Unit: PMO Focal Point OBJECTIVE: This Operational Procedures presents the guidelines for the risk assessment and allocation process in projects.
PERFORMANCE-BASED BUDGETING METHODOLOGY AND TOOLS
LEARN HOW TO LINK YOUR BUDGET DECISIONS WITH STRATEGIC OUTCOMES In this time of economic instability, citizens want real-time updates on the financial decisions and budget allocations made by their local
A STUDY OF DATA MINING ACTIVITIES FOR MARKET RESEARCH
205 A STUDY OF DATA MINING ACTIVITIES FOR MARKET RESEARCH ABSTRACT MR. HEMANT KUMAR*; DR. SARMISTHA SARMA** *Assistant Professor, Department of Information Technology (IT), Institute of Innovation in Technology
Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson
Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced
Errors in Operational Spreadsheets: A Review of the State of the Art
Errors in Operational Spreadsheets: A Review of the State of the Art Stephen G. Powell Tuck School of Business Dartmouth College [email protected] Kenneth R. Baker Tuck School of Business Dartmouth College
Position Paper for Cognition and Collaboration Workshop: Analyzing Distributed Community Practices for Design
Position Paper for Cognition and Collaboration Workshop: Analyzing Distributed Community Practices for Design Jean Scholtz, Michelle Steves, and Emile Morse National Institute of Standards and Technology
Know Your Enemy: Software Risk Management 1
Know Your Enemy: Software Risk Management 1 Karl E. Wiegers Process Impact 716-377-5110 www.processimpact.com Software engineers are eternal optimists. When planning software projects, we often assume
The Psychology Foundation of Australia (Incorporated in NSW) www.psychologyfoundation.org.au. 26 February 2007
The Psychology Foundation of Australia (Incorporated in NSW) www.psychologyfoundation.org.au President: Prof David Badcock School of Psychology The University of Western Australia 08 6488 3243 [email protected]
INDECO Management Solutions
INDECO Management Solutions Learning to manage projects as though they mattered: implementing strategy, adding value, and delivering benefits through project management Peter W.G. Morris Professor of Construction
Merrill Lynch & Co. Process Risk Management Program
Merrill Lynch & Co. Process Risk Management Program The Process Risk Management function at Merrill Lynch is focused upon motivating two key management practices Learning from mistakes; and Assessing the
INTERNATIONAL STANDARDS FOR THE PROFESSIONAL PRACTICE OF INTERNAL AUDITING (STANDARDS)
INTERNATIONAL STANDARDS FOR THE PROFESSIONAL PRACTICE OF INTERNAL AUDITING (STANDARDS) Introduction to the International Standards Internal auditing is conducted in diverse legal and cultural environments;
Developing and Implementing a Strategy for Technology Deployment
TechTrends Developing and Implementing a Strategy for Technology Deployment Successfully deploying information technology requires executive-level support, a structured decision-making process, and a strategy
Risk Management Primer
Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.
Hand IN Hand: Balanced Scorecards
ANNUAL CONFERENCE T O P I C Risk Management WORKING Hand IN Hand: Balanced Scorecards AND Enterprise Risk Management B Y M ARK B EASLEY, CPA; A L C HEN; K AREN N UNEZ, CMA; AND L ORRAINE W RIGHT Recent
TenStep Project Management Process Summary
TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
DESCRIPTION OF COURSES
DESCRIPTION OF COURSES MGT600 Management, Organizational Policy and Practices The purpose of the course is to enable the students to understand and analyze the management and organizational processes and
A Characterization Taxonomy for Integrated Management of Modeling and Simulation Tools
A Characterization Taxonomy for Integrated Management of Modeling and Simulation Tools Bobby Hartway AEgis Technologies Group 631 Discovery Drive Huntsville, AL 35806 256-922-0802 [email protected]
PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)
TABLE OF CONTENTS Page 1 of 18 PURPOSE 2 SCOPE 2 DEFINITION 2 ORGANIZATION AND RESPONSIBILITIES 2 Organization and Function 2 Integration of Control Functions 5 7 Introduction 7 Planning and Scheduling
Job Description. Job title Database Administrator: Microsoft SQL. Department Support and Overheads: Information Technology and Systems
Job Description Job title Database Administrator: Microsoft SQL Department Support and Overheads: Information Technology and Systems Reporting structures DIRECTLY 1ST LEVEL Senior Specialist: Application
Spreadsheet Modelling Best Practice
Spreadsheet Modelling Best Practice by Nick Read and Jonathan Batson BUSINESS DYNAMICS April 1999 This document has been published by the Institute of Chartered Accountants for England and Wales who jointly
Understanding the Entity and Its Environment and Assessing the Risks of Material Misstatement
Understanding the Entity and Its Environment 1667 AU Section 314 Understanding the Entity and Its Environment and Assessing the Risks of Material Misstatement (Supersedes SAS No. 55.) Source: SAS No. 109.
10 Best Practices in Printer Fleet Management
10 Best Practices in Printer Fleet Management Corporations recognize that they need to address out of control costs associated with network printing. How do they get there? Many are looking to solve it
Issues in Information Systems
TAXONOMY OF MULTIPLE LEVELS OF SWOT ANALYSIS IN PROJECT MANAGEMENT Ganesh Vaidyanathan, Indiana University South Bend, [email protected] Asghar Sabbaghi, Indiana University South Bend, [email protected]
The likelihood that students will
Rethinking College Readiness High schools need to graduate greater numbers of young people prepared for college and careers. But how should readiness be defined? DAVID T. CONLEY The likelihood that students
Project Management Using Microsoft Project Plan - Basic
Project Management Using Microsoft Project Plan Basic V2.0 Project Management Using Microsoft Project Plan - Basic Version 2.0, February, 2011 Illume-Tech Solutions & Services COPYRIGHT 2011 ILLUME-TECH
An Approach to Proactive Risk Classification
An Approach to Proactive Risk Classification M.S. Rojabanu 1, Dr. K. Alagarsamy 2 1 Research Scholar, Madurai Kamaraj Universtiy, Madurai,India. 2 Associate Professor, Computer Centre, Madurai Kamaraj
Profit Forecast Model Using Monte Carlo Simulation in Excel
Profit Forecast Model Using Monte Carlo Simulation in Excel Petru BALOGH Pompiliu GOLEA Valentin INCEU Dimitrie Cantemir Christian University Abstract Profit forecast is very important for any company.
Bidirectional Tracing of Requirements in Embedded Software Development
Bidirectional Tracing of Requirements in Embedded Software Development Barbara Draxler Fachbereich Informatik Universität Salzburg Abstract Nowadays, the increased complexity of embedded systems applications
Monte Carlo analysis used for Contingency estimating.
Monte Carlo analysis used for Contingency estimating. Author s identification number: Date of authorship: July 24, 2007 Page: 1 of 15 TABLE OF CONTENTS: LIST OF TABLES:...3 LIST OF FIGURES:...3 ABSTRACT:...4
Project management. Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 1
Project management Ian Sommerville 2004 Software Engineering, 7th edition. Chapter 5 Slide 1 Objectives To explain the main tasks undertaken by project managers To introduce software project management
Risk Management (3C05/D22) Unit 3: Risk Management. What is risk?
Risk Management (3C05/D22) Unit 3: Risk Management Objectives To explain the concept of risk & to develop its role within the software development process To introduce the use of risk management as a means
Northwestern Michigan College Supervisor: Employee: Department: Office of Research, Planning and Effectiveness
General Information Company: Northwestern Michigan College Supervisor: Employee: Department: Office of Research, Planning and Effectiveness Employee No: Detail Job Title: Coordinator of Data Reporting
A Study On Factors Influencing Construction Contract Claim Management
A Study On Factors Influencing Construction Contract Claim Management K.Sundhar #1, N.Nandhini #2 #1 PG Student (M.E Construction Engineering and Management), #2 Assistant Professor ( Department of civil
Project Management Manual Update 2006. Transportation Department City of Edmonton
Project Management Manual Update 2006 Transportation Department City of Edmonton Project Management Manual for Transportation Projects EXECUTIVE SUMMARY This document has been updated to fulfill the requirements
Specialists in Strategic, Enterprise and Project Risk Management. PROJECT RISK MANAGEMENT METHODS Dr Stephen Grey, Associate Director
BROADLEAF CAPITAL INTERNATIONAL PTY LTD ACN 054 021 117 23 Bettowynd Road Tel: +61 2 9488 8477 Pymble Mobile: +61 419 433 184 NSW 2073 Fax: + 61 2 9488 9685 Australia www.broadleaf.com.au [email protected]
A Case Study in Software Enhancements as Six Sigma Process Improvements: Simulating Productivity Savings
A Case Study in Software Enhancements as Six Sigma Process Improvements: Simulating Productivity Savings Dan Houston, Ph.D. Automation and Control Solutions Honeywell, Inc. [email protected] Abstract
Impact of Supply Chains Agility on Customer Satisfaction
2010 International Conference on E-business, Management and Economics IPEDR vol.3 (2011) (2011) IACSIT Press, Hong Kong Impact of Supply Chains Agility on Customer Satisfaction Dr. Akhilesh Barve Assistant
Elite: A New Component-Based Software Development Model
Elite: A New Component-Based Software Development Model Lata Nautiyal Umesh Kumar Tiwari Sushil Chandra Dimri Shivani Bahuguna Assistant Professor- Assistant Professor- Professor- Assistant Professor-
Business Statistics. Successful completion of Introductory and/or Intermediate Algebra courses is recommended before taking Business Statistics.
Business Course Text Bowerman, Bruce L., Richard T. O'Connell, J. B. Orris, and Dawn C. Porter. Essentials of Business, 2nd edition, McGraw-Hill/Irwin, 2008, ISBN: 978-0-07-331988-9. Required Computing
Project Management. Massimo Felici Room 1402, JCMB, KB 0131 650 5899 [email protected]
Project Management Massimo Felici Room 1402, JCMB, KB 0131 650 5899 [email protected] Project Management Software project management is an essential part of software engineering Concerned with activities
Audit Readiness Lessons Learned
Audit Readiness Lessons Learned Four Tips for Achieving a Smooth Audit It seems obvious: Prepare well and prepare ahead of time and the year-end audit does not have to be the painful experience most organizations
In initial planning phases In monitoring and execution phases
Project management What is it? Project management is a framework for a range of tools for helping plan and implement development and change projects. A range of tools exist, including: Gantt charts (bar
P3M3 Portfolio Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction
CFSD 21 ST CENTURY SKILL RUBRIC CRITICAL & CREATIVE THINKING
Critical and creative thinking (higher order thinking) refer to a set of cognitive skills or strategies that increases the probability of a desired outcome. In an information- rich society, the quality
UNIVERSITY-LEVEL ENTREPRENEURSHIP EDUCATION IN POLAND. Prof. Jerzy Cieslik, Leon Kozminski Academy of Entrepreneurship and Management, Warsaw, Poland
UNIVERSITY-LEVEL ENTREPRENEURSHIP EDUCATION IN POLAND Prof. Jerzy Cieslik, Leon Kozminski Academy of Entrepreneurship and Management, Warsaw, Poland ABSTRACT This paper outlines Polish experiences in fostering
The impact of Discussion Classes on ODL Learners in Basic Statistics Ms S Muchengetwa and Mr R Ssekuma e-mail: [email protected], [email protected].
1 The impact of Discussion Classes on ODL Learners in Basic Statistics Ms S Muchengetwa and Mr R Ssekuma e-mail: [email protected], [email protected] Abstract Open distance learning institutions, like
Software Development Risk Assessment
Software Development Risk Assessment Note: The purpose of this prompt list is to provide project managers with a tool for identifying and planning for potential project risks. It is process-based and supports
How To Develop An Application
What is Application Lifecycle Management? David Chappell Sponsored by Microsoft Corporation Copyright 2014 Chappell & Associates Defining application lifecycle management (ALM) isn t easy. Different people
Risk Mitigation: The X Factor in Contingent Workforce Management
Risk Mitigation: The X Factor in Contingent Workforce Management Perspective Article In this perspective article, Bartech the leading workforce management solutions provider examines the pivotal role of
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage
A Survey on Requirement Analysis in the Nigerian Context
A Survey on Requirement Analysis in the Nigerian Context Olaronke Ganiat Elias 1, Janet Olusola Olaleke 1, Micheal Segun Olajide 1, and Nureni John Ayinla 1 1 Computer Science Department, Adeyemi College
Level 1 Articulated Plan: The plan has established the mission, vision, goals, actions, and key
S e s s i o n 2 S t r a t e g i c M a n a g e m e n t 1 Session 2 1.4 Levels of Strategic Planning After you ve decided that strategic management is the right tool for your organization, clarifying what
GLOBAL FINANCIAL PRIVATE CAPITAL, LLC. Job Description. JOB TITLE: Compliance Director
GLOBAL FINANCIAL PRIVATE CAPITAL, LLC Job Description JOB TITLE: Compliance Director SUMMARY: This position is primarily responsible for serving as the manager and supervisor within the Compliance Department
5 Best Practices for SAP Master Data Governance
5 Best Practices for SAP Master Data Governance By David Loshin President, Knowledge Integrity, Inc. Sponsored by Winshuttle, LLC 2012 Winshuttle, LLC. All rights reserved. 4/12 www.winshuttle.com Introduction
Managerial Decision Making when values take over rational economical thought
Student Self-administered case study Managerial Decision Making when values take over rational economical thought Case duration (Min): 45-60 Principles of Management (PoM) Organizational Behaviour (OB)
Data Quality Assessment. Approach
Approach Prepared By: Sanjay Seth Data Quality Assessment Approach-Review.doc Page 1 of 15 Introduction Data quality is crucial to the success of Business Intelligence initiatives. Unless data in source
Guidelines for the Assessment of Candidates for Norwegian Doctoral Degrees
Guidelines for the Assessment of Candidates for Norwegian Doctoral Degrees Recommended by the Norwegian Association of Higher Education Institutions 23 March 2007. Passed by the Board of NTNU on 13 June
Review of Business Information Systems Second Quarter 2009 Volume 13, Number 2
An Investigation Into Computerized Estimating Software Used In Accounting For Cost Estimates By Residential Builders Mark D. Law, Bloomsburg University, USA Gary S. Robson, Bloomsburg University, USA ABSTRACT
CSC340: Information Systems Analysis and Design. About the Course
CSC340: Information Systems Analysis and Design Professor Jennifer Campbell [email protected] http://www.cs.toronto.edu/~csc340h/ Acknowledgement: Material Provided by Professor Steve Easterbrook
ITCS 430 Introduction to Health Informatics Essay Topic 4
ITCS 430 Introduction to Health Informatics Essay Topic 4 Nurhazman Abdul Aziz (2005) Nurhazman Abdul Aziz (2666192) School of IT & Computer Sciences ITCS 430 Introduction to Health Informatics (Autumn
Admission Criteria Minimum GPA of 3.0 in a Bachelor s degree (or equivalent from an overseas institution) in a quantitative discipline.
Overview Offered by the Mona School of Business in conjunction with the Department of Mathematics, Faculty of Science & Technology, The University of the West Indies. The MSc. ERM degree programme is designed
Software Engineering. Project Management. Based on Software Engineering, 7 th Edition by Ian Sommerville
Software Engineering Project Management Based on Software Engineering, 7 th Edition by Ian Sommerville Objectives To explain the main tasks undertaken by project managers To introduce software project