Colorado Regulation No. 8, Part B, Asbestos 100 Questions
|
|
|
- Kory Payne
- 10 years ago
- Views:
Transcription
1 List of Questions Click on a question and you will be redirected to the answer. Page 1. On a non-friable project, can any poly used be disposed of as non-friable waste material? What s the ruling for metal deck staining? Can PLM bulk sampling be used to determine if any residue or non-friable adhesive is present at <1%? Need to clarify as to whether the rule is no asbestos, or if some is OK What s the ruling for concrete deck pits? Can PLM bulk sampling be used to determine if any residue or non-friable adhesive is present at <1%? Need to clarify as to whether the rule is no asbestos, or if some is OK Must a certified AMS be certified as an asbestos building inspector to conduct a visual inspection? What if bulk sampling is required as a part of the visual inspection (i.e. soil)? Can an insurance adjuster or home inspector/appraiser collect bulk samples for ACM analysis? For grandfathered AMS applicants who paid the AMS application fee in May 2003, what time period does that cover and when would additional fees be required? Can an AMS employer hire a new AMS trainee and use him/her for work activities as a trainee for a period of time and never have the person fully certified? Can other states on-the-job training apply to the Colorado AMS training requirements? If the outside samples for an AHERA TEM clearance are not collected, is that in violation of Regulation No. 8 even if you do not intend to use the Z-test? Will CDPHE be conducting any spill response workshops? Can CDPHE clarify requirements for responses to fires or areas that sustain smoke damage, specifically as they relate to tenants personal belongings and clearance requirements? Can CDPHE identify why abatement work done in a structure on a single-family home site other than the primary residence, i.e., out buildings, falls into the requirement for single-family residence for permitting purposes? What s the story with poly sheeting? Regulation No. 8 calls for two layers, so why can t poly be folded over and hung on the walls that way? Isn t that equivalent to two layers?...6 Page 1 of 7
2 1. On a non-friable project, can any poly used be disposed of as non-friable waste material? Yes, poly sheeting from non-friable asbestos projects may be disposed of as non-friable asbestos waste. 2. What s the ruling for metal deck staining? Can PLM bulk sampling be used to determine if any residue or non-friable adhesive is present at <1%? Need to clarify as to whether the rule is no asbestos, or if some is OK. No visible dust or debris may remain in the work area for it to successfully pass a final visual inspection. Note that this standard does not distinguish between asbestos and non-asbestos debris. Residue and non-friable adhesives constitute dust and debris and must be removed. Stains, which are an integral and inseparable part of the metal, do not constitute dust and debris and therefore do not have to be removed. If it can be shown that the metal decking was coated with more than one layer, and that the first layer applied to the deck was non-asbestos, then the Division would consider allowing PLM to verify that the residue is nonasbestos and could remain in place. On the other hand, if the metal deck was covered with just one layer of material, and initial bulk sampling resulted in the material being considered ACM, then we would not allow follow-up PLM bulk sampling to, in effect, go back and declare material as non-acm that had already been deemed ACM. 3. What s the ruling for concrete deck pits? Can PLM bulk sampling be used to determine if any residue or non-friable adhesive is present at <1%? Need to clarify as to whether the rule is no asbestos, or if some is OK. No visible dust or debris may remain in the work area for it to successfully pass a final visual inspection. Residue and non-friable adhesives constitute dust and debris and must be removed. Visible debris, asbestos or otherwise, must be removed from concrete deck pits. If it can be shown that the concrete deck was coated with more than one layer, and that the first layer applied to the deck was non-asbestos, then the Division would consider allowing PLM to verify that the residue is nonasbestos and could remain in place. On the other hand, if the concrete deck was covered with just one layer of material, and initial bulk sampling resulted in the material being considered ACM, then we would not allow Page 2 of 7
3 follow-up PLM bulk sampling to, in effect, go back and declare material as non-acm that had already been deemed ACM. 4. Must a certified AMS be certified as an asbestos building inspector to conduct a visual inspection? What if bulk sampling is required as a part of the visual inspection (i.e. soil)? AMS certification is the only required credential for a person performing a final visual inspection for clearance of an abatement project. If, for whatever reason, bulk sampling is performed at any time, the person collecting the sample must be state-certified as an asbestos building inspector. This determination stems from Regulation No. 8, Section III.B.2., which states the following: With respect to school buildings, public or commercial buildings and single-family residential dwellings, any individual who inspects any building for the presence of asbestos shall be certified as a Building Inspector in accordance with this regulation. In addition, Definition A.3. of the ASHARA defines inspection as follows: Inspection means an activity undertaken in a school building, or a public and commercial building, to determine the presence or location, or to assess the condition of, friable or non-friable asbestos-containing building material (ACBM) or suspected ACBM, whether by visual or physical examination or by collecting samples of such material The term does not include the following: a. Periodic surveillance b. Inspections performed by employees or agents of Federal, State or local government solely for the purpose of determining compliance c. visual inspections of the type described in 40 CFR (i) solely for the purpose of determining completion of response actions. 5. Can an insurance adjuster or home inspector/appraiser collect bulk samples for ACM analysis? Refer to the answer to Question #4, which says that the person collecting the sample must be state-certified as an asbestos building inspector. Regulation No. 8, Section III.B.2., requires the following: With respect to school buildings, public or commercial buildings and single-family residential dwellings, any individual who inspects any building for the presence of asbestos shall be certified as a Building Inspector in accordance with this regulation. Page 3 of 7
4 The ASHARA defines an inspection as follows: Inspection means an activity undertaken to assess the condition of, friable or non-friable asbestos-containing building material (ACBM) or suspected ACBM, whether by visual or physical examination or by collecting samples of such material 6. For grandfathered AMS applicants who paid the AMS application fee in May 2003, what time period does that cover and when would additional fees be required? Existing AMS applicants will be fully certified when the applicant brings in the AMS refresher certificate. The date of the refresher class will be the date that the Division will use for certification. For renewal of AMS certification, after the AMS takes a refresher class, the AMS will then need to bring to the Division the refresher certificate, a completed application and the associated fee. 7. Can an AMS employer hire a new AMS trainee and use him/her for work activities as a trainee for a period of time and never have the person fully certified? Can other states on-the-job training apply to the Colorado AMS training requirements? The rationale for allowing the AMS trainee to perform some work activities under the supervision and observation of the mentoring AMS was to allow consulting companies to put these trainees to work until an AMS training class became available. It was understood and agreed to by all Parties to the last Reg. 8 revision that any efforts to circumvent the training requirement would result in a move to request that the Commission revise the regulation so that it required that the AMS training course be taken prior to any fieldwork being performed, and that this effort would be supported fully by the Parties. The on-the-job experience requirement for AMS applicants requires that the applicant be supervised and observed by a currently Colorado-certified AMS. Since this became a requirement of new AMS on March 30, 2003, experience before that date cannot be considered. If there will be work conducted in another state that involves both the mentoring- and applicant-ams, please call the Division to discuss this on a case-by-case basis. The decision may hinge on clearance and air monitoring requirements for that other state. If someone wants to qualify to be an AMS by reciprocity, they must possess a valid certificate, license or other registration from another state, District of Columbia or other territory of the United States, or other Divisionapproved national entity (specifically, the National Asbestos Examinations and Registration System) which has a certification and testing program that has been approved by the EPA and which is at least as stringent as the Commission's and provide documentation to the Division showing that they have been certified to conduct Air Monitoring Specialist activities for at least 1 year (See Regulation No. 8, Section II.I., Reciprocity) Page 4 of 7
5 8. If the outside samples for an AHERA TEM clearance are not collected, is that in violation of Regulation No. 8 even if you do not intend to use the Z-test? If you are collecting the samples for clearance in a school building, a minimum of 13 samples (5 inside, 5 outside and 3 blanks) must be collected for each work area. This question is answered in the EPA s 100 Commonly Asked Questions (Question #83). You are only required to analyze the inside samples. In a nonschool building, you are only required to collect the inside samples. The minimum number of samples to be collected is based on the table in Regulation No. 8, Section III.P.3.a.(ii) on page Will CDPHE be conducting any spill response workshops? The Division and CWIACA have agreed to form an ad hoc committee made up of industry representatives and federal, state and county regulators to meet to share their expertise, experiences and opinions regarding the broader question of how to deal with asbestos spills. The goal will be to develop a standard set of protocols to be followed when dealing with asbestos spills. Once these protocols are completed the Division will develop a Spill Response Workshop. There are many different types of spills, from a delaminating sprayed-on acoustical ceiling to an office building fire and its associated smoke and water damage. How to best respond to a spill can depend on a whole host of factors, including: Is it in an Area of Public Access? Is it a Public and Commercial building, SFRD or school? What kind of HVAC system is there in the building? Is the building currently occupied? If so, do we order evacuation? If yes, under what conditions may the tenants re-enter the building/structure? Or remove personal belongings? Is the building structurally unsound? What type of damage has the building sustained? Fire? Smoke? Water? Other? Defining the spill boundaries: o Who should do it? o How should it be done? o What tests should be used to define the boundaries? What protocols should be followed in conducting those tests? Once the spill boundaries are defined, how do we deal with carpeting, clothing, furniture, electronics, curtains, partitions, etc. impacted by the spill? These are just a few of the many questions that must be answered before it can be determined what steps need to be taken in responding to a spill involving asbestos. Therefore, there is no one answer that could be given here that would apply to all spill situations. Page 5 of 7
6 Nonetheless, Regulation No. 8, in Section III.T. (Asbestos Spill Response) beginning on page 50, lays out the basic steps that need to be taken by the building owner or contractor in the event of a major spill. In addition, Section III.T.1.k. further requires the building owner or contractor to [c]omply with any other measure deemed necessary by the Division to protect public health. 10. Can CDPHE clarify requirements for responses to fires or areas that sustain smoke damage, specifically as they relate to tenants personal belongings and clearance requirements? The Division views this question and question #9 on spill responses as inter-related, so please refer back to our response to question # Can CDPHE identify why abatement work done in a structure on a single-family home site other than the primary residence, i.e., out buildings, falls into the requirement for single-family residence for permitting purposes? Although it could be interpreted that out buildings, such as detached garages, outhouses, sheds, etc., are not structures whose primary use is for housing of one family, the Division believes the intent of the regulation is to treat structures that are directly associated with, and dependent upon, the actual residence itself as singlefamily residential dwellings (SFRD), unless the abatement in the structure could somehow affect persons other than the family residing in the home. This is based on the Division s interpretation of the legislative intent to provide a homeowner/occupant exemptions from complying with the regulations when exposure to asbestos would be relatively limited to the homeowner/occupant and not affect the public (the homeowner/occupant should be allowed to choose their level of risk, but the homeowner/occupant cannot make that choice for other persons who may suffer asbestos exposure from the homeowner/occupant s choices). Thus, out buildings, which are an integral part of the house, are, therefore, considered part of the single-family residential dwelling (SFRD) for all intents and purposes. With respect to farms, out buildings that are utilized for a commercial purpose would be considered public and commercial buildings. Exceptions could include detached garages used for storage cars and out-houses. 12. What s the story with poly sheeting? Regulation No. 8 calls for two layers, so why can t poly be folded over and hung on the walls that way? Isn t that equivalent to two layers? Page 6 of 7
7 Folded poly does not comply with the regulatory requirement for two layers of poly, in that folded poly does not provide either the intended or equivalent level of protection against water and debris finding its way behind poly that two, single-layers of overlapping poly provide, which is what the regulatory requirement contemplated. The folded poly does reduce the potential for penetration through direct physical contact, like two separate layers, but it does not provide the critical protection at the attachment point, which is where poly barriers typically fail, and it does not facilitate proper teardown practices to minimize exposure of the surface. In fact, folding the poly actually increases the chances of barrier failure and contamination as explained below: a. Weight problem: If poly is folded over, the duct tape used to hold the poly in place must support twice as much poly, and therefore twice as much weight, as it would if two separate layers of overlapping poly are used. This unnecessarily increases the likelihood of the wall poly pulling free from the wall or from the tape. b. Two sealed areas vs. one sealed area: Two separate layers of poly (and two separate strips of duct tape) provide for at least double the protection from water or debris finding its way behind the poly because there are two separately sealed areas where poly is attached to the wall with duct tape. With two separate layers, if one seal is compromised, there s a backup second sealed area remaining. c. Backup layer of protection: In the case of duct tape failure, both layers of poly would come down in the folded over method, while only one layer of poly would come down in the separate layer method, leaving at least one layer of poly as backup protection for the walls. d. Mechanics: The ability of poly to remain adhered to duct tape is greatly reduced in the folded-over method. This is difficult to describe and difficult to picture, so try this: apply the lower 3 of a 12 length of duct tape to the seam of a square foot piece of folded poly and tape it to a wall. Now, simulate the weight of an entire wall covered with poly by pulling straight down on the layer of poly farthest from the wall and notice how well the poly adheres to the duct tape. Now try it again, but this time pull straight down on the layer of poly closest to the wall. Notice how much less force (weight) it takes to get the poly to separate from the duct tape. This is a good illustration of why folded poly is much harder to secure with duct tape than two separate layers of poly. e. Teardown contamination problem: In the teardown phase, it is difficult to remove the inner layer of folded poly without damaging or causing outright delamination of the outer layer. The simultaneous removal of both layers of poly simultaneously is undesirable because the inner layer has gross amounts of fibers that will shake loose during removal and packaging, exposing wall and floor surfaces to asbestos fibers. To minimize this contamination potential, the outer layer must stay intact during the stripping and packaging of the grossly contaminated inner layer. Hence, two independent layers are important to correctly affect proper de-construction of the containment barriers. Page 7 of 7
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.
AHERA 3-Year Asbestos Re-Inspection
AHERA 3-Year Asbestos Re-Inspection Denver 940 Fillmore Street Denver, Colorado 80206 Report Date: November 20, 2013 OEI Project No. 13.159 Prepared For: John Lewis Denver 940 Fillmore Street Denver, CO
Colorado Department of Public Health And Environment Hazardous Materials and Waste Management Division
Brian Long Solid Waste Compliance Assurance Unit [email protected] Richard Mruz Hazardous Waste Corrective Action Unit [email protected] Colorado Department of Public Health And Environment
LRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material
LRI Hidden Valley Acceptance Criteria for Asbestos and Asbestos Contaminate Waste Material Asbestos Policy and Criteria Policy: Pierce County Recycling Composting and Disposal (LRI) has established an
Asbestos Management POLICY
Asbestos Management POLICY All Asbestos Containment Material (ACM) removal activities shall comply with applicable federal, state, and local regulations. Areas of responsibility of Facilities Management
UI Procedures for Asbestos Management
UI Procedures for Asbestos Management The University of Iowa Rev.12/12/2012 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing
ASBESTOS BACKGROUND INFORMATION
ASBESTOS BACKGROUND INFORMATION Asbestos Facts What is Asbestos? Asbestos is a mineral. It is a natural rock mined from the ground. Most of the asbestos used in this country comes from Quebec in Canada.
University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS
Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations
Asbestos Inspection Project Procedure
EOSMS 402 Date: 01/13/2014 Page 1 of 6 1) Purpose This document is intended to specify the scope of services required of Asbestos Contractor in asbestos inspection projects at Kennesaw State University
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD
THE COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT S REVISED ASBESTOS-IN-SOILS REGULATIONS AND THE COLORADO BROWNFIELDS TAX CREDIT
THE COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT S REVISED ASBESTOS-IN-SOILS REGULATIONS AND THE COLORADO BROWNFIELDS TAX CREDIT Presented by Polly Jessen Kaplan Kirsch & Rockwell LLP January 22,
OGS LIMITED ASBESTOS & LEAD SURVEY REPORT
our people and our passion in every project OGS LIMITED ASBESTOS & LEAD SURVEY REPORT Building 44 Willard Drug Treatment Center 7116 County Road 132 Willard, NY Prepared for: NYSOGS 33 rd Floor, Corning
Asbestos Abatement Work Plan for the Carter Carburetor Superfund Site
for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project
IDENTIFICATION OF ASBESTOS You can t identify asbestos-containing materials with the naked eye. Experienced employees can identify suspected
Asbestos is a mineral fiber that was historically used in a variety of building construction materials due to its structural strength and for its qualities as an insulator and fire-retardant. The use of
A Guide to the Regulation Respecting Asbestos on Construction Projects and in Buildings and Repair Operations. November 1, 2007
A Guide to the Regulation Respecting Asbestos on Construction Projects and in Buildings and Repair Operations November 1, 2007 A Guide to the Regulation respecting Asbestos on Construction Projects and
June 27, 2013. Project GSA1570019. Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102
June 27, 2013 Project GSA1570019 Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102 Subject: Determination of Asbestos Conditions Former USDA
DIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions
DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of
North Carolina State University. Asbestos Management Plan
North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building
Summary of Georgia s Lead-Based Paint (LBP) Renovation, Repair and Painting (RRP) Rules For Contractors, Property Managers, and Maintenance Personnel
Second Edition Revised January 2014 Summary of Georgia s Lead-Based Paint (LBP) Renovation, Repair and Painting (RRP) Rules For Contractors, Property Managers, and Maintenance Personnel Summary of Requirements
UBC Plant Operations Asbestos Work Procedures April 2004
UBC Plant Operations Asbestos Work Procedures April 2004 These Procedures are for use by UBC Plant Operations, Utilities, Housing & Conferences, and IT Services only and are not intended for use by other
Loss Control TIPS Technical Information Paper Series
Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM Asbestos-Containing Material (ACM) In Buildings The presence of asbestos in buildings, particularly those
Asbestos Management Plan EC 45 Page 1
Name: Asbestos and ACBM (asbestos containing building material) Management Plan Areas Affected: All buildings that contain asbestos and ACBM on campus Effective Date: 1/1/09 Reviewed/Revised: 12/15/12
Asbestos NESHAP ISSUES AND QUESTIONS
Asbestos NESHAP ISSUES AND QUESTIONS FIRE-DAMAGED BUILDINGS HOW DOES THE NESHAP APPLY? After the Fire Is Out Building condition can vary widely from smoke damage to complete destruction with variations
ASBESTOS in state and local government
ASBESTOS in state and local government Inspection campaign In 2013/14, WorkSafe WA is conducting a proactive inspection campaign focusing on the management of asbestos in state and local government buildings.
ASBESTOS BUILDING INSPECTION REPORT. for. Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823
ASBESTOS BUILDING INSPECTION REPORT for Michigan State University Office of Environmental and Occupational Safety East Lansing, Michigan 48823 at Bailey Hall Building #315 East Lansing, Michigan 48823
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations
Asbestos Work Permit Procedures
These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace
Standards for Asbestos Abatement
19a-332a-1. Definitions Standards for Asbestos Abatement 19a-332a-1. Definitions The following definitions shall apply for the purpose of Section 19a-332a-1 to Section 19a-332a- 16 inclusive. (a) "Adequately
Fact Sheet on Asbestos
Fact Sheet on Asbestos WHAT IS ASBESTOS? Asbestos is a naturally occurring mineral found in certain rock formations, mined from open pit mines. Most of the asbestos used in the United States today comes
Restoration Specific Asbestos and Lead Based Paint Survey Report. 2503 Logan Ave Colorado Springs, CO 80909
Restoration Specific Asbestos and Lead Based Paint Survey Report Property Information: 2503 Logan Ave Colorado Springs, CO 80909 Inspection Conducted By: Shannon Anderson Colorado Cert #14225 Ted Anderson
2013 AHERA 3 Year Re-Inspection Report For. Northeast Elementary School 82 Scofieldtown Road Stamford, CT. Performed by
2013 AHERA 3 Year Re-Inspection Report For 82 Scofieldtown Road Stamford, CT Performed by P.O. Box 423 Stratford, CT 06615 Inspection Date: April 17, 2013 82 Scofieldtown Road Stamford, CT I. EXECUTIVE
ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS
ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS 1.0 GENERAL 1.1 SUMMARY A. The following procedures apply to the project manual and drawings for asbestos in
Approved by: UBC ACT Committee
The University of British Columbia Asbestos Safety Policy Prepared by: Russell R. English Policy Approved by: UBC ACT Committee Issue Date: April 1, 2004 Replaces: March, 1989 I-B-05 1.0 Policy: This policy
Asbestos in your home. Information on living with Asbestos
Asbestos in your home Information on living with Asbestos Why I have I got this leaflet? You have received this leaflet as Slough Borough Council have identified, through an inspection process, that you
Asbestos abatement Sampling & Analysis. Abatement Project Supervision
Asbestos abatement Sampling & Analysis Abatement Project Supervision TOPICS FOR DISCUSSION Air Sampling PERSONNEL AREA Analysis PCM Analysis TEM Analysis TYPES OF SAMPLING Two types of air sampling are
EXHIBIT A SCOPE OF SERVICES
EXHIBIT A SCOPE OF SERVICES 1.0 INTRODUCTION Asbestos consulting services are required for Item/Segment No. 227775-1, SR-7 (US 441) from Fillmore Street to South of Stirling Road, Hollywood, Broward County,
Asbestos 2 hr. Awareness
Asbestos 2 hr. Awareness LEA Designee Definition Any local educational agency as defined in section 198 of the Elementary and Secondary Education Act of 1965 (20U.S.C. 3381) The owner of any nonpublic,
Asbestos Policy & Procedure
Asbestos Policy & Procedure 1. Purpose & Introduction This policy and procedure sets out Octavia s commitment and approach to ensuring, so far as reasonably practicable, that residents, contractors and
6% Chrysotile NA 2 008 White floor tile 2 nd Floor 10,000 sq ft Cat 1 2% Chrysotile Poor
1.0 Asbestos Inspection Barge, Waggoner Summer & Cannon performed an asbestos survey for building 4666 (the Building) at the George C. Marshall Space Flight Center in Huntsville, Alabama on April 5, 2012.
SECTION 02 8213 ASBESTOS ABATEMENT
PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.
AHERA ASBESTOS REINSPECTION
AHERA ASBESTOS REINSPECTION 200 S. Fruitland kennewick, Washington Prepared For: Kennewick School District Prepared By: 320 North Johnson Street, Suite 700 Kennewick, Washington 99336 August 2013 Project
Asbestos Survey. for. Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington. May 1, 2014. Project #A2014/0406.
Asbestos Survey for Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington May 1, 2014 Project #A2014/0406 prepared for: Port of Pasco PO Box 769 Pasco, WA 99301 prepared by: Blue Mountain
LEGAL REVIEW & UPDATE
LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break
Prestige Home Inspection LLC
Cover Page Prestige Home Inspection LLC IAC2/ESA - Mold Assessment and Water Damage Report 555 W. Brook ave., Client's town MI, 48059 Inspection prepared for: Client's name Inspection Date: 10/15/2012
2. 40 CFR Part 763; The Asbestos Hazard Emergency Response Act (AHERA), EPA Worker Protection Rule, February 25, 1987.
Penn State University Environmental Health and Safety Asbestos Management Program I. Introduction Over the past several decades the hazards of asbestos exposure have become well known. With this influx
How To Perform A Limited Asbestos Survey
Limited Asbestos Survey Report Presented To: Barbara Wethington Project Manager Weston Solutions, Inc. 960 West Elliot Road, Suite 201 Tempe, Arizona 85284 Project: Southeast Corner of Arizona Highway
Asbestos Procedures. Asbestos Products
Asbestos Procedures Asbestos Products Where is asbestos known to be located on The Evergreen State College? Please see Appendix A for a list of known asbestos containing materials located on the Olympia
CONTROL METHODS. There are five ways to control the release of asbestos fibers:
Control Methods CONTROL METHODS When asbestos containing materials are found in a building, the owner must decide which method or methods will be used to deal with the asbestos. The decision will be based
NDSU TABLE OF CONTENTS
NDSU TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 DEFINITIONS AND DESCRIPTIONS 3.0 OPERATIONS AND MAINTENANCE PROCEDURES FOR ACM 4.0 FIBER RELEASE EPISODES 5.0 DEMOLITION INFORMATION 6.0 REMARKS 1.0 INTRODUCTION
Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW
Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW August 2006 NSW Department of Commerce Parsons Brinckerhoff Australia Pty Limited ACN 078 004 798 and Parsons
Why was asbestos used?
Asbestos Awareness What is Asbestos? Why was asbestos used? Asbestos appealed to manufacturers and builders for a variety of reasons. It is strong yet flexible, and it will not burn. It conducts electricity
Control Provisions under the Air Pollution Control Ordinance
ProPECC PN 2/97 ENVIRONMENTAL PROTECTION DEPARTMENT PRACTICE NOTE FOR PROFESSIONAL PERSONS Handlin of Asbestos Containin Materials in Buildins Introduction Asbestos is a generic name given to a group of
Asbestos Flooring Information and Issues
UNIVERSITY OF WISCONSIN MILWAUKEE Physical Plant Services-Asbestos Management Program USB 222 P.O. Box 413, Milwaukee, WI 53201 (414) 229-4576 Developed By: Robert Grieshaber, CIH Date/Revision: December
Policy for the Management of Asbestos in the Workplace
Southwark Council Management of Asbestos in the Workplace November 2011 Page 1 of 15 CONTENTS 1. INTRODUCTION... 3 2. POLICY STATEMENT... 3 3. ASBESTOS RISK CLASSIFICATION SCHEME... 5 4. SAMPLING OF ASBESTOS
DUST AND DEBRIS MANAGEMENT PROCEDURES HPD HOUSING REHABILITATION PROGRAMS
DUST AND DEBRIS MANAGEMENT PROCEDURES HPD HOUSING REHABILITATION PROGRAMS Dust and Debris Management Procedures refers to preventive measures that shall be undertaken by the contractor to prevent exposure
DESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE
1.0 Introduction DESERT RESEARCH INSTITUTE This Desert Research Institute (DRI) Mold Assessment and Remediation Procedure was established to assure that consistent and uniform information is provided to
Preparing the Work Area
Preparing the Work Area Work Area Preparation Objectives of Work Area Prep Sequence and Methods for Prep Engineering Controls: Negative Pressure Requirements, Equipment and Set-up Purpose of Area Prep
Building Owners Responsibilities for Asbestos
Building Owners Responsibilities for Asbestos August 2012 Minnesota Department of Labor and Industry Occupational Safety and Health Division This material can be provided to you in a different format (Braille,
have been provided with information on whether they do or do not contain asbestos before starting work;
Health Effects of Asbestos If your work involves possible exposure to asbestos, you should: be aware of the risks from asbestos exposure; understand the importance of keeping exposure as low as possible;
Regulatory Requirements for Asbestos Inspections Prior to Renovation Projects
Regulatory Requirements for Asbestos Inspections Prior to Renovation Projects Subject: Abstract for the 2012 Healthcare Engineering Society of Northern Illinois Mr. Kohon, having attended last yearʼs event
Asbestos in Your Home
Asbestos in Your Home You may have some asbestos in your home, but may not be sure what it is, what it looks like, or what to do about it. Just because asbestos is there doesn't mean there's a problem.
Mount Sinai Pediatric Environmental Health Specialty Unit WTC Asbestos Fact Sheet
This fact sheet answers frequently asked health questions (FAQs) about asbestos. It is part of a series of fact sheets describing potential health risks to children from exposures related to the World
COMPLIANCE WITH THIS PUBLICATION IS MANDATORY
BY ORDER OF THE COMMANDER 56TH FIGHTER WING (AETC) AIR FORCE INSTRUCTION 32-1052 LUKE AIR FORCE BASE Supplement 1 5 NOVEMBER 2008 Civil Engineering FACILITY ASBESTOS MANAGEMENT COMPLIANCE WITH THIS PUBLICATION
Policy on the Management of Asbestos
WISHAW AND DISTRICT HOUSING ASSOCIATION Policy on the Management of Asbestos As with all the Association s policies and procedures, this document, where required, may be able to be translated into other
Asbestos Management & Abatement
Asbestos Management & Abatement Latest revised date: October 29, 2012 Page 1 of 18 1.0 LEGAL & LEGISLATIVE REQUIREMENTS This standard provides guidance to meeting the minimum requirements of the Act &
Characteristics/Applications
Facilities Operations and Development Environmental Health & Safety 1314 Kinnear Rd. Columbus, Ohio 43212 Phone (614) 292-1284 Fax (614) 292-6404 http://fod.osu.edu The Ohio State University Asbestos Management
A Guide to Asbestos in your Home
A Guide to Asbestos in your Home IL25 A Guide to Asbestos in your Home A Guide to Asbestos in your home South Derbyshire District Council Housing Services Civic Offices, Civic Way, Swadlincote, Derbyshire
ASBESTOS IN THE HOME
J:\Public Protection Division\Food and Occupational Safety\Leaflets\A S B E S T O S.docJ:\Public Protection Division\Food and Occupational Safety\Leaflets\A S B E S T O S.doc ASBESTOS IN THE HOME What
ABClean Frequently Asked Questions (FAQ)
ABClean Frequently Asked Questions (FAQ) 1. How can I recognize asbestos containing products during cleaning, renovation, demolition or dismantling task? Considering construction date, which buildings
How To Manage Asbestos From Roofing And Siding
Contents Frequently Asked Questions Asphaltic Roofing and Siding Materials.... 1 Floor Tile.... 4 Non-Traditional Asbestos Abatement Work Practice Approvals.... 6 Survey Requirements.... 7 Vermiculite
ASBESTOS BUILDING INSPECTION REPORT. for the. City of East Lansing Waste Water Treatment Plant East Lansing, Michigan 48823.
ASBESTOS BUILDING INSPECTION REPORT for the City of East Lansing Waste Water Treatment Plant East Lansing, Michigan 48823 at the City of East Lansing Waste Water Treatment Plant and Woodingham Pump Station
THE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL ENVIRONMENT, HEALTH AND SAFETY 1120 Estes Drive Extension Chapel Hill, North Carolina 27599 CB#1650
THE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL ENVIRONMENT, HEALTH AND SAFETY 1120 Estes Drive Extension Chapel Hill, North Carolina 27599 CB#1650 REVISION TWO EFFECTIVE DATE: August 2008 UPDATED: April
ASBESTOS CONTROL PLAN
ASBESTOS CONTROL PLAN POLICY It is the long term plan of Emily Carr University to have an asbestos free workplace. In the interim, The University plans to manage asbestos hazards based on prioritization
GUIDANCE DOCUMENT (redline version 2.0, released 01/30/09) on amended Industrial Code Rule 56(ASBESTOS) Page 1 of 88
1 1. 2 (b ) Purpose and Intent. This Section indicates that these regulations include those who supervise and employ persons employed in all aspects of an asbestos project. Does this statement include
UNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE
SECTION 01013 - SUMMARY OF THE WORK - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
Frequently Asked Questions Concerning Verification of Asbestos Surveys Before Issuing Building Permits
Frequently Asked Questions Concerning Verification of Asbestos Surveys Before Issuing Building Permits 1. Why do we need Occupations Code 1954.259/ 25 Texas Admin. Code (TAC) 295.34(l)? The Department
Asbestos Frequently Asked Questions
Asbestos Frequently Asked Questions What is asbestos? Asbestos is a mineral which is mined, processed, and used in many building materials. Since 1988, asbestos has been banned in most US building components;