Contract No. EP/SP/61/10 Organic Waste Treatment Facilities Phase 1: First Monthly EM&A Report
|
|
|
- Abraham Clarence Blake
- 10 years ago
- Views:
Transcription
1 MONTHLY EM&A REPORT OSCAR Bioenergy Joint Venture Contract No. EP/SP/61/10 Organic Waste Treatment Facilities Phase 1: First Monthly EM&A Report 21 May June 2015 Environmental Resources Management 16/F, Berkshire House, 25 Westlands Road, Quarry Bay, Hong Kong Telephone: (852) Facsimile: (852) http: //
2
3
4 CONTENTS EXECUTIVE SUMMARY 1 INRODUCTION PURPOSE OF THE REPORT STRUCTURE OF THE REPORT 1 2 PROJECT INFORMATION BACKGROUND GENERAL SITE DESCRIPTION CONSTRUCTION ACTIVITIES PROJECT ORGANISATION AND MANAGEMENT STRUCTURE STATUS OF ENVIRONMENTAL APPROVAL DOCUMENTS 4 3 ENVIRONMENTAL MONITORING REQUIREMENT, ENVIRONMENTAL MITIGATION MEASURES 5 4 IMPLEMENTATION STATUS ON ENVIRONMENTAL PROTECTION REQUIREMENTS 6 5 WASTE MANAGEMENT 7 6 ENVIRONMENTAL INSPECTIONS WEEKLY SITE AUDITS LANDSCAPE AND VISUAL AUDIT 9 7 ENVIRONMENTAL NON-CONFORMANCE SUMMARY OF ENVIRONMENTAL NON-COMPLIANCE SUMMARY OF ENVIRONMENTAL COMPLAINT SUMMARY OF ENVIRONMENTAL SUMMON AND SUCCESSFUL PROSECUTION 12 8 FUTURE KEY ISSUES KEY ISSUES FOR THE COMING MONTH CONSTRUCTION PROGRAMME 13 9 CONCLUSIONS 14
5 LIST OF TABLES Table 2.1 Table 2.2 Table 5.1 Table 8.1 Summary of Construction Activities Undertaken in the Reporting Period Summary of Environmental Licensing, Notification and Permit Status Quantities of Waste Generated from the Project Construction Works to be undertaken in the Next Reporting Period LIST OF ANNEXES ANNEX A ANNEX B ANNEX C ANNEX D ANNEX E ANNEX F ANNEX G LOCATION OF PROJECT WORKS LOCATION CONSTRUCTION PROGRAMME FOR THE PROJECT PROJECT ORGANIZATION CHART AND CONTACT DETAIL IMPLEMENTATION SCHEDULE OF MITIGATION MEASURES WASTE FLOW TABLE ENVIRONMENTAL COMPLAINT, ENVIRONMENTAL SUMMONS AND PROSECUTION LOG
6 EXECUTIVE SUMMARY The construction works of No. EP/SP/61/10 Organic Waste Treatment Facilities Phase I (the Project) commenced on 21 May This is the 1 st monthly Environmental Monitoring and Audit (EM&A) report presenting the EM&A works carried out during the period from 21 May 2015 to 30 June 2015 in accordance with the EM&A Manual. Summary of Construction Works undertaken during the Reporting Month Works undertaken in the reporting month included: Open cutting; Pre-drilling; and Piling. Environmental Monitoring and Audit Progress A summary of the monitoring activities undertaken in this reporting period is listed below: Joint Environmental Site Inspection Landscape & Visual Monitoring 5 times 2 times Waste Management Waste generated from this Project includes inert construction and demolition (C&D) materials (public fill) and non-inert C&D materials (construction wastes). In total, tonnes of inert C&D material were generated from the Project tonnes were disposed as public fill tonnes of general refuse was disposed as landfill kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period. Environmental Site Inspection Five weekly joint environmental site inspections were carried out by the representatives of the Contractor, SOR and the Environmental Team (ET). The IEC was also present at the joint inspection on 17 June Details of the audit findings and implementation status of the mitigation measures are presented in Section 6.1. Landscape & Visual An onsite inspection on landscape and visual mitigation measures was performed on 5 and 17 June Details of the audit findings and implementation status of the mitigation measures are presented in Sections 6.2. Environmental Exceedance/Non-conformance/Compliant/Summons and Prosecution No exceedance was recorded during the reporting period.
7 No non-compliance event was recorded during the reporting period. No environmental complaint and summon/prosecution was received in this reporting period. Future Key Issues Works to be undertaken in the next reporting month include: Piling; Removing Topsoil from Building 2; and Foundation Footing of Tower Crane. Environmental impacts arising from the above construction activities are mainly associated with dust, construction noise, site runoffs, waste management and landscaping issues.
8 1 INRODUCTION ERM-Hong Kong, Limited (ERM) was appointed by OSCAR Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme for the Contract No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I (the Project). 1.1 PURPOSE OF THE REPORT This is the 1 st EM&A report which summarises the monitoring results and audit findings for the EM&A programme during the reporting period from 21 May 2015 to 30 June STRUCTURE OF THE REPORT The structure of the report is as follows: Section 1: Introduction It details the scope and structure of the report. Section 2: Project Information It summarises the background and scope of the Project, site description, project organization, construction programme, construction works undertaken and status of the Environmental Permits (EP)/licences over the construction phase of the Project. Section 3: Environmental Monitoring Requirements It summarises the environmental monitoring requirements including monitoring parameters, programmes, methodologies, frequency, locations, Action and Limit Levels, Event/Action Plans, environmental mitigation measures as recommended in the EM&A Manual and approved EIA report. Section 4: Implementation Status on Environmental Mitigation Measures It summarises the implementation of environmental protection measures during the reporting period. Section 5: Waste Management It summarises the quantity of public fill and construction waste generated in the reporting period Section 6: Environmental Site Inspection It summarises the audit findings of the weekly site inspections undertaken within the reporting period. Section 7: Environmental Non-conformance ENVIRONMENTAL RESOURCES MANAGEMENT 1 OSCAR BIOENERGY JOINT-VENTURE
9 It summarises any exceedance of environmental performance standard, environmental complaints and summons received within the reporting period. Section 8: Further Key Issues It summarises the impact forecast and monitoring schedule for the next reporting month. Section 9: Conclusions ENVIRONMENTAL RESOURCES MANAGEMENT 2 OSCAR BIOENERGY JOINT-VENTURE
10 2 PROJECT INFORMATION 2.1 BACKGROUND The Organic Waste Treatment Facilities (OWTF) Phase I development (hereinafter referred to as the Project ) is to design, construct and operate a biological treatment facility with a capacity of about 200 tonnes per day and convert source-separated organic waste from commercial and industrial sectors (mostly food waste) into compost and biogas through proven biological treatment technologies. The environmental acceptability of the construction and operation of the Project had been confirmed by findings of the associated Environmental Impact Assessment (EIA) Study completed in The Director of Environmental Protection approved this EIA Report under the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report). Subsequent Report on Re-assessment on Environmental Implications and Report on Re-assessment on Hazard to Life Implications were completed in 2013, respectively. An Environmental Permit (EP) (No. EP-395/2010) was issued by the Environmental Protection Department (EPD) to the EPD, the Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013 (No. EP-395/2010/B), respectively. The Design Build and Operate Contract for the OWTF (Contract No. EP/SP/61/10 Organic Waste Treatment Facilities Phase I (the Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering Limited and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR Bioenergy Joint Venture (OSCAR or the Contractor). A Further EP (No. FEP-01/395/2010/B) was issued by the EPD to the OSCAR on 16 February Under the requirements of Condition 5 of the EP (No. FEP-01/395/2010/B), an Environmental Monitoring and Audit (EM&A) programme as set out in the Agreement No. CE7/2008 (EP) EM&A Manual (hereinafter referred to as EM&A Manual) is required to be implemented. ERM-Hong Kong, Ltd (ERM) has been appointed by OSCAR as the Environmental Team (ET) to undertake the EM&A programme for the Contract. The construction works commenced on 21 May 2015 and are scheduled for completion by April GENERAL SITE DESCRIPTION The Project Site is located at Siu Ho Wan in North Lantau with an area of about 2 hectares. The layout of the Project Site is illustrated in Annex A. ENVIRONMENTAL RESOURCES MANAGEMENT 3 OSCAR BIOENERGY JOINT-VENTURE
11 2.3 CONSTRUCTION ACTIVITIES A summary of the major construction activities undertaken in the reporting period is shown in Table 2.1. The locations of the construction activities are shown in Annex B. The construction programme of the Project is presented in Annex C. Table 2.1 Summary of Construction Activities Undertaken in the Reporting Period Construction Activities Undertaken Open cutting Pre-drilling Piling 2.4 PROJECT ORGANISATION AND MANAGEMENT STRUCTURE The project organisation chart and contact details are shown in Annex D. 2.5 STATUS OF ENVIRONMENTAL APPROVAL DOCUMENTS A summary of the valid permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.2. Table 2.2 Summary of Environmental Licensing, Notification and Permit Status Permit/ Licences/ Notification Environmental Permit Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation Water Discharge License Construction Noise Permit Chemical Waste Producer Registration Reference Validity Period Remarks FEP-01/395/2010/B Ref No Throughout the Contract Throughout the Contract WT May May 2020 GW-RW April August 2015 WPN O Throughout the Contract Permit granted on 16 February Licence approved on 29 April 2015 ENVIRONMENTAL RESOURCES MANAGEMENT 4 OSCAR BIOENERGY JOINT-VENTURE
12 3 ENVIRONMENTAL MONITORING REQUIREMENT, ENVIRONMENTAL MITIGATION MEASURES All the relevant environmental mitigation measures listed in the EIA Report and EM&A Manual are summarised in Annex E. According to the EM&A Manual and EP requirement, no air quality, noise and water quality monitoring is required. Bi-weekly landscape and visual audit is required to ensure that the design, implementation and maintenance of landscape and visual mitigation measures recommended in the EIA Report are fully achieved. ENVIRONMENTAL RESOURCES MANAGEMENT 5 OSCAR BIOENERGY JOINT-VENTURE
13 4 IMPLEMENTATION STATUS ON ENVIRONMENTAL PROTECTION REQUIREMENTS The Contractor has implemented environmental mitigation measures and requirements as stated in the approved EIA Report and EM&A Manual. The implementation status of the measures during the reporting period is summarised in Annex E. ENVIRONMENTAL RESOURCES MANAGEMENT 6 OSCAR BIOENERGY JOINT-VENTURE
14 5 WASTE MANAGEMENT Wastes generated from this Project include inert construction and demolition (C&D) materials (public fill) and non-inert C&D materials (construction waste). Construction waste comprises general refuse, metals and paper/cardboard packaging materials. Metals generated from the Project are also grouped into construction waste as the materials were not disposed of with others at public fill. Reference has been made to the Monthly Summary Waste Flow Table prepared by the Contractor (see Annex F). With reference to the relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Table 5.1. Table 5.1 Quantities of Waste Generated from the Project Month / Year Total Inert C&D Materials Generated (a) Quantity Non-inert C&D Materials (b) C&D Materials Recycled (c) C&D Waste Disposed of at Landfill (d) Chemical Waste May tonnes 0.00 kg 0.00 tonnes 0 L June , tonnes 0.00 kg 9.66 tonnes 0 L Notes: (a) Inert C&D materials (public fill) include bricks, concrete, building debris, rubble and excavated spoil. In total, tonnes of inert C&D material were generated from the Project tonnes were disposed as public fill tonnes of general refuse was disposed as landfill. The detailed waste flow is presented in Annex F. (b) Non-inert C&D materials (construction wastes) include metals, paper / cardboard packaging waste, plastics and other wastes such as general refuse. Metals generated from the Project were grouped into construction wastes as the materials were not disposed of with others at the public fill. (c) 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period. (d) Construction wastes other than metals, paper/cardboard packaging, plastics and chemicals were disposed of at NENT Landfill by subcontractors. ENVIRONMENTAL RESOURCES MANAGEMENT 7 OSCAR BIOENERGY JOINT-VENTURE
15 6 ENVIRONMENTAL INSPECTIONS 6.1 WEEKLY SITE AUDITS Joint site inspections were conducted by representatives of the Contractor, the ER, IC and the ET on 28 May, and 5, 12, 17 and 26 June The IEC was also present at the joint inspection on 17 June Follow-up actions resulting from the last site inspections were taken as reported by the Contractor and their results were observed in the site inspections conducted in the reporting period. Major observations during the reporting period are summarised as follows: 28 May 2015 The discharge point is not yet covered properly. It is recommended to place sand bags around the discharge point or cover the discharge point to avoid untreated wastewater run-off. The sedimentation tank was observed to be full after raining and the untreated water in the sedimentation tank was discharged onto the site without passing through the WetSep for treatment. It is recommended to recirculate the untreated water back to the sump pit and stop pumping water to the sedimentation tank from sump pit when the WetSep is shut down for emergency or maintenance purpose. General refuse and debris was observed within the tree protection zone of Trees T40, T41 and T44. It is recommended to clear general refuse near the trees (T40, 41 and T44) and provide toolbox talk to all workers on tree protection measures. The tree trunk of Trees T40, T41 and T44 was observed to be tied too tight by plastic strips. It is recommended to loosen ropes and plastic strips and avoid tying around the trees. No protection zone was set up for trees T43 and T44 within the site. It is recommended to fence off the identified trees to block the access to the identified trees. Wire was observed to be hanged on the branches of Tree T44. It is recommended to remove wires and avoid hanging any materials on the tree. 5 June 2015 Pond water is found in the tray under the chemical container. It is recommended to clear the pond water regularly, especially after raining. 12 June 2015 Pond water is found in some areas such as areas near vehicle washing facilities, parking area, on tarpaulin sheets and in the U-channel. It is recommended to clear the pond water regularly, especially after raining. ENVIRONMENTAL RESOURCES MANAGEMENT 8 OSCAR BIOENERGY JOINT-VENTURE
16 Pond water is found in the cop of an excavator. It is recommended to check if there is any pond water regularly, especially after raining. It is also recommended to turn it upside down to prevent pond water. Pond water is found in drip trays. It is recommended to clear the pond water regularly, especially after raining. Drip tray is missing for some of the chemical containers. It is recommended to provide drip tray under every chemical containers, even if the chemical are recently arrived to avoid chemical leakage. 17 June 2015 A single chemical container without a drip tray is found. It is recommended to provide drip tray under every chemical containers, and to place the same type of chemical in the same area. Exposed area is found to be dry and dusty. It is recommended to spray water regularly to prevent dry and dusty situation. 26 June 2015 Soil is found to be not completely covered by tarpaulin. It is recommended to fully cover it to prevent dry and dusty situation. Drip tray is missing for some of the chemical containers. It is recommended to provide drip tray under every chemical containers, even if the chemical are recently arrived to avoid chemical leakage. General refuse is found in a tank. It is recommended to provide general refuse point in AD Plant Tank area. Pond water is found in drip trays. It is recommended to clear the pond water regularly, especially after raining 6.2 LANDSCAPE AND VISUAL AUDIT In accordance with the EM&A Manual, bi-weekly landscape and visual inspection is required to ensure that the design, implementation and maintenance of landscape and visual mitigation measures recommended in the EIA Report are fully achieved. An onsite inspection of the landscape and visual mitigation measures was performed on 5 and 17 June Follow-up actions resulting from the last site inspections were taken as reported by the Contractor and their results were observed in the site inspections conducted in the reporting period. It was confirmed that most of the necessary landscape and visual mitigation measures as summarised in Annex E were implemented by the Contractor. The major findings are summarised as follows: ENVIRONMENTAL RESOURCES MANAGEMENT 9 OSCAR BIOENERGY JOINT-VENTURE
17 5 June 2015 Item Observation & Recommendation Photo Record 1. The tree trunk of Tree T10 was observed to be tied too tight by plastic strips. It is recommended to loosen ropes and plastic strips and avoid tying around the trees. 2. A branch of a tree outside the site boundary is found to be tied around the trunk of Tree T11. It is recommended to loosen ropes and plastic strips and avoid unwanted tying around the trees. (T10) 3. Name tag for tree T43 is lost. It is recommended to fence off the identified tree to block the access to the identified trees and tag the tree properly. (T11) (T43) 4. Trees at the northern site boundary are tagged properly and a fence is erected to separate the trees and the site office. However, to give a clear indication on protecting those trees, it is recommended to provide a Tree Protection Zone sign on the fence to restrict the access to the trees. N/A ENVIRONMENTAL RESOURCES MANAGEMENT 10 OSCAR BIOENERGY JOINT-VENTURE
18 17 June 2015 No observation is recorded. ENVIRONMENTAL RESOURCES MANAGEMENT 11 OSCAR BIOENERGY JOINT-VENTURE
19 7 ENVIRONMENTAL NON-CONFORMANCE 7.1 SUMMARY OF ENVIRONMENTAL NON-COMPLIANCE No non-compliance event was recorded during the reporting period. 7.2 SUMMARY OF ENVIRONMENTAL COMPLAINT No complaint was received during the reporting period. environmental complaint log is shown in Annex G. The cumulative 7.3 SUMMARY OF ENVIRONMENTAL SUMMON AND SUCCESSFUL PROSECUTION No summon/prosecution was received during the reporting period. cumulative summons/prosecution log is shown in Annex G. The ENVIRONMENTAL RESOURCES MANAGEMENT 12 OSCAR BIOENERGY JOINT-VENTURE
20 8 FUTURE KEY ISSUES 8.1 KEY ISSUES FOR THE COMING MONTH Works to be undertaken for the coming monitoring period are summarised in Table 8.1. Table 8.1 Construction Works to be undertaken in the Next Reporting Period Construction Activities Undertaken Piling Removing Topsoil from Building 2 Foundation Footing of Tower Crane Potential environmental impacts arising from the above construction activities will be mainly associated with dust, construction noise, site runoffs, waste management and landscaping issues. 8.2 CONSTRUCTION PROGRAMME The most up-to-date construction programme for the Project is presented in Annex C. ENVIRONMENTAL RESOURCES MANAGEMENT 13 OSCAR BIOENERGY JOINT-VENTURE
21 9 CONCLUSIONS This EM&A Report presents the EM&A programme undertaken during the reporting period from 21 May 2015 to 30 June 2015 in accordance with EM&A Manual and requirements of EP (FEP-01/395/2010/B). No air quality, noise and water quality monitoring is required. Bi-weekly landscape and visual monitoring was conducted in the reporting period. Most of the necessary landscape and visual mitigation measures recommended in the EIA Report were implemented by the Contractor. Follow-up actions are required by the Contractor to improve protection of the retained or to-be transplanted trees. No non-compliance event was recorded during the reporting period. No complaint and summons/prosecution was received during the reporting period. The ET will keep track of the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all the necessary mitigation measures in the coming periods. ENVIRONMENTAL RESOURCES MANAGEMENT 14 OSCAR BIOENERGY JOINT-VENTURE
22 Annex A Project Layout
23
24 Annex B Works Location
25
26 Annex C Construction Programme of the Project
27 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float Contract No. EP/SP/61/10 - The Design & Construction Works Nov Apr Nov Apr-17 0 LETTER OF ACCEPTANCE 1 19-Nov Nov Nov Nov Nov Nov Nov Nov Nov Nov Nov Nov Nov Nov Nov Nov-14 0 KD LETTER OF ACCEPTANCE 1 19-Nov Nov Nov Nov-14 0 Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr LETTER OF ACCEPTANCE Contract Programme v1.2 OSCAR BIOENERGY JV MAJOR MILESTONES Dec Mar Mar Apr MC1 Milestones for Preliminaries and General Requirments Dec Apr Apr Apr Dec Apr Apr Apr Dec Apr Apr Apr MC MC1.1 - Substantial Completion of ER & IC Accommodation 0 27-Apr Apr MC MC1.2 - Joint signing of IC Agreement 0 17-Dec Apr MC MC1.3 - Employer's consent granted on draft Contractor's Plans 0 18-Mar Apr MC2 Milestones for Design of the Works Jun Dec Apr Apr MC2.1 The Employer's consent granted on Detailed Design Submission Jun Dec Apr Apr Jun Dec Apr Apr MC MC Employer's consent granted in respect of Detailed Design of Waste Receiving & Pre-treatment System 0 20-Jul Apr MC MC Employer's consent granted in respect of Detailed Design of Anaerobic Digestion Treatment System 0 25-Aug Apr MC MC Employer's consent granted in respect of Detailed Design of Biogas treatment & CHP Generation System 0 05-Aug Apr MC MC Employer's consent granted in respect of Detailed Design of Composting System 0 15-Jun Apr MC MC Employer's consent granted in respect of Detailed Design of CAPCS & WWTS 0 21-Sep Apr MC MC Employer's consent granted in respect of Detail Design of control & instrumentation works 0 22-Oct Apr MC MC Employer's consent granted in respect of building services & electrical works 0 11-Nov Apr MC MC Employer's consent granted in respect of Detailed Design of civil, structural & geotechnical works 0 25-Nov Apr MC MC Employer's consent granted in respect of Detailed Design of architectural & landscape works 0 03-Dec Apr MC2.2 Completion of the Design of the Works 0 03-Dec Dec Apr Apr Dec Dec Apr Apr MC MC2.2 - Completion of the Design of the Works 0 03-Dec Apr MC3 Milestones for Construction of the Works Jul Mar Mar Apr MC3.1 Construction of Civil and Structural Works Jul Dec Apr Apr Jul Dec Apr Apr MC MC Completion of site formation 0 03-Dec Apr MC MC Completion of 50% of piling works 0 06-Jul Apr MC MC Completion of 100% of piling works 0 22-Sep Apr MC MC Completion of 50% of superstructure works 0 08-Jan Apr MC MC Completion of 80% of superstructure works 0 13-Feb Apr MC MC Completion of 100% of superstructure works 0 11-Apr Apr MC MC Completion of 100% of drainage, road and geotechnical works 0 31-Dec Apr MC3.2 Delivery of Materials and Equipment to the Site Nov Jul Apr Apr Nov Jul Apr Apr MC MC Completion of Delivery of Pfre-treatment System 0 26-Jan Apr MC MC Completion of Delivery of Anaerobic Digesters 0 11-Jan Apr MC MC Completion of Delivery of Combined Heat and Power Units 0 02-Jul Apr MC MC Completion of Delivery of Composting Tunnels 0 08-Jan Apr MC MC Completion of Delivery of Centralized Air Pollution Control System 0 11-Nov Apr MC MC Completion of Delivery of Wastewater Treatment System 0 11-Apr Apr MC3.3 Equipment and System Installations Jun Nov Apr Apr Jun Nov Apr Apr MC MC Completion of Waste Receiving, Storage and Feeding System & Pre-treatment System 0 15-Aug Apr MC MC Completion of Anaerobic Digestion Treatment System 0 12-Sep Apr MC MC Completion of Biogas Cleaning and Storage System 0 08-Nov Apr MC MC Completion of Heat Recovery and Power Generation System 0 30-Nov Apr MC MC Completion of Composting System 0 12-Nov Apr MC MC Completion of Centralized Air Pollution Control System 0 25-Aug Apr MC1.1 - Substantial Completion of ER & IC Accommodation MC1.2 - Joint signing of IC Agreement MC1.3 - Employer's consent granted on draft Contractor's Plans MC Employer's consent granted in respect of Detailed Design of Waste Receiving & Pre-treatment System MC Employer's consent granted in respect of Detailed Design of Anaerobic Digestion Treatment System MC Employer's consent granted in respect of Detailed Design of Biogas treatment & CHP Generation System MC Employer's consent granted in respect of Detailed Design of Composting System MC Employer's consent granted in respect of Detailed Design of CAPCS & WWTS MC Employer's consent granted in respect of Detail Design of control & instrumentation works MC Employer's consent granted in respect of building services & electrical works MC Employer's consent granted in respect of Detailed Design of civil, structural & geotechnical works MC Employer's consent granted in respect of Detailed Design of architectural & landscape works MC2.2 - Completion of the Design of the Works MC Completion of site formation MC Completion of 50% of piling works MC Completion of 100% of piling works MC Completion of 50% of superstructure works MC Completion of 80% of superstructure works MC Completion of 100% of superstructure works MC Completion of 100% MC Completion of Delivery of Pfre-treatment System MC Completion of Delivery of Anaerobic Digesters MC Completion of Delivery of Combined Heat and Power Units MC Completion of Delivery of Composting Tunnels MC Completion of Delivery of Centralized Air Pollution Control System MC Completion of Delivery of Wastewater Treatment System MC Completion of Waste Receiving, Storage and Feeding MC Completion of Anaerobic Digestion Treatment S MC Completion of Biogas Cleaning a MC Completion of Heat Recov MC Completion of Composting Syst MC Completion of Centralized Air Pollution Control Syste Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 1 of 27 print: 27-Mar-15 18:32 Oracle Corporation
28 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float MC MC3.3.7 Completion of Wastewater Treatment System 0 20-Jun Apr Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MC3.3.7 Completion of Wastewater Treatment System MC MC Completion of control and instrumentation works 0 19-Aug Apr MC MC Completion of building services works & electrical works 0 29-Sep Apr MC3.4 Architectural and Landscape works 0 20-Dec Dec Apr Apr Dec Dec Apr Apr MC MC3.4 - Completion of architectural and landscape works 0 20-Dec Apr MC3.5 Tes ting and Comm issioning Jan Mar Apr Apr Jan Mar Apr Apr MC MC Employer's consent granted on all FAT,SAT,System Comm.Test,Process Start Up & Process Comm.&Plant 0 20-Jan Apr Comm.T.Plan MC MC Employer's consent granted on all System Commissioning Reports 0 19-Jan Apr MC MC Employer's consent granted on the Process Start Up & Process Commissioning Report 0 14-Feb Apr MC MC Employer's consent granted on the Plant Commissioning Report 0 16-Mar Apr MC3.6 Issuance of the Certificate of Substantial Completion by the Employer 0 16-Mar Mar Mar Mar Mar Mar Mar Mar-17 0 MC MC3.6 Issuance of the Certificate of Substantial Completion by the Employer 0 16-Mar Mar-17 0 MC Completion of control and instrumentation works MC Completion of building services works & el MC3.4 - Completion of architect MC Employer's co MC Employer's co MC Employ MC MC3.6 Iss PRELIMINARY AND GENERAL REQUIREMENT WORKS Nov Apr Nov Apr-17 0 Appointment and Assignment of Contractor's Superintendents, Designers, IC and ER Nov Dec Dec May Nov Dec Dec May Nov Dec Dec May PL Notify the Employer of the proposed Project Manager 5 20-Nov Nov Dec Dec-14 8 PL Submit Contractor's Management Team to Employer Nov Dec Dec Dec-14 8 PL Employer appoves proposed Project Manager 0 10-Dec Dec-14 8 PL Appoint Project Manager 5 11-Dec Dec Dec Dec-14 8 PL Jointly Appoint the Independent Consultant with the Employer Nov Dec Dec Dec-14 8 PL IC to submit names of representatives to Employer & Contractor Nov Dec Apr May PL Employer notifies Contractor of Employer's Representative 0 17-Dec Dec-14 8 Further Environmental Permit Nov Jan Apr Jun Nov Jan Apr Jun Nov Jan Apr Jun PL Submit application for Further Environmental Permit 5 20-Nov Nov May May PL Prepare & submit Emergency Procedures Plan by ET to IEC & ER Nov Dec Apr May PL IEC checks & verifies Emergency Procedures Plan Dec Dec May May PL ER approves Emergency Procedures Plan 0 05-Jan Jun PL Submit approved Emergency Procedures Plan to Dir of EP 4 06-Jan Jan Jun Jun PL Obtain Further Environmental Permit from Dir of EP 0 16-Jan Jun Guarantees, Undertakings & Insurances Nov Jan Dec May Nov Jan Dec May Nov Jan Dec May PL Provision of Guarantee to Employer Nov Dec Dec Dec PL Provision of Undertaking to Employer Nov Dec Dec Dec PL Provision of Undertakings from related companies to Employer Nov Dec Dec Dec PL Provision of the Bond to Employer Nov Dec Dec Dec PL Provision of Contractor's All Risks Insurance Nov Dec Dec Dec-14 8 PL Provision of Professional Indemnity Insurance Nov Dec Dec Dec-14 8 PL Provision of Employee Compensation Insurance Nov Dec Dec Dec-14 8 PL Provision of Motor Vehicle Insurance Nov Dec Dec Dec-14 8 PL Submit Undertakings & Certificates of PI Insurance Nov Jan Mar May Programme Nov Jan Mar Jun Nov Jan Mar Jun Nov Jan Mar Jun PL Prepare & Submit Programme to IC & Employer Nov Dec Apr May PL IC checks & certifies Programme Dec Dec May Jun PL Employer Consents to Contract Programme 0 14-Jan Jun PL Prepare & submit 3 months programme to Employer, ER & IC Dec Dec May May Notify the Employer of the proposed Project Manager Submit Contractor's Management Team to Employer Employer appoves proposed Project Manager Appoint Project Manager Jointly Appoint the Independent Consultant with the Employer IC to submit names of representatives to Employer & Contractor Employer notifies Contractor of Employer's Representative Submit application for Further Environmental Permit Prepare & submit Emergency Procedures Plan by ET to IEC & ER IEC checks & verifies Emergency Procedures Plan ER approves Emergency Procedures Plan Submit approved Emergency Procedures Plan to Dir of EP Obtain Further Environmental Permit from Dir of EP Provision of Guarantee to Employer Provision of Undertaking to Employer Provision of Undertakings from related companies to Employer Provision of the Bond to Employer Provision of Contractor's All Risks Insurance Provision of Professional Indemnity Insurance Provision of Employee Compensation Insurance Provision of Motor Vehicle Insurance Submit Undertakings & Certificates of PI Insurance Prepare & Submit Programme to IC & Employer IC checks & certifies Programme Employer Consents to Contract Programme Prepare & submit 3 months programme to Employer, ER & IC Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 2 of 27 print: 27-Mar-15 18:32 Oracle Corporation
29 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float PL Prepare & submit Critical Path Network to Employer, ER & IC Nov Dec Mar Apr Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Prepare & submit Critical Path Network to Employer, ER & IC Contract Programme v1.2 OSCAR BIOENERGY JV PL IC checks & certifies Critical Path Network Dec Dec Apr May PL Employer Consents to Critical Path Network 0 14-Jan May Prepare & submit Contractor's Plans to Employer, ER & IC Nov Apr Nov May Nov Apr Nov May Nov Apr Nov May PL Sub-contractor Management Plan Nov Dec Apr May PL Draft Project Management Plan Nov Dec Mar Apr PL IC checks & certifies Project Management Plan Dec Dec Apr May PL Employer consents to Project Management Plan 0 14-Jan May PL Draft Human Resource Plan Nov Dec Mar Apr PL IC checks & certifies Human Resource Plan Dec Dec Apr May PL Employer consents to Human Resource Plan 0 14-Jan May PL Draft Design Plan Nov Dec Nov Dec-14 0 PL IC checks & certifies Design Plan Dec Dec Dec Dec-14 0 PL Employer consents to Design Plan 0 14-Jan Jan-15 0 PL Draft Works Plan Nov Dec Mar Apr PL IC checks & certifies Works Plan Dec Dec Apr May PL Employer consents to Works Plan 0 14-Jan May PL Draft Operation Plan Nov Feb Jan Apr PL IC checks & certifies Operation Plan Feb Mar Apr May PL Employer consents to Operation Plan 0 18-Mar May PL Draft Asset Management Plan Nov Dec Mar Apr PL IC checks & certifies Asset Management Plan Dec Dec Apr May PL Employer consents to Asset Management Plan 0 14-Jan May PL Draft Environmental Management Plan Nov Dec Jan Feb PL IC checks & certifies Environmental Management Plan Dec Dec Apr May PL Employer consents to Environmental Management Plan 0 14-Jan May PL Final Environmental Management Plan Dec Jan Feb Mar PL Draft Quality Plan Nov Dec Mar Apr PL IC checks & certifies Quality Plan Dec Dec Apr May PL Employer consents to Quality Plan 0 14-Jan May PL Submit CV for Quality Sub-agent 0 30-Apr May PL Draft Safety and Health Plan Nov Dec Mar Apr PL IC checks & certifies Safety & Health Plan Dec Dec Apr May PL Employer consents to Safety & Health Plan 0 14-Jan May PL Final Safety and Health Plan Dec Jan Apr May PL Site Management Plan for Trip Ticket System (TTS) Dec Jan Apr Apr PL IC checks & certifies TTS Site Management Plan Jan Jan Apr May PL Employer consents to TTS Site Management Plan 0 30-Jan May Prepare & submit complaints procedure Nov Jan Apr May Nov Jan Apr May Nov Jan Apr May PL Submit complaints procedure to ER Nov Dec Apr May PL ER agrees to complaint procedures 0 31-Dec May PL Establish Hotline for complaints 4 02-Jan Jan May May General 5 02-Feb Feb Sep Sep Feb Feb Sep Sep Feb Feb Sep Sep PL Submit particulars of Tree supervisor to Employer 5 02-Feb Feb Sep Sep IC checks & certifies Critical Path Network Employer Consents to Critical Path Network Sub-contractor Management Plan Draft Project Management Plan IC checks & certifies Project Management Plan Employer consents to Project Management Plan Draft Human Resource Plan IC checks & certifies Human Resource Plan Employer consents to Human Resource Plan Draft Design Plan IC checks & certifies Design Plan Employer consents to Design Plan Draft Works Plan IC checks & certifies Works Plan Employer consents to Works Plan Draft Operation Plan IC checks & certifies Operation Plan Employer consents to Operation Plan Draft Asset Management Plan IC checks & certifies Asset Management Plan Employer consents to Asset Management Plan Draft Environmental Management Plan IC checks & certifies Environmental Management Plan Employer consents to Environmental Management Plan Final Environmental Management Plan Draft Quality Plan IC checks & certifies Quality Plan Employer consents to Quality Plan Submit CV for Quality Sub-agent Draft Safety and Health Plan IC checks & certifies Safety & Health Plan Employer consents to Safety & Health Plan Final Safety and Health Plan Site Management Plan for Trip Ticket System (TTS) IC checks & certifies TTS Site Management Plan Employer consents to TTS Site Management Plan Submit complaints procedure to ER ER agrees to complaint procedures Establish Hotline for complaints Submit particulars of Tree supervisor to Employer Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 3 of 27 print: 27-Mar-15 18:32 Oracle Corporation
30 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float Training of Operation & Maintenance Staff Apr Nov Aug Mar Apr Nov Aug Mar Apr Nov Aug Mar TN Prepare & submit training syllabus and materials to IC & Employer Apr May Aug Sep Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Prepare & submit training syllabus and materials to IC & Employer TN IC checks & certifies training syllabus & materials May Jun Nov Nov TN Employer agrees to training syllabus and materials 0 20-Jun Nov TN O&M Training of Contractor's Operation staff Jul Oct Nov Feb TN O&M Training of Employer's staff Aug Nov Dec Mar Preparation of Testing / Operation Plan Jun Jan Sep Mar Detail CV Jun Aug Sep Oct Jun Aug Sep Oct OP Submission of Detail CV before Process Start up and commissioning 1 20-Jun Jun Sep Sep OP IC checks & comments on Detail CV Jun Jul Sep Sep OP Revise & resubmit Detail CV 7 05-Jul Jul Sep Oct OP IC checks & certifies Detail CV 7 12-Jul Jul Oct Oct OP Employer Consents to Detail CV before Process Start up and commissioning 0 01-Aug Oct All System Commissioning Plan Jun Aug Nov Jan Jun Aug Nov Jan OP Submission of All System Commissioning Plan 5 14-Jun Jun Nov Nov OP IC checks & comments on All System Commissioning Plan Jun Jul Nov Dec OP Revise & resubmit All System Commissioning Plan 7 05-Jul Jul Dec Dec OP IC checks & certifies All System Commissioning Plan 7 12-Jul Jul Dec Dec OP Employer Consents to All System Commissioning Plan 0 01-Aug Jan Process Start Up Plan Oct Nov Dec Jan Oct Nov Dec Jan OP Submission of Process Start up Plan 5 03-Oct Oct Dec Dec OP IC checks & comments on Process Start up Plan Oct Oct Dec Dec OP Revise & resubmit Process Start up Plan 7 22-Oct Oct Dec Dec OP IC checks & certifies Process Start up Plan 7 29-Oct Nov Dec Jan OP Employer Consents to Process Start up Plan 0 18-Nov Jan Process Commissioning Plan Dec Jan Jan Mar Dec Jan Jan Mar OP Submission of Process Commissioning Plan 5 05-Dec Dec Jan Feb OP IC checks & comments on Process Commissioning Plan Dec Dec Feb Feb OP Revise & resubmit Process Commissioning Plan 7 24-Dec Dec Feb Feb OP IC checks & certifies Process Commissioning Plan 7 31-Dec Jan Feb Mar OP Employer Consents to Process Commissioning Plan 0 20-Jan Mar Operation Plan Jun Aug Jan Feb Jun Aug Jan Feb OP Submission of Operation Plan 1 21-Jun Jun Jan Jan OP IC checks & comments on Operation Plan Jun Jul Jan Jan OP Revise & resubmit Operation Plan 7 06-Jul Jul Jan Jan OP IC checks & certifies Operation Plan 7 13-Jul Jul Jan Feb OP Employer Consents to Operation Plan 0 02-Aug Feb Plant Commissioning Plan Nov Dec Dec Feb Nov Dec Dec Feb OP Submission of Plant Commissioning Plan 5 07-Nov Nov Dec Dec OP IC checks & comments on Plant Commissioning Plan Nov Nov Jan Jan OP Revise & resubmit Plant Commissioning Plan 7 26-Nov Dec Jan Feb OP IC checks & certifies Plant Commissioning Plan 7 03-Dec Dec Feb Feb OP Employer Consents to Plant Commissioning Plan 0 23-Dec Feb Operation and Maintenance Manuals and Record Drawings Dec Apr Feb Apr Dec Apr Feb Apr Dec Apr Feb Apr-17 0 OP Submission of draft Operation and Maintenance Manual ( SPE-A Clause ) 0 19-Dec Feb IC checks & certifies training syllabus & materials Employer agrees to training syllabus and materials O&M Training of Contractor's Operation staff O&M Training of Employer's staff Submission of Detail CV before Process Start up and commissioning IC checks & comments on Detail CV Revise & resubmit Detail CV IC checks & certifies Detail CV Employer Consents to Detail CV before Process Start up and comm Submission of All System Commissioning Plan IC checks & comments on All System Commissioning Plan Revise & resubmit All System Commissioning Plan IC checks & certifies All System Commissioning Plan Employer Consents to All System Commissioning Plan Submission of Process Start up Plan IC checks & comments on Process Start up P Revise & resubmit Process Start up Plan IC checks & certifies Process Start up Plan Employer Consents to Process Start up Submission of Process Commissio IC checks & comments on Pro Revise & resubmit Process C IC checks & certifies Proce Employer Consents to P Submission of Operation Plan IC checks & comments on Operation Plan Revise & resubmit Operation Plan IC checks & certifies Operation Plan Employer Consents to Operation Plan Submission of Plant Commissioning Plan IC checks & comments on Plant Comm Revise & resubmit Plant Commission IC checks & certifies Plant Commis Employer Consents to Plant Co Submission of draft Operation an Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 4 of 27 print: 27-Mar-15 18:32 Oracle Corporation
31 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float OP IC checks & comments on draft Operation and Maintenance Manual Dec Jan Feb Mar Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr IC checks & comments o OP Submission of Operation and Maintenance Manual ( SPE-A Clause ) 0 16-Mar Mar-17 0 OP IC checks & Certifies the Operation and Maintenance Manual Mar Apr Mar Apr-17 5 OP Submission of Record Drawings ( SPE-A Clause ) 0 18-Apr Apr-17 0 Submissio IC S COMMENCEMENT AND SITE POSSESSION Dec Dec Dec Apr Dec Dec Dec Apr Dec Dec Dec Apr Dec Dec Dec Apr KD COMMENCEMENT OF THE DESIGN AND THE WORKS 0 18-Dec Dec-14 0 KD Start Date of Possession of Portion Dec Jan COMMENCEMENT OF THE DESIGN AND THE WORKS Start Date of Possession of Portion 1 KD Start Date of Possession of Portion Jun Apr Start Date of Possession of Portion 2 KD End Date of Possession of Portion Dec Apr End Date of Possession of P KD Start Date of Possession of Portion Dec May Start Date of Possession of Portion 3 KD End Date of Possession of Portion 3 (to be extended) 0 31-May May-16 0 End Date of Possession of Portion 3 (to be extended) SITE ESTABLISHMENT WORKS Dec May Jan May Dec May Jan May Dec May Jan May Dec May Jan May SE Start of Site Establishment Works 0 18-Dec Jan SE Submit record photographs of Site & vicinity to ER & IC 6 19-Dec Dec May May SE Submit General Arrangement of Site Establishment Dec Jan Jan Jan SE IC certifies & ER consents to General Arrangement of Site Establishment 0 12-Jan Jan SE Start of Site Establishment 0 19-Jan Mar SE Tree survey (Excluding Natural Terrain) Dec Jan Jan Jan SE Project Signboard Feb Feb May May SE General Works of Site Establishment Jan Feb Mar Apr SE Site Clearance Jan Feb Jan Feb SE Hoarding, Fencing, Gates & Lighting Jan Mar Mar Apr SE Demolition of Concrete Pavement (To be Omitted) Mar Apr Apr May SE Employer Representative Officer's & IC Accommodation at P Feb Apr Mar May SE Contractor's Accommodation at P Feb Apr Mar May SE Provision of Survey Equipment & Computer Facilities Mar May Mar May SE Provision of Land Transport for ER Feb Mar Apr May SE Completion of Site Establishment Works 0 11-May May SE Install Type II Sheet Pile forming solid fence of 3m high along boundary facing the Siu Ho Wan Water Treatment Works Mar Apr Apr May SE Submit Tree preservation, transplanting and felling proposal to LandsD and EPD (Excl. Natural Terrain) Jan Jan Jan Feb SE Formation of access to Natural Terrain ( if required) 6 11-Feb Feb Mar Apr SE Tree survey (Natural Terrain - if required) Feb Mar Apr Apr SE Submit Tree preservation, transplanting and felling proposal to LandsD and EPD (Natural Terrain - if required) Mar Apr Apr May DESIGN PREPARATION Nov May Nov Aug Design Criteria Submission (DCS) Nov Feb Nov May Nov Feb Nov May Nov Feb Nov May DP Prepare & submit Design Criteria, Codes & Standards to IC, ER & Employer Nov Jan Nov Jan-15 0 DP IC checks & comments on Design Criteria Submission Jan Jan Feb Feb DP Revise & resubmit Design Criteria to IC, ER & Employer 7 29-Jan Feb Feb Mar DP IC checks & certifies Design Criteria Submission 7 05-Feb Feb Mar Mar DP Submit Design Criteria Check Certificate to Employer & ER 0 16-Feb May Design Consolidation - Process Layout 7 20-Nov Nov Nov Dec Nov Nov Nov Dec Nov Nov Nov Dec-14 4 DP Overall Process Layout 7 20-Nov Nov Nov Dec-14 4 Start of Site Establishment Works Submit record photographs of Site & vicinity to ER & IC Submit General Arrangement of Site Establishment IC certifies & ER consents to General Arrangement of Site Establishment Start of Site Establishment Tree survey (Excluding Natural Terrain) Project Signboard General Works of Site Establishment Site Clearance Hoarding, Fencing, Gates & Lighting Demolition of Concrete Pavement (To be Omitted) Employer Representative Officer's & IC Accommodation at P3 Contractor's Accommodation at P3 Provision of Survey Equipment & Computer Facilities Provision of Land Transport for ER Completion of Site Establishment Works Install Type II Sheet Pile forming solid fence of 3m high along boundary facing the Siu Ho Wan Water Treatment Works Submit Tree preservation, transplanting and felling proposal to LandsD and EPD (Excl. Natural Terrain) Formation of access to Natural Terrain (if required) Tree survey (Natural Terrain - if required) Submit Tree preservation, transplanting and felling proposal to LandsD and EPD (Natural Terrain - if required) Prepare & submit Design Criteria, Codes & Standards to IC, ER & Employer IC checks & comments on Design Criteria Submission Revise & resubmit Design Criteria to IC, ER & Employer IC checks & certifies Design Criteria Submission Submit Design Criteria Check Certificate to Employer & ER Overall Process Layout Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 5 of 27 print: 27-Mar-15 18:32 Oracle Corporation
32 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DP JV Process Layout Plan 7 20-Nov Nov Nov Dec-14 4 Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr JV Process Layout Plan DP Organic Waste Treatment Systems Layout 7 20-Nov Nov Nov Dec-14 4 DP Biogas Process Layout 7 20-Nov Nov Nov Dec-14 4 DP Wastewater Process Layout 7 20-Nov Nov Nov Dec-14 4 DP Waste Air Process Layout 7 20-Nov Nov Nov Dec-14 4 DP Completion of Process Layout 0 28-Nov Dec-14 4 Waste Receiving, Pre-treatment & Administration Building # Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec-14 5 DP Waste Reception Area Layout 9 01-Dec Dec Dec Dec-14 5 DP Pre-treatment System Layout 9 01-Dec Dec Dec Dec-14 5 DP Wastewater Treatment System Layout 9 01-Dec Dec Dec Dec-14 5 DP Administration Building Layout 9 01-Dec Dec Dec Dec-14 5 DP Centralized Air Pollution Control System Layout 9 01-Dec Dec Dec Dec-14 4 DP Completion of Pre-Treatment Building Layout 0 11-Dec Dec-14 5 Composting & Maturation Building # Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec Dec-14 5 DP Composting Tunnel Layout 9 01-Dec Dec Dec Dec-14 5 DP Maturation Area & Facilities Layout 9 01-Dec Dec Dec Dec-14 5 DP Digestate Dewatering System Layout 9 01-Dec Dec Dec Dec-14 5 DP Completion of Compositing Building Layout 0 11-Dec Dec-14 5 Auxiliary Buildings & Facilities Layout # Dec Feb Dec Feb Dec Feb Dec Feb Dec Feb Dec Feb-15 2 DP Anaerobic Digestion Treatment System Layout 9 01-Dec Dec Dec Dec-14 5 DP Biogas Cleaning and Storage System Layout 9 01-Dec Dec Dec Dec-14 5 DP Heat Recovery and Power Generation System Layout 9 01-Dec Dec Dec Dec-14 5 DP Weighbridge System Layout 9 01-Dec Dec Dec Dec-14 5 DP Switchgear Room & Facilities Layout 9 01-Dec Dec Dec Dec-14 5 DP Continuous Emission Monitoring System Layout 9 01-Dec Dec Dec Dec-14 5 DP Completion of Auxiliary Buildings Layout 0 11-Dec Dec-14 5 DP Piled Foundation Jan Feb Jan Feb-15 2 General Dec Feb Dec Mar Dec Feb Dec Mar Dec Feb Dec Mar DP Topographic Survey Jan Jan Jan Feb DP Completion of Design Layout 0 11-Dec Dec-14 5 DP Completion of Design Preparation 0 23-Jan Feb DP Frozen E&M Equipment Loading and General Layout 5 01-Dec Dec Mar Mar DP Finalized E&M Equipment Detail Dec Feb Jan Mar Ground Investigation (including Natural Terrain Hazards) Nov Mar Nov Apr Nov Mar Nov Apr Nov Mar Nov Apr DP Prepare & submit GI Plan to IC & ER Nov Dec Nov Dec-14 3 DP IC certifies GI Plan Dec Dec Dec Dec-14 3 DP ER Consents to GI Plan 0 05-Jan Jan-15 3 DP Mobilization and Appointment of GI Sub-Contractor Nov Dec Dec Jan DP Fieldwork (Including Predrilling and works at Natrual Terrain Unit 4) Jan Feb Jan Feb-15 3 DP Preliminary Fieldwork Report for AD Tanks Piling Design 3 20-Jan Jan Jan Jan-15 3 DP Final Fieldwork Report and Geotechnical Interpretative Report 8 16-Feb Feb Feb Mar-15 8 DP Fieldwork (Natural Terrain - if required) 8 07-Mar Mar Apr Apr Organic Waste Treatment Systems Layout Biogas Process Layout Wastewater Process Layout Waste Air Process Layout Completion of Process Layout Waste Reception Area Layout Pre-treatment System Layout Wastewater Treatment System Layout Administration Building Layout Centralized Air Pollution Control System Layout Completion of Pre-Treatment Building Layout Composting Tunnel Layout Maturation Area & Facilities Layout Digestate Dewatering System Layout Completion of Compositing Building Layout Anaerobic Digestion Treatment System Layout Biogas Cleaning and Storage System Layout Heat Recovery and Power Generation System Layout Weighbridge System Layout Switchgear Room & Facilities Layout Continuous Emission Monitoring System Layout Completion of Auxiliary Buildings Layout Piled Foundation Topographic Survey Completion of Design Layout Completion of Design Preparation Frozen E&M Equipment Loading and General Layout Finalized E&M Equipment Detail Prepare & submit GI Plan to IC & ER IC certifies GI Plan ER Consents to GI Plan Mobilization and Appointment of GI Sub-Contractor Fieldwork (Including Predrilling and works at Natrual Terrain Unit 4) Preliminary Fieldwork Report for AD Tanks Piling Design Final Fieldwork Report and Geotechnical Interpretative Report Fieldwork (Natural Terrain - if required) Plate Load Test Jan Feb Jan Jun Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 6 of 27 print: 27-Mar-15 18:32 Oracle Corporation
33 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float Jan Feb Jan Jun DP Excavation for Plate Load Test Jan Feb Jan Feb Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Excavation for Plate Load Test Contract Programme v1.2 OSCAR BIOENERGY JV DP Setup Loading platform and equipment for Plate Loat Test 6 09-Jan Jan Jan Jan DP Carry-out Plate Load Tes t PLT6~8 (Bldg # 2) 6 16-Jan Jan Jan Feb DP Carry-out Plate Load Tes t PLT9~11 (Bldg # 1) 6 23-Jan Jan Feb Feb DP Carry-out Plate Load Tes t PLT2, 3, & 5 (Bldg #3) 6 30-Jan Feb Feb Feb DP Carry-out Plate Load Tes t PLT1 & 4 (Bldg #3) 6 06-Feb Feb Feb Mar DP Prepare Preliminary Report for PLT6~8 (Bldg # 2) 2 23-Jan Jan Mar Mar DP Prepare Preliminary Report for PLT9~11 (Bldg #1) 2 30-Jan Jan Apr Apr DP Prepare Preliminary Report for PLT2, 3, & 5 (Bldg #3) 2 06-Feb Feb Jun Jun DP Prepare Preliminary Report for PLT1&4 (Bldg #3) 2 13-Feb Feb Mar Mar DP Issue Formal Report for Plate Load Test 4 16-Feb Feb Mar Mar Variation Environmental Permit (VEP) Dec May Mar Aug Environmental Review Report (ERR) Dec Apr Mar Jun Air Quality Impact Assessment (AQIA) Dec Feb Mar May DP Forecast of 2031 traffic data (if needed) Dec Jan Mar Apr DP Air dispersion modelling Dec Feb Mar May Landscape & Visual Impact Assessment (LVIA) Dec Jan Mar May DP Update photomontages Dec Jan Mar May Environmental Review Report (ERR) Feb Apr Apr Jun DP Prepare & submit ERR to EPD for informal review Feb Mar Apr May DP EPD to issue administrative comments on ERR 0 14-Apr Jun Variation Environmental Permit (VEP) Apr May Jun Aug Apr May Jun Aug DP Revise ERR and submit VEP to Director of EPD 5 15-Apr Apr Jun Jun DP EPD issue VEP 0 21-May Aug DETAILED DESIGN SUBMISSION (DDS) GENERAL, CIVIL, ABWF AND LANDSCAPE Dec Dec Dec Dec Overall Design Dec Sep Dec Nov General Building Plans Design Dec Apr Dec May Dec Apr Dec May DD Prepare & submit General Buiding Plans to Stat Authorities/ Government, IC, ER & Employer Dec Feb Dec Feb-15 0 DD General Building Plans endorsed by Stat Authorities/ Government 0 03-Mar Mar-15 8 DD Submit General Building Plans to IC, ER & Employer 0 04-Mar Mar-15 8 DD IC checks & comments on General Building Plans Mar Mar Mar Mar DD Revise & resubmit General Building Plans to IC, ER & Employer 7 19-Mar Mar Apr Apr DD IC checks & certifies General Building Plans 7 26-Mar Apr Apr Apr DD Employer consents to General Building Plans 0 15-Apr May Fire Safety Strategy Report Dec Apr Dec Aug Dec Apr Dec Aug DD Prepare & submit Detailed Design of Fire Safety Strategy Report to Stat Authorities/ Government, IC, ER & Employer Dec Mar Dec Mar-15 5 DD Detailed Design of Fire Safety Strategy Report endorsed by Stat Authorities/ Government 0 18-Mar Apr DD Submit Detailed Design of Fire Safety Strategy Report to IC, ER & Employer 0 19-Mar Apr DD IC checks & comments on Detailed Design of Fire Safety Strategy Report Mar Apr Apr May DD Revise & resubmit Detailed Design of Fire Safety Strategy Report to IC, ER & Employer 7 03-Apr Apr May May DD IC checks & certifies Detailed Design of Fire Safety Strategy Report 7 10-Apr Apr May May DD Employer consents to Detailed Design of Fire Safety Strategy Report 0 30-Apr Aug Layout Drawings Feb Mar Aug Aug Feb Mar Aug Aug DD Prepare & submit Site Wide Layout Drawings for ArchSD Comment Mar Mar Aug Aug DD Prepare & submit Architectural Layout Drawings of Building #2 for ArchSD Comment Mar Mar Aug Aug DD Prepare & submit Architectural Layout Drawings of Building #1 for ArchSD Comment Feb Mar Aug Aug DD Prepare & submit Architectural Layout Drawings of Building #3 for ArchSD Comment Feb Mar Aug Aug Setup Loading platform and equipment for Plate Loat Test Carry-out Plate Load Tes t PLT6~8 (Bldg # 2) Carry-out Plate Load Tes t PLT9~11 (Bldg # 1) Carry-out Plate Load Tes t PLT2, 3, & 5 (Bldg #3) Carry-out Plate Load Tes t PLT1 & 4 (Bldg #3) Prepare Preliminary Report for PLT6~8 (Bldg # 2) Prepare Preliminary Report for PLT9~11 (Bldg #1) Prepare Preliminary Report for PLT2, 3, & 5 (Bldg #3) Prepare Preliminary Report for PLT1&4 (Bldg #3) Issue Formal Report for Plate Load Test Forecast of 2031 traffic data (if needed) Air dispersion modelling Update photomontages Prepare & submit ERR to EPD for informal review EPD to issue administrative comments on ERR Revise ERR and submit VEP to Director of EPD EPD issue VEP Prepare & submit General Buiding Plans to Stat Authorities/ Government, IC, ER & Employer General Building Plans endorsed by Stat Authorities/ Government Submit General Building Plans to IC, ER & Employer IC checks & comments on General Building Plans Revise & resubmit General Building Plans to IC, ER & Employer IC checks & certifies General Building Plans Employer consents to General Building Plans Prepare & submit Detailed Design of Fire Safety Strategy Report to Stat Authorities/ Government, IC, ER & Employer Detailed Design of Fire Safety Strategy Report endorsed by Stat Authorities/ Government Submit Detailed Design of Fire Safety Strategy Report to IC, ER & Employer IC checks & comments on Detailed Design of Fire Safety Strategy Report Revise & resubmit Detailed Design of Fire Safety Strategy Report to IC, ER & Employer IC checks & certifies Detailed Design of Fire Safety Strategy Report Employer consents to Detailed Design of Fire Safety Strategy Report Prepare & submit Site Wide Layout Drawings for ArchSD Comment Prepare & submit Architectural Layout Drawings of Building #2 for ArchSD Comment Prepare & submit Architectural Layout Drawings of Building #1 for ArchSD Comment Prepare & submit Architectural Layout Drawings of Building #3 for ArchSD Comment Geotechnical Design including Natural Terrain Hazard Mitigation works Jan Sep Jan Nov Geotechnical Design Jan May Jan May Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 7 of 27 print: 27-Mar-15 18:32 Oracle Corporation
34 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DD Prepare & submit geotechnical design to GEO Jan Feb Jan Mar Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Prepare & submit geotechnical design to GEO Contract Programme v1.2 OSCAR BIOENERGY JV DD GEO - Approval of Geotechnical design 0 27-Mar Apr-15 6 DD Submit geotechnical design to IC, ER & Employer 0 30-Mar Apr-15 6 DD IC Checks & comments on Geotechnical Design Mar Apr Apr Apr DD Revise & resubmit Geotechnical Design to IC, Employer & ER 7 14-Apr Apr Apr May DD IC checks & certifies geotechnical design 7 21-Apr Apr May May DD Employer consents to geotechnical design 0 11-May May Natural Terrain Hazard Mitigation Mar Sep Apr Nov DD Prepare & submit NTHA Study report to GEO Mar Apr Apr May DD GEO - Approval of NTH Study report 0 01-Jun Jun DD Prepare & submit Design of NTH Mitigation works to GEO Jun Jun Jun Jul DD Prepare & submit NTH Mitigation Method of Construction Jun Jul Jul Aug DD GEO - Approval of NTH Mitigation Design Jun Jul Jul Aug DD Submit NTH Mitigation Design to IC, ER & Employer 0 29-Jul Aug DD IC checks & comments on NTH Mitigation Design Jul Aug Oct Oct DD Revise & resubmit NTH Mitigation Design to IC, Employer & ER 7 13-Aug Aug Oct Oct DD IC checks & certifies NTH Mitigation Design Aug Sep Oct Nov DD Employer consents to NTH Mitigation Design 0 16-Sep Nov Man-made Slope Jun Sep Aug Nov DD Prepare & submit Design of Manmade Slope to GEO Jun Jun Aug Sep DD Prepare & submit Manmade Slope Method of Construction Jun Jul Sep Oct DD GEO - Approval of Manmade Slope Design Jun Jul Sep Oct DD Submit Manmade Slope Design to IC, ER & Employer 0 29-Jul Oct DD IC checks & comments on Manmade Slope Design Jul Aug Oct Oct DD Revise & resubmit Manmade Slope Design to IC, Employer & ER 7 13-Aug Aug Oct Oct DD IC checks & certifies Manmade Slope Design Aug Sep Oct Nov DD Employer consents to Manmade Slope Design 0 16-Sep Nov Waste Receiving, Pre-treatment & Administration Building # Apr Nov Apr Jun Substructure Design Apr Jul Apr Aug Apr Jul Apr Aug DD Prepare & submit Detailed Substructure Design of Bldg #1 to IC, ER & Employer Apr Jun Apr Jun-15 2 DD Prepare & submit Method of Construction for Substructure of Bldg # Apr Jun May Jul DD IC checks & comments on Detailed Substructure Design of Bldg # Jun Jun Jul Jul DD Revise & resubmit Detailed Substructure Design of Bldg #1 to IC, Employer & ER 7 18-Jun Jun Jul Jul DD IC checks & certifies Detailed Substructure Design of Bldg # Jun Jul Jul Aug DD Employer consents to Detailed Substructure Design of Bldg # Jul Aug Superstructure Design Jun Aug Jun Oct Jun Aug Jun Oct DD Prepare & submit Detailed Superstructure Design of Bldg #1 to IC, ER & Employer Jun Jul Jun Jul-15 5 DD Prepare & submit Method of Construction for Superstructure of Bldg # Jun Jul Jul Aug DD IC checks & comments on Detailed Superstructure Design of Bldg # Jul Aug Aug Sep DD Revise & resubmit Detailed Superstructure Design of Bldg #1 to IC, Employer & ER 7 04-Aug Aug Sep Sep DD IC checks & certifies Detailed Superstructure Design of Bldg # Aug Aug Sep Sep DD Employer consents to Detailed Superstructure Design of Bldg # Aug Oct Steelwork Design Jul Nov Sep Jun Building #1 Roof Steel Structure Jul Oct Sep Dec DD Prepare & submit Detailed Design of Bldg #1 Roof - Structural Steelwork to IC, ER & Employer Jul Sep Sep Nov DD Prepare & submit Method of Construction for Bldg #1 Roof - Structural Steelwork Aug Sep Oct Nov DD IC checks & comments on Detailed Design of Bldg #1 Roof - Structural Steelwork Sep Sep Nov Dec DD Revise & resubmit Detailed Design of Bldg #1 Roof - Structural Steelwork to IC, Employer & ER 7 26-Sep Oct Dec Dec GEO - Approval of Geotechnical design Submit geotechnical design to IC, ER & Employer IC Checks & comments on Geotechnical Design Revise & resubmit Geotechnical Design to IC, Employer & ER IC checks & certifies geotechnical design Employer consents to geotechnical design Prepare & submit NTHA Study report to GEO GEO - Approval of NTH Study report Prepare & submit Design of NTH Mitigation works to GEO Prepare & submit NTH Mitigation Method of Construction GEO - Approval of NTH Mitigation Design Submit NTH Mitigation Design to IC, ER & Employer IC checks & comments on NTH Mitigation Design Revise & resubmit NTH Mitigation Design to IC, Employer & ER IC checks & certifies NTH Mitigation Design Employer consents to NTH Mitigation Design Prepare & submit Design of Manmade Slope to GEO Prepare & submit Manmade Slope Method of Construction GEO - Approval of Manmade Slope Design Submit Manmade Slope Design to IC, ER & Employer IC checks & comments on Manmade Slope Design Revise & resubmit Manmade Slope Design to IC, Employer & ER IC checks & certifies Manmade Slope Design Employer consents to Manmade Slope Design Prepare & submit Detailed Substructure Design of Bldg #1 to IC, ER & Employer Prepare & submit Method of Construction for Substructure of Bldg #1 IC checks & comments on Detailed Substructure Design of Bldg #1 Revise & resubmit Detailed Substructure Design of Bldg #1 to IC, Employer & ER IC checks & certifies Detailed Substructure Design of Bldg #1 Employer consents to Detailed Substructure Design of Bldg #1 Prepare & submit Detailed Superstructure Design of Bldg #1 to IC, ER & Employer Prepare & submit Method of Construction for Superstructure of Bldg #1 IC checks & comments on Detailed Superstructure Design of Bldg #1 Revise & resubmit Detailed Superstructure Design of Bldg #1 to IC, Employer & ER IC checks & certifies Detailed Superstructure Design of Bldg #1 Employer consents to Detailed Superstructure Design of Bldg #1 Prepare & submit Detailed Design of Bldg #1 Roof - Structural Steelwork to IC, ER & Employer Prepare & submit Method of Construction for Bldg #1 Roof - Structural Steelwork IC checks & comments on Detailed Design of Bldg #1 Roof - Structural Steelwork Revise & resubmit Detailed Design of Bldg #1 Roof - Structural Steelwork to IC, Employer & ER Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 8 of 27 print: 27-Mar-15 18:32 Oracle Corporation
35 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DD IC checks & certifies Detailed Design of Bldg #1 Roof - Structural Steelwork 7 03-Oct Oct Dec Dec Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr IC checks & certifies Detailed Design of Bldg #1 Roof - Structural Steelwork Contract Programme v1.2 OSCAR BIOENERGY JV DD Employer consents to Detailed Design of Bldg #1 Roof - Structural Steelwork 0 23-Oct Dec CAPC Stack Sep Nov Mar Jun DD Prepare & submit Detailed CAPC Stack - Steel Support Design to IC, ER & Employer Sep Oct Mar Apr DD Prepare & submit Method of Construction for CAPC Stack - Steel Support Sep Oct Mar Apr DD IC checks & comments on Detailed CAPC Stack - Steel Support Design Oct Oct Apr May DD Revise & resubmit Detailed CAPC Stack - Steel Support Design to IC, Employer & ER 7 29-Oct Nov May May DD IC checks & certifies Detailed CAPC Stack - Steel Support Design 7 05-Nov Nov May May DD Employer consents to Detailed CAPC Stack - Steel Support Design 0 25-Nov Jun Composting & Maturation Building # Mar Oct Mar Nov-15 6 Substructure Design Mar May Mar May Mar May Mar May-15 0 DD Prepare & submit Detailed Substructure Design of Bldg #2 to IC, ER & Employer Mar Apr Mar Apr-15 0 DD Prepare & submit Method of Construction for Substructure of Bldg # Mar Apr Mar Apr-15 0 DD IC checks & comments on Detailed Substructure Design of Bldg # Apr Apr Apr Apr-15 0 DD Revise & resubmit Detailed Substructure Design of Bldg #2 to IC, Employer & ER 7 25-Apr May Apr May-15 0 DD IC checks & certifies Detailed Substructure Design of Bldg # May May May May-15 0 DD Employer consents to Detailed Substructure Design of Bldg # May May-15 0 Superstructure Design Jul Sep Jul Nov Jul Sep Jul Nov DD Prepare & submit Detailed Superstructure Design of Bldg #2 to IC, ER & Employer Jul Aug Jul Aug-15 5 DD Prepare & submit Method of Construction for Superstructure of Bldg # Jul Aug Aug Sep DD IC checks & comments on Detailed Superstructure Design of Bldg # Aug Sep Sep Oct DD Revise & resubmit Detailed Superstructure Design of Bldg #2 to IC, Employer & ER 7 03-Sep Sep Oct Oct DD IC checks & certifies Detailed Superstructure Design of Bldg # Sep Sep Oct Oct DD Employer consents to Detailed Superstructure Design of Bldg # Sep Nov Steelwork Design Aug Oct Aug Nov-15 6 Link Bridge Steelwork Aug Oct Aug Nov-15 6 DD Prepare & submit Detailed Link Bridge Steelwork Design of Bldg #2 to IC, ER & Employer Aug Sep Aug Sep-15 5 DD Prepare & submit Method of Construction for Bldg #2 Link Bridge Steelwork Aug Sep Aug Sep-15 5 DD IC checks & comments on Detailed Link Bridge Steelwork Design of Bldg # Sep Oct Sep Oct-15 7 DD Revise & resubmit Detailed Link Bridge Steelwork Design of Bldg #2 to IC, Employer & ER 7 03-Oct Oct Oct Oct-15 7 DD IC checks & certifies Detailed Link Bridge Steelwork Design of Bldg # Oct Oct Oct Oct-15 7 DD Employer consents to Detailed Link Bridge Steelwork Design of Bldg # Oct Nov-15 7 Auxiliary Buildings & Facilities # Feb Oct Feb Jan Piling Foundation and Pile Cap Design Feb May Feb May Feb May Feb May-15 0 DD Prepare & submit Detailed Piling and Pile Cap Design of AD Tank to IC, ER & Employer Feb Mar Feb Mar-15 0 DD Prepare & submit Detailed Piling and Pile Cap Design of CAPCS Stack to IC, ER & Employer Feb Mar Feb Mar-15 0 DD Prepare & submit Detailed Piling and Pile Cap Design of Ammonia Stripper to IC, ER & Employer Feb Mar Feb Mar-15 0 DD Prepare & submit Method of Construction for Piling and Pile Cap of Bldg # Feb Mar Feb Mar-15 0 DD IC checks & comments on Detailed Piling and Pile Cap Design of Bldg & Facilities # Apr Apr Apr Apr-15 0 DD Revise & resubmit Detailed Piling and Pile Cap Design of Bldg & Facilities #3 to IC, Employer & ER 7 15-Apr Apr Apr Apr-15 0 DD IC checks & certifies Detailed Piling and Pile Cap Design of Bldg & Facilities # Apr Apr Apr Apr-15 0 DD Employer consents to Detailed Piling and Pile Cap Design of Bldg & Facilities # May May-15 0 Substructure Design Jun Aug Jun Aug Jun Aug Jun Aug-15 0 DD Prepare & submit Detailed Substructure Design of Energy Centre to IC, ER & Employer Jun Jul Jun Jul-15 0 DD Prepare & submit Detailed Substructure Design of Biogas Cleaning & Storage Tank to IC, ER & Employer Jun Jul Jun Jul-15 0 DD Prepare & submit Detailed Substructure Design of Desulphorization/Biogas Plant Rm. to IC, ER & Employer Jun Jul Jun Jul-15 0 DD Prepare & submit Detailed Substructure Design of Desulphurization Tank to IC, ER & Employer Jun Jul Jun Jul-15 0 DD Prepare & submit Detailed Substructure Design of Weighbridge to IC, ER & Employer Jun Jul Jun Jul-15 0 Employer consents to Detailed Design of Bldg #1 Roof - Structural Steelwork Prepare & submit Detailed CAPC Stack - Steel Support Design to IC, ER & Employer Prepare & submit Method of Construction for CAPC Stack - Steel Support IC checks & comments on Detailed CAPC Stack - Steel Support Design Revise & resubmit Detailed CAPC Stack - Steel Support Design to IC, Employer & ER IC checks & certifies Detailed CAPC Stack - Steel Support Design Employer consents to Detailed CAPC Stack - Steel Support Design Prepare & submit Detailed Substructure Design of Bldg #2 to IC, ER & Employer Prepare & submit Method of Construction for Substructure of Bldg #2 IC checks & comments on Detailed Substructure Design of Bldg #2 Revise & resubmit Detailed Substructure Design of Bldg #2 to IC, Employer & ER IC checks & certifies Detailed Substructure Design of Bldg #2 Employer consents to Detailed Substructure Design of Bldg #2 Prepare & submit Detailed Superstructure Design of Bldg #2 to IC, ER & Employer Prepare & submit Method of Construction for Superstructure of Bldg #2 IC checks & comments on Detailed Superstructure Design of Bldg #2 Revise & resubmit Detailed Superstructure Design of Bldg #2 to IC, Employer & ER IC checks & certifies Detailed Superstructure Design of Bldg #2 Employer consents to Detailed Superstructure Design of Bldg #2 Prepare & submit Detailed Link Bridge Steelwork Design of Bldg #2 to IC, ER & Employer Prepare & submit Method of Construction for Bldg #2 Link Bridge Steelwork IC checks & comments on Detailed Link Bridge Steelwork Design of Bldg #2 Revise & resubmit Detailed Link Bridge Steelwork Design of Bldg #2 to IC, Employer & ER IC checks & certifies Detailed Link Bridge Steelwork Design of Bldg #2 Employer consents to Detailed Link Bridge Steelwork Design of Bldg #2 Prepare & submit Detailed Piling and Pile Cap Design of AD Tank to IC, ER & Employer Prepare & submit Detailed Piling and Pile Cap Design of CAPCS Stack to IC, ER & Employer Prepare & submit Detailed Piling and Pile Cap Design of Ammonia Stripper to IC, ER & Employer Prepare & submit Method of Construction for Piling and Pile Cap of Bldg #3 IC checks & comments on Detailed Piling and Pile Cap Design of Bldg & Facilities #3 Revise & resubmit Detailed Piling and Pile Cap Design of Bldg & Facilities #3 to IC, Employer & ER IC checks & certifies Detailed Piling and Pile Cap Design of Bldg & Facilities #3 Employer consents to Detailed Piling and Pile Cap Design of Bldg & Facilities #3 Prepare & submit Detailed Substructure Design of Energy Centre to IC, ER & Employer Prepare & submit Detailed Substructure Design of Biogas Cleaning & Storage Tank to IC, ER & Employer Prepare & submit Detailed Substructure Design of Desulphorization/Biogas Plant Rm. to IC, ER & Employer Prepare & submit Detailed Substructure Design of Desulphurization Tank to IC, ER & Employer Prepare & submit Detailed Substructure Design of Weighbridge to IC, ER & Employer Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 9 of 27 print: 27-Mar-15 18:32 Oracle Corporation
36 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DD Prepare & submit Method of Construction for Substructure of Bldg # Jun Jul Jun Jul Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Prepare & submit Method of Construction for Substructure of Bldg #3 Contract Programme v1.2 OSCAR BIOENERGY JV DD IC checks & comments on Detailed Substructure Design of Bldg & Facilities # Jul Aug Jul Aug-15 0 DD Revise & resubmit Detailed Substructure Design of Bldg & Facilities #3 to IC, Employer & ER 7 04-Aug Aug Aug Aug-15 0 DD IC checks & certifies Detailed Substructure Design of Bldg & Facilities # Aug Aug Aug Aug-15 0 DD Employer consents to Detailed Substructure Design of Bldg & Facilities # Aug Aug-15 0 Superstructure Design Aug Oct Oct Jan Aug Oct Oct Jan DD Prepare & submit Detailed Supertructure Design of Energy Centre to IC, ER & Employer Aug Sep Oct Nov DD Prepare & submit Detailed Supertructure Design of Weighbridge to IC, ER & Employer Aug Sep Oct Nov DD Prepare & submit Detailed Supertructure Design of Gate House to IC, ER & Employer Aug Sep Oct Nov DD Prepare & submit Detailed Supertructure Design of AD Tanks & Bund Wall to IC, ER & Employer Aug Sep Oct Nov DD Prepare & submit Method of Construction for Superstructure of Bldg # Aug Sep Oct Nov DD IC checks & comments on Detailed Superstructure Design of Bldg & Facilities # Sep Oct Nov Dec DD Revise & resubmit Detailed Superstructure Design of Bldg & Facilities #3 to IC, Employer & ER 7 02-Oct Oct Dec Dec DD IC checks & certifies Detailed Superstructure Design of Bldg & Facilities # Oct Oct Dec Dec DD Employer consents to Detailed Superstructure Design of Bldg & Facilities # Oct Jan External Civil Engineering Works Mar Nov Apr Feb Section 1- Sewerage System and Rising Main and Section 2- Storm Drain Mar Aug Apr Oct Mar Aug Apr Oct DD Prepare & submit Detailed Civil Design of external works (Section 1 & 2) to EPD & DSD Mar May Apr Jun DD Prepare & submit Method of Construction for External Works (Section 1 & 2) May Jun Jul Aug DD Submit Detailed Design of External Works (Section 1 & 2) to IC, Employer & ER 0 25-Jun Aug DD IC checks & comments on Detailed Design of External Works (Section 1 & 2) Jun Jul Aug Sep DD Revise & resubmit Detailed Design of External Works (Section 1 & 2) to IC, Employer & ER 7 10-Jul Jul Sep Sep DD IC checks & certifies Detailed Civil Design of External Works (Section 1 & 2) 7 17-Jul Jul Sep Sep DD Employer consents to Detailed Civil Design of External Works (Section 1 & 2) 0 06-Aug Oct Section 3- Street Fire Hydrant and Section 4- Water Supply Apr Jul May Oct Apr Jul May Oct DD Prepare & submit Detailed Civil Design of external works (Section 3 & 4) to WSD Apr May May Jun DD Prepare & submit Method of Construction for External Works (Section 3 & 4) May Jun Jul Aug DD Submit Detailed Design of External Works (Section 3 & 4) to IC, Employer & ER 0 15-Jun Aug DD IC checks & comments on Detailed Design of External Works (Section 3 & 4) Jun Jun Aug Sep DD Revise & resubmit Detailed Design of External Works (Section 3 & 4) to IC, Employer & ER 7 29-Jun Jul Sep Sep DD IC checks & certifies Detailed Civil Design of External Works (Section 3 & 4) 7 06-Jul Jul Sep Sep DD Employer consents to Detailed Civil Design of External Works (Section 3 & 4) 0 26-Jul Oct Section 5- Road, Paving, Road Marking, Section 6- Ext. Lighting, Section 7 Fencing, Gate, Perm. Signboard Jul Nov Aug Dec Jul Nov Aug Dec DD Prepare & submit Detailed Civil Design of external works (Section 5,6, 7) to Hyd & TD Jul Sep Aug Oct DD Prepare & submit Method of Construction for External Works (Section 5,6, 7) Sep Oct Oct Nov DD Submit Detailed Design of External Works (Section 5,6, 7) to IC, Employer & ER 0 14-Oct Nov DD IC checks & comments on Detailed Design of External Works (Section 5,6, 7) Oct Oct Nov Nov DD Revise & resubmit Detailed Design of External Works (Section 5,6, 7) to IC, Employer & ER 7 29-Oct Nov Nov Nov DD IC checks & certifies Detailed Civil Design of External Works (Section 5,6, 7) 7 05-Nov Nov Dec Dec DD Employer consents to Detailed Civil Design of External Works (Section 5,6, 7) 0 25-Nov Dec Sub & Superstructure - Boundary Wall Aug Nov Oct Feb Aug Nov Oct Feb DD Prepare & submit Detailed Civil Design of external works (Sub & Superstructure - Boundary Wall) to IC, Employer & ER Aug Oct Oct Dec DD Prepare & submit Method of Construction for External Works (Sub & Superstructure - Boundary Wall) Aug Oct Nov Dec DD IC checks & comments on Detailed Design of External Works (Sub & Superstructure - Boundary Wall) Oct Oct Dec Jan DD Revise & resubmit Detailed Design of External Works (Sub & Superstructure - Boundary Wall) to IC, Employer & ER 7 17-Oct Oct Jan Jan DD IC checks & certifies Detailed Civil Design of External Works (Sub & Superstructure - Boundary Wall) 7 24-Oct Oct Jan Jan IC checks & comments on Detailed Substructure Design of Bldg & Facilities #3 Revise & resubmit Detailed Substructure Design of Bldg & Facilities #3 to IC, Employer & ER IC checks & certifies Detailed Substructure Design of Bldg & Facilities #3 Employer consents to Detailed Substructure Design of Bldg & Facilities #3 Prepare & submit Detailed Supertructure Design of Energy Centre to IC, ER & Employer Prepare & submit Detailed Supertructure Design of Weighbridge to IC, ER & Employer Prepare & submit Detailed Supertructure Design of Gate House to IC, ER & Employer Prepare & submit Detailed Supertructure Design of AD Tanks & Bund Wall to IC, ER & Employer Prepare & submit Method of Construction for Superstructure of Bldg #3 IC checks & comments on Detailed Superstructure Design of Bldg & Facilities #3 Revise & resubmit Detailed Superstructure Design of Bldg & Facilities #3 to IC, Employer & ER IC checks & certifies Detailed Superstructure Design of Bldg & Facilities #3 Employer consents to Detailed Superstructure Design of Bldg & Facilities #3 Prepare & submit Detailed Civil Design of external works (Section 1 & 2) to EPD & DSD Prepare & submit Method of Construction for External Works (Section 1 & 2) Submit Detailed Design of External Works (Section 1 & 2) to IC, Employer & ER IC checks & comments on Detailed Design of External Works (Section 1 & 2) Revise & resubmit Detailed Design of External Works (Section 1 & 2) to IC, Employer & ER IC checks & certifies Detailed Civil Design of External Works (Section 1 & 2) Employer consents to Detailed Civil Design of External Works (Section 1 & 2) Prepare & submit Detailed Civil Design of external works (Section 3 & 4) to WSD Prepare & submit Method of Construction for External Works (Section 3 & 4) Submit Detailed Design of External Works (Section 3 & 4) to IC, Employer & ER IC checks & comments on Detailed Design of External Works (Section 3 & 4) Revise & resubmit Detailed Design of External Works (Section 3 & 4) to IC, Employer & ER IC checks & certifies Detailed Civil Design of External Works (Section 3 & 4) Employer consents to Detailed Civil Design of External Works (Section 3 & 4) Prepare & submit Detailed Civil Design of external works (Section 5,6, 7) to Hyd & TD Prepare & submit Method of Construction for External Works (Section 5,6, 7) Submit Detailed Design of External Works (Section 5,6, 7) to IC, Employer & ER IC checks & comments on Detailed Design of External Works (Section 5,6, 7) Revise & resubmit Detailed Design of External Works (Section 5,6, 7) to IC, Employer & ER IC checks & certifies Detailed Civil Design of External Works (Section 5,6, 7) Employer consents to Detailed Civil Design of External Works (Section 5,6, 7) Prepare & submit Detailed Civil Design of external works (Sub & Superstructure - Boundary Wall) to IC, Employer & ER Prepare & submit Method of Construction for External Works (Sub & Superstructure - Boundary Wall) IC checks & comments on Detailed Design of External Works (Sub & Superstructure - Boundary Wall) Revise & resubmit Detailed Design of External Works (Sub & Superstructure - Boundary Wall) to IC, Employer & ER IC checks & certifies Detailed Civil Design of External Works (Sub & Superstructure - Boundary Wall) Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 10 of 27 print: 27-Mar-15 18:32 Oracle Corporation
37 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DD Employer consents to Detailed Civil Design of External Works (Sub & Superstructure - Boundary Wall) 0 13-Nov Feb Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Employer consents to Detailed Civil Design of External Works (Sub & Superstructure - Boundary Wall) Contract Programme v1.2 OSCAR BIOENERGY JV Architectural, Building Works & Finishes (ABWF) Apr Oct Sep Mar Building #1 (Waste Receiving, Pre-treatment & Admin. Building) Jun Sep Dec Mar Jun Sep Dec Mar DD Prepare & submit Detailed Design of Bldg.#1 ABWF to IC, ER & Employer Jun Aug Dec Feb DD Prepare & submit Method of Construction for Bldg.#1 ABWF Jun Aug Jan Feb DD IC checks & comments on Detailed Design of Bldg.#1 ABWF Aug Aug Feb Feb DD Revise & resubmit Detailed Design of Bldg.#1 ABWF to IC, Employer & ER 7 19-Aug Aug Mar Mar DD IC checks & certifies Detailed Design of Bldg.#1 ABWF 7 26-Aug Sep Mar Mar DD Employer consents to Detailed Design of Bldg.#1 ABWF 0 15-Sep Mar Building #2 (Composting & Maturation Building) Apr Jul Sep Jan Apr Jul Sep Jan DD Prepare & submit Detailed Design of Bldg.#2 ABWF to IC, ER & Employer Apr Jun Sep Nov DD Prepare & submit Method of Construction for Bldg.#2 ABWF May Jun Oct Nov DD IC checks & comments on Detailed Design of Bldg.#2 ABWF Jun Jul Dec Dec DD Revise & resubmit Detailed Design of Bldg.#2 ABWF to IC, Employer & ER 7 03-Jul Jul Dec Dec DD IC checks & certifies Detailed Design of Bldg.#2 ABWF 7 10-Jul Jul Dec Dec DD Employer consents to Detailed Design of Bldg.#2 ABWF 0 30-Jul Jan Building #3 (Auxillary Buildings & Facilities) Jul Oct Nov Feb Jul Oct Nov Feb DD Prepare & submit Detailed Design of Bldg.#3 ABWF to IC, ER & Employer Jul Sep Nov Dec DD Prepare & submit Method of Construction for Bldg.#3 ABWF Aug Sep Nov Dec DD IC checks & comments on Detailed Design of Bldg.#3 ABWF Sep Sep Jan Jan DD Revise & resubmit Detailed Design of Bldg.#3 ABWF to IC, Employer & ER 7 25-Sep Oct Jan Jan DD IC checks & certifies Detailed Design of Bldg.#3 ABWF 7 02-Oct Oct Jan Jan DD Employer consents to Detailed Design of Bldg.#3 ABWF 0 22-Oct Feb Interior Fitting-out Works Sep Dec Sep Dec Sep Dec Sep Dec Sep Dec Sep Dec DD Prepare & submit Detailed Interior Fitting-out Design to IC, ER & Employer Sep Oct Sep Nov DD Prepare & submit Method of Construction for Interior Fitting-out Sep Oct Sep Nov DD IC checks & comments on Detailed Interior Fitting-out Design Oct Nov Nov Nov DD Revise & resubmit Detailed Fitting-out Design to IC, Employer & ER 7 06-Nov Nov Nov Nov DD IC checks & certifies Detailed Interior Fitting-out Design 7 13-Nov Nov Nov Nov DD Employer consents to Detailed Interior Fitting-out Design 0 03-Dec Dec External Landscape Works and Building #2 Green Roof May Sep Jun Oct May Sep Jun Oct May Sep Jun Oct DD Prepare & submit Detailed Design of Landscape and Building #2 Green Roof to EPD, LandsD, PlanD, ArchSD May Jul Jun Aug DD Prepare & submit Method of Construction for Landscape and Building #2 Green Roof Jul Aug Aug Aug DD Submit Detailed Design of Landscape and Building #2 Green Roof to IC, Employer & ER 0 10-Aug Aug DD IC checks & comments on Detailed Design of Landscape and Building #2 Green Roof Aug Aug Aug Sep DD Revise & resubmit Detailed Design of Landscape and Building #2 Green Roof to IC, Employer & ER 7 25-Aug Aug Sep Sep DD IC checks & certifies Detailed Design of Landscape and Building #2 Green Roof 7 01-Sep Sep Sep Sep DD Employer consents to Detailed Design of Landscape and Building #2 Green Roof 0 21-Sep Oct Prepare & submit Detailed Design of Bldg.#1 ABWF to IC, ER & Employer Prepare & submit Method of Construction for Bldg.#1 ABWF IC checks & comments on Detailed Design of Bldg.#1 ABWF Revise & resubmit Detailed Design of Bldg.#1 ABWF to IC, Employer & ER IC checks & certifies Detailed Design of Bldg.#1 ABWF Employer consents to Detailed Design of Bldg.#1 ABWF Prepare & submit Detailed Design of Bldg.#2 ABWF to IC, ER & Employer Prepare & submit Method of Construction for Bldg.#2 ABWF IC checks & comments on Detailed Design of Bldg.#2 ABWF Revise & resubmit Detailed Design of Bldg.#2 ABWF to IC, Employer & ER IC checks & certifies Detailed Design of Bldg.#2 ABWF Employer consents to Detailed Design of Bldg.#2 ABWF Prepare & submit Detailed Design of Bldg.#3 ABWF to IC, ER & Employer Prepare & submit Method of Construction for Bldg.#3 ABWF IC checks & comments on Detailed Design of Bldg.#3 ABWF Revise & resubmit Detailed Design of Bldg.#3 ABWF to IC, Employer & ER IC checks & certifies Detailed Design of Bldg.#3 ABWF Employer consents to Detailed Design of Bldg.#3 ABWF Prepare & submit Detailed Interior Fitting-out Design to IC, ER & Employer Prepare & submit Method of Construction for Interior Fitting-out IC checks & comments on Detailed Interior Fitting-out Design Revise & resubmit Detailed Fitting-out Design to IC, Employer & ER IC checks & certifies Detailed Interior Fitting-out Design Employer consents to Detailed Interior Fitting-out Design Prepare & submit Detailed Design of Landscape and Building #2 Green Roof to EPD, LandsD, PlanD, ArchSD Prepare & submit Method of Construction for Landscape and Building #2 Green Roof Submit Detailed Design of Landscape and Building #2 Green Roof to IC, Employer & ER IC checks & comments on Detailed Design of Landscape and Building #2 Green Roof Revise & resubmit Detailed Design of Landscape and Building #2 Green Roof to IC, Employer & ER IC checks & certifies Detailed Design of Landscape and Building #2 Green Roof Employer consents to Detailed Design of Landscape and Building #2 Green Roof DETAILED DESIGN SUBMISSION (DDS) ELECTRICAL AND MECHANICAL Dec Oct Dec Feb HAZOP Mar Apr Jul Jul Mar Apr Jul Jul Mar Apr Jul Jul DE HAZOP Analysis Mar Apr Jul Jul Detailed Process Documentation Submission Apr Jun Aug Nov Apr Jun Aug Nov Apr Jun Aug Nov DE Prepare & submit Detailed Process Documentation Submission to IC, ER & Employer Apr Apr Aug Aug HAZOP Analysis Prepare & submit Detailed Process Documentation Submission to IC, ER & Employer Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 11 of 27 print: 27-Mar-15 18:32 Oracle Corporation
38 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DE IC checks & comments on Detailed Process Documentation Submission May May Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr IC checks & comments on Detailed Process Documentation Submission Contract Programme v1.2 OSCAR BIOENERGY JV DE Revise & resubmit Detailed Process Documentation Submission to IC, Employer & ER 7 15-May May Oct Oct DE IC checks & certifies Detailed Process Documentation Submission 7 22-May May Oct Oct DE Employer consents to Detailed Process Documentation Submission 0 11-Jun Nov Waste Receiving, Storage and Feeding System Dec Jul Jan Oct Dec Jul Jan Oct Dec Jul Jan Oct DE Prepare & make Waste Receiving Equipment & Performance Submission to IC, ER & Employer Dec Jan Jan Feb DE IC checks & comments on Waste Receiving, Storage & Feeding Equipment Jan Feb Feb Feb DE Revise & resubmit Waste Receiving, Storage & Feeding Equipment to IC, Employer & ER 7 07-Feb Feb Feb Mar DE IC checks & certifies Waste Receiving, Storage and Feeding Equipment 7 14-Feb Feb Mar Mar DE Employer consents to Waste Receiving, Storage and Feeding Equipment 0 06-Mar Mar DE Prepare & submit Detailed Design of Waste Receiving, Storage & Feeding System to IC, ER & Employer Apr May Jul Sep DE Prepare & submit Method of Construction for Waste Receiving, Storage and Feeding System Apr May Aug Sep DE IC checks & comments on Detailed Design of Waste Receiving, Storage & Feeding System May Jun Sep Sep DE Revise & resubmit Detailed Design of Waste Receiving, Storage & Feeding System to IC, Employer & ER 7 11-Jun Jun Sep Sep DE IC checks & certifies Waste Receiving, Storage and Feeding System 7 18-Jun Jun Sep Oct DE Employer consents to Waste Receiving, Storage and Feeding System 0 08-Jul Oct Pre-Treatment System Jan Jul Jan Oct Jan Jul Jan Oct Jan Jul Jan Oct DE Prepare & make Pre-treatment Equipment & Performance Submission to IC, ER & Employer Jan Feb Jan Feb-15 2 DE IC checks & comments on Pre-Treatment Equipment Feb Feb Feb Feb-15 4 DE Revise & resubmit Pre-Treatment Equipment IC, Employer & ER 7 19-Feb Feb Feb Mar-15 4 DE IC checks & certifies Pre-treatment Equipment 7 26-Feb Mar Mar Mar-15 4 DE Employer consents to Pre-treatment Equipment 0 18-Mar Mar-15 4 DE Prepare & submit Detailed Design of Pre-treatment System to IC, ER & Employer Apr Jun Jul Sep DE Prepare & submit Method of Construction for Pre-treatment System May Jun Aug Sep DE IC checks & comments on Detailed Design of Pre-Treatment System Jun Jun Sep Sep DE Revise & resubmit Detailed Design of Pre-Treatment System to IC, Employer & ER 7 23-Jun Jun Sep Sep DE IC checks & certifies Detailed Design of Pre-treatment System 7 30-Jun Jul Sep Oct DE Employer consents to Detailed Design of Pre-treatment System 0 20-Jul Oct Anaerobic Digestion (AD) Treatment System Feb Aug May Nov Feb Aug May Nov Feb Aug May Nov DE Prepare & make AD Equipment & Performance Submission to IC, ER & Employer Feb Mar May Jun DE IC checks & comments on AD Equipment Mar Mar Jun Jun DE Revise & resubmit AD Equipment to IC, Employer & ER 7 21-Mar Mar Jun Jun DE IC checks & certifies AD Equipment 7 28-Mar Apr Jun Jun DE Employer consents to AD Equipment 0 17-Apr Jul DE Prepare & submit Detailed Design of AD Treatment System to IC, ER & Employer May Jul Aug Oct DE Prepare & submit Method of Construction for AD Treatment System Jun Jul Sep Oct DE IC checks & comments on Detailed Design of AD treatment System Jul Jul Oct Oct DE Revise & resubmit Detailed Design of AD Treatment System to IC, Employer & ER 7 29-Jul Aug Oct Oct DE IC checks & certifies AD Treatment System 7 05-Aug Aug Oct Nov DE Employer consents to Detailed Design of AD Treatment System 0 25-Aug Nov Biogas Cleaning, Storage and Distribution System Jan Aug Feb Aug Jan Aug Feb Aug Jan Aug Feb Aug DE Prepare & make Biogas Equipment & Performance Submission to IC, ER & Employer Jan Feb Feb Mar DE IC checks & comments on Biogas Cleaning & Storage Equipment Feb Mar Mar Mar Revise & resubmit Detailed Process Documentation Submission to IC, Employer & ER IC checks & certifies Detailed Process Documentation Submission Employer consents to Detailed Process Documentation Submission Prepare & make Waste Receiving Equipment & Performance Submission to IC, ER & Employer IC checks & comments on Waste Receiving, Storage & Feeding Equipment Revise & resubmit Waste Receiving, Storage & Feeding Equipment to IC, Employer & ER IC checks & certifies Waste Receiving, Storage and Feeding Equipment Employer consents to Waste Receiving, Storage and Feeding Equipment Prepare & submit Detailed Design of Waste Receiving, Storage & Feeding System to IC, ER & Employer Prepare & submit Method of Construction for Waste Receiving, Storage and Feeding System IC checks & comments on Detailed Design of Waste Receiving, Storage & Feeding System Revise & resubmit Detailed Design of Waste Receiving, Storage & Feeding System to IC, Employer & ER IC checks & certifies Waste Receiving, Storage and Feeding System Employer consents to Waste Receiving, Storage and Feeding System Prepare & make Pre-treatment Equipment & Performance Submission to IC, ER & Employer IC checks & comments on Pre-Treatment Equipment Revise & resubmit Pre-Treatment Equipment IC, Employer & ER IC checks & certifies Pre-treatment Equipment Employer consents to Pre-treatment Equipment Prepare & submit Detailed Design of Pre-treatment System to IC, ER & Employer Prepare & submit Method of Construction for Pre-treatment System IC checks & comments on Detailed Design of Pre-Treatment System Revise & resubmit Detailed Design of Pre-Treatment System to IC, Employer & ER IC checks & certifies Detailed Design of Pre-treatment System Employer consents to Detailed Design of Pre-treatment System Prepare & make AD Equipment & Performance Submission to IC, ER & Employer IC checks & comments on AD Equipment Revise & resubmit AD Equipment to IC, Employer & ER IC checks & certifies AD Equipment Employer consents to AD Equipment Prepare & submit Detailed Design of AD Treatment System to IC, ER & Employer Prepare & submit Method of Construction for AD Treatment System IC checks & comments on Detailed Design of AD treatment System Revise & resubmit Detailed Design of AD Treatment System to IC, Employer & ER IC checks & certifies AD Treatment System Employer consents to Detailed Design of AD Treatment System Prepare & make Biogas Equipment & Performance Submission to IC, ER & Employer IC checks & comments on Biogas Cleaning & Storage Equipment Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 12 of 27 print: 27-Mar-15 18:32 Oracle Corporation
39 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DE Revise & resubmit Biogas Cleaning & Storage Equipment to IC, Employer & ER 7 11-Mar Mar Mar Apr Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Revise & resubmit Biogas Cleaning & Storage Equipment to IC, Employer & ER Contract Programme v1.2 OSCAR BIOENERGY JV DE IC checks & certifies Biogas Cleaning & Storage Equipment 7 18-Mar Mar Apr Apr DE Employer consents to Biogas Cleaning & Storage Equipment 0 07-Apr Apr DE Prepare & submit Detailed Design of Biogas System to IC, ER & Employer May Jun May Jul DE Prepare & submit Method of Construction for Biogas Cleaning & Storage System May Jun Jun Jul DE IC checks & comments on Detailed Design of Biogas System Jun Jul Jul Jul DE Revise & resubmit Detailed Design of Biogas System to IC, Employer & ER 7 09-Jul Jul Jul Aug DE IC checks & certifies Biogas Cleaning & Storage System 7 16-Jul Jul Aug Aug DE Employer consents to Biogas Cleaning & Storage System 0 05-Aug Aug Combined Heat Recovery and Power (CHP) Generation System Jan Jul Jan Jul Jan Jul Jan Jul Jan Jul Jan Jul-15 0 DE Prepare & make CHP Equipment & Performance Submission to IC, ER & Employer Jan Jan Jan Jan-15 0 DE IC checks & comments on CHP Equipment Jan Feb Jan Feb-15 0 DE Revise & resubmit CHP Equipment to IC, Employer & ER 7 14-Feb Feb Feb Feb-15 0 DE IC checks & certifies CHP Equipment 7 21-Feb Feb Feb Feb-15 0 DE Employer consents to CHP Equipment 0 13-Mar Mar-15 0 DE Prepare & submit Detailed Design of CHP Generation System to IC, ER & Employer Mar May Mar May-15 0 DE Prepare & submit Method of Construction for CHP Generation System Apr May Apr May-15 0 DE IC checks & comments on Detailed Design of CHP Generation System May Jun May Jun-15 0 DE Revise & resubmit Detailed Design of CHP Generation System to IC, Employer & ER 7 06-Jun Jun Jun Jun-15 0 DE IC checks & certifies CHP Generation System 7 13-Jun Jun Jun Jun-15 0 DE Employer consents to CHP Generation System 0 03-Jul Jul-15 0 Continuous Emission Monitoring System (CEMS) Feb Sep Mar Dec Feb Sep Mar Dec Feb Sep Mar Dec DE Prepare & make CEMS Equipment & Performance Submission to IC, ER & Employer Feb Mar Mar Apr-15 6 DE IC checks & comments on CEMS Equipment Mar Apr Apr Apr DE Revise & resubmit CEMS Equipment to IC, Employer & ER 7 10-Apr Apr Apr Apr DE IC checks & certifies CEMS Equipment 7 17-Apr Apr Apr May DE Employer consents to CEMS Equipment 0 07-May May DE Prepare & submit Detailed Design of CEMS to IC, ER & Employer Jun Jul Jun Aug-15 9 DE Prepare & submit Method of Construction for CAPC System Jun Jul Sep Oct DE IC Checks & comments on Detailed Design of CEMS Jul Aug Oct Nov DE Revise & resubmit Detailed Design of CEMS to IC, Employer & ER 7 11-Aug Aug Nov Nov DE IC checks & certifies CEMS 7 18-Aug Aug Nov Nov DE Employer consents to CEMS 0 07-Sep Dec Digestate Dewatering System Dec Jun Dec Feb Dec Jun Dec Feb Dec Jun Dec Feb DE Prepare & make Digestate Dewatering Equipment & Performance Submission to IC, ER & Employer Dec Jan Dec Jan-15 0 DE IC checks & comments on Digestate Dewatering Equipment Jan Jan Jan Jan-15 0 DE Revise & resubmit Digestate Dewatering Equipment to IC, Employer & ER 7 29-Jan Feb Jan Feb-15 0 DE IC checks & certifies Digestate Dewatering Equipment 7 05-Feb Feb Feb Feb-15 0 DE Employer consents to Digestate Dewatering Equipment 0 25-Feb Feb-15 0 DE Prepare & submit Detailed Design of Digestate Dewatering System to IC, ER & Employer Mar May Nov Dec DE Prepare & submit Method of Construction for Digestate Dewatering System Mar May Nov Dec DE IC checks & comments on Detailed Design of Digestate Dewatering System May May Jan Jan DE Revise & resubmit Detailed Design of Digestate Dewatering System to IC, Employer & ER 7 19-May May Jan Jan DE IC checks & certifies Digestate Dewatering System 7 26-May Jun Jan Jan IC checks & certifies Biogas Cleaning & Storage Equipment Employer consents to Biogas Cleaning & Storage Equipment Prepare & submit Detailed Design of Biogas System to IC, ER & Employer Prepare & submit Method of Construction for Biogas Cleaning & Storage System IC checks & comments on Detailed Design of Biogas System Revise & resubmit Detailed Design of Biogas System to IC, Employer & ER IC checks & certifies Biogas Cleaning & Storage System Employer consents to Biogas Cleaning & Storage System Prepare & make CHP Equipment & Performance Submission to IC, ER & Employer IC checks & comments on CHP Equipment Revise & resubmit CHP Equipment to IC, Employer & ER IC checks & certifies CHP Equipment Employer consents to CHP Equipment Prepare & submit Detailed Design of CHP Generation System to IC, ER & Employer Prepare & submit Method of Construction for CHP Generation System IC checks & comments on Detailed Design of CHP Generation System Revise & resubmit Detailed Design of CHP Generation System to IC, Employer & ER IC checks & certifies CHP Generation System Employer consents to CHP Generation System Prepare & make CEMS Equipment & Performance Submission to IC, ER & Employer IC checks & comments on CEMS Equipment Revise & resubmit CEMS Equipment to IC, Employer & ER IC checks & certifies CEMS Equipment Employer consents to CEMS Equipment Prepare & submit Detailed Design of CEMS to IC, ER & Employer Prepare & submit Method of Construction for CAPC System IC Checks & comments on Detailed Design of CEMS Revise & resubmit Detailed Design of CEMS to IC, Employer & ER IC checks & certifies CEMS Employer consents to CEMS Prepare & make Digestate Dewatering Equipment & Performance Submission to IC, ER & Employer IC checks & comments on Digestate Dewatering Equipment Revise & resubmit Digestate Dewatering Equipment to IC, Employer & ER IC checks & certifies Digestate Dewatering Equipment Employer consents to Digestate Dewatering Equipment Prepare & submit Detailed Design of Digestate Dewatering System to IC, ER & Employer Prepare & submit Method of Construction for Digestate Dewatering System IC checks & comments on Detailed Design of Digestate Dewatering System Revise & resubmit Detailed Design of Digestate Dewatering System to IC, Employer & ER IC checks & certifies Digestate Dewatering System Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 13 of 27 print: 27-Mar-15 18:32 Oracle Corporation
40 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DE Employer consents to Digestate Dewatering System 0 15-Jun Feb Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Employer consents to Digestate Dewatering System Composting and Maturation System Dec Jun Dec Dec Dec Jun Dec Dec Dec Jun Dec Dec DE Prepare & make Composting & Maturation Equipment & Performance Submission to IC, ER & Employer Dec Jan Dec Jan-15 0 DE IC checks & comments on Composting & Maturation Equipment Jan Jan Jan Jan-15 0 DE Revise & resubmit Composting & Maturation Equipment to IC, Employer & ER 7 29-Jan Feb Jan Feb-15 0 DE IC checks & certifies Composting & Maturation Equipment 7 05-Feb Feb Feb Feb-15 0 DE Employer consents to Composting & Maturation Equipment 0 25-Feb Feb-15 0 DE Prepare & submit Detailed Design of Composting System to IC, ER & Employer Mar May Sep Nov DE Prepare & submit Method of Construction for Composting System Mar May Oct Nov DE IC checks & comments on Detailed Design of Composting System May May Nov Nov DE Revise & resubmit Detailed Design of Composting System to IC, Employer & ER 7 19-May May Nov Dec DE IC checks & certifies Composting System 7 26-May Jun Dec Dec DE Employer consents to Composting System 0 15-Jun Dec Wastewater Treatment System (WWTS) Jan Sep Jan Nov Jan Sep Jan Nov Jan Sep Jan Nov DE Prepare & make WWTS Equipment & Performance Submission to IC, ER & Employer Jan Feb Jan Feb-15 5 DE IC checks & comments on WWTS Equipment Feb Feb Feb Mar DE Revise & resubmit WWTS Equipment to IC, Employer & ER 7 28-Feb Mar Mar Mar DE IC checks & certifies WWTS Equipment 7 07-Mar Mar Mar Mar DE Employer consents to WWTS Equipment 0 27-Mar Apr DE Prepare & submit Detailed Design of WWTS to IC, ER & Employer Jun Aug Jul Aug-15 9 DE Prepare & submit Method of Construction for Wastewater Treatment System Jul Aug Sep Oct DE IC checks & comments on Detailed Design ofwwts Aug Aug Oct Oct DE Revise & resubmit Detailed Design of WWTS to IC, Employer & ER 7 25-Aug Aug Oct Nov DE IC checks & certifies Wastewater Treatment System 7 01-Sep Sep Nov Nov DE Employer consents to Wastewater Treatment System 0 21-Sep Nov Centralized Air Pollution Control (CAPC) System Dec Jun Dec Jan Dec Jun Dec Jan Dec Jun Dec Jan DE Prepare & make CAPC Equipment & Performance Submission to IC, ER & Employer Dec Jan Dec Jan-15 0 DE IC checks & comments on CAPC System Equipment Jan Jan Jan Jan-15 0 DE Revise & resubmit CAPC System Equipment to IC, Employer & ER 7 29-Jan Feb Jan Feb-15 0 DE IC checks & certifies CAPC System Equipment 7 05-Feb Feb Feb Feb-15 0 DE Employer consents to CAPC System Equipment 0 25-Feb Feb-15 0 DE Prepare & Submit Detailed Design of CAPC System to IC, ER & Employer Mar May Jun Jul DE Prepare & submit Method of Construction for CAPC System Mar May Oct Nov DE IC checks & comments on Detailed Design of CAPC System May May Nov Dec DE Revise & resubmit Detailed Design of CAPC System to IC, Employer & ER 7 19-May May Dec Dec DE IC checks & certifies CAPC System 7 26-May Jun Dec Dec DE Employer consents to CAPC System 0 15-Jun Jan Electrical System and Accessories - Switchgear, LCP, Cable, Earthing, etc Mar Oct Mar Oct Mar Oct Mar Oct Mar Oct Mar Oct DE Prepare & make Elect. Equipment & Performance Submission to IC, ER & Employer Mar Apr Mar Apr-15 0 DE IC checks & comments on Electrical System Equipment Apr Apr Apr Apr-15 0 DE Revise & resubmit Electrical System Equipment to IC, Employer & ER 7 17-Apr Apr Apr Apr-15 0 DE IC checks & certifies Electrical System Equipment 7 24-Apr Apr Apr Apr-15 0 DE Employer consents to Electrical System Equipment 0 14-May May-15 0 Prepare & make Composting & Maturation Equipment & Performance Submission to IC, ER & Employer IC checks & comments on Composting & Maturation Equipment Revise & resubmit Composting & Maturation Equipment to IC, Employer & ER IC checks & certifies Composting & Maturation Equipment Employer consents to Composting & Maturation Equipment Prepare & submit Detailed Design of Composting System to IC, ER & Employer Prepare & submit Method of Construction for Composting System IC checks & comments on Detailed Design of Composting System Revise & resubmit Detailed Design of Composting System to IC, Employer & ER IC checks & certifies Composting System Employer consents to Composting System Prepare & make WWTS Equipment & Performance Submission to IC, ER & Employer IC checks & comments on WWTS Equipment Revise & resubmit WWTS Equipment to IC, Employer & ER IC checks & certifies WWTS Equipment Employer consents to WWTS Equipment Prepare & submit Detailed Design of WWTS to IC, ER & Employer Prepare & submit Method of Construction for Wastewater Treatment System IC checks & comments on Detailed Design ofwwts Revise & resubmit Detailed Design of WWTS to IC, Employer & ER IC checks & certifies Wastewater Treatment System Employer consents to Wastewater Treatment System Prepare & make CAPC Equipment & Performance Submission to IC, ER & Employer IC checks & comments on CAPC System Equipment Revise & resubmit CAPC System Equipment to IC, Employer & ER IC checks & certifies CAPC System Equipment Employer consents to CAPC System Equipment Prepare & Submit Detailed Design of CAPC System to IC, ER & Employer Prepare & submit Method of Construction for CAPC System IC checks & comments on Detailed Design of CAPC System Revise & resubmit Detailed Design of CAPC System to IC, Employer & ER IC checks & certifies CAPC System Employer consents to CAPC System Prepare & make Elect. Equipment & Performance Submission to IC, ER & Employer IC checks & comments on Electrical System Equipment Revise & resubmit Electrical System Equipment to IC, Employer & ER IC checks & certifies Electrical System Equipment Employer consents to Electrical System Equipment Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 14 of 27 print: 27-Mar-15 18:32 Oracle Corporation
41 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DE Prepare & submit Detailed Design of Electrical System to IC, ER & Employer Jul Aug Jul Sep Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Prepare & submit Detailed Design of Electrical System to IC, ER & Employer Contract Programme v1.2 OSCAR BIOENERGY JV DE Prepare & submit Method of Construction for Electrical System Jul Aug Aug Sep-15 9 DE IC checks & comments on Detailed Design of Electrical System Aug Sep Sep Sep DE Revise & resubmit Detailed Design of Electrical System to IC, Employer & ER 7 08-Sep Sep Sep Sep DE IC checks & certifies Electrical System 7 15-Sep Sep Sep Oct DE Employer consents to Electrical System 0 05-Oct Oct Instrumentation, Control and Monitoring System (SCADA/PLC) Mar Oct Jun Dec Mar Oct Jun Dec Mar Oct Jun Dec DE Prepare & make SCADA/PLC Equipment & Performance Submission to IC, ER & Employer Mar Apr Jun Jul DE IC checks & comments on SCADA/PLC Equipment Apr May Jul Aug DE Revise & resubmit SCADA/PLC Equipment to IC, Employer & ER 7 09-May May Aug Aug DE IC checks & certifies SCADA/PLC Equipment 7 16-May May Aug Aug DE Employer consents to SCADA/PLC Equipment 0 05-Jun Sep DE Prepare & submit Detailed Design of SCADA/PLC to IC, ER & Employer Jul Sep Sep Nov DE Prepare & submit Method of Construction for SCADA/PLC System Aug Sep Oct Nov DE IC checks & comments on Detailed Design of SCADA/PLC System Sep Sep Nov Dec DE Revise & resubmit Detailed Design of SCADA/PLC System to IC, Employer & ER 7 24-Sep Sep Dec Dec DE IC checks & certifies SCADA/PLC System 7 01-Oct Oct Dec Dec DE Employer consents to SCADA/PLC System 0 21-Oct Dec DETAILED DESIGN SUBMISSION (DDS) BUILDING SERVICES Apr Nov Apr Dec Lift & Fire Services Installations (FSI) Jun Oct Jun Dec Jun Oct Jun Dec Jun Oct Jun Dec DS Prepare & submit Lift, Fire Safety, Dangerous Goods Application & FSI to FSD & EMSD Jun Aug Jun Aug-15 8 DS Prepare & submit Method of Construction for Lift & FSI Jul Aug Aug Sep-15 9 DS Submit Lift & FSI Detailed Design to IC, ER & Employer 0 01-Sep Sep-15 8 DS IC checks & comments on Lift & FSI Detailed Design Sep Sep Oct Nov DS Revise & resubmit Lift & FSI Detailed Design to IC, Employer & ER 7 16-Sep Sep Nov Nov DS IC checks & certifies Lift & FSI Detailed Design 7 23-Sep Sep Nov Nov DS Employer consents to Lift & FSI Detailed Design 0 13-Oct Dec Waste Receiving, Pre-treatment & Administration Bldg # May Jul Sep Dec May Jul Sep Dec May Jul Sep Dec DS Prepare & make Bldg #1 BS Detailed Design - Electrical System to IC, ER & Employer May Jun Sep Oct DS Prepare & make Bldg #1 BS Detailed Design - FS System to IC, ER & Employer May Jun Sep Oct DS Prepare & make Bldg #1 BS Detailed Design - P/D System to IC, ER & Employer May Jun Sep Oct DS Prepare & make Bldg #1 BS Detailed Design - MVAC System to IC, ER & Employer May Jun Sep Oct DS Prepare & submit Method of Construction for Bldg #1 Building Services May Jun Sep Oct DS IC checks & comments on Bldg #1 Building Services Jun Jul Oct Nov DS Revise & resubmit Bldg #1 BS Detailed Design to IC, Employer & ER 7 02-Jul Jul Nov Nov DS IC checks & certifies Bldg #1 Building Services 7 09-Jul Jul Nov Nov DS Employer consents to Bldg #1 Building Services 0 29-Jul Dec Composting & Maturation Building # Apr Jun Apr Jul Apr Jun Apr Jul Apr Jun Apr Jul-15 8 DS Prepare & make Bldg #2 BS Detailed Design - Electrical System to IC, ER & Employer Apr May Apr May-15 6 DS Prepare & make Bldg #2 BS Detailed Design - FS System to IC, ER & Employer Apr May Apr May-15 6 DS Prepare & make Bldg #2 BS Detailed Design - P/D System to IC, ER & Employer Apr May Apr May-15 6 DS Prepare & make Bldg #2 BS Detailed Design - MVAC System to IC, ER & Employer Apr May Apr May-15 6 DS Prepare & submit Method of Construction for Bldg #2 Building Services Apr May Apr May-15 6 Prepare & submit Method of Construction for Electrical System IC checks & comments on Detailed Design of Electrical System Revise & resubmit Detailed Design of Electrical System to IC, Employer & ER IC checks & certifies Electrical System Employer consents to Electrical System Prepare & make SCADA/PLC Equipment & Performance Submission to IC, ER & Employer IC checks & comments on SCADA/PLC Equipment Revise & resubmit SCADA/PLC Equipment to IC, Employer & ER IC checks & certifies SCADA/PLC Equipment Employer consents to SCADA/PLC Equipment Prepare & submit Detailed Design of SCADA/PLC to IC, ER & Employer Prepare & submit Method of Construction for SCADA/PLC System IC checks & comments on Detailed Design of SCADA/PLC System Revise & resubmit Detailed Design of SCADA/PLC System to IC, Employer & ER IC checks & certifies SCADA/PLC System Employer consents to SCADA/PLC System Prepare & submit Lift, Fire Safety, Dangerous Goods Application & FSI to FSD & EMSD Prepare & submit Method of Construction for Lift & FSI Submit Lift & FSI Detailed Design to IC, ER & Employer IC checks & comments on Lift & FSI Detailed Design Revise & resubmit Lift & FSI Detailed Design to IC, Employer & ER IC checks & certifies Lift & FSI Detailed Design Employer consents to Lift & FSI Detailed Design Prepare & make Bldg #1 BS Detailed Design - Electrical System to IC, ER & Employer Prepare & make Bldg #1 BS Detailed Design - FS System to IC, ER & Employer Prepare & make Bldg #1 BS Detailed Design - P/D System to IC, ER & Employer Prepare & make Bldg #1 BS Detailed Design - MVAC System to IC, ER & Employer Prepare & submit Method of Construction for Bldg #1 Building Services IC checks & comments on Bldg #1 Building Services Revise & resubmit Bldg #1 BS Detailed Design to IC, Employer & ER IC checks & certifies Bldg #1 Building Services Employer consents to Bldg #1 Building Services Prepare & make Bldg #2 BS Detailed Design - Electrical System to IC, ER & Employer Prepare & make Bldg #2 BS Detailed Design - FS System to IC, ER & Employer Prepare & make Bldg #2 BS Detailed Design - P/D System to IC, ER & Employer Prepare & make Bldg #2 BS Detailed Design - MVAC System to IC, ER & Employer Prepare & submit Method of Construction for Bldg #2 Building Services Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 15 of 27 print: 27-Mar-15 18:32 Oracle Corporation
42 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float DS IC checks & comments on Bldg #2 Building Services May May May Jun Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr IC checks & comments on Bldg #2 Building Services Contract Programme v1.2 OSCAR BIOENERGY JV DS Revise & resubmit Bldg #2 BS Detailed Design to IC, Employer & ER 7 30-May Jun Jun Jun DS IC checks & certifies Bldg #2 Building Services 7 06-Jun Jun Jun Jun DS Employer consents to Bldg #2 Building Services 0 26-Jun Jul Auxilary Building & Facilities # Aug Nov Aug Nov Aug Nov Aug Nov Aug Nov Aug Nov DS Prepare & make Bldg #3 BS Detailed Design - Electrical System to IC, ER & Employer Aug Sep Aug Oct DS Prepare & make Bldg #3 BS Detailed Design - FS System to IC, ER & Employer Aug Sep Aug Oct DS Prepare & make Bldg #3 BS Detailed Design - P/D System to IC, ER & Employer Aug Sep Aug Oct DS Prepare & make Bldg #3 BS Detailed Design-MVAC of Energy Centre to IC, ER & Employer Aug Sep Aug Oct DS Prepare & make Bldg #3 BS Detailed Design- ELV System to IC, ER & Employer Aug Sep Aug Oct-15 8 DS Prepare & submit Method of Construction for Bldg #3 Building Services Aug Sep Sep Oct-15 8 DS IC checks & comments on Bldg #3 Building Services Oct Oct Oct Oct DS Revise & resubmit Bldg #3 BS Detailed Design to IC, Employer & ER 7 15-Oct Oct Oct Nov DS IC checks & certifies Bldg #3 Building Services 7 22-Oct Oct Nov Nov DS Employer consents to Bldg #3 Building Services 0 11-Nov Nov STATUTORY AND UTILITIES DESIGN SUBMISSION Jan Oct Feb Sep Jan Oct Feb Sep Jan Oct Feb Sep Jan Oct Feb Sep SU EPD, LandsD, PlanD & ArchSD - Approval for Landscape & Bldg #2 Green Roof Design Jul Aug Aug Aug SU ArchSD - Comment for Architectural Design Mar Apr Sep Sep SU GEO - Comment for Geotechnical Matters Feb Mar Apr May SU EPD - Sewage Discharge License approval May Jun Jul Aug SU CLP - Approval of Transformer Room layout, Cable duct arrangement and Grid Connection Aug Sep Sep Oct SU CLP - Approval of Submission Package on Grid Arrangement Aug Sep Sep Oct SU DSD - Approval for Stormwater and Sewerage Connection May Jun Jul Aug SU WSD - Approval for Water Supply & Plumbing May Jun Jun Jul SU FSD - Approval for Fire Safety, Dangerous Goods Application and Fire Services Installations Aug Aug Aug Sep SU EMSD - Approval for Lift Design Aug Aug Aug Sep SU HyD & TD - Approval for Access Road & Entrance Sep Oct Oct Nov SU LandsD & EPD - Approval of Tree preservation, transplanting and felling proposals (Excl. Natural Terrain) Jan Apr Feb May SU LandsD & EPD - Approval of Tree preservation, transplanting and felling proposals (Natural Terrain - if any) Apr Jun Jul Sep PROCUREMENT, MANUFACTURING, F.A.T., SHIPMENT AND DELIVERY OF E&M SYSTEMS EQUIPMENT Feb Jul Feb Nov Waste Receiving, Storage and Feeding System Mar Jan Mar Sep Mar Jan Mar Sep Mar Jan Mar Sep PR Issue orders & receive shop drawings from Waste Receiving, Storage and Feeding System suppliers Mar Apr Mar Apr PR Overhead Grabbing System Apr Jan Jul Apr PR Weighbridge Platform Jul Dec Mar Aug PR Weighbridge Computer System Oct Jan Jun Sep PR Vehicle Wash Plant Jul Dec May Sep PR Water Reclamation System Jul Dec May Sep Pre-Treatment System Mar Jan Mar Aug Mar Jan Mar Aug Mar Jan Mar Aug PR Issue orders & receive shop drawings from Pre-treatment suppliers Mar Apr Mar Apr-15 2 PR Reception Hoppers and Screw Conveyors Aug Dec Feb Jun PR Crushers Sep Jan Mar Jul PR Sieve Drums Sep Jan Jan May PR Sand Grip Trap Sep Jan Mar Jul Revise & resubmit Bldg #2 BS Detailed Design to IC, Employer & ER IC checks & certifies Bldg #2 Building Services Employer consents to Bldg #2 Building Services Prepare & make Bldg #3 BS Detailed Design - Electrical System to IC, ER & Employer Prepare & make Bldg #3 BS Detailed Design - FS System to IC, ER & Employer Prepare & make Bldg #3 BS Detailed Design - P/D System to IC, ER & Employer Prepare & make Bldg #3 BS Detailed Design-MVAC of Energy Centre to IC, ER & Employer Prepare & make Bldg #3 BS Detailed Design- ELV System to IC, ER & Employer Prepare & submit Method of Construction for Bldg #3 Building Services IC checks & comments on Bldg #3 Building Services Revise & resubmit Bldg #3 BS Detailed Design to IC, Employer & ER IC checks & certifies Bldg #3 Building Services Employer consents to Bldg #3 Building Services EPD, LandsD, PlanD & ArchSD - Approval for Landscape & Bldg #2 Green Roof Design ArchSD - Comment for Architectural Design GEO - Comment for Geotechnical Matters EPD - Sewage Discharge License approval CLP - Approval of Transformer Room layout, Cable duct arrangement and Grid Connection CLP - Approval of Submission Package on Grid Arrangement DSD - Approval for Stormwater and Sewerage Connection WSD - Approval for Water Supply & Plumbing FSD - Approval for Fire Safety, Dangerous Goods Application and Fire Services Installations EMSD - Approval for Lift Design HyD & TD - Approval for Access Road & Entrance LandsD & EPD - Approval of Tree preservation, transplanting and felling proposals (Excl. Natural Terrain) LandsD & EPD - Approval of Tree preservation, transplanting and felling proposals (Natural Terrain - if any) Issue orders & receive shop drawings from Waste Receiving, Storage and Feeding System suppliers Overhead Grabbing System Weighbridge Platform Weighbridge Computer System Vehicle Wash Plant Water Reclamation System Issue orders & receive shop drawings from Pre-treatment suppliers Reception Hoppers and Screw Conveyors Crushers Sieve Drums Sand Grip Trap Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 16 of 27 print: 27-Mar-15 18:32 Oracle Corporation
43 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float PR Suspension Buffer Tank Sep Jan Apr Aug Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Suspension Buffer Tank PR Pumps and Mixers Oct Jan May Aug PR Overhead Travelling Crane Jul Jan Nov May Pumps and Mixers Overhead Travelling Crane Anaerobic Digestion (AD) Treatment System Apr Jan Jul Aug Apr Jan Jul Aug Apr Jan Jul Aug PR Issue orders & receive shop drawings from AD suppliers Apr May Jul Aug Issue orders & receive shop drawings from AD suppliers PR Digester Tanks Aug Dec Nov Mar PR Jet Mixing System Aug Dec Nov Mar PR Heat Exchangers Aug Dec Nov Mar PR Digestate Circulation and Feeding Pumps Aug Dec Nov Mar PR Intermediate Digestate Tanks Oct Jan May Aug Digester Tanks Jet Mixing System Heat Exchangers Digestate Circulation and Feeding Pumps Intermediate Digestate Tanks Biogas Cleaning, Storage and Distribution System Apr Jun Apr Jul Biogas Cleaning and Storage System Apr Feb Apr Jul Apr Feb Apr Jul PR Issue orders & receive shop drawings from Biogas suppliers Apr Apr Apr May Issue orders & receive shop drawings from Biogas suppliers PR Desulphurisation System Nov Feb Apr Jul PR Biogas Storage Tank Nov Feb Apr Jul Biogas Distribution System Apr Jun Apr Jul Apr Jun Apr Jul PR Standby Gas Flaring Unit Aug Jan Feb Jul Desulphurisation System Biogas Storage Tank Standby Gas Flaring Unit PR Issue orders & receive shop drawings from Biogas suppliers Apr Apr Apr May Issue orders & receive shop drawings from Biogas suppliers PR Biogas Blowers Aug Jun Aug Jul PR Biogas Cooling and Condensate Removal System Aug Jun Aug Jul Biogas Blowers Biogas Cooling and Condensate Removal System Combined Heat Recovery and Power (CHP) Generation System Mar Jul Mar Aug Mar Jul Mar Aug Mar Jul Mar Aug PR Issue orders & receive shop drawings from CHP suppliers Mar Mar Mar Mar-15 0 Issue orders & receive shop drawings from CHP suppliers PR Co Generator and Heat Exchanger Jul Jul Jul Jul-16 0 Co Generator and Heat Exchanger PR FAT of Co-Generator and Heat Exchanger 5 29-Sep Oct Jun Jun PR Electric Water Heater Jul Oct May Aug PR Heat Water Circulation Pumps Jul Oct May Aug Continuous Emission Monitoring System (CEMS) May Feb May May May Feb May May PR Issue orders & receive shop drawings from CEMS suppliers May Jun May Jun-15 9 PR CEMS Equipment Sep Feb Dec May Digestate Dewatering System Feb Jan Feb Sep Feb Jan Feb Sep Feb Jan Feb Sep PR Issue orders & receive shop drawings from Digestate Dewatering suppliers Feb Mar Feb Mar-15 0 PR Centrifuge Jun Jan Feb Sep PR Polymer Dosing System Jun Jan Feb Sep Composting System (Composting Tunnel, Maturation Area and Structurant Reception Area) Feb Jan Feb Nov Feb Jan Feb Nov Feb Jan Feb Nov PR Issue orders & receive shop drawings from Composting suppliers Feb Mar Feb Mar-15 0 PR Crusher Jun Nov Apr Sep PR Mixers Jun Jan Feb Sep PR Sieve Jun Nov Apr Sep PR Compost Bagging Machine Jun Nov Jun Nov PR Aeration Blowers Jun Nov May Oct PR Heat Exchangers Jun Nov May Oct PR Hot Water Circulation Pumps Jun Nov May Oct PR Tunnel Doors Jun Nov Dec May FAT of Co-Generator and Heat Exchanger Electric Water Heater Heat Water Circulation Pumps Issue orders & receive shop drawings from CEMS suppliers CEMS Equipment Issue orders & receive shop drawings from Digestate Dewatering suppliers Centrifuge Polymer Dosing System Issue orders & receive shop drawings from Composting suppliers Crusher Mixers Sieve Compost Bagging Machine Aeration Blowers Heat Exchangers Hot Water Circulation Pumps Tunnel Doors Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 17 of 27 print: 27-Mar-15 18:32 Oracle Corporation
44 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float PR Wheel Loaders Jun Nov May Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Wheel Loaders Contract Programme v1.2 OSCAR BIOENERGY JV Wastewater Treatment System (WWTS) Mar Apr Mar Jun Mar Apr Mar Jun Mar Apr Mar Jun PR Issue orders & receive shop drawings from WWTS suppliers Mar Apr Mar Apr-15 8 Issue orders & receive shop drawings from WWTS suppliers PR Wastewater Treatment Plant Sep Feb Nov Apr PR Ammonia Stripping Plant Sep Apr Dec Jun Wastewater Treatment Plant Ammonia Stripping Plant Centralized Air Pollution Control (CAPC) System Feb Nov Feb Jun Feb Nov Feb Jun Feb Nov Feb Jun PR Issue orders & receive shop drawings from CAPC suppliers Feb Mar Feb Mar-15 0 Issue orders & receive shop drawings from CAPC suppliers PR CAPC System Equipment Jun Nov Jan Jun Bulk Material Jul Mar Nov Aug Jul Mar Nov Aug Jul Mar Nov Aug PR Mechanical Equipment - Penstock, Pipework, Valve, Lifting Appliance, Roller Shutters etc Jul Dec Nov Apr PR Platforms, Handrails and Ladders Nov Mar Apr Aug Electrical System & Accessories May Apr May Apr May Apr May Apr May Apr May Apr-16 9 PR Issue orders & receive shop drawings from Electrical suppliers May Jun May Jun-15 0 PR MCC and Electrical Accessories System Oct Apr Oct Apr-16 9 PR Cables and Accessories, Cable Containment System Oct Dec Jan Apr PR Earthing and Lightning Oct Dec Feb Apr PR Emergency Generator Oct Mar Nov Apr Main LV Switch Board Oct Apr Oct Apr Oct Apr Oct Apr PR LV Switch Board, switchgear and Instrumentation Oct Apr Oct Apr PR FAT of LV Switch Board 2 24-Mar Mar Apr Apr SCADA /PLC System May Feb Aug May May Feb Aug May May Feb Aug May PR Issue orders & receive shop drawings from SCADA/PLC suppliers May Jun Aug Sep PR SCADA/PLC System and component Oct Feb Dec May PR FAT of SCADA/PLC System 2 29-Jan Feb Apr Apr Building Services Equipment (Including Lift & Renewable Energy System) Feb Apr Mar Jul Feb Apr Mar Jul Feb Apr Mar Jul PR Issue orders & receive shop drawings from BS suppliers Feb Mar Mar Apr PR Firemen and Disable Lift Oct Feb Dec Apr PR Absorption Chiller Jul Nov Dec Apr PR Electrical Chiller Nov Mar Dec Apr PR Cooling Tower Nov Mar Nov Mar-16 9 PR Airduct and Accessories Jan Apr Feb Apr-16 9 PR Chilled Water Circulation Pumps Jul Nov Dec Apr PR Fan coil and air handling units Jul Nov Dec Apr PR Fire Services System Equipment Nov Mar Dec Apr PR Plumbing and Drainage System Equipment Nov Mar Dec Apr PR ELV System Equipment Nov Mar Mar Jul CIVIL AND STRUCTURAL WORKS Feb Dec Apr Apr General Feb Mar Apr May Feb Mar Apr May Feb Mar Apr May CC Permission / Comments from WSD before Commencement of works Feb Mar Apr May CAPC System Equipment Mechanical Equipment - Penstock, Pipework, Valve, Lifting Appliance, Roller Shutters etc. Platforms, Handrails and Ladders Issue orders & receive shop drawings from Electrical suppliers MCC and Electrical Accessories System Cables and Accessories, Cable Containment System Earthing and Lightning Emergency Generator LV Switch Board, switchgear and Instrumentation FAT of LV Switch Board Issue orders & receive shop drawings from SCADA/PLC suppliers SCADA/PLC System and component FAT of SCADA/PLC System Issue orders & receive shop drawings from BS suppliers Firemen and Disable Lift Absorption Chiller Electrical Chiller Cooling Tower Airduct and Accessories Chilled Water Circulation Pumps Fan coil and air handling units Fire Services System Equipment Plumbing and Drainage System Equipment ELV System Equipment Permission / Comments from WSD before Commencement of works Waste Receiving, Pre-treatment & Administration Building #1 (Zone #1) Aug Oct Aug Mar Location at Grid 6-15/H-M Aug Oct Aug Jan Aug Oct Aug Jan Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 18 of 27 print: 27-Mar-15 18:32 Oracle Corporation
45 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float CC Excavation by Open Cut Aug Sep Aug Sep-15 0 Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Excavation by Open Cut CC Installation of Ground Beams and Slabs Sep Oct Sep Oct-15 0 CC Underground Drainage Work Oct Oct Dec Jan Location at Grid 6-15/L-O Sep Nov Nov Mar Sep Nov Nov Mar CC Excavation by Open Cut Limited to Grid 11-15/M-O Sep Sep Nov Dec CC Drive Type II Sheet Pile forming planking wall for ELS 6 25-Sep Oct Jan Jan CC Install ELS and further excavate for Deep Bunker Oct Oct Jan Jan CC Construct Deep Bunker r.c. structure Oct Nov Jan Feb CC Backfilling - reinstate to Lev. Approx m.P.D Nov Nov Feb Mar CC Excavation by Open Cut to whole area Sep Oct Dec Jan CC Installation of Ground Beams and Slabs Oct Nov Jan Feb General Oct Oct Oct Mar Oct Oct Oct Mar CC Underground Drainage Work Nov Dec Mar Apr CC Base of Suspension Buffer Tank Nov Dec Feb Mar CC Wall and Column G/F to m.P.D Oct Dec Oct Dec-15 0 CC Floor Slabs and Beam at m.P.D Dec Dec Dec Dec-15 0 CC Wall and Column from m.P.D. to m.P.D Dec Jan Dec Jan-16 0 CC Floor Slabs and Beam at m.P.D Jan Feb Jan Feb-16 0 CC Wall and Column from m.P.D. to m.P.D Feb Mar Mar Apr CC Fabricate & Deliver Roof Structural Steelwork Oct Jan Dec Apr CC Erect Roof Steelwork at mPD 6 03-Mar Mar Apr Apr CC Roof at m.P.D Mar Mar Nov Nov CC Clearance of Internal Area of G/F 6 29-Dec Jan Mar Mar CC Erect bamboo working platform at Internal Area of G/F Jan Jan Mar Mar CC ABWF Works at G/F Jan Feb Mar Apr CC Clearance of Internal Area of Mezz Lev. & 1/F 9 01-Mar Mar Mar Mar-16 0 CC Erect bamboo working platform at Internal Area of Mess Lev. & 1.F Mar Mar Mar Mar-16 0 CC ABWF Works at 1/F to R/F Mar May Mar May-16 0 CC Rermoval of Scaffolding and Working Platform 0 17-May Aug CC External and Remaining ABWF Works Mar Jul Dec Mar CC Handover G/F to E&M Works (Zone #1.1) 0 04-Feb Apr CC Handover 1/F to E&M Works (Zone #1.2) 0 18-Apr Apr-16 0 CC Interior Fitting-out Works to Admin & Visitor Areas Aug Oct Dec Mar Installation of Ground Beams and Slabs Underground Drainage Work Excavation by Open Cut Limited to Grid 11-15/M-O Drive Type II Sheet Pile forming planking wall for ELS Install ELS and further excavate for Deep Bunker Construct Deep Bunker r.c. structure Backfilling - reinstate to Lev. Approx m.P.D. Excavation by Open Cut to whole area Installation of Ground Beams and Slabs Underground Drainage Work Base of Suspension Buffer Tank Wall and Column G/F to m.P.D. Floor Slabs and Beam at m.P.D. Wall and Column from m.P.D. to m.P.D. Floor Slabs and Beam at m.P.D. Wall and Column from m.P.D. to m.P.D. Fabricate & Deliver Roof Structural Steelwork Erect Roof Steelwork at mPD Roof at m.P.D. Clearance of Internal Area of G/F Erect bamboo working platform at Internal Area of G/F ABWF Works at G/F Clearance of Internal Area of Mezz Lev. & 1/F Erect bamboo working platform at Internal Area of Mess Lev. & 1.F ABWF Works at 1/F to R/F Rermoval of Scaffolding and Working Platform External and Remaining ABWF Works Handover G/F to E&M Works (Zone #1.1) Handover 1/F to E&M Works (Zone #1.2) Interior Fitting-out Works to Admin & Visitor A Composting Building & Facilities - Zone # May Dec May Mar Composting Building #2 (Zone #2.1) May Dec May Mar For Location at Grid 1-5/A-C May Jul May Oct CC Excavation by Open Cut May Jun May Jun-15 0 Excavation by Open Cut CC Tank slabs and walls Jun Jul Jun Jul-15 0 CC Installation of Ground Beams and Slabs Jul Jul Sep Oct CC Underground Drainage Work Jul Jul Jul Jul-15 0 For Location at Grid 1-5/C-G Jul Sep Jul Oct CC Excavation by Open Cut Jul Aug Jul Aug-15 0 CC Installation of Ground Beams and Slabs Aug Sep Sep Oct CC Underground Drainage Work Aug Sep Sep Oct General Sep Dec Oct Mar CC Backfilling works Sep Oct Oct Nov CC Walls & Columns G/F to 1/F Oct Jan Nov Jan-16 6 CC Superstructure - 1/F Slab & Beams Dec Jan Jan Feb-16 6 Tank slabs and walls Installation of Ground Beams and Slabs Underground Drainage Work Excavation by Open Cut Installation of Ground Beams and Slabs Underground Drainage Work Backfilling works Walls & Columns G/F to 1/F Superstructure - 1/F Slab & Beams Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 19 of 27 print: 27-Mar-15 18:32 Oracle Corporation
46 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float CC Superstructure - 1/F to Roof Feb Feb Jun Jul Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Superstructure - 1/F to Roof CC Clearance 6 18-Feb Feb Jul Jul CC Erect Bamboo Working Platform for Internal Finishing Works Feb Mar Jul Aug CC Internal Finishing Works Mar Apr Jan Mar CC Erect Bamboo Working Platform for External Finishing Works Mar Mar Aug Aug CC External Finishing Works Mar May Aug Oct CC ABWF Work Jan Feb Jan Mar-16 6 CC Remaining ABWF Work Feb May Mar May-16 6 CC Handover to E&M Works (Zone #2.1) 0 23-May May-16 6 CC Green Roof and Planting Preparation Works Jul Oct Oct Jan CC Green Roof and Planting Works Oct Nov Jan Feb CC Green Roof Landscape Softworks Nov Dec Feb Mar Link Bridge (Zone #2.2) Oct May Dec Jul Oct May Dec Jul CC Fabricate & deliver Structural Steelwork Oct Mar Dec May CC Installation of Bearing Support for Link Bridge at Bldg 1 & Mar Mar Apr May CC Erect Steelwork for Link Bridge Mar Apr May May CC ABWF Works at Link Bridge Apr May May Jul CC Handover to E&M Works at Link Bridge (Zone #2.2) 0 25-May Jul Auxilliary Buildings & Facilities (Zone #3) May Dec May Apr Energy Centre (Building # 3/Zone #3.1) Oct Mar Oct Mar Oct Mar Oct Mar-16 0 CC Excavation for Bldg #3.1 & Cogen Units Oct Nov Oct Nov-15 0 CC Raft Foundations Nov Dec Nov Dec-15 0 CC Foul Drainage Connections Dec Dec Dec Dec-15 0 CC Slab at G/F Bldg # Dec Jan Dec Jan-16 0 CC Walls & Columns G/F to 1/F 5 09-Jan Jan Jan Jan-16 0 CC Slab at 1/F 6 15-Jan Jan Jan Jan-16 0 CC Walls & Columns 1/F to R/F 6 22-Jan Jan Jan Jan-16 0 CC R/F Slab & Beams 6 29-Jan Feb Jan Feb-16 0 CC Parapet Walls 5 05-Feb Feb Feb Feb-16 0 CC Backfilling Works Jan Jan Feb Feb CC Concrete Plinths / Walls / Trenches Jan Feb Feb Mar CC ABWF Works Feb Mar Feb Mar-16 0 CC Handover to E&M Works (Bldg #3/Zone #3.1) 0 03-Mar Mar-16 0 Anaerobic Digestion Tanks ( Zone #3.2) May Mar May Mar May Oct May Oct-15 0 CC Mobilization and Pre-drilling for AD Tank Socketed Steel-H Piles May Jul May Jul-15 0 CC Installation of Pre-bored Socketed Steel-H Piles May Aug May Aug-15 0 CC Proof Drilling Aug Sep Aug Sep-15 0 CC Pile Load Test Aug Sep Aug Sep-15 0 CC Excavation Sep Oct Sep Oct-15 0 Installation of AD r.c. Pile Cap Oct Jan Oct Jan-16 0 CC AD Pump Room Oct Nov Oct Nov-15 0 CC AD Tank Nov Nov Nov Nov-15 0 CC AD Tank Nov Dec Nov Dec-15 0 CC AD Tank Dec Jan Dec Jan-16 0 General Jan Mar Jan Mar CC Backfilling to pile cap Jan Feb Jan Feb-16 0 CC AD Pump Room Jan Feb Jan Feb Clearance Erect Bamboo Working Platform for Internal Finishing Works Internal Finishing Works Erect Bamboo Working Platform for External Finishing Works External Finishing Works ABWF Work Remaining ABWF Work Handover to E&M Works (Zone #2.1) Green Roof and Planting Preparation Works Green Roof and Planting Works Green Roof Landscape Softwor Fabricate & deliver Structural Steelwork Installation of Bearing Support for Link Bridge at Bldg 1 & 2 Erect Steelwork for Link Bridge ABWF Works at Link Bridge Handover to E&M Works at Link Bridge (Zone #2.2) Excavation for Bldg #3.1 & Cogen Units Raft Foundations Foul Drainage Connections Slab at G/F Bldg #3 Walls & Columns G/F to 1/F Slab at 1/F Walls & Columns 1/F to R/F R/F Slab & Beams Parapet Walls Backfilling Works Concrete Plinths / Walls / Trenches ABWF Works Handover to E&M Works (Bldg #3/Zone #3.1) Mobilization and Pre-drilling for AD Tank Socketed Steel-H Piles Installation of Pre-bored Socketed Steel-H Piles Proof Drilling Pile Load Test Excavation AD Pump Room 1 AD Tank 1 AD Tank 2 AD Tank 3 Backfilling to pile cap AD Pump Room 1 Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 20 of 27 print: 27-Mar-15 18:32 Oracle Corporation
47 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float CC AD plinths Jan Feb Jan Feb Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr AD plinths CC ABWF for Pump Buildings Feb Mar Mar Mar CC Foul Drain Connection Feb Mar Mar Mar CC Boundary Wall (Wall Stem) Feb Mar Feb Mar-16 0 CC Bund Wall Mar Mar Feb Mar CC Concrete Plinths / Walls / Trenches Feb Mar Feb Mar-16 0 CC ABWF Works Mar Mar Mar Mar-16 0 CC Handover to E&M Works (Zone #3.2) 0 24-Mar Mar-16 0 Ammonia Stripper (Zone #3.3) Aug Nov Mar Jun Aug Nov Mar Jun CC Pre-drilling for Ammonia Stripper Socketed Steel-H Piles Aug Aug Mar Apr CC Installation of Pre-bored Socketed Steel-H Piles Aug Aug Mar Apr CC Proof Drilling 7 01-Sep Sep Apr Apr CC Pile Load Test Sep Sep Apr May CC Excavation 6 23-Sep Sep May May CC Pile Cap Oct Oct May Jun CC Backfilling to pile cap 6 28-Oct Nov Jun Jun CC Handover to E&M Works (Zone #3.3) 0 03-Nov Jun CAPCS Stack (Zone #3.4) Aug Sep Mar Apr Aug Sep Mar Apr CC Pre-drilling for CAPCS Stack Socketed Steel-H Piles 8 07-Aug Aug Mar Mar CC Installation of Pre-bored Socketed Steel-H Piles Aug Aug Mar Mar CC Proof Drilling 4 22-Aug Aug Mar Apr CC Pile Load Test Aug Sep Apr Apr CC Excavation Sep Sep Apr May CC Pile Cap Sep Oct May Jun CC Backfilling to pile cap 6 26-Oct Oct Jun Jun CC Erect structural steel support for CAPCS duct Nov Dec Jun Jun CC Handover to E&M Works (Zone #3.4) 0 16-Dec Jul ABWF for Pump Buildings Foul Drain Connection Boundary Wall (Wall Stem) Bund Wall Concrete Plinths / Walls / Trenches ABWF Works Handover to E&M Works (Zone #3.2) Pre-drilling for Ammonia Stripper Socketed Steel-H Piles Installation of Pre-bored Socketed Steel-H Piles Proof Drilling Pile Load Test Excavation Pile Cap Backfilling to pile cap Handover to E&M Works (Zone #3.3) Pre-drilling for CAPCS Stack Socketed Steel-H Piles Installation of Pre-bored Socketed Steel-H Piles Proof Drilling Pile Load Test Excavation Pile Cap Backfilling to pile cap Erect structural steel support for CAPCS duct Handover to E&M Works (Zone #3.4) CC ABWF Work Aug Sep Mar Apr ABWF Work Biogas Cleaning & Storage Tank (Zone #3.5) Sep Jan Oct Jul Intermediate Digestate Tank Sep Nov Apr Jun CC Excavation Sep Sep Apr Apr CC Raft Foundations Sep Oct Apr May CC Foul Drainage Connections Oct Oct May May CC Concrete Plinths Oct Nov May Jun CC Backfilling Works 6 06-Nov Nov Jun Jun Desulphurization/Biogas Plant Room Oct Jan Oct Jul CC Excavation Oct Oct Oct Oct-15 0 CC Raft Foundations 6 30-Oct Nov Apr May CC Underground Drainage Work 6 06-Nov Nov May May CC R.C. structure of Plant Room Nov Nov May May CC Clearance 4 18-Dec Dec Jun Jun CC ABWF Works Dec Jan Jun Jul Desulphurization Tanks Oct Nov Jul Jul CC Excavation 6 16-Oct Oct Jul Jul CC Raft Foundations 9 24-Oct Nov Jul Jul CC Concrete Plinths 4 04-Nov Nov Jul Jul Handover to E&M Works 0 22-Jan Jan Jul Jul CC Handover to E&M Works (Zone #3.5) 0 22-Jan Jul Excavation Raft Foundations Foul Drainage Connections Concrete Plinths Backfilling Works Excavation Raft Foundations Underground Drainage Work R.C. structure of Plant Room Clearance ABWF Works Excavation Raft Foundations Concrete Plinths Handover to E&M Works (Zone #3.5) Weighbridge (Zone #3.6) Nov Apr Apr Aug Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 21 of 27 print: 27-Mar-15 18:32 Oracle Corporation
48 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float Nov Apr Apr Aug CC Excavation Nov Dec Apr May Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Excavation Contract Programme v1.2 OSCAR BIOENERGY JV CC Control Room Footing 9 04-Dec Dec May May CC Wall, Floor Slab and Stair Dec Jan May Jun CC Wall and Roof Slab Jan Jan Jun Jun CC Parapet 6 22-Jan Jan Jun Jun CC Backfill and Formation 6 29-Jan Feb Jun Jul CC Concrete Structure for Weighbridge Feb Feb Jul Jul CC ABWF Work Feb Apr Jul Aug CC Handover to E&M Works ( Zone #3.6) 0 01-Apr Aug Miscellaneous Works (Zone #4) May Dec May Apr May Oct May Mar CC Tree felling and transplanting (Excl. Natural Terrain) May Jun May Jun CC Tree felling and transplanting (Natural Terrain - if any) Jul Aug Oct Nov CC Standby Flare Nov Dec Jun Jul CC Boundary Fence May Jul Jan Mar CC Gate House Feb Apr Jul Aug CC Handover of Gate House for E&M Works 0 15-Apr Aug CC Sitewide Drainage Aug Feb Oct Apr CC Sitewide Sewage Aug Feb Dec Jun CC Sitewide Pipe Ducts, Trenches and Utilities Nov May Dec Jun CC Site Roadworks May Jul Jul Aug CC NTH Mitigation works Jul Oct Nov Mar CC Manmade Slope Stability Work Jul Oct Nov Mar Boundary Wall Mar Jul Jul Nov CC Excavation Mar Apr Jul Sep CC Footing and Wall Mar Jun Jul Oct CC Backfilling Jun Jul Oct Nov Landscaping Work Jul Dec Oct Mar CC Preparation works Jul Oct Oct Jan CC Planting works Oct Nov Jan Feb CC Landscape Softworks Nov Dec Feb Mar Roadworks at Portion Jul Dec Oct Apr CC Utitlities Diversion Jul Oct Oct Feb CC Road Construction Nov Dec Feb Apr STATUTORY AND UTILITIES WORKS Mar Oct Mar Nov Electricity Supply and Energization - CLP Mar Jul Mar Jul-16 0 CLP Transformer Room at Pre-Treatment Building Mar Jul Mar Jul Mar Jul Mar Jul-16 0 SW Handover of Electrical Building and Transformer room to BS 0 03-Mar Mar-16 0 SW Building services installation in Transformer room Mar Apr Mar Apr-16 0 SW Handover Transformer Room to CLP 0 21-Apr Apr-16 0 SW CLP to install transformers Apr Jul Apr Jul-16 0 SW Handover Associated cable duct to CLP 6 18-Mar Mar Jun Jun SW CLP to install HV cable and LV cable Mar Apr Jun Jul SW Submit WR1 to CLP and CLP inspection 6 29-Apr May Jul Jul SW CLP install energy meter and energize power 6 21-Jul Jul Jul Jul-16 0 LIft Installation - EMSD Aug Aug Aug Sep Aug Aug Aug Sep Aug Aug Aug Sep-16 8 SW Submit Form LE5 to EMSD Aug Aug Aug Aug-16 8 SW EMSD Inspection 0 18-Aug Aug-16 8 Control Room Footing Wall, Floor Slab and Stair Wall and Roof Slab Parapet Backfill and Formation Concrete Structure for Weighbridge ABWF Work Handover to E&M Works ( Zone #3.6) Tree felling and transplanting (Excl. Natural Terrain) Tree felling and transplanting (Natural Terrain - if any) Standby Flare Boundary Fence Gate House Handover of Gate House for E&M Works Sitewide Drainage Sitewide Sewage Sitewide Pipe Ducts, Trenches and Utilities Site Roadworks NTH Mitigation works Manmade Slope Stability Work Excavation Footing and Wall Backfilling Preparation works Planting works Landscape Softworks Utitlities Diversion Road Construction Handover of Electrical Building and Transformer room to BS Building services installation in Transformer room Handover Transformer Room to CLP CLP to install transformers Handover Associated cable duct to CLP CLP to install HV cable and LV cable Submit WR1 to CLP and CLP inspection CLP install energy meter and energize power Submit Form LE5 to EMSD EMSD Inspection Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 22 of 27 print: 27-Mar-15 18:32 Oracle Corporation
49 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float SW Lift Certificate (Use Permit) Obtained 0 29-Aug Sep-16 8 Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Lift Certificate (Use Permit) Obtained Fire Services - FSD Mar Oct Jul Oct Mar Oct Jul Oct Mar Oct Jul Oct-16 8 SW Re-submit Form FS Mar Jul SW FSD Acceptance Mar Apr Jul Aug Re-submit Form FS314 FSD Acceptance SW Submit Form FS Aug Aug Aug Sep-16 8 SW FS & DG Inspection 0 29-Aug Sep-16 8 SW FS & DG Re-inspection 0 12-Sep Sep-16 8 SW F.S. Approval Certificate FS251 & DG Certificate Sep Oct Sep Oct-16 8 Plumbing - WSD Jun Aug Jul Sep Jun Aug Jul Sep Jun Aug Jul Sep SW Submit WW046 Part 4 request for Inspection 0 21-Jun Jul SW WSD inspection and reinspection Jun Jul Jul Aug SW WW046 Part Jul Aug Aug Sep Telecommunication May Aug Jun Aug May Aug Jun Aug May Aug Jun Aug SW Handover plant room and cable duct to Telecom Company 5 24-May May Jun Jun SW Telecom. Company to install cable and Equipment May Aug Jun Aug Others Mar Oct Jul Nov Mar Oct Jul Nov Mar Oct Jul Nov SW Registration of Boilers & Pressure Vessels Sep Oct Nov Nov SW Approval for installation of furnaces, ovens or chimneys Jun Jul Jul Aug Submit Form FS501 FS & DG Inspection FS & DG Re-inspection F.S. Approval Certificate FS251 & DG Certificate Submit WW046 Part 4 request for Inspection WSD inspection and reinspection WW046 Part 5 Handover plant room and cable duct to Telecom Company Telecom. Company to install cable and Equipment Registration of Boilers & Pressure Vessels Approval for installation of furnaces, ovens or chimneys SW Chemical Waste Producer Registration Mar Apr Jul Aug Chemical Waste Producer Registration SW Storage Approval for Chemicals (Control of Chemicals Regulation) Jun Jun Jul Aug E & M INSTALLATION WORKS Feb Nov Mar Nov-16 0 Waste Receiving, Storage and Feeding System Feb Jul Apr Nov Feb Jul Apr Nov Feb Jul Apr Nov EM Installation of Overhead Grabbing System Apr May Apr May-16 9 EM Installation of Weighbridge System Apr May Aug Oct EM Installation of Weighbridge System May Jun Oct Nov EM Installation of Computer System Apr Jun Sep Nov EM Cable Tray Laying Works May Jun Oct Oct EM Cabling Works Jun Jul Oct Nov EM Completion of E&M Installation of Waste Receiving, Storage and Feeding System 0 05-Jul Nov EM Vehicle Washing System Feb Apr Sep Nov Pre-Treatment System Feb Aug Apr Sep Feb Aug Apr Sep Feb Aug Apr Sep EM Installation of Reception Hopper 1 and Screw Conveyors Apr May Jun Jul EM Installation of Crusher No May May Jul Aug EM Installation of Reception Hopper 2 and Screw Conveyors May May Jul Aug EM Installation of Crusher No May Jun Aug Aug EM Installation of Pumps and Mixers Jun Jul Aug Sep EM Installation of Sieve Drum no Feb Mar May Jun EM Installation of Sieve Drum no Mar Apr Jun Jul EM Installation of Sand Grit Trap No Apr Apr Jul Aug EM Installation of Sand Grit Trap No Apr May Aug Aug EM Installation of Heavy/ Light Fraction Screw No May May Aug Aug EM Installation of Heavy/ Light Fraction Screw No May Jun Sep Sep Storage Approval for Chemicals (Control of Chemicals Regulation) Installation of Overhead Grabbing System Installation of Weighbridge System 1 Installation of Weighbridge System 2 Installation of Computer System Cable Tray Laying Works Cabling Works Completion of E&M Installation of Waste Receiving, Storage and Feeding S Vehicle Washing System Installation of Reception Hopper 1 and Screw Conveyors Installation of Crusher No 1 Installation of Reception Hopper 2 and Screw Conveyors Installation of Crusher No 2 Installation of Pumps and Mixers Installation of Sieve Drum no 1 Installation of Sieve Drum no 2 Installation of Sand Grit Trap No 1 Installation of Sand Grit Trap No 2 Installation of Heavy/ Light Fraction Screw No 1 Installation of Heavy/ Light Fraction Screw No 2 Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 23 of 27 print: 27-Mar-15 18:32 Oracle Corporation
50 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float EM Installation of Overhead Travelling Crane Apr May May May Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Installation of Overhead Travelling Crane EM Installation of Suspension buffer tank Feb Mar Aug Sep EM Cable Tray Laying Work Feb Mar Apr May EM Cabling Works Mar May May Jul EM10090B Associated Building Service Works May Jun Jul Aug EM10095B Remaining Cabling and Building Services Works on 1/F May Aug May Aug-16 9 EM Completion of E&M Installation of Pre-Treatment System 0 15-Aug Sep Installation of Switchboard Apr Jun Apr Jun Apr Jun Apr Jun-16 0 EM Installation of Swithboard at Pre-treatment Swichboard room Apr Jun Apr Jun-16 0 Anaerobic Digestion Treatment System Mar Sep Mar Sep Mar Sep Mar Sep Mar Sep Mar Sep-16 0 EM Installation of Digester Tank No.1 with Jet Mix ing System Mar Jul Mar Jul-16 0 EM Installation of Digester Tank No.2 with Jet Mix ing System Apr Jul Apr Jul-16 0 EM Installation of Digester Tank No.3 with Jet Mix ing System Apr Aug Apr Aug-16 0 EM Installation of Link Bridge for Digester Tanks Aug Sep Aug Sep-16 0 EM Installation of pumping system Aug Aug Aug Aug-16 5 EM Installation of Odour Extraction Ductworks Jul Sep Jul Sep-16 0 EM Installation of Intermediate Digestate Tank Aug Sep Aug Sep-16 5 EM Completion of E&M Installation of Anaerobic Digestion Treatment System 0 12-Sep Sep-16 0 Installation of Switchboard Mar May Jul Sep Mar May Jul Sep EM Installation of Swithboard at Swichboard room no Mar May Jul Sep Heat Recovery and Power Generation System Jul Nov Jul Nov Jul Nov Jul Nov Jul Nov Jul Nov-16 0 EM Installation of Combine Heat Power System no Jul Aug Jul Aug-16 0 EM Installation of Combine Heat Power System no Aug Oct Aug Oct-16 7 EM Installation of Combine Heat Power System no Oct Nov Oct Nov-16 7 EM Installation of Heat Recovery system Aug Sep Aug Sep-16 0 EM Installation of Electric Boiler Aug Oct Aug Oct-16 0 EM Installation of Continuous Emissions Monitoring System (CEMS) Nov Nov Nov Nov-16 0 EM Cable Tray Laying Works Nov Nov Nov Nov-16 0 EM Cabling Works Oct Nov Oct Nov-16 0 EM Completion of E&M Installation of Heat Recovery and Power Generation System 0 30-Nov Nov-16 0 Biogas Cleaning and Storage System Jul Nov Jul Nov Jul Nov Jul Nov Jul Nov Jul Nov EM Installation of Bio Gas Cleaning System no Jul Aug Jul Aug EM Installation of Bio Gas Cleaning System no Aug Aug Aug Sep EM Installation of Bio Gas Cleaning Storage Tank Sep Oct Oct Nov EM Installation of Desulphirsation Sep Sep Oct Oct EM Associated Bio gas Conveying Duct Works Sep Oct Oct Nov EM Cable Tray Laying Works Sep Oct Sep Nov EM Cabling Works Oct Nov Nov Nov EM Completion of E&M Installation of Biogas Cleaning and Storage System 0 08-Nov Nov Biogas Distribution System Jul Sep Jul Nov Jul Sep Jul Nov Jul Sep Jul Nov EM Installation of Standby Flaring Gas Unit Jul Jul Jul Aug EM Installation of Biogas Blowers Jul Jul Sep Sep EM Installation of Biogas Cooling and Condensate Removal System Jul Jul Sep Sep Installation of Suspension buffer tank Cable Tray Laying Work Cabling Works Associated Building Service Works Remaining Cabling and Building Services Works on 1/F Completion of E&M Installation of Pre-Treatment System Installation of Swithboard at Pre-treatment Swichboard room Installation of Digester Tank No.1 with Jet Mix ing System Installation of Digester Tank No.2 with Jet Mix ing System Installation of Digester Tank No.3 with Jet Mix ing System Installation of Link Bridge for Digester Tanks Installation of pumping system Installation of Odour Extraction Ductworks Installation of Intermediate Digestate Tank Completion of E&M Installation of Anaerobic Digestion Tre Installation of Swithboard at Swichboard room no 2 Installation of Combine Heat Power System no 1 Installation of Combine Heat Power System no 2 Installation of Combine Heat Power Sys Installation of Heat Recovery system Installation of Electric Boiler Installation of Continuous Emissions M Cable Tray Laying Works Cabling Works Completion of E&M Installation of Hea Installation of Bio Gas Cleaning System no.1 Installation of Bio Gas Cleaning System no.2 Installation of Bio Gas Cleaning Storage Tank Installation of Desulphirsation Associated Bio gas Conveying Duct Works Cable Tray Laying Works Cabling Works Completion of E&M Installation of Biogas C Installation of Standby Flaring Gas Unit Installation of Biogas Blowers Installation of Biogas Cooling and Condensate Removal System Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 24 of 27 print: 27-Mar-15 18:32 Oracle Corporation
51 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float EM Cable Tray Laying Works Jul Sep Sep Nov Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Cable Tray Laying Works EM Cabling Works Sep Sep Nov Nov EM Completion of E&M Installation of Biogas Disgtribution System 0 27-Sep Nov Wastewater Treatment System Feb Jun Apr Aug Feb Jun Apr Aug Feb Jun Apr Aug EM Installation of Pumping System and associated pipework Feb Apr Apr Jun EM Installation of Aeration Pipework Apr May Jun Jul EM Installation of Odour Containment System May Jun Jul Aug EM Installation of Odour Extraction Ductwork May Jun Jul Aug EM Installation of ASP Apr Jun Jun Aug EM Cable Tray Laying Works Apr May Jun Jul EM Cabling Works May Jun Jul Aug EM Completion of E&M Installation of Wastewater Treatment System 0 20-Jun Aug Composting System May Nov May Nov-16 6 Installation of Tunnel Composting 1 to May Oct May Oct May Oct May Oct-16 6 EM Installation Air Extraction Ductwork May Aug May Aug-16 6 EM Installation of Water Spraying System Aug Oct Aug Oct-16 6 Installation of Leachate Treatment System Oct Nov Oct Nov Oct Nov Oct Nov-16 6 EM Installation of Leachate Treatment System Oct Nov Oct Nov-16 6 Installation of Maturation Area May Sep Oct Nov May Sep Oct Nov EM Installation Air Extraction System Aug Sep Oct Nov EM Installation of Sieve 9 12-Sep Sep Nov Nov EM Installation of Bagging Facilities 6 23-Sep Sep Nov Nov EM Installation of Mobile Mixer 2 24-May May Oct Oct EM Cable Tray Laying Works 9 26-May Jun Oct Nov EM Cabling Works Jun Jun Nov Nov Installation of Structurant Storage Area May Jul Jul Sep May Jul Jul Sep EM Installation Air Extraction System May Jun Jul Aug EM Installation of Structurant Storage System May Jun Aug Aug EM Cable Tray Laying Works Jun Jul Aug Aug EM Cabling Works Jul Jul Aug Sep Installation of Digestate Dewatering System Jul Sep Sep Nov Jul Sep Sep Nov EM Installation of Centrifuges 9 16-Jul Jul Sep Sep EM Instllation of Sludge Pumping system 9 27-Jul Aug Oct Nov EM Installation of Screw Conveyors System 9 06-Aug Aug Nov Nov EM Installation of Dewatering Storage Tank 4 17-Aug Aug Nov Nov EM Installtion of Strirer 2 22-Aug Aug Nov Nov EM Cable Tray Laying Work Jul Sep Sep Nov EM Cabling Works Aug Sep Sep Nov Composting System May Nov Sep Nov May Nov Sep Nov-16 6 EM Completion of E&M Installation of Composting System 0 12-Nov Nov-16 6 EM Installaton Electrical Switchboard Room no May Jul Sep Nov Centralized Air Pollution Control System Apr Aug Jun Nov Apr Aug Jun Nov Apr Aug Jun Nov EM Installation of Chemical Scrubber Apr May Jun Jul EM Installation of Dosing Pumps and associated pipeworks Apr May Jun Jul EM Installation of Activated Carbon Filter May Jun Oct Nov Cabling Works Completion of E&M Installation of Biogas Disgtribution Installation of Pumping System and associated pipework Installation of Aeration Pipework Installation of Odour Containment System Installation of Odour Extraction Ductwork Installation of ASP Cable Tray Laying Works Cabling Works Completion of E&M Installation of Wastewater Treatment System Installation Air Extraction Ductwork Installation of Water Spraying System Installation of Leachate Treatment System Installation Air Extraction System Installation of Sieve Installation of Bagging Facilities Installation of Mobile Mixer Cable Tray Laying Works Cabling Works Installation Air Extraction System Installation of Structurant Storage System Cable Tray Laying Works Cabling Works Installation of Centrifuges Instllation of Sludge Pumping system Installation of Screw Conveyors System Installation of Dewatering Storage Tank Installtion of Strirer Cable Tray Laying Work Cabling Works Completion of E&M Installation of Compos Installaton Electrical Switchboard Room no 4 Installation of Chemical Scrubber Installation of Dosing Pumps and associated pipeworks Installation of Activated Carbon Filter Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 25 of 27 print: 27-Mar-15 18:32 Oracle Corporation
52 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float EM Installation of Odour Extraction Duct Work May Aug Jul Oct Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Installation of Odour Extraction Duct Work EM Installation of Chemical Storage Tanks May Jun Jul Aug EM Cable Tray Laying Works May Jun Aug Oct EM Cabling Works Jun Jul Oct Nov EM Completion of E&M Installation of Centralized Air Pollution Control System 0 25-Aug Nov EM Installation of Swithboard at CAPCS Swichboard room Jun Jul Jun Jul-16 0 Administration Offices & Visitor Areas Feb Aug May Aug Feb Aug May Aug Feb Aug May Aug EM17010B Building Service Installation of Adminstration Offices Apr Jun May Jul EM17012B Lift Installation of Adminstration Offices May Aug Jun Aug EM Visitor and Educational Centre Jun Jul Jul Aug EM17020B Completion of E&M Installation of Administration Offices & Visitor Areas 0 01-Aug Aug EM Installation of Electrical Switchboard Room no Feb Mar Jun Jul General Apr Sep Apr Oct Apr Sep Apr Oct Apr Sep Apr Oct EM Insturmentation, Control & Monitoring System (SCADA/PLC) Apr Aug May Sep EM19020B Building Services and Management System (Building #1) Apr Sep Apr Sep-16 0 Installation of Chemical Storage Tanks Cable Tray Laying Works Cabling Works Completion of E&M Installation of Centralized Air Pollution Cont Installation of Swithboard at CAPCS Swichboard room Building Service Installation of Adminstration Offices Lift Installation of Adminstration Offices Visitor and Educational Centre Completion of E&M Installation of Administration Offices & Visitor Are Installation of Electrical Switchboard Room no 3 Insturmentation, Control & Monitoring System (SCADA/PLC) Building Services and Management System (Building #1) EM19021B Switchboard and MCC Installation (Building #1) Apr Aug Apr Aug-16 0 EM19022B Cables and Accessories, Cable Containment System Installation (Building #1) Apr Sep Apr Sep EM19023B Earthing and Lightning System Installation (Building #1) Apr Aug May Sep EM19024B Emergency Genset Installation (Building #1) Jul Aug Jul Aug EM19025B Equipment at Gate House Apr Apr Sep Sep EM19030B ELV System Installation (Building #3) Jun Aug Jul Sep EM19050B Platform & Handrails (FRP) Aug Sep Aug Oct Energisation of Switchboards 1 28-Jul Jul Jul Nov Jul Jul Jul Nov Jul Jul Jul Nov EN Energisation of Switchboard (Main LV Switchroom) 1 28-Jul Jul Jul Jul-16 0 EN Energisation of Switchboard (For Anaerobic Digestion System and Dewatering System) 1 28-Jul Jul Sep Sep EN Energisation of Switchboard (For Adminstration Building) 1 28-Jul Jul Jul Jul-16 0 EN Energisation of Switchboard (For Composting System) 1 28-Jul Jul Nov Nov EN Energisation of Switchboard (For Pre-Traetment System) 1 28-Jul Jul Jul Jul-16 0 EN Energisation of Switchboard (For Centralized Air Pollution System) 1 28-Jul Jul Jul Jul-16 0 TESTING AND COMMISSIONING Jul Mar Aug Mar-17 0 Site Testing (including hydraulic testing & pipe pressure testing) Jul Jan Aug Jan Jul Jan Aug Jan Jul Jan Aug Jan-17 6 TC Site Testing of Pretreatment System Sep Oct Sep Oct-16 0 TC Site Testing of Anaerobic Digestion Treatment System Sep Oct Sep Oct-16 0 TC Site Testing of Heat Recovery and Power Generation System Dec Jan Dec Jan-17 0 TC Site Testing of Biogas Cleaning and Storage System Nov Dec Dec Jan TC Site Testing of WWTS Jul Sep Aug Oct TC Site Testing of CAPCS Aug Oct Nov Jan TC Site Testing of Composting System Nov Jan Nov Jan-17 6 TC Site Testing of Weighbridge System & Vehicle Wash System Jul Sep Nov Jan System Commissioning (24 hours) Oct Jan Oct Jan Oct Jan Oct Jan Oct Jan Oct Jan-17 0 TC Pre-Treatment Building & Facilities 1 20-Oct Oct Oct Oct-16 0 TC Biogas Cleaning and Storage System 1 24-Oct Oct Jan Jan Switchboard and MCC Installation (Building #1) Cables and Accessories, Cable Containment System Installa Earthing and Lightning System Installation (Building #1) Emergency Genset Installation (Building #1) Equipment at Gate House ELV System Installation (Building #3) Platform & Handrails (FRP) Energisation of Switchboard (Main LV Switchroom) Energisation of Switchboard (For Anaerobic Digestion System and De Energisation of Switchboard (For Adminstration Building) Energisation of Switchboard (For Composting System) Energisation of Switchboard (For Pre-Traetment System) Energisation of Switchboard (For Centralized Air Pollution System) Site Testing of Pretreatment System Site Testing of Anaerobic Digestion Treatment S Site Testing of Heat Recove Site Testing of Biogas Cleaning an Site Testing of WWTS Site Testing of CAPCS Site Testing of Composting S Site Testing of Weighbridge System & Vehicle Wash Syste Pre-Treatment Building & Facilities Biogas Cleaning and Storage System Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 26 of 27 print: 27-Mar-15 18:32 Oracle Corporation
53 Environmental Protection Department of the HKSAR Activity ID Activity Name Original Duration Contract No. EP/SP/61/10 Organic Waste Treatment Facilities, Phase 1 Early Start Early Finish Late Start Late Finish Total Float TC Wastewater Treatment System 1 11-Jan Jan Jan Jan-17 0 Contract Programme v1.2 OSCAR BIOENERGY JV Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Wastewater Treatment Sy TC Centralized Air Pollution Control System 1 12-Jan Jan Jan Jan-17 0 TC Vehicle Washing System 1 18-Jan Jan Jan Jan-17 0 TC Master Control System - SCADA/PLC System 1 19-Jan Jan Jan Jan-17 0 Anaerobic Digestion Treatment System 3 21-Oct Oct Oct Jan Oct Oct Oct Jan TC Anaerobic Digester no Oct Oct Oct Oct-16 0 TC Anaerobic Digester no Oct Oct Jan Jan TC Anaerobic Digester no Oct Oct Jan Jan Heat Recovery and Power Generation System 3 08-Jan Jan Jan Jan Jan Jan Jan Jan-17 0 TC Combine Heat Power System no Jan Jan Jan Jan-17 0 TC Combine Heat Power System no Jan Jan Jan Jan-17 0 TC Combine Heat Power System no Jan Jan Jan Jan-17 0 Composting System 3 13-Jan Jan Jan Jan Jan Jan Jan Jan-17 0 TC Tunnel Composting nos Jan Jan Jan Jan-17 0 TC Tunnel Composting nos Jan Jan Jan Jan-17 0 TC Maturation Area Facilities 1 15-Jan Jan Jan Jan-17 0 Weighbridge System 2 16-Jan Jan Jan Jan Jan Jan Jan Jan-17 0 TC Weighbridge System No Jan Jan Jan Jan-17 0 TC Weighbridge System No Jan Jan Jan Jan-17 0 Process Startup, Process Commissioning & Plant Commissioing Oct Mar Oct Mar-17 0 Process Start up Oct Jan Oct Jan Oct Jan Oct Jan-17 0 PS N2 Purging of Anaerobic Digester No Oct Oct Oct Oct-16 0 PS Inoculate Anaerobic Digester No.1 (Seeding) Oct Nov Oct Nov-16 0 PS N2 Purging of Anaerobic Digester No Nov Nov Nov Dec PS N2 Purging of Anaerobic Digester No Nov Nov Dec Dec PS Start up test with Anaerobic Digester No Nov Dec Nov Dec-16 0 PS Biogas Production from Anaerobic Digester No Dec Dec Dec Dec-16 0 PS Start-Up of Gas System (Including Desulphurisation System) 7 19-Dec Dec Jan Jan PS Dewatering Test and Start-Up of Dewatering System Dec Jan Jan Jan PS Start-Up of Composting System Dec Jan Jan Jan PS Transfering 50% Digester from Anaerobic Digester No.1 to No Dec Dec Dec Dec-16 0 PS Start up test with Anaerobic Digester No Dec Jan Dec Jan-17 0 PS Biogas Production from Anaerobic Digester No Jan Jan Jan Jan-17 0 PS Transfering 50% Digester from Anaerobic Digester No.2 to No Jan Jan Jan Jan-17 0 PS Start up test with Anaerobic Digester No Dec Jan Dec Jan-17 0 PS Biogas Production from Anaerobic Digester No Jan Jan Jan Jan-17 0 Process Commissioning Jan Feb Jan Feb Jan Feb Jan Feb-17 0 PS Process Commissioning with Anaerobic Digester No 1&2 ( Assume 2 no Anaerobic digesters ) Jan Feb Jan Feb-17 0 Plant Commissioning Feb Mar Feb Mar Feb Mar Feb Mar-17 0 PS Plant Commissioning with Anaerobic Digesters ( Assume 2 no Anaerobic digesters ) Feb Mar Feb Mar-17 0 COMPLETION OF THE WORKS 1 16-Mar Mar Mar Mar Mar Mar Mar Mar Mar Mar Mar Mar Mar Mar Mar Mar-17 0 KD COMPLETION OF THE DESIGN AND THE WORKS INCLUDING TESTING AND COMMISSIONING 0 16-Mar Mar-17 0 KD COMMENCEMENT OF THE OPERATION 0 17-Mar Mar-17 0 Centralized Air Pollution Co Vehicle Washing System Master Control System - Anaerobic Digester no 1 Anaerobic Digester no 2 Anaerobic Digester no 3 Combine Heat Power Syste Combine Heat Power Syste Combine Heat Power Syst Tunnel Composting nos 1 Tunnel Composting nos 4 Maturation Area Facilities Weighbridge System No Weighbridge System No N2 Purging of Anaerobic Digester No 1 Inoculate Anaerobic Digester No.1 (Seedin N2 Purging of Anaerobic Digester No 2 N2 Purging of Anaerobic Digester No 3 Start up test with Anaerobic Digest Biogas Production from Anaerob Start-Up of Gas System (Includ Dewatering Test and Start-U Start-Up of Composting Syst Transfering 50% Digester from A Start up test with Anaero Biogas Production from A Transfering 50% Digeste Start up test with Anaero Biogas Production from A Process Commis Plant Com COMPLE COMMEN Project:OWTF1_v1.2Final Ref.:WS-OSC-00-0-TM-0001-B, Date: 27-Mar-2015 Activity Milestone Critical Page 27 of 27 print: 27-Mar-15 18:32 Oracle Corporation
54 Annex D Project Organization Chart with Contact Details
55 Project Organization During Construction Phase (with contact details) Project Proponent EPD Mr Derek Lui Tel: Supervising Officer s Representative AECOM Tim Lee Tel: Independent Environment Checker Meinhardt Infrastructure and Environment Ltd Ms Helen Cochrane Tel: Contractor OSCAR Bioenergy Joint Venture EPD Hotline Number OSCAR Bioenergy Joint Venture Tel: Mr Marshall Tsoi Tel: Tel: Environmental Team Leader ERM Hong Kong Ltd Ms Winnie Ko Tel: Project Management Responsibility Communication ENVIRONMENTAL RESOURCES MANAGEMENT OSCAR BIOENERGY JOINT-VENTURE D1
56 Annex E Implementation Schedule of Mitigation Measures
57 Annex E Summary of Mitigation Measures Implementation Schedule EIA Ref. EM&A Log Ref. Environmental Protection Measures Location/ Timing Status Summary of Environmental Mitigation Measures in the EIA and EM&A Manual A. Air Quality Air Pollution Control (Construction Dust) Regulation & Good Site Practices Use of regular watering, with complete coverage, to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather. Use of frequent watering for particularly dusty construction areas and areas close to ASRs. Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to frequent usage, watering should be applied to aggregate fines. Open stockpiles should be avoided or covered. Where possible, prevent placing dusty material storage piles near ASRs. Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations. Establishment and use of vehicle wheel and body washing facilities at the exit points of the site. Provision of wind shield and dust extraction units or similar dust mitigation measures at the loading points, and use of water sprinklers at the loading area where dust generation is likely during the loading process of loose material, particularly in dry seasons/ periods. Imposition of speed controls for vehicles on unpaved site roads. 8 kilometers per hour is the recommended limit. Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs. Every stock of more than 20 bags of cement or dry pulverised fuel ash (PFA) should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides. Cement or dry PFA delivered in bulk should be stored in a closed silo fitted with an audible high level alarm which is interlocked with the material filling line and no overfilling is allowed. Loading, unloading, transfer, handling or storage of bulk cement or dry PFA should be carried out in a totally enclosed system or facility, and any vent or exhaust should be fitted with an effective fabric filter or equivalent air pollution control system. Construction Site / During Construction Period <> B. Hazard to Life Construction Phase Construction Site / During N/A ENVIRONMENTAL RESOURCES MANAGEMENT E-1 OSCAR BIOENERGY JOINT-VENTURE
58 EIA Ref. EM&A Log Ref. Environmental Protection Measures Location/ Timing Status The number of workers on site during construction stage should be kept at the same level as the assessment. Construction works should be suspended when delivery of chlorine takes place. 3m high fence should be constructed along the boundary facing the SHWWTW. Emergency evacuation procedures should be formulated and the Contractor should ensure all workers on site should be familiar with these procedures as well as the route to escape in case of gas release incident. Relevant Departments, such as Fire Services Department (FSD), should be consulted during the development of Emergency procedures. Diagram showing the escape routes to a safe place should be posted in the site notice boards and at the entrance/exit of site. A copy of the latest version emergency procedures should be dispatched to Tung Chung Fire Station for reference once available. The emergency procedures should specify means of providing a rapid and direct warning (e.g. Siren and Flashing Light) to construction workers in the event of chlorine gas release in the SHWWTW. The Contractor should establish a communication channel with the SHWWTW operation personnel and FSD during construction stage. In case of any hazardous incidents in the treatment works, operation personnel of SHWWTW should advise the Contractor to inform construction workers to proceed with emergency procedure. The Contractor should appoint a Liaison Officer to communicate with FSD Incident Commander on site in case of emergency. Introduction training should be provided to any staff before carryout construction works at the Project site. Periodic drills should be coordinated and conducted to ensure all construction personnel are familiar with the emergency procedures. Upon completion of the drills, a review on every step taken should be conducted to identify area of improvement. Prior notice of periodic drills should be given to Station Commander of Tung Chung Fire Station. Joint operational exercise with FSD and SHWWTW is recommended. Construction Period C. Water Quality Construction site run-off and general construction activities: The mitigation measures as outlined in the ProPECC PN 1/94 Construction Site Drainage should be adopted where applicable. Construction Site / During Construction Period <> Excavation of Soil Materials The construction programme should be properly planned to minimise soil excavation, if any, in rainy seasons. This prevents soil erosion from exposed soil surfaces. Any exposed soil surfaces should also be properly protected to minimise dust emission. In areas where a large amount of exposed soils exist, earth bunds or sand bags should be provided. Exposed Construction Site / During Construction Period <> ENVIRONMENTAL RESOURCES MANAGEMENT E-2 OSCAR BIOENERGY JOINT-VENTURE
59 EIA Ref. EM&A Log Ref. Environmental Protection Measures Location/ Timing Status stockpiles should be covered with tarpaulin or impervious sheets at all times. The stockpiles of materials should be placed at locations away from any stream courses so as to avoid releasing materials into the water bodies. Final surfaces of earthworks should be compacted and protected by permanent work Accidental spillage of chemicals: Contractor must register as a chemical waste producer if chemical wastes would be produced from the construction activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and complied with for control of chemical wastes. Construction Site / During Construction Period Maintenance of vehicles and equipments involving activities with potential for leakage and spillage should only be undertaken within the areas which appropriately equipped to control these discharges. Construction Site / During Construction Period Oils and fuels should only be used and stored in designated areas which have pollution prevention facilities. All fuel tanks and storage areas should be sited on sealed areas in order to prevent spillage of fuels and solvents to the nearby watercourses. All waste oils and fuels should be collected in designated tanks prior to disposal. Construction Site / During Construction Period <> Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows: Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport. Chemical waste containers should be suitably labeled, to notify and warn the personnel who are handling the wastes, to avoid accidents. Storage area should be selected at a safe location on site and adequate space should be allocated to the storage area. Construction Site / During Construction Period 5.50 Construction solid waste, debris and rubbish on site should be collected, handled and disposed of properly to avoid entering to the nearby watercourses. Stockpiles of cement and other construction materials should be kept covered when not being used. Rubbish and litter from construction sites should also be collected to prevent spreading of rubbish and litter from the site area. It is recommended to clean the construction sites on a regular basis. Construction Site / During Construction Period <> ENVIRONMENTAL RESOURCES MANAGEMENT E-3 OSCAR BIOENERGY JOINT-VENTURE
60 EIA Ref. EM&A Log Ref. Environmental Protection Measures Location/ Timing Status Sewage Effluent The presence of construction workers generates sewage. It is recommended to provide sufficient chemical toilets in the works areas. The toilet facilities should be more than 30m from any watercourse. A licensed waste collector should be deployed to clean the chemical toilets on a regular basis. Work site/during the construction period N/A Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment during the construction phase of the project. Regular environmental audit on the construction site can provide an effective control of any malpractices and can achieve continual improvement of environmental performance on site. Work Site / During Construction Period Nullah Decking To minimize the potential water quality impacts from the nullah reconstruction works, the practices outlined below should be adopted where applicable: The proposed works should be carried out within the dry season between October and March when the flow in the open nullah is low. The use of less or smaller construction plants may be specified to reduce the disturbance to the nullah bed. Temporary storage of materials (e.g. equipment, filling materials, chemicals and fuel) and temporary stockpile of construction materials should be located well away from the nullah and any water courses during carrying out of the construction works. Stockpiling of construction materials and dusty materials should be covered and located away from the nullah any water courses. Construction debris and spoil should be covered up and/or disposed of as soon as possible to avoid being washed into the nullah and nearby water receivers. Construction activities, which generate large amount of wastewater, should be carried out in a distance away from the nullah, where practicable. Construction effluent, site run-off and sewage should be properly collected and/or treated. Any works site inside the nullah should be temporarily isolated, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props to prevent adverse impact on the water quality. Proper shoring may need to be erected in order to prevent soil/mud from slipping into the nullah and nearby watercourse. Supervisory staff should be assigned to station Work Site / During Construction Period D. Waste Management ENVIRONMENTAL RESOURCES MANAGEMENT E-4 OSCAR BIOENERGY JOINT-VENTURE
61 EIA Ref. EM&A Log Ref. Environmental Protection Measures Location/ Timing Status Good Site Practices Recommendations for good site practices during the construction phase would include: Obtain relevant waste disposal permits from appropriate authorities, in accordance with the Waste Disposal Ordinance (Cap. 354) and subsidiary Regulations and the Land (Miscellaneous Provisions) Ordinance (Cap. 28); Provide staff training for proper waste management and chemical handling procedures; Provide sufficient waste disposal points and regular waste collection; Provide appropriate measures to minimize windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers; Carry out regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors; Separate chemical wastes for special handling and disposed of to licensed facility for treatment; and Employ licensed waste collector to collect waste. Work Site / During Construction Period <> Waste Reduction Measures Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices. Recommendations to achieve waste reduction include: Design foundation works that could minimise the amount of excavated material to be generated; Provide training to workers on the importance of site cleanliness and appropriate waste management procedures, including waste reduction, reuse and recycling; Sort out demolition debris and excavated materials from demolition works to recover reusable/ recyclable portions (i.e. soil, broken concrete, metal etc.); Segregate and store different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal; Encourage the collection of aluminium cans by providing separate labelled bins to enable this waste to be segregated from other general refuse generated by the workforce; and Plan and stock construction materials carefully to minimize the amount of waste to be generated and to avoid unnecessary generation of waste. Work Site/During Design & Construction Period Excavated and C&D Materials In order to minimise the impact resulting from collection and transportation of C&D material for off-site disposal, the excavated material arising from site formation and foundation works should be reused on-site as backfilling material and for landscaping works as far as practicable. Other mitigation requirements are listed below: A WMP, which becomes part of the Environmental Management Plan (EMP), should be Work Site/During Design & Construction Period ENVIRONMENTAL RESOURCES MANAGEMENT E-5 OSCAR BIOENERGY JOINT-VENTURE
62 EIA Ref. EM&A Log Ref. Environmental Protection Measures Location/ Timing Status prepared in accordance with ETWB TCW No.19/2005; A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites) should be adopted for easy tracking; and In order to monitor the disposal of excavated and C&D material at public filling facilities and landfills and to control fly-tipping, a trip-ticket system should be adopted (refer to ETWB TCW No. 31/2004) An EMP should be prepared and implemented in accordance with ETWB TCW No. 19/2005 which describes the arrangements for avoidance, reuse, recovery, recycling, storage, collection, treatment and disposal of different categories of waste to be generated from construction activities. The EMP should be submitted to the Supervising Officer (SO) and Supervising Officer s Representative (SOR) for approval. The EMP should be reviewed regularly and updated, preferably on a monthly basis. A system should be devised to work for on-site sorting of excavated and C&D materials and promptly removing all sorted and process materials arising from the construction activities to minimize temporary stockpiling on-site. The system should be included in the EMP identifying the source of generation, estimated quantity, arrangement for on-site sorting, collection, temporary storage areas and frequency of collection by recycling Contractors or frequency of removal off-site Chemical Waste Should chemical wastes be produced at the construction site, the Contractor would be required to register with EPD as a Chemical Waste Producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste (such as explosive, flammable, oxidizing, irritant, toxic, harmful, or corrosive). The Contractor should employ a licensed collector to transport and dispose of the chemical wastes, to either the CWTC in Tsing Yi, or any other licensed facilities, in accordance with the Waste Disposal (Chemical Waste) General) Regulation General Refuse General refuse should be stored in enclosed bins or compaction units separated from C&D material. A licensed waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material. Preferably an enclosed and covered area should be provided to reduce the occurrence of 'wind blown' light material. Work Site/During Design & Construction Period Work Site / During Construction Period Work Site / During Construction Period <> E. Landscape and Visual ENVIRONMENTAL RESOURCES MANAGEMENT E-6 OSCAR BIOENERGY JOINT-VENTURE
63 EIA Ref & Table 7.7 EM&A Log Ref. Table 6.1 Environmental Protection Measures Location/ Timing Status Construction Phase Topsoil, where identified, should be stripped and stored for re-use in the construction of the soft landscape works, where practical Compensatory tree planting should be provided to compensate for felled trees. - Compensation tree species shall be chosen from both indigenous and ornamental species - Compensatory tree planting quantities shall be as per DLO approved requirement. Control of night-time lighting Erection of decorative screen hoarding compatible with the surrounding setting Work site/during Design & Construction Stages <> F. Noise Good Site Practice: Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program; Mobile plant, if any, should be sited as far from noise sensitive receivers (NSRs) as possible; Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum; Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs; and Material stockpiles and other structures should be effectively utilized, wherever practicable, in screening noise from on-site construction activities. Work site/during Design & Construction Stages Remark: Compliance of Mitigation Measures <> Compliance of Mitigation but need improvement x Non-compliance of Mitigation Measures Non-compliance of Mitigation Measures but rectified by OSCAR Bioenergy JV Deficiency of Mitigation Measures but rectified by OSCAR Bioenergy JV N/A Not Applicable in Reporting Period ENVIRONMENTAL RESOURCES MANAGEMENT E-7 OSCAR BIOENERGY JOINT-VENTURE
64 Annex F Waste Flow Table
65 No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I Monthly Summary Waste Flow Table Actual Quantities of Inert C&D Materials Generated (see Note 13) Actual Quantities of Non-inert C&D Materials (Construction Waste) Generated (see Note 13) Month Total Quantity Generated Reused in the Contract Reused in other Projects Hard Rocks & Large Broken Concrete Disposed as Public Fill Metals (see Note 1) Paper/ cardboard packaging (see Note 1) Plastics (see Note 2) Chemical Waste Others, e.g. general refuse (see Note 3) tonne tonne tonne tonne tonne kilogram kilogram kilogram Litre tonne May June Total Notes: (1) Metal and paper/cardboard packaging were collected by recycler for recycling. (2) Plastics refer to plastic bottles/containers, plastic sheets/foam from packaging material collected by recycler for recycling. (3) General refuse was disposed of at NENT by subcontractors. 1
66 Annex G Environmental Complaint, Environmental Summons and Persecution Log
67 Annex G Cumulative Complaint and Summons/Prosecutions Log Reporting Month Number of Complaints in Reporting Month Number of Summons/Prosecutions in Reporting Month May June Overall Total 0 0 ENVIRONMENTAL RESOURCES MANAGEMENT G1 OSCAR BIOENERGY JOINT-VENTURE
Development of Organic Waste Treatment Facilities, Phase 2
ENVIRONMENTAL PROTECTION DEPARTMENT Development of Organic Waste Treatment Facilities, Phase 2 Project Profile April 2011 CONTENTS 1 PURPOSE OF PROJECT PROFILE... 3 2 BASIC INFORMATION... 3 2.1 Project
ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE
For discussion on 8 April 2014 PWSC(2014-15)1 ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE HEAD 705 CIVIL ENGINEERING Environmental Protection Refuse Disposal 172DR Organic waste treatment facilities
Construction and Demolition Waste
Re-issued under new categorization in August 2009 as Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers ADV-19 Buildings Department Practice Note
Environmental Site Inspection Checklist
Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated
Environmental Impact Assessment Ordinance (Cap. 499) Environmental Impact Assessment Report Sludge Treatment Facilities
40/F, Revenue Tower, 5 Gloucester Road, Wan Chai, Hong Kong 香 港 灣 仔 告 士 打 道 5 號 稅 務 大 樓 40 樓 ACE-EIA Paper 2/2009 For advice Environmental Impact Assessment Ordinance (Cap. 499) Environmental Impact Assessment
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
Contract No. CV / 2007 / 06 Kwai Chung Incineration Plant Demolition and Decontamination Works Site Management Plan for TRIP TICKET SYSTEM
Site Management Plan for TRIP TICKET SYSTEM (Version 1.3) CONTENT Item Description(s) Page No. 1. Introduction 2-3 2. Disposal of C & D Materials to Designated Disposal Ground 4 3. Site Management Plan
Introduction to Waste Treatment Technologies. Contents. Household waste
Contents Introduction to waste treatment technologies 3 Section 1: The treatment of recyclable waste 4 Bulking facilities 5 Materials Reclamation Facility (MRF) 6 Reuse and recycling centres 8 Composting
MONTHLY ENVIRONMENTAL MONITORING AND AUDIT REPORT NO. 38
THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION TERRITORY DEVELOPMENT DEPARTMENT HK ISLAND & ISLANDS DEVELOPMENT OFFICE Agreement No. CE 7/99 Design and Construction MONTHLY ENVIRONMENTAL
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING
SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING 1 TABLE OF CONTENTS 1.0 Introduction and Purpose 3 2.0 Description of Work 3 3.0 Site Supervisor/Foremen Responsibilities 4 4.0 Equipment
Waste management in Hong Kong/business opportunities
Waste management in Hong Kong/business opportunities Author: Netherlands Consulate General in HK Introduction Waste and waste management create a number of challenges for the Hong Kong (HK) government.
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention
Bills Committee on Waste Disposal (Amendment)(No.2) Bill 2003. List of follow-up actions arising from the discussion at the meeting on 13 May 2004
CB(1) 1882/03-04(02) Bills Committee on Waste Disposal (Amendment)(No.2) Bill 2003 List of follow-up actions arising from the discussion at the meeting on 13 May 2004 Follow up actions (1) To include in
Temporary Batch Plants
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
Concrete Waste Management
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
Analysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
Activity Yes No N/A Notes
CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3
Buildings Departmen t Lands Department Planning Department
Buildings Departmen t Lands Department Planning Department Joint Practice Note No. 3 Re-engineering of Approval Process for Land and Building Developments Introduction The processing of a building development
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
Appendix I: BMP Inspection Form CASQA SWPPP Template 91 January2011 BMP INSPECTION REPORT Date and Time of Inspection: Date Report Written: Inspection Type: (Circle one) Weekly Complete Parts I,II,III
Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills.
WQ-10 Best Management Practice (BMP) Water Quality Protection Guideline Secondary Containment Design Standards Fuel Storage on Construction Sites According to the EPA, the majority of water pollution in
Solid Waste Treatment Facility Solid Waste Permit Application
Part One: Fees A check or money order for the appropriate fees must be submitted with the permit application. If the required fees are not included, the permit application will be returned to the applicant.
Ingredion ANZ Pty Ltd
Ingredion ANZ Pty Ltd 170 Epping Road, Lane Cove, NSW 2066 EPL: 518 Page 1 of 8 1. Purpose and Background POLLUTION INCIDENT RESPONSE The purpose of this Pollution Incident Response Management Plan (PIRMP)
Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot
Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and
The principles, processes, tools and techniques of project management
Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives
SECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
Jeff Haby, P.E. Director Sewer System Improvements. September 15, 2015. Agenda
SAWS Sanitary Sewer Overflow Reduction Program Jeff Haby, P.E. Director Sewer System Improvements SA Military Engineers Meeting Agenda SAWS Overview Consent Decree CD Compliance Programs Program Transition
Waste Handling & Disposal
Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Improper storage and handling of solid wastes can allow toxic compounds, oils and greases, heavy metals, nutrients, suspended
GENERAL SPECIFICATION
R64 - PAVEMENT MARKING August 1996 GENERAL SPECIFICATION G10 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT
Urban Environmental Management in Singapore. Jothieswaran P Chief Engineer Pollution Control Department National Environment Agency
Urban Environmental Management in Singapore Jothieswaran P Chief Engineer Pollution Control Department National Environment Agency Introduction City state comprising a main island and some islets Land
CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)
CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management
Standard terms and conditions
Standard terms and conditions INTRODUCTION For the provision of a water service (Water Supply, Wastewater and Drainage) Under Section 73(2)(a) of the Water Services Act 2012, landowners may be entitled
WHS Contractor Management Procedure
Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety
Demolition Works Measures for Public Safety
Re-issued under new categorization in August 2009 as Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-21 Buildings Department Practice Note
DRAFT Public Outreach Document for What s an SSMP?
DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials
Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue
Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority
Engineering Policy 146. Severe Weather Management Plans
Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...
Construction Site Draina e
ProPECC PN 1/94 ENVIRONMENTAL PROTECTION DEPARTMENT PRACTICE NOTE FOR PROFESSIONAL PERSONS Construction Site Draina e Introduction The purpose of this practice note is to provide some basic environmental
Pollution Incident Response Plan
Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution
Guide Document for Development of WHS Management Plans
DISCLAIMER: THIS DOCUMENT IS PROVIDED AS GUIDANCE TO ASSIST CONTRACTORS IN MEETING THEIR OBLIGATIONS UNDER THE WHS LAW AND NTG CONTRACTS. NTG DOES NOT ACCEPT ANY RESPONSIBILITY FOR THE CONTENTS OF CONTRACTORS
Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events) 2015
Redland City Council Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events) 2015 Redland City Council Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events)
Management Plan. Contractor Management
Management Plan Contractor Management Doc ID No. Version No. Owner Next Review Date Management Plan Contractor Management Risk Statement: High This document will be reviewed on a one yearly basis, unless
7. Do you perform any out of state work?... If yes, in what states and provide details of work performed
Applicant s Name* (*If more than one entity, attach separate sheet with description of each entity s operations, relationship to each other and ownership.) Contractors Application Agent Applicant Mailing
Implementation Plan: Development of an asset and financial planning management. Australian Capital Territory
Implementation Plan: Development of an asset and financial planning management framework for TAMS Australian Capital Territory NATIONAL PARTNERSHIP AGREEMENT TO SUPPORT LOCAL GOVERNMENT AND REGIONAL DEVELOPMENT
Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024
Environmental Incident Response Procedure Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Document Number: NGSF-PSV-NAS-EN-PLN-0024 Version:
Environmental Management Plan
Environmental Management Plan This environmental management plan outlines Red Bus Services objectives and strategies for protecting the environment. This plan sets out how Red Bus Services intends to comply
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local
Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1
Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 The Montgomery County Dept. of Environmental Protection, in cooperation with the Dept. of Permitting Services and the Washington
CHAPTER 24: ENVIRONMENTAL MANAGEMENT
Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document
OWNER BUILDER AS AN WHAT ARE MY RESPONSIBILITIES UNDER THE DEVELOPMENT ACT 1993
AS AN OWNER BUILDER building work? What records should I keep? Is insurance required? W I need approval for? What do I need approval for? How do I obtain building work? How do I obtain approval? What records
SILICON VALLEY CLEAN WATER. May 2015
SILICON VALLEY CLEAN WATER May 2015 Slug Discharge Control and Spill Containment Guidelines This document was revised and used with the permission of the Los Angeles County Sanitation District, Industrial
Waste Management Action Plan 2011-2015
Waste Management Action Plan 2011-2015 Approved on: 7 June 2011 Owner: Program Manager, 8203 7723 Trim Reference: ACC2011/77875 Next Review Date: June 2014 Executive Summary This Waste Management Action
CONSUMER INFORMATION NOTICE APPLICATOR OR BUSINESS NAME ADDRESS PHONE NUMBER
CONSUMER INFORMATION NOTICE APPLICATOR OR BUSINESS NAME ADDRESS PHONE NUMBER Dear Customer: As of November 19, 2001, the New Jersey DEP Pesticide Control Program instituted a new program that requires
3. QUALITY ASSURANCE REQUIREMENTS
3. QUALITY ASSURANCE REQUIREMENTS 3.1 General This section covers the Kaipara District Council requirements for monitoring and testing of physical asset construction to ensure that the final asset delivered
BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY
MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near
Pollution Incident Response Management Plan
Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes
Proposed Development Phase IV at CRC Oil Terminal, Tsing Yi - Refrigerated Storage Tanks for Liquefied Gas
in association with China Resources Petrochems (Group) Co. Ltd Proposed Development Phase IV at CRC Oil Terminal, Tsing Yi - Refrigerated Storage Tanks for Liquefied Gas Project Profile July 2005 CONTENTS
Approval Services Unit
Approval Services Construction Management Plan Pro-Forma Commercial Properties Please complete the enclosed form and return to:- By Mail: Approval Services Unit City of Perth Council House 27 St Georges
Liquid Effluent Treatment Plant (LETP) Land Clean-Up
Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to
CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13
Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if
Ardessie Hydro Electric Project
Ardessie Hydro Electric Project Appendix T - Traffic Management Plan 13 th December 2014 V1.0 Jacinta MacDermot DHG Hydro Ltd 7 St James s Gardens London W11 4RB [email protected] 077 888
Toronto s Wet Weather Flow Master Plan
Toronto s Wet Weather Flow Master Plan 1. The Master Plan 2. The Don And Waterfront Study 3. What the Individual Can Do Wet Weather Flow Management Master Plan 2000 Storm Presentation to Don Mouth Naturalization...
Computing & Telecommunications Services Monthly Report March 2015
March 215 Monthly Report Computing & Telecommunications Services Monthly Report March 215 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex [email protected] www.wright.edu/cats/ Last Modified
Construction Management Plan Template
Plan Template Planning Permit Number:... Date Planning Permit Issued:... Approval Stamp (Office Use only): Standard Plan Template Project details Company Operational Details.. Directors Name Company Name
ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN
ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN Best Management Practices (BMPs) will be implemented during construction of the Allegany Wind Power Project to prevent and contain spills.
WHS CONTRACTOR MANAGEMENT PROCEDURE
1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and
2016 Dry Cleaning Compliance Calendar
Missouri Department of Natural Resources Division of Environmental Quality 20 Dry Cleaning Compliance Calendar Recycled Paper 12/2015 PUB001310 LEGEND OF TERMS APCP - Air Pollution Control Program EIQ
Depending on your facility and the equipment contained within, all or part of the checklists/logs can be printed for use.
Large Facility Fire Safety Checklists and Logs This package contains checklists to ensure that all fire and life safety equipment are properly inspected. There are also logs on which to record the inspections
THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION
THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass
CONSTRUCTION GENERAL PERMIT RISK ASSESSMENT R-FACTOR CALCULATION NOTIFICATION
CONSTRUCTION GENERAL PERMIT RISK ASSESSMENT R-FACTOR CALCULATION NOTIFICATION NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) GENERAL PERMIT FOR STORM WATER DISCHARGES ASSOCIATED WITH CONSTRUCTION
1200 United Boulevard
MINISTRY OF ENVIRONMENT Thompson and Cariboo Regions 1259 Dalhousie Drive Kamloops BC V2C 5Z5 Telephone: (250) 371-6200 Fax: (250) 828-4000 OPERATIONAL CERTIFICATE FOR THE CACHE CREEK LANDFILL Under the
CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is
~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions
Knock Down Rebuild. Building Process Building process - knock down rebuild 1
Knock Down Rebuild Building Process Building process - knock down rebuild 1 Building Process Your action Our action REMINDER Pre site Step 1 New Home Selection Congratulations. This marks the start of
ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN
ABC CIRCUITS 10 Circuit Drive Circuit Town, IN 12345 SLUG CONTROL PLAN The purpose of this plan is to provide detailed instructions for slug prevention and control. A complete copy of this plan is maintained
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
Department of Public Works. Recycling policy for buildings and civil infrastructure
Department of Public Works Recycling policy for buildings and civil infrastructure A whole-of-government recycling policy for buildings and civil infrastructure Policy statement The Queensland Government
Supervisor Instructions for Approving Web Time Entry
Supervisor Instructions for Approving Web Time Entry Time Approval Deadlines by Category Local 2110 Members members submit time by NOON on Monday of the pay week. Time should be approved no later than
Developer s/consultants Field Services Guidelines
Developer s/consultants Field Services Guidelines 2007 Engineering and Works Department DEVELOPER S/CONSULTANT S FIELD SERVICES GUIDELINES Fourth Electronic Edition February 2007 STATEMENT OF COMPLETION
Construction Site Inspection. Inspecting to Keep You in Compliance
Construction Site Inspection Inspecting to Keep You in Compliance Inspection/Monitoring/Reporting Know if your plan is working Document corrective actions Ketchikan A Contractor that destroys their site
Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP
Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented
City of Raleigh Public Utilities Department. Wastewater EMS Manual
City of Raleigh Public Utilities Department Wastewater EMS Manual TABLE OF CONTENTS PAGE 2 Wastewater EMS Manual Table of Contents Management Direction 1) EMS Manual 2) Management Policy Planning 3) Process
Environmental Guidelines for Preparation of an Environmental Management Plan
2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF
Environmental guidelines for preparation of an Environment Management Plan
Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use
4.05e WHS Guidelines for Incident Investigation Procedures Page 1 of 7
Page 1 of 7 1 Purpose It is a legal requirement under the NSW Work Health and Safety Act 2011 and NSW Work Health and Safety Regulation 2011 to identify hazards, assess the risk of those hazards, implement
In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including:
Enterprise Risk Management Process and Procedures Scope In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including: Risk identification
Legislative Council Panel on Security. Construction of an Ambulance Depot at Choi Shun Street, Sheung Shui
LC Paper No. CB(2)2452/11-12(03) For discussion on 4 July 2012 Legislative Council Panel on Security Construction of an Ambulance Depot at Choi Shun Street, Sheung Shui PURPOSE This paper consults the
Appendix C3: Response Plan for Investigations of Illegal Discharges, 2016
Appendix C3: Response Plan for Investigations of Illegal Discharges, 2016 Response Plan for Investigations For the City and County of Honolulu Municipal Separate Storm Sewer System National Pollutant Discharge
PLANNING & REGULATION COMMITTEE 16 JANUARY 2012
Division(s): Sutton Courtenay & Harwell Contact Officer: John Duncalfe ([email protected]) Tel: 01865 815356 PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 TO CRUSH, SCREEN, BLEND AND STOCK
How To Recover From A Flood In Bundaberg
BUNDABERG FLOODS NOW THE MUD HAS DRIED FLOOD RECOVERY AT MILLBANK Paper Presented by: Kym Kneebone Author: Kym Kneebone, Assistant Coastal Treatment Co-ordinator, Bundaberg Regional Council 37th Annual
Ashley Institute of Training Schedule of VET Tuition Fees 2015
Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-