1 Project Charter Human Resource Management System (HRMS) Replacement - Implementation Project Number: 2209 Final Version: 1.0 Date: June 5, 2012

2 Distribution List: Name Dan Guimond MaryAnn Kempe Heather Reichert Dale Bezte Ginette Johnston John Remillard Gary Dessler Chad Bisko Shawn Campbell Title, Department Vice-President, Strategy & Innovation and Chief Information Officer (CIO) Vice-President, Community & Corporate Relations Vice-President, Finance & Chief Financial Officer Executive Director, BTO Director, Project Delivery Director, Business Strategy Chief Technical Architect Project Director and Business Strategy Solutions Architect EPMO Template Updated: March, 2011 ii

3 Table of Contents 1 INTRODUCTION PROJECT PURPOSE (WHY) REFERENCES PROJECT OBJECTIVES (WHAT) PROJECT SCOPE SCOPE OF WORK (INCLUSIONS) OUT OF SCOPE (EXCLUSIONS) RELATED DEPENDENCIES HIGH LEVEL DELIVERABLES PROJECT STRATEGY (HOW) IMPLEMENTATION ROADMAP PROPOSED IMPLEMENTATION ROADMAP PHASE DURATION GUIDELINES PROJECT BUDGET PROJECT ORGANIZATION (WHO) PROJECT PLANNING TEAM: EXTERNAL ORGANIZATIONS INVOLVED IN PROJECT EXECUTION ORGANIZATION GOVERNING THE PROJECT KNOWN PROJECT CONSTRAINTS DEPENDENCIES ASSUMPTIONS AUTHORIZATION EPMO Template Updated: March, 2011 iii

4 1 INTRODUCTION This Project Charter summarizes the business and management aspects of the Human Resource Management System (HRMS) Replacement project. When signed by the sponsor(s), this charter serves as an agreement between the business and the project groups, formally authorizes the existence of the project, and gives authorization for the Project Manager to engage resources in the planning and execution of the project activities, based on the conditions established. 2 PROJECT PURPOSE (WHY) In 2009, Manitoba Public Insurance (MPI) undertook a review of its existing HRMS application, referred to as HR Director. The results of that review determined the system did not meet the current or anticipated future human resource needs of the organization. The limited capabilities of the existing system, especially related to human resource and time and expense management, and talent management including recruitmet and selection, requires a large number of business and operational processes to be completed manually. In addition, the system provides limited opportunities for integration to other support systems, including but not limited to Payroll and Training and Development, necessitating the manual entry of the same data into multiple systems. This results in increased cost, lower productivity and discrepancies in data across systems. The overall purpose of this project is to replace the existing HRMS application with a solution that will provide Manitoba Public Insurance with a fully integrated and automated solution which supports and enables: Achievement of the corporation s business strategies Key Human Resource and Finance activities including, but not limited to: Talent Aquisition (including Workforce Planning) Personnel Management (including Employee transaction mgmt, Position mgmt, Labour Relations support, Organizational Charts and employee contact database) Compensation & Benefits administration Job Evaluation Payroll Time & Expense and Absence reporting Performance Management (including Training Development and Succession management) System interfaces with key vendors such as Civil Service Superannuation Board (CSSB) and Manitoba Blue Cross Employee and Manager self-service Solution to be best-in-class, delivering a full suite of functions and capabilities to meet the current and future needs of the corporation. EPMO Template Updated: March,

5 2.1 REFERENCES Applicable references include these documents and/or spreadsheets: 1. Submission to the Human Resource Committee of the Board of Directors of Manitoba Public Insurance (January 27, 2010) 2. Human Resource Divisional Review (March, 2009) 3. Human Resource Management Information System Review (comparison of Manitoba Public Insurance human resource management functions to capabilities of new HRMS solutions) (August 19, 2008) 4. Desired State Report - Human Resources Division (September 18, 2008) 5. Lawson Software Americas, Inc. Statement of Work For Manitoba Public Insurance Corporation (April 2011) 6. HRMS Replacements (Decisions) presented to Management Committee (May8) 7. Lawson Licensing Overview presented to Management Committee (May8) 8. Lawson Software America, Inc. Change Order-006 WorkBrain (May 31, 2012) 9. Lawson Software America, Inc. Change Order-007 LTM, Upgrade to LTM10 (May 31, 2012) 3 PROJECT OBJECTIVES (WHAT) Over the next two years, Manitoba Public Insurance will replace the existing human resource management system with a solution that will provide the corporation with a fully integrated and automated solution which supports and enables the achievement of the Corporation s business strategies and key human resource activities. An integrated HRMS solution will allow the Corporation to continue to transform how HR services are delivered to employees by standardizing human resources processes and eliminating time-consuming manual processes. As well, employees will be given access to view and maintain their own human resource information and managers will be given access to key data about their direct reports. With this advanced automation and self-service functionality, administration will be minimized so employees can focus on delivering outstanding customer service. EPMO Template Updated: March,

6 4 PROJECT SCOPE 4.1 SCOPE OF WORK (INCLUSIONS) Functional Scope The project will be implemented in a phased approach. Four phases are recommended: Phase 1 - Lawson Upgrade has been completed (Reference Lawson 9.01 Upgrade Charter), Phase 2 - HRMS Core Global HR Human Resource Management Payroll Benefits Administration Absence Management Employee and Manager Self Service Time Entry and Administration Organization Charts (OrgPlus Enterprise and Blueprint) Phase 3 - Lawson Talent Management (LTM) Part 1 Talent Acquisition Compensation Performance Management Goals Management Expense Management Project and Activity management Job Evaluation Phase 4 - Lawson Talent Management (LTM) Part 2 Learning & Development Succession Management Priorities for Phases 3 and 4 can be reassessed during planning for Phase 3 of the project. Technical Scope Lawson Process Flow Integrator (PFI) Lawson Business Intelligence (LBI) Lawson Security 9.0 Necessary infrastructure (hardware, network, and database) and appropriate personnel required to operate and manage the infrastructure. Four instances of S3 Back applications will be installed for Development, Test, Production, and Production Support/Disaster Recovery. EPMO Template Updated: March,

7 Four instances of Lawson Talent Management, plus the Landmark Foundation (base functionality required to run the application) will be installed for Development, Test, Production, and Production Support/Disaster Recovery. Two instances of Time Entry will be installed for Test and Production. Lawson Learning Accelerator Two instances of Travel Expense Management, plus the Landmark Foundation will be installed for Development/Test, and Production/Production Support/Disaster Recovery. Two instances of Lawson Business Intelligence suite will be installed for Development/Test, and Production/Production Support/Disaster Recovery. Two instances of OrgPlus Enterprise and Blueprint will be installed for Test and Production. 4.2 OUT OF SCOPE (EXCLUSIONS) The following items are explicitly outside the scope of this project. Lawson Resource Navigator. 4.3 RELATED DEPENDENCIES The following is a list of dependencies which are related to the HRMS Replacement Project: Lawson 9.01 Upgrade Project - This project will upgrade the current Lawson technical environment to supported versions (LSF 9.0.1). Lawson s Human Resource Management suite of products shares the technical environment (the S3 Stack ) with Lawson Finance and Procurement applications. Corporate Portal (employee self service) Learning Management System (LMS) Corporate Intranet upgrade / re-engineering Performance Management Project (ACHIEVE Form) Data Center transition Rollout of new desktops 4.4 HIGH LEVEL DELIVERABLES The deliverables identified in this section are subject to refinement. These and other project related deliverables will be identified in the project plan and all will undergo formal review and signoff by the Project Acceptor. 1. Project Plans for HRMS Core, Quality Plan and Risk Assessment 2. Lawson Statement of Work for professional services and Product Order Form for software licensing. 3. Business Model / Business Requirements / Business Process Surveys 4. Lawson Operational Systems (Hardware, Applications, Database) for Development, Test, Production, and Production Support. 5. Business Process Documentation (Process nodes, process profiles, Job Instructions, Policies, and Procedures) 6. Data Migration and Conversion Strategy and Routines. EPMO Template Updated: March,

8 7. Approved customizations and required interfaces, reports, workflows, and alerts. 8. Test Strategy, Test Plan, and Test Scripts/Cases 9. Acceptance Test 10. Training Strategy, Training Plan, and Training Program 11. Communication Strategies and Plan. 12. Change Management Plan and other Change Management deliverables. 13. Implementation Strategy and Implementation Plan 14. Revised Disaster Recovery Plan EPMO Template Updated: March,

9 5 PROJECT STRATEGY (HOW) Project Management This project will be a joint effort between Lawson Professional Services and Manitoba Public Insurance. A Lawson Project Manager will work directly with Manitoba Public Insurance s Project Manager to plan, execute, and monitor the project. Throughout the delivery of the product(s) or service(s) described in this Charter, the Manitoba Public Insurance Project Manager will use the Manitoba Public Insurance Enterprise Project Management Methodology and EPMO Toolkit to provide the framework for managing the project. Implementation Methodology A hybrid methodology consisting of Lawson s StepWise Implementation Approach and Methodology and Manitoba Public Insurance s methodology will be followed/maintained throughout the life of this project. Business Vision/Requirements During the Establish phase of the project, workshops will be held to confirm Manitoba Public Insurance s business vision/business model and guiding principles for the Human Resource Management System. The project team will also be oriented and trained on Lawson applications before requirements are finalized so the team can better understand available options. Lawson consultants will engage with his or her respective business subject matter expert or process owner to confirm details required for each process area. The consultant uses a prepared set of questions (Business Process Survey) to ensure that all necessary information is obtained. This information is used to confirm the Statement of Work and validate business needs. This ensures that the project team is well prepared to build the initial beta prototype. Lawson consultants will explain only the application and validation processes relevant to MPI's specific solution, rather than every solution option available. In addition, Lawson will use information gathered during the Business Process Survey phase to create an initial beta version. MPI will validate each version before the next is built. Customizations A guiding principle of this project is to re-design existing Manitoba Public Insurance business processes and operations to align to the way the Lawson solution operates. Manitoba Public Insurance senior leadership has provided direction that the project to replace the HRMS application should be one of configuring a commercially available (COTS) solution and that Manitoba Public Insurance processes would, wherever possible, be modified to align with the new solution. Customization of the solution should be limited to those areas where the base solution cannot support specific and unique business, regulatory, and collective bargaining requirements. While no customizations have been identified to date, some customizations are typically identified. A formal change control process will be implemented to review and approve customizations both during the project and on a go-forward basis after implementation. EPMO Template Updated: March,

10 Some Lawson technical consulting hours will be included in the Lawson Statement of Work to implement approved customizations. Data Migration and Conversions Manitoba Public Insurance will be responsible extraction of data from legacy systems, transformation and cleansing/rationalization of data, then loading of cleansed data into Lawson. Lawson will provide the following guidance and support: Asssist with extraction and mapping. Provide data mapping tools. Deliver Data Migration workshops to define the data migration process and mapping required. Collaborate with Manitoba Public Insurance Corporation during workshops to define strategy, approach, tools and timing required for migration activities. Provide data mapping guidance during workshops between Manitoba Public Insurance Corporation's source and Lawson target systems. Provide guidance on data cleansing issues as necessary. Manitoba Public Insurance will be responsible for confirming and validating converted data. Interfaces Lawson is responsible for development of the interface from Time Entry. Both Lawson and Manitoba Public Insurance will share the responsibility for all other interfaces. Lawson will provide the following guidance and support: Deliver interface training on Lawson tools, including best practices for interface development via Process Automation Interface Workshop. Technical consulting hours will be included in the Lawson Statement of Work to assist Manitoba Public Insurance in development and Quality Assurance reviews of interfaces. Reports, Alerts, and Workflows Lawson and Manitoba Public Insurance will share the responsibility for development or modification of reports, process flows (workflows), and alerts. Lawson will provide knowledge transfer to MPI s Support resources on the components that Lawson is responsible for developing and will provide the following guidance and support: Deliver training on Lawson tools, including Lawson Business Intelligence (reports), and workflows. Technical consulting hours will be included in the Lawson Statement of Work to assist Manitoba Public Insurance in development and Quality Assurance reviews of the reports, alerts, and workflows that Manitoba Public Insurance will be responsible for. Training Training on Lawson applications for the project team members will be primarily delivered through a combination of class room training and workshops onsite at Manitoba Public Insurance. There is also a web-based online learning suite that is available to team members. EPMO Template Updated: March,

11 Technical training (System Administration, Security) will be delivered at Lawson training centres. A train the trainer approach will be followed for delivery of training for Manitoba Public Insurance end-users. Knowledge Management Services (KMS) typically prepares, delivers and maintains MPI training material. KMS will not be responsible for delivering the training materials. The project team may require some support which will be explored during the project. As a result, the project team will be responsible for development of training materials, and delivery of training to end users. Deliverables will be included in the project plan to: Clarify who, how and what tools should be used to develop and deliver HRMS training material Determine if and how KMS's quality standards for training format and content will be adhered to. Clarify whether KMS will ultimately inherit the HRMS training material when choosing tools, styles, etc Confirm KMS engagement and accountability 6 Implementation Roadmap 6.1 PROPOSED IMPLEMENTATION ROADMAP Year 1 Year 2 Year 3 Q1 Q2 Q3 Q4 Q5 Q6 Q7 Q8 Q9 Revised Implementation Roadmap Phase 1 - Lawson Upgrade Phase 2 Planning Phase 2 - HRMS Core Phase 3 - LTM Part 1 Phase 4 - LTM Part 2 Global HR, Human Resources, Personnel Admin, Payroll, Absence Reporting, Benefits Admin, Lawson Security 9.0- HRMS and Financials,Self Service Time Reporting,Self Service for Managers, Organization Charts Talent Acquisition, Compensation, Performance and Goal Management, Expense Management Job Evaluation, Project and Activity Accounting Learning and Development, Succession Planning 6.2 PHASE DURATION GUIDELINES Phase Duration in Months 1 Financial Upgrade 6 2 HRMS Core 18 3 LTM Part LTM Part 2 4 Duration based on Lawson experience. EPMO Template Updated: March,

12 7 PROJECT BUDGET A budget amount of $10,000,000 has been established for this project. At the point of writing, the above estimated budget is based on the functionality to be delivered as per scope, through the implementation of the Lawson HRMS Core and Lawson Talent Management components. It should be noted that Finance is in the process of evaluating the Lawson functionality that is being leveraged by Finance. As well, detailed planning is underway based on the content of this charter and from the results of the the business realization of the requirements that is currently underway. This could also futher impact the high level estimate budget once the configuration of the full implementation has been defined, assigned and scheduled. EPMO Template Updated: March,

13 8 PROJECT ORGANIZATION (WHO) 8.1 PROJECT PLANNING TEAM: NAME Ginette Johnston John Remillard Chad Bisko ROLE Director, Project Delivery Director, Business Strategy Project Director and Business Relationship Manager Cathy Gamby Shannon Leppky Director, Human Resources Director, Staff Development & Change Services Diane Hopkins Manager, Financial Services Gary Dessler Corporate Technical Architect Shawn Campbell Solutions Architect 8.2 EXTERNAL ORGANIZATIONS INVOLVED IN PROJECT EXECUTION ORGANIZATION Marie Pebesma ROLE Practice Director Delivery, Lawson Software Beverley Mizun Gille Cutland Lawson Project Manager Implementation Consultant EPMO Template Updated: March,

14 8.3 ORGANIZATION GOVERNING THE PROJECT The BTO Governance will be used in the oversight, management and execution of the HRMS Replacement project: Director, Business Strategy John Remillard Sponsor Dan Guimond VP Business Owner Director EPMO Louis Kolly Management Committee Director EPMS1 John Krupinski Executive Director BTO Dale Bezte Steering Committee Director Project Delivery Ginette Johnston Chief Technical Architect Gary Dessler Director, Project Delivery Ginette Johnston Working Committee Project Control Analyst (Optional) BTO Management Project Manager/ Project Director Committees Vendors External Partners Business Team Lead 2 Technical Architecture Team Lead Technical Team Lead UAT Testing Team Lead Change Management Team Lead Policies and Procedures Team Lead External Communications Team Lead Legal Team Lead Procurement 1 EPMS Enterprise Portfolio Management Services 2 On larger projects Team Lead may have project managers reporting to the Lead 3 Acquire goods or services needed to develop, maintain and repair the Corporation s properties, acquire or lease land and buildings and construct or renovate buildings, as well as purchase and install facilities Business Architecture Team Requirements & Business Scenarios, Forms/Document Changes, System UC & UI Reviews, Support UAT, KMS, CM, Communications, legislation drafting and stakeholder relations Technical Architecture Team Technical Team Technical Delivery, System Testing, Technical Implementation User Acceptance Testing Team Acceptance Testing Change Management Team Technical Training, Non-Technical Training, Internal Communications (align with external), External stakeholders, Human Resource Integrated Training Plan Corporate Directive Policies and Procedures Team Policies & Procedures, Business Process Training, Training Material Development, Application Training, Internet Knowledge Systems (e.g. DSR Calculator) External Communications Team English/French content (Design/Wording) of customer facing materials, forms, pamphlets & partner communications, Web-site amendments Legal Team Prepare procurement docs e.g. Contracts Assist in negotiating contracts Provide legal opinions Assist with evaluation - during Procurement Contract Interpretation Research current legislation Legislation drafting Business Services Goods or services relating to computer hardware, software and related services Premises Services related to facilities 3 Admin Services All other goods or services RFP, RFQ, RFI, RFT infrastructure EPMO Template Updated: March,

15 9 KNOWN PROJECT CONSTRAINTS 9.1 DEPENDENCIES Availability of skilled and knowledgeable Subject Matter Experts (SME's) and other required resources from Manitoba Public Insurance, Lawson Software, Human Concepts (OrgPlus), and ADP. 9.2 ASSUMPTIONS Changes to Manitoba Public Insurance s Chart of Accounts are not extensive. Minor changes (e.g. addition of new accounts) may be required to support integration of Lawson SHCM with Lawson Financials. Existing and alternative training and delivery tools will be reviewed against the requirements of the project, and a recommendation made based on the outcome of that review. EPMO Template Updated: March,

16 AUTHORIZATION Name: Dan Guimond Signature: Original signed by Role: Executive Project Sponsor Date: Name: MaryAnn Kempe Signature: Original signed by Role: VP Business Owner Date: Name: Heather Reichert Signature: Original signed by Role: VP Business Owner Date: Name: Dale Bezte Signature: Original signed by Role: Executive Director, BTO Date: Name: Ginette Johnston Signature: Original signed by Role: Director, Project Delivery Date: Name: John Remillard Signature: Original signed by Role: Director, Business Strategy Date: EPMO Template Updated: March,

HRMS - HRMS Charter - AI.18. Project Charter Human Resource Management System (HRMS) Replacement - Implementation Project Number: 2209.

HRMS - HRMS Charter - AI.18. Project Charter Human Resource Management System (HRMS) Replacement - Implementation Project Number: 2209. Project Charter Human Resource Management System (HRMS) Replacement - Implementation Project Number: 2209 Final Version: 1.0 Date: June 5, 2012 Distribution List: Name Dan Guimond MaryAnn Kempe Heather

More information

KMS Implementation Roadmap

KMS Implementation Roadmap KMS Implementation Roadmap Sample Excerpt Prepared by: The Knowledge Compass, Inc. TABLE OF CONTENTS 1. EXECUTIVE SUMMARY 5 1.1 Overview 5 1.2 Project Goals & Objectives 5 1.3 Implementation Approach 5

More information

SECTION I PROJECT SUMMARY (TRW)

SECTION I PROJECT SUMMARY (TRW) SECTION I PROJECT SUMMARY (TRW) Table I Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Managers: Ron McCranie/Andy Loveland Status Meeting Date:

More information

The Financial Planning Analysis and Reporting System (FPARS) Project: Implementation Status Update

The Financial Planning Analysis and Reporting System (FPARS) Project: Implementation Status Update STAFF REPORT ACTION REQUIRED The Financial Planning Analysis and Reporting System (FPARS) Project: Implementation Status Update Date: March 24, 2014 To: From: Wards: Reference Number: Government Management

More information

How To Implement An Enterprise Resource Planning Program

How To Implement An Enterprise Resource Planning Program ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing

More information

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam 44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION

More information

CARLETON UNIVERSITY POSITION DESCRIPTION. Position Title: Manager, HR Systems Position No.: 298879. Approved by:

CARLETON UNIVERSITY POSITION DESCRIPTION. Position Title: Manager, HR Systems Position No.: 298879. Approved by: CARLETON UNIVERSITY POSITION DESCRIPTION Position Title: Manager, HR Systems Position No.: 298879 Reports to: Department: Assistant Director HR, Talent Programs Human Resources Approved by: (Incumbent/Date)

More information

2. Please describe the project s alignment with the Common System Principles (Appendix 1).

2. Please describe the project s alignment with the Common System Principles (Appendix 1). Project Name Project Summary Please provide the project charter with this request. Please note any changes to the scope or schedule, or budget in this section and any other information you feel necessary.

More information

Performance Audit Concurrent Review: ERP Pre-Solicitation

Performance Audit Concurrent Review: ERP Pre-Solicitation Performance Audit Concurrent Review: ERP Pre-Solicitation April 2002 City Auditor s Office City of Kansas City, Missouri 24-2001 April 10, 2002 Honorable Mayor and Members of the City Council: We conducted

More information

How To Implement Fusion Hcm

How To Implement Fusion Hcm Fixed Scope Offering Fusion HCM Implementation Mindtree limited 2015 Agenda Business Objectives Product Overview Key Implementation Features Implementation Packages & Timelines High Level Scope Implementation

More information

Human Capital Management Mapping a Blueprint to the Cloud. June 25 th, 2 3pm EST

Human Capital Management Mapping a Blueprint to the Cloud. June 25 th, 2 3pm EST Human Capital Management Mapping a Blueprint to the Cloud June 25 th, 2 3pm EST Today s Presenters Stacey Harris VP Research & Analytics @StaceyHarrisHR www.linkedin.com/in/staceyharris/ Richard George

More information

iapps Consulting DWC LLC Fixed Scope Offering (FSO) For Taleo Recruit and On-Boarding Drive Transformation Create Value

iapps Consulting DWC LLC Fixed Scope Offering (FSO) For Taleo Recruit and On-Boarding Drive Transformation Create Value iapps Consulting DWC LLC Fixed Scope Offering (FSO) For Taleo Recruit and On-Boarding Drive Transformation Create Value 18-05-2015 1 About Us We are a technology and business consulting firm, focused on

More information

Bid/Proposal No. P15/9888 Business Intelligence Management

Bid/Proposal No. P15/9888 Business Intelligence Management Answers to Vendor Questions Questions are in black, Answers are in red 1. Who is the Executive Sponsor(s) for this project Information not available at this time 2. Will PCC provide the selected consultant

More information

How To Write An Slcm Project Plan

How To Write An Slcm Project Plan SLCM 2003.1 Artifacts in a Nutshell ( as of 01/21/2005) Project Development Phases Pension Benefit Guaranty Corporation s (PBGC) System Life Cycle Methodology (SLCM) is comprised of five project development

More information

Request for Proposal for Application Development and Maintenance Services for XML Store platforms

Request for Proposal for Application Development and Maintenance Services for XML Store platforms Request for Proposal for Application Development and Maintenance s for ML Store platforms Annex 4: Application Development & Maintenance Requirements Description TABLE OF CONTENTS Page 1 1.0 s Overview...

More information

Information Technology Governance Overview and Charter

Information Technology Governance Overview and Charter Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author

More information

Colorado Department of Health Care Policy and Financing

Colorado Department of Health Care Policy and Financing Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for

More information

PROJECT CHARTER University of Tennessee

PROJECT CHARTER University of Tennessee PROJECT CHARTER University of Tennessee Table of Contents 1 Introduction 1.1 Overview 1.2 Statement of Work Conflicts 1.3 Project Objectives 1.4 Benefits 1.5 Project Assumptions and Constraints 2 Scope

More information

REQUEST FOR INFORMATION (RFI) for Time Data Collection Solutions for The CITY OF PHILADELPHIA. Issued by:

REQUEST FOR INFORMATION (RFI) for Time Data Collection Solutions for The CITY OF PHILADELPHIA. Issued by: REQUEST FOR INFORMATION (RFI) for Time Data Collection Solutions for The CITY OF PHILADELPHIA Issued by: The Office of Innovation and Technology (OIT) October 6th, 2015 Submission Due Date: November 2nd,

More information

ID Task Name Time Pred

ID Task Name Time Pred 0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive

More information

Solution Architecture Framework Toolkit

Solution Architecture Framework Toolkit Solution Architecture Framework Toolkit Health and Human Services Agency, Revision History REVISION HISTORY REVISION/WORKSITE # DATE OF RELEASE OWNER SUMMARY OF CHANGES Initial Release (v1.0) December

More information

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Today s Business Challenges Adopt leading CRM practices and stream line processes Take advantage

More information

Qlik UKI Consulting Services Catalogue

Qlik UKI Consulting Services Catalogue Qlik UKI Consulting Services Catalogue The key to a successful Qlik project lies in the right people, the right skills, and the right activities in the right order www.qlik.co.uk Table of Contents Introduction

More information

Company A Project Plan

Company A Project Plan Company A Project Plan Project Name: Close Optimization Project Example Prepared By: David Done - Project Manager Title: John Doe -Project Manager Date: March 17, 2011 Project Plan Approval Signatures

More information

Fixed Scope Offering for Oracle Fusion HCM. Slide 1

Fixed Scope Offering for Oracle Fusion HCM. Slide 1 Fixed Scope Offering for Oracle Fusion HCM Slide 1 Today s Business Challenges Adopt leading Global HCM practices. Streamline the HCM processes and achieve measurable efficiencies. Achieve HR excellence

More information

SECTION I PROJECT SUMMARY (TRW)

SECTION I PROJECT SUMMARY (TRW) AS OF OCTOBER 11, 2010 SECTION I PROJECT SUMMARY (TRW) Table I Project Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Project Director: Tom McCullion

More information

Accenture Human Capital Management Solutions. Transforming people and process to achieve high performance

Accenture Human Capital Management Solutions. Transforming people and process to achieve high performance Accenture Human Capital Management Solutions Transforming people and process to achieve high performance The sophistication of our products and services requires the expertise of a special and talented

More information

Standards for Developing and Implementing Administrative Systems at UC Davis

Standards for Developing and Implementing Administrative Systems at UC Davis Page 1 of 7 Standards for Developing and Implementing Administrative Systems at UC Davis Introduction The purpose of this document is to describe Standards for Developing and Implementing Administrative

More information

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing

Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing STATE OF MICHIGAN SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing Executive Summary The State of Michigan has dedicated integrated team of resources for the

More information

Exhibit F. VA-130620-CAI - Staff Aug Job Titles and Descriptions Effective 2015

Exhibit F. VA-130620-CAI - Staff Aug Job Titles and Descriptions Effective 2015 Applications... 3 1. Programmer Analyst... 3 2. Programmer... 5 3. Software Test Analyst... 6 4. Technical Writer... 9 5. Business Analyst... 10 6. System Analyst... 12 7. Software Solutions Architect...

More information

Three Strategies for Implementing HR in the Cloud

Three Strategies for Implementing HR in the Cloud Three Strategies for Implementing HR in the Cloud Adoption of cloud-based, software-as-a-service (SaaS) human resource management systems (HRMS) has become one of the hottest trends in HR. According to

More information

Planning an ERP Implementation Project @ Small and Medium Enterprises

Planning an ERP Implementation Project @ Small and Medium Enterprises Planning an ERP Implementation Project @ Small and Medium Enterprises 27 th Regional WIRC Conference 31 August 2012 Table of Contents What is an SME and ERP Why an ERP for the SME segment Assessing the

More information

HR Strategic Design Initiative. Project Status. June 2015

HR Strategic Design Initiative. Project Status. June 2015 HR Strategic Design Initiative Project Status June 2015 Embarked upon the HR Strategic Design Initiative Objectives Develop a thorough and fact-based understanding of the University s HR requirements Design

More information

Development, Acquisition, Implementation, and Maintenance of Application Systems

Development, Acquisition, Implementation, and Maintenance of Application Systems Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of

More information

TAMUS HR/Payroll System Selection Evaluation Process

TAMUS HR/Payroll System Selection Evaluation Process The Texas A&M University System Revised 9/19/2014 Version 1.0 Contents 1 - Objectives... 1 2 - Deliverables... 1 3 - Evaluation Team... 1 3.0 Team Member Responsibilities... 1 3.1 Team Composition... 2

More information

Information Technology Services Project Management Office Operations Guide

Information Technology Services Project Management Office Operations Guide Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...

More information

HR Technology Strategies that Work in Healthcare. Background

HR Technology Strategies that Work in Healthcare. Background HR Technology Strategies that Work in Healthcare Shawn Davis Intermountain Healthcare Background Shawn Davis Director, HR Workforce Solutions & Analytics IHRIM Board of Directors (2009-2011) HRIP Certification

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : BearBuy Implementation PREPARED BY: Vanessa Wong and Jon Conhaim DATE (MM/DD/YYYY): 07/23/2011 PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED CURRENT STATUS) (MM/DD/YYYY)

More information

Mitel Professional Services Catalog for Contact Center JULY 2015 SWEDEN, DENMARK, FINLAND AND BALTICS RELEASE 1.0

Mitel Professional Services Catalog for Contact Center JULY 2015 SWEDEN, DENMARK, FINLAND AND BALTICS RELEASE 1.0 Mitel Professional Services Catalog for Contact Center JULY 2015 SWEDEN, DENMARK, FINLAND AND BALTICS RELEASE 1.0 Contents MITEL PROFESSIONAL SERVICES DELIVERY METHODOLOGY... 2 CUSTOMER NEEDS... 2 ENGAGING

More information

Iowa State University Proposal for HR-01 ISU HR Operating Model

Iowa State University Proposal for HR-01 ISU HR Operating Model Iowa State University Proposal for HR-01 ISU HR Operating Model Overview: Iowa State University proposes undertaking the HR-01 ISU HR Operating Model business case to transform the quality, manner and

More information

Request for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018

Request for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018 Request for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018 for City of Pitt Meadows Table of Contents Table of Contents... 2 General Information...

More information

The State of Oregon. Department of Procurement Services Issues the Following

The State of Oregon. Department of Procurement Services Issues the Following The State of Oregon Department of Procurement Services Issues the Following Request for Information (RFI) # DASPS-2346-15 For The Oregon Enterprise-wide Human Resource Information System Project Single

More information

Program and Budget Committee

Program and Budget Committee E WO/PBC/21/12 ORIGINAL: ENGLISH DATE: JULY 1, 2013 Program and Budget Committee Twenty-First Session Geneva, September 9 to 13, 2013 PROGRESS REPORT ON THE IMPLEMENTATION OF A COMPREHENSIVE INTEGRATED

More information

COST/FUNDING SOURCE: $549,050/FY2014 and FY2015 Uniform Rate

COST/FUNDING SOURCE: $549,050/FY2014 and FY2015 Uniform Rate AGENDA ITEM C3 DATE: April 7, 2014 TO: FROM: SUBJECT: Matt Jordan, General Manager Charles H. Carden, Chief Operating Officer Computerized Maintenance Management System Implementation Services Award Contract

More information

Domain 1 The Process of Auditing Information Systems

Domain 1 The Process of Auditing Information Systems Certified Information Systems Auditor (CISA ) Certification Course Description Our 5-day ISACA Certified Information Systems Auditor (CISA) training course equips information professionals with the knowledge

More information

MANAGEMENT CONSULTING ENTERPRISE SOLUTIONS IT OUTSOURCING. CAPABILITY briefing

MANAGEMENT CONSULTING ENTERPRISE SOLUTIONS IT OUTSOURCING. CAPABILITY briefing MANAGEMENT CONSULTING ENTERPRISE SOLUTIONS IT OUTSOURCING MILESTONES 1999-Present 8(a) / SDB Certified Woman-Owned Certified GSA Schedule 70 GSA STARS II NAICS Codes 541511, 541512, 541519, 541618, 541611,

More information

2015 2016 HR Systems Survey

2015 2016 HR Systems Survey 2015 2016 HR Systems Survey 18 th Annual Edition Executive Summary Innovation, Insights, and Strategy Conducted by Stacey Harris VP of Research & Analytics Erin Spencer Research Consultant Information

More information

Process Validation Workshops. Overview Session

Process Validation Workshops. Overview Session Process Validation Workshops Overview Session 2 Session Objectives: Prepare staff for participating in a Process Validation Workshop Clarify the Purpose of Process Validation Workshops Clarify Expected

More information

Analysis Item 65: Department of Revenue Property Valuation System

Analysis Item 65: Department of Revenue Property Valuation System Analysis Item 65: Department of Revenue Property Valuation System Analysts: John Borden and Sean McSpaden Request: Allocate $1.5 million from the Emergency Fund for an increase to the Property Valuation

More information

PUB (MPI) 1-62 Reference: Gartner Scorecard

PUB (MPI) 1-62 Reference: Gartner Scorecard Information Requests Round 1 PUB (MPI) 1-62 Reference: Gartner Scorecard PUB/MPI 2-23 2013 GRA a) Please file an update to the response to Gartner s recommendations provided at PUB/MPI 2-23 from last year

More information

Enterprise Project and Portfolio Management Implementation Project. Update to the ETS Customer Utility Board Julie Pearson May 27, 2015

Enterprise Project and Portfolio Management Implementation Project. Update to the ETS Customer Utility Board Julie Pearson May 27, 2015 Enterprise Project and Portfolio Management Implementation Project Update to the ETS Customer Utility Board Julie Pearson May 27, 2015 Why do we need PPM? Office of the State CIO Key Initiatives (from

More information

Department of Defense MANUAL. Procedures for Ensuring the Accessibility of Electronic and Information Technology (E&IT) Procured by DoD Organizations

Department of Defense MANUAL. Procedures for Ensuring the Accessibility of Electronic and Information Technology (E&IT) Procured by DoD Organizations Department of Defense MANUAL NUMBER 8400.01-M June 3, 2011 ASD(NII)/DoD CIO SUBJECT: Procedures for Ensuring the Accessibility of Electronic and Information Technology (E&IT) Procured by DoD Organizations

More information

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance

More information

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010 Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning

More information

Fixed Scope Offering for. Oracle Taleo EE Saas Implementation

Fixed Scope Offering for. Oracle Taleo EE Saas Implementation Fixed Scope Offering for Oracle Taleo EE Saas Implementation Agenda Company Profile Business Challenges Business Objectives Solution Proposal Scope Modules and Functionalities Implementation Approach Project

More information

State of Michigan Department of Technology, Management & Budget

State of Michigan Department of Technology, Management & Budget State of Michigan Department of Technology, Management & Budget Information, Communications and Technology (ICT) Strategy Technical Advisory Services Prepared for: Deliverable F Road Map 24 February 2012

More information

Microsoft Enterprise Project Management 2010 Licensing Guide

Microsoft Enterprise Project Management 2010 Licensing Guide Microsoft Enterprise Project Management 2010 Licensing Guide Microsoft Project 2010 Licensing Microsoft Project 2010 is a family of products that provide a range of functionality depending on organizational

More information

Enterprise Projects Fiscal Year 2009/2010 Third Quarter Report

Enterprise Projects Fiscal Year 2009/2010 Third Quarter Report Enterprise Projects Fiscal Year 2009/2010 Third Quarter Report Enterprise Projects Fiscal Year 2009/2010 - Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance

More information

DOC Electronic Timekeeping System Quarterly Project Oversight Report: Comprehensive Review For Period January March 2015

DOC Electronic Timekeeping System Quarterly Project Oversight Report: Comprehensive Review For Period January March 2015 Department of Corrections Electronic Timekeeping System Project For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Corrections (DOC) Project Name: Electronic Timekeeping

More information

Validating Enterprise Systems: A Practical Guide

Validating Enterprise Systems: A Practical Guide Table of Contents Validating Enterprise Systems: A Practical Guide Foreword 1 Introduction The Need for Guidance on Compliant Enterprise Systems What is an Enterprise System The Need to Validate Enterprise

More information

PHASE 1: INITIATION PHASE

PHASE 1: INITIATION PHASE PHASE 1: INITIATION PHASE The Initiation Phase begins when agency management determines that a business function requires enhancement through an agency information technology (IT) project and investment

More information

2003 Patricia Ensworth Page 1

2003 Patricia Ensworth Page 1 1 1 Sample software development project 2 1.1 Start project 3 1.2 Initiation phase 4 1.2.1 Develop project charter 5 1.2.2 Project charter approved 6 1.3 Planning phase 7 1.3.1 Product activities 8 1.3.1.1

More information

Five Ways to Leverage ERP Investment. 5 Ways to Leverage Your ERP Investment Page 1

Five Ways to Leverage ERP Investment. 5 Ways to Leverage Your ERP Investment Page 1 Five Ways to Leverage ERP Investment 5 Ways to Leverage Your ERP Investment Page 1 Most higher education institutions focus on costs, schedules, hardware, software features, and other technology problems

More information

2015 BUSINESS PLAN PRELIMINARY INITIATIVES/GOALS

2015 BUSINESS PLAN PRELIMINARY INITIATIVES/GOALS 2015 BUSINESS PLAN PRELIMINARY INITIATIVES/GOALS 1 2015 Business Plan & Budget Process Sept 18, 2014 Preliminary 2015 Initiatives/Goals Presented to Board at Strategic Planning Meeting October 20, 2014

More information

Strategic Briefing Data Center Management & Automation

Strategic Briefing Data Center Management & Automation Strategic Briefing Data Center & Automation Contents Why is Data Center & Automation (DCMA) so important? 2 The Solution Pathway: Data Center and Automation 2 Identifying and Addressing the Challenges

More information

FIXED SCOPE OFFERING FOR ORACLE FUSION TALEO CLOUD

FIXED SCOPE OFFERING FOR ORACLE FUSION TALEO CLOUD Vijay Karthick Kumbeswaran Head - Enterprise Human Capital, Finance & Supply Chain Management Practice Email : marketing-communication-in@altimetrik.com Altimetrik is a Business Transformation and Technology

More information

Project Charter CONTOSO, LTD MICROSOFT DYNAMICS CRM IMPLEMENTATION FOR CALL CENTER

Project Charter CONTOSO, LTD MICROSOFT DYNAMICS CRM IMPLEMENTATION FOR CALL CENTER Project Charter CONTOSO, LTD MICROSOFT DYNAMICS CRM IMPLEMENTATION FOR CALL CENTER Prepared for Prepared by Jonathan Haas, Proseware, Inc. Sr Project Manager Proseware, Inc. Table of Contents 1 INTRODUCTION...

More information

Fixed Scope Offering for Implementation of Oracle ERP Financials in Cloud. Oracle ERP Finacials Cloud Offerings

Fixed Scope Offering for Implementation of Oracle ERP Financials in Cloud. Oracle ERP Finacials Cloud Offerings Fixed Scope Offering for Implementation of Oracle ERP Financials in Cloud Oracle ERP Finacials Cloud Offerings 1 Executive Summary Hexaware is pleased to present to you this fixed scope offering for implementation

More information

Facilities Portfolio Management Tool

Facilities Portfolio Management Tool 2016 Facilities Portfolio Management Tool Project Charter Budget- Facilities Oversight Office of Financial Management 4/10/2016 CONTENTS Overview... 2 Purpose Statement... 2 Background... 2 Goals & Objectives...

More information

Federal CIO: Cloud Selection Toolkit. Georgetown University: Chris Radich Dana Christiansen Doyle Zhang India Donald

Federal CIO: Cloud Selection Toolkit. Georgetown University: Chris Radich Dana Christiansen Doyle Zhang India Donald Federal CIO: Cloud Selection Toolkit Georgetown University: Chris Radich Dana Christiansen Doyle Zhang India Donald Agenda Project Introduction Agency Cloud Challenges Toolkit Solution Overview Step 1:

More information

State of Oregon. State of Oregon 1

State of Oregon. State of Oregon 1 State of Oregon State of Oregon 1 Table of Contents 1. Introduction...1 2. Information Asset Management...2 3. Communication Operations...7 3.3 Workstation Management... 7 3.9 Log management... 11 4. Information

More information

DITA Adoption Process: Roles, Responsibilities, and Skills

DITA Adoption Process: Roles, Responsibilities, and Skills DITA Adoption Process: Roles, Responsibilities, and Skills Contents 2 Contents DITA Adoption Process: Roles, Responsibilities, and Skills... 3 Investigation Phase... 3 Selling Phase...4 Pilot Phase...5

More information

OFFICE OF THE STATE SUPERINTENDENT FOR EDUCATION Chief Information Office (CIO) Enterprise Licensing and Case Management Initiative Scope of Work

OFFICE OF THE STATE SUPERINTENDENT FOR EDUCATION Chief Information Office (CIO) Enterprise Licensing and Case Management Initiative Scope of Work C.1 SCOPE OFFICE OF THE STATE SUPERINTENDENT FOR EDUCATION Chief Information Office (CIO) Enterprise Licensing and Case Management Initiative Scope of Work The Government of the District of Columbia, Office

More information

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University. Data Sheet Cisco Optimization s Optimize Your Solution using Cisco Expertise and Leading Practices Optimizing Your Business Architecture Today, enabling business innovation and agility is about being able

More information

Template K Implementation Requirements Instructions for RFP Response RFP #

Template K Implementation Requirements Instructions for RFP Response RFP # Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship

More information

PRECANT CONSULTING PRIVATE LIMITED. Sales Office: No. 17, Inhwa Business Centre, IRIS Tech Park, Gurgaon.

PRECANT CONSULTING PRIVATE LIMITED. Sales Office: No. 17, Inhwa Business Centre, IRIS Tech Park, Gurgaon. PRECANT CONSULTING PRIVATE LIMITED Sales Office: No. 17, Inhwa Business Centre, IRIS Tech Park, Gurgaon. Development Center: D-77, Sector 63, Noida-201301. Phone +91 120 4313630 (India) Mobile +91 91 9910210572,

More information

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS

CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Chapter 3: Managing Implementation Projects CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Objectives Introduction The objectives are: Describe common problems that occur in implementation projects. Describe

More information

ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES

ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES RFP#CON2014-18 Attachments I through VI from the Response Teams will be evaluated and scored (1000 points total) in accordance with the criteria

More information

Understanding Software Project Management PMI fundamentals, Project Selection, Initial documents Emanuele Della Valle http://emanueledellavalle.

Understanding Software Project Management PMI fundamentals, Project Selection, Initial documents Emanuele Della Valle http://emanueledellavalle. Planning and Managing Software Projects 2011-12 Class 3 Understanding Software Project Management PMI fundamentals, Project Selection, Initial documents Emanuele Della Valle http://emanueledellavalle.org

More information

A New Framework for Administrative Applications Governance

A New Framework for Administrative Applications Governance A New Framework for Administrative Applications Governance IT Task Force September 26, 2008 Michael Krugman, Interim VP IST Rafael Reisz, RAFINCO Why are we here? Describe the origin of ERGO framework

More information

trusted efficient responsive best practices HR, Benefits, and Payroll Solutions for Public Sector Employers

trusted efficient responsive best practices HR, Benefits, and Payroll Solutions for Public Sector Employers trusted efficient responsive best practices HR, Benefits, and Payroll Solutions for Public Sector Employers ADP s Enterprise HR Solutions: The Public Sector s HR Answer HR tasks are taxing your resources,

More information

Fixed Scope Offering for Implementation of Taleo

Fixed Scope Offering for Implementation of Taleo Fixed Scope Offering for Implementation of Taleo Mindtree limited 2015 All third party identities used within this presentation are copyrighted properties of the respective companies. Viewers and users

More information

Oakland County Department of Information Technology Project Scope and Approach

Oakland County Department of Information Technology Project Scope and Approach Oakland County Department of Information Technology Project Scope and Approach Project Name: Change Management Integration Project ID: DR0181CM Leadership Group: IT Steering Committee Department: Information

More information

Enterprise Business Systems Change Management Coordinator

Enterprise Business Systems Change Management Coordinator Announcing an Outstanding Career Opportunity Enterprise Business Systems Change Management Coordinator Application Deadline: September 22, 2013 A national search is underway for highly qualified candidates

More information

How To Improve Your Business

How To Improve Your Business IT Risk Management Life Cycle and enabling it with GRC Technology 21 March 2013 Overview IT Risk management lifecycle What does technology enablement mean? Industry perspective Business drivers Trends

More information

Office of the Auditor General AUDIT OF IT GOVERNANCE. Tabled at Audit Committee March 12, 2015

Office of the Auditor General AUDIT OF IT GOVERNANCE. Tabled at Audit Committee March 12, 2015 Office of the Auditor General AUDIT OF IT GOVERNANCE Tabled at Audit Committee March 12, 2015 This page has intentionally been left blank Table of Contents Executive Summary... 1 Introduction... 1 Background...

More information

Auditor General s Office. Governance and Management of City Computer Software Needs Improvement

Auditor General s Office. Governance and Management of City Computer Software Needs Improvement Auditor General s Office Governance and Management of City Computer Software Needs Improvement Transmittal Report Audit Report Management s Response Jeffrey Griffiths, C.A., C.F.E Auditor General, City

More information

I D C M A R K E T S P O T L I G H T. P r i va t e a n d H yb r i d C l o u d s E n a b l e New L e ve l s o f B u s i n e s s and IT Collaboration

I D C M A R K E T S P O T L I G H T. P r i va t e a n d H yb r i d C l o u d s E n a b l e New L e ve l s o f B u s i n e s s and IT Collaboration I D C M A R K E T S P O T L I G H T P r i va t e a n d H yb r i d C l o u d s E n a b l e New L e ve l s o f B u s i n e s s and IT Collaboration September 2013 Adapted from IDC Maturity Model: Cloud A

More information

DHHS Directive Number II-12

DHHS Directive Number II-12 DHHS Directive Number II-12 Title: Delegation of Authority to the Director, Division of Information Resource Management Effective Date: November 3, 2008 Revision History: January 1, 2002 Authority: G.S.

More information

ADMINISTRATIVE SUPPORT AND CLERICAL OCCUPATIONS SIN 736 1

ADMINISTRATIVE SUPPORT AND CLERICAL OCCUPATIONS SIN 736 1 Following are the Contractor Site and Government Site Labor Categories for SIN 736-1, SIN 736-1, and SIN 736-5. Please do not hesitate to contact us at gsataps@amdexcorp.com if you have any questions ADMINISTRATIVE

More information

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development Project Planning and Management (PPM) V2.0 Project Type Guide Custom Development Version 1.1 January 2014 Last Revision: 1/22/2014 Page 1 Project Type Guide Summary: Custom Development Custom software

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

SENIOR INFORMATION SYSTEMS MANAGER

SENIOR INFORMATION SYSTEMS MANAGER CITY OF PORTLAND Multiple SENIOR INFORMATION SYSTEMS MANAGER FLSA Status: Union Representation: Exempt Nonrepresented DEFINITION To plan, manage, supervise and coordinate information systems activities

More information

The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case

The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case Final version for release Human Capital Management See more at psc.nsw.gov.au/hcm Index - Business

More information

PROJECT SCOPE STATEMENT

PROJECT SCOPE STATEMENT PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010

More information

Response to Written Inquiries April 24, 2009 Redesign and Implementation of Improved Cost Allocation Plan

Response to Written Inquiries April 24, 2009 Redesign and Implementation of Improved Cost Allocation Plan Response to Written Inquiries April 24, 2009 Redesign and Implementation of Improved Cost Allocation Plan 1. Should the vendor proposals include proposals for and the price of cost allocation software

More information

U.S. Department of Justice. Mission First...Linking Strategy to Success

U.S. Department of Justice. Mission First...Linking Strategy to Success U.S. Department of Justice Mission First...Linking Strategy to Success Department of Justice Human Capital Strategic Plan 2007-2012 Table of Contents Foreword.......................................................................1

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

ERP Briefing. Cook County Government. Bureau of Finance Enterprise Resource Planning Center of Excellence. August 19, 2014

ERP Briefing. Cook County Government. Bureau of Finance Enterprise Resource Planning Center of Excellence. August 19, 2014 Cook County Government Bureau of Finance Enterprise Resource Planning Center of Excellence ERP Briefing August 19, 2014 DISCLAIMER: This presentation is thought to be accurate on the date it is posted,

More information

Wilhelmenia Ravenell IT Manager Eli Lilly and Company

Wilhelmenia Ravenell IT Manager Eli Lilly and Company Wilhelmenia Ravenell IT Manager Eli Lilly and Company Agenda Introductions The Service Management Framework Keys of a successful Service management transformation Why transform? ROI and the customer experience

More information