Risk Pricing in Construction Tenders How, Who What
|
|
|
- Owen Byrd
- 9 years ago
- Views:
Transcription
1 Risk Pricing in Construction Tenders How, Who What Marcus Tower and David Bacarini (Department of Construction Management, Curtin University of Technology, Perth, Western Australia ABSTRACT Construction projects are most commonly procured in Australia by means of a traditional design tender build model, whereby design is largely completed then contractors submit tenders in a competitive environment. Construction contractors must consider risks within their tenders. This paper reports the research findings into pricing for risk in competitive tenders by construction contractors. The research is based on structured interviews with 10 contracting personnel; supplemented by 23 responses of construction personnel from an online survey. Two common methods to price for risk are a trade-by-trade basis or an overall percentage or lump sum addition to the base estimate. Experience and intuition plays a significant role in pricing for risk in tenders and the number and type of people involved varies with project size, with greater involvement as project size increases. The most significant risks priced in tenders were: availability of resources; design or documentation errors; incomplete design; buildability issues; and inclement weather. The most significant project factors considered by contractors when pricing for risk in tenders are: value of liquidated damages; type of contract/procurement; completeness of documentation; project complexity; and current workload. These risks and project factors are primarily those over which the contractor has limited or no control. Keywords: Construction, Risk, Tendering, INTRODUCTION Construction projects are most commonly procured in Australia by means of a traditional design tender build model (RCBCI 2002). Under traditional procurement, project delivery is a sequential process whereby design is largely completed before construction work commences and contractors submit tenders in a competitive environment (McDermott & Rowlinson 1999). Risk is an inherent element of construction contracting (Baccarini & Archer 2001). So in preparing tenders, construction organisations must estimate base costs and make management decisions to determine the amount to be added in the tender for risk. A common terminology for the financial amount allocated for risk in tenders is a contingency sum (Smith & Bohn 1999). So the main purpose of a contingency sum is counteract the risks that may occur during the course of a construction project (Mak et al. 1998; Smith & Bohn 1999). Traditionally, contingencies for risks are often calculated as an across-the-board percentage addition on the base estimate, typically derived from intuition, past experience and historical data (Mak et al, 1998). A different contingency percentage may be calculated for each major cost element (Moselhi, 1997). The across-theboard percentage addition approach for contingency calculation is considered an arbitrary method and difficult for the estimator to justify or defend (Yeo 1990, Newton 1992). Estimation relies on estimators intuition, experience and judgement (Liu & Ling 2003). As Flanagan and Norman (1993, p 128) note, the single factor that characterises all price forecasting is uncertainty and price prediction is an art which requires both intuition and expert judgement. Moselhi (1997) believes that most estimators use a crystal ball to determine contingency sums, and in most cases is determined based on gut feel, intuition and past experience with similar projects. RESEARCH METHODLOGY The aim of this research is to determine how construction contractors price for risk in competitive tenders. This research is basic, applied, descriptive, qualitative and quantitative (Kumar 2005; Sarantakos 2005). The research used two data collection approaches - structured interviews and online surveys. The research sample was selected on a purposive basis, according to the judgement of the researcher as to who could provide the best information to achieve the objectives of the study (Kumar 2005). The research sample comprised of construction professionals drawn from commercial and civil construction contracting organisations that are members of the Master Builders Association (Western Australia), which is an industry association with members drawn from the range of professions, trades and services in the building industry. The MBA provided access to a database of construction organisations engaged in tendering in nonresidential building projects. Senior managers
2 at 10 construction organisations were purposively selected to be interviewed to provide qualitative data; and a further 145 construction personnel at selected commercial or civil construction contractor were invited to complete an online survey to provide quantitative data. This elicited 23 responses, giving a response rate of 15.8%. So, overall there were 33 respondents in this study. RESULTS Demographics Demographic details for the interviewees and online respondents are set out in Tables 1-4, which show: Job title three job types dominated the sample: Managing Director, Estimator and Company Director Work experience in preparing tenders the majority have over 15 years experience Types of project - nearly all work in commercial construction Project values - respondents work on wide range of project values Job Title Nr % Managing Director Estimator 7 22 Company Director 5 15 Project Manager 2 5 Business Development Manager 1 3 Estimating Manager 1 3 Contracts Manager 1 3 Construction Director 1 3 Chairman of Directors 1 3 Table 1 - Respondents - Job Title Years of experience Nr % 0-5 years years years Table 2 - Respondents - Experience Area of expertise Nr % Commercial construction Civil Construction 3 9 Table 3 - Respondents - Expertise Project values Nr % Under $5m $5m - $20m 7 21 over $20m Table 4 - Respondents Project value Pricing for risk The ten interviewees were asked: When preparing tenders is pricing, for risk a separate process to preparing the base estimate? (Online respondents were not asked this question). This study identified three discernable approaches to determining how risk is priced in r tenders See Table 5. The responses suggest there is no universally accepted standard or default protocol in the tendering process for pricing risk. Risk Pricing Process Separate to preparing base estimate 4 Integral part of preparing base estimate 3 during & after base estimate preparation 3 Table 5 Risk Pricing Process Four respondents indicated that pricing of risk is an entirely separate process to preparing the base estimate. Two respondents stated that risk is not considered until the base estimate has been prepared. In the other two organisations, risk is priced over the same period of time in which the base estimate is prepared, however it is usually conducted by separate parties and both processes are Nr 10
3 mutually exclusive. One respondent described this process: Once we receive the project documents two separate processes begin. The first process is that the estimator will work through the documents and drawings and price the quantifiable aspects of the project using standard engineering principles. At the same time other parties will identify and price any commercial, technical, environmental or OS&H risk associated with the project. So although these activities happen in parallel they are separate processes. In three organisations, pricing of risk occurs as an integral part of preparing the base estimate. The parties responsible for preparing the base estimate price for risk as the estimate is prepared and document any decisions or assumptions, for review by management before the tender is submitted. As one respondent explained: The risk is priced into the individual components of where we see the risk. When we add this contingency to each sub trade it appears as a separate figure underneath the relevant sub trade within our estimate these amounts are then reviewed by management before the tender is submitted Three respondents indicated that the process in their organisation is to price risk for all trade elements of the project as the base estimate is prepared, which is a common method of pricing for risk (Ahmad & Minkarah 1988). Then risk associated with non-trade elements of the project, such as preliminaries and contractual risk, is generally priced once the base cost of the project has been established. In summary, the responses indicate that there is no dominant process for pricing risk in tenders; rather the process is contingent upon organisational preference. These findings contrast with the literature, which tends to emphasise that pricing for risks is a separate process that follows on from preparing the base estimate. Involvement in Pricing Risk Interviewees were asked: Who is involved in the process of pricing for risk? (Online respondents were not asked this question). All respondents indicated that executive management was ultimately responsible for determining the price of risk, which usually occurs during a tender review or adjudication meeting. As Smith (1995) contends, tender adjudication meetings are usually attended by those who have played a significant part in preparing the estimate and representatives from senior management. Akintoye & Fitzgerald (2000) also found that approval of tender sums for both small and large projects is undertaken by senior management. The value of the project tends to have has a relationship with the number of people involved in pricing for risk. Construction organisations tendering for projects less than $5 million may have as few as two people involved in the pricing of risk, the primary persons being the estimator and executive manager. If necessary, other members of the organisation such as additional executive managers, contract managers or site managers may also be involved. As observed by Akintoye & Fitzgerald (2000), it is unusual for small firms to have a separate cost estimating department, which means that proprietors of the firm are usually more closely involved in the preparation of tenders and the pricing of risk. In organisations bidding for projects between $5 million and $20 million, respondents indicated there are generally approximately four people involved in pricing risk - estimator, contract manager, site manager and executive manager. All organisations primarily tendering for projects in excess of $20 million described a multi-stage process, consisting of a series of meetings or brainstorming sessions attended by members of the estimating team and executive management throughout the tender preparation period. In the two largest firms surveyed, tenders exceeding a certain value go through an iterative process and the tender is reviewed several times by people with increasingly higher levels of responsibility to ensure all risks have been adequately accounted for. The process followed by one large commercial construction contractor is: 1. The tender is prepared in a standard format and the estimating team documents where and why they have included a contingency for each trade. 2. The base estimate and all documentation are reviewed by State management. 3. The tender is reviewed by an Internal Credit Committee made up of the Managing Directors of each state to ensure due diligence has been followed and regional market conditions have been accounted for. The responses suggest that the number and type of organisational personnel involved in the pricing of risks in tenders tends to vary with project size. Generally, as project size increases so the number and level of personnel increases with more senior management involvement. This might be expected because greater project value demands more financial investment, which one could reasonably expect to stimulate more intensive consideration on the risk pricing process in tenders.
4 Calculation of risk Interviewees were asked: How do you calculate the amount to include for risk in your tenders (Online respondents were not asked this question). Interestingly, with a small sample of ten interviewees, five methods of pricing risk were identified (see Table 6), which indicates a wide range of possible approaches to calculating risks in tenders. Methods of calculating risk Micro 3 Macro 3 Micro + Macro 2 Construction period 2 Monte Carlo simulation 1 Nr 11* *Note: 11 responses from 10 respondents. One organisation uses two methods: Monte Carlo simulation for projects over a certain value; micro method for projects below this value Table 6 Methods of calculating risk Micro Three respondents price risk on a trade by trade or elemental basis and a contingency amount is included in each trade area or element as the base estimate is prepared. One respondent explained this process: We price risk on a trade by trade basis as we receive subcontractor and supplier prices We assess the suitability of the prices we receive and determine how much it should cost to do the work We need to look at each area of the work in isolation to assess our risk and make adjustments accordingly the same also applies for amounts we include for preliminaries and supervision. Several authors (e.g. Smith & Bohn 1999; Karlsen & Lereim 2005) suggest the calculation of a different contingency amount for each major cost element is a common approach to pricing risk in tenders. Each major segment of the estimate is classified in terms of its degree of uncertainty and attracts its own inclusion for risk (Bent & Humphreys 1996). This method of pricing risk is considered more reliable than the simple application of one overall percentage or lump sum addition to the base estimate because it encourages close examination of each cost area (Moselhi 1997). Macro Three respondents prepare the base estimate then an amount is added to cover risk in all trade areas. One respondent highlighted this process: I always instruct my estimators to price the job in accordance with the trade prices we receive and their best guess for preliminaries and supervision. Then we will have a discussion with the Managing Director to assess the project and identify and price any extraneous factors when we are finalising the tender It may mean we add a lump sum to cover all the risk items we have identified or we may just make a consideration in the amount of margin we apply. Another respondent indicated they usually apply a macro approach: Generally we will look at a past project and say that the contingency percentage we used on that project was pretty spot on so if we do the same for the new project we should be OK of course we will examine the documentation to identify any major differences between the projects and make adjustments accordingly. According to Clark et al (1997), amounts to include for risk are often applied as an across-the-board mark-up typically derived from past experience and historical data. By looking at the contingency percentage for past projects, risk is priced from this benchmark. Micro + Macro Two respondents price some risk on a trade by trade or elemental basis as the base estimate is prepared and some risk is priced by making a lump sum or percentage addition to the base estimate. One respondent explained the process: For each cost centre we will look at past projects and consider any problems we have had with that area of work and include a lump sum for that trade area if we feel it is necessary for this job as well as that, we may apply a percentage or lump sum amount for entire job if the project is particularly complex. Construction Period Two respondents include for risk calculated on the duration of the construction period. From one respondent: We loosely calculate the amount to include based on the nominated construction period. We look at several factors to determine a rate per week which is then multiplied by the number of weeks to calculate our contingency amount. This approach support s research by Skitmore & Wilcock (1994) that found some contractors examine the construction period stated in the tender documents to assess the feasibility of that period and if necessary they make an allowance for extra time by multiplying the weekly liquidated damages by the difference between the number of weeks stated in the
5 tender documents and the period they consider reasonable and practical. Monte Carlo Simulation Monte Carlo simulation is a probabilistic estimating technique that allows determination of an overall contingency amount. One respondent from a large organisation explained the use Monte Carlo simulation to assist in pricing risk: We have tender standards which dictate that we use Monte Carlo analysis for all projects valued over $100 million. However in the West Australian branch we probably use it more along the lines of any project worth over $10 million. For projects valued at less than $10 million, the respondent indicated they use the micro method because the systems they employ for Monte Carlo simulation are quite sophisticated and require an external facilitator which is not warranted on smaller projects. Previous studies have found it is uncommon for contracting organisations to employ statistical or mathematical methods to price risk in tenders (e.g. Dulaimi & Shan 2002) and this is the case in this research Experience and intuition Interviewees and online respondents were asked How important is experience and intuition in determining the amount you include for risk in your tenders to price for risk. All respondents agreed that experience and intuition is very important. For example: Each completed project builds a company's understanding of risks and how to approach future tenders with regard to risk. Many times you can't really tell the magnitude or likelihood of a risk until you have experienced its consequences ; Pricing of risk cannot be too scientific, therefore it comes down to intuition to strike the balance between risk acceptance and competitiveness. Many of the respondents explained that the people primarily involved in the pricing of risk in tenders have a wealth of experience, which according to Hegazy & Moselhi (1995) is more important than any procedure or tool. One respondent felt that without at least 10 years of experience it would be unlikely for an individual to have sufficient insight to adequately identify and assess the magnitude of risk to which the company may be exposed during the course of a construction project. One respondent indicated there was very little science associated with pricing risk and ultimately it was down to the best guess of experienced people to ensure all risks are covered in their tenders. Tah et al. (1994) found that contractors rely on experience and intuition to price risk in tenders and surmised that the amount included for risk is usually based on subjective judgement. Most significant risks From the literature, 23 risks relevant to construction contractors were identified. All 33 respondents were asked to indicate the 5 risks they felt were most significant when pricing for risk in their tender - see table 7 Examining the five risks which contractors rate as the most significant, two discernable areas of risk can be identified: Risks Nr % 1 Design or documentation errors Availability of labour, materials or equipment Buildability issues Subcontractor/supplier ability Incomplete design Possible estimation error Site access issues Complexity of project team Exchange rates Inclement weather Scope changes Industrial relations action Ecological damage/pollution Financial failures of subcontractors Changes in regulations/ legislation Site safety requirements Financial failure of owner Equipment failure Unforeseen site conditions Low labour productivity Rework Political uncertainty Fire 0 0 Table 7 Most significant risks when pricing tender Design related risks Three of the five most significant risks - Design or documentation errors, buildability issues and incomplete design - stem from design issues. Contractors have very little control over these risks in a traditional procurement arrangement but may have to suffer any financial consequences, so they price for them in their tenders. One respondent, who has been in the construction industry for over 30 years, stated: In the hundreds of projects I
6 have been involved with since joining this industry I cannot recall a single one where there was no conflicting or missing information in the project documents and only a foolhardy soul would not include an amount in their tender price to allow for this. This is supported by the literature, particularly in a recent study into the quality of project documentation and its impact on the efficiency and cost of Australian construction (Tilley et al. 2002). Incomplete design is a well known risk facing contractors and as Paek (1994), notes, contractors often have little or no option but to bid for projects based on preliminary, incomplete, or even non existent documentation so there is a clear need to include an amount for risk when this is the case. On the issue of buildability, one respondent stated: It is all good and well for an architect or designer to come up with a concept but ultimately as the contractor, we are the ones who have to figure out a way to construct the facility. Ultimately all buildings can be built somehow but if the best way to go about it is not immediately clear we need to include an amount to cover ourselves for this Labour related risks Two of the five most significant risks are availability of resources and ability of the labour force or suppliers. One respondent elaborated on the risk of labour unavailability: In the current market with so much activity it is important to get your trades locked in for the job as soon as you can because if you don t, you often find that the people whose price you used to prepare the tender get committed on other jobs and you get left holding the baby so to speak. Another contractor indicated that as a rule of thumb their organisation aims to get at least 70% of the trade value of the project locked in with the appropriate subcontractors before they commit a price to the client. The ability of subcontractors and suppliers to deliver their portion of the work in accordance with the contract was also highlighted as an important consideration for contractors when pricing risk. As one respondent stated: Sometimes we will engage a subcontractor we have not worked with before and this poses a risk to us because we don t know until after the job has started if they are any good so in that situation we would generally make an allowance for this when we are pricing our tender. Table 8. As might be expected, there is a strong relationship between the risks contractors most often consider and the risks rated most significant. However, some risks had a discernable difference between their significance and consideration rankings: Unforeseen site conditions - Contractors consider unforeseen site conditions when preparing tenders but do not see it as a significant risk. This may be due to the fact that unforeseen site conditions are often dealt with in most standard forms of contract. Low labour productivity - Contractors consider the risk of labour productivity e but do not see it as being significant. This may be because contractors attempt to only engage subcontractors they have worked with before so they can be reasonably confident about productivity rates. Scope changes - Contractors do not often consider scope changes but when they do, it is seen as a significant risk. This may be because when projects are procured using the traditional method, scope changes are typically reimbursed through the contract, and therefore contractors do not consider this as a risk which needs to be priced when preparing tenders. Most significant project factors From the literature, 20 project factors that may influence how risk is priced in tenders were identified. Respondents were asked to indicate the 5 factors most significant when pricing for risk in their tenders see Table 9 Risks considered Using the same 23 risks in table 7, all 33 respondents were asked how often these risks are considered in the tendering process - see
7 Risks Significance Ranking Consideration Ranking Variance 1 Design or documentation errors Availability of labour, materials, equipment Buildability issues Subcontractor/supplier ability Incomplete design Possible estimation error Site access issues Complexity of project team Exchange rates Inclement weather Scope changes Industrial relations action Ecological damage/pollution Financial failures of subcontractors Changes in regulations/ legislation Site safety requirements Financial failure of owner Equipment failure Unforeseen site conditions Low labour productivity Rework Political uncertainty Fire Table 8 Risks in tenders Significance v Consideration Project factors Nr % 1 Value of liquidated damages Type of contract/procurement Completeness of documentation Project complexity Current work load Size of contract Need for work Duration of project Location of project Owner (Private/Public) Economy (availability of work) Escalation in material prices Owner s special requirements Use of nominated subcontractor Past profit in similar job Experience in similar project Tendering duration Competitiveness of competitors Establishing relationship with clients Project cash flow 1 3 Table 9 Most significant project factors when pricing tender These five factors can be grouped into three categories (Dulaimi & Shan 2002): Contract Conditions - The type of contract has a bearing on how contractors price risk. From one respondent: we always look at the contract to see if there are any onerous clauses and assess how much risk the client has shoved onto our side of the fence. Several respondents indicated that they would price risk based on the procurement arrangement. From one respondent: When we are tendering on a project where the design has already been completed at least we have a decent amount of information on which to base our price. When we are tendering on a project on a design and construct basis there are many more variables which have not yet been decided so the risks are higher and we will allow for this in our tender. One respondent indicated that the most common overall contingency they apply is for time based risk: One of the first things we do is have a good look at the proposed
8 program and if it is tight we will include an amount to cover us for liquidated damages... if the liquidated damages are out of whack in relation to the size of the job we may even choose not to tender. Completeness of documentation is another issue contractors take into account when pricing risk. Several respondents explained that it was not uncommon for them to produce tenders without complete information. As one respondent put it: You often have to submit tenders based on documentation which is not 100% complete, sometimes even if the design is finished we may not have any details about finishes or door hardware or several other aspects of the project so we have to cover ourselves as best we can by allowing for this in our tender. Project characteristics - Project complexity was the fourth most significant factor considered by contractors when pricing for risk. As one respondent stated: There are significant risks associated with tendering for a project that is particularly complex where innovative methods will be needed to complete the job when we need to use methods we have not tried before we always include some fat to cover ourselves just in case things don t go the way we plan. According to Akintoye (2000), the complexity of a project has direct consequences for the production rates achieved on the project and the more complex a project the greater the risk of lower than expected levels of profitability. Two respondents noted that complex projects can provide opportunities that may not be available on straightforward projects. From one respondent: We generally include an amount to cover us if we believe a project is particularly complex. However we often find that by using innovative construction and or management techniques complex projects can also present substantial opportunities. Organisational issues - Current workload was the fifth most significant factor when pricing tenders, as highlighted by one respondent: There is a lot of work around at the moment and we get the opportunity to tender on at least two new projects every week. We have to consider each project carefully in relation to how much work we are already doing because we need to ensure we have the resources to do all the work on our books at any given time if we can t it can lead to liquidated damages and a world of pain. This respondent went on to explain that they would not necessarily choose not to submit a tender if their current work load was high but they would price the job differently to ensure they could bring more resources into the organisation if necessary. Shash & Abdul- Hadi (1992) suggest contractors are more likely to price risk in a conservative fashion if their workload is low and they need to maintain turnover. Project factors considered Applying the same project factors in Table 9, all 33 respondents were asked How often are the following project factors considered when pricing for risk in your tenders? see Table10 Some project factors have a discernable difference between their significance and consideration rankings: Experience in a similar project - When deciding whether to tender for a project contractors will consider if they have the requisite experience to complete the project. Once that decision has been made contractors believe previous experience does not pose a significant risk which needs to be allowed for in their tender because if it was decided they did not have the right mix of experience they would be more inclined not to tender for the project rather than attach a price to that risk. Establishing long relationships with clients - The desire to establish an ongoing relationship with a client may lead a contractor to make a conscious decision to reduce their profit margin, so it is a consideration in the way they price their tender, but it is unlikely to be the cause of additional project risk. SUMMARY AND CONCLUSIONS Construction projects are most commonly procured in Australia by means of a traditional design tender build model, whereby design is largely completed then contractors submit tenders in a competitive environment. Construction contractors must consider risks within their tenders. This paper reports the research findings into pricing for risk in competitive tenders by construction contractors. The research is based on structured interviews with 10 contracting personnel involved in pricing for risk in competitive tenders; supplemented by 23 responses of construction personnel from an online survey. The key findings of this research are: There is no universally approach for pricing risk in construction tenders Two common methods to price for risk are a trade by trade basis and an overall
9 percentage or lump sum addition to the base estimate. In essence the majority of methods used to price risk rely heavily on experience and intuition. So experience, intuition and judgment play a significant role is pricing for risk in tenders and the number and type of people who provide this varies with project size, with greater involvement as project size increases. The most significant risks priced in tenders were: availability of resources; design or documentation errors; incomplete design; buildability issues; and inclement weather. The most significant project factors considered by contractors when pricing for risk in tenders are: value of liquidated damages; type of contract/procurement; completeness of documentation; project complexity; and current workload. These risks and project factors are primarily those over which the contractor has limited or no control. For example, quality of design and documentation, buildability, value of liquidated damages, and type of contract/procurement are mainly determined by the client s project team and set in place prior to pricing tenders. Whilst other risks or factors such as availability of resources and workload are mostly created in the economic external environment within which construction contractors operate. In conclusion, it is interesting to note that whilst there is extensive research of risk management by construction contractors, there is very little research devoted to investigating the process by which construction organisations price these risk within competitive tenders. This paper adds to the knowledge in this area.
10 Project Factors Significance Ranking Consideration Ranking Variance Value of liquidated damages Type of contract/procurement Completeness of documentation Project complexity Current work load Size of contract Need for work Duration of project Location of project Owner (Private/Public) Economy (availability of work) Escalation in material prices Owner s special requirements Use of nominated subcontractor Past profit in similar job Experience in similar project Tendering duration Competitiveness of competitors Establishing relationship with clients Project cash flow Table 10 Project Factors - significance v consideration
11 REFERENCES Ahmad, I. & Minkarah, I. 1988, 'Questionnaire survey on bidding in construction', Journal of Management in Engineering, vol. 4, no. 3, pp Akintoye, A. 2000, 'Analysis of factors influencing project cost estimating practice', Construction Management & Economics, vol. 18, no. 1, pp Akintoye, A. & Fitzgerald, E. 2000, 'A survey of current cost estimating practices in the UK', Construction Management & Economics, vol. 18, no. 2, pp Baccarini, D. & Archer, R. 2001, 'The risk ranking of projects: a methodology', International Journal of Project Management, vol. 19, no. 3, pp Bent, J. A. & Humphreys, K. K. (eds.) 1996, Effective project management through applied cost and schedule control, M. Dekker, New York. Clark, F. D., Lorenzoni, A. B. & Jimenez, M. 1997, Applied cost engineering, 3rd ed., Marcel Dekker, New York. Dulaimi, M. F. & Shan, H. G. 2002, 'The factors influencing bid mark-up decisions of large- and medium-size contractors in Singapore', Construction Management & Economics, vol. 20, no. 7, pp Flanagan, R. & Norman, G. 1993, Risk management and construction, Blackwell Scientific, Oxford, England. Hegazy, T. & Moselhi, O. 1995, 'Elements of cost estimation: A survey in Canada and the United States', Cost Engineering, vol. 37, no. 5, p. 27 Karlsen, J. T. & Lereim, J. 2005, 'Management of Project Contingency and Allowance', Cost Engineering, vol. 47, no. 9, pp Kumar, R. 2005, Research methodology: a step-by-step guide for beginners, 2nd ed., Pearson Longman, Frenchs Forest, N.S.W. Liu, M. & Ling, Y. Y. 2003, 'Using fuzzy neural network approach to estimate contractors' markup', Building and Environment, vol. 38, no. 11, pp Mak, S., Wong, J. & Picken, D. 1998, 'The effect on contingency allowances of using risk analysis in capital cost estimating- a Hong Kong case study', Construction Management and Economics, vol. 16, no. 5, pp McDermott, P. & Rowlinson, S. M. (eds.) 1999, Procurement systems: a guide to best practice in construction, E & FN Spon, London. Moselhi, O. 1997, 'Risk assessment and contingency estimating', AACE International Transactions, vol. b, no. a1, p. 90. Paek, J. H. 1994, 'Contractor risks in conceptual estimating', Cost Engineering, vol. 36, no. 12, pp RCBCI 2002, Discussion paper one - Royal commission into the building and construction industry, Retrieved: 03/04/06, from 201%20Overview.pdf Sarantakos, S. 2005, Social research, 3rd ed., Palgrave Macmillan, Houndmills, Basingstoke, Hampshire; New York. Shash, A. A. & Abdul-Hadi, N. H. 1992, 'Factors affecting a contractor's mark-up size decision in Saudi Arabia.' Construction Management & Economics, vol. 10, no. 5, p Skitmore, M. & Wilcock, J. 1994, 'Estimating processes of smaller builders', Construction Management & Economics, vol. 12, no. 2, pp Smith, G. R. & Bohn, C. M. 1999, 'Small to Medium Contractor Contingency and Assumption of Risk', Journal of Construction Engineering and Management, vol. 125, no. 2, pp Smith, N. J. (ed.) 1995, Project cost estimating, T. Telford, London. Tah, J. H. M., Thorpe, A. & McCaffer, R. 1994, 'A survey of indirect cost estimating in practice.' Construction Management & Economics, vol. 12, no. 1, p. 31. Tilley, P., Gallo, G., Lucas, G., McLennan, A. & Parminter, T. 2002, Project Documentation Quality and its Impact on Efficiency in the Building & Construction Industry, Queensland Division of the Institution of Engineers, Australia, Brisbane
PROJECT RISK MANAGEMENT IN THE QUEENSLAND ENGINEERING CONSTRUCTION INDUSTRY: A SURVEY
Lyons, Terry and Skitmore, Martin (2004) Project risk management in the Queensland engineering construction industry: a survey. International Journal of Project Management 22(1):pp. 51-61. Copyright 2004
ESTIMATING PROJECT COST CONTINGENCY A MODEL AND EXPLORATION OF RESEARCH QUESTIONS
ESTIMATING PROJECT COST CONTINGENCY A MODEL AND EXPLORATION OF RESEARCH QUESTIONS David Baccarini Department of Construction Management, Curtin University of Technology, PO Box U198, Perth 6845, Western
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department
Guaranteed Maximum Price contracts in Western Australia
Guaranteed Maximum Price contracts in Western Australia P. R. Davis 1, D. Stevenson 2 1 Curtin University of Technology Perth WA 2 Project Director INCOLL - Project Management Consultants Corresponding
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the
FACTORS AFFECTING THE BID/ NO BID DECISION MAKING PROCESS OF SMALL TO MEDIUM SIZE CONTRACTORS IN AUCKLAND
FACTORS AFFECTING THE BID/ NO BID DECISION MAKING PROCESS OF SMALL TO MEDIUM SIZE CONTRACTORS IN AUCKLAND Student Name: Huan Ma Student Identification Number: 1330096 A Report for Industry Project CONS
Study of the Importance and Applicability of the Factor "Mark-up in the Budgeting of Construction
Study of the Importance and Applicability of the Factor "Mark-up in the Budgeting of Construction Abstract Forming the price of a service and the subsequent finding of the value of the proposal is based
Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO
Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr
The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2
The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2 1 Curtin University of Technology, Perth, Western Australia 2 Broad Construction Services, Perth, Western
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT Chaitali S. Pawar 1, Suman S. Jain 2, Abhijeet M. Gaikwad 3 1 Post Graduate Student, RMDSSOE, Pune, India. Email: [email protected] 2 Asso.
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry
CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1
Risk Analysis and Quantification
Risk Analysis and Quantification 1 What is Risk Analysis? 2. Risk Analysis Methods 3. The Monte Carlo Method 4. Risk Model 5. What steps must be taken for the development of a Risk Model? 1.What is Risk
Comparing Procurement Methods for Design-Build Projects
Comparing Procurement Methods for Design-Build Projects by Marwa A. El Wardani Technical Report No. 45 Copyright May 2004 Computer Integrated Construction Research Program Department of Architectural Engineering
Characteristics of the Participants
3 Financial Analysis for Replacement of Construction Equipment in Saudi Arabia Ali A. Shash (Center for Engineering Research, Research Institute, King Fahd University of Petroleum & Minerals, Saudi Arabia)
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
A Preliminary Study on Human Resource Management in International Construction
A Preliminary Study on Human Resource Management in International Construction Jianjian Du, Chunlu Liu and David Picken (School of Architecture and Building, Deakin University, Geelong, Australia) ABSTRACT
Measuring, Estimating and Tendering Processes in Construction and the Built Environment
Unit 9: Measuring, Estimating and Tendering Processes in Construction and the Built Environment NQF Level 3: Guided learning hours: 60 BTEC National Unit abstract Estimating is concerned with the processes
Investors in People First Assessment Report
Investors in People First Assessment Report K.H.Construction Cambridge Assessor: Lesley E Ling On-site Date/s: 3 rd September 2008. Recognition Date: Contents 1. Introduction Page 2 2. Assessment and Client
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
Measurement of Banks Exposure to Interest Rate Risk and Principles for the Management of Interest Rate Risk respectively.
INTEREST RATE RISK IN THE BANKING BOOK Over the past decade the Basel Committee on Banking Supervision (the Basel Committee) has released a number of consultative documents discussing the management and
1 The Role of Accounting
5 1 The Role of Accounting Accounting Information Accounting provides financial information for a variety of entities to enable them to make informed judgements and decisions. It is important that you
aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608
aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 NCSA 01 Competency Based Assessment in Architecture THE
CIOB Awarding Organisation. CIOB Level 4 Certificate and Diploma in Site Management (QCF) Syllabus. October 2013
CIOB Awarding Organisation CIOB Certificate and Diploma in Site Management (QCF) Syllabus October 2013 Rev5_RT_07/10/2013 CONTENTS Page No. 1. PROGRAMME STRUCTURE AND RULES OF COMBINATION 1 1.1 Entry Requirements
Report Building Procurement Methods
Report Building Procurement Methods Research Project No: 2006-034-C-02 The research in this report has been carried out by Project Leader Researchers Project Affiliates Peter Davis Peter Davis Peter Love
Association of Independent Schools of NSW Block Grant Authority Limited PROJECT AND CONSTRUCTION MANAGEMENT GUIDELINES
Association of Independent Schools of NSW Block Grant Authority Limited PROJECT AND CONSTRUCTION MANAGEMENT GUIDELINES AIS N.S.W. BGA LIMITED PROJECT AND CONSTRUCTION MANAGEMENT GUIDELINES Project Management:
Dr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction
Speech by the Hon Rimsky Yuen, SC, JP, Secretary for Justice Hong Kong Construction Arbitration Centre & University of Hong Kong Joint Conference on Construction Dispute Resolution 2015 Resolution of Construction
Estimating Project Cost Contingency Beyond the 10% syndrome
Estimating Project Cost Contingency Beyond the 10% syndrome D.Baccarini Faculty of Built Environment, Art & Design, Curtin Univeristy of Technology, Perth, Western Australia ABSTRACT Projects require budgets
ESTIMATION OF PROJECT OVERHEADS: A CONTRACTOR S PERSPECTIVE
ESTIMATION OF PROJECT OVERHEADS: A CONTRACTOR S PERSPECTIVE Caroline Tak Wa Chan 1 and Christine Pasquire 2 1 Division of Building Science and Technology, City University of Hong Kong, Tat Chee Avenue,
6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
Risk Management of Construction - A Graduate Course
(pressing HOME will start a new search) ASC Proceedings of the 37th Annual Conference University of Denver - Denver, Colorado April 4-7, 2001 pp 95-100 Risk Management of Construction - A Graduate Course
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
Review of Business Information Systems Second Quarter 2009 Volume 13, Number 2
An Investigation Into Computerized Estimating Software Used In Accounting For Cost Estimates By Residential Builders Mark D. Law, Bloomsburg University, USA Gary S. Robson, Bloomsburg University, USA ABSTRACT
EXPLORING THE TYPES OF CONSTRUCTION COST MODELLING FOR INDUSTRIALISED BUILDING SYSTEM (IBS) PROJECTS IN MALAYSIA
EXPLORING THE TYPES OF CONSTRUCTION COST MODELLING FOR INDUSTRIALISED BUILDING SYSTEM (IBS) PROJECTS IN MALAYSIA Nor Azmi Ahmad Bari Universiti Putra Malaysia Introduction: Construction cost is an important
DESIGN IS GOOD BUSINESS
COMPENSATING YOUR ARCHITECT The creature comforts are one thing, but for a house to become a home it s got to be elevated to the point that it s about raising one s spirits as well. SAMUEL MOCKBEE Building
CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected] or telephone 029 2031 5512
BIBA Report on the Importance of Advice in the Small to Medium Enterprise Market
BIBA Report on the Importance of Advice in the Small to Medium Enterprise Market The best insurance is a BIBA broker www.biba.org.uk Member helpline: 0845 77 00 266 The FSA define advice as an opinion
EXECUTION RISK MANAGEMENT IN DESIGN-BUILD INFRASTRUCTURE PROJECTS BY JACK DIGNUM, PATRICIA GALLOWAY AND KRIS NIELSEN
EXECUTION RISK MANAGEMENT IN DESIGN-BUILD INFRASTRUCTURE PROJECTS BY JACK DIGNUM, PATRICIA GALLOWAY AND KRIS NIELSEN 1 INTRODUCTION The construction industry at large has utilized the Design-Build construction
A quality assurance and benchmarking framework in an academic library
A quality assurance and benchmarking framework in an academic library Imogen Garner University Librarian Curtin University Library, Australia [email protected] Karen Tang Associate Director Curtin
What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7.
Welcome to the November 2009 INSIGHTS published by acumen7. The purpose of this newsletter is to bring you new perspectives on key subjects to stimulate your own thoughts and ideas. In each edition (which
The SME Engagement Handbook
The SME Engagement Handbook The purpose of this document is to help microbusinesses and small to medium enterprises ( SMEs ) interact more effectively when bidding to supply goods or services to larger
Procurement Routes. Curtin University of Technology
Procurement Routes An Overview Curtin University of Technology Overview of Principal Routes Traditional / conventional design led Design and construct Management (Fee) Traditional Client appoints consultants
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
PERCEPTION OF BASIS OF SHE AND SHE RISK MANAGEMENT
PERCEPTION OF BASIS OF SHE AND SHE RISK MANAGEMENT Per Berg and Roger Preston Safety Section, Global SHE, AstraZeneca INTRODUCTION After the merger between the two pharmaceutical companies Astra and Zeneca
ICE Legal Notes Series
ICE Legal Notes Series Legal Notes Reviewing the work of another Engineer and replacing another Engineer Institution of Civil Engineers www.ice.org.uk Published by the Institution of Civil Engineers (ICE).
A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method
Send Orders for Reprints to [email protected] 254 The Open Cybernetics & Systemics Journal, 2014, 8, 254-258 Open Access A Robustness Simulation Method of Project Schedule based on the Monte Carlo
Employer Demand for Qualifications for Sales Professionals
Employer Demand for Qualifications for Sales Professionals Chichester CWL Development Fund Project Final Report Prepared by: Sandra Coley Business Development Manager 24 th June 2011 Contents Page 1. Introduction
Chapter 1. Introduction
Chapter 1 Introduction What is productivity, how is it measured and why is it important? These questions are a useful starting point from which we can define and explain the range of productivity measures
A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components
Produced for SCALA and the Local Government Task Force by Rob Tate Dip Arch. Dip TP. Dip Arb. FCIArb. RIBA 01582 516662 [email protected] You can contact the Local Government Task Force tel 020 7837
School Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK Mihirkumar B. Naik 1, Dr. Neerajkumar D. Sharma 2, Prof. Bhavin K. Kashiyani 3 PG. Student, S.N. Patel Institute of Technology
SourceIT User Notes. Specific Clauses. Licence and Support Contract Commercial off-the-shelf Software RELEASE VERSION 2.
SourceIT User Notes Specific Clauses Licence and Support Contract Commercial off-the-shelf Software RELEASE VERSION 2.3 DECEMBER 2012 AGIMO is part of the Department of Finance and Deregulation SourceIT
Project Management. [Student s Name] [Name of Institution]
1 Paper: Assignment Style: Harvard Pages: 10 Sources: 7 Level: Master Project Management [Student s Name] [Name of Institution] 2 Project Management Introduction The project management also known as management
Revenue Recognition for Contractors
1 New on the Horizon: Revenue recognition for building and construction July 2010 REAL ESTATE & CONSTRUCTION Revenue Recognition for Contractors A perspective on revenue recognition in the future AUDIT
A Guide to Small Works. A brief explanation
A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here
The South African Council for the Project and Construction Management Professions (SACPCMP)
The South African Council for the Project and Construction Management Professions (SACPCMP) Registration Rules for Professional Construction Mentors in terms of Section 18(1) (c) of the Act, 2000 (Act
INVESTIGATING THE CRITERIA FOR CONTRACTORS SELECTION AND BID EVALUATION IN EGYPT
INVESTIGATING THE CRITERIA FOR CONTRACTORS SELECTION AND BID EVALUATION IN EGYPT M. Salama 1, H. Abd El Aziz 2, H. El Sawah 3 and A. El Samadony 3 1School of Built Environment, Heriot Watt University,
Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia
Implementation of TQM in Manufacturing Industries in the Kingdom of Saudi Arabia Anisur Rahman 1 and Muhammad T. Attar 2 1,2 Griffith School of Engineering, Griffith University, Gold Coast Campus, QLD
Knowledge-Based Sustainable Decision-making Framework for the Implementation of Innovative Technologies in the Malaysian Construction Industry
Knowledge-Based Sustainable Decision-making Framework for the Implementation of Innovative Technologies in the Malaysian Construction Industry ROHANA MAHBUB Faculty of Architecture Planning and Surveying
AN EVALUATION OF CONSTRUCTION CASH FLOW MANAGEMENT APPROACHES IN CONTRACTING ORGANISATIONS. Paper presented at
AN EVALUATION OF CONSTRUCTION CASH FLOW MANAGEMENT APPROACHES IN CONTRACTING ORGANISATIONS Paper presented at The 19 th Annual Association of Researchers in Construction Management (ARCOM) Conference held
Monte Carlo analysis used for Contingency estimating.
Monte Carlo analysis used for Contingency estimating. Author s identification number: Date of authorship: July 24, 2007 Page: 1 of 15 TABLE OF CONTENTS: LIST OF TABLES:...3 LIST OF FIGURES:...3 ABSTRACT:...4
BID/ NO-BID DECISION MODELLING FOR CONSTRUCTION PROJECTS
BID/ NO-BID DECISION MODELLING FOR CONSTRUCTION PROJECTS Abdulrahman Bagies 1 and Chris Fortune School of the Built Environment, Heriot-Watt University, Riccarton Campus, Edinburgh EH14 4AS Not bidding
Surety 101. An Introduction to the Surety Industry
Surety 101 An Introduction to the Surety Industry Surety bonds have played a major role in Canada s growth since they emerged as a modern North American industry in the late 19th and early 20th centuries.
LGRF. Procurement Probity Plan. July 2012
LGRF July 2012 When to develop a : A probity plan is best used for any procurement of medium complexity and size and above. A probity plan can be implemented without use of a probity advisor/auditor. Description
Procurement Strategy and Contract Selection
GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works
Procurement of Goods, Services and Works Policy
Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March
1.1 Introduction. Chapter 1: Feasibility Studies: An Overview
Chapter 1: Introduction 1.1 Introduction Every long term decision the firm makes is a capital budgeting decision whenever it changes the company s cash flows. Consider launching a new product. This involves
Capital Works Management Framework
POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset
GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities
GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement
How to get value for money from service providers on major projects
How to get value for money from service providers on major projects Session Focus Contracting as a relationship Identifying win/win arrangements Procurement & Planning on major projects Understanding the
Operational Parameters. for the. Review and Evaluation of. Construction Management Projects
Operational Parameters for the Review and Evaluation of Construction Management Projects Operational Parameters for the Review and Evaluation of Construction Management Projects Table of Contents Introduction...
Procurement guidance Prequalifying suppliers
Procurement guidance Prequalifying suppliers Procurement guidance: Prequalifying suppliers Page 2 of 21 Table of contents Table of contents... 2 Purpose of this Guide... 4 Who should read this Guide?...
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
Standards of proficiency. Dietitians
Standards of proficiency Dietitians Contents Foreword 1 Introduction 3 Standards of proficiency 7 Foreword We are pleased to present the Health and Care Professions Council s standards of proficiency for
The New Standard Construction Contracts: NZS3910, 3916 and 3917
The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of
Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel
Page 1 of 6 ALM Properties, Inc. Page printed from: New York Law Journal Back to Article Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel James E. Hughes New York
Digital Inclusion Programme Started. BL2a
PROJECT BRIEF Project Name Digital Inclusion Programme Status: Started Release 18.05.2011 Reference Number: BL2a Purpose This document provides a firm foundation for a project and defines all major aspects
CIPS Exam Report for Learner Community:
CIPS Exam Report for Learner Community: Qualification: Unit: Exam series: Advanced diploma in procurement and supply AD2 Management risk in supply chains November, 2013 Exam Series INFORMATION FOR CANDIDATES
WORKPLACE SAFETY KIT A STEP BY STEP GUIDE TO SAFETY FOR BUSINESS GUIDE 2001. WorkCover NSW Health and Safety Guide. WorkCover. Watching out for you.
WORKPLACE SAFETY KIT A STEP BY STEP GUIDE TO SAFETY FOR BUSINESS GUIDE 2001 WorkCover NSW Health and Safety Guide WorkCover. Watching out for you. Table of Contents Table of Content: How to Use the Workplace
Australian Standard. General conditions of contract for design and construct. AS 4300 1995 (Incorporating Amendment No. 1)
AS 4300 1995 (Incorporating Amendment No. 1) Australian Standard General conditions of contract for design and construct This Australian Standard was prepared by Committee OB/3, General Conditions of Contract.
Factors Affecting the Accuracy of Pre-Tender Cost Estimates in the Gaza Strip
Journal of Construction in Developing Countries, 18(1), 73 94, 2013 Factors Affecting the Accuracy of Pre-Tender Cost Estimates in the Gaza Strip * Adnan Enshassi 1, Sherif Mohamed 2 and Munther Abdel-Hadi
Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process
CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
Risk Workshop Overview. MOX Safety Fuels the Future
Risk Workshop Overview RISK MANAGEMENT PROGRAM SUMMARY CONTENTS: Control Account Element Definition ESUA Form Basis of Estimate Uncertainty Calculation Management Reserve 1. Overview 2. ESUA Qualification
Developing a Public-Private Partnership Framework: Policies and PPP Units
Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
Barriers to Affordable & Accessible Student Accommodation
Barriers to Affordable & Accessible Student Accommodation June 2015 STAFF RESPONSIBLE FOR THIS REPORT WERE: Director Associate Director Senior Consultant Job Code Clinton Ostwald Mark Dawson Ryan Mackenzie
RISK MITIGATION IN FAST TRACKING PROJECTS
Voorbeeld paper CCE certificering RISK MITIGATION IN FAST TRACKING PROJECTS Author ID # 4396 June 2002 G:\DACE\certificering\AACEI\presentation 2003 page 1 of 17 Table of Contents Abstract...3 Introduction...4
Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting
Rebuilding Flood Damaged Roads in South East Queensland in the middle of the Coal Seam Gas Expansion/Explosion - A Local Governments Experience and Learning's David Pemberton [email protected] Mobile
Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004
Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 1. INTRODUCTION Financial institutions outsource business activities, functions and processes
Managing Software Development Projects
Managing Software Development Projects Technical Writing (English 4010) University of Wyoming Laramie, Wyoming By Dan Randolph Graduate Student in Computer Science May 09, 2001 CONTENTS page Abstract...........
Introduction. Project Management in New Zealand
AN ANALYSIS OF THE USE OF INFORMATION TECHNOLOGY FOR PROJECT MANAGEMENT IN THE NEW ZEALAND CONSTRUCTION INDUSTRY Dr Suzanne Wilkinson, Senior Lecturer, Department of Civil and Resource Engineering The