Capital Project Management and Construction

Size: px
Start display at page:

Download "Capital Project Management and Construction"

Transcription

1 Capital Project Management and Construction Project Management is Tough: Most project managers are just thrust into the roles. College engineering programs don t cover practical construction. Project management classes are offered at very few colleges. Most companies do not have in-house project management or construction training. Until now there has been no single source for learning what you need to know about project management and construction. Now there is... CP Project Services offers three unique, one-day seminars that will teach you all you need to know to properly and efficiently manage capital projects.

2 Capital Project Selection, Justification, Estimation, Planning, Execution, and Control Seminar Objective To fuse seamlessly project management as taught by the Project Management Institute s PMBOK (the ANSI standard on project management) and capital project management in the CPI, Pharmaceutical, and Food and Beverage Industries. The PMBOK, though a thorough and powerful document, is general. It must be translated into specific action unique to a given field. This seminar translates the PMBOK into the lingo and documents used by capital project managers in the CPI, Pharmaceutical, and Food and Beverage Industries. It also goes beyond and delves into specifics of selected areas of project management especially helpful to its targeted audience. How can all this be done in one day? Quite simply, it s all beef. There is no fill here. CP Project Services realizes how busy project managers are and consequently has made every minute count. Still Not Sure if This Seminar is for You? Take the Test! Do your projects frequently have cost overruns? Do you put together a written project plan in accordance with the PMBOK (ANSI standard on project management) for every project? Can you name nine areas that must be covered in every project plan? Do you write a lot of AFE s that don t get approved? Do you know how to accurately predict project completion date and cost when only 15% of the budget has been spent? Do you know how to track your project with the simple but powerful tools of earned value? Do your issued for construction drawings frequently contain many errors? What is the best number of contractors to bid for a job? Can a 30% variance in contractor quotes be legitimate? Can you look at contractor work in the field and immediately tell if it s on schedule? If you are not satisfied with even one of your answers, this seminar is a must for you! It will save your projects money and time, and make your work life much easier. Some of What You Will Learn About Project Management How to manage your time. How to deal with difficult project team members. How to delegate work. How to create a project plan in accordance with the PMBOK. The basics of contract law How to completely scope any project How to write tight scopes of work for engineering and construction. How to make sure drawings are properly reviewed and fit for bidding with few errors. How contractors negotiate with you and how you should with them. How to analyze contractors quotes. How to use earned value to track your project How to find out early if you have cost or schedule problems and what to do about them. How to look at work in the field and tell immediately if it s on schedule or not. How to estimate task time duration, and costs for AFE s. How to either kill a project quickly or justify it properly to get AFE approval. Take-Homes Each attendee will be given A floppy disc with a project plan that can be used for any project with minor modification A floppy disc with a preliminary and detailed engineering scope of work that can be used to bid engineering for any project with minor modification. A manual that will make note taking unnecessary. 2

3 Capital Project Management is Primarily about Construction not Chemical Engineering Even after the proper project management tools have been mastered, they cannot be utilized to their fullest without the appropriate knowledge of construction. Unfortunately, most chemical and mechanical engineers who manage projects have had no training in the construction trades, the construction process, or even in the process control hardware used today. Unless an effort is made to fill in these gaps, the project manager will be supervising work that he doesn t understand and cannot critique, and will be dealing with people in a rather complicated realm, the construction process, that he doesn t understand either. And worst of all, this lack of understanding leads to increased costs, expanded schedules, and a compromise in quality. Two seminars address this knowledge need: What the Capital Project Manager Needs to Know about Soil, Foundations, Concrete, Welding, and Piping, and What the Capital Project Manager Needs to Know About Electrical Power and Control Systems. These two seminars provide the project manager with what he needs to know about construction and control to efficiently manage his projects. Each is a one-day seminar, kept concise to accommodate busy schedules. What the Capital Project Manager Needs to Know about Soil, Foundations, Concrete, Welding, and Piping Seminar Objective The capital project manager doesn t need to become an architect, but he does need to have a good, general understanding of the various trades, and the construction process. This seminar addresses those concerns and supplies the capital project manager with what he needs to know about soil, foundations, concrete, welding, and piping. The seminar is aimed only at the project manager. This unique approach cuts right to the chase and provides the information that he needs to know to manage his projects efficiently. Still Not Sure if This Seminar is for You? Take the Test! Soil Can soil be sharply classified as sand, gravel, clay, silt, or rock? If topsoil is compacted to 2000 psf of bearing capacity, is it possible for layers of soil below to be weaker? Is the water table an underground lake below which there is more dry soil? Does rock settle? Foundations Is placing the bottom of a concrete pad below the frost line the only way to avoid frost heave? Are piles immune to frost heave? Is removing a weight of soil equal to the weight of your new construction a guarantee that the ground below can provide proper support? Do all foundations settle? Concrete Is stating type, compressive strength, and slump enough to completely specify concrete? Is it OK to add water to concrete at the job site for extra workability? Does it matter when finishing begins? If your concrete samples test OK, does that mean the concrete in the field is fine too? Welding Can you read welding symbols? Why is heat treatment sometimes required after welding? When welding with a DC machine, does it matter if the electrode is made positive or negative? Why are root passes in SMAW (stick welding) butt welds commonly made with TIG? Piping When should a stress analysis be performed on a piping design? Is temperature the primary variable used to select pipe supports? When should a constant support hanger be used? When should a pump be aligned? Learn the answers to these questions and much, much more! 3

4 Some of What you Will Learn about Soil, Foundations, and Concrete: Soil types and strengths Soil testing methods Foundation types Concrete theory Types of concrete Common concrete maladies and how to prevent them Design of Concrete mixtures Transporting, testing, and placing concrete Finishing Hot and cold weather concrete placement How to protect your project against unscrupulous construction practices Some of What You Will Learn about Welding and Piping: How to read welding symbols Overview of welding processes SMAW (stick), TIG, and MIG Overview of piping systems How to select support types How to determine if a stress analysis is necessary Piping and pipe rack design fundamentals When to align pumps When vibration must be considered in design How to protect your project against unscrupulous construction practices Take-Homes Each attendee will be given A manual that will make note taking unnecessary. What the Capital Project Manager Needs to Know About Electrical Power and Control Systems Seminar Objective The capital project manager doesn t need to become an electrical engineer or a control engineer, but he does need to have a good, general understanding of electrical power and control systems, and the construction process. This seminar addresses those concerns and supplies the capital project manager with what he needs to know about electrical power and control systems. The seminar is aimed only at the project manager. This unique approach cuts right to the chase and provides the information he needs to know to manage his projects efficiently. Still Not Sure if This Seminar is for You? Take the Test! Electrical Power Generation How is electricity produced from coal, gas, water, and nuclear power? Why is electricity produced in three phases? Describe electricity s path from the generating station to the final user? What s the difference between a delta and a wye transformer? Plant Electrical Power Usage Is it possible to artificially reduce transformer power by over sizing circuit breakers? Can you calculate project power needs from scope documents? Can you determine if an existing transformer can carry your load? Can you read line diagrams? 4

5 Control System Basics What are the six main parts of a computer? Define operating system, application software, support software? Are there differences between a programmable logic controller and a computer? How are modems related to data highways? Process Control What is the distinguishing feature of a DCS? Can a single PLC control several processes? How do Foundation Fieldbus and HART differ from each other? Can a single bus have instruments from different processes on it? Can a single PLC accommodate dumb transmitters as well as HART and Foundation Fieldbus? Can PLC s from different manufacturers be linked with each other as well as with personal computers? Learn the answers to these questions and much, much more! Some of What You Will Learn about Electrical Power and Control Systems: Electric Power Power generation and transmission Apparent power, real power, power factor Single phase and three phase power calculations Calculating process kva needs Sizing conductors, conduit, and circuit breakers for motors, panelboards, and transformers Line diagrams How to protect your project against unscrupulous construction practices Your Presenter Glen Rosentrater has spent his career managing capital projects and has authored several papers dealing with project management. He earned his BS and MS in chemical engineering from the Univ. of Illinois at Chicago, and is a project management professional (PMP). Rosentrater is a member of AICHE and the Project Management Institute (PMI). Process Control Computer basics Main frames and PCs Industrial computers PLC program types Distributed Control systems Standards and protocols Hybrid control systems Smart transmitters HART Foundation Fieldbus Take-Homes Each attendee will be given A manual that will make note taking unnecessary. CP Project Services, inc., 4034 Wainwright, Oak Lawn, IL , tel (708) , fax (708) , cpprojserv@aol.com 5

6 Capital Project Management and Construction presented by CP Project Services, inc. Mail checks and registration forms to CP Project Services, inc., 4034 Wainwright, Oak Lawn, IL Please make sure your check is enclosed. Registration Form Name Position/Title: Phone: Fax: Company: Street Address: City: State Zip Code: Seminar Title: Seminar Location/Date: CP Project Services, inc Wainwright Oak Lawn, IL Capital Project Management and Construction Learn what you need to know about both!

Soils, Foundations & Moisture Control

Soils, Foundations & Moisture Control Soils, Foundations & Moisture Control Soil The top loose layer mineral and/or organic material on the surface of the Earth that serves as a natural medium for the growth of plants and support for the foundations

More information

JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES

JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES Main Courses Duration: 26 weeks 1. NVQ Level 2 Performing Process Operation in Replicating Environment 2. NVQ Level 2 Performing

More information

Quick fix for frost heave:

Quick fix for frost heave: Quick fix for frost heave: HELICAL PILES Megan Milbradt Civil Engineer Basin Electric Power Shane Vasbinder Civil Engineer Basin Electric Power Concrete piers were 6 inches to 2 feet out of the ground.

More information

Cold Weather Concrete Practices

Cold Weather Concrete Practices Cold Weather Concrete Practices The Information below is an outline of common practice for residential foundation placement and winter construction utilize Edmonton and surrounding Area. Conditions in

More information

Machine Foundation Design

Machine Foundation Design Machine Foundation Design As the structural engineer who recently designed the machine foundation for one of the largest vertical turning and milling centers in the country, in addition to over 250 other

More information

PLC Based Liquid Filling and Mixing

PLC Based Liquid Filling and Mixing PLC Based Liquid Filling and Mixing 1 Mihir Panchal, 2 Aashish Panaskar. 3 Prof. Lalit Kumar KJ College of Engineering and Management Research, Pune, India Abstract: The objective of this paper is to design,

More information

Applying For New or Revised Electric Service

Applying For New or Revised Electric Service Applying For New or Revised Electric Service Dear Customer: ComEd is happy to assist you in initiating new or revised electric service to your location. Please complete, sign and return the attached service

More information

Max. Length of HTS Cables in the Future

Max. Length of HTS Cables in the Future Max. Length of HTS Cables in the Future K. Schippl, Nexans Deutschland Industries, Hannover, Germany TOPICS: Limitation of the cable design: 1. Physical limitations 2. Shipping limitations 3. Maintenance

More information

NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers

NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers NFPA 70E 2012 Rolls Out New Electrical Safety Requirements Affecting Data Centers A market position paper from the experts in Business-Critical Continuity TM Executive Summary Electrocutions are the fourth

More information

05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525

05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525 CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525 Summary of Duties: Performs professional electrical engineering work in

More information

THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING

THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING Delton Short Course Programmes English Language Technical English Language English Language for the Oil Industry Oil

More information

Chapter 3. The Project Management Framework. Objectives

Chapter 3. The Project Management Framework. Objectives Chapter 3 The Project Management Framework Objectives Understand the importance of the Project Management Institute and other professional societies Define the five process groups and understand how they

More information

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION

More information

POLK STATE COLLEGE CHILLER PLANT EVALUATION WINTER HAVEN, FLORIDA APRIL 2, 2014. C arastro & A ssociates, C&A# 5747

POLK STATE COLLEGE CHILLER PLANT EVALUATION WINTER HAVEN, FLORIDA APRIL 2, 2014. C arastro & A ssociates, C&A# 5747 POLK STATE COLLEGE WINTER HAVEN, FLORIDA CHILLER PLANT EVALUATION APRIL 2, 2014 C&A# 5747 C arastro & A ssociates, c o n s u l t i n g e n g i n e e r s inc. 2609 W. De Leon Street, Tampa, Florida 33609

More information

NorthEast Transportation Training and Certification Program (NETTCP) Course Registration Form

NorthEast Transportation Training and Certification Program (NETTCP) Course Registration Form (NETTCP) Course Registration Form Interim Certification (Cost $300 members / $425 non-members) HMA Plant Technician* HMA Paving Inspector* Soils & Aggregate Inspector* Soils & Aggregate Lab Technician*

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

This is a Master s degree level apprenticeship which includes academic learning combined workplace learning and training.

This is a Master s degree level apprenticeship which includes academic learning combined workplace learning and training. Power Engineer Degree Apprenticeship The UK s energy sector is integral to the prosperity and stability of the UK economy as a whole, delivering an absolutely fundamental service for all its citizens.

More information

University of Iowa Main Power Plant 2008 Flood Preparations, Event, & Recovery

University of Iowa Main Power Plant 2008 Flood Preparations, Event, & Recovery University of Iowa Main Power Plant 2008 Flood Preparations, Event, & Recovery Yellow Alert for Mayflower Residence hall Peak at 31.5 feet Power Plant floods from steam tunnel and shuts down 1993 Flood

More information

ORC TURBOGENERATOR TYPE CHP - Organic Rankine Cycle Turbogenerator fed by thermal oil, for the combined production of electric energy and heat -

ORC TURBOGENERATOR TYPE CHP - Organic Rankine Cycle Turbogenerator fed by thermal oil, for the combined production of electric energy and heat - Doc. : 08C00031_e Date : 10.02.2009 Page : 1 / 9 ORC TURBOGENERATOR TYPE CHP - Organic Rankine Cycle Turbogenerator fed by thermal oil, for the combined production of electric - (Preliminary) Doc. : 08C00031_e

More information

Backup Fuel Oil System Decommissioning & Restoration Plan

Backup Fuel Oil System Decommissioning & Restoration Plan Backup Fuel Oil System Page 1 of 19 Overview of Physical Fuel Oil System and Decommissioning Steps The fuel oil system at Milford Power consists of a number of subsystems. These include the following:

More information

Electrical. This section applies to the design and installation of building power distribution systems.

Electrical. This section applies to the design and installation of building power distribution systems. Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions

More information

WET/DAMP BASEMENTS ANSWER: BASEMENT WALLS AND FLOORS CAN BECOME WET BY A LEAK, CAPILLARY SUCTION OR CONDENSATION.

WET/DAMP BASEMENTS ANSWER: BASEMENT WALLS AND FLOORS CAN BECOME WET BY A LEAK, CAPILLARY SUCTION OR CONDENSATION. WET/DAMP BASEMENTS PROBLEM. IS THIS BASEMENT LEAKING OR COULD WE HAVE ANOTHER PROBLEM? Water line arching up on wall in corners of basement. Water collecting on concrete floor starting in corners. ANSWER:

More information

Candle Plant process automation based on ABB 800xA Distributed Control Systems

Candle Plant process automation based on ABB 800xA Distributed Control Systems Candle Plant process automation based on ABB 800xA Distributed Control Systems Yousef Iskandarani and Karina Nohammer Department of Engineering University of Agder Jon Lilletuns vei 9, 4879 Grimstad Norway

More information

Grounding Practice at Data and Communications Centers. David Brender, P.E., CPQ National Program Manager Copper Development Association Inc.

Grounding Practice at Data and Communications Centers. David Brender, P.E., CPQ National Program Manager Copper Development Association Inc. Grounding Practice at Data and Communications Centers David Brender, P.E., CPQ National Program Manager Copper Development Association Inc. Overview of This Presentation Elements of building wiring and

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

The rock cycle. Introduction. What are rocks?

The rock cycle. Introduction. What are rocks? The rock cycle This Revision looks at the three types of rock: sedimentary, igneous and metamorphic. It looks at how they are formed, the weathering of rocks and the way one form of rock turns into another,

More information

Mechanical Engineer. Process Engineer. Civil Engineer. PFD 001 - Inlet works and screening 40.0 27. PFD 002 - Membrane Bioreactor 34.

Mechanical Engineer. Process Engineer. Civil Engineer. PFD 001 - Inlet works and screening 40.0 27. PFD 002 - Membrane Bioreactor 34. 1.00 Site Visit / Data Gathering Scope definition & design verification,inspection of the site, Collation of information, Condition report and priorities, Cost estimates and Preliminary programme 35.5

More information

Qualification of Auditor and Lead Auditor to perform an assessment according NSQ-100

Qualification of Auditor and Lead Auditor to perform an assessment according NSQ-100 Page 1 / 11 ABSTRACT Qualification of Auditor and Lead Auditor to CONTENTS 0. GENERAL... 2 0.1. Purpose... 2 0.2. Scope of application... 2 0.3. References... 2 0.4. Terminology... 2 1. SECTIONS... 2 1.1.

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

City of San Diego Residential Photovoltaic Systems Inspection Guidelines

City of San Diego Residential Photovoltaic Systems Inspection Guidelines City of San Diego Residential Photovoltaic Systems Inspection Guidelines The purpose of inspections by DSD staff is to ensure compliance with the California Electrical Code (CEC), other applicable codes

More information

heat treatment equipment & accessories

heat treatment equipment & accessories heat treatment equipment & accessories INDUSTRIAL FURNACES Dear Customer, ElectroHeat Sweden AB is an innovative company based in Gothenburg, Sweden, and has been operating since 1975. We manufacture industrial

More information

Series Six Plus Programmable Controller

Series Six Plus Programmable Controller Series Six Plus Programmable Controller Gl?K-0147B June 1989 Central Processor Unit 8-Slot Rack 1l-Slot Rack General Description The Central Processor Unit (CPU) for the Series Six Plus Programmable Logic

More information

Energy savings in commercial refrigeration. Low pressure control

Energy savings in commercial refrigeration. Low pressure control Energy savings in commercial refrigeration equipment : Low pressure control August 2011/White paper by Christophe Borlein AFF and l IIF-IIR member Make the most of your energy Summary Executive summary

More information

Agile Project Execution

Agile Project Execution ebook Agile Project Execution The future of Industrial Process Automation projects v1.4 EMK(VDS)-TR-EB-01 APEX ebook Table of Contents Intro Agile Project Execution Page 2. Chapter 1 Conventional Project

More information

Designed and Engineered to Perform

Designed and Engineered to Perform History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the

More information

Air Conditioner Water Heater Model ACWH18

Air Conditioner Water Heater Model ACWH18 Air Conditioner Water Heater Model ACWH18 Installation Guide IMPORTANT! READ THIS FIRST! Commissioning of this unit must be done by a licensed HVAC technician. Commissioning includes making the electrical

More information

SPECIAL SPECIFICATION 5757 Power Duct System

SPECIAL SPECIFICATION 5757 Power Duct System 2004 Specifications CSJ 0353-04-088 SPECIAL SPECIFICATION 5757 Power Duct System 1. Description. This Item shall govern for the furnishing and installing of all materials, equipment, and labor listed in

More information

Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6

Effective: September 10, 2006 Vermont Attachment 1 to Rule 5.500 Public Service Board Page 1 of 6 Public Service Board Page 1 of 6 STANDARD APPLICATION FOR INTERCONNECTION OF GENERATION RESOURCES IN PARALLEL TO THE ELECTRIC SYSTEM OF: (Interconnecting Utility) Preamble and Instructions: An owner of

More information

Certain soils - Clay soils are particularly vulnerable to subsidence since they shrink and swell depending on their moisture content.

Certain soils - Clay soils are particularly vulnerable to subsidence since they shrink and swell depending on their moisture content. Subsidence - Dealing With The Problem Introduction It is the sight every homeowner dreads - cracks appearing in the walls of their home. But don t fear the worst - while there has been an increase in subsidence

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Chapter 4 Forms of energy

Chapter 4 Forms of energy Chapter 4 Forms of energy Introduction This chapter compromises a set of activities that focuses on the energy sources and conversion. The activities illustrate The concept and forms of energy; The different

More information

Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances

Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances Page 50 of 100 Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances (Replaces A-190556) THIS CUSTOMER REFERENCE SPECIFICATION (CRS) IS PART OF THE RULES FOR

More information

CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1

CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1 CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1 1 This Chapter of the FERC Engineering Guidelines has been prepared under contract with R & H Thomas, Inc. JANUARY 1993 Chapter VII Construction

More information

FLEXIBLE SOLUTIONS FOR FLUIDS AND GASES

FLEXIBLE SOLUTIONS FOR FLUIDS AND GASES FLEXIBLE SOLUTIONS FOR FLUIDS AND GASES www.amnitec.nl AmniTec B.V., Rotterdam, is part of a group of companies called United Flexible with an annual turnover of $ 70 Million and 5 operating facilities

More information

Freezer Floor Heaving and Solution

Freezer Floor Heaving and Solution Freezer Floor Heaving and Solution Prepared By H. Charles Woolley and John Fountain For International Association for Cold Storage Contractors November 2-5, 2011 Introduction Mr. Charles Woolley -Vice

More information

Cathodic Protection Use On Tank Bottoms & Underground Piping In Power Generation Plants

Cathodic Protection Use On Tank Bottoms & Underground Piping In Power Generation Plants Cathodic Protection Use On Tank Bottoms & Underground Piping In Power Generation Plants PG&E Office San Francisco January 18, 2007 Craig K. Meier Corrosion Control Incorporated Corrosion process for tanks

More information

PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY

PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY PROGRAM CRITERIA FOR ELECTRICAL ENGINEERING TECHNOLOGY Scope These program criteria apply to programs having titles involving Electrical Engineering Technology including: electrical engineering, electrical

More information

Whitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada

Whitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada Whitepaper Modular Substation Cable Termination Design Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada Abstract The methods for cable penetrations into modular industrial substations are

More information

1A PLANNING AND DEVELOPMENT SHERIDAN COLLEGE GOES DANISH IMPLEMENTING THEIR DISTRICT ENERGY

1A PLANNING AND DEVELOPMENT SHERIDAN COLLEGE GOES DANISH IMPLEMENTING THEIR DISTRICT ENERGY 1A PLANNING AND DEVELOPMENT SHERIDAN COLLEGE GOES DANISH IMPLEMENTING THEIR DISTRICT ENERGY AGENDA 1. Background up till now 2. District Energy on two campuses current work 3. System optimisation and some

More information

Renovation instructions

Renovation instructions 1(13) Renovation instructions The purpose of these instructions is to inform you of the things to consider when renovating an apartment. You can avoid many possible problems and additional costs following

More information

Morris S. Stover, P.E. Sponsor, Transmission Area

Morris S. Stover, P.E. Sponsor, Transmission Area Page 1 of 5 Job Function Morris has nearly 28 years in the power industry including design and construction of transmission line and substation facilities, He has extensive experience in contract development

More information

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0.

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC 28262. DRAFT V0. Innovation Park Charlotte. NC 28262 DRAFT V0.1 Page 2 CyberFortress Data Center at Innovation Park BECO South purchased Innovation Park in March 2010 and immediately launched a dramatic top-to-bottom $30M

More information

Specifications for Residential Property Owners Connection to New Public Sewer

Specifications for Residential Property Owners Connection to New Public Sewer Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the

More information

Stanford University Guest Lecturer, Professor s Assistant, 1999-2004 Advanced Construction Issues and Claims, Civil Engineering Department

Stanford University Guest Lecturer, Professor s Assistant, 1999-2004 Advanced Construction Issues and Claims, Civil Engineering Department Current Position PKR CONSULTING, INC. Founder and Chief Executive Officer, 2004 Present Provides construction consulting, dispute resolution and expert witness services to owners, contractors, subcontractors,

More information

Permeable Pavement Construction Guide

Permeable Pavement Construction Guide Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce

More information

ELECTRONIC INFORMATION SECURITY A.R.

ELECTRONIC INFORMATION SECURITY A.R. A.R. Number: 2.6 Effective Date: 2/1/2009 Page: 1 of 7 I. PURPOSE In recognition of the critical role that electronic information systems play in City of Richmond (COR) business activities, this policy

More information

CHAPTER 8- REDUCING THE MOISTURE

CHAPTER 8- REDUCING THE MOISTURE CHAPTER 8- REDUCING THE MOISTURE I ve learned many different ways to cut down on moisture and dampness over my many years of being a homeowner. All those tips I ve included right here for you so that you

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

Services. Three Phase Service

Services. Three Phase Service Services Primary Service vs Secondary Service Overhead vs Underground Common Service Types Three Phase Wye Closed Open Delta Corner Grounded Center Tapped Open Single Phase Three Phase Service Wye Delta

More information

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids

More information

Septic Tank to Cistern Conversions. Saving Water & Saving Money

Septic Tank to Cistern Conversions. Saving Water & Saving Money Florida Keys Aqueduct Authority 1100 Kennedy Drive Key West, Florida 33040 Septic Tank to Cistern Conversions Saving Water & Saving Money One of the benefits of connecting to the Central Wastewater System

More information

HOW TO SELECT A LOW VOLUME (L.V ) BOILER

HOW TO SELECT A LOW VOLUME (L.V ) BOILER HOW TO SELECT A LOW VOLUME (L.V ) BOILER FREQUENTLY ASKED QUESTIONS OR COMMENTS ON BOILERS Dear Potential Customer: Low Volume Operator Exempt boilers have been marketed in Ontario to eliminate the requirement

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION February 2013 NOTE: If conflict exists between St. Thomas Energy s Conditions of Service and this document, the Conditions

More information

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance 02/15 Labko GRP cesspools Instructions for installation, operation and maintenance Reliable solutions Wastewater treatment systems Contents 1 LABKO CESSPOOLS... 3 1.1 GENERAL... 3 1.2 IMPORTANT TO KNOW

More information

Use of Fly ash from KKAB, for sealing of landfills

Use of Fly ash from KKAB, for sealing of landfills Use of Fly ash from KKAB, for sealing of landfills Kristina Hargelius M.Sc. Civ. Eng. Kristina.hargelius@ramboll.se Abstract The paper must include an abstract, which should be no more than and 150 words.

More information

DUFFERIN-PEEL CATHOLIC DISTRICT SCHOOL BOARD

DUFFERIN-PEEL CATHOLIC DISTRICT SCHOOL BOARD DUFFERIN-PEEL CATHOLIC DISTRICT SCHOOL BOARD JOB DESCRIPTION POSITION TITLE: Air Conditioning Mechanic DEPARTMENT: Plant TITLE OF IMMEDIATE SUPERVISOR: Supervisor, Maintenance Services Position Summary

More information

LOST FOAM PROTOTYPING METHODS

LOST FOAM PROTOTYPING METHODS LOST FOAM PROTOTYPING METHODS A Comparison of Methods and Processes Copyright 2002 Austin Group, LLC. All rights reserved. INTRODUCTION TERRY AUSTIN PRESIDENT AUSTIN GROUP, LLC QUINCY, ILLINOIS INTRODUCTION

More information

RAID systems within Industry

RAID systems within Industry White Paper 01/2014 RAID systems within Industry Functioning, variants and fields of application of RAID systems. A white paper issued by: Siemens. Siemens AG 2014. All rights reserved Warranty and liability

More information

Short Form Catalogue. Alarm Systems. Reliable Supervision and Control

Short Form Catalogue. Alarm Systems. Reliable Supervision and Control Short Form Catalogue Alarm Systems Reliable Supervision and Control Alarm Monitors and Indicators The SELCO product range includes a number of alarm monitors and indicator panels for use in numerous applications.

More information

UOP Career Development. Career development program for mechanical and civil engineers

UOP Career Development. Career development program for mechanical and civil engineers UOP Career Development Career development program for mechanical and civil engineers MAKING OUR WORLD SAFER AND MORE SECURE, MORE COMFORTABLE AND ENERGY EFFICIENT, AND MORE INNOVATIVE AND PRODUCTIVE Our

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

A quick guide to our floodcare scheme

A quick guide to our floodcare scheme A quick guide to our floodcare scheme What to do in case of sewer flooding We re here to help We appreciate that dealing with the results of sewage flooding is always unpleasant and we know how upsetting

More information

due to uncertainty. This, in turn, has a direct impact on equipment availability and maintenance costs. Unfortunately, due to misconceptions and

due to uncertainty. This, in turn, has a direct impact on equipment availability and maintenance costs. Unfortunately, due to misconceptions and due to uncertainty. This, in turn, has a direct impact on equipment availability and maintenance costs. Unfortunately, due to misconceptions and pressure from plant operators to get "back on line", it

More information

Module 5 Cost Management PMP Exam Questions

Module 5 Cost Management PMP Exam Questions Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

Alain Nifenecker - General Electric Manager Controls Engineering

Alain Nifenecker - General Electric Manager Controls Engineering GE Energy Benefits of Integrating a Single Plant-Wide Control System Into a Standard Plant Design Philosophy Authors: Luis Cerrada Duque - Empresarios Agrupados Director of I&C Department Charles Weidner

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and

More information

CLEANING IN PLACE AUTOMATION FOR PROCESS INDUSTRY USING PLC AND SCADA SOFTWARE

CLEANING IN PLACE AUTOMATION FOR PROCESS INDUSTRY USING PLC AND SCADA SOFTWARE CLEANING IN PLACE AUTOMATION FOR PROCESS INDUSTRY USING PLC AND SCADA SOFTWARE Siddhesh Dhonde 1, Bhaskar Nadigatla 2, D.U. Dalavi 3 1,2, 3 ETC, SCSCOE, SPPU, (India), ABSTRACT In Process Industries, proper

More information

Quality Assurance Concepts. Outline

Quality Assurance Concepts. Outline Quality Assurance Concepts Peter C. Taylor Outline What is quality? Who cares? How do we get it? What is the important stuff? 1 Defining Quality Simple Definition (Philip Crosby) Quality: Conformance to

More information

A guide to preventing structural damage

A guide to preventing structural damage A guide to preventing structural damage Home owners guide to planning landscaping and maintenance of foundations Structural damage can result from movement in clay soils caused by varying moisture conditions

More information

PLATE HEAT EXCHANGER. Installation Manual. Customer Name: Serial number: Purchase order number: Project:

PLATE HEAT EXCHANGER. Installation Manual. Customer Name: Serial number: Purchase order number: Project: PLATE HEAT EXCHANGER Installation Manual Customer Name: Serial number: Purchase order number: Project: Table of Contents ----------------------------------------------------------------- Page: 2 3 Name

More information

A GROUNDWATER PROTECTION PLAN FOR HOME HEATING OIL TANKS

A GROUNDWATER PROTECTION PLAN FOR HOME HEATING OIL TANKS A GROUNDWATER PROTECTION PLAN FOR HOME HEATING OIL TANKS What is a groundwater protection plan? A groundwater protection plan identifies the activities being conducted that can pollute groundwater and

More information

340 Skilled Trades Technologies. Associate of Applied Science Degree

340 Skilled Trades Technologies. Associate of Applied Science Degree 340 Associate of Applied Science Degree Building Maintenance Major...242 Construction Trades Major...345 Electrical Major...346 Mechanical Major...348 Certificates Building Maintenance...343 Electrical...347

More information

Questions and Answers for Heating and A/C Contractors

Questions and Answers for Heating and A/C Contractors 1. How do we accomplish grounding of furnaces and / or water heaters on two wire circuits? 250.134 Equipment Fastened in Place or Connected by Permanent Wiring Methods (Fixed) Grounding. Unless grounded

More information

Embedded Parts Introduction - Anchors

Embedded Parts Introduction - Anchors In the plant construction or process plants such as chemical, petrochemical, gas or power plants various disciplines are brought into contact and built on each other. Civil, mechanical, electro technical

More information

ENERGY MANAGEMENT. for INDUSTRY AND BUSINESS

ENERGY MANAGEMENT. for INDUSTRY AND BUSINESS ENERGY MANAGEMENT for INDUSTRY AND BUSINESS [Principles of Energy Management] Denis Cooke Denis Cooke & Associates Pty Limited Phone + 61 2 9871 6641 Fax +61 2 9614 1723 Email: denis@decoa.com.au Web Site

More information

A Real Time, Object Oriented Fieldbus Management System

A Real Time, Object Oriented Fieldbus Management System A Real Time, Object Oriented Fieldbus Management System Mr. Ole Cramer Nielsen Managing Director PROCES-DATA Supervisor International P-NET User Organisation Navervej 8 8600 Silkeborg Denmark pd@post4.tele.dk

More information

CONTAMINANT REMOVAL FROM CENTRIFUGAL SYSTEMS

CONTAMINANT REMOVAL FROM CENTRIFUGAL SYSTEMS CONTAMINANT REMOVAL FROM CENTRIFUGAL SYSTEMS BULLETIN 240-10-3 June 2004 Supersedes June 1983 Many centrifugal systems get little maintenance. As a result they operate with the refrigerant highly contaminated

More information

Soils and Aggregates Division

Soils and Aggregates Division Dan Sajedi, Division Chief 443-572-5162 George Hall, Assistant Division Chief Field Operations 443-572-5271 Eric Frempong, Assistant Division Chief Laboratory 443-572-5055 Aggregate Materials, Controlled

More information

Building Your Interlocking Concrete Pavement to Last a Lifetime

Building Your Interlocking Concrete Pavement to Last a Lifetime Building Your Interlocking Concrete Pavement to Last a Lifetime A Guide for Consumers Contents Building Your Interlocking Concrete Pavement to Last a Lifetime.... 3 What Does Installation Involve?....

More information

C hapter 15. Construction Scheduling

C hapter 15. Construction Scheduling Objectives C hapter 1 Construction Scheduling After studying this chapter, you will be able to: Summarize three uses for schedules. Identify three scheduling methods commonly used in construction. Explain

More information

Degree programme in Automation Engineering

Degree programme in Automation Engineering Degree programme in Automation Engineering Course descriptions of the courses for exchange students, 2014-2015 Autumn 2014 21727630 Application Programming Students know the basis of systems application

More information

MAINTENANCE INSTRUCTIONS. Thermia Robust heat pump

MAINTENANCE INSTRUCTIONS. Thermia Robust heat pump MAINTENANCE INSTRUCTIONS Thermia Robust heat pump 9 6 8 0-5 4 7 4 5 0 0 1 R e v. 3 Table of contents 1 Important information.................. 2 1.1 Product description....................... 2 1.2 General................................

More information

Water Heating and Heat Recovery 1

Water Heating and Heat Recovery 1 PID 113 (488) Water Heating and Heat Recovery 1 Florida Power Corporation 2 ENERGY-EFFICIENT WATER HEATING: IT S THE EASIEST WAY TO SAVE ENERGY DOLLARS Anywhere from 10% to 25% of the money you spend on

More information

Investigations of a Long-Distance 1000 MW Heat Transport System with APROS Simulation Software

Investigations of a Long-Distance 1000 MW Heat Transport System with APROS Simulation Software th International Conference on Structural Mechanics in Reactor Technology (SMiRT ) Espoo, Finland, August 9-4, 9 SMiRT -Division 3, Paper 56 Investigations of a Long-Distance MW Heat Transport System with

More information

Electricity to your property

Electricity to your property Vattenfall Distribution AB Electricity to your property How an electrical connection is made and what you need to consider How electricity reaches your property 8 simple steps! 1. Please leave plenty of

More information

SERVICES 2015 ISO 18001

SERVICES 2015 ISO 18001 SERVICES 2015 A family business with a solid foundation of experience, we handle all aspects of site investigation.... Phase 1 Environmental Studies Phase 2 Intrusive Investigations Phase 3 Remediation

More information