PREPA Renewable Energy Resources Integration Study San Juan February 19 th 2014
|
|
|
- Stephanie Garrett
- 10 years ago
- Views:
Transcription
1 PREPA Renewable Energy Resources Integration Study San Juan February 19 th 2014 Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
2 Agenda Introduction System Studies Load Flow Short Term Stability Long Term Stability PROMOD Assessment Procedure and models to process the meteorological data. Models testing and assessment PROMOD set up. Scenario Definition Scenario I; Base Case Scenario II: Case with storage. Scenario III: Case with Combined Cycle Intra-Hour Modeling Conclusions Page 2
3 Introduction In this presentation we will cover the main results of the study carried out by Siemens PTI to determine the secure and economic levels that renewable generation can be incorporated in PREPA s system. The studies are organized in three main components: Load flow and short term dynamics Long Term Dynamics PROMOD / Production Costing evaluations. These sections correspond to the studies carried out to determine the impacts of renewable generation and determine solutions as presented next. Page 3
4 Issues to be considered when evaluating renewable Generation The table below describes the main issues associated with large penetration and the section of the study that addressed them Issues with typical Renewable Gen Impact Actions Timeframe Lack of Inertia Angular instability - Inertial Response/ storage 0 to 5 sec No governor and dispatched at max Large ramps / Contingencies Large frequency excursions Large frequency excursions - Governor like response - Increased reserves - Storage (as reserve) - Ramp Limitations - AGC adjustments - Reserve & storage 5 to 30 sec (tens of sec) Tens of sec to several minutes Primarily Evaluated in Short Term Dynamics Short Term Dynamics Long term dynamics Page 4 Large ramps / Contingencies Variability Uncertainty Reduced reserves / curtailment Increased Operating Costs Increased Operating Costs - Increase reg reserve. minutes - Increase reg reserve. - Cost assessment - Frequent ED minutes to hours - Improved forecasts Hours Un-dispatchability Curtailment - Limit the penetration long term PROMOD IV Intra-hour PROMOD IV Load following PROMOD IV Forecast Uncertainty PROMOD IV Optimal Penetration
5 PREPA Renewable Energy Resources Integration Study System Studies Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
6 System Studies Initial Project Selection To start the system studies we need a feasible dispatch The dispatch was selected maximizing the renewable generation without consideration to economics, only the capability of the generating fleet at specific moments in time. This selection made sure that the system studies would be carried out with worst possible conditions Dispatch and Economic Studies (PROMOD) were expected to confirm or reduce these values. A model was created working with PREPA that accounted for these dispatch limitations and it was determined that that up to 895 MW of PV and Wind Turbine generation could be integrated. We show next an screen shot to the model for the critical light load day. Page 6
7 Initial Project Selection Light Load Day The critical time is noon time when renewable is expected to be maximum The light load has a load that has 90% probability of being exceeded at noon time. Checks on limits and reserves were carried out. Generation Characteristics Min Day Regulating Range Operating Range On Daytime Machine Machine Machine Nighttime Machine Machine Name Type Min Max Min Max Line Peak Primary R Regulating Reserve Peak Regulating Reserve MW MW MW MW I / O 12:00 PM PMax Margin Margin 12:00 PM Margin Margin Palo Seco 4 * Steam Not Reg Under Costa Sur 5 Steam Aguirre 1 Steam AgCCV 1 CCP Not Reg Not Reg No Reserve AgCCGT 1-1 CCP Not Reg AgCCGT 1-2 CCP Off Off Off AgCCGT 1-3 CCP Off Off Off AgCCGT 2-1 CCP Off Off Off AgCCGT 2-2 CCP Off Off Off AgCCGT 2-3 CCP Off Off Off SJ Rep Steam 1 CCP Not Reg Not Reg SJ Rep Gas 1 CCP Not Reg Not Reg AES1 Coal Not Reg Not Reg Not Reg 0.0 AES2 Coal Not Reg Not Reg Not Reg 0.0 ECOSTEA Cogen N/A ECOGT1 Cogen ECOGT2 Cogen PaloSecoGT11 GT Off Off PaloSecoGT12 GT Off Off PaloSecoGT21 GT Off Off PaloSecoGT22 GT Off Off PaloSecoGT31 GT Off Off PaloSecoGT32 GT Off Off VegaBajaGT11 GT Off Off VegaBajaGT12 GT Off Off AguirreGT21 GT Off Off AguirreGT22 GT Off Off JobosGT11 GT Off Off JobosGT12 GT Off Off DaguaoGT11 GT Off Off DaguaoGT12 GT Off Off YabucoaGT11 GT Off Off YabucoaGT12 GT Off Off SOUCOGT11 GT Off Off SOUCOGT12 GT Off Off MAY AERO #1 GT Off Off Page 7 TOTAL Conventional Total Renewable WTE Total Renewable PV & Wind Turbine Total Generation Dispatch Summary 0.0 Load MW Balance Check OK OK Regulating Reserve Regulating Reserve OK OK OK Regulating Reserve in Aguirre 1 & 2 + Costa Sur 5&6 (40 MW min) Regulating reserve OK in Ag & CS? OK OK Online Spining Reserve Spinning Reserve OK OK OK GT's Online (does not include Cambalache if dispatched) % GT's 0% 73% GT's Offline + Reserve (fast start) w/o Cambalache
8 Initial Project Selection Based on this and by inspection of PREPA s PPOA contracts we selected the projects indicated for a total of MW. This selection was done to have a representative sample to study that could be accommodated in the dispatch, but no inference to a particular contract should be made. Page 8 NUM Project Name Type Capacity 31 Pattern Wind Go Green PR (Punta Lima) Wind 26 1 AES Ilumina Solar Wind-59 Wind Wind-61 Wind Wind-2 Wind Solar-18 Solar 10 4 Solar-4 Solar Solar-30 Solar Solar-46 Solar 20 7 Solar-7 Solar 40 3 Solar-3 Solar Solar-36 Solar Solar-21 Solar Solar-62 Solar Solar-47 Solar Solar-42 Solar Solar-43 Solar Solar-15 Solar Solar-63 Solar Solar-17 Solar Solar-16 Solar Solar-54 Solar Solar-39 Solar Solar-40 Solar Solar-56 Solar Solar-57 Solar Solar-27 Solar Solar-23 Solar Solar-53 Solar Solar-44 Solar 20 8 Solar-8 Solar 10 9 Solar-9 Solar Solar-10 Solar 30 TOTAL: 884.2
9 Load Flow Evaluation Verification of Interconnection Capability The 884 MW of renewable projects were added to PREPA s Load Flow models. The system was tested for N-1 contingency conditions No thermal or severe voltage violations associated with this integration were found resulting in an acceptable case. The importance of Renewable Projects to control voltages was observed (MTR compliance) Few high voltages were identified, but these were minor (at 38 kv) and do not compromise the assessment of stability. Note that 1.10 pu is usually accepted for contingency conditions. Page 9 Bus # Bus Name KV ContVolt BaseVolt Contingency Description Pre-Proj ContVolt Delta V Deviation (>0.5%) 49 MONACILLO MONACILLO CORRECCION #N/A #N/A 0.74% 59 MARTIN PE A MARTIN PE A DEPTOFAMILIA #N/A #N/A 0.65% 113 ACACIAS ACACIAS CABO ROJO NO #N/A #N/A 0.65% 123 BERWIND BERWIND LOS ANGELES #N/A #N/A 1.16% 215 BARRANQUITAS BARRANQUITAS OROCOVIS #N/A #N/A 0.62% 249 CABO ROJO NO CABO ROJO NO CABOROJOPRO #N/A #N/A 1.54% 276 COMERIO CIDRA SECC COMERIO #N/A #N/A 1.00% 300 S.GERMANTC S.GERMANTC LOCTITE #N/A #N/A 0.58% 361 COMERIO NO CIDRA SECC COMERIO #N/A #N/A 0.92% 456 PONCE CEMENT PONCE CEMENT CEMEX PONCE #N/A #N/A 1.32% 505 XTRA MAYAG ACACIAS CABO ROJO NO #N/A #N/A 0.50% 582 BAXT AIBONIT BAXT AIBONIT TO RICO #N/A #N/A 1.65% 584 LOCTITE SABANAGRANDE LOCTITE #N/A #N/A 0.55% 666 CORRECCION CIEN MEDICAS CORRECCION #N/A #N/A 1.25% 1051 TREN MARTIN PE A DEPTOFAMILIA #N/A #N/A 0.65% 1155 MARTINPE AB RECNATURALES MARTINPE AB #N/A #N/A 0.71% 1169 AAA TAP S.JOS AAA #N/A #N/A 2.34%
10 Short Term Stability Evaluation Verification of System Response A detailed dynamic stability model adding the dynamic models for the renewable generation and including storage to PREPA s model. The storage model was developed by us as well as new models for representing PREPA s load shedding schemes. Various contingencies including tripping of lines and generation were assessed. 3ph Faults at Generation Facilities, Normal Clearing - Unit Trip No Type Description kv FLT-01 3ph, normal clearing At Ecoelectrica 319, units at 858,859,869 are tripped 230 FLT-02 3ph, normal clearing At Aguirre 106, unit at 809 tripped 230 FLT-03 3ph, normal clearing At Costa Sur 96, unit at 805 tripped 230 FLT-04 3ph, normal clearing At AES 321, unit at 871 tripped 230 FLT-05 3ph, normal clearing At San Juan 88, units at 811 and 856 are tripped 115 FLT-06 3ph, normal clearing At Palo Seco 63, unit at 819 tripped 115 Page 10
11 Short Term Stability Evaluation Verification of System Response Also line trips and load rejection events were studied... 3ph Faults at Generation Facilities, Normal Clearing - Line Trip No Type Description kv FLT-20 3ph, normal clearing At Aguirre 106, trip line to Agubuenas FLT-21 3ph, normal clearing At Aguirre 107, trip line to Jobos FLT-22 3ph, normal clearing At Costa Sur 96, trip line to Manati FLT-23 3ph, normal clearing At Costa Sur 2, trip line to Canas FLT-24 3ph, normal clearing At AES 321, trip line to Yabucoa FLT-25 3ph, normal clearing At San Juan 88, trip line to Viaducto FLT-26 3ph, normal clearing At Palo Seco 63, trip line to Monacillo SLG Faults at Generation Facilities, Delayed Clearing - Line Trip No Type Description kv FLT-27 SLG, delayed clearing At Aguirre 106, trip line to Agubuenas FLT-28 SLG, delayed clearing At Aguirre 107, trip line to Jobos FLT-29 SLG, delayed clearing At Costa Sur 96, trip line to Manati FLT-30 SLG, delayed clearing At Costa Sur 2, trip line to Canas FLT-31 SLG, delayed clearing At AES 321, trip line to Yabucoa FLT-32 SLG, delayed clearing At San Juan 88, trip line to Viaducto FLT-33 SLG, delayed clearing At Palo Seco 63, trip line to Monacillo ph Fault at 230 kv S/S (Non-Generating), Normal Clearing - Line Trip No Type Description kv FLT-07 3ph, normal clearing At Bayamon 99, trip 3wnd TF to Bayamon /115 FLT-08 3ph, normal clearing At S.llana 120, trip line to Agubuenas FLT-09 3ph, normal clearing At Manati 196, trip line to Costa Sur FLT-10 3ph, normal clearing At Mayaguz 204, trip line to Maya TC FLT-11 3ph, normal clearing At Maya TC 232, trip line to Costa Sur FLT-12 3ph, normal clearing At Yabucoa 233, trip line to AES FLT-13 3ph, normal clearing At Mora 352, trip 3wnd TF to Moca /115 FLT-14 3ph, normal clearing At Ponce TC 363, trip line to Pon Bypass FLT-15 3ph, normal clearing At Camb GP 440, trip line to Dbocas FLT-16 3ph, normal clearing At Agubuenas 451, trip line to Aguirre FLT-17 3ph, normal clearing At Cacao 956, trip line to Yabucoa FLT-18 3ph, normal clearing At Pon Bypass 1077, trip line to Costa Sur FLT-19 3ph, normal clearing At Dbocas Fase 1110, trip line to Costa Sur ph Fault at Indicated Bus followed by opening of lines / buses No Type Description FLT-34 3ph fault at bus 38 Load Rejection , 177, 400, 555 FLT-35 3ph fault at bus 92 Load Rejection , 245, 248, 593, 594, 595, 599, 746, 747, 748, 990, 991, 1049, 1065, 1174 FLT-36 3ph fault at bus 98 Load Rejection , 220, 265, 285, 422, 435, 437, 438, 585, 617, 621, 641, 660, 783, 961, 965, 967, 1010, 1034, 1147 Page 11
12 Short Term Stability Evaluation Verification of System Response All events analyzed resulted in stable behavior, but in some cases load shedding was required to obtain stability. In particular it was identified that it was important for the renewable to comply with the MTR and provide voltage support and frequency regulation. As a reference the figure below shows the trip of Ecoelectrica with compliance of the MTR (storage) to the left and without (no storage) to the right Fault 01 - Frequency at bus 50 MTR Compliance Time (seconds) 35 60,2 60, ,9 59,8 59,7 59,6 59,5 59,4 59,3 59,2 59, ,9 58,8 58,7 58,6 58,5 58,4 58,3 58,2 58, Fault 01: frequency at bus 50 No MTR Lower frequency for longer Time (seconds) 30 gfedcb 60*(1+A) : FLT01-3PH-peak_load gfedcb 60*(1+A) : FLT01-3PH-light_load gfedcb 60*(1+A) : FLT01-3PH-peak_load-no-storage gfedcb 60*(1+A) : FLT01-3PH-light_load-no-storage Page 12
13 Short Term Stability Evaluation Verification of System Response The tables below provide further details on the most critical contingencies evaluated that were associated with the trip of generation. Note the greater need for load shed if storage is not considered. Disturbance Peak Load Peak Load Renewable without BESS ID-Loss of Generation Generation Tripped [MW] Post-contingency Available Primary Reserve [MW] Lowest Frequency [Hz] Load Shedding [MW] Lowest Frequency [Hz] Load Shedding [MW] 01-Ecoelectrica Aguirre Costa Sur AES S J Repwr Palo Seco Disturbance Light Load Light Load Renewable without BESS ID-Loss of Generation Generation Tripped [MW] Post-contingency Available Primary Reserve [MW] Lowest Frequency [Hz] Load Shedding [MW] Lowest Frequency [Hz] Load Shedding [MW] 01-Ecoelectrica Aguirre Costa Sur AES S J Repwr Page Palo Seco
14 Long Term Dynamic Evaluation Verification of System Response The evaluation of long term dynamics (LTD) assesses how PREPA s conventional generation will respond in the multi-minute range to sudden events as the trip generation and generation changes in the renewable. A key component evaluated is the Automatic Generation Control (AGC) that should bring the frequency back to the nominal 60 Hz. In addition to the generation trips just presented the renewable generation changes include; Steep power change; changes of -3%/minute and 15 minutes duration on all PV s in the island (loss of 324 MW of PV power). Long duration power changes: changes of -2%/minute of 30 minutes duration affecting all PV s in the island (loss of 432 MW of PV power) Localized changes up to 50% / min without ramp control and 10%/min with ramp control. Page 14
15 60*(1+A) : FLT02-AGC-3PH-peak_load 21 - ACE : FLT02-AGC-3PH-peak_load Long Term Dynamic Evaluation Verification of System Response The analysis identified that with the initial dispatch considered there would be insufficient secondary reserve to recover the frequency to 60 Hz under certain contingencies. Disturbance Status after fault 60,5 FLT 02: trip Aguirre 01 f [Hz] & ACE [pu] 200 ID-Loss of Generation tripped [MW] Peak load Light load 01-Ecoelectrica 507 OK OK 02-Aguirre Insufficient reserve* OK 60, ,75 59, Costa Sur OK OK 04-AES OK OK 59, S J Rep 129 OK OK Palo Seco OK OK 58, , Time (seconds) gfedcb 60*(1+A) : FLT02-AGC-3PH-peak_load gfedcb 21 - ACE : FLT02-AGC-3PH-peak_load Page 15
16 60*(1+A) : RAMP-PV-02-peak_load 21 - ACE : RAMP-PV-02-peak_load 60*(1+A) : RAMP-PV-03-peak_load 21 - ACE : RAMP-PV-01-peak_load Long Term Dynamic Evaluation The analysis identified that with the initial dispatch considered there would be insufficient secondary reserve to recover the frequency to 60 Hz under certain RAMP 01: -3%/min x 15 min to all PV gen. f [Hz] & ACE [pu] contingencies (Cont). 60,075 60,05 60, Disturbance Status after fault ID Generation loss [MW] Peak load Light load 59,975 59, Ramp 01: -45% of all PV gen. 324 OK OK Ramp 02: -60% of all PV gen. 432 Insufficient reserve* OK 59,925 59,9 59, Ramp 03: -75% of north cluster PV gen. 213 OK OK Ramp 04: -90% of north cluster PV gen. 255 OK OK Ramp 05: -100% of all Wind gen. 164 OK OK Ramp 06: -100% of Site 21 PV gen. 87 OK OK 59,85 59, , Time (seconds) Ramp 02: -2%/min x 30 min to all PV gen. f [Hz] & ACE [pu] gfedcb 60*(1+A) : RAMP-PV-01-peak_load gfedcb 21 - ACE : RAMP-PV-01-peak_load Ramp 07: -100% of Site 21 PV gen. 87 OK OK Ramp 08: -100% of Wind gen at Pattern 76 OK OK 60, ,95 59,9 59,85 59, , , , , Time (seconds) Page 16 gfedcb 60*(1+A) : RAMP-PV-02-peak_load gfedcb 21 - ACE : RAMP-PV-02-peak_load
17 Long Term Dynamic Evaluation Adjustment From simulations, it was determined that if the amount of secondary reserve is equal or greater than 50% of the total renewable generation dispatch the response should be adequate. To meet these requirements, the peak load case was modified by a reduction of the generation at Ecoelectrica of 100 MW and increasing the generation at AES and Palo Seco 3 & 4 that were not regulating. This solved the situation as shown below for the previous events 60,5 FLT 02: trip Aguirre 01 unit - comparisson original and new dispatched case Ramp 02: MW PV variation - comparisson original and new dispatch case 60,05 60, ,75 59,5 59,95 59, ,9 58,75 58, Time (seconds) , Time (seconds) Page 17 gfedcb 60*(1+A) : FLT02-AGC-3PH-peak_load gfedcb 60*(1+A) : FLT02-AGC-3PH-peak_load-redispatched gfedcb 60*(1+A) : RAMP-PV-02-peak_load gfedcb 60*(1+A) : RAMP-PV-02-peak_load-redispatched
18 60*(1+A) : RAMP-PV-07-peak_load 21 - ACE : RAMP-PV-06-light_load 21 - ACE : RAMP-PV-07-peak_load Long Term Dynamic Evaluation Localized Events Renewable simulation and field observations indicate that sharp changes in renewable generation are possible. We evaluated a 50%/min (43 MW/min) change and found that the frequency could dip under 59.9 Hz and require 400 seconds to recover. Considering that this could happen several times during the day and could be compounded with other conditions in the system, from a planning perspective we are of the opinion that would be unacceptable. With 10%/min the frequency dips close to HZ, which is quite acceptable. 60,35 60,3 60,25 60,2 RAMP 06: -50%/min x 2 min at Site 21 PV gen. f [Hz] & ACE [pu] ,03 60,025 60,02 60,015 60,01 Ramp 07: -10%/min x 10 min at Site 21 PV gen. f [Hz] & ACE [pu] , , ,1 60, ,95 59, ,995 59,99 59,985 59,98 59, , Time (seconds) Page 18 gfedcb 60*(1+A) : RAMP-PV-06-light_load gfedcb 21 - ACE : RAMP-PV-06-light_load 59, gfedcb Time (seconds) 60*(1+A) : RAMP-PV-07-peak_load gfedcb 21 - ACE : RAMP-PV-07-peak_load
19 System Assessment Conclusions The study confirms that with 884 MW of renewable generation PREPA s grid should be able to ride through the set of severe contingencies and generation changes. No voltage collapse occurred. Primary and secondary reserve can be secured It is recommended that PREPA keeps resources available with secondary reserve of least 50% of the renewable generation dispatched. The importance of 100% compliance with the MTR s was observed; voltage, frequency and ramp controls. Given the significant contribution that the renewable generation can provide from BESS; It is recommended that PREPA revises its MTR to require that renewable generation projects do not inhibit the contribution from the BESS even when dispatched at contractual maximum. Page 19
20 PREPA Renewable Energy Resources Integration Study PROMOD EVALUATION Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
21 Introduction This part of the presentation will enter into the details and results of the Production costing evaluations using PROMOD. PROMOD is widely used program by the industry for the formulation of a Security Constraint Unit Commitment and Security Constrained Economic Dispatch The PROMOD simulations achieve the objective of evaluating the performance of the generation fleet in the presence of the renewable generation. Page 21
22 Topics Procedure and models to process the meteorological data to create the Renewable models used for PROMOD. Models testing and assessment Set up the PROMOD evaluations considering the renewable. Scenario Definition Scenario I; Base Case Scenario II: Case with storage. Scenario III: Case with Combined Cycle Intra-Hour Modeling Page 22
23 PREPA Renewable Energy Resources Integration Study Procedure and models to process the meteorological data to create the Renewable models used for PROMOD Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
24 Renewable Generation Models AWS Truepower (AWS) Mesoscale Models Renewable Models Start From Meteorological Data AWS developed a Mesoscale Numerical Prediction Model for Puerto Rico. The model provides simulated wind and solar data for Puerto Rico and captures in a realistic fashion both the temporal and spatial variability of the wind and solar resource The model was developed taking into consideration the conditions during 2011, corrected for the effect of Hurricane Irene. The model provides all data required for accurate representation of the renewable resource Parameters for 23 sites were produced. Page 24
25 Evaluated Renewable Projects Solar (PV) Projects 720 MW Solar PV projects were modeled. The project capacity and corresponding AWS site is a key element in the modeling. NUM Name Location Capacity MW AWS SITE 1 AES Ilumina, LLC Guayama Photovoltaic #1 Barceloneta Photovoltaic #2 Salinas Photovoltaic #3 Humacao Photovoltaic #4 Lajas Photovoltaic #5 Naguabo Photovoltaic #6 San Lorenzo Photovoltaic #7 Hatillo Photovoltaic #8 Guayama Photovoltaic #9 Hatillo Photovoltaic #10 Salinas Photovoltaic #11 Morovis Photovoltaic #12 Juncos Photovoltaic #13 Juncos Photovoltaic #14 Aguadilla Photovoltaic #15 Vega Baja Photovoltaic #16 Barceloneta Photovoltaic #17 Fajardo Photovoltaic #18 Añasco Photovoltaic #19 Quebradillas Photovoltaic #20 Añasco Photovoltaic #21 Loíza Photovoltaic #22 San German Photovoltaic #23 Vega Baja Photovoltaic #24 Yabucoa Photovoltaic #25 Dorado-Toa Baja Photovoltaic #26 Yauco-Guayanilla Photovoltaic #27 Ponce Photovoltaic #28 Yabucoa Total Page 25
26 Evaluated Renewable Projects Wind (WTG) Projects WTG Projects added to 164 MW installed. As before the project s capacity and corresponding AWS site is a key element in the modeling. NUM Name Location Capacity MW AWS SITE 2 Wind Generation # 1 Santa Isabel Pattern Santa Isabel, LLC Santa Isabel Punta Lima (Go Green PR) Naguabo Wind Generation # 2 Guayanilla Wind Generation # 3 Guayanilla Total These projects with the 720 MW PV add to the 884 MW considered during the stability evaluations Page 26
27 Renewable Generation Models Grouping of Projects 8 -Mayaguez Regional effects are important to be evaluated so the projects were grouped in increasing level: AWS Site / Project All projects move in unison. Area Some diversity between the Network Areas. Cluster Further diversity within Areas in Cluster Island Level Maximum diversity between Clusters. 7 Arecibo Bayamon 2 Bayamon 1 San Juan West Page 27 North South 6 Ponce OE 5 Ponce ES East 3 Carolina 4 Caguas Site Area Name Cluster PV WTG Total 1 7 ARECIBO North ARECIBO North ARECIBO North ARECIBO North BAYAMON North BAYAMON North BAYAMON North CAROLINA East CAROLINA East CAROLINA East CAGUAS East CAGUAS East PONCE ES South PONCE ES South PONCE ES South PONCE OE South PONCE OE South MAYAGUEZ West MAYAGUEZ West MAYAGUEZ West CAGUAS East CAROLINA East CAROLINA East Total
28 Power per MW installed PV Model Development Solar Models The program PVSyst was used to estimate production at each AWS Site based on the Global Horizontal Irradiance (GHI) and the Diffuse Horizontal Irradiance (DHI) as provided by AWS in 10 minutes intervals New Design Original Global Effective Incidence W/m2 Page 28
29 Wind Turbine Model Development WTG were created based on the results of the climate data and a Siemens SWT wind turbine generator Power Curve model. This turbine was selected as representative of the wind turbines available in the market for medium to low speed sites. Note it s better performance at low speeds than the SWT 3.0 The power curve correlates the wind speed at the hub with power output was used to determine a curve fitting equation. pu Wind Turbine Power Output SWT vs SWT The wind speed at the hub is affected by Shading: impact of one turbine on another or external obstacles The speed was forecasted at the right height Wind Speed m/sec SWT Power (pu) SWT Power (pu) Page 29
30 Wind Turbine Model Development Model Development Shading Factors were selected considering that the impact of shading being about 5% of the energy output due to other turbines and that bodies outside the fence can reduce the energy output further by another 5% or more. This was verified for PREPA considering the actual reported production for existing projects. A model (analogous to PVSyst) was created to determine power starting from the AWS forecasted wind speed by site,. Page 30
31 Model Development Post Processing A post processing model was developed for Produce 10 minute output based on PVSyst hourly production and irradiance data from AWS. WTG production was already in 10 minutes Verification maximum output and capacity factors. Aggregation of results by Area, Cluster and Island, to evaluate impacts at this level. of capacity Site Number Area Area 6 Cluster PONCE OE Site Adjustment Factor: Max Ramp %/min Contracted Capacity (CA) % Max MW output at site per MW gross Time Max MW output per MW gross - Selected /10/11 3:20 PM Base Power Maximum value Days reached 38% 38% Capacity Factor 33.76% 33.76% Time Base Power 0 D 2/25/11 6:20 AM Check Active Total PONCE OE Longest 30 min Ramp Increase MW & %/min % Duration mn & %/min Time 5/13/11 1:30 AM Power per MW Power output gross MW %CA/min - 10min Index MW/min 10Site Number Total Island wide Area AWS Site Data Cluster % % 1.0 Site Adjustment Factor: Max Ramp %/min Longest 30 min+ Ramp % Contracted Capacity (CA) % 7.32% -2.0 Increase MW & %/min 10Max MW output at site per MW gross % Time Max MW output per MW gross - Selected /30/ % 7:40 AM % % 3.0 Base Power Maximum value Duration mn & %/min % Days reached % % 0.15% Capacity Factor % % 0.13% Time 6.0 Time 0 D 1/26/11 10:00 AM 7/14/11 4:20 PM Active Total Island wide Page 31 Power per MW gross Power output MW %CA/min - 10min Index MW/min % % % % % 1.0
32 PV Model Development 60 Minutes Models PROMOD requires hourly values so two models were created to produce these inputs to the program. Code 2 Hour SITE 32 SITE 02 SITE 31 SITE 59 SITE 61 max ouput Capacity Factor 28.22% 32.18% 37.90% 27.46% 27.46% Installed PPA AVG Max Min Hour SITE 32 SITE 02 SITE 31 SITE 59 SITE Page 32
33 PREPA Renewable Energy Resources Integration Study Models testing and assessment Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
34 Model Testing and Assessment PV Results Cluster or Island-wide Cluster Installed PV Maximum value Capacity Factor Max Ramp MW Max Ramp %/min Long Ramp MW Long Ramp %/Min Time for max ramp Time for long ramp North % % % 5/1/11 12:00 PM 6/16/11 10:50 AM East % % % 5/15/11 11:00 AM 5/1/11 12:20 PM South % % % 8/13/11 1:20 PM 7/7/11 12:50 PM West % % % 6/30/11 12:20 PM 9/19/11 1:50 PM Island Wide % % % 5/1/11 12:00 PM 5/1/11 12:20 PM All projects can be operating close to their maximum output simultaneously. 5% of the time the combined PV output is over 650 MW (90% of installed capacity) and 20% of the time we would have production over 600 MW at noontime The aggregated capacity factor for each of the clusters is as expected in the order of 21%. Page 34
35 . Model Testing and Assessment PV Cluster or Island-wide The maximum aggregated generation changes are in the range of 4.34% to 6.37% at the cluster and 2.64% at the Island-Wide level The figure shows the maximum change over 10 minutes; 123 MW at the cluster level and 190 MW Island-Wide on May 1st at noon. The long steep changes of 257 MW Island-Wide over 20 minutes were observed (1.8% / minute ). Page 35
36 Model Testing and Assessment PV at the Area Level Area Area Name Installed PV Capacity Factor Maximum value Max Ramp MW The max changes (6.01% average) and the long changes (2.96% average) are higher than the corresponding results for the Clusters and Island-Wide values. This is expected earlier because as we reduced the size of the area under consideration, local effects have greater impact. Max Ramp %/min Long Ramp MW Long Ramp %/Min Time for max ramp Time for long ramp 1 S.JUAN 0 2 BAYAMON % % % 5/1/11 1:00 PM 5/1/11 1:00 PM 3 CAROLINA % % % 7/4/11 11:50 AM 9/25/11 10:50 AM 4 CAGUAS % % % 5/15/11 11:00 AM 8/10/11 11:30 AM 5 PONCE ES % % % 9/6/11 10:40 AM 5/14/11 1:20 PM 6 PONCE OE % % % 3/21/11 12:20 PM 7/16/11 2:20 PM 7 ARECIBO % % % 5/1/11 12:00 PM 5/31/11 2:00 PM 8 MAYAGUEZ % % % 6/30/11 12:20 PM 7/27/11 12:00 PM Total or avg % 2.96% Page 36
37 Model Testing and Assessment Sites Site 1 Site 2 Site 3 Site 4 Site 5 Site 6 Site 7 Site 8 Site 9 Site 10 Installed MW Max MW Capacity Factor 20% 21% 21% 21% 20% 21% 21% 0% 19% 20% Max Ramp% 8.2% 8.0% 8.3% 8.4% 8.3% 7.8% 8.3% 0.0% 8.3% 7.1% Max MW change Site 11 Site 12 Site 13 Site 14 Site 16 Site 17 Site 18 Site 19 Site 20 Site 21 Site 22 TOTAL Installed MW Max MW Capacity Factor 20% 20% 21% 21% 21% 21% 21% 19% 20% 20% 21% Ramp% 8.2% 8.4% 7.0% 7.3% 8.2% 7.2% 7.7% 8.3% 8.2% 8.1% 8.0% 7.6% Max MW change We observe that all sites have capacity factors in the expected range and of course all of them reach their maximum value. Sites have the greatest volatility with maximum aggregated production changes as high as 8.4%/min observed. Note that as the meteorological data was in 10 minutes interval changes of 10%/min or greater cannot be observed with this information. Page 37
38 7:00 AM 7:30 AM 8:00 AM 8:30 AM 9:00 AM 9:30 AM 10:00 AM 10:30 AM 11:00 AM 11:30 AM 12:00 PM 12:30 PM 1:00 PM 1:30 PM 2:00 PM 2:30 PM 3:00 PM 3:30 PM 4:00 PM 4:30 PM 5:00 PM 5:30 PM 6:00 PM 7:00 AM 7:30 AM 8:00 AM 8:30 AM 9:00 AM 9:30 AM 10:00 AM 10:30 AM 11:00 AM 11:30 AM 12:00 PM 12:30 PM 1:00 PM 1:30 PM 2:00 PM 2:30 PM 3:00 PM 3:30 PM 4:00 PM 4:30 PM 5:00 PM 5:30 PM 6:00 PM Model Testing and Assessment PV Cluster or Island-wide - Peaks Finally although the model produced contains the plots for all sites, here we will present two groups of sites for the typical day in July were we note the difference in volatility across sites MW MW MW MW Site 1 Site 2 Site 3 Site 4 Site 6 Site 7 Site 10 Site 11 Site 12 Site 19 Site 20 Site 21 Total Site 5 Site Site 13 Site Site 16 Site Site 18 Site Total Page 38
39 0.0% 1.0% 2.0% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0% 9.0% 10.0% 11.0% 12.0% 13.0% 14.0% 15.0% 16.0% 17.0% Probablity that the value will be less Model Testing and Assessment PV Effect of time intervals on Ramps Timeframe has an important impact on observed ramps. Considering 5 minutes intervals we identified change was in the order of 10% to 13% and it can reach values as high as 16% using one weather station data At the site level; PREPA has observed changes as high as 75 %/minute; see below. Changes need time to propagate, but steep ramps can happen at the local level and can have potential impacts in the frequency and voltages, as shown earlier % % 90.00% 80.00% 70.00% 60.00% 50.00% 40.00% 5 Minutes 15 minutes 30.00% 20.00% 10.00% 0.00% Ramp Rate %/minute Page 39
40 7:00 AM 7:40 AM 8:20 AM 9:00 AM 9:40 AM 10:20 AM 11:00 AM 11:40 AM 12:20 PM 1:00 PM 1:40 PM 2:20 PM 3:00 PM 3:40 PM 4:20 PM 5:00 PM 5:40 PM 6:20 PM 7:00 PM 7:40 PM 8:20 PM 9:00 PM 9:40 PM 10:20 PM 11:00 PM 11:40 PM 12:20 AM 1:00 AM 1:40 AM 2:20 AM 3:00 AM 3:40 AM 4:20 AM 5:00 AM 5:40 AM 6:20 AM Model Testing and Assessment WTC Cluster or Island-wide Cluster Installed WTG Maximum value Capacity Factor Max Ramp MW The peaks can be long duration; Max Ramp %/min Long Ramp MW Long Ramp %/Min Time for max ramp Time for long ramp North East % % % 4/30/11 12:20 AM 5/2/11 12:30 PM South % % % 7/30/11 7:40 AM 7/30/11 7:40 AM West Island Wide % % % 7/30/11 7:40 AM 7/14/11 4:20 PM The all projects reach their maximum output simultaneously and in multiple days. WTG reached its maximum output simultaneously 8% of the days MW South East Total Page 40
41 05:02 AM 05:45 AM 06:28 AM 07:12 AM 07:55 AM 08:38 AM 09:21 AM 10:04 AM 10:48 AM 11:31 AM 12:14 PM 12:57 PM 01:40 PM 02:24 PM 03:07 PM 03:50 PM 04:33 PM 05:16 PM 06:00 PM 06:43 PM 07:26 PM 08:09 PM Model Testing and Assessment Cluster or Island-wide When PV production is considered in addition to the WTG we find that on April the maximum renewable simultaneous production of 876-MW was reached. This represents 99% of the installed capacity It demonstrates that this event can and will happen MW WTG PV TOTAL Page 41
42 7:00 AM 7:40 AM 8:20 AM 9:00 AM 9:40 AM 10:20 AM 11:00 AM 11:40 AM 12:20 PM 1:00 PM 1:40 PM 2:20 PM 3:00 PM 3:40 PM 4:20 PM 5:00 PM 5:40 PM 6:20 PM 7:00 PM 7:40 PM 8:20 PM 9:00 PM 9:40 PM 10:20 PM 11:00 PM 11:40 PM 12:20 AM 1:00 AM 1:40 AM 2:20 AM 3:00 AM 3:40 AM 4:20 AM 5:00 AM 5:40 AM 6:20 AM 7:00 AM 7:40 AM 8:20 AM 9:00 AM 9:40 AM 10:20 AM 11:00 AM 11:40 AM 12:20 PM 1:00 PM 1:40 PM 2:20 PM 3:00 PM 3:40 PM 4:20 PM 5:00 PM 5:40 PM 6:20 PM 7:00 PM 7:40 PM 8:20 PM 9:00 PM 9:40 PM 10:20 PM 11:00 PM 11:40 PM 12:20 AM 1:00 AM 1:40 AM 2:20 AM 3:00 AM 3:40 AM 4:20 AM 5:00 AM 5:40 AM 6:20 AM Model Testing and Assessment WTG Cluster or Island-wide Given it concentrated location in the south, the WTG generation experiences larger aggregated changes. The maximum observed changes are 7.32%/min for PREPA and 8.8%/min for the South Cluster. At the project level we observed ramps of 10%/min, which is the maximum that could be observed for 10 min intervals. The maximum observed Long Changes in the case were % for a 134 MW reduction. This occurred on July 14 at 4:20 pm and is shown in the lower figure. At the local level meteorological data and PREPA s measurements indicate that14%/min ramps are possible and values higher than 19%/min are possible MW South East Total MW South East Total Page 42
43 Renewable Modeling Conclusion and Observations Renewable generation does peak at the same time on certain days of the year. PV can present important aggregated changes at the island level 2.64%/minute over 10 minutes; total change 190 MW 1.8%/minute and a total change of 257 MW over 20 minutes. The North Cluster also shows important changes: 4.34%/min for 10 min as well as the long ramp of 2.2/min % for 20 minutes. PV can experience localized changes 37%/min and up to 65% per minute. For WTG 10%/min for 10 minutes can happen at the island level 20%/min in 5 minutes at the project level. Page 43
44 PREPA Renewable Energy Resources Integration Study PROMOD Setup Considering Renewable Resources Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
45 PROMOD Set Up Renewable Generation Renewable Generation was modeled as Must Run with hourly profiles. Page 45
46 PROMOD Set Up Conventional Generation PROMOD Generator Capability & Capacity Segments The operating limits, ramping rates, O&M costs, start up costs, capacity segments, maintenance and heat rate curves of the conventional generation was reviewed and updated as necessary. Also minimum down time and run time was reviewed (more on this later) Fuels Specific fuels were added to the database in the years when expected to be available Natural Gas Ecoelectrica (from first year 2015 in the model) Natural Gas Norte (from 2017 in the model) Natural Gas Costa Sur (from first year 2015 in the model) Natural Gas Aguirre (from 2017 in the model) The fuel prices are adjusted by month and year and are deemed conservative. Page 46
47 PROMOD Renewable Models Fuel Costs Forecast ($/MMBtu) FuelForecast Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Average Bunker- Aguirre Bunker-PSSP Bunker-SJSP Bunker-Souco COAL-AES Light D.-AGUIRRE Light D.-Camabalac Light D.-PREPA Light D.-SJUAN Natural Gas - Aguirre Natural Gas - Contract Natural Gas EcoElectrica Natural Gas Norte FuelForecast Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Average Bunker- Aguirre Bunker-PSSP Bunker-SJSP Bunker-Souco COAL-AES Light D.-AGUIRRE Light D.-Camabalac Light D.-PREPA Light D.-SJUAN Natural Gas - Aguirre Natural Gas - Contract Natural Gas EcoElectrica Natural Gas Norte Page 47
48 PROMOD Set Up Requirements FLOWGATES; PROMOD takes into consideration the transmission limitations an in particular the limits indicated below: 230 kv Line name Line Number Bus From Bus To Ckt# Thermal Limit MVA Loading Limit % of Thermal Costa Sur Manati COSTA SUR230_96 MANATI 230_ % 300 Aguirre Aguas Buenas AGUIRRE 230_106 AGUBUENAS230_ % 416 Aguirre Aguas Buenas AGUIRRE 230_106 AGUBUENAS230_ % 416 Costa Sur Mayagüez COSTA SUR230_96 MAYA TC 230_ % 300 Aguirre Costa Sur COSTA SUR230_96 AGUIRRE 230_ % 139 Actual Limit MVA RETIREMENTS: Given the working period ( ) a number of units were noted as retired. These were initially set and then revised by PREPA later the in evaluation process. The following Units were modeled as retired for PSSP 1& 2 SJSP 7&8 SOUCO 1 to 4 Several GTs Page 48
49 PROMOD Renewable Models Thermal Modeling Impacts Heat Rates PREPA provided updates for almost all units Later adjustments were performed as some units did not perform as expected to reflect the onsite conditions. Fixed and Variable O&M Fixed O&M prices were adjusted for all units (per PREPA) Variable O&M prices were adjusted for all units (per PREPA) Maintenance Maintenance schedules were updated (per PREPA) Page 49
50 PREPA Renewable Energy Resources Integration Study Scenario Definition Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
51 Scenario I Expected Short Term Conditions Scenario I corresponds to the expected conditions in the system by 2015 and it is considered the Base Scenario. The scenario assumes the load as observed in PREPA during 2011 and it assumes that there is a recovery of the island industrial and economic activity. Natural Gas availability is considered to be limited to Costa Sur, hence in addition to Ecoelectrica, the generating units Costa Sur 5&6 are expected to be generating using natural gas (80% natural gas / 20% bunker). The scenario considers the renewable generation indicated previously (884.2 MW installed) and 64 MW of Net-metering. Page 51
52 Scenario II Evaluation of Storage This scenario corresponds to the expected conditions in the system by 2017 or 2018 and they are considered medium term sensitivities. The load is assumed to be the same as 2015 (Scenario I). Natural gas is expected to become available in Aguirre and in the north of the island, hence the following units are expected to be converted to natural gas: Name Short Name Unit Number Category Startup Fuel AGUIRRE COMBINED CYCLE 1 C.CYCLE 1 STEAM Natural Gas - Aguirre AGUIRRE COMBINED CYCLE 2 C.CYCLE 2 STEAM Natural Gas - Aguirre AGUIRRE STEAM 1 AGUIRRE 1 STEAM Natural Gas - Aguirre AGUIRRE STEAM 2 AGUIRRE 2 STEAM Natural Gas - Aguirre PSSP 3 PSSP 3 STEAM Natural Gas Norte PSSP 4 PSSP 4 STEAM Natural Gas Norte SAN JUAN COMBINED CYCLE 5 CC SJUAN 1 STEAM Natural Gas Norte SAN JUAN COMBINED CYCLE 6 CC SJUAN 2 STEAM Natural Gas Norte SJSP 10 SJSP 10 STEAM Natural Gas Norte SJSP 9 SJSP 9 STEAM Natural Gas Norte Page 52
53 Scenario II Evaluation of Storage 12% Penetration is required and more projects need to be added, largely solar. The following table shows the determination of the additional PV required (note Net-metering not considered only PPOA) Current Target Total PV + WTG 1,890, ,317, Less net-metering 126, , PPOA 1,763, ,190, Penetration 9.66% 12.00% Additional Required 426, In order to produce the 427 GWh from PV, approximately 235 MW of PV generation with a profile similar to the average PV production in Puerto Rico. This generation was added in a strong bus in the north for which we selected Bayamon 230 kv Net-Metering is expected to increase to 100 MW in this scenario Page 53
54 Scenario III Modeling Scenario III is identical to Scenario II but in order to accommodate the additional generation and achieve 12% energy penetration new combined cycles were added to the system. A coincident peak 1158 MW of renewable generation occurs when PV as necessary for reaching the 12% penetration is added to the system Coincident Max Energy MWh MW PPOA 1,763, Net Metering 126, Total 1,890, Additional PV 426, Total with new PV 2,317, ,158 With this we found that a feasible dispatch during Low Demand Day can be obtained with two combined cycles that had a) peak capacity of at least 320 MW each (640 MW total), b) that could be turned on and off daily c) a minimum operating value 128 MW (40% of max). Page 54
55 Scenario III Modeling It is important to note that the only gives indication that PROMOD would be able to find an acceptable solution integrating this level of renewable. The next step was to select the combined cycle plant (CCP) the following were considered and the SGT800 5x1 adopted due its flexibility and efficiency Similar machines can be obtained from various vendors. Page 55
56 PREPA Renewable Energy Resources Integration Study PROMOD Analysis: Scenario I Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
57 PROMOD Analysis Overview The PROMOD analysis was conducted for the various scenarios to capture the impacts of the renewable resources on existing thermal generation. Several key aspects are derived from the analysis are: Energy curtailment (dump energy) Unit cycling Impact of renewable generation variability Impact of errors in the renewable generation forecast Overall generation costs. Before we enter into the details of Scenario I it is important to discuss some of these key aspects. Page 57
58 PROMOD Analysis Energy Curtailment & Emergency Power PROMOD utilizes the term Dump (Curtailment)& Emergency Power to allow for successful solutions. Dump reflects a condition where more power than load is dispatched due to restrictions in the case, Curtailment of generation is required; curtailing renewable generation and/or reducing power plants to their emergency lower limits. Emergency Power reflects the condition where not enough generation is dispatched, therefore more generation dispatch is required; or load shedding in practice. This occurs because of the inflexibilities or insufficiencies build into the models. It should be noted that typically when there is only conventional generation, the inequalities above are rare. Page 58
59 PROMOD Analysis Energy Curtailment & Emergency Power The PREPA model produced conditions where Energy Curtailment is needed to balance the generation to load. The PREPA model produced these conditions because of two factors: Renewable generation is modeled as Must Run according to the hourly profiles. Conventional generation can be dispatched but is set up to maintain required levels of reserve, running times and ramping. These conditions do occur in real time, however, operators resort to curtailing generation as needed to maintain the system balance, stability and security. Page 59
60 PROMOD Analysis Energy Curtailment & Emergency Power Curtailment of Renewable Generation in the Industry This is a common occurrence in the industry ERCOT, SPS, PSCo, NSP, MISO, BPA and PJM have all experienced renewable curtailment There is a clear trend to within the industry to reduce curtailment of renewable resources which we expect to stabilize in the order of 2% to 3%. Page 60
61 PROMOD Analysis Energy Curtailment & Emergency Power If PREPA curtails renewable energy it has to pay for it, based on the energy that would have been produced based on the meteorological conditions during the time of the curtailment and the curtailed project production characteristics. This result is an increase in the price of the energy that is actually taken A 2% curtailment implies an increase in price of 2.04% or about 3.5 $/MWh. PREPA s Operation is committed to minimize this value, but as will be seen for larger levels of penetration it cannot be made zero. Page 61
62 PROMOD Analysis Unit Cycling Renewable Resources has high injection levels during the day and zero or very low injection levels at night This introduces the risk that the conventional generation fleet will exhibit a large number of starts and shutdowns (Cycling.) This is particularly noted in the steam generators in the fleet in this analysis This condition creates wear-and-tear, high operating costs and eventually outages on the steam generation; thus it is not a desired operating practice. Actions were taken to prevent excessive number of starts and stops on the steam generators in PREPA (discussed later) Page 62
63 PROMOD Analysis Renewable Variability Renewable variability introduces additional operations costs by forcing conventional units to deviate from optimal dispatches. To define how this impacts the system, the renewable resources were modeled as block generation across the entire year while maintaining the energy produced at each renewable site With the renewable resources defined as block sources the conventional generation is able to dispatch optimally The cost difference of the conventional generation between the renewable variable and block models provides an estimation of the cost of variability Impact of Variability of Renewable Resources Increased in production cost $36,078,136 Increased curtailment 4.22% Increased in average production cost $/MWH $1.60 More GT's on line hours Page 63
64 PROMOD Analysis Renewable Generation Forecast Error Impacts Generators are required to make day-ahead plans so that system security and economics can be maintained; Security Constrained Unit Commitment. This includes projections of renewable generators. Renewable forecasting errors increase with the forecasting horizon, having maximum impact on the day-ahead unit commitment. Large Forecasting errors result in Increased production costs due to deviation from optimal unit commitment and/or Increased curtailment; generation cannot be taken. Our study estimated the impact of forecast error using different methodologies to show how error may impact production costs and curtailment Page 64
65 PROMOD Analysis Scenario I The results of Scenario I and the required adjustments to the case are presented next. As will be seen two types of adjustments were required; to increase the minimum run time for the steam units to avoid excessive cycling and a reduction of the renewable generation to obtain reasonable levels of curtailment. These adjustments resulted in variations of the Scenario I which are presented and discussed. Page 65
66 PROMOD Analysis Scenario 1-0 This scenario corresponds to the initial run of Scenario I, without any adjustments. The case resulted in an excessive amount of cycling for economic reasons. As can be seen below where the Base Case only has the existing renewable projects, there was a large jump in the number of starts. Total Base Case I Scenario 1-O Forced / Sch Starts Economic Starts Total Forced / Sch Starts Economic Starts EcoElect AES CC SJUAN AGUIRRE 1& SOCO 5 & Aguirre CCP PSSP 3& SJSP 9& Cambalache Mayaguez GT's Hydro New CCP Page 66
67 PROMOD Analysis Scenario 1-1-0; Overview This scenario corresponds to the same conditions in previous scenario, but to achieve acceptable cycling, the minimum run time was increased to 720 hours for all the steam units. As will be shown next this change resulted in correct cycling of the steam generation, but there was important energy dump and the need to curtail renewable generation Page 67
68 PROMOD Analysis Scenario 1-1-0; Overview The tables below show that to match the generation with the load approximately 106 GWh have to be curtailed, most of it out of renewable generation, representing 5.63% of the energy and quite high. We also note that there is an small amount of thermal curtailment, but this can be absorbed using the emergency minimum of generators. Page 68
69 PROMOD Analysis Scenario Generation Results Ecoelectrica & AES base loaded however lower capacity factor than with existing renewable Similar situation for other large producers Aguirre & SOUCO. Note that the cost of these producers is lower than the cost of the renewable. Scenario Energy MWh Capacity Factor Costs $/MWh Energy MWh Base Case I Capacity Factor Base Case Costs $/MWh EcoElect 1 3,743, % $ ,982, % $76.46 AES 3,224, % $ ,402, % $94.24 CC SJUAN 1,848, % $ ,934, % $ AGUIRRE 1&2 4,053, % $ ,403, % $ SOUCO 5 & 6 5,246, % $ ,727, % $ Aguirre CCP 43, % $ , % $ PSSP 3&4 1,534, % $ ,537, % $ SJSP 9&10 888, % $ , % $ Cambalache 1, % $ , % $ Mayaguez 57, % $ , % $ GT's 5, % $ , % $ Hydro 126, % $ , % $0.00 Total 20,773,734 $ ,213,077 $ Net Metering 126,921 - PV 1,294, % $ , % $ WTG 468, % $ , % $ Total Renewable w/o netmetering 1,763, % $ , % $ Page 69 Case Total 22,664,234 22,563,801 $151.67
70 PROMOD Analysis Scenario Unit Cycling This case was designed to resolve the issue of unacceptable economic cycling of the units to values in line with their capabilities and minimize the wear and tear of the units. This objective was achieved as shown below where the Base Case, Scenario 1-0 and Scenario are compared. Total Base Case I Scenario 1-O Scenario 1-1-O Forced / Sch Starts Economic Starts Total Forced / Sch Starts Economic Starts Total Forced / Sche Starts EcoElect AES CC SJUAN AGUIRRE 1& SOCO 5 & Aguirre CCP PSSP 3& SJSP 9& OK X Cambalache Mayaguez OK GT's Hydro New CCP OK X Economic Starts OK OK OK Page 70
71 PROMOD Analysis Scenario Case Costs The Scenario with renewable generation results in a cost increase of US$ 77.3 million with respect of the Base Case. The reduction in conventional generation costs is not compensated by the increase in payments for the renewable generation. The table also shows the cost of volatility by comparing the cost of the case with an identical case where the renewable is dispatched as a base block (no volatility.) We see that this adds in the order of $ 36 million. Scenario Costs MM$ $/MWh Conventional Gen Cost 2,811,373, OK Block Costs 2,775,295, Cost of Renewable voltatility 36,078, X Renewable Gen Costs 312,003, Total Case Costs 3,123,376, Case with existing Renewable 3,046,147, Total Savings (Costs) (77,228,839) X Base Case Costs MM$ $/MWh Conventional Gen Cost 2,990,421, Renewable Gen Costs 55,726, Total Case Costs 3,046,147, Total Savings (Costs) Page 71
72 Number of times PROMOD Analysis Scenario 1-1-0: Renewable Volatility Another way to visualize the impact of the variability of the renewable generation is to compare the changes in the Net Load (Actual Load less Renewable) from one hour to the next with those of the Actual Load (i.e. true load supplied). The figure is an histogram showing the number of occurrences that the load changed a given amount in % from one hour to the next As can be observed in this figure the actual load has changes mostly concentrated from 10% to 8% while the Net Load has Changes from -12% to +12%. Hence greater volatility Gross Load Net Load 0 % Change over the hour Page 72
73 PROMOD Analysis Scenario Representative days. Maximum Load Day (Thursday - 08/13/2015) The demand is the red line shown at the very top of all the other displayed generation indicating that no curtailment is required. We note however that even in this day AES generation has to be reduced during some hours WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page 73
74 PROMOD Analysis Scenario Representative days. Minimum Daytime Load Day (Saturday - 01/03/2015): To serve the demand in the evening, enough conventional generation must be dispatched resulting in substantial excess during daytime requiring its curtailment. The load drops below the thermal output. However in this case the dispatchers can use the emergency limits; e.g. Costa Sur = 250 down to 200, Aguirre 1&2 230 down to 200. Renewable must be curtailed to resolve this between 5 am and 5 pm WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page 74
75 PROMOD Analysis Scenario Representative days. Maximum Renewable Day (Sunday - 04/05/2015): to allow for the amount of renewable, conventional generation must be off or at minimum levels between 8 am 3 pm. Ecoelectrica has an economic shutdown. The amount of conventional generation dispatched is necessary to cover the evening demand Part of the renewable generation has to be curtailed WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page 75
76 PROMOD Analysis Scenario Representative days. Maximum Dump Day (Friday - 04/24/2015): to allow for the amount of renewable, conventional generation must be off or at minimum levels between 7 am 3 pm. The amount of conventional generation dispatched is necessary to cover the evening demand Only renewable generation needs to be curtailed WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page 76
77 PROMOD Analysis Scenario Representative days. High Dump Day (Sunday - 10/25/2015): Defined as a day where the level of dump is above average and happens in multiple days. 6 am 3 pm generation exceeds demand and renewable generation must be curtailed. Conventional generation is at minimums but must be on-line to secure demand in the evening hours WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page 77
78 Curtailme nt as % of renewable energy PROMOD Analysis Scenario 1-1-0: Curtailment Reduction. The figure shows the renewable (blue) and total (red) curtailment reduction as Energy is being rejected from the case. We see that to achieve close to 2% curtailment almost 35% of the energy from renewable needs to be rejected, with a negative impact in achieving the required levels of penetration. There are diminishing returns for reductions beyond 3.4%, but this value is somewhat high. A balance must be found between curtailment and required penetration. 6.0% 5.0% 4.0% 3.0% 2.0% 1.0% Renewable Dump Total Dump PROMOD Calculated Dump Total PROMOD Calculated Dump Renewable only % Page % 0.0% 5.0% 10.0% 15.0% 20.0% 25.0% 30.0% 35.0% 40.0% 45.0% 50.0% % of Rejected Renewable Energy
79 PROMOD Analysis Scenario 1-1-0: Curtailment Reduction. The table below provides the details behind the curve above. Here we observe that with MW in projects the curtailment is slightly above 2 % (curtailment of renewable) and to go to the next step the curtailment is 1.92% but the projects retained are reduced by 50 MW and the penetration drops from 6.6% to 6.1%. Thus MW of renewable projects were retained, as shown in the next slide. Values Values Values Values Values Values Values Values Values MW Keept MW Rejected Penetration 9.66% 8.87% 8.66% 8.17% 7.68% 7.30% 6.59% 6.10% 5.65% Renewable Dump Original 102, , , , , , , , , Dump Reduction 0 28,537 34,722 47,512 58,575 65,496 75,370 80,723 84,798 New Dump 102, , , , , , , , , New Dump % new energy 5.4% 4.2% 4.0% 3.4% 2.9% 2.5% 2.0% 1.7% 1.5% Energy Rejected 0.0% 7.7% 9.6% 14.4% 19.2% 22.8% 29.7% 34.4% 38.8% Total Dump including termal as % renewable 5.63% 4.46% 4.19% 3.64% 3.13% 2.80% 2.33% 2.07% 1.86% PROMOD Calculated Dump Total 5.63% 2.99% 2.87% 2.55% 2.23% 2.04% PROMOD Calculated Dump Renewable only % 5.41% 2.76% 2.64% 2.26% 1.92% 1.70% Page 79
80 PROMOD Analysis Curtailment Reduction: Case 1-1-F. This case has the MW accepted for continued analysis and should have curtailment in the order of 2% of the renewable generation. Rejected Maintained NUM TECNOLOGIA Capacidad NUM TECNOLOGIA Capacidad 1 Solar Fotovoltaica 20 Page 80 8 Solar Fotovoltaica 10 9 Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica 20 Total Eólica 10 3 Solar Fotovoltaica 20 4 Solar Fotovoltaica 57 7 Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Eólica Eólica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Solar Fotovoltaica Eólica Eólica Solar Fotovoltaica Solar Fotovoltaica 20 Total 579.4
81 PROMOD Analysis Scenario 1-1-F; Overview The tables below show that to match the generation with the load approximately 30 GWh have to be curtailed, most of it out of renewable generation, representing 2.26% of the energy as expected. We also note that there is an small amount of thermal curtailment, but this can be absorbed using the emergency minimum of generators. Peak MW MWH Load Factor Load 3, ,557, % Peak MW MWH Times Unserved PROMOD Unserved zero reserve Peak MW MWH % Dump renewable , % Renewable component , % Thermal component , % Reconciliation Load 22,557,867 Less not served - Plus energy dumped 34,321 Total Generation 22,592,188 Page 81
82 PROMOD Analysis Scenario 1-1-F Generation Results Ecoelectrica & AES again base loaded with lower capacity factor than in the Base Case. Similar situation for other large producers Aguirre & SOUCO. As before the cost of these producers is lower than the cost of the renewable. Energy MWh Scenario 1-1-F Capacity Factor Costs $/MWh Energy MWh Base Case I Capacity Factor Base Case Costs $/MWh EcoElect 1 3,875, % $ ,982, % $76.46 AES 3,308, % $ ,402, % $94.24 CC SJUAN 1,854, % $ ,934, % $ AGUIRRE 1&2 4,144, % $ ,403, % $ SOUCO 5 & 6 5,406, % $ ,727, % $ Aguirre CCP 49, % $ , % $ PSSP 3&4 1,523, % $ ,537, % $ SJSP 9&10 889, % $ , % $ Cambalache 1, % $ , % $ Mayaguez 62, % $ , % $ GT's 5, % $ , % $ Hydro 126, % $ , % $0.00 Total 21,248,451 $ ,213,077 $ Net Metering 126,921 - PV 748, % $ , % $ WTG 468, % $ , % $ Total Renewable w/o netmetering 1,216, % $ , % $ Page 82 Case Total 22,592,189 22,563,801 $151.67
83 PROMOD Analysis Scenario 1-1-F Unit Cycling Scenario 1-1-F has the same adjustments as to prevent excessive starts and as before this results in acceptable levels of economic cycling of units. Total Base Case I Scenario 1-1-O Scenario 1-1-F Forced / Sch Starts Economic Starts Total Forced / Sche Starts Economic Starts Total Forced / Sche Starts EcoElect AES CC SJUAN AGUIRRE 1& SOCO 5 & Aguirre CCP PSSP 3& SJSP 9& Cambalache Mayaguez GT's Hydro New CCP Economic Starts Page 83
84 PROMOD Analysis Scenario 1-1-F Case Costs The Scenario with renewable generation results in a cost increase of US$ 24 million with respect of the Base Case with limited (exiting) renewable generation. Note that as before the reduction in conventional generation costs is not compensated by the increase in payments to the renewable generation providers The volatility in this case is less than in as shown next. Scenario 1-1-F Base Case I MM$ $/MWh MM$ $/MWh Conventional Gen Cost 2,859,314, Conventional Gen Cost 2,990,421, Renewable Gen Costs 210,655, Renewable Gen Costs 55,726, Total Case Costs 3,069,969, Total Case Costs 3,046,147, Case w/o Renewable 3,046,147, Total Savings (Costs) (23,821,392) Total Savings (Costs) Page 84
85 Number of times PROMOD Analysis Scenario 1-1-F: Renewable Volatility Reviewing the variability of the Net Load (Actual Load less Renewable Generation) we observe in this case a similar distribution in the histogram as PREPA s load, The Actual and Net load has changes mostly concentrated from 10% to 8% Gross Load Net Load % Change over the hour Page 85
86 PROMOD Analysis Scenario 1-1-F Representative days. Maximum Load Day (Thursday - 08/13/2015) Load-generation for is balanced (no curtailment or emergency power necessary). AES, Ecoelectrica & San Juan CC at or near max capacity WTG PV 2500 Hydro GT's Scenario WTG Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand EcoElect 1 Demand Page 86
87 PROMOD Analysis Scenario 1-1-F Representative days. Maximum Renewable Day (Sunday - 04/05/2015): Similar to Scenario 1-1-O, there is some level of curtailment on renewable, but in this case Ecoelectrica was not shut down for economic reasons WTG PV Case Hydro GT's Mayaguez Cambalache WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN 1000 SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN 500 AES EcoElect AES EcoElect 1 Demand Demand Page 87
88 2500 PROMOD Analysis Scenario 1-1-F Representative days. Maximum Dump Day / Minimum Demand Day (Saturday - 01/03/2015): We observe that the plots appear to be very much the same except that the renewable peak is shaved (lower) in the Scenario 1-1-F. There is some thermal generation dump, but this can be handled by the emergency lower limits. Case Minimum Demand Day 2000 WTG PV Hydro GT's 1500 Mayaguez Cambalache SJSP 9&10 PSSP 3& Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN 500 AES EcoElect 1 Demand Case Max Dump 2500 WTG PV Hydro 2000 GT's Mayaguez Cambalache 1500 SJSP 9&10 PSSP 3&4 Aguirre CCP 1000 SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES 500 EcoElect 1 Demand Page 88
89 PROMOD Analysis Scenario 1-1-F Representative days. High Dump Day (Sunday - 10/25/2015): Defined as a day where the level of dump is above average and happens in multiple days. 6 am 2 pm generation exceeds demand and renewable generation must be curtailed. The dump is much less than in scenario Conventional generation is at minimum but must be on-line to serve demand in the evening hours 3000 Case WTG PV Hydro 1000 GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP 500 SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Demand Page 89
90 PROMOD Analysis Scenario 1-1-F - Impact of Errors in the Forecast Objective: determine what different levels of errors do to the performance of the system in terms of operating costs and curtailment Option 1 Assume a percentage of error either over or under the forecast Option 2 Shift the forecast forward or backward by one hour Option 3 Perform a Monte Carlo simulation Option 1: modeling (8% lower production) shows a net cost of $12. 3million or 8% higher production has the impact of 0.7% higher curtailment. There is a reduction in costs. Option 1 Single extreme value + => more energy - => less energy -8% 2 Error in forecast timing by 1 hour Max Min 3 Monte Carlo (uniform ditribution) Max / Min 8% -8% Option Selected 1 Option 1 Single extreme value + => more energy - => less energy 8% 2 Error in forecast timing by 1 hour Max Min 3 Monte Carlo (uniform ditribution) Max / Min 8% -8% Option Selected 1 Net Costs 12,030, Curtailed Energy 0.00% Net Costs (12,430,663.72) Curtailed Energy 0.68% Page 90
91 PROMOD Analysis Scenario 1-1-F - Impact of Errors in the Forecast Impact of Errors in the Forecast Option 2 indicates that there would be a reduction in costs by advancing the forecast by one our. The curtailment is increased by 0.29%. The a cost increase happens if the production is shifted back by one hour Errors in Forecast Results Option 1 Single extreme value + => more energy - => less energy -8% 2 Error in forecast timing by 1 hour Max Min 3 Monte Carlo (uniform ditribution) Max / Min 8% -8% Option Selected 2 Net Costs (7,661,747.26) Curtailed Energy 0.29% Page 91
92 PROMOD Analysis Scenario 1-1-F Impact of Errors in the Forecast Option 3 shows a net cost reduction of $21,752. and an increase in curtailment of 0.19%. Errors in Forecast Results Option 1 Single extreme value + => more energy - => less energy -8% 2 Error in forecast timing by 1 hour Max Min 3 Monte Carlo (uniform ditribution) Max / Min 8% -8% Option Selected 3 Net Costs (21,752.51) Curtailed Energy 0.19% The most significant impact of errors in the forecast is the increase in curtailment that could happen if the renewable generation produced more than what was forecasted and reflected in the unit commitment. Page 92
93 PREPA Renewable Energy Resources Integration Study Scenario II Storage Case Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
94 PROMOD Analysis Scenario II: Formulation Scenario II is intended to represent the conditions during 2017 or 2018, when PREPA is expected to have 12% of its load supplied from renewable resources and natural gas is available at Aguirre and in the north of the island. The scenario also contains a larger amount of net-metering (100MW) The key element of Scenario II is that to allow 12% penetration with PREPA s current generating fleet a large storage facility is added. Most typical types of storage devices; pump storage or compressed air storage; are not feasible for Puerto Rico, thus the analysis is based on Battery Energy Storage Systems (BESS.) However if other technologies were available the study is still valid. Page 94
95 Total Curtailment (% of renewable) PROMOD Analysis Scenario II : BESS Selection Battery Energy Storage Systems (BESS) are expensive hence we minimized its size. We did not attempt to shift energy between the days, but it was delivered to the load as soon as the conditions allowed; delaying it did not compensate the costs 4.5% Some level of curtailment has to be accepted. 4,000 GWh (0.6% curtailment) and 1,750 GWh (2.1% curtailment selected for the evaluation. Both 240 MW. 4.0% 3.5% 3.0% 2.5% 2.0% 1.5% 1.0% 0.5% 0.0% Size of Storage GWh Page 95
96 PROMOD Analysis Scenario II: BESS Costs Energy Storage Costs We reviewed various sources for the costs of BESS and selected the minimum cost found as we expect significant economies of scale. Production Cost Savings by the releasing of the energy were accounted for. Cost annualized using 9% discount rate and a conservative 20 years life (15 is more typical) 4000 MWh Storage Parameters and Costs Cost* Unit $/kwh or $/kw MWh or MW MM$ Energy Capacity Total Annuity with 20 years 9% 183 O&M Fixed $/KW Total Annual Cost Annual Savings Net Cost MWh Storage Parameters and Costs Cost* Unit $/kwh or $/kw MWh or MW MM$ Energy Capacity Total Annuity with 20 years 9% 85 O&M Fixed $/KW Total Annual Cost 87.0 Annual Savings Net Cost Storage Cap Limit 240 Curtailment MWh 13, Curtailment % or renewable 0.6% Storage Cap Limit 240 Curtailment MWh 50, Curtailment % of renewable 2.1% Page 96
97 PROMOD Analysis Scenario II: Overview The tables below show the energy production and curtailment for each of the alternatives studied. We note effect of larger storage on the curtailment MWh 1750 MWh Peak MW MWH Load Factor Load 3, ,557, % Peak Load MW MWH Factor Load 3, ,557, % Page 97 Peak MW MWH Times Unserved PROMOD Unserved zero reserve Peak MW MWH Times Dump renewable , % Reconciliation Load 22,557,867 Less not served 0 Plus energy dumped 13,133 Plus left in storage 0.00 Total Generation 22,571,000 Peak MW MWH Times Unserved PROMOD Unserved zero reserve Peak MW MWH Times Dump renewable , % Reconciliation Load 22,557,867 Less not served - Plus energy dumped 50,822 Plus left in storage - Total Generation 22,608,689
98 PROMOD Analysis Scenario II; 4000 GWH Generation Results We observe the same results as in the previous cases; the generation reduction on generators whose cost is less than the price paid for the renewable. Base Case II; is current fleet converted to gas and existing renewable generation Note the increase in the cost of Ecoelectrica and AES due to the fixed payments over less energy. Scenario II - 4,000 MWh Energy MWh Capacity Factor Costs $/MWh Energy MWh Base Case II Capacity Factor Costs $/MWh EcoElect 1 3,516, % $ ,993, % $84.23 AES 3,128, % $ ,409, % $98.35 CC SJUAN 2,371, % $ ,577, % $ AGUIRRE 1&2 4,490, % $ ,311, % $ SOUCO 5 & 6 3,943, % $ ,923, % $ Aguirre CCP 801, % $ , % $ PSSP 3&4 1,259, % $ ,258, % $ SJSP 9&10 525, % $ , % $ Cambalache 1, % $ , % $ Mayaguez 12, % $ , % $ GT's 7, % $ , % $ Hydro 126, % $ , % $0.00 Total 20,183,433 $ ,212,571 $ Net Metering 197, % PV 1,721, % $ , % $ WTG 468, % $ , % $ Total Renewable 2,190, % $ , % $ Page 98 Case Total 22,571,001 22,563,295
99 PROMOD Analysis Scenario II 1750 GWh; Generation Results Same results as the case above; most of the generation reduction happens in generators whose cost is less than the price paid for the renewable. Scenario II - 1,750 MWh Energy MWh Capacity Factor Costs $/MWh Energy MWh Base Case II Capacity Factor Costs $/MWh EcoElect 1 3,531, % $ ,993, % $84.23 AES 3,133, % $ ,409, % $98.35 CC SJUAN 2,374, % $ ,577, % $ AGUIRRE 1&2 4,500, % $ ,311, % $ SOUCO 5 & 6 3,947, % $ ,923, % $ Aguirre CCP 802, % $ , % $ PSSP 3&4 1,259, % $ ,258, % $ SJSP 9&10 525, % $ , % $ Cambalache 1, % $ , % $ Mayaguez 12, % $ , % $ GT's 7, % $ , % $ Hydro 126, % $ , % $0.00 Total 20,221,123 $ ,212,571 $ Net Metering 197, % PV 1,721, % $ , % $ WTG 468, % $ , % $ Total Renewable 2,190, % $ , % $ Case Total 22,608,690 22,563,295 Page 99
100 PROMOD Analysis Scenario II Unit Cycling The cycling of the units is increased, note that there were 5 economic stops for Ecoelectrica, but this is within the capabilities of the units. Same case for Aguirre CCP Base Case II Scenario II Scenario III Total Forced / Sche Starts Economic Starts Total Forced / Sche Starts Economic Starts Total Forced / Sche Starts Economi Starts EcoElect AES CC SJUAN AGUIRRE 1& SOCO 5 & Aguirre CCP PSSP 3& SJSP 9& Cambalache Mayaguez GT's Hydro New CCP Page 100
101 PROMOD Analysis Scenario Case Costs This Scenario resulted in a significant increase in costs (169 to 260 million per year) due to the investment on the storage and the cost to be paid for the renewable that is not compensated by the reduction in operating costs. Scenario II - 4,000 MWh Base Case II MM$ $/MWh MM$ $/MWh Conventional Gen Cost $2,519,222,376 $ Conventional Gen Cost $2,736,575,761 $ StorageAnnual Costs $128,434,743 Renewable Gen Costs $403,333,646 $ Renewable Gen Costs $54,868,346 $ Total Case Costs $3,050,990,765 $ Total Case Costs $2,791,444,106 $ Case with existing Renewable $2,791,444,106 $ Total Savings (Costs) ($259,546,658) Scenario II - 1,750 MWh Base Case II MM$ $/MWh MM$ $/MWh Conventional Gen Cost $2,523,455,454 $ Conventional Gen Cost $2,736,575,761 $ StorageAnnual Costs $34,075,993 Renewable Gen Costs $403,333,646 $ Renewable Gen Costs $54,868,346 $ Total Case Costs $2,960,865,093 $ Total Case Costs $2,791,444,106 $ Case with existing Renewable $2,791,444,106 $ Total Savings (Costs) ($169,420,987) Page 101
102 Number of times PROMOD Analysis Scenario II The volatility in this case is higher than in any of the previous cases due to the impact of much higher renewable generation. The Net Load reaches values of up to 18% per hour (using as the base the previous hour load). In this case we identified that there was a change of 300 MW from one hour to the next However in this case the storage that has a capacity of 240 MW and that can react very quickly to changes in renewable generation, can mitigate if not completely eliminate the impacts of these fast changes Gross Load Net Load % Change over the hour Page 102
103 MW Storage MWh PROMOD Analysis Scenario II Representative days. Maximum Load Day (Thursday - 08/13/2015) Load-generation for is balanced (no curtailment or emergency power necessary) The storage was not necessary so both cases have the same curve. Scenario From Storage & Add PV WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOUCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Demand + Storage Storage Page
104 MW Storage MWh PROMOD Analysis Scenario II Representative days. Minimum Day time load with (Saturday 01/03/2017) Storage is necessary to prevent curtailment. The storage did not go over 1750 MWh, so both cases have the same results & 1750 MWh ,138 MWh Load + flows to storage 1200 From Storage 2000 To Storage 1000 From Storage & Add PV WTG PV Hydro 1500 Load 800 GT's Mayaguez Cambalache SJSP 9&10 Energy in storage 600 PSSP 3&4 Aguirre CCP 1000 SOUCO 5 & AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Demand + Storage Storage Page 104
105 MW MW Storage MWh Storage MWh PROMOD Analysis Scenario II Representative days. Maximum Renewable Day (Sunday 04/05/2017) Storage is necessary to prevent curtailment and reaches its maximum capacity Note the significant difference in curtailment due to the difference in limits To Storage 4000 MWh 4000 MWh From Storage Energy in storage curtailment ,750 MWh 3000 From Storage & Add PV To Storage WTG PV MWh Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOUCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Demand + Storage Storage curtailment Energy in storage 2000 From Storage From Storage & Add PV WTG PV Hydro GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 Aguirre CCP SOUCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Demand + Storage Storage Page 105
106 MW MW Storage MWh Storage MWh PROMOD Analysis Scenario II Representative days. Maximum Dump Day (Sunday 01/18/2017) Storage again is necessary to prevent curtailment and reaches its maximum capacity Note that in both cases there is some energy leftover in storage from the previous day. This limits the absorption during this day To Storage MWh 4000 MWh From Storage curtailment ,750 MWh 3000 From Storage & Add PV 3500 WTG To Storage PV 1750 MWh 2500 Hydro 3000 GT's Mayaguez Cambalache SJSP 9&10 PSSP 3&4 curtailment 2000 From Storage 1800 From Storage & Ad 1600 WTG PV Hydro 1400 GT's Mayaguez 1200 Cambalache SJSP 9& PSSP 3& Energy in storage Aguirre CCP SOUCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Demand + Storage Storage Energy in storage Aguirre CCP SOUCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Demand + Storage Storage Page
107 PREPA Renewable Energy Resources Integration Study Scenario III : Combined Cycle Addition Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
108 PROMOD Analysis Scenario III Scenario III has the same conditions as Scenario II, but in order to achieve the 12% penetration level, two new combined cycle plant (SGT800 5x1 ACC) are added to the system. As presented previously these units have the ability to move from 35 MW to 334 MW at 30MW/min. A full description of the additional PV for 12% penetration and the new combined cycle unit were provided earlier in this presentation. Page 108
109 PROMOD Analysis Scenario III; Overview The tables below show that to match the generation with the load approximately 56 GWh have to be curtailed, all of it renewable generation, representing 2.35% of the energy. This is considered reasonable. Load, Dump & Unserved Energy Results Peak Load MW MWH Factor Load ,557, % Peak MW MWH Times Unserved PROMOD Unserved zero reserve Peak MW MWH Times Dump renewable , % Renewable Component , % Thermal Component % Reconciliation Load 22,557,867 Less not served 0 Plus energy dumped 56,372 Total Generation 22,614,239 Check OK Page 109
110 PROMOD Analysis Scenario III Generation Results As before there was a significant reduction in the generation of more efficient generation. However in this case the new CCP s with a capacity factor of 50% are providing relatively cheap energy. Note that SJSP was not dispatched in the case and almost no GT s Energy MWh Scenario III Capacity Factor Costs $/MWh Energy MWh Base Case II Capacity Factor Costs $/MWh EcoElect 1 3,912, % $ ,993, % $84.23 AES 3,383, % $ ,409, % $98.35 CC SJUAN 2,430, % $ ,577, % $ AGUIRRE 1&2 3,393, % $ ,311, % $ SOUCO 5 & 6 3,466, % $ ,923, % $ Aguirre CCP 272, % $ , % $ PSSP 3&4 278, % $ ,258, % $ SJSP 9& % $ , % $ Cambalache 0 0.0% $0.00 4, % $ Mayaguez 2, % $ , % $ New_CC 2,948, % $ % $0.00 GT's % $ , % $ Hydro 126, $ , % $0.00 Total 20,215,294 $ ,212,571 $ PV 1,886, % $ , % $ WTG 512, % $ , % $ Ttl Renewable (incl netmeter) 2,398, % $ , % $ Case Total 22,614,232 22,563,295 Page 110
111 PROMOD Analysis Scenario 1-1-F Unit Cycling This case has increased level of economic starts/shutdowns when compared with the base case but basically on Aguirre CCP s GT in addition to 4 cycles at Ecoelectrica. Base Case II Scenario II Scenario III Total Forced / Sche Starts Economic Starts Total Forced / Sche Starts Economic Starts Total Forced / Sche Starts Economic Starts EcoElect AES CC SJUAN AGUIRRE 1& SOCO 5 & Aguirre CCP PSSP 3& SJSP 9& Cambalache Mayaguez GT's Hydro New CCP Page 111
112 PROMOD Analysis Scenario III Case Costs In this case the operating costs had an important reduction due to the entry of the combined cycle. Therefore it is necessary to add to the case the cost of this investment which was added as a fixed annual value assuming a life 25 years and a discount rate of 9%. The capital was assumed to be in the order of $ 1,100 per kw all in installed The tables below show the results for this scenario, where we note that it resulted in an increase in costs of approximately $ 61 million assuming Natural Gas. If LFO # 2 is required the cost will be higher. Scenario III Base Case II MM$ $/MWh MM$ $/MWh Conventional Gen Cost 2,363,109, Conventional Gen Cost 2,736,575, CCP Annual Costs 83,119,148 Renewable Gen Costs 406,744, Renewable Gen Costs 54,868, Total Case Costs 2,852,973, Total Case Costs 2,791,444, Case w/o Renewable 2,791,444, Total Savings (Costs) (61,528,903) Page 112
113 -18.0% -17.0% -16.0% -15.0% -14.0% -13.0% -12.0% -11.0% -10.0% -9.0% -8.0% -7.0% -6.0% -5.0% -4.0% -3.0% -2.0% -1.0% 0.0% 1.0% 2.0% 3.0% 4.0% 5.0% 6.0% 7.0% 8.0% 9.0% 10.0% 11.0% 12.0% 13.0% 14.0% 15.0% 16.0% 17.0% 18.0% Number of times PROMOD Analysis Scenario III - Volatility The volatility of this case is similar to that of Scenario II and it is higher than that observed in any of the other cases. However, in this case the new CCP (668 MW) can completely mitigate this extra effect it is the main machine that will be following the variations in the renewable resource as shown in the next section Gross Load Net Load % Change over the hour Page 113
114 PROMOD Analysis Scenario III Maximum Load Day (Thursday -08/13/2015): Ecoelectrica, AES, San Juan CC and Costa Sur 5&6 are at or very near maximum output through the day. Aguirre 1&2 is also very close to its maximum. The bulk of the reduction to accommodate for the renewable generation is provided by the new CCP s as well as the evening supply WTG PV Hydro GT's Mayaguez Cambalache New CCP SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page
115 PROMOD Analysis Scenario III Maximum Dump Day (02/22/2015 Sunday ): The new CCP was brought down to zero during the curtailment and Ecoelectrica was off. The balance of the generation was low cost, necessary for the evening peak and it was at the minimum WTG PV Hydro GT's Mayaguez Cambalache New CCP SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page 115
116 PROMOD Analysis Scenario III Minimum Daytime Load Day ( Saturday 01/03/2015): There is an small amount of curtailment before Aguirre was turned off WTG PV Hydro GT's Mayaguez Cambalache New CCP SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page 116
117 PROMOD Analysis Scenario III Maximum Renewable Day (Sunday - 04/05/2015): Necessary to curtail the renewable between about 7:00 am through about 3:00 pm. The new CCP is brought down to its minimum during the curtailment. Ecoelectrica was off WTG PV Hydro GT's Mayaguez Cambalache New CCP SJSP 9&10 PSSP 3&4 Aguirre CCP SOCO 5 & 6 AGUIRRE 1&2 CC SJUAN AES EcoElect 1 Demand Page
118 PREPA Renewable Energy Resources Integration Study Intra-Hour Modeling Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
119 05:02 AM 05:45 AM 06:28 AM 07:12 AM 07:55 AM 08:38 AM 09:21 AM 10:04 AM 10:48 AM 11:31 AM 12:14 PM 12:57 PM 01:40 PM 02:24 PM 03:07 PM 03:50 PM 04:33 PM 05:16 PM 06:00 PM 06:43 PM Intra-hour modeling The objective is to bridge the gap between long term stability assessment and the hourly assessment performed by PROMOD. Renewable generation is modeled in 10 minute intervals The analysis is done with an auxiliary program called PAT that reads PROMOD results and evaluates the behavior inside selected hours. Several critical hours were evaluated in detail. April 15 2:00 pm 6:00 pm March 11 11:00 am 1:00 pm April 13 9:00 am 11:00 am December 16 4:00 pm 6:00 pm WTG PV TOTAL Page 119
120 14:00 14:10 14:20 14:30 14:40 14:50 15:00 15:10 15:20 15:30 15:40 15:50 16:00 16:10 16:20 16:30 16:40 16:50 17:00 17:10 17:20 17:30 17:40 17:50 18:00 18:10 18:20 18:30 18:40 18:50 14:00 14:10 14:20 14:30 14:40 14:50 15:00 15:10 15:20 15:30 15:40 15:50 16:00 16:10 16:20 16:30 16:40 16:50 17:00 17:10 17:20 17:30 17:40 17:50 18:00 18:10 18:20 18:30 18:40 18:50 Intra-hour modeling Results The April 15th and hours between 2:00 pm and 6:00 pm and December 16th and hours between 4 and 6 pm were the most critical, On April 15 th the thermal units available had an aggregated 44 MW/minute ramping capability to meet a maximum requirement of 17 MW/minute resulting from the load and renewable resources On December 16 th the generation available was 38 MW/min for a ramp requirement of 19 MW/min. Ramp Capability Upper Limit SOUCO 6 SOUCO SAN JUAN COMBINED CYCLE 2 SAN JUAN COMBINED CYCLE MAYAGUEZ GT 3 MAYAGUEZ GT 2 MAYAGUEZ GT 1 AGUIRRE STEAM_2 AGUIRRE STEAM_1 TOTAL MOVING THERMAL 0 Ramp Capability Lower Limit -20 ACTUAL RAMP MW/MINUTE UP RAMP MW/MINUTE CAPABILITY DOWN RAMP MW/MINUTE CAPABILITY MAX CAPACITY OF MOVING UNITS 500 MIN CAPACITY OF MOVING UNITS Page 120
121 PROMOD Analysis Summary of Results & Conclusions Base Case Scenario I Scenario I-O Scenario I-1-O Scenario I-1-F Base Case Scenario II & III Scenario II 1750 MWh Scenario II 4000 MWh Scenario III Total PREPA Generation (net of dump) 22,557,867 22,430,946 22,430,946 22,557,867 22,360,462 22,360,462 22,360,462 Energy Dump / Curtilment 0.67% 5.41% 2.26% 1.56% 2.32% 0.60% 2.35% Renewable Generation in Case Renewable Concident Peak MW Net-Metering Capacity in case MW PPOA Capacity in case MW Renewable MWh (includes net-metering) 350, ,890, ,343, , ,387, ,387, ,398, Renewable MWh (only PPOA) 350, ,763, ,190, ,190, ,190, Penetration 1.92% 9.66% 6.47% 1.92% 12.00% 12.00% 12.00% Other investments 240 MW BEES / 1750 MWh 240 MW BEES / 4000 MWh 2x334 MW CCP Operating Costs Conventional 2,745,921,490 2,566,873,209 2,614,814,284 2,736,575,761 2,523,455,454 2,519,222,376 2,363,109,426 Renewable 55,726, ,003, ,157,564 54,868, ,333, ,333, ,744,436 Storage or CCP carrying value 34,075, ,434,743 83,119,148 Total 2,801,647,982 2,878,876,822 2,847,971,848 2,791,444,106 2,960,865,093 3,050,990,765 2,852,973,009 Cost in $/MWh Number of cycles for economic reasons EcoElect AES CC SJUAN AGUIRRE 1& SOUCO 5 & Aguirre CCP PSSP 3& SJSP 9& Cambalache Mayaguez GT's Hydro New CCP 6 Total Page 121
122 PREPA Renewable Energy Resources Integration Study Conclusions Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
123 Summary of Results & Conclusions PREPA s system in its planned 2015 configuration and generating fleet can accept up to 580 MW of renewable generation, split in 160 MW of wind turbine generation and 420 of Photovoltaic generation,with an acceptable levels of curtailment (2.26%.) This results are based on an assumed peak demand of 3,300 MW, lower values may affect this result. The renewable penetration in this case is 6.6 % of the sales. If net metering projects are allowed to exceed 64 MW, the actual system s limit to manage renewable projects would be reduced to penetration levels below 580 MW. The total PPOA renewable generation limit (580 MW) already includes the existing plants, AES Ilumina, Pattern, and Punta Lima (121 MW). When the payments for the renewable generation are included the cost of serving the load are higher than with the existing system ($ 23 million/yr.). Page 123
124 Summary of Results & Conclusions PREPA s system was found stable both during short term and long term dynamic stability assessments with renewable generation up to 884 MW. The renewable generation projects to comply with PREPA s Minimum Technical Requirements. PREPA should modify its MTR to require the renewable generation to contribute to frequency regulation from its storage even when the project is being dispatched at the PPOA contractual values. PREPA should review its secondary regulation requirements to maintain the larger reserve resulting of a) 50% of the renewable generation on line or b) 200 MW (current practices.) The under-frequency load shedding scheme is necessary to maintain the stability of the system under various events. Page 124
125 Summary of Results & Conclusions 12 % penetration can be achieved using storage to manage the energy that could not be delivered to the load to be released during the night peak. However given the high cost of the storage options available, for Puerto Rico, this option it is not considered economic at this time; $ 169 million / yr over the costs of supplying the system with conventional generation and the existing levels of renewable (Base Case). We note that this case has 2.32% of curtailment; if less curtailment is to be achieved the cost increase very rapidly Page 125
126 PROMOD Analysis Summary of Results & Conclusions Two new combined cycle plants (2 x 334 MW) that can ramp very fast and are flexible with the capability of cycling every day can accommodate 12% penetration % curtailment was reached, which is considered acceptable. However when the capital payments for the CCP are considered the case is more costly than the base case in $ 61 million/ yr. A total of 100 MW of Net Metering was included in Scenario II and III, which is the expected level of penetration for Increasing the total level of Net-Metering would reduce the total amount of PPOA renewable generation that can be integrated to PREPA s system. This combined cycle would require at least 5 years to commissioning for permitting, engineering and construction. In summary PREPA should be able to integrate into its system up to 580 MW of renewable generation with changes to its operating practices, provided that this generation complies 100% with PREPA s MTR. Page 126
127 PREPA Renewable Energy Resources Integration Study Discussion Restricted Siemens Industry, Inc All rights reserved. Answers for infrastructure and cities.
USER INFORMATION 18.0
USER INFORMATION 18.0 Page 1 of 9 The following section contains items of information for Resellers & CLECs to use for communication purposes to their end users. Holidays The following is a list of PRTC
Energy Storage for Renewable Integration
ESMAP-SAR-EAP Renewable Energy Training Program 2014 Energy Storage for Renewable Integration 24 th Apr 2014 Jerry Randall DNV GL Renewables Advisory, Bangkok 1 DNV GL 2013 SAFER, SMARTER, GREENER DNV
Natural Gas Diversification Strategy for PREPA GOVERNMENT DEVELOPMENT BANK FOR PUERTO RICO
Natural Gas Diversification Strategy for PREPA GOVERNMENT DEVELOPMENT BANK FOR PUERTO RICO Agenda 1 Importance of Diversifying to Natural Gas 2 Natural Gas Diversification Strategy 2 Currently, Puerto
Form TRB 200-M Statistical Highlights of the Telecommunication Industry Month and Year
Statistical Highlights of the Telecommunication Industry Month and Year Block 1: Company Identification 100 Certification number provided by the Board: JRT - Cert or JRT- CMRS 101 Legal name of reporting
Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid
Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy
CHAPTER 1 INTRODUCTION
CHAPTER 1 INTRODUCTION Power systems form the largest man made complex system. It basically consists of generating sources, transmission network and distribution centers. Secure and economic operation
Multi-Faceted Solution for Managing Flexibility with High Penetration of Renewable Resources
Multi-Faceted Solution for Managing Flexibility with High Penetration of Renewable Resources FERC Technical Conference Increasing RT & DA Market Efficiency Through Improved Software June 24 26, 2013 Nivad
Grid Operations and Planning
Grid Operations and Planning Report Kent Saathoff ERCOT Board of Directors April 20, 2010 Kent Content Summary March 2010 Operations Peak Demand: Actual vs. Forecast On-line Resources: Total at Peak and
Methodology for Merit Order Dispatch. Version 1.0
Methodology for Merit Order Dispatch Version 1.0 25 th April 2011 TABLE OF CONTENTS 1. OBJECTIVES... 1 2. ROADMAP FOR IMPLEMENTATION... 1 3. DEFINITIONS... 3 4. OPERATIONS PLANNING... 3 4.1. General Considerations...
Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3
Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3 Basics of Power systems Network topology Transmission and Distribution Load and Resource Balance Economic Dispatch Steady State System
HEATWAVE 13 17 JANUARY 2014. DATE: 26 January 2014
PREPARED BY: Systems Capability DATE: 26 January 2014 Contents 1 INTRODUCTION... 3 2 RESERVE LEVELS DURING THE HEATWAVE... 3 2.1 EVENTS ON THE NEM POWER SYSTEM CONTRIBUTING TO LOW RESERVES... 4 2.2 RISKS
Grid of the Future. Integration of Renewables Energy Storage Smart Grid. Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations
Grid of the Future Integration of Renewables Energy Storage Smart Grid Presentation by David Hawkins Lead Renewables Power Engineer Grid Operations Grid of the Future Current Power System Gen. Trans. Dist.Cust.
Field experience and best practices in managing MW scale Li-ion energy storage systems coupled to large wind and solar plants
Field experience and best practices in managing MW scale Li-ion energy storage systems coupled to large wind and solar plants Michael Lippert & Jesus Lugaro IRES Düsseldorf 1 March 215 Summary 1. Characterization
VOLATILITY AND DEVIATION OF DISTRIBUTED SOLAR
VOLATILITY AND DEVIATION OF DISTRIBUTED SOLAR Andrew Goldstein Yale University 68 High Street New Haven, CT 06511 [email protected] Alexander Thornton Shawn Kerrigan Locus Energy 657 Mission St.
Flexible Capacity Planning for Renewable Integration CEF Topical White Paper Jeremy Hargreaves, Elaine Hart, Ryan Jones, Arne Olson E3
July 15, 2013 Flexible Capacity Planning for Renewable Integration CEF Topical White Paper Jeremy Hargreaves, Elaine Hart, Ryan Jones, Arne Olson E3 Problem Statement For California, meeting an economy-
Value of storage in providing balancing services for electricity generation systems with high wind penetration
Journal of Power Sources 162 (2006) 949 953 Short communication Value of storage in providing balancing services for electricity generation systems with high wind penetration Mary Black, Goran Strbac 1
General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System
General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System Direction Planification des actifs et expertise de transport February 2011 TABLE OF CONTENTS 1. CONDUCTING
Simulated PV Power Plant Variability: Impact of Utility-imposed Ramp Limitations in Puerto Rico
Simulated PV Power Plant Variability: Impact of Utility-imposed Ramp Limitations in Puerto Rico Matthew Lave 1, Jan Kleissl 2, Abraham Ellis 3, Felipe Mejia 2 1 Sandia National Laboratories, Livermore,
Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage
Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,
Renewable Energy Interconnection Requirements for the US. IEEE PES Meeting Denver, CO July 26-30, 2015 J. Charles Smith, Executive Director, UVIG
1 Renewable Energy Interconnection Requirements for the US IEEE PES Meeting Denver, CO July 26-30, 2015 J. Charles Smith, Executive Director, UVIG 2 Outline of Topics Background and Introduction NERC Integrating
ANCILLARY SERVICES SUPPLIED TO THE GRID: THE CASE OF THISVI CCGT POWER PLANT (GREECE)
Claudio Cavandoli, Alessandro Crippa EDISON S.p.A., Engineering Department ANCILLARY SERVICES SUPPLIED TO THE GRID: THE CASE OF THISVI CCGT POWER PLANT (GREECE) 1 ANCILLARY SERVICES SUPPLIED TO THE GRID:
Design and Operation of Power Systems with Large Amounts of Wind Power, first results of IEA collaboration
Design and Operation of Power Systems with Large Amounts of Wind Power, first results of IEA collaboration H. Holttinen, P. Meibom, A. Orths, F. Van Hulle, C. Ensslin, L. Hofmann, J. McCann, J. Pierik,
CSP. Feranova Reflect Technology. klimaneutral natureoffice.com DE-296-558771 gedruckt
RENEWABLE SOURCES RENEWABLE SOURCES CSP Feranova Reflect Technology klimaneutral natureoffice.com DE-296-558771 gedruckt Gedruckt auf 100% Recyclingpapier Circlesilk Premium White 200/150 g/m 2 2012 Feranova
Monitoring the Operation of Wind Turbines Alex Robertson, Vestas Northern Europe
Monitoring the Operation of Wind Turbines Alex Robertson, Vestas Northern Europe Renewable Efficient Energy II Conference, 21.03.2012, Vaasa, Finland Modern wind power plant produce more data than ever
Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report
Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives (Required per CPUC Decision No. C10-1328) Final Report (Submitted with Public Service s 2011 ERP) Executive Summary The objective
Guidelines for Large Photovoltaic System Integration
1 Guidelines for Large Photovoltaic System Integration Silviu Darie, PhD(EE), PE(EE) Abstract- The paper summarizes the result of a research project funded by the Department of Energy (DOE) in collaboration
Industries Association. ERCOT Successes and Challenges
Texas Renewable Energy Industries Association ERCOT Successes and Challenges Laura Doll Board Chair Electric Reliability Council of Texas November 7, 2011 ERCOT Overview The ERCOT market covers roughly
Natural Gas Wholesale Prices at PG&E Citygate as of November 7, 2006
QUARTERLY GAS ISSUES UPDATE December 26 I. Supply Issues Wholesale Natural Gas Prices Above normal temperatures and a lack of hurricane activity caused market prices to decrease in October. By November,
FULL ELECTRICAL LNG PLANTS: HIGHEST AVAILABILITY AND ENERGY EFFICIENCY THROUGH OVERALL SYSTEM DESIGN
FULL ELECTRICAL LN PLANTS: HIHEST AVAILABILITY AND ENERY EFFICIENCY THROUH OVERALL SYSTEM DESIN Dr. Edwin Lerch Siemens A Infrastructure and Cities Sector, IC S SE PTI, ermany Phone: 49-9131-7-34052 Fax:
REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES
REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES Mitigating Energy Risk through On-Site Monitoring Marie Schnitzer, Vice President of Consulting Services Christopher Thuman, Senior Meteorologist Peter Johnson,
Optimal Power Flow Analysis of Energy Storage for Congestion Relief, Emissions Reduction, and Cost Savings
1 Optimal Power Flow Analysis of Energy Storage for Congestion Relief, Emissions Reduction, and Cost Savings Zhouxing Hu, Student Member, IEEE, and Ward T. Jewell, Fellow, IEEE Abstract AC optimal power
FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003
F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify
Energy Systems Integration
Energy Systems Integration Dr. Martha Symko-Davies Director of Partnerships, ESI March 2015 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy,
Smart solutions for fleets of all types & sizes of power generation. Marcus König, E F IE SGS / September 2013
Smart solutions for fleets of all types & sizes of power generation Marcus König, E F IE SGS / September 2013 Instrumentation, Controls & Electrical The Siemens structure: Four Sectors close to the customer
Vectren Integrated Resource Plan (IRP) Stakeholder Meeting 3 of 3. Discussion of Analysis Results September 24, 2014
Vectren Integrated Resource Plan (IRP) Stakeholder Meeting 3 of 3 Discussion of Analysis Results September 24, 2014 IRP Timeline 2 1. Identify key objectives and metrics Complete 2. Gather information
Berlin, June 14, 2013 2nd Annual Electricity Price & Load Forecasting Forum 13-14 June Tim Buber
Merit Order of Energy Storages by 2030 The Impact of Storage Technologies and Market Regulation on Future Electricity Prices and the Value of Flexibility Berlin, June 14, 2013 2nd Annual Electricity Price
2010 STATE OF THE MARKET REPORT
2010 STATE OF THE MARKET REPORT FOR THE ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market August 2011 TABLE OF CONTENTS Executive Summary...
Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems
Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems Sandra Scalari Enel Ingegneria e Ricerca SpA Copenhagen, May 27-28 th 2014 Enel Presentation Generation Shift & Market in Europe Enel
An Introduction to Variable-Energy-Resource Integration Analysis Energy Exemplar October 2011
An Introduction to Variable-Energy-Resource Integration Analysis Energy Exemplar October 2011 1. Introduction Increased Renewable Portfolio Standards (RPS) are being enacted at the state, provincial, and
ALL ISLAND GRID STUDY WORK STREAM 4 ANALYSIS OF IMPACTS AND BENEFITS
ALL ISLAND GRID STUDY WORK STREAM 4 ANALYSIS OF IMPACTS AND BENEFITS January 2008 Executive Summary The All Island Grid Study is the first comprehensive assessment of the ability of the electrical power
The Natural Gas-Electric Interface: Summary of Four Natural Gas-Electric Interdependency Assessments WIEB Staff November 30, 2012
Introduction. The Natural Gas-Electric Interface: Summary of Four Natural Gas-Electric Interdependency Assessments WIEB Staff November 30, 2012 The increased reliance on natural gas as the primary fuel
Comparison of CO 2 Abatement Costs in the United States for Various Low and No Carbon Resources. Total System Levelized Cost Based on EIA LCOE
Comparison of CO 2 Abatement Costs in the United States for Various Low and No Carbon Resources Every year the Energy Information Administration (EIA) publishes its Annual Energy Outlook (AEO). In the
Ontario Wholesale Electricity Market Price Forecast. Ontario Energy Board
Ontario Wholesale Electricity Market Price Forecast For the Period May 1, 2015 through October 31, 2016 Presented to Ontario Energy Board April 20, 2015 Navigant Consulting Ltd. 333 Bay Street, Suite 1250
Modelling of wind power fluctuations and forecast errors. Prof. Poul Sørensen Wind Power Integration and Control Wind Energy Systems
Modelling of wind power fluctuations and forecast errors Prof. Poul Sørensen Wind Power Integration and Control Wind Energy Systems Modelling of wind power fluctuations Simulation tool: CorWind Based on
Brief review of Spanish Ancillary services scheme Renewable energy in Spain today Challenges integrating renewable energy nowadays Wind forecast and
Ancillary Services in Spain: dealing with High Penetration of RES Ignacio de la Fuente Brief review of Spanish Ancillary services scheme Renewable energy in Spain today Challenges integrating renewable
Electricity Supply. Monthly Energy Output by Fuel Type (MWh)
Ontario Energy Report Q4 Electricity October December Electricity Supply Electricity production was lower in Q4 than in previous years, with milder than normal weather in October and December resulting
CURTAILABLE RATE PROGRAM FOR INDIVIDUAL CUSTOMER LOADS
Page 1 of 16 CURTAILABLE RATE PROGRAM FOR INDIVIDUAL CUSTOMER LOADS PROPOSED TERMS AND CONDITIONS January 2015 Page 2 of 16 TABLE OF CONTENTS 1. Definitions... 3 2. Curtailable Load Options... 6 3. Nomination
ECCO International, Inc. 268 Bush Street, Suite 3633 San Francisco, CA 94104
PROMAX SHORT-TERM ENERGY & TRANSMISSION MARKET SIMULATION SOFTWARE PACKAGE ECCO International, Inc. 268 Bush Street, Suite 3633 San Francisco, CA 94104 ECCO International, Inc. Copyright 2009 EXECUTIVE
2013 STATE OF THE MARKET REPORT ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market
2013 STATE OF THE MARKET REPORT FOR THE ERCOT WHOLESALE ELECTRICITY MARKETS POTOMAC ECONOMICS, LTD. Independent Market Monitor for the ERCOT Wholesale Market September 2014 TABLE OF CONTENTS Executive
Ancillary Services and Flexible Generation
Ancillary Services and Flexible Generation Contents Ancillary Services Overview Types of Ancillary Services Market Impact Benefits of Medium Speed Solution Contact Information What are Ancillary Services?
Solar Variability and Forecasting
Solar Variability and Forecasting Jan Kleissl, Chi Chow, Matt Lave, Patrick Mathiesen, Anders Nottrott, Bryan Urquhart Mechanical & Environmental Engineering, UC San Diego http://solar.ucsd.edu Variability
Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas
Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional power generation Power generation from renewables
Storage Battery System Using Lithium ion Batteries
Offices and schools Utilities / Renewable energy Storage Battery System Using Lithium ion Batteries Worldwide Expansion of Storage Battery System s Commercial Buildings Residential The Smart Energy System
Energy Forecast UPDATE TO THE WHOLESALE ELECTRICITY PRICE FORECAST
Energy Forecast UPDATE TO THE WHOLESALE ELECTRICITY PRICE FORECAST February 213 Executive Summary This Wholesale Electricity Price Forecast updates the forecast developed in 21 for the Council s Sixth
Advanced Protection of Distribution Networks with Distributed Generators
Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School
System Protection Schemes in Eastern Denmark
System Protection Schemes in Eastern Denmark Joana Rasmussen COWI A/S, Energy Department System Protection Schemes in Eastern Denmark 1.Advanced system protection schemes are investigated and perspectives
Sanjeev Choudhary SunEdison Advanced Solutions
Sanjeev Choudhary SunEdison Advanced Solutions Solar Focus 2015 Solar Plus Storage Introduction to SunEdison Topics What makes a viable energy storage market opportunity? SunEdison storage application
Yield Reduction due to Shading:
1x4 1x16 10 x CBC Energy A/S x Danfoss Solar Inverters CBC-40W Poly 40 W TLX 1,5k 5 ; 1x11 3x4 0 1,5kW 1536 x CBC Energy A/S 1 x Power-One CBC-40W Poly 40 W TRIO-7,6-TL-OUTD 30 ; 4x14 0 7,6kW Location:
Renewable Energy. Solar Power. Courseware Sample 86352-F0
Renewable Energy Solar Power Courseware Sample 86352-F0 A RENEWABLE ENERGY SOLAR POWER Courseware Sample by the staff of Lab-Volt Ltd. Copyright 2009 Lab-Volt Ltd. All rights reserved. No part of this
Karnataka Electricity Regulatory Commission. Discussion note on
Karnataka Electricity Regulatory Commission Discussion note on Draft KERC (Forecasting, Scheduling, Deviation settlement and related matters for Wind and Solar Generation sources) Regulations, 2015. 1.0.
Demand Response Market Overview. Glossary of Demand Response Services
Demand Response Market Overview Glossary of Demand Response Services Open Energi has partnered with Tarmac to provide Demand Response What s inside... Market Overview Balancing Electricity Supply and Demand
Grid codes for renewable energy integration
Rabat 2015-06-02 Grid codes for renewable energy integration Harald G Svendsen SINTEF Energy Research Norway [email protected] Work Package leader for grid integration activities in the EuroSunMed
Your guide to electricity pricing in Ontario
Your guide to electricity pricing in Ontario A guide designed to help you understand and decipher the components of your electricity bill for your Ontario-based commercial or manufacturing business. -
Draft Electric Resource Plan 2009 2018 Technical Workshop. Technology Screening Analysis
Draft Electric Resource Plan 2009 2018 Technical Workshop Technology Screening Analysis June 15, 2009 www.lipower.org Resource Planning Process Overview Process Methodology Screening Analysis Determine
Grid integration of renewable energy
CRGM Online Training 2015 Online Training on Grid integration of renewable energy with exam: Outline Certified ReGrid Manager (CRGM) Page 1 of 10 1 What does ReGrid mean?... 2 2 Awarded certificates (Certified
TABLE OF CONTENTS CARIBBEAN AREA STATE OFFICE... 1-2 ARECIBO SERVICE CENTER... 2 CAGUAS SERVICE CENTER... 2 COROZAL SERVICE CENTER...
JUNE 2016 TABLE OF CONTENTS PAGE CARIBBEAN AREA STATE OFFICE... 1-2 ARECIBO SERVICE CENTER... 2 CAGUAS SERVICE CENTER... 2 COROZAL SERVICE CENTER... 3 JUANA DIAZ SERVICE CENTER... 3 MAYAGUEZ SERVICE CENTER...
Emissions Comparison for a 20 MW Flywheel-based Frequency Regulation Power Plant
Emissions Comparison for a 20 MW Flywheel-based Frequency Regulation Power Plant Beacon Power Corporation KEMA Project: BPCC.0003.001 May 18, 2007 Final Report with Updated Data Emissions Comparison for
Renewable Electricity in California in September 2015
Renewables International. www.renewablesinternational.net Renewable Electricity in California in September 2015 Bernard CHABOT Renewable Energy Expert and Trainer E-mail: [email protected] 1 Summary
The South African Grid Code
The South African Grid Code The Scheduling and Dispatch Rules Draft Revision 7.15T Comments to this document can be forwarded to: Attention: Mr. Nhlanhla Lucky Ngidi National Energy Regulator of South
System-friendly wind power
System-friendly wind power Lion Hirth (neon) Simon Müller (IEA) BELEC 28 May 2015 [email protected] Seeking advice on power markets? Neon Neue Energieökonomik is a Berlin-based boutique consulting
150 Watts. Solar Panel. one square meter. Watts
Tool USE WITH Energy Fundamentals Activity land art generator initiative powered by art! 150 Watts 1,000 Watts Solar Panel one square meter 600 Watts SECTION 1 ENERGY EFFICIENCY 250 Watts 1,000 Watts hits
Generator Interconnection and Deliverability Study Methodology Technical Paper
Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:
Energy Management in the Greek Islands
21, rue d Artois, F-75008 PARIS C6-303 CIGRE 2012 http : //www.cigre.org Energy Management in the Greek Islands Nikos HATZIARGYRIOU 1,2 Stavros PAPATHANASIOU 2,Isidoros VITELLAS 1, Stavros MAKRINIKAS 1,
Chapter 5. System security and ancillary services
Chapter 5. System security and ancillary services 1 Introduction Markets for electrical energy can function only if they are supported by the infrastructure of a power system. System should continue to
Generation Expansion Planning under Wide-Scale RES Energy Penetration
CENTRE FOR RENEWABLE ENERGY SOURCES AND SAVING Generation Expansion Planning under Wide-Scale RES Energy Penetration K. Tigas, J. Mantzaris, G. Giannakidis, C. Nakos, N. Sakellaridis Energy Systems Analysis
Section 4: Scheduling Philosophy & Tools
Welcome to the Scheduling Philosophy & Tools section of the PJM Manual for Scheduling Operations. In this section you will find the following information: A description of the PJM OI s scheduling philosophy
USBR PLEXOS Demo November 8, 2012
PLEXOS for Power Systems Electricity Market Simulation USBR PLEXOS Demo November 8, 2012 Who We Are PLEXOS Solutions is founded in 2005 Acquired by Energy Exemplar in 2011 Goal People To solve the challenge
Modelling framework for power systems. Juha Kiviluoma Erkka Rinne Niina Helistö Miguel Azevedo
S VISIONS SCIENCE TECHNOLOGY RESEARCH HIGHLIGHT 196 Modelling framework for power systems Juha Kiviluoma Erkka Rinne Niina Helistö Miguel Azevedo VTT TECHNOLOGY 196 Modelling framework for power systems
ScienceDirect. Base case analysis of a HYSOL power plant
Available online at www.sciencedirect.com ScienceDirect Energy Procedia 69 (2015 ) 1152 1159 International Conference on Concentrating Solar Power and Chemical Energy Systems, SolarPACES 2014 Base case
Concepts and Experiences with Capacity Mechanisms
Concepts and Experiences with Capacity Mechanisms Manuel Baritaud, International Energy Agency Conference Capacity Mechanisms: Experiences in Various European Countries Bundesministerium fur Wirtschaft
Wind Power and District Heating
1 Wind Power and District Heating New business opportunity for CHP systems: sale of balancing services Executive summary - Both wind power and Combined Heat and Power (CHP) can reduce the consumption of
Grid Integration of Aggregated Demand Response, Part 2: Modeling Demand Response in a Production Cost Model
Grid Integration of Aggregated Demand Response, Part 2: Modeling Demand Response in a Production Cost Model Marissa Hummon, David Palchak, Paul Denholm, and Jennie Jorgenson National Renewable Energy Laboratory
Solar Input Data for PV Energy Modeling
June 2012 Solar Input Data for PV Energy Modeling Marie Schnitzer, Christopher Thuman, Peter Johnson Albany New York, USA Barcelona Spain Bangalore India Company Snapshot Established in 1983; nearly 30
ATTACHMENT G. Network Operating Agreement
ATTACHMENT G Network Operating Agreement 1. PURPOSE OF NETWORK OPERATING AGREEMENT The purpose of this Agreement is to identify contractual requirements related to Network Integration Transmission Service
SGT5-8000H SCC5-8000H 1S. Experience of Commercial Operation at Irsching 4. ANIMP-ATI, Sesto San Giovanni 26 June 2012
SGT5-8000H SCC5-8000H 1S Experience of Commercial Operation at Irsching 4 ANIMP-ATI, Sesto San Giovanni 26 June 2012 Massimo Gianfreda 8000H Overview Validation Status Summary Fig. 2 Siemens Large Scale
Low Load Operational Flexibility for Siemens G-class Gas Turbines
Low Load Operational Flexibility for Siemens G-class Gas Turbines Power-Gen International 2008 Orlando, Florida www.siemens.com Power-Gen International Orlando, Florida December 2008 2 Low Load Operational
