TECHNICAL BASELINE MANAGEMENT SYSTEM- A LIFE CYCLE PROJECT PLANNING AND TRACKING SYSTEM
|
|
|
- Alvin Bailey
- 9 years ago
- Views:
Transcription
1 ABSTRACT TECHNICAL BASELINE MANAGEMENT SYSTEM- A LIFE CYCLE PROJECT PLANNING AND TRACKING SYSTEM Rick Millikin, BWXT of Ohio Doug Wertz, Fluor Hanford Inc. Ricardo Martinez, Project Enhancement Corporation Pasquale Volza, Project Enhancement Corporation Sue Bracey, Project Enhancement Corporation In recent years, the focus of the U.S. Department of Energy (DOE) complex has shifted from production to facility stabilization, deactivation, decommissioning, and environmental restoration. The decision to transition a facility from an operating mode through stabilization, deactivation and decommissioning typically requires development of a new project baseline plan to establish the project life cycle cost and schedule. This paper describes an integrated systems engineering/project management planning tool that has been used successfully in the past (the Hanford Plutonium Finishing Plant [PFP], Hanford 300 Area), and is also currently being used (Mound Facilities), to plan the transition of DOE facilities in a way that is consistent with the requirements provided in DOE Order 430.1A, Life Cycle Asset Management (LCAM). The DOE has developed four guides to provide implementation guidance for requirements found in DOE Order 430.1A, specific to the transition and disposition of these contaminated, excess facilities. The LCAM Order requires that a systematic method for detailed engineering planning and documentation be used to execute the preferred deactivation alternative. As such, a systems engineering approach has been recommended for use throughout this process to ensure the essential elements of the deactivation process are integrated at all appropriate levels. DOE Guide , Deactivation Implementation Guide, provides the recommended content and purpose of deactivation project management plans and documentation. In order to facilitate the development and revision of project baselines and minimize the impact on facility resources, a data base management system, Technical Baseline Management System (TBSM) was developed and used at Hanford to manage the linkage between the project technical elements and the functional elements of the Work Breakdown Structure (WBS). The methods, tools and products derived from the Hanford facilities efforts provided useful lessons learned and templates for the Mound Site and other DOE facilities planning transition and D&D projects. This paper explains the life cycle project planning and tracking system, TBMS, which has been previously used at Hanford and is currently being utilized by the Mound site to manage the linkage between the technical elements and the functional elements of the Work Breakdown Structure (WBS). Although papers have been presented in the past on similar projects at Hanford, the intent of this paper is to show how this management system, and its planning tools, have evolved and how the system can be used at other DOE facilities planning transition and D&D projects.
2 INTRODUCTION Facilities undergoing deactivation transition planning require Technical/Cost and Schedule baselines to be developed and maintained to meet customer expectations on scope analysis, schedule certainty, and quality of estimate. Issues specific to major deactivation transition planning project missions and baseline maintenance include (see Figure 1): Maintaining Safe and Compliant Conditions, specifically: Confidence in project estimate, and Requirements basis Stabilizing/Disposition of Nuclear Materials, specifically: Confidence in project schedule, Delay in DOE Complex commitments to the DNSFB, and Interface/Approach inconsistencies throughout the complex Transition Planning, specifically: Confidence in project scope/schedule/estimate, and Impending State CERCLA/RCRA negotiations/agreements Other Factors: Facility/Stakeholder expectations for re-baseline quality versus compressed schedule and competing priorities, and Contract Performance Agreements to establish the Life Cycle cost/schedule baseline. Technical Baseline Data often needs to be developed from a clean slate. This is usually done when the facility is in a shut down mode or is just completing final operations. The Facility deactivation planning Work Breakdown Structure (WBS) is normally developed functionally, based on system end points and other requirement drivers. Often, a focused Planning Team approach is used to develop initial baselines. The development of a project baseline requires a significant expenditure of resources and typically results in the generation of a high volume of information and data (studies, requirements, product and waste inputs/outputs, issues and assumptions, interfaces, etc.). For relatively small projects, the skilled project manager is able to manage these in subproject plans and project estimates/schedules. For more complex projects, the data is too voluminous and if not properly captured, integrated, maintained, and managed, this critical project information can be lost or difficult to find and link to the appropriate project elements. It was for this intended purpose that TBMS was developed, to integrate technical, cost, and schedule baseline information. In doing so it allows the project manager easy development and management of program plans, and provides a retrievable and traceable means for managing programmatic baseline data.
3 DOE Issues Shutdow n Maintain Facility in a Safe and Compliant Condition Maintain Safeguards & Security of SNM Stabilize Nuclear Materials/Wastes Disposition Nuclear Materials/Wastes Deactivation Planning Key is to Projectize the Baseline using a Functionally Based/ Requirements Driven Fig. 1. Transition Efforts Deactivation of Inactive Deactivation of Remaining Areas & Systems Dismantlement to End State Transfer to Site Environmental Restoration Contractor
4 The TBMS is a life cycle project planning and tracking system (Figure 2) that provides the deactivation activity project manager with a tool to assimilate and monitor project implementation criteria. The system is built around the project s functional analysis as defined by the work breakdown structure (WBS). The WBS is mapped to all baseline elements (technical scope descriptions, requirements, work location descriptions, hazards identification, risks, interfaces, technical scope, issues/assumptions, input/output quantities, project resource estimates and duration, etc.). The TBMS provides project managers the ability to quickly identify and assess impacts of changes to any change in a project technical element. The system also provides the project manager with tracking capabilities for technical issues, enabling assumptions, alternatives analysis, decision points, waste forecasts, and interface control documentation. PROJECT DATA MANAGEMENT AND CONTROL The TBMS was developed to collect and manage the key information that comprises the project baseline. The TBMS relies on a link to the appropriate WBS element to archive and retrieve critical information. This link allows the project manager to generate reports by data type (e.g., requirements) for a specific WBS element. The reports can then be used to evaluate quickly and effectively the impact of proposed changes on the project baseline and provides for high confidence corporate memory as the project evolves. It is also used to compile and generate the Basis of Estimate documents that support the project cost estimate and schedule. Figure 3 depicts the information provided in a typical Basis of Estimate document which is maintained by the TBMS. Figure 4 provides an outline of the TBMS structure and data element relationships. System Structure The TBMS is driven by Microsoft Access software with window driven input and display screens. The screens and available data are dependent on the level in the WBS requested. The system can be input directly from the input screen or data can be transferred in via Access or Excel spreadsheets. The system was developed in this manner to allow for multiple users to provide input on standalone spreadsheets (i.e., waste forecast, requirements, location assessments) where going through multiple WBS items was not efficient. Once these import files are prepared, a mapping exercise to the specific WBS is required prior to importing into the TBMS. Security is provided through a data administrator and again is tied to the WBS. Change control is managed by the database administrator through authorizing change control numbers into TBMS that changes can be recorded against. Once a change control action is ready for management approval, a change control package can be generated out of TBMS to include all of the affected project elements.
5 Fig. 2. Technical Baseline Management
6 Technical Cost, and Schedule Baseline Systems Engineering Project Management Life-Cycle Estimating Resource Loaded Schedules Cost Estimate Project Schedule (P3) Logic Diagrams Basis of Estimate Waste Streams Inputs/Outputs Alternatives Analysis Responsibility Assignment Matrix Location Assessment Interface Management List Requirements Analysis Issues & Assumptions Functions & Scope Statements BASIS OF ESTIMATE Fig. 3. Technical Baseline Management
7 Fig. 4. TBMS Data Relationship
8 Facility User Security WBS Dictionary Locations by WBS Location Identifiers Building Alternative Analysis by WBS Alternative Analysis Assumption/Issue by WBS Assumptions/ Issues Types Methodology and Historical Data Purpose of Estimate Miscellaneous Budget and Reporting P3 Cost Estimate Input Sheet (CEIS) Area/System Methodology Action Type Basis of Estimate Organization CEIS (MS-Excel Spreadsheet) Room Existing Equipment Hazards Security Special Working Conditions Alternatives Analysis Final Alternatives Path Forward Document ID Description Requirement by WBS Requirement Types Descriptions Deliverables References Methodology/ Historic Rates Input/Output Interface Facility Interface Document CACN Rates Contingency Facility Identifiers Validation Criteria Report List Menu IDs Milestone Description Sheets Milestone Closeout Validated Resources Organization Codes Code of Accounts Activity IDs PowerTool Cost Resources Cost Code Fig. 5. TBMS Data Relationship
9 TBMS Modules As stated earlier, the TBMS is developed and integrated around the projects functional analysis or WBS. The TBMS contains data tables/input screens or modules for the following project elements (Figure 4 & 5): Requirements, Issues/Assumptions, Locations, Interfaces, Inputs/Outputs, Milestones, and Resources. Requirements. Contains requirement reference, brief description, requirement deliverable (expectation or outcome), and type (for sorting purposes) Issues/Assumptions. Contains Issue or Assumption description, type, impact, closeout requirements, closeout due dates, enabling assumption used in the baseline, champion, sponsor, and schedule requirements. Locations. Contains data for the buildings, areas, systems, rooms, and components. Data includes as-is condition, radiological, chemical, and industrial hazards, and special working conditions. Interfaces. Contains internal and external interfaces between project functions (WBS). This lists interface description, receiving and supporting function, the interface control document, required documentation, document author, and schedule requirements. Inputs/Outputs. Records system inputs and outputs related to material and waste processing. Other inputs/outputs could be tracked if desired (i.e., support materials and utilities). Details include input/output source and receiver, quantity type (i.e., cubic feet or meters, cans or items), packaging type, schedule data, and spreads over early start/early finish. Milestones. Provides a milestone description sheet and historical closeout notes page. Resources. Contains a Cost Estimating Input Sheet with planning assumptions, estimate stage, resource requirements, and notes page to record calculations. User Interface The TBMS was developed to be on a local area network server with both read-only and read-write capabilities. The user primarily needs to know Windows point and click applications, although knowledge of Excel and/or Word is helpful. The system contains user help options. System Interface TBMS has the capability to send export files to various site level systems including the site managed technical baseline system, and the site standard scheduling estimating system (currently Primavera P3). TBMS FEATURES AND BENEFITS As stated earlier, TBMS provides project managers the ability to quickly identify and assess impacts of changes to any change in a project technical element. The system also provides the project manager with tracking capabilities for technical issues, enabling assumptions, alternatives analysis, decision points, waste forecasts, and interface control documentation. Additional features and benefits of TBMS are: TBMS is used as a repository and report writer for Basis Of Estimate documents (Project Management Plan basis): Basis of estimates can be customized for printing at any level of the WBS for the particular project needs, and
10 Has the rigor and trace ability needed to withstand Independent Cost Estimating (ICE) team reviews TBMS provides the ability to generate other useful reports: Waste Forecasts Issues Management (risk reduction/avoidance) Interface Management Endpoint Close-out (requirements management) Location Analysis Subproject Management Plans TBMS provides other management tools: Provides a tool for doing what if exercises. Provides online/real time access of data for regulatory documents/reports. Provides a management tool for managing risks and future baseline change requests. TBMS FIELD EXPERIENCE AND LESSONS LEARNED TBMS is currently being used on a number of transition project (program) applications Hanford 300 Area, Accelerated Closure Project Plan & Hanford 324/327, Rev. 3 Project Management Plan development - Integrates Data from Multiple Site Contractors - Produces custom slice reports - Basis for Performance - Supports Waste Forecasting & Issues Management Hanford PFP, Rev. 3 Integrated Project Management Plan (IPMP) Update - Basis of Estimate (BOE) update Mound Advanced Technology Site, Mound Exit Project Plan (See Lessons Learned) - Basis of Estimate (BOE) update - Integrates data from multiple site groups - Supports issue and risk management activities - Supports sub-project management plans TBMS is also being used to support project & subproject level execution. Project Plans/Engineering Analysis/Change processes at Hanford and Mound
11 LESSONS LEARNED The use of Technical Baseline Management System at Mound Early in Fiscal 2000, the Mound Site began a revision to the site baseline. This was required to implement a new technical approach associated with its critical path project, Main Hill Tritium. In addition, changes to operable unit cleanup strategies and other changed conditions within noncritical path projects needed to be incorporated into the baseline. The work breakdown structure (WBS) and schedule network required significant updating to reflect the incorporation of technical approach and changed conditions. During the development of this new structure enabling assumptions and potential issues were encountered in order to continue development of the network without the benefit of completed alternatives analysis and/or definitive design. In order to complete such a revision to the baseline the tools to be employed to develop the baseline were reviewed. The Mound Site used Timberline as a scheduling tool, Primavera as the scheduling tool, and COBRA as a performance measurement tool. It was determined that the scheduling, estimating, and performance measurement tools were more than adequate to complete the revision and manage the resultant baseline. What was missing was an integrated tool to manage the technical baseline. The Technical Baseline Management System (TBMS) was evaluated and was selected as the tool to assist in managing the technical baseline. The WBS was cross-walked to the activity identification numbers (ActID) in the Primavera Schedule. For Main Hill Tritium an eighth level of WBS was developed to correspond with the assembly detail in the Timberline estimate (level 7 matched the ActID on the schedule). Scope of work descriptions were then assembled for each level of the WBS. While assembling these scope descriptions, the WBS level was also evaluated for enabling assumptions, technical or regulatory issues, interfaces and basic assumptions. This evaluation was documented in the Issues/Assumptions module of TBMS for evaluation, use in the Project Risk Assessment, and future issue/assumption resolution and management. In addition WBS elements that generated waste were analyzed for waste characterization, volumes, projected containerization strategy, and final destination. This data has been loaded into the input/output module of TBMS and was used to be the basis for the waste forecast. Although TBMS has other modules associated with location specific analysis, the milestone module, and requirements basis. These modules have yet to be used at mound. The location and milestone module will probably not be used since others systems exist on site that meet those needs. In the future Mound will continue to use TBMS to manage the technical baseline including baseline change control for technical issues, issues/assumption and risk management, and waste forecasting. If funding allows, we would also like to complete the requirements analysis module and network TBMS to the rest of the Mound Site. It has been a valuable tool during the last year saving many
12 computer input labor hours due to its relational database features, and in assembling issues, assumption, scope, and waste baseline data that may have slipped through the cracks during the baseline development process. The use of Technical Baseline Management System at the Plutonium Finishing Plant The TBMS system was evaluated and selected at PFP to assist in the development of the basis of estimates (BOE) reports for the PFP annual Project Management Plan. These reports are based on Work Breakdown Schedule (WBS) provided on the site wide Primavera baseline system and its change control process. Scope of work definitions are assembled at each level of the WBS and the BOE reports them at the eighth level. At this time there is no direct data link between Primavara and TBMS. PFP is looking to partner with the 300 Area in its effort to enhance TBMS and make it an integrated system between Primavara, the site schedulers, and the site planners. TBMS Field Experience and Lessons Learned at the 324/327 buildings at Hanford TBMS is being employed in deactivation and transition projects. The software is compliant with networking protocol and is accessible to multiple users and locations simultaneously. Richland Operations, Hanford Washington: 324/327 Buildings Stabilization / Deactivation Project, Project Management Plan (PMP). This project represents the birthplace of the concept of capturing a complete basis of estimate (BOE) in an electronic database that became known as TBMS. Since inception in FY 1998, the TBMS has been improved and upgraded with respect to the depth of interrelationships between the work breakdown structure and the basis of estimate information components, cost resource tables, and reporting functions. The 324/327 PMP has been through three revisions, utilizing TBMS for the 2 nd and 3 rd revisions. Only a limited number of hardcopy volume sets were delivered for Rev. 3, with the contractor and customer (DOE-RL) instead relying on the electronic database of information for validation and acceptance. The use of TBMS greatly eased the task of validation and the gaining of acceptance of the estimate by the customer. Having now entered the maintenance mode, an annual upgrade to the PMP will occur in FY 2001 through the use of TBMS. DESKTOP ROLLOUT: 324/327 PMP FY 2000 TBMS was made available on a limited number of desktops (15 personnel) through use of the HANFORD Intranet in FY 2000, where it has been used by both Project Managers and Baseline Control / Project Control personnel. The most common use for TBMS has been to access and make reference to the technical description of work to be performed, located in the BOE s, and other informational tables including Issues Management, Waste Forecasts and Customer Requirements. Project Planning and Integration staff were able to complete a risk analysis evaluation of the 324/327 Project with minimal participation / disruption of the facility through use of the information contained in TBMS.
13 UPDATE CAPABILITY AND CONFIGURATION CONTROL Finalization of the TBMS planning module, which will allow for online revision and configuration control of baseline changes in nearing completion and is scheduled for implementation in March This module will allow the users to generate, review, approve and electronically update the data tables concurrent with baseline changes. This will greatly ease TBMS s information maintenance requirements and save the man-hours previously required when periodically upgrading and validating a basis of estimate during fiscal year work planning and out-year budgetary cycles. Built into this updating / configuration control feature is the assignment of different user classes to include read only, read and write in selected databases, and overall master editor with administrative update capability, designated and controlled by user access. Therefore, effective control of the data contained within TBMS can be achieved using the power of both software-access control and administrative procedure. SITE INTRANET COMPATABILITY TBMS will be available for download and access by any user at the Hanford site in April Included in this upgrade are the databases for the 324/327 PMP, the Plutonium Finishing Plant (PFP) Integrated Project Management Plan (IPMP), and the 300 Area Accelerated Closure Plan (300 ACP). Managed by the Site s Information Resource Management (IRM) contractor (Lockheed Martin Services, Inc.- LMSI), TBMS will complete final software testing and conform to all production software procedures and protocol. The completion of this phase will serve to bolster the confidence that potential users of this system may have as they consider adoption at other deactivation sites throughout the Complex. The TBMS core software was upgraded to Microsoft Access 2000 in January AREA CLOSURE PLAN (300 ACP) The flexibility and power this system was demonstrated in FY 2000 when a multi-contractor team (Fluor Hanford, Inc., Bechtel Hanford Inc., and Battelle-Pacific Northwest National Laboratory) assembled a deactivation project basis of estimate utilizing the structure and informational modules available with TBMS. Of significance was the ability of the users to import cost information from several different tools including POWERTOOL, a deactivation endpoint determination software that is being used at multiple sites throughout the Complex. Having TBMS available at the onset of this project was of great benefit in that the team was able to quickly agree on the content and format of the product that was required for delivery. Access to this information database is included in the site Intranet rollout previously discussed in this paper. Lessons Learned The use of Crystal Software as the report writer for TBMS has reduced the flexibility and ease in developing / changing report outputs that have been requested by multiple users. The inclusion of Crystal Report software added to the professional appearance of the reports available in TBMS but has restricted the ease in which new reports or variations of basic report formats can be gained. With a majority of available personnel resources being more familiar with
14 Microsoft Access software and few Crystal Report software personnel available, a change in the report writer to Microsoft Access is being contemplated. Tests on alternate report generation capability are scheduled for FY 2001.
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
TOOLS FOR CLOSURE PROJECT AND CONTRACT MANAGEMENT: DEVELOPMENT OF THE ROCKY FLATS INTEGRATED CLOSURE PROJECT BASELINE
TOOLS FOR CLOSURE PROJECT AND CONTRACT MANAGEMENT: DEVELOPMENT OF THE ROCKY FLATS INTEGRATED CLOSURE PROJECT BASELINE C.M. Gelles, F.R. Sheppard United States Department of Energy Office of Environmental
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
Multi-Site Project Management A Program for Reducing the Cost of Technology Deployment at Department of Energy Sites - 9480
Multi-Site Project Management A Program for Reducing the Cost of Technology Deployment at Department of Energy Sites - 9480 N. R. Davis, E. R. Selden, D. B. Little, M. C. Coleman, J. T. Bennett Washington
Independent Verification and Validation of SAPHIRE 8 Software Project Plan
INL/EXT-09-17022 Rev. 2 Independent Verification and Validation of SAPHIRE 8 Software Project Plan March 2010 The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance
11.0 WORK SCHEDULE, WORK PLANS, AND ASSOCIATED REPORTS
11.1 INTRODUCTION 11.0 WORK SCHEDULE, WORK PLANS, AND ASSOCIATED REPORTS This section describes the format and content of the work schedule, supporting plans and reports, and the process for updates and
300 Scheduling and Budgeting
Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes
// Benchmarking Project Schedules
// Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...
PROJECT MANGEMENT PLAN EXAMPLES Prepare Baselines - Performance Baseline Examples
PROJECT MANGEMENT PLAN EXAMPLES Prepare Baselines - Performance Baseline Examples Example 34 6.0 PROJECT BASELINE This section presents a summary of the PFP Stabilization and Deactivation Project baseline,
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Project Risk Assessment Examples
PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Project Risk Assessment Examples Example 54 10.0 PROJECT RISK This section outlines a methodology which will be used to
Mastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft
DEVELOPMENT OF PROCESS TEMPLATES AS A PROJECT MANAGEMENT TOOL FOR THE PLUTONIUM FINISHING PLANT
DEVELOPMENT OF PROCESS TEMPLATES AS A PROJECT MANAGEMENT TOOL FOR THE PLUTONIUM FINISHING PLANT ABSTRACT William G. Jasen, Project Enhancement Corporation Thomas W. Halverson, Fluor Hanford, Inc. Steven
What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate
The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re
PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples
PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples Example 40 5.0 PROJECT MANAGEMENT AND CONTROL The Project Management
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
NE-50413B Mastering Microsoft Project 2010
NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
Baseline Change Control Procedure
Earned Value Management System (EVMS) Implementing Procedures Baseline Change Control Procedure EVMS-P-7 Revision 0 - October, 2006 Change Log Earned Value Management System Procedure Change Log Revision
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
REAL PROPERTY ASSET MANAGEMENT (DOE O 430.1B) REQUIREMENTS CHECKLIST
DOE O 430.1B Requirements The management of real property assets must take a corporate, holistic, and performance-based approach to real property life-cycle asset management that links real property asset
Microsoft Project Professional
Microsoft Project Professional A 100% practical workshop to master Microsoft Project, training the main features of the application for project management. Objective Insight into the functions required
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Scott M. Francis, P.E., PSP Table of Contents 1. INTRODUCTION...
Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.
Project Management Institute Construction Extension to A Guide to the Project Management Body of Knowledge PMBOK Guide 2000 Edition Provisional Construction Extension to A Guide to the Project Management
CDC UNIFIED PROCESS JOB AID
Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related
Project Time Management an essential element to project success
Project Time Management an essential element to project success Abstract This paper discusses the reasons behind the necessity to apply sound Project Time Management principles and processes to projects
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
NFSA Project Management Guidelines
NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and
PHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
Supporting Workflow Overview. CSC532 Fall06
Supporting Workflow Overview CSC532 Fall06 Objectives: Supporting Workflows Define the supporting workflows Understand how to apply the supporting workflows Understand the activities necessary to configure
Project Management Terms
FDM 2-1 Attachment 1.1 Terms Terms Baseline Term Baseline Budget Baseline Schedule Baseline Scope Budget Budget Change Control Communication Corrective Action Cost-Benefit Analysis Critical Path Decision
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
PHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)
Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
Abar Solutions Petroleum Consultancy & Training Qualified From KPC Training & Consulting Services Provider. Code Period Language Start End Location
Training Course : Project Management Skills & Estimation Development Training Course For One Week In Canada, Montreal, Hyatt Regency Montreal Which Be Held As Under Details : Tel. : 00965 22610021 99600277,
CHAPTER 4 TYPES OF COST ESTIMATES
CHAPTER 4 TYPES OF COST ESTIMATES 1. INTRODUCTION All projects, both construction and environmental restoration, require cost estimates to plan and budget the project efficiently. Numerous estimates are
How project management software can smooth the way
How project management software can smooth the way By Michael V. Brown New Standard Institute The most demanding call on maintenance resources comes when a plant or facility is shut down for an extended
Project Management Planning
The Project Plan Template The Project Plan The project plan forms the basis for all management efforts associated with the project. A project plan template is included in this document. The information
A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition
Brochure More information from http://www.researchandmarkets.com/reports/2326795/ A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition Description: A compendium of ready made
Managing and Maintaining Windows Server 2008 Servers
Managing and Maintaining Windows Server 2008 Servers Course Number: 6430A Length: 5 Day(s) Certification Exam There are no exams associated with this course. Course Overview This five day instructor led
MDS. Measured Data Server Online Measurement Network. Properties and Benefits »»» »»»» ProduCt information
ProduCt information MDS Measured Data Server Online Measurement Network Properties and Benefits Unlimited access to your data via Internet Measured data can be transferred online in minute intervals Economical
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
CA Clarity PPM. Project Management User Guide. v13.0.00
CA Clarity PPM Project Management User Guide v13.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation )
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
Assessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
SECTION 4 TESTING & QUALITY CONTROL
Page 1 SECTION 4 TESTING & QUALITY CONTROL TESTING METHODOLOGY & THE TESTING LIFECYCLE The stages of the Testing Life Cycle are: Requirements Analysis, Planning, Test Case Development, Test Environment
Project Management Courses
A well planned project will give results exactly as planned. Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the delivery
3. SCHEDULING THE MOST IMPORTANT PHASE PLANNING ACTIVITY. 3.1 Project Management Software Does it Really Do That?
3. SCHEDULING THE MOST IMPORTANT PHASE PLANNING ACTIVITY 3.1 Project Management Software Does it Really Do That? Not really it doesn t do any management that takes a talented human like you! A betternamed
Introduction. Editions
Introduction TRAIN TRACK Employee Training Management Software gives you the tools you need to make sure employee training requirements are met. Assign required training for groups or individuals. Easily
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in
Process Guide. Release Management. Service Improvement Program (SIP)
Process Guide Release Service Improvement Program (SIP) i Table of Contents Process Guide Release Document Information... 3 Approval... 4 Section 1: Process Vision... 6 Overview... 6 Process Mission and
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
Restoration Toolkit. Jerel G. Nelson. Technical Director Global Restoration Technologies
Restoration Toolkit A unique suite of customizable tools combining experience, proven processes, and rigor to enhance performance, deliver technical quality and confidence, and provide added value Jerel
The Fast Forward MBA in Project Management. 4th Edition
Brochure More information from http://www.researchandmarkets.com/reports/2218300/ The Fast Forward MBA in Project Management. 4th Edition Description: An updated and revised edition of the bestselling
The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision of resources to support service requirements.
CAPACITY AND AVAILABILITY MANAGEMENT A Project Management Process Area at Maturity Level 3 Purpose The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision
Facility Maintenance Management Competency 4.9
Competency 4.9 Facility maintenance management personnel shall demonstrate the ability to perform project management duties as required to provide facility maintenance management technical support to a
5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]
231 5.2 Template for IT Project Plan Name of the Tool: Source: Usage: Description: Template for IT Project Plan GIZ This template has been designed as a tool to support the planning of IT projects for
Mastering Microsoft Project 2013
Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals
Project Management Planning
Overview of Project Scheduling Following the definition of project activities, the activities are associated with time to create a project schedule. The project schedule provides a graphical representation
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days
3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: [email protected] Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:
Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP
Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented
The Fast Track Project Glossary is organized into four sections for ease of use:
The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face
5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter
Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the
Using Microsoft SharePoint for Project Management
ASPE IT Training Using Microsoft SharePoint for Project Management A WHITE PAPER PRESENTED BY ASPE www.aspe-it.com 877-800-5221 Using Microsoft SharePoint for Project Management A modern Project Management
NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE Head, Office of Project Support Services
Overview of the Remedial Action Cost Engineering Requirements (RACER ) Software
Overview of the Remedial Action Cost Engineering Requirements (RACER ) Software For More Information, Please Contact: Andrew Schleppi RACER Product Line Manager 717 17th Street, Suite 2600 Denver, CO 80202
Bureau of Land Management. Information System Decommissioning Guide
Department Bureau of the Land Interior Management Bureau of Land Management Information System Decommissioning Guide Version Control Log Date Version # Author Description January 11, 2011 0.1 WO-550 Original
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
Accounting System. Page 1 of 9
Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems
Frequently Asked Questions in Project Management
Frequently Asked Questions in Project Management 1. Question: What is Project Management? Answer: Project Management is the collection and application of skills, knowledge, processes, and activities to
Project Managing to Support Change. Cathryn Stam, PMP Tina Salaris, RN, PMP
Project Managing to Support Change Cathryn Stam, PMP Tina Salaris, RN, PMP Project Managing to Support Change Change is a constant in life People by nature do not like change Whether redesigning processes
Project Management Courses
"A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the
Earned Value Management System (EVMS) Manual. System Description and Implementing Procedures
Manual System Description and Implementing Procedures Manual System Description and Implementing Procedures Contact Information This document is maintained, updated, and formally revised electronically
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Fred Moavenzadeh Spring 2009
SECTION 16926 CONTROL SOFTWARE
SECTION 16926 CONTROL SOFTWARE PART 1 GENERAL 1.01 SUMMARY: A. Contractor shall furnish a complete control software package for the Red River Wastewater Treatment Plant and the Northeast Wastewater Treatment
