1 Department of Corrections Electronic Timekeeping System Project For Period: January March 2015
2 Quarter Ending: 3/31/2015 Agency Name: Department of Corrections (DOC) Project Name: Electronic Timekeeping System Project Description: The Electronic Timekeeping System project is to improve and streamline DOC s current time management processes, replace paper timesheets, avoid costs related to staff overtime, and have a real-time count of correctional officers. The majority of DOC s correctional institution staff, approximately 18,000, are currently unable to enter their work time into the People First personnel system due to computer access limitations and security reasons. As a result, each employee completes, reviews and signs a paper timesheet at the end of each 28 day period. Supervisors then manually approve and timekeepers manually enter the information into People First. DOC has contracted with Kronos for a Software-as-a-Service (SaaS) timekeeping system. Section I: Executive Summary Executive Summary Although it appears best practices planning phase events and artifacts have not been effectively completed, the project is currently in the execution phase. Scope: The project is outside the scope as compared with the Schedule IV-B and the contract s services scope statement for this reporting period. DOC requested $10M for FY ; however, was appropriated $5M. It is unclear how the scope has been adjusted to meet the difference in funding. It appears that both system configuration decisions and changes to goals and objectives have been made without governance review. The Agency for State Technology (AST) has identified deficiencies related to project governance, scope definition and control, requirements documentation and traceability, change control, and contract management practices. Cost: The AST is unable to determine budgetary compliance as there is no spending plan nor have project expenditures been planned over FY Schedule: AST is unable to determine schedule compliance as schedule is incomplete and has never been formally approved by DOC. Risks and Issues: Risks and issues have not remained stable during this reporting period. The project would benefit from active sponsorship, governance, a project management plan and appropriate risk and issues management. AST recommends the immediate charter of a governance body to oversee this project. With active sponsorship, the new leadership team at DOC could enable the alignment of the project with stakeholders needs and objectives. AST and DOC are working closely together on corrective action planning activities to remediate the deficiencies noted herein. 3/31/2015 Page 2
3 Section II: Scope Scope Summary In the absence of project management documentation, AST has used the Schedule IV-B, the Kronos contract, and the Services Scope Statement (SSS). While these sources provide AST with a broad sense of the project s objectives, they are inadequate substitutes for a proper project scope statement that is shared with, and formally approved by, key project stakeholders and team members. Further, since the Kronos agreement was signed, there has been some confusion pertaining to scope (e.g., what is and what is not included in the implementation). A refined scope statement would lend clarity to expectations for success. Although the Schedule IV-B, the Kronos contract, and the Services Scope Statement (SSS) outline minimum requirements and/or success criteria, it is unclear if all requirements will be met since (1) a traceability approach has not been established; and (2) scope has changed without any evidence of change control, governance, or contract amendments. Due to decisions being made without a baselined scope statement and a formal project change control process, it is unclear when decisions were made, by whom they were made, the impact on project objectives, and the impact to contract costs. Scope Variance Discussion There were indications of scope variance when attempting to use the Schedule IV-B, the Kronos contract, and the Services Scope State (SSS) as indicators of intended scope. 1. The contract states the training program is fixed fee and includes all staff training, end-user training, 25 trainthe-trainers and online ongoing training 1. However, rather than planning and tracking the training completed by the number of employees in scope, the training strategy provides consumable training points that do not clearly align to the number of employees, managers, project staff, trainers, etc. found in scope. 2. A contract requirement provides, contractor shall create and provide the department with a web-based tutorial to be used interchangeably where instructor-led training is not feasible, as well as use for ongoing new hire department staff training. However, the employee s training curriculum does not provide for a web-based tutorial. 3. While change management services includes workshops and coaching front-line mangers/supervisors, no direct change management support, coaching or workshop was scheduled prior to the deployment date of June 12, The only change management deliverable provided during this reporting period was an Intranet communication. The Intranet communication may not have been the preferred method for communicating since at least 12,000 employees have limited access to a department computer System testing was scheduled to begin March 1, 2015; however, without requirements traceability, business requirements cannot be traced to design parameters that are included in the delivered system. 1 #C2836; IV. Compensation; A. Payment; Training Program Description; pg. 24 of Schedule IV-B; B. Baseline Analysis; 1 Current Business Process(es); 3 rd paragraph; pg. 5 of 30 3/31/2015 Page 3
4 Scope Variance Discussion 5. Ad hoc reporting is a system requirement. During a Workforce Timekeeper Design Document Review meeting held on March 23, 2015, Kronos stated the system does not provide ad hoc reporting capability. They offered to build ad hoc reports at a cost. 3/31/2015 Page 4
5 Section III: Cost Management Cost Management Summary AST is unable to determine budgetary compliance since there is no spending plan nor have project expenditures been planned over FY Cost Variance Discussion Without a spending plan, AST can only note and speculate specific items that may impact the approved allocation. The vendor charged DOC for training classes without DOC s knowledge or approval and without following DOC training procedures. Training should be for defined audiences at a fixed fee; however, the training approach, training classes, training audience, training objectives, etc. were not clearly defined in the training strategy or in the project schedule. The use of consumable training points rather than the training audiences in scope could result in unanticipated training costs. There may be additional charges for multiple administrator licenses (e.g., Workforce HR/Payroll Administrator 1:100 Ratio) or an additional Human Resource/Payroll license bundle 1. The Product Design documents and training strategy provide for several administrator roles for system configurations. The current Workforce Timekeeper license bundle does not include an administrator 2 and the contract states, the parties agree that department is not licensing Workforce Payroll Software under this contract. 3 As a result, it is unclear if the administrator roles will have the rights to use the system. Organizational Change Management (OCM) referred to as Change Management Services in the Services Scope Statement (SSS) is part of the fixed fee professional services provided by Momentum Enterprise, a subcontractor to Kronos. The fixed fee is $1,363, There are clearly defined Change Management deliverables in the SSS; however, the vendor has submitted an invoice with hours worked rather than associating their invoicing with Change Management deliverables. 1 Contract #C2836; 1. Rights to Use; 1.5; The parties agree that the Department is not licensing Workforce Payroll Software under this Contract. Pg. 38 of81 2 SSS; Order Form; Applications (Invoiced in arrears); Part #/Module column; pg. 80 of 81 3 Contract; VIII. Conditions; M. Copyrights, Right to Use, Patents; 1. Rights to Use; 1.2; pg. 37 of 81. 3/31/2015 Page 5
6 Section IV: Schedule Management Schedule Management Summary The project schedule is managed by the project s vendor, Kronos. The project schedule has not been baselined, has fluctuated and has not been formally approved by DOC. Changes to omissions and deletions, as well as edits to dates of major deliverables have been observed. These changes have occurred without traceability, formal notification or governance action. There was no formal change control process. Omitted deliverables without tasks related to delivery, review, or acceptance, include: Finalize Project Plan/Timeline Project Governance Procedures General Assessment readiness and Pre-Assessment Learning Kronos Quality Assurance Standards Project Governance Signoff Requirements Project Management Procedures Document configuration elements Document recommended processes Document access requirements Training Strategy Testing Strategy Communication Strategy/Plan Detailed Deployment Checklist Plan/Assess Phase Review Deleted Deliverables: Customer Implementation Guide January 19, February 2, Project Workbook or Checklist January 19, February 2, 2015 Edited Deliverables: WTK - Configure and Show Prototypes February 17, March 3, 2015 WTK Configure and Show Security Prototypes February 17, March 4, 2015 The project schedule does not contain all task and deliverable dependencies. 3/31/2015 Page 6
7 Schedule Variance Discussion AST cannot apply best practice methodologies to assess the schedule variance since the schedule is not baselined and appears to be incomplete. 3/31/2015 Page 7
8 Section V: Risk Assessment Evaluation of Project Risks and Issues Kronos maintains an Issue Tracking and Risk Assessment spreadsheet; however, the log does not appear to contain all known risks and issues of the project, nor those identified by DOC. DOC does not have a plan or approach to manage risks and issues that includes an escalation process. As a result, some risks and issues identified in various forums are undocumented, unassigned, and unmanaged. Risk Management Discussion 1. The DOC timekeeping process future state will increase the Officer In Charges daily responsibilities to include any correctional officers exception time reporting (e.g., missed login/log out, sick leave, etc.); whereas, today they only approve officers timesheets every 28 days. 2. DOC has not demonstrated the use of a standard project management methodology in this project. 3. The deliverable review of project artifacts does not indicate executive management involvement. 4. Governance and Change Control was undefined and ad hoc. 5. It does not appear that a DOC contract manager is monitoring the Kronos contract. 6. A DOC testing lead has not been appointed and there is no evidence of testing best practices. 7. This is a configurable system with multiple administrators without the benefit of an operations and maintenance plan or approach. 8. Requirements traceability is non-existent. 9. The only status reporting is provided by the vendor and it may not reflect DOC s risks, issues or view of the current status. 10. Human Resource policies and procedures need to be updated by DOC staff to build in changes due to the new equipment and software. 11. There was insufficient project team manpower for the effort. The engaged project manager was trying to lead the project and the testing and training efforts, control contracted deliverable reviews, mitigate all project risks, manage data quality and scope creep, and serve in his assigned Office of Information Technology duties as the System Programming Administrator for all regions. 3/31/2015 Page 8
9 Section VI: Corrective Action Plan for Out of Variance Projects AST s Recommended Corrective Action Plan (CAP) # Description Action Completion Date Scope S1 S2 S3 S4 S5 S6 Schedule Institute a chartered project governance structure that includes defined roles and responsibilities for each member of the governance team and ensures involvement from executive management. Primary stakeholder identification and involvement in governance is a best practice. A detailed project scope statement must be articulated in a Project Management Plan. Scope should be refined in consultation with the contractor and based on the agreement with the vendor. This statement needs to eliminate any confusion about which deliverables are included and what are excluded. Develop a Project Management Plan that includes scope, risk and issue management (defining escalation to the executive governance team), change management (as described above), a communications plan (the frequency and manner of status reporting to executive governance), quality assurance (how work will be monitored to ensure conformance with best practices), as well as requirements for schedule management. Define and implement a change management process for identifying, escalating, approving (by the executive governance team) project changes related to project scope, schedule, and cost baselines or a change to any project deliverables. Develop a Deliverable Review Plan identifying all the contracted deliverables, identify membership for the deliverable review teams for each deliverable, provide an approach for documenting and aggregating all the deliverable review feedback, develop the process and communications for approving or rejecting deliverables, and develop an escalation process. Identify a Project Sponsor to: 1. Authorize the allocation of resources to the project; 2. Champion the project; 3. Endow the project manager and contract manager with project execution authority. (Planned) Completed 5/4/2015 5/4/2015 In progress 5/22/2015 Completion Date (Actual) Completed 5/4/2015 5/4/2015
10 T1 Cost C1 C2 Risk R1 R2 R3 Update, approve and baseline the project schedule to include: 1. Delivery, review and acceptance of all contract deliverables; 2. All dependencies; and, 3. Capable of utilizing Earned Value Management 1. Assign a contract manager to focus on the contract management obligations associated with this contract. Services Scope Statement s Order Form attached in Contract #C2836 needs to be reviewed for consistency with the Services Scope Statement. Retain a project manager who is: 1. Dedicated to this project, i.e., not splitting time performing other duties 2. PMP certified 3. Experienced managing large, complex projects utilizing a contractor/vendor. Assign a training lead to manage the contracted training effort to ensure: 1. Contractor is training as per contract; 2. The training effort is not exceeding training points; 3. Training staff are assigned to train-the-trainer; and, 4. All 18,200 employees, software administrators, 1,820 supervisors, 25 trainer, and 10 project staff are trained effectively to assume their assigned user roles without increased training costs. Assign a data analyst to: 1. Manage the data quality effort (e.g., inventorying existing data, profiles, cleansing source system data defects, define new drivers, parameters, data objects, number of tables, number of critical data elements); and Completed 4/20/2015 4/20/2015 Completed 5/5/2015 5/5/2015 Pending Click here to 1 The State Term Contract for Information Technology Consulting; RFP No K; Task Order Recommendations. Performance Management System: For Task Orders in Project Areas 1-3, the Department recommends that the Customer require Contractor to have a performance management system to track project cost, schedule, deviations, and status. Such systems should be similar to the earned value project management system that complies with the ANSI Standard on "Earned Value Management Systems Guidelines". Examples can be found at: and 3/31/2015 Page 10
11 R5 R6 R7 R9 2. Ensure all interfaces are importing and exporting data without defects. (e.g., map source data to new system data warehouses, number of tests to be performed, execute migration, test interfaces, test exception reporting capability, address deficiencies and ultimately ensure report reliability (e.g., People First, Roster Management, etc.). Develop an Operations and Maintenance Plan providing support personnel with the information necessary to maintain the system effectively. This document should define the support environment, roles and responsibilities, and scheduled activities essential to support and maintenance. A biweekly status report must be developed and provided to the governance team during scheduled bi-weekly meetings. Select the DOC business process owner to: 1. Ensure there is optimal business fit between people, process, and technology (tool); and 2. Ensure proper key performance indicators are set and achieved. Develop a Requirements Traceability Matrix (RTM) to: 1. Document all system and hardware requirements; 2. Link requirements from their origin to the deliverables that satisfy them; and 3. Capture the progressive detail of the requirements and linkage throughout the project. Pending Click here to Click here to Completed 4/20/2015 4/20/2015 In progress 5/29/2015 Click here to 3/31/2015 Page 11
12 Document Version Control Version Date Change(s).01 3/26/2015 Original Draft.04 4/13/2015 Updated.05 4/20/2014 Updated with Curtis Unruh edits.06 5/6/2015 Updated with DOC edits.07 5/7/2015 Updated with AST & DOC agreed upon edits.08 5/8/2015 Updated with ES, TSK, SM, and BB edits 3/31/2015 Page 12
ID Task Name Time Pred
0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive
PHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
Department of Highway Safety & Motor Vehicles Motorist Modernization Project Phase One
Motorist Modernization Project Phase One For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Highway Safety & Motor Vehicles (HSMV) Project Name: Motorist Modernization
Implementing an HRMS Where Do You Begin. Dino Nosella, PMP
Implementing an HRMS Where Do You Begin Dino Nosella, PMP Thursday Agenda Introduction Definition of HRMS/HRIS The life cycle of Implementing an HRMS/HRIS Questions 1 Definition of HRMS/HRIS? A Human Resources
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
Appeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Attachment 7 Requirements Traceability Matrix (RTM) ATMS RFP. New York State Department of Transportation Advanced Traffic Management System
Attachment 7 Requirements Traceability Matrix (RTM) ATMS RFP New York State Department of Transportation Advanced Traffic Management System i 1. INTRODUCTION This Requirements Traceability Matrix (RTM)
CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS
Chapter 3: Managing Implementation Projects CHAPTER 3: MANAGING IMPLEMENTATION PROJECTS Objectives Introduction The objectives are: Describe common problems that occur in implementation projects. Describe
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
Department of Highway Safety & Motor Vehicles Motorist Modernization Project Phase One
Motorist Modernization Project Phase One For Period: April - June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Highway Safety & Motor Vehicles (HSMV) Project Name: Motorist
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
Draft Document STATE OF MICHIGAN. SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing
STATE OF MICHIGAN SACWIS Planning Department of Human Services Strategic Implementation Plan: Project Staffing Executive Summary The State of Michigan has dedicated integrated team of resources for the
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
PHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services
John Keel, CPA State Auditor The ReHabWorks System at the Department of Assistive and Rehabilitative Services Report No. 12-045 The ReHabWorks System at the Department of Assistive and Rehabilitative Services
WEB-BASED TIME AND ATTENDANCE & DCAA COMPLIANCE
WEB-BASED TIME AND ATTENDANCE & DCAA COMPLIANCE White Paper AUDIT CONCERNS Certain types of organizations who contract with the US Government must follow specific timekeeping guidelines set forth by the
BMC Software Consulting Services. Fermilab Computing Division Service Catalog & Communications: Process and Procedures
BMC Software Consulting Services Service Catalog & Communications: Process and Procedures Policies, Client: Date : Version : Fermilab 02/12/2009 1.0 GENERAL Description Purpose This document establishes
System Development Life Cycle Guide
TEXAS DEPARTMENT OF INFORMATION RESOURCES System Development Life Cycle Guide Version 1.1 30 MAY 2008 Version History This and other Framework Extension tools are available on Framework Web site. Release
Core: WF Analytics Core Scope: 2,500 employees or less
Kronos Workforce Central SaaS Setup Detail Document Scroll down for vertical setup detail : WF Analytics Scope: 2,500 employees or less : Workforce Analytics Scope Workforce Analytics Standard Configuration
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
VoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2
VoteCal Statewide Voter Registration System Project Master Project Management Plan Version 1.2 October 2010 October 2010 i REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF CHANGES 0.1 3/12/2009
CLASS SPECIFICATION. Business Intelligence Supervisor
San Diego Unified Port District Class Code: B843-UE08 CLASS SPECIFICATION FLSA Status: EEOC Job Category: Classified: Union Representation: Exempt Professionals No Unrepresented GENERAL PURPOSE Under general
NuView HRMS & Payroll Training Courses
NuView HRMS & Payroll Training Courses Learning & Development NuView Systems recognizes the importance of a knowledgeable and efficient HR and Payroll staff, who must manage the complexities involved with
PROJECT MANAGEMENT PLAN Florida A&M University Financials Version 9.0 Upgrade and Redeployment
PROJECT MANAGEMENT PLAN Florida A&M University Financials Version 9.0 Upgrade and Redeployment Author: Carl F. Paroby, Oracle Consulting Creation Date: October 24, 2007 Last Updated: Version: DRAFT 3A
Sound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management
3.1 Overview of Software Development and Integration Activities
3 PART 2 SOFTWARE DEVELOPMENT PLAN 3.1 Overview of Software Development and Integration Activities The Development Team will utilize the SDLCM Methodology standards and procedures for all development with
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
The Key to a Successful KM Project
Introduction An integrated PKM methodology enables organizations to maximize their investments by ensuring initiatives are on time and within budget, while sharing project challenges and successes that
CHANGE NOTICE NO. 4 to CONTRACT NO. 071B3200088 between THE STATE OF MICHIGAN and
Form No. DTMB-3521 (Rev. 7/2015) AUTHORITY: Act 431 of 1984 COMPLETION: Required PENALTY: Contract change will not be executed unless form is filed STATE OF MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT
Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
Enterprise Test Management Standards
Enterprise Test Management Standards Version 4.0 09/28/2012 Document Number: FSA_TOADG_STDS_TEST.TMS_001 Document Version Control This section summarizes this document revision history. Each entry includes
Software Quality Assurance Plan
For Database Applications Document ID: Version: 2.1a Planning Installation & Acceptance Integration & Test Requirements Definition Design Development 1 / 54 Copyright 2000-2006 Digital Publications LLC.
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
DCSS Time and Attendance Project
2014 DCSS Time and Attendance Project Dougherty County School System 3/28/2014 Contents Definition of Terms.. 2 Introduction.. 3 Background.. 3 Specifications/Scope of Work.. 3 Current Application Overview..
Enterprise Data Governance
Enterprise Aligning Quality With Your Program Presented by: Mark Allen Sr. Consultant, Enterprise WellPoint, Inc. ([email protected]) 1 Introduction: Mark Allen is a senior consultant and enterprise
How To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
TheFinancialEdge. Converting to Payroll 7
TheFinancialEdge Converting to Payroll 7 101811 2011 Blackbaud, Inc. This publication, or any part thereof, may not be reproduced or transmitted in any form or by any means, electronic, or mechanical,
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
Minnesota Health Insurance Exchange Project (MNHIX) Deliverable Definition Document (DDD) For Project Management Plan Date: 07-31-2012
Minnesota Health Insurance Exchange Project (MNHI) Deliverable Definition Document (DDD) For Project Plan Date: 07-31-2012 11/9/2012 1:18 PM Page 1 of 8 1. High Level Deliverable Description The Project
Initiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP
1 Initiating Forms 1.0 INITIATING PROCESS GROUP The purpose of the initiating process group is to authorize a project, provide a high-level definition of the project, and identify stakeholders. There are
CARLETON UNIVERSITY POSITION DESCRIPTION. Position Title: Manager, HR Systems Position No.: 298879. Approved by:
CARLETON UNIVERSITY POSITION DESCRIPTION Position Title: Manager, HR Systems Position No.: 298879 Reports to: Department: Assistant Director HR, Talent Programs Human Resources Approved by: (Incumbent/Date)
Information Technology Governance Overview and Charter
Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author
UCPath Project Status Report
UCPath Project Status Report Report Date August 23, 2013 Project Director Anthony Lo [email protected] Executive Sponsors Nathan Brostrom Peter Taylor Project Summary Tony Lo has resigned as Project
Fixed Scope Offering for Oracle Fusion HCM. Slide 1
Fixed Scope Offering for Oracle Fusion HCM Slide 1 Today s Business Challenges Adopt leading Global HCM practices. Streamline the HCM processes and achieve measurable efficiencies. Achieve HR excellence
Ellucian Implementation Methodology. Summary of Project Management and Solution Delivery Phases
Ellucian Implementation Methodology Summary of Project Management and Solution Delivery Phases Rev. 5/10/2013 Table of Contents Overview 3 Project Management Initiation 4 Planning 5 Execution 6 Monitor
Appendix G: Organizational Change Management Plan. DRAFT (Pending approval) April 2007
Appendix G: Organizational Change Management Plan DRAFT (Pending approval) April 2007 Table of Contents TABLE OF CONTENTS... 1 INTRODUCTION:... 2 ABT ORGANIZATIONAL CHANGE MANAGEMENT SCOPE... 2 PEOPLESOFT
Overview of Florida Information Technology Project Management and Oversight Standards. Jason M. Allison, Executive Director
Overview of Florida Information Technology Project Management and Oversight Standards Jason M. Allison, Executive Director AGENCY FOR STATE TECHNOLOGY Statutory duties and responsibilities of AST: Establish
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
Streamline your staffing process with a vendor management system that fits your business
Peopleclick VMS Streamline your staffing process with a vendor management system that fits your business Peopleclick VMS is web-based, enterprise-wide vendor management software that automates, tracks
State of XXXXX. Project Name/Phase (Planning Development Implementation) Status Report. Date Ending: Mm/dd/yy
APPENDIX E SAMPLE STATUS REPORT ** This sample report is a suggested guideline, and models the Status Report Checklist found in Appendix D State of XXXXX Project Name/Phase (Planning Development Implementation)
Manager Domain Experts. Delivery Team. C h ic a g o
Outsourc es erv ice Engagement Domain Experts Vendor Account er d i ov Pr Finance Executive Sponsor Bo sto n C h ic a g o Project Empowering Agile with PPM Digite, Inc. 21060 Homestead Rd, Suite 220, Cupertino,
Memorandum. Date: 11.27.13 RE: Citizens Advisory Committee December 4, 2013
Memorandum Date: 11.27.13 RE: Citizens Advisory Committee December 4, 2013 To: From: Subject: Summary Citizens Advisory Committee Cynthia Fong Deputy Director for Finance and Administration ACTION Adopt
PROJECT CHARTER GUIDE
Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Technology PROJECT CHARTER GUIDE February 1999 Chief Information Officer Branch
SC121 Umoja Contractor & Consultant Services Overview. Umoja Contractor & Consultant Services Overview Version 7
SC121 Umoja Contractor & Consultant Services Overview Umoja Contractor & Consultant Services Overview Version 7 Last Copyright Modified: United 14-August-13 Nations 1 Agenda Course Introduction Module
AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT PAYROLL AUDIT PROGRAM
PAYROLL GENERAL: The Payroll Department is responsible for processing all District payrolls and compliance with all rules and regulations pertaining to and/or resulting from payroll operations which includes
Role and Skill Descriptions. For An ITIL Implementation Project
Role and Skill Descriptions For An ITIL Implementation Project The following skill traits were identified as fairly typical of those needed to execute many of the key activities identified: Customer Relationship
Resource Management. Determining and managing the people resources on projects can be complex as:
Baseline Resource Management RESOURCE MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project people resources. Overview This Phase is used to establish
Documentation of salaries and wages is often necessary to support
Documentation of salaries and wages is often necessary to support charges to specific funding sources (resources), instructional settings (goals), and activities (functions). Some level of formalized time
September 2005 Report No. 06-009
An Audit Report on The Health and Human Services Commission s Consolidation of Administrative Support Functions Report No. 06-009 John Keel, CPA State Auditor An Audit Report on The Health and Human Services
ITIL Version 3.0 (V.3) Service Transition Guidelines By Braun Tacon
ITIL Version 3.0 (V.3) Service Transition Guidelines By Braun Tacon Executive Summary: This document is seven pages. Page one is informational/background only. What follows over the next six pages are
Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB41507 Certificate IV in Project Management
Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB41507 Certificate IV in Project Management First published 2010 ISBN 978-1-74205-510-7 Department of Training
HOW NOT TO ATTRACT AN ENTREPRENEURIAL PM
HOW NOT TO ATTRACT AN ENTREPRENEURIAL PM FORTUNE 500 HIGH-TECH EQUIPMENT AND SERVICES COMPANY Process-focused job description indicates low potential for career enhancement and discourages talent from
Title: DESKTOP TICKET MANAGEMENT PROCEDURE
POLICY: This policy describes the methods by which help desk tickets will be accepted, managed and resolved by. A consistent, high-level process for ticket management is essential to the delivery of high-quality,
Project Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
WEB-BASED TIME AND ATTENDANCE DCAA COMPLIANCE. White Paper
WEB-BASED TIME AND ATTENDANCE AND DCAA COMPLIANCE White Paper Page 1 AUDIT CONCERNS Certain types of organizations who contract with the US Government must follow specific timekeeping guidelines set forth
IT Risk & Security Specialist Position Description
Specialist Position Description February 9, 2015 Specialist Position Description February 9, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level
Systems Development Life Cycle (SDLC)
DEPARTMENT OF BUDGET & MANAGEMENT (SDLC) Volume 1 Introduction to the SDLC August 2006 Table of Contents Introduction... 3 Overview... 4 Page 2 of 17 INTRODUCTION 1.0 STRUCTURE The SDLC Manual consists
Development, Acquisition, Implementation, and Maintenance of Application Systems
Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Customer Account Data Engine 2 Systems Development Guidelines; However, Process Improvements Are Needed to Address Inconsistencies September 30, Year
TORFQ # ITS-EPA-III-RFQ-10-0009 SERVICE DESK/EPA CALL CENTER AMENDMENT #1
TORFQ # ITS-EPA-III-RFQ-10-0009 SERVICE DESK/EPA CALL CENTER AMENDMENT #1 April 15, 2010 Dear ITS-EPA II BPA Holder: This amendment is issued to: 1) amend various aspects of the RFQ 2) Incorporate wage
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
The PMP Application Process
The PMP Application Process The purpose of this document is to explain the PMP application process and provide helpful links and tools for submitting your application. Reference: The reference for the
Kronos Workforce Central 6.1 with Microsoft SQL Server: Performance and Scalability for the Enterprise
Kronos Workforce Central 6.1 with Microsoft SQL Server: Performance and Scalability for the Enterprise Providing Enterprise-Class Performance and Scalability and Driving Lower Customer Total Cost of Ownership
INTEGRATED PROJECT MANAGEMENT (IPM) DOCUMENT SECTION 1
PMO QA/Approval: September 11, 2015 Project Title/Subject: INTEGRATED PROJECT MANAGEMENT (IPM) DOCUMENT SECTION 1 Back Office Collaboration and Integration Project GENERAL INFORMATION [this section completed
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
The purpose of this course is to provide practical assistance for defining and managing project scope.
Scope Definition and Scope Management Purpose - To provide practical assistance for defining and managing project scope. This course will focus on tips for creating a scope statement rather than a step-by-step
California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9 th Street, Room 141 Sacramento, CA 95814
IT Project Status Report For an MHSA-Funded IT Project Please send the Signed Original to the following address: California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9
Requirements Management Best Practices
Requirements Management Best Practices Sponsored by: Karl Wiegers Principal Consultant, Process Impact www.processimpact.com Sponsor: RequirementOne Free 30 day trial Sign up by 31 st May and benefit from
Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management
Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB51407 Diploma of Project Management First published 2010 ISBN 978-1-74205-511-4 Department of Training and
We released this document in response to a Freedom of Information request. Over time it may become out of date. Department for Work and Pensions
We released this document in response to a Freedom of Information request. Over time it may become out of date. Department for Work and Pensions SCHEDULE 4 KEY PERFORMANCE INDICATORS, SERVICE LEVELS AND
ICT Service Desk Creation
ICT Service Desk Creation Project Initiation Document Document: ICT Service desk Creation: PID Issue Date: 26 th November 2010 Version: 0.1 Draft Version Number: 1.0 Change Control Quality Assurance Document: