Project Evaluation Guidelines
|
|
|
- Myrtle Smith
- 10 years ago
- Views:
Transcription
1 Project Evaluation Guidelines Queensland Treasury February 1997 For further information, please contact: Budget Division Queensland Treasury Executive Building 100 George Street Brisbane Qld 4000 or telephone (07)
2 Contents 1. Introduction What is project evaluation? The purpose of project evaluation Which projects should be evaluated? Costs and timing How does project evaluation link to strategic plans and the budget process? The project evaluation process Define the objectives and scope of the project Identify and select suitable options Carry out the project analysis Economic analysis Social analysis Environmental analysis Budget analysis Select the preferred option The project evaluation report Post implementation review Reference material... 20
3 1. Introduction These guidelines outline the rationale, processes and requirements for the evaluation of capital projects in the Queensland Public Sector. Project evaluations of major capital projects are required under the Public Finance Standard for Asset Management (Sect , July 1995), and form part of the procedures associated with the State s Capital Works Program. The guidelines will assist agencies to evaluate project options in a consistent and comprehensive manner, and to prioritise competing projects. At a whole of government level they provide a uniform framework for the evaluation of capital projects in the context of the State strategic planning process. Government Owned Corporations are not subject to these guidelines as their investment evaluation criteria are established by shareholding ministers; commercialised entities within departments would place greater emphasis on financial aspects of the project. These guidelines cover the key principles to be applied in the evaluation of capital projects, but, consistent with these principles, individual agencies are encouraged to develop their own evaluation manuals to address the particular issues and concerns relevant to each organisation. The focus of these guidelines is primarily on what is required for a project evaluation rather than on detailed descriptions of long established techniques, such as cost benefit analysis, for which there is already a wide range of literature available (see references at the end of these guidelines). 1
4 2. What is project evaluation? Project evaluation is a methodology for assessing the economic, social, environmental and financial impact of proposed capital projects. All the impacts associated with a capital project are identified and, where possible, costs and benefits valued in monetary terms, so that the projects selected by government will provide the maximum net benefit to the State. Project evaluation assesses the economic, social, environmental and financial impacts of a project and combines these to provide an overall assessment of the project. Economic analysis assesses the net worth of a project for the economy. It is usually the major element of a project evaluation because it provides a means to rank projects in terms of the efficient allocation of resources. It provides an initial default ranking for projects which may then be modified by analyses of the social, environmental and budgetary issues associated with these projects. For these reasons, economic analysis is discussed in greater detail in these guidelines than the other analyses. Social and environmental analyses assess the effect of the project on social groups, employment, regional development, etc. and on natural ecosystems, pollution, heritage, rare species etc. respectively. They also identify ways to deal with these issues. The extent to which these analyses form part of a project evaluation depends on the importance of these issues for a particular project. The fourth element in project evaluation, budget analysis, provides decision-makers with information on cashflows, borrowings, funding sources, etc. in order to assess the budgetary implications of the project. It is required for all projects which impact on the State Budget. These various analyses are then considered together, the options ranked and a preferred option selected. 2
5 3. The purpose of project evaluation The purposes of project evaluation are to improve the quality of services, to ensure value for money, and to prioritise proposed capital projects. This is achieved through a structured process which makes it possible to: clearly define project objectives, and consider a wide range of options to meet these objectives; link the project to the strategic objectives of the government, the State Capital Works Program and an agency s physical asset strategic plan; carry out economic, social, environmental and budgetary analyses of the project; and identify the net benefit of the project to the community, and the effect on the State Budget. Project evaluations assist departments to make decisions on proposed capital projects. They provide the means to assess the viability of proposed capital projects, and to rank competing projects in the department s annual capital works program. Project evaluations also facilitate deliberations by the Cabinet Budget Committee during the Budget process. They assist in the selection of projects to be included in the State Capital Works Program. 3
6 4. Which projects should be evaluated? All capital projects, including fixed capital expenditure, plant and equipment, and capital grants and subsidies, should be subject to evaluation, commensurate with the level of investment, to provide the necessary information to decision-makers. There are also formal reporting requirements for capital projects greater than $1 million. Under the Public Finance Standard for Asset Management (Section 347), accountable officers are to provide the Treasurer with evaluations of physical asset investments if the investment is estimated to be more than: Under the Public Finance Standards, there are formal reporting requirements for evaluations of capital projects over $1 million. (a) $5 million and is to be funded from the department s capital base; or (b) $1 million and; (i) is to be funded from specific budget funding; or (ii) the Treasurer has asked for the document. All capital projects should be evaluated irrespective of whether they are funded through the State Budget or from other sources (for example, an organisation s own revenues, borrowings, Commonwealth funding etc.). It is the expected value of a project to the community which is being evaluated, not the source of funding. Evaluations should also be undertaken in respect of any substantial capital projects and expenditures for which individual ministers; or organisations may have discretion and can commit without reference to Cabinet. 4
7 5. Costs and timing Costs The resources devoted to an evaluation of a capital project should be commensurate with the value and importance of the project. The resources devoted to each evaluation should be commensurate with the size and importance of expenditure involved. As a major purpose of project evaluation is to improve value for money, the cost of project evaluation must be balanced against the benefits of improved decision making. The resources allocated to a project evaluation should be the minimum necessary to inform decision-makers adequately of the worth and impact of the project. Key clients and stakeholders (e.g. departmental management, Treasury) should be consulted on a periodic basis to ensure the evaluations are relevant to client needs and to avoid unnecessary costs and delays. Timing Early contact should be made with the Budget Division of Treasury, to allow adequate consideration of the project in the Budget process, particularly where the evaluations involve contentious issues or where advice is required on specific issues. In view of the substantial financial implications of the capital works program, it is essential that information on the viability of proposed capital projects is available to Treasury and the Cabinet Budget Committee in the development of the State Budget. Project evaluations for major capital projects, to be funded from a department s capital base and to commence in the next financial year, should be completed by the start of the annual Budget process. The evaluations should be completed sufficiently in advance of the Budget process to allow the necessary time for review. This applies especially where there are contentious issues. Initially, only short-form evaluations are required for new capital initiatives. Projects which the Cabinet Budget Committee determines merit further consideration will require a full evaluation to be undertaken. These will be then considered by the committee later in the Budget process. More detailed information on the Budget process itself is outlined in the Treasury Budget Manual. The Budget Division of Treasury can provide the specific dates for the budget process for a particular year. 5
8 6. How does project evaluation link to strategic plans and the budget process? The evaluation of capital projects is a key element of a department s financial and service delivery planning, and in the development of the State s Capital Works Program. Project evaluations are used to optimise service delivery strategies and resource utilisation within a department, and to do so from a whole of government perspective. Physical asset planning, project evaluation and budgeting are the key elements in determining what assets are needed, which provide the best value for money, and which can and should be funded. Although these three elements have been presented sequentially, they represent an ongoing process which is interlinked and interdependent. For example, the results of project evaluations could be expected to modify both physical asset planning and Budget decisions. Ensuring that these three elements are linked effectively is important in being able to provide the right infrastructure at the right price and at the right time. These linkages are illustrated in diagram 1. To achieve this linkage, service delivery strategies and the assets necessary to support them should be identified in a department s corporate plan and its physical asset strategic plan. Information on this aspect of the process is contained in Treasury s Physical Asset Strategic Planning Guidelines. In line with this overall strategic direction, project proposals are selected and then evaluated in order to prioritise them, and to decide whether to include them in the department s proposed capital program. Proposals are then considered in the Budget context and, based on which proposals are approved, the departmental and the State capital programs are developed. These Project Evaluation Guidelines are designed to assist in the evaluation and prioritisation part of the process. 6
9 Diagram 1 Strategic Planning, Project Evaluation and the Budget Process State Strategic Direction (link to overall government strategic policy and direction) Corporate Strategic Plan (analysis of issues and strategies including major asset strategies) Physical Asset Strategic Plan (analysis of asset issues and strategies including major asset needs) Project Evaluation (scan and preliminary analysis of all options, detailed analyses of selected options, rank and select preferred option) Project Approval (e.g. Cabinet Budget Committee, departmental management) Project Implementation 7
10 7. The project evaluation process The project evaluation process involves the identification of service delivery needs, the listing of options (including a do nothing option), the gathering of relevant data on these options, detailed analyses of the options, and the selection of a preferred option. The process is shown in diagram Define the objectives and scope of the project The services to be provided by the project must be assessed and identified in order to clarify the purpose of the project. This purpose can be expressed as an outcome (e.g. better recreational access), and as an output (e.g. build a new road). These outcomes and outputs should derive from the organisation s corporate and physical asset strategic plans. Any capital proposal should explicitly identify its contribution to a department s service delivery strategies. The identification of service needs should also be linked to overall government objectives as spelt out in the State strategic planning processes, and in agreed regional strategies. In determining the scope of a capital proposal, consideration should be given to determining what constitutes a discrete project, i.e. avoid excessive aggregation or excessive dis-aggregation of capital works components, and consider the impact on other projects or organisations. 7.2 Identify and select suitable options All realistic options should be identified at the early stage in the planning process, including a realistic base case option of do nothing or do without i.e., maintaining the status quo. Other options can include: refurbishing existing facilities; various options in terms of timing and scale; options to rent, build or purchase; provision of the service or facility by the private sector; maintenance by the private sector; various combinations of capital and recurrent expenditure; various locations or site options; co-operation with other spheres of government; or co-location or shared facilities with other agencies. 8
11 Diagram 2 The Project Evaluation Process Identify service need and define objectives and scope Identify all options Select and short list suitable options Economic analysis: assess costs and benefits and determine net benefits of the selected options Social analysis Environmental analysis Budget analysis Combine analyses, rank and select preferred option Project evaluation report 9
12 Options can be generated by asking questions such as: Could the operation be scaled down or closed? Are all elements of the operation justified? Could the operation be combined or divided to advantage? Can the project be linked to other projects? Could the operation be integrated with other functions? Is there a role for the private sector? Could the operation or part of it be contracted out? Are different sizes or qualities of operation feasible? How can the design and/or life of the scheme be varied? Is there scope to trade-off capital and maintenance costs? What interim solutions are available? Following identification and preliminary assessment of all reasonable options, the most suitable options should be short listed for more detailed assessment. 7.3 Carry out the project analysis To ensure that all aspects of a project are assessed adequately, the economic, social, environmental and budgetary impacts should be investigated. The analyses of each of these issues, which often may be interrelated, are then considered together to form the overall analysis of the project. The weight placed on each type of analysis will depend on the nature of the project Economic analysis Economic analysis assesses the impact of capital projects on the economy. The costs and benefits of a project are identified, valued (using estimates if necessary), analysed and ranked according to net economic benefit. The two techniques mainly used for economic analysis are Cost/Benefit Analysis and Cost/Effectiveness Analysis. Cost/Effectiveness Analysis is particularly applicable to projects with strong community or social welfare objectives which may be difficult to value. It expresses the benefits in physical units rather than in monetary units and would apply, for example, where the output of a project cannot be readily assigned a monetary value. Because of the informational 10
13 The five steps of economic analysis are: Identify benefits Identify costs Calculate net benefits Prioritise options Assess risk and uncertainty demands of Cost/Benefit Analysis, the project and the benefits have to be of reasonable significance to justify the resources required for it. There are five steps in an economic analysis. (a) Identify benefits In identifying benefits consideration should be given to: avoided costs costs which are unavoidable if nothing is done, but may be avoided if action is taken; cost savings verifiable reductions in existing levels of expenditure if a project proceeds; revenues revenues which result directly or indirectly from the project; revenue changes which would have occurred regardless of the project must not be included; benefits to consumers, and to the broader community as a whole (externalities); and the residual value of the asset (if any). Multipliers, which measure the secondary or indirect effects of a project on the economy, should not be included as benefits in an economic analysis. Multipliers, which measure the secondary or indirect effects of a project on the economy, should not be included as benefits in an economic analysis. The inclusion of multipliers is inappropriate because any construction project will generate activity, directly and indirectly. However, these could also be generated by alternative uses of the funds. Benefits should be valued in monetary terms wherever possible, e.g. by using real or estimated market prices. Often some notional financial measures will be available, but in some cases valuation may be excessively expensive and the results produced may be uncertain. Hence, organisations should use discretion as to the worth of undertaking such valuations. (b) Identify costs Evaluations should be based on the additional cost to the State of undertaking the particular project. Costs which would have been incurred anyway should be excluded. The stream of costs should cover the life of the proposed capital item. The degree of accuracy in identifying costs will vary with the significance of the project and the availability of data. Assumptions underlying all capital and recurrent cost estimates should be made explicit in the evaluation, including assumptions regarding, for example, real labour costs, real energy costs, demand growth or real charges/rates. 11
14 It is important that estimates of costs be undertaken on a consistent basis to enable meaningful comparisons to be made between competing options and projects. Also valuation of costs should be on the same basis as benefits. (c) Calculate net benefits Nominal and real values must not be used in the same analysis. The concept of present value is used to facilitate comparison between projects. For Cost/Benefit Analysis the various future costs and benefits should be expressed in present value terms. For Cost/Effective Analysis, a present value should be provided for costs. Discounting takes account of the fact that initial investment costs are borne up front, while benefits and/or operating costs may extend far into the future. Discounting reflects the concept of the time preference of money which is relevant even in the absence of inflation. The use of real interest rates, i.e., with the effect of inflation removed, for example, reflects this time preference. As a general rule, costs and benefits should be valued in real terms and the stream of costs and benefits should be discounted. Where nominal costs and benefits are used then this should be stated. Nominal and real values should not be used in the same analysis. The calculation of present value requires the use of a discount rate. A common discount rate is recommended for all departments in the economic evaluation of capital projects in the general Budget sector to facilitate the comparison and ranking of projects within and between portfolios. A test discount rate of 6% real should be used with appropriate sensitivity testing. All departments in the general Budget sector should use a test discount rate of 6% real with appropriate sensitivity testing, e.g. 4% and 8%. Commercialised entities would normally, subsequent to an economic evaluation, undertake an overall financial evaluation of the project which would use an appropriate commercial rate. The time period the analysis covers should be the expected life of the asset to be created so that immediate costs and benefits, as well as those that occur at varying times in the future, are included in the assessment. In many cases a 20-year time frame will be appropriate. 12
15 (d) Prioritise options In a Cost/Benefit Analysis, Net Present Value (NPV) is a key decision criterion; this is the difference between the streams of costs and benefits of a project, both discounted to present value. All evaluations should show the Net Present Value or Net Present Value of Costs to assist in ranking projects. A project is viable if the Net Present Value is greater than zero; i.e., the total discounted value of benefits is greater than the total discounted costs. If projects offer alternative solutions to a single problem, the project with the highest Net Present Value should be selected. For Cost/Effectiveness Analysis, Net Present Value of Cost is the key decision criterion used to rank projects on the basis of cost and to show the lowest cost alternative. (e) Assess risk and uncertainty There will always be some degree of uncertainty surrounding the outcome of an evaluation. To estimate the risks associated with this uncertainty, and to determine the sensitivity to adverse movements in particular variables, the projected outcomes should be tested under different scenarios. An assessment should be made of a realistic range for all key variables. NPV calculations should then be performed using different combinations of worst and best case scenarios. The analysis should identify the minimum set of changes in key assumptions that would render the project uneconomic. Analytical techniques for assessing risk and uncertainty include: Sensitivity analysis: this illustrates what would happen if a small number of the key variables changed and how these changes would affect the overall cost or benefit of the project. Risk analysis: this can be used where there are a limited number of key variables. Risk analysis assigns probabilities to the key variables, weights the key values by their probability of occurrence and uses these data to calculate the net present value of the project. A bias towards optimism should be avoided and all scenarios, including pessimistic scenarios, should be considered adequately and presented. Scenario planning: this approach is used if there are many assumptions in the project evaluation, each of which could vary. It is a process of looking at various possible situations or future scenarios. Scenario planning usually focuses on long term rather than short term horizons and is used to illustrate a range of technical, economic, social, and political uncertainties which may affect the success of a project. A clear statement of the assumptions used in the analyses and the reasons for choosing them must be given, so that the decision maker is aware of the assumptions underlying the analysis. 13
16 While both optimistic and pessimistic scenarios should be presented, particular attention should be given to the development of pessimistic or conservative scenarios. Areas where a bias towards optimism may occur are in the under-estimation of future costs and over-estimation of benefits Social analysis The analysis should identify: If there are any significant social impacts from the project If anything can, or should be done in relation to these issues What are the costs and benefits of any such action? An analysis of the social impacts of a capital project provides information, such as distributional effects, which are not included in an economic analysis but may be needed for decision-makers in assessing the desirability of projects. An analysis of the social impacts of a project should be undertaken where it is likely that the project will: result in significant distributional shifts in costs and benefits between and within communities; substantially affect employment, trade, private sector or other levels of government etc.; cause disproportionate disadvantage to a particular sector; provoke appreciable community concern; or require changes in government policy and direction. An analysis of the social impacts of a project should: identify any significant social issues or opportunities associated with the project; outline the extent to which they may impact on the project; and develop strategies and options to deal with these issues. Risks and uncertainty associated with the analysis, in particular with assumptions underlying the analysis, should be outlined to assist decision-makers in the overall assessment of project risk. Issues identified in this analysis should be stated clearly in the evaluation report so that decision-makers are fully aware of any policy implications or community reactions to the project proposal. The extent and nature of the social analysis of a project proposal should be commensurate with the importance of the project and of the social issues involved. 14
17 7.3.3 Environmental analysis An environmental analysis is required for all capital projects to ensure that they meet the requirements of the Environmental Protection Act 1994 and other relevant legislation, including the Queensland Heritage Act The environmental analysis may include a preliminary review to determine the extent and nature of the environmental issues and whether further investigation is needed, followed by a detailed environmental impact statement commensurate with the significance of the environmental issues and the project. Environmental analyses provides decision-makers with information about the environmental issues associated with capital projects, and should also identify ways of dealing with these issues. The analysis should identify: If there are any significant environmental issues If anything can, or should be done in relation to these issues What are the costs and benefits associated with these actions? The analysis should assess: the extent and nature of both on-site and off-site environmental consequences; the short- and long-term environmental effects from the project; opportunities to improve environmental benefits from the project (e.g. through the incorporation of conservation initiatives); and whether environmental considerations associated with the project are likely to be of significant community concern. Where an assessment confirms areas of significant environmental concern, strategies and options should be developed, where feasible, to address these concerns. The costs and benefits associated with these strategies should then be identified and valued to assist in the ranking of options. Risks and uncertainty associated with the analysis, in particular with assumptions underlying the analysis, should be outlined to assist decision-makers in the overall assessment of project risk. The extent and nature of the analysis should be commensurate with the nature of the environmental issues involved. 15
18 7.3.4 Budget analysis A budget analysis should be provided for the selected options. This should identify outlays and revenues for each year over the three year forward estimates period, and subsequently as appropriate. The budget analysis of a project should outline: the outlays, both capital and recurrent; the revenues; and the funding source, including details of any financial arrangements These can all be summarised in tabular format, for example: NPV Year 1 Year 2 Year 3 Post Funding Year 3 Source Capital outlays Recurrent outlays Revenues Net All effects on the State s Budget should be identified. These include: All effects of the project on the State Budget should be identified, with particular emphasis on the three year forward estimates period. any budget impacts on other organisations, e.g. inter-departmental/ agency charging; possible effects on organisations budgets including capital and recurrent outlays, appropriations from the Consolidated Fund or Trust Funds, Commonwealth and State grants, borrowings and debt service charges, taxes and fees; and whole of government impacts, e.g. on other agencies. Cash flows should be in current dollar terms, not in real or constant dollar terms (which excludes the effect of inflation). Note that analyses undertaken in real dollars will need to be adjusted to current dollars for Budget estimates. Particular emphasis should be given to the initial three year forward estimates period. Borrowings and any risks or uncertainties, particularly with external funding sources, should be identified and described. 16
19 7.4 Select the preferred option Net Present Value and Net Value of Costs are important factors in ranking projects, but not necessarily the only factors to be considered. Options should be ranked initially on the basis of the economic analysis using Net Present Value or the Net Present Value of Costs as the yardstick. This facilitates comparisons on a consistent basis. The ranking from the economic analysis should then be re-assessed in the light of the social, environmental and budgetary analyses and the ranking adjusted where necessary, and where the preferred option differs from that selected in the economic analysis, the reasons should be stated clearly. It must always be recognised that the lowest cost option is not necessarily the best option; the best option is the one that most closely fulfils all government policy objectives (economic, social, environmental, etc.). 17
20 8. The project evaluation report The purpose of a project evaluation report is to inform departmental management, ministers and Cabinet Budget Committee of the relative importance and worth of capital projects. To be able to do this project evaluation reports must be clear and concise. To facilitate consideration by the Cabinet Budget Committee, a summary of the report should state: whether the project is consistent with the government s overall direction and the department s strategic plan; if the project forms part of an interdepartmental strategy; what impact the project will have on service delivery; how the project contributes to increased productivity; what budgetary impact and economic return the project will produce; whether options other than the government as owner and operator have been considered; whether the project will attract external funding; whether borrowings are to fund all or part of the project; and what scope there is for user charges to meet all or part of the cost. The body of the report should: identify the project name, location and Australian Bureau of Statistics Statistical Division; state the project objective/s, and identify the most suitable options to meet the objective/s; briefly describe the process used to analyse these options; outline the results of the economic analysis including; the costs and benefits of the most suitable options, the results of the analyses of these options, and the identification and justification of assumptions used; outline the results of the social, environmental and budget analyses; provide a risk assessment of the options; present a combined assessment of the economic, budgetary, social and environmental assessments, and then rank the options; identify the preferred option; and provide an analysis of the impact of the preferred option on the State Budget, and on other agencies. 18
21 9. Post implementation review A selection of the major projects undertaken by an organisation should be subject to ex-post evaluations. In addition, major on-going programs which may involve a series of smaller capital projects should be subject to ex-post evaluations. These evaluations would involve: a re-examination of the benefits and costs of the selected option to assess whether the anticipated benefits were realised and the forecast costs achieved; an assessment of the effectiveness in meeting government priorities and objectives; reconsideration of alternative options (if still applicable); and an examination of the project design and implementation to assess the scope for improvement to the adopted option. Ex-post evaluations will assist in the development and evaluation of future project proposals, and so the investment in ex-post evaluations should be considered in the context of benefits likely to be gained. 19
22 10. Reference material General An Economic Framework for Assessing the Financial Performance of Government Trading Enterprise. Steering Committee on National Performance Monitoring of Government Trading Enterprises, Industry Commission, Melbourne, Introduction to Cost /Benefit Analysis for Program Managers. Commonwealth Department of Finance, Australian Government Publication Service, Handbook of Cost/Benefit Analysis. Commonwealth Department of Finance, Australian Government Publication Service, Strategic Asset Management Best Practice Guidelines. Queensland Department of Public Works and Housing. Queensland Treasury publications Budget Manual Financial Administration and Audit Act 1977 Physical Asset Strategic Planning Guidelines Public Finance Standards PFS 340 to 348 Management of Physical Assets Recording and Valuation of Non-Current Physical Assets in the Queensland Public Sector 20
1.1 Objective 4. 1.2 Competencies and resources required 4. 1.3 Scope 4. 1.4 Related documents 5. 3.1 Defining the objectives and scope of projects 7
Contents 1.0 Introduction 3 1.1 Objective 4 1.2 Competencies and resources required 4 1.3 Scope 4 1.4 Related documents 5 2.0 Project evaluation 5 3.0 Project feasibility 7 3.1 Defining the objectives
Project Assessment Framework Cost-benefit analysis
Project Assessment Framework Cost-benefit analysis July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below. Overarching
Capital Planning Guidelines
Capital Planning Guidelines Contents Capital Planning Guidelines... 1 1. INTRODUCTION... 3 2. CAPITAL PROJECTS EVALUATION PROCESS... 3 3. APPRAISAL PROCESS UNDERTAKEN BY DEPARTMENTS... 4 3.1 Extension
CAPITAL PLANNING GUIDELINES
CAPITAL PLANNING GUIDELINES 1. INTRODUCTION... 2 2. EXTENSION OF EXISTING INFRASTRUCTURE PROJECTS... 2 3. NEW CAPITAL PROJECTS... 2 4. MINIMUM INFORMATION REQUIRED... 3 5. PREPARATORY WORK... 3 5.1 NEEDS
Long Term Financial Planning
Long Term Financial Planning Framework and Guidelines Long Term Financial Planning Framework and Guidelines for Western Australian Local Governments p1. Contents Foreword 4 1. Introduction 7 2. Purpose
State of Queensland. Published by the Department of Infrastructure and Planning, September 2010, 100 George Street, Brisbane Qld 4000.
Looking forward. Delivering now. The Department of Infrastructure and Planning leads a coordinated Queensland Government approach to planning, infrastructure and development across the state. State of
december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper
december 08 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The NSW Government is committed to the ongoing improvement of public services by ensuring
Strategic Asset Management Framework
STRATEGIC ASSET MANAGEMENT Strategic Asset Management Framework (Second Edition) Achieving better value for South Australians from our investment in State assets Government of South Australia First edition
Life Insurance (prudential standard) determination No. 7 of 2010
Life Insurance (prudential standard) determination No. 7 of 2010 Prudential Standard LPS 2.04 Solvency Standard Life Insurance Act 1995 I, John Roy Trowbridge, Member of APRA: (a) (b) under subsection
Financial Sustainability Information Paper 8. Long-term Financial Plans
Financial Sustainability Information Paper 8 Long-term Financial Plans Revised January 2012 Introduction This Information Paper is one of a series of Information Papers about Financial Sustainability and
2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines
2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines Introduction The guidelines below provide departments and entities with information to make budget submissions for capital projects
FINANCIAL SERVICES TRAINING PACKAGE FNB99
FINANCIAL SERVICES TRAINING PACKAGE FNB99 This is Volume 12 of a 13-volume set. This volume should not be used in isolation but in the context of the complete set for the Financial Services Training Package.
Alternative infrastructure funding and financing
Alternative infrastructure funding and financing Research Paper (commissioned by the Queensland Government) 21 March 2016 Department Of Infrastructure, Local Government and Planning This page intentionally
TEC Capital Asset Management Standard January 2011
TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining
A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division
A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose
<Business Case Name> <Responsible Entity> <Date>
(The entity Chief Information Officer, Chief Financial Officer and Business Area programme Lead must sign-off the completed business case) Signed: Date:
MEASURING ECONOMIC IMPACTS OF PROJECTS AND PROGRAMS
Economic Development Research Group April 1997 MEASURING ECONOMIC IMPACTS OF PROJECTS AND PROGRAMS GLEN WEISBROD, ECONOMIC DEVELOPMENT RESEARCH GROUP BURTON WEISBROD, ECONOMICS DEPT., NORTHWESTERN UNIV.
THE INSURANCE BUSINESS (SOLVENCY) RULES 2015
THE INSURANCE BUSINESS (SOLVENCY) RULES 2015 Table of Contents Part 1 Introduction... 2 Part 2 Capital Adequacy... 4 Part 3 MCR... 7 Part 4 PCR... 10 Part 5 - Internal Model... 23 Part 6 Valuation... 34
Part B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
Foreign Exchange Policy and Procedures
Foreign Exchange Policy and Procedures Commencement Date: 23 August, 2006 Category: Finance 1. PURPOSE The purpose of this policy is to regulate Foreign Currency transactions of Material amounts and to
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our
Capital Expenditure Guidelines
Division of Local Government Department of Premier and Cabinet Capital Expenditure Guidelines December 2010 These are Director General s Guidelines issued pursuant to section 23A of the Local Government
WATER AND SEWERAGE FINANCIAL MANAGEMENT PLANNING
WATER AND SEWERAGE FINANCIAL MANAGEMENT PLANNING ABSTRACT Chris Adam, Cardno MBK (Qld) Pty Ltd In recent years, the utilities industries have been subject to far greater commercial scrutiny than ever before.
Leasing in the Queensland Public Sector Policy Guidelines. Policy Guidelines for public sector entities considering entering into lease arrangements
Leasing in the Queensland Public Sector Policy Guidelines Policy Guidelines for public sector entities considering entering into lease arrangements November 2014 Table of Contents 1. INTRODUCTION...3 2.
TOTAL ASSET MANAGEMENT. Life Cycle Costing Guideline
TOTAL ASSET MANAGEMENT Life Cycle Costing Guideline September 2004 TAM04-10 Life Cycle Costing Guideline September 2004 TAM04-10 ISBN 0 7313 3325 X (set) ISBN 0 7313 3272 5 1. Asset management New South
Budget development and management within departments
V I C T O R I A Auditor General Victoria Budget development and management within departments Ordered to be printed by Authority. Government Printer for the State of Victoria No. 39, Session 2003-2004
ASSET MANAGEMENT STRATEGY
ASSET MANAGEMENT STRATEGY Page 1 of 15 TABLE OF CONTENTS 1. INTRODUCTION...3 2. THE ASSET LIFECYCLE...3 2.1 Asset Planning...5 2.2 Asset Creation / Acquisition...6 2.3 Asset Operations...7 2.4 Asset Maintenance...7
Introduction to Cost-Benefit Analysis and Alternative Evaluation Methodologies January 2006. Archived FINANCIAL MANAGEMENT REFERENCE MATERIAL NO.
Introduction to Cost-Benefit Analysis and Alternative Evaluation Methodologies January 2006 FINANCIAL MANAGEMENT REFERENCE MATERIAL NO. 5 Commonwealth of Australia 2006 ISBN 1 921182 00 8 (print) ISBN
BEPS ACTIONS 8-10. Revised Guidance on Profit Splits
BEPS ACTIONS 8-10 Revised Guidance on Profit Splits DISCUSSION DRAFT ON THE REVISED GUIDANCE ON PROFIT SPLITS 4 July 2016 Public comments are invited on this discussion draft which deals with the clarification
NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013
APPENDIX 1 NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 Page 1 of 10 1. INTRODUCTION It is widely recognised that asset management is a core component of effective
Central Bank of Ireland Guidelines on Preparing for Solvency II Pre-application for Internal Models
2013 Central Bank of Ireland Guidelines on Preparing for Solvency II Pre-application for Internal Models 1 Contents 1 Context... 1 2 General... 2 3 Guidelines on Pre-application for Internal Models...
1. INTRODUCTION... 1 2. PURPOSE OF THE ASSET MANAGEMENT STRATEGY... 2 3. ASSET MANAGEMENT... 3
ASSET MANAGEMENT STRATEGY 2010-2020 November 2009 1. INTRODUCTION... 1 2. PURPOSE OF THE ASSET MANAGEMENT STRATEGY... 2 3. ASSET MANAGEMENT... 3 4. WESTERN AUSTRALIAN ASSET MANAGEMENT IMPROVEMENT PROGRAM
Scotland Your project business plan
Scotland Your project business plan Scotland Your project business plan Further copies available from: Email [email protected] Phone 0870 240 2391 Textphone 0141 242 1500 Our website
Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and
Review of PIRSA s Cost Recovery Policy and practices, including their application to the Fisheries and Aquaculture Industries Primary Industries and Regions SA 29 July 2015 Contents Executive Summary...
CODE: E.003 Financial Services BUDGET AND BUSINESS PLANNING POLICY. 1.2 The essential activities covered by this policy include:
BUDGET AND BUSINESS PLANNING POLICY CONTENTS 1.1 Budget and business planning is undertaken to support strategic planning and decision-making and to serve accountability by enabling administration to plan
A QUICK REFERENCE GUIDE FOR ELECTED OFFICIALS AND STAFF WHOLE-OF-LIFE COSTING
A QUICK REFERENCE GUIDE FOR ELECTED OFFICIALS AND STAFF WHOLE-OF-LIFE COSTING A This booklet is a quick reference guide to help you to: nn understand the purpose and benefits of applying the fundamental
INTEGRATED PLANNING AND REPORTING
Government of Western Australia Department of Local Government INTEGRATED PLANNING AND REPORTING Framework and Guidelines Integrated Planning and Reporting Framework and Guidelines p1. Contents Foreword
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
july 07 tpp 07-4 Commercial Policy Framework: Guidelines for Financial Appraisal OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper
july 07 Commercial Policy Framework: Guidelines for Financial Appraisal OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The Guidelines for Financial Appraisal is a policy document prepared
The Public Spending Code D. Standard Analytical Procedures
The Public Spending Code D. Standard Analytical Procedures Guide to economic appraisal: Carrying out a cost benefit analysis D.03 Document Summary: CBA is a key economic appraisal technique under the Public
CAPITAL CHARGE RATE AND CHANGES TO THE INCENTIVE REGIME
DH 6-2-1 21 December 2000 Treasury Circular 2000/16 Unrestricted Distribution Chief Executives Directors of Finance/Chief Accountants Contact for Enquiries: Treasury Vote Teams CAPITAL CHARGE RATE AND
Handbook of Cost-Benefit Analysis January 2006. Archived FINANCIAL MANAGEMENT REFERENCE MATERIAL NO. 6
Handbook of Cost-Benefit Analysis January 2006 FINANCIAL MANAGEMENT REFERENCE MATERIAL NO. 6 Commonwealth of Australia 2006 ISBN 1 921182 01 6 (print) ISBN 1 921182 03 2 (online) Department of Finance
KEY PERFORMANCE INFORMATION CONCEPTS
Chapter 3 KEY PERFORMANCE INFORMATION CONCEPTS Performance information needs to be structured to demonstrate clearly how government uses available resources to deliver on its mandate. 3.1 Inputs, activities,
Long-Term Asset Management Plan 2011-2021
Long-Term Asset Management Plan 2011-2021 Contents Introduction...3 A shared vision...4 Strategic planning to achieve our goals...4 Towards 2031...5 A long-term vision, communicated by our community...5
Capital Adequacy: Advanced Measurement Approaches to Operational Risk
Prudential Standard APS 115 Capital Adequacy: Advanced Measurement Approaches to Operational Risk Objective and key requirements of this Prudential Standard This Prudential Standard sets out the requirements
Business Combinations
Compiled Accounting Standard AASB 3 Business Combinations This compilation was prepared on 6 March 2006 taking into account amendments made up to and including 22 June 2005. Prepared by the staff of the
How To Write A Listing Policy For A Species At Risk Act
Fisheries and Oceans Canada Species at Risk Act Listing Policy and Directive for Do Not List Advice DFO SARA Listing Policy Preamble The Fisheries and Oceans Canada (DFO) Species at Risk Act (SARA) Listing
DRAKENSTEIN MUNICIPALITY LONG TERM FINANCIAL PLAN
DRAKENSTEIN MUNICIPALITY LONG TERM FINANCIAL PLAN APPROVED 26 MAY 2010 TABLE OF CONTENTS 1. FINANCIAL MANAGEMENT 3 1.1 Introduction 3 2. FINANCIAL STRATEGIES OVERVIEW 3 2.1 General Considerations 3 Social
Not-for-profit entity requirements in Australian Accounting Standards (Updated December 2008)
Not-for-profit entity requirements in Australian Accounting Standards This document identifies requirements in Australian Accounting Standards that relate specifically to not-for-profit (NFP) entities.
SOL PLAATJE LOCAL MUNICIPALITY
SOL PLAATJE LOCAL MUNICIPALITY LONG TERM FINANCIAL PLANNING POLICY 1 P a g e TABLE OF CONTENTS TABLE OF CONTENTS... A 1. INTRODUCTION...1 2. PURPOSE OF THIS DOCUMENT...1 3. DEFINITIONS... 2 4. OBJECTIVES...
Department of Finance. Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector
Department of Finance Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector January 2005 Table of Contents Page Preface Role of Government and Ministers 4 Introduction
COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited
PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date
GOLDSMITHS University of London COUNCIL. FINANCE AND RESOURCES COMMITTEE 18 March 2014
GOLDSMITHS University of London CNCL/96 14-101 G TREASURY MANAGEMENT OPERATIONS 1 Background COUNCIL FINANCE AND RESOURCES COMMITTEE 18 March 2014 Goldsmiths Treasury Management Policy was last extensively
ICT Business Case Guide
ICT Business Case Guide JULY 2012 AGIMO is part of the Department of Finance and Deregulation Contents Introduction 3 First Pass Business Case 5 1. Executive Summary 6 2. Current Situation 7 3. Proposed
Project Management. Session 4 - Dr. Sepehri. Sharif MBA Fall 1385. Feasibility Study, Project Selection. Burke Chapter 4-5
Project Management Sharif MBA Fall 1385 Session 4 - Dr. Sepehri Feasibility Study, Project Selection Burke Chapter 4-5 1 Project Feasibility Feasibility study ensures that projects are technically and
Investment Decision Analysis
Lecture: IV 1 Investment Decision Analysis The investment decision process: Generate cash flow forecasts for the projects, Determine the appropriate opportunity cost of capital, Use the cash flows and
Further comments are provided under Examiner s Comments for individual questions.
F3 FINANCIAL STRATEGY Examiner s general comments This was the first diet under the 2010 syllabus for F3, which replaces P9 under the old syllabus. The syllabus content is largely unchanged but a revised
Framework for Long Term Financial and Asset Management Planning for all Tasmanian Councils
TASMANIAN STATE GOVERNMENT and LOCAL GOVERNMENT ASSOCIATION OF TASMANIA Framework for Long Term Financial and Asset Management Planning for all Tasmanian Councils FINAL REPORT September 2009 Document Control
Commonwealth Financial Accountability Review (CFAR) Paper Is Less More?
Commonwealth Financial Accountability Review (CFAR) Paper Is Less More? Thank you for your correspondence on the CFAR paper Is Less More and for the opportunity to comment on the proposals contained therein.
Project Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
Department of Accounting and Finance
Department of Accounting and Finance Modules, other than Introductory modules may have pre-requisites or co-requisites (please, see module descriptions below) and a student must have undertaken and passed
Introduction to Discounted Cash Flow and Project Appraisal. Charles Ward
Introduction to Discounted Cash Flow and Project Appraisal Charles Ward Company investment decisions How firms makes investment decisions about real projects (not necessarily property) How to decide which
Financial Management (Sustainability) Guideline 2013 Version 1.1
Financial Management (Sustainability) Guideline 2013 Version 1.1 For the purposes of explaining the concept of sustainability and to provide guidance for calculating the relevant financial sustainability
1. This Prudential Standard is made under paragraph 230A(1)(a) of the Life Insurance Act 1995 (the Act).
Prudential Standard LPS 110 Capital Adequacy Objective and key requirements of this Prudential Standard This Prudential Standard requires a life company to maintain adequate capital against the risks associated
Information Paper 10. Debt Management
Information Paper 10 Debt Management February 2007 Introduction Local Government financial statements, like those of other spheres of government and the corporate sector, include a good many items of considerable
Life Cycle Cost Analysis (LCCA)
v01-19-11 Life Cycle Cost Analysis (LCCA) Introduction The SHRP2 R-23 Guidelines provide a number of possible alternative designs using either rigid of flexible pavements. There is usually not a single
The Levy Control Framework
Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 4 Key facts The Levy Control Framework Key facts 2bn
Sec. 22a-1a page 1 (4-97)
Department of Environmental Protection Sec. 22a-1a page 1 (4-97) TABLE OF CONTENTS Connecticut Environmental Policy Act Definitions... 22a-1a- 1 Determination of sponsoring agency.... 22a-1a- 2 Determination
TITLE C171 ASSET MANAGEMENT POLICY DEPARTMENT. Engineering Services POLICY DIRECTIVE
TITLE C171 ASSET MANAGEMENT POLICY DEPARTMENT Engineering Services POLICY DIRECTIVE This Asset Management policy will ensure that Asset Management is clearly recognised by Council and community in accordance
HELP Interest Rate Options: Equity and Costs
HELP Interest Rate Options: Equity and Costs Bruce Chapman and Timothy Higgins July 2014 Abstract This document presents analysis and discussion of the implications of bond indexation on HELP debt. This
REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION
REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION January 2008 C O N T E N T S Page No. 1. Overview 1 2. Introduction 3 3. RIC s Regulatory Framework
Accounting for Goodwill
Australian Accounting Standard AAS 18 June 1996 Accounting for Goodwill Prepared by the Public Sector Accounting Standards Board of the Australian Accounting Research Foundation and by the Australian Accounting
Social impact assessment. Guideline to preparing a social impact management plan
Social impact assessment Guideline to preparing a social impact management plan September 2010 Looking forward. Delivering now. The Department of Infrastructure and Planning leads a coordinated Queensland
PRACTICE NOTE 22 THE AUDITORS CONSIDERATION OF FRS 17 RETIREMENT BENEFITS DEFINED BENEFIT SCHEMES
PRACTICE NOTE 22 THE AUDITORS CONSIDERATION OF FRS 17 RETIREMENT BENEFITS DEFINED BENEFIT SCHEMES Contents Introduction Background The audit approach Ethical issues Planning considerations Communication
STAG Technical Database Section 13
Risk and Uncertainty May 2014 Transport Scotland Once printed or downloaded this document is considered to be uncontrolled. For the current version refer to the Scot-TAG section of the Transport Scotland
Using the FRR to rate Project Business Success
Using the FRR to rate Project Business Success The purpose of this note is to explain the calculation of the financial rate of return (FRR), with a view, firstly to clarify the FRR concept and its determination,
S t a n d a r d 4. 4 a. M a n a g e m e n t o f c r e d i t r i s k. Regulations and guidelines
S t a n d a r d 4. 4 a M a n a g e m e n t o f c r e d i t r i s k Regulations and guidelines THE FINANCIAL SUPERVISION AUTHORITY 4 Capital adequacy and risk management until further notice J. No. 1/120/2004
SUPPLEMENTARY GREEN BOOK GUIDANCE
SUPPLEMENTARY GREEN BOOK GUIDANCE ADJUSTING FOR TAXATION IN PFI vs PSC COMPARISONS 1 INTRODUCTION 1.1 This guidance looks at the differential tax receipts that arise from the use of the Private Finance
Developing and Managing Internal Budgets. top-down. embed. hasing variation. allocation. forecasting. bottom-up
Developing and Managing Internal Budgets top-down embed hasing variation forecasting allocation bottom-up Better Practice Guide June 2008 ISBN No. 0 642 81021 4 Commonwealth of Australia 2008 COPYRIGHT
Handbook for municipal finance officers Performance management Section J
1. Introduction The Department of Provincial and Local Government (DPLG) defined performance management as a strategic approach to management, which equips leaders, managers, employees and stakeholders
Commonwealth Debt Management
The Auditor-General Audit Report No.14 1999 2000 Performance Audit Commonwealth Debt Management Australian National Audit Office Commonwealth of Australia 1999 ISSN 1036-7632 ISBN 0 644 39162 6 This work
Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors
Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table
Capitalisation of Software
The Auditor-General Audit Report No.14 2010-11 Performance Audit Australian Bureau of Statistics Civil Aviation Safety Authority IP Australia Australian National Audit Office Commonwealth of Australia
Performance objectives
Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants. They also outline the values
OCCASIONAL PAPERS ON PUBLIC MANAGEMENT ACCOUNTING FOR WHAT?: THE VALUE OF ACCRUAL ACCOUNTING TO THE PUBLIC SECTOR
GENERAL DISTRIBUTION OCDE/GD(93)178 OCCASIONAL PAPERS ON PUBLIC MANAGEMENT ACCOUNTING FOR WHAT?: THE VALUE OF ACCRUAL ACCOUNTING TO THE PUBLIC SECTOR ORGANISATION FOR ECONOMIC CO-OPERATION AND DEVELOPMENT
