1 Scope Management Guideline August, 2015 Check the Capital Project Delivery website to ensure this is the current version.

2 Table of Contents Scope Management Overview... 1 Charter... 4 Scope Statement... 5 Project Management Plan... 7 Managing Scope Changes... 8

3 Scope Management Overview Scope Management is the process used to include all required work in a project or proposed project and to manage and control scope over the life of the project. New Jersey Department of Transportation (NJDOT) Policy & Procedure 818, Scope Management for Capital Projects, states that projects and proposed projects are properly authorized by the Capital Program Committee (CPC) using a Charter, have defined Scope Statements documenting project work for specific phases (Concept Development, Preliminary Engineering and Final Design) and have a Project Management Plan documenting the overall approach to the management of the project. Purpose The primary goal of scope management is to make certain the work of the project or proposed project is identified, authorized, defined and managed over the life of the project. Accomplishing this goal will help to eliminate unauthorized work, minimize unwarranted changes and ultimately minimize the cost of the project and the time required to complete the project. Definitions See the Capital Project Delivery (CPD) Process Web Site Glossary Page for current definitions. Procedure Authorizing Work: During the Problem Screening (PS) phase, Capital Investment Planning and Development (CIPD) reviews and screens Problem Statements to determine appropriate action. CIPD consults with Subject Matter Experts (SMEs), Management Systems Owners and the Division of Project Management, if needed. If a Problem Statement is to be recommended to advance into Concept Development (CD), CIPD coordinates with SMEs and creates a Charter. CIPD then presents the Charter and all other pertinent documentation to the Capital Program Screening Committee (CPSC) for recommendation to the CPC. Ultimately, the CPC approves the Charter authorizing the Problem Statement to advance into CD. This approval also authorizes the time and funds to complete the work of CD. Defining and Managing Scope: For phases following PS, the scope of the effort must be documented and formally approved. This is accomplished using a Scope Statement. There are separate Scope Statement templates for CD, Preliminary Engineering (PE) and Final Design (FD). Each Scope Statement template is based on the Project Delivery Process and lists all of the products for the phase. The Project Manager customizes each Scope Statement based on the specifics of the project or proposed project. The Project Manager uses the Scope Statements to manage and control work. Documenting Project Management Approach: The Project Management Plan (PM Plan) documents the overall project management approach. The Project Manager creates the initial PM Plan Revision 3 Pg 1 of 8 Released: 08/2015

4 late in CD documenting any significant variation from the standard Project Delivery Process. The PM Plan also documents the justification for each variance. In future phases, the Project Manager revises the PM Plan, as needed, showing any changes to the previously defined approach. Key Products Charter: The Charter is a document created by CIPD and approved by the CPC that authorizes the existence and advancement of a problem statement, and provides the authority to apply organizational resources to work activities. The Charter typically includes the name of the problem statement, justification, objectives, recommendation, responsible unit and authorizing signatures. Scope Statement: The CD, PE and FD Phases each have a Scope Statement specific to the work to be accomplished in that phase. The Scope Statement lists the anticipated work for a project and includes details of the project deliverables. This includes a description of the limit of scope of the project to the extent known at the beginning of the phase. Project Management Plan: A formal document that is mandatory for all projects and proposed projects. The PM Plan details the approach to be used to deliver a specific project and how the project will be executed, monitored and controlled. The PM Plan includes the overall approach and justification for exceptions to the standard project delivery process. Major Stakeholders Capital Investment Planning and Development (CIPD): CIPD reviews and ranks Problem Statements. CIPD also works with stakeholders, including SMEs, to develop Charters on behalf of Management System Owners for presentation to the CPSC. Capital Program Committee (CPC): The CPC signs the Charter authorizing the proposed project to advance into CD and begin work. Following CD, the CPC will authorize proposed projects and projects to advance to PE and then to FD. Capital Program Screening Committee (CPSC): The CPSC reviews the Charter and related documentation and submits to the CPC for authorization to advance into CD. In later phases, the CPSC will recommend the CPC authorize the proposed project or project to advance to the next phase. Designer: The Designer performs work in accordance with the approved Scope Statement at the direction of the Project Manager. Division of Project Management (DPM): DPM collaborates with CIPD and Management Systems Owners as needed during the development of the Charter. DPM concurs with the Charter before CIPD presents to CPSC. DPM creates and manages the CD, PE and FD Scope Statements. DPM creates the PM Plan. DPM is responsible for any required updates to the PM Plan during PE or FD. Revision 2 Pg 2 of 8 Released: 08/2013

5 Management System Owner: Management System Owners track and rank transportation problems within their responsible areas. For appropriate transportation problems, Management System Owners present Problem Statements to CIPD for review. Management System Owners collaborate with CIPD and DPM during the creation of the Charter and the respective Scope Statements throughout the project lifecycle. The Management System Owner presents the Charter to the CPSC for recommendation to the CPC. Subject Matter Experts: SMEs may be involved in any aspect of scope management. SMEs are often consulted during Problem Screening to provide input for Tier 1 and Tier 2 Screenings. SMEs are consulted during other Phases in the creation and review of Scope Statements. SMEs sign PE and FD Scope Statements indicating concurrence for their related work in context of the specific project. Change The Charter typically is not changed once authorization is granted. Changes to scope are the responsibility of the Project Manager. Significant changes to Scope Statements, as defined in NJDOT Policy & Procedure 405 Change in Project Scope and Status, once initially approved, must adhere to and follow Change Control Board (CCB) guidance. The PM Plan is revised at the end of each phase, if needed. Communication Communication occurs as needed between various stakeholders in the execution of the scope management process. Typically, stakeholders will communicate and collaborate in the development of the scope management products (Charter, Scope Statements and PM Plan). Scope Team meetings must be attended by all involved SME groups and the representative must have sufficient authority, knowledge and experience to address issues and make decisions. The representative SME is responsible to communicate project or proposed project scope and all decisions to their respective organizations. The Design Communications Report (DCR) is utilized to document communications regarding design decisions. The Project Reporting System (PRS) is utilized to document and communicate project status. Key Performance Indicators Key Performance Indicators are needed to measure the performance of the scope management process. It is important to measure performance of the scope management process, including the tools and the use of the tools, to see impact to the ultimate objectives of lower cost and fewer schedule delays and to identify additional improvements to be incorporated into the process. An initial measurement (baseline) should be made and used for comparison after the process changes have been in place for a significant period. Revision 2 Pg 3 of 8 Released: 08/2013

6 Charter Purpose The Charter authorizes work to begin on the proposed project. To accomplish this, the Charter must briefly state the scope of the work being authorized. The Charter is used to authorize CD only. After CD, the work is authorized by the approved Scope Statement specific to each phase. Since the Charter is used only for CD, the scope of work described is only the work to be completed during CD. The Charter is used in future phases to help keep scope aligned with the originally authorized work. Charter Template Sections Most of the fields in the Charter Template are self-explanatory and align with data to be entered into PRS. Information entered into the descriptive fields is to be brief. Charters are expected to be no longer than one page. Charters for similar proposed projects originating in Management Systems can be combined into a single Charter for the group with an attached listing of the associated proposed projects. Justification: Explain why the work of this effort is important and why the work should be approved now. This should be a single paragraph. The intent is to answer Why do this work now? Objectives: Provide a brief overview of what will be accomplished. The intent is, in one or two sentences, to answer What will be fixed? For example, Replace the southbound bridge deck. Description: Provide additional detail as needed to explain the objectives. For example, Route 130 is a state highway with two lanes in each direction with shoulders and a grassy median. The final product will be the same. The existing southbound lanes are on an older structure than the northbound lanes. The southbound deck has deteriorated and needs to be replaced. The southbound deck will be removed and a new deck constructed. Summary Milestone Schedule: At this point in the lifecycle of the proposed project there is not enough information to provide a detailed schedule with any confidence. Include in the Charter any summary milestones that are known. Include when CD is expected to begin and end. If possible, include what year FD will finish and in what year(s) Construction will occur. Summary Budget/Budget Cap: The authorizing body, the CPC, is only authorizing CD. Include in the Charter the estimate for completing CD. When to Use Charters are to be created at the end of PS and are used only for proposed projects that are to be recommended to advance into CD. Revision 2 Pg 4 of 8 Released: 08/2013

7 Procedure During Problem Screening: 1. CIPD ensures the Problem Statement is properly completed, accurately describes the problem and that the work should be advanced at this time. For proposed projects advancing to CD, CIPD collaborates with the Management System Owner, DPM and SMEs to create the Charter. 2. The appropriate Management System Owner presents the Charter to the CPSC for recommendation to the CPC. The Management System Owner is essentially the sponsor of the work at this time and must justify the scope and timing (why address this problem now), as defined in the Charter, to the CPSC. 3. The CPSC recommends to the CPC that the proposed project advance to CD. 4. The CPC approves the Charter authorizing the proposed project to advance to CD. During Concept Development: 5. The Project Manager refers to the Charter when developing the CD Scope Statement to ensure all needed work is accomplished and to facilitate constraining the proposed project scope to that authorized by the CPC. During Any Phase: 6. The Project Manager, Designer and SMEs refer to the Charter when assessing any requested change in scope. Any change that exceeds the original bounds of the Charter, as authorized by the CPC, must be presented to the CPSC and CPC for approval. Communication Communication and collaboration are essential to successful scope management. CIPD works with Management System Owners and DPM to define a Charter that clearly summarizes the work to be authorized for CD. Management System Owners work with CIPD and DPM to prepare Charters and then present the Charters to the CPSC for recommendation for approval to the CPC. SMEs may also be consulted in the development of Charters. It is critical that the Scope for CD is clearly defined in the Charter and that the Management Systems Owner, CIPD and DPM all concur on the scope and the justification before the Charter is submitted to CPSC for recommendation to CPC. Scope Statement Purpose The Scope Statement defines and formally authorizes work to complete for a specific phase of the proposed or actual project. To accomplish this, the Scope Statement must clearly document the scope of the work being authorized. Scope Statements are used to identify and authorize the work to be completed in CD, PE and FD. Scope for the Construction (CON) Phase is defined and authorized in the Contract Documents. Each Scope Statement provides sufficient detail for a Designer to commit to completing the defined scope of work for an agreed to dollar amount over a specific period. Revision 2 Pg 5 of 8 Released: 08/2013

8 When to Use Scope Statements are created at the beginning of CD and at the end of CD and PE and are used to define and manage the work to be completed during each particular phase. Procedure for CD Scope Statement During Concept Development: 1. At the initiation of CD, the Project Manager uses the CD Scope Statement Template to create the CD Scope Statement for the specific proposed project. The Project Manager consults SMEs as needed. 2. DPM Management reviews and approves the CD Scope Statement. 3. The Project Manager uses the approved CD Scope Statement to execute a Task Order agreement, if a Consultant will be used, or to engage the in-house design staff to complete the scope of work. 4. During CD, the Project Manager uses the CD Scope Statement to manage and control work. Procedure for PE Scope Statement During Concept Development: 5. Near the end of CD, once the Preliminary Preferred Alternative has been created and the Local Officials have been briefed, the Project Manager uses the PE Scope Statement Template to create the PE Scope Statement for the specific proposed project. 6. Subject Matter Experts review the PE Scope Statement and provide comments to the Project Manager. 7. SMEs approve their assigned sections of the PE Scope Statement. 8. DPM Management reviews and approves the PE Scope Statement. 9. The Project Manager includes the PE Scope Statement in the CD Report. 10. The Project Manager uses the PE Scope Statement to solicit a Designer (if a Consultant will be used) or to develop an understanding with the in-house design staff to complete the scope of work for PE. During Preliminary Engineering: 11. The Project Manager uses the PE Scope Statement to manage and control work. Procedure for FD Scope Statement During Preliminary Engineering: 12. Near the end of PE, during the creation of the PE Report, the Project Manager uses the FD Scope Statement Template to create the FD Scope Statement for the specific project. 13. Subject Matter Experts review the FD Scope Statement and provide comments to the Project Manager. 14. SMEs approve their assigned sections of the FD Scope Statement. 15. The Executive Regional Manager accepts the FD Scope Statement. 16. DPM Management reviews and approves the FD Scope Statement. 17. The Project Manager includes the FD Scope Statement in the PE Report. Revision 2 Pg 6 of 8 Released: 08/2013

9 During Final Design: 18. The Project Manager uses the FD Scope Statement to negotiate with the Design Consultant or with in-house design staff to complete the scope of work for Final Design. 19. The Project Manager uses the FD Scope Statement to manage and control work. 20. The Project Manager uses the FD Scope Statement to create Contract Documents. Communication Communication and collaboration are essential to successful scope management. Scope for a specific phase must be clearly defined in the phase Scope Statement. SMEs and DPM must concur on the scope to be completed. The SMEs and the Project Manager must attend and participate in Scope Meetings. Designers work with DPM and SMEs throughout the phases executing work as defined in Scope Statements. Project Management Plan Purpose The Project Management Plan defines how the project or proposed project is executed, monitored and controlled. All projects will follow the Project Delivery Process. The PM Plan clearly documents ways the Project Manager will customize the Project Delivery Process to the specific project. The PM Plan documents any significant deviation in process from the standard and provides justification for the different approach. This allows major stakeholders, including NJDOT Senior Management and FHWA, to see how and why a specific project will execute any work outside the normal process. In the case of projects estimated total construction cost in excess of $500 million, or designated as a Major Project by the FHWA, additional PM Plan guidance must be followed and can be found on the FHWA web site. When to Use PM Plans are created near the end of CD after the Preliminary Preferred Alternative has been determined and the local officials have been briefed. If necessary, the PM Plan is updated toward the end of PE and the end of FD. The PM Plan is used throughout the project as needed to reference the project execution approach. Procedure During Concept Development: 1. Near the end of CD, once the Preliminary Preferred Alternative has been created and the Local Officials have been briefed, the Project Manager uses the PM Plan Template to create the PM Plan for the specific proposed project. 2. The Project Manager consults SMEs as needed. 3. DPM Management approves the PM Plan. 4. The Project Manager includes the PM Plan in the CD Report. Revision 2 Pg 7 of 8 Released: 08/2013

10 During Preliminary Engineering: 5. Once the Design Exception Report has been approved (if required) and the Environmental Document has been completed, the Project Manager updates the PM Plan, if needed. 6. DPM Management approves the updated PM Plan. 7. The Project Manager includes the PM Plan in the PE Report. During Final Design: 8. During FD, once the Plans, Specifications and Estimates package is complete, the Project Manager updates the PM Plan, if needed. 9. DPM Management approves the updated PM Plan. Communication Communication and collaboration are essential to successful scope management. Any deviations from the standard Project Delivery Process are documented in the PM Plan. The PM Plan must be available to key stakeholders such as SMEs, NJDOT Senior Management and FHWA. Managing Scope Changes All significant changes to a project s or a proposed project s scope are subject to NJDOT s Change Control Board Procedures. Guidance on these procedures is available on the NJDOT web site. All affected stakeholders (SMEs, NJDOT Senior Management, FHWA) must be notified of any significant change. Revision 2 Pg 8 of 8 Released: 08/2013

Project Delivery Process Overview

Project Delivery Process Overview New Jersey Department of Transportation Project Delivery Process Overview Presented by the Program Management Office January, 2012 Project Delivery Process Overview The New Jersey Department of Transportation

More information

Project Customization Guideline May, 2016

Project Customization Guideline May, 2016 Project Customization Guideline May, 2016 Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Introduction... 1 Section I: Project Customization General

More information

Quality Management Plan Procedure

Quality Management Plan Procedure Quality Management Plan Procedure Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Quality Management Plan Overview... 1 Introduction... 1 Objectives...

More information

OFFICE OF THE CIO. PROCEDURE Informational VERSION: 1.0

OFFICE OF THE CIO. PROCEDURE Informational VERSION: 1.0 OFFICE OF THE CIO PROCEDURE Informational VERSION: 1.0 Purpose Project Management of Major or Large NDUS Information Technology Projects Project Managers Guide/Checklist This procedural process will ensure

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of

More information

CHANGE MANAGEMENT PLAN TEMPLATE

CHANGE MANAGEMENT PLAN TEMPLATE CHANGE MANAGEMENT PLAN TEMPLATE This template allows a project manager to control, manage and monitor change requests that occur throughout the life of a project. This plan defines who has the authority

More information

Organization. Project Name. Project Overview Plan Version # Date

Organization. Project Name. Project Overview Plan Version # Date Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

How To Write A Project Management Plan

How To Write A Project Management Plan Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents

More information

PROJECT SCOPE STATEMENT

PROJECT SCOPE STATEMENT PROJECT SCOPE STATEMENT Note: Any work not explicitly included in this Project Scope Statement is implicitly excluded from the project. Create links to referenced documents (e.g., Link_To_ ) by using Insert

More information

SCHEDULE 8 Generalist Project Services Framework 2015

SCHEDULE 8 Generalist Project Services Framework 2015 SCHEDULE 8 Generalist Project Services Framework 2015 Nominal Insurer And Schedule 8 (Project Services Framework) Page: 1 of 6 Schedule 8 Generalist Project Services Framework Contents Overview... 3 1.

More information

At the end of this chapter. Project Charter. What is a Project Charter? What is a Project Charter? Why is a Project Charter used?

At the end of this chapter. Project Charter. What is a Project Charter? What is a Project Charter? Why is a Project Charter used? At the end of this chapter Project Charter Describe what a project charter is and why it is critical to project success. Explain what a project scope statement is and why it is important. List the various

More information

U.S. Department of Education Federal Student Aid

U.S. Department of Education Federal Student Aid U.S. Department of Education Federal Student Aid Lifecycle Management Methodology Stage Gate Review Process Description Version 1.3 06/30/2015 Final DOCUMENT NUMBER: FSA_TOQA_PROC_STGRW.NA_001 Lifecycle

More information

DRAFT. Propose that environmental considerations be added to the list of strategic considerations.

DRAFT. Propose that environmental considerations be added to the list of strategic considerations. DRAFT Proposed changes and reasoning for proposed changes to 5 th Edition of the PMBOK Guide. Rich Maltzman, MSIE, PMP Dave Shirley, MBA, PMP Tom Mochal, PgMP, PMP Andrea Krasnoff, PMP 1.4.3 Strategic

More information

CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)

CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB

More information

LGS Project Management Methodology

LGS Project Management Methodology Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant

More information

Cost Estimating Guideline December, 2015

Cost Estimating Guideline December, 2015 Cost Estimating Guideline December, 2015 Procedures are subject to change without notice. Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Section 1 -

More information

IT Project Management Methodology. Project Scope Management Support Guide

IT Project Management Methodology. Project Scope Management Support Guide NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald

More information

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview

Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...

More information

Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo

Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management Alfred Sankara, DigiBridge TelCo Introduction The Project Management Institute (PMI) is the world's leading

More information

UNIVERSITY OF GUELPH PROJECT MANAGEMENT FRAMEWORK

UNIVERSITY OF GUELPH PROJECT MANAGEMENT FRAMEWORK UNIVERSITY OF GUELPH PROJECT MANAGEMENT FRAMEWORK Table of Contents Document Purpose:... 3 What is a Project?... 3 What is not a Project? (e.g. Operational Tasks)... 3 What is Project Management?... 4

More information

Project Management Fundamentals. Office of the Senior Associate Vice President for Finance

Project Management Fundamentals. Office of the Senior Associate Vice President for Finance Project Management Fundamentals Project Management Institute PMI is an aggregation of best practices from thousands of professional project managers Principles in this training are based on PMI methodologies,

More information

Project Management Planning

Project Management Planning The Project Plan Template The Project Plan The project plan forms the basis for all management efforts associated with the project. A project plan template is included in this document. The information

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

INFORMATION TECHNOLOGY PROJECT EXECUTION MODEL GUIDE FOR SMALL AND MEDIUM PROJECTS

INFORMATION TECHNOLOGY PROJECT EXECUTION MODEL GUIDE FOR SMALL AND MEDIUM PROJECTS NOT MEASUREMENT SENSITIVE DOE G 415.1-2 INFORMATION TECHNOLOGY PROJECT EXECUTION MODEL GUIDE FOR SMALL AND MEDIUM PROJECTS [This Guide describes acceptable, but not mandatory means for complying with requirements.

More information

Commonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management.

Commonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management. Schedule Management Values - Goals Schedule Management Schedule Management v1.0 1 of 6 10/27/2010 Schedule Management Values - Goals Table of Contents 1 Schedule Management Guideline... 3 1.1 Determine

More information

Delivery Management Guidelines Delivery Process 2 - Project Management

Delivery Management Guidelines Delivery Process 2 - Project Management Delivery Management Guidelines Delivery Process 2 - Project Management Version control Version 9-1 Date 2010-10-18 Status Approved The IDMS Prov Infr Strat DP1: Portfolio Management DP1-1 Infrastructure

More information

Facilities Development Manual Chapter 2 Project Management Section 15 Project Integration Management

Facilities Development Manual Chapter 2 Project Management Section 15 Project Integration Management Facilities Development Manual Chapter 2 Project Management Section 15 Project Integration Management Wisconsin Department of Transportation FDM 2-15-1 Project Integration Management December 11, 2014 1.1

More information

Project Management: Trainee Guide Module 5 POST IMPLEMENTATION

Project Management: Trainee Guide Module 5 POST IMPLEMENTATION 200 Project Management: Trainee Guide Module 5 POST IMPLEMENTATION Bridges Social Development Project Management Training Program http://training.canadabridges.com 09/09/2009 PROJECT MANAGEMENT TRAINING

More information

HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)

HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC) Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise

More information

IT Project Management Practices Guide

IT Project Management Practices Guide IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or

More information

PIMA COUNTY PROJECT TRACKING REPORT

PIMA COUNTY PROJECT TRACKING REPORT PIMA COUNTY PROJECT TRACKING REPORT [DEPARTMENT NAME] [PROJECT NAME] Revision Date: [03/18/09] The Project Tracking Report document will provide a single source document where the Project Charter can continue

More information

FLORIDA DEPARTMENT OF EDUCATION Office of Independent Education and Parental Choice and the Florida Education Foundation Request for Proposal (RFP)

FLORIDA DEPARTMENT OF EDUCATION Office of Independent Education and Parental Choice and the Florida Education Foundation Request for Proposal (RFP) FLORIDA DEPARTMENT OF EDUCATION Office of Independent Education and Parental Choice and the Florida Education Foundation Request for Proposal (RFP) Program Name District-Charter Collaborative Compacts

More information

SCOPE MANAGEMENT PLAN <PROJECT NAME>

SCOPE MANAGEMENT PLAN <PROJECT NAME> SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

The Department intends to select one team. The contract will be for two years with a one year extension at the discretion of the Department.

The Department intends to select one team. The contract will be for two years with a one year extension at the discretion of the Department. TITLE: Statewide Asset Management Plan REQUEST FOR PROPOSALS USING AGENCY: NC Department of Transportation State Asset Management ISSUE DATE: November 15, 2013 SUBMITTAL DEADLINE: December 17, 2013 at

More information

The purpose of this course is to provide practical assistance for defining and managing project scope.

The purpose of this course is to provide practical assistance for defining and managing project scope. Scope Definition and Scope Management Purpose - To provide practical assistance for defining and managing project scope. This course will focus on tips for creating a scope statement rather than a step-by-step

More information

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1 Appendix C Change Management Plan Communication Plan QA/QC Plan Transition and Closure Plan C-1 CHANGE MANAGEMENT PLAN Whether the effects of changes are positive or negative, managing change is an important

More information

Central Project Office: Charter

Central Project Office: Charter Central Project Office: Charter ITCS: Central Project Office EAST CAROLINA UNIVERSITY 209 COTANCHE STREET, GREENVILLE, NC 27858 1 Table of Contents INTRODUCTION... 3 PURPOSE... 3 EXPECTED BENEFITS... 3

More information

SECTION I PROJECT SUMMARY (TRW)

SECTION I PROJECT SUMMARY (TRW) SECTION I PROJECT SUMMARY (TRW) Table I Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Managers: Ron McCranie/Andy Loveland Status Meeting Date:

More information

CHAPTER 20 Project Development Cost Estimates Table of Contents

CHAPTER 20 Project Development Cost Estimates Table of Contents Chapter 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates... 20-3 SECTION 1 Project Cost

More information

Six sigma project management

Six sigma project management Six sigma project management Bizagi Suite Six sigma project management 1 Table of Contents Six Sigma Project Management... 3 Process Elements... 9 Project Charter... 9 Define... 11 Measure...12 Analyze...12

More information

SECTION I PROJECT SUMMARY (TRW)

SECTION I PROJECT SUMMARY (TRW) AS OF OCTOBER 11, 2010 SECTION I PROJECT SUMMARY (TRW) Table I Project Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Project Director: Tom McCullion

More information

Development, Acquisition, Implementation, and Maintenance of Application Systems

Development, Acquisition, Implementation, and Maintenance of Application Systems Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of

More information

Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R.

Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R. August 2007 Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R. Max Wideman This series of papers has been developed from our work

More information

Independent Verification and Validation of SAPHIRE 8 Software Project Plan

Independent Verification and Validation of SAPHIRE 8 Software Project Plan INL/EXT-09-17022 Rev. 2 Independent Verification and Validation of SAPHIRE 8 Software Project Plan March 2010 The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance

More information

Contract Administration

Contract Administration Chapter 5 Contract Administration Section 3 Change Orders 5-301 General 5-302 Change Order Policy 5-303 Purpose of Change Orders 5-304 Initiation of Change Orders 5-305 Preliminary Considerations 5-306

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections

POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections Policy Subject: Policy Number: Project Management 1.1.5 Date of Issue: Authority: Effective Date: May 29, 2009 Signature on File

More information

PROJECT SCOPE CHANGE MANAGEMENT PLAN

PROJECT SCOPE CHANGE MANAGEMENT PLAN PROJECT SCOPE CHANGE MANAGEMENT PLAN Clark County School District Report date: June 28, 2013 Objectives: Change Management Guidelines Roles and Responsibilities Change Management Process 2 Table of Contents

More information

Introduction. Change Management Approach. Definitions of Change

Introduction. Change Management Approach. Definitions of Change Introduction Start the development of your Project Change Management Plan with this template. Download the Micro Change Management is an important part of any project. Changes must be vetted and managed

More information

Certification Exam Objectives: PK0-003

Certification Exam Objectives: PK0-003 Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate

More information

Module 1 Diploma of Project Management

Module 1 Diploma of Project Management Module 1 Diploma of Project Management Project Management Fundamentals in association with This two day course takes participants through all aspects of Project Management and provides in depth examination

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices : A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it

More information

Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes

Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure

More information

Partnering for Project Success: Project Manager and Business Analyst Collaboration

Partnering for Project Success: Project Manager and Business Analyst Collaboration Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,

More information

National IT Project Management Methodology

National IT Project Management Methodology NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology Project Reporting Support Guide Version 0.5 Project Reporting Support Guide version 0.5 Page 1 Document Version

More information

Overview of Florida Information Technology Project Management and Oversight Standards. Jason M. Allison, Executive Director

Overview of Florida Information Technology Project Management and Oversight Standards. Jason M. Allison, Executive Director Overview of Florida Information Technology Project Management and Oversight Standards Jason M. Allison, Executive Director AGENCY FOR STATE TECHNOLOGY Statutory duties and responsibilities of AST: Establish

More information

Project Management Plan Template

Project Management Plan Template Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION

More information

Project success depends on

Project success depends on Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?... CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........

More information

MINNESOTA STATE POLICY

MINNESOTA STATE POLICY Version: 2.00 Approved Date: 02/24/2012 Approval: Signature on file MINNESOTA STATE POLICY From the Office of Carolyn Parnell Chief Information Officer, State of Minnesota IT Project Portfolio Data Management

More information

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs - Project Information Existing Conditions Cracked and settled pavement. Structural failure within the asphalt pavement section. Anticipated Project Elements Reconstruction of all asphalt pavement on US Route

More information

Successfully Market your PMO

Successfully Market your PMO Successfully Market your PMO Tom Mochal President, TenStep, Inc 1 Agenda Background PMO Communication Plan Marketing the value 2 High-level Value Proposition Companies define goals/strategies toward a

More information

NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services

NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE Head, Office of Project Support Services

More information

STIP Process to Add NY Works Accelerated Bridge & Pavement Preservation Programs

STIP Process to Add NY Works Accelerated Bridge & Pavement Preservation Programs STIP Process to Add NY Works Accelerated Bridge & Pavement Preservation Programs Frequently Asked Questions (FAQ s) 1 - What is this accelerated transportation program? In December 2011, Governor Cuomo

More information

Baseline Change Control Procedure

Baseline Change Control Procedure Earned Value Management System (EVMS) Implementing Procedures Baseline Change Control Procedure EVMS-P-7 Revision 0 - October, 2006 Change Log Earned Value Management System Procedure Change Log Revision

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

How To Manage Transportation Asset Management

How To Manage Transportation Asset Management 1 TRANSPORTATION ASSET MANAGEMENT THE NEW BUSINESS MODEL FOR TRANSPORTATION AGENCIES Presented at the AASHTO Subcommittee on Transportation Finance Policy Business Meeting Irvine, California June 26, 2012

More information

Project Management. On-Site Training and Facilitation Services. www.performanceweb.org. For more information, visit

Project Management. On-Site Training and Facilitation Services. www.performanceweb.org. For more information, visit Project Management On-Site Training and Facilitation Services For more information, visit www.performanceweb.org Benefits of On-Site Training The Performance Institute s proven consulting methodology is

More information

U.S. Department of Education Federal Student Aid

U.S. Department of Education Federal Student Aid U.S. Department of Education Federal Student Aid Lifecycle Management Methodology Version 1.3 06/30/15 Final DOCUMENT NUMBER: FSA_TOQA_PROC_STGRW.NA_001 Update History Lifecycle Management Methodology

More information

INDOT Professional Services Contract Administration Manual Vers. 1/9/15

INDOT Professional Services Contract Administration Manual Vers. 1/9/15 INDOT Professional Services Contract Administration Manual Vers. 1/9/15 Table of Contents Chapter 1 Consultant Contracting General... 1 Introduction... 1 1.1.1 Determination of Need... 1 1.1.2 Initiation

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

The Fast Track Project Glossary is organized into four sections for ease of use:

The Fast Track Project Glossary is organized into four sections for ease of use: The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face

More information

CMS Policy for Configuration Management

CMS Policy for Configuration Management Chief Information Officer Centers for Medicare & Medicaid Services CMS Policy for Configuration April 2012 Document Number: CMS-CIO-POL-MGT01-01 TABLE OF CONTENTS 1. PURPOSE...1 2. BACKGROUND...1 3. CONFIGURATION

More information

How To Plan For A Home Security Grant Program

How To Plan For A Home Security Grant Program U. S. D E P A R T M E N T O F H O M E L A N D S E C U R I T Y FISCAL YEAR 2014 HOMELAND SECURITY GRANT PROGRAM INVESTMENT JUSTIFICATION PLANNING GUIDE: INSTRUCTIONS, IJ TEMPLATE AND PROJECT WORKSHEET MARCH

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Grant that we may not so much seek to be understood as to understand. ~St. Francis of Assisi Daniel B. Edds, MBA. PMP FCS GROUP WFOA Annual Conference, September 2008

More information

Information Technology Governance Overview and Charter

Information Technology Governance Overview and Charter Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author

More information

Consulting Services for CORPORATE SPONSORSHIP ASSET INVENTORY & VALUATION

Consulting Services for CORPORATE SPONSORSHIP ASSET INVENTORY & VALUATION REQUEST FOR PROPOSALS RFP No. 14-01-11 Consulting Services for CORPORATE SPONSORSHIP ASSET INVENTORY & VALUATION Proposals will be received on or before 2:00 pm local time Wednesday, February 19, 2014

More information

Incident Standard Service Request Information Request. IT Request. Minor/Low Impact Change to Existing Service. Capture and refine the idea

Incident Standard Service Request Information Request. IT Request. Minor/Low Impact Change to Existing Service. Capture and refine the idea Incident Standard Service Request Information Request IT Request Idea Capture and refine the idea Determine the type of work Minor/Low Impact to Existing Service Mgmt. Work with customer, management to

More information

Common Application Form

Common Application Form New York/New Jersey Area Application Form The foundations and corporations that developed this common application form hope it will help nonprofit organizations in the New York/New Jersey area save time

More information

1200 Project Control System Procedures

1200 Project Control System Procedures Control System Manual Jefferson Science Associates, LLC 1200 Control System Procedures 1200 Control System Procedures Control System Manual Revision 7-102 - Control System Manual PCS-01 Schedule Planning

More information

Advanced Topics for TOGAF Integrated Management Framework

Advanced Topics for TOGAF Integrated Management Framework Instructor: Robert Weisman MSc, PEng, PMP CD Robert.weisman@buildthevision.ca Advanced Topics for TOGAF Integrated Management Framework ROBERT WEISMAN CEO BUILD THE VISION, INC. WWW.BUILDTHEVISION.CA EMAIL:

More information

WVU. PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members. Robert C. Byrd Health Sciences Center Chancellor s Office

WVU. PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members. Robert C. Byrd Health Sciences Center Chancellor s Office WVU Robert C. Byrd Health Sciences Center Chancellor s Office PROJECT MANAGEMENT LITE Training Manual for Project Managers and Team Members Fostering a culture of high purpose, accountability & accomplishment

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

ACESS A Comprehensive Enterprise Social Services System

ACESS A Comprehensive Enterprise Social Services System State of Louisiana Department of Social Services ACESS A Comprehensive Enterprise Social Services System Scope and Change Management Plan Deliverable AC07 APRIL 27, 2005 VERSION 2.0 State of Louisiana

More information

Systems Approach Workbook Communications Tools: Developing a Communications Plan

Systems Approach Workbook Communications Tools: Developing a Communications Plan Systems Approach Workbook Communications Tools: Developing a Communications Plan Why a Communications Plan? Improving the quality, accessibility and range of services and supports for substance use in

More information

Charter & Scope Statement Web & Portal Redesign. Brookdale Community College

Charter & Scope Statement Web & Portal Redesign. Brookdale Community College Charter & Scope Statement Web & Portal Redesign Brookdale Community College May October, 2012 Table of Contents PROJECT PURPOSE AND JUSTIFICATION 3 EXECUTIVE SUMMARY 3 PROJECT SCOPE AND DELIVERABLES PROJECT

More information

Project Management Topics

Project Management Topics S E C T I O N II T W O Project Management Topics SECTION II: PROJECT MANAGEMENT TOPICS TABLE OF CONTENTS Introduction 3 1. PROJECT TRIAGE 5 1.1 Gather the Data 7 1.2 Review and Analyze the Data 10 1.3

More information

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012

LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE

More information

INFORMATION TECHNOLOGY PROJECT REQUESTS

INFORMATION TECHNOLOGY PROJECT REQUESTS INFORMATION TECHNOLOGY PROJECT REQUESTS Guidelines & Instructions for Maryland State Agencies Revised Two Step PPR/PIR Approval Process Fiscal Year 2013 Table of Contents Part 1: Overview... 2 1.1 Introduction...

More information

This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>.

This is the software system proposal document for the <name of the project> project sponsored by <name of sponsor>. Guide to Preparing the SOFTWARE PROJECT MANAGEMENT PLAN R. Buckley CSc 190 Senior Project Department of Computer Science - College of Engineering and Computer Science California State University, Sacramento

More information