PROJECT MANAGEMENT OF A MAJOR MASS TRANSIT PROJECT - KCR WEST RAIL

Size: px
Start display at page:

Download "PROJECT MANAGEMENT OF A MAJOR MASS TRANSIT PROJECT - KCR WEST RAIL"

Transcription

1 PROJECT MANAGEMENT OF A MAJOR MASS TRANSIT PROJECT - KCR WEST RAIL Ian M Thoms Director, West Rail Kowloon-Canton Railway Corporation 7/F, Citylink Plaza Hong Kong * Presentation by C N Fung, Project Manager South, West Rail Kowloon-Canton Railway Corporation Abstract West Rail is currently the Hong Kong's largest construction project. It is also the biggest capital expansion project ever undertaken by the Kowloon-Canton Railway Corporation. The planning, design and implementation of such a massive infrastructure project requires the use of proven and effective project management techniques to ensure success. Efficient project management will avoid delays in project completion, budget over-runs and unsatisfactory performance of the final product. West Rail is more than half way through its construction phase, and is well within budget and ahead of schedule. This paper gives an overview of West Rail development and sets out the key elements of its project management system. INTRODUCTION West Rail, at an estimated cost of HK$46.4 billion (US$5.9 billion), is a 30.5-km domestic passenger railway linking urban Kowloon with the North West New Territories in Hong Kong. When the system becomes operational near the end of 2003, West Rail will serve over 300,000 passengers a day. Demand is expected to grow to 500,000 passengers a day by the year Construction of West Rail involves building nine stations, a 32.5-hectare maintenance centre, and laying 88 km of track along a route line comprising 13.4 km of viaduct, 14.7 km of tunnels and 2.4 km of surface alignment (Figure 1). The project also requires the purchase of 154 new train cars, and the installation of a state-of-the-art Seltrac signalling system together with other tried and tested, modern railway systems along the line, including traction power and overhead line, telecommunications, main control system, etc. The Kowloon-Canton Railway Corporation (KCRC) commenced construction of West Rail following the Hong Kong Special Administrative Region Government's authorisation of the railway scheme in September The project is currently progressing smoothly to programme, with overall implementation 63% complete at the end of December 2001, and is on target for operation to commence before the end of This achievement is due to a combination of factors, including the expertise, 1

2 experience and demonstrated capability of the West Rail team in managing this large multi-disciplinary project; and the skill, endeavours and cooperation of a significant number of contractors and consultants, who have responded remarkably well to West Rail's informal partnering style of project management and highly collaborative approach to problem solving. Figure 1 Route plan and forms of construction of West Rail Phase I PROJECT MANAGEMENT OF THE WEST RAIL PROJECT The prime objective of the project management strategy for West Rail is to ensure that the new railway is commissioned safely, on time, within budget, and to the satisfaction of all the stakeholders. Contracting and Procurement Strategies KCRC has established a procurement strategy for West Rail following fair, open and competitive tendering practices in accordance with the World Trade Organisation procurement rules. Contract conditions set out in the KCRC documents are based on ICE and FIDIC requirements, both being internationally recognised standards. The actual wording of the contractual clauses also draws upon the experience of Hong Kong s Airport Core Programme and the various terms of contract used by Government, the MTR Corporation and the Airport Authority. West Rail adopts two contracting approaches, one is to combine the design and the construction works into a single design-build (DB) contract, and the second is to separate the design activities from the 2

3 works, resulting in design-only contracts plus separate construct-only (CC) contracts. These two different approaches are used for improved flexibility and cost-effectiveness, the choice depending upon the nature, magnitude and complexity of the works involved. In terms of contract packaging, the detailed civil engineering design of West Rail is split into 5 Detailed Design (DD) contracts. The civil construction works are split into two Design-Build contracts for the two major tunnel sections, plus 15 construct-only contracts for the stations and running lines. The contract split is based upon size, geographical location and nature of work, thus allowing economic use of plant and maximum opportunity for participation by local as well as international contractors. The railway operating systems, for which conceptual design and preparation of performance specifications have been carried out in-house, are packaged into 8 DB contracts, 3 Supply and Installation (SI) contracts, and 9 Supply and Purchase (SP) contracts. In addition, there are 2 permanent way (CC) contracts. The underlying principle for the form of contract adopted in each particular case for both the civil and the systems contracts is to apportion contractual risks fairly between the Employer and the Contractor. The major West Rail contracts are scheduled at Annex 1. The timing of contract award was critical. The five main design consultancies were let in early 1998, to be completed by the end of 1998 to facilitate construction contracts to be awarded as early as possible in 1999, based on 100% completion of detailed design. All construction contracts and the core systems contracts were awarded by the end of 1999, in line with the master programme objectives, despite significant design changes brought about by a very major value engineering exercise carried out in the second half of West Rail s procurement procedures follow those of the Hong Kong SAR Government, which complies with the World Trade Organisation s Agreement on Government Procurement. The procurement selection goes through a number of rigorous processes including pre-qualification, short-listing, tendering, tender assessment and award. These processes ensure openness, fairness and competition with the aim of awarding contracts to tenderers who are technically and financially capable. Project Management Team The establishment of a project management team with clearly defined roles and lines of communication is essential in meeting the demanding requirements of any massive project. A major component of West Rail s project management system is people and their organisation. The overall strategy is to have sufficient number of suitable calibre staff available to complete required tasks at each stage of the project. As staff contributes significantly to overall costs, they should be employed such that marginal benefit exceeds marginal cost, taking into account both construction and operating phases. To achieve this, certain activities are carried out by consultants, such as land acquisition and detailed design. Other activities are generally carried out by in-house staff, who are mostly on two year renewable contracts. Both internal and external resources operate as an integrated team. Given the scale and complexity of the project, the task for the West Rail project management team is demanding and challenging. Figure 2 shows the major processes and functional areas of the project which are required to be managed in a structured and integrated manner. 3

4 Programme management Quality assurance Environmental management Design process Contract formulation Procurement Construction implementation Testing & commissioning Trial operation Change management & cost control Risk management Community relations Systems safety assurance Construction safety management Figure 2 Major process and functional areas of the West Rail Project Management System To manage these issues, KCRC s 800 strong West Rail Division is divided into three main departments. Figure 3 shows the project management team of the West Rail Division. The Construction Department is responsible for civil design and construction management, land matters, environmental aspects and construction safety. The Railway Systems Department is responsible for design management, manufacturing, installation, systems integration, and testing & commissioning of all railway systems contracts. The Project Support Department is responsible for all support functions including financial, human resources, legal, cost and programme control, procurement, information technology, and public affairs. In addition, a small Operations and Maintenance Section ensures that the ultimate operational requirements are catered for throughout the design, construction and commissioning phases. Director West Rail Manager Operations & Maintenance General Manager Railway Systems General Manager Construction General Manager Project Support - End user s requirements - Systems safety - Rail systems equipment installation - Testing & commissioning - Statutory inspections - All railway systems contracts - Conceptual design - Design management - Manufacturing - Installation - Systems planning & control - Systems integration - Testing & commissioning - Design management - Land acquisition - Environmental - Construction safety - Construction planning - Construction management Figure 3 The West Rail Project Management Team - Financial - Administration - Human resources - Cost control & programme - Procurement - Information technology - Legal - Public Affairs 4

5 Construction Management For the civil engineering works, the Corporation has adopted the practice of appointing Resident Site Staff (RSS) through the Detailed Design Consultant (DDC), to ensure that their design responsibilities are carried through to the construction phase (see Figure 4). The KCRC acts as the overall project manager, the DDCs serve as the Engineer and provide RSS who integrate with KCRC staff to work with the contractors on site. Delegation of authority and responsibility with accountability are well defined. Figure 5 shows the relationship of the three parties forming a management triangle. KCRC employs consultants to design the railway and then awards the contracts to contractors accordingly. The consultants and their resident site staff take up the role of monitoring contractors' work while KCRC oversees the whole project and coordinates with the consultants and contractors, as well as with external bodies within the Government and the community sectors. Each party's role is clearly defined and frequent dialogue is carried out among the three parties. The close partnership developed within the triangle has proved effective in keeping the project on the right track towards successful completion in terms of quality, cost and time. Employer Design Respon. DDC The Engineer CRE & Resident Site Staff Consultant KCRC RSS SITE BASED Delegation of Powers of the Engineer KCRC Project Manager Employer s Representative Contractor Structure B/S Arch. Work Interfacing Contractors Rolling Stock Signalling Track Work L& Esc Master Control Systems etc. Interfacing Agencies Highway Water Supply CLP HK Tel DSD etc. Figure 4 Construction Management Structure 5

6 KCRC Management Triangle Contractors RSS/Consultants Figure 5 The West Rail Management Triangle The organisational framework enables structured interfaces with all the stakeholders for accurate forecasting of programme and cost parameters. These are regularly compared with the established baseline to assess any overall impact. As soon as there is evidence of a deviation, the project team mitigates proactively any negative impact of change. Partnering Approach KCRC recognizes that communication is key to the successful running of the West Rail project. With over 30 major contracts in full swing, and over 11,000 staff and site operatives working towards completion of West Rail, the project requires a dedicated level of co-ordination and communication to allow necessary information to flow freely. By developing an organisation that embraces partnering to enable the successful completion of West Rail through the efforts of the Employer, the Engineer s staff and the Project Contractors, the Corporation intends to create a level playing field where the interests of all parties are addressed professionally and fairly. In this vein, the Corporation invites all its contractors and consultants to come together once per quarter, on an informal basis, for an information exchange at the Quarterly Review Meeting (QRM) to solve problems, raise and discuss concerns, and share experiences. Involving over 150 representatives from the civil and railway systems contractors, the design consultants, resident site staff and KCRC's own project team, the logistics for these quarterly review meetings are complex, but results have already proved positive in opening lines of communication and cutting through complicated issues to reach agreed solutions. Key short-term targets to be achieved in the coming quarter are also agreed at the meetings and monitored through to the subsequent QRM. Cost Control The objective of the cost control process is to ensure that budgetary requirements are adhered to during the design and implementation of the project and that the out-turn cost is in line with the KCRC's and the Government's expectations. 6

7 On a weekly basis, potential changes to the planned scope of work are identified and quantified. The details of proposed changes are entered into a computer system, which automatically routes the information to all concerned parties. Review, assessment and interim approval are done on line, and the senior management of the project meets once a week in the Cost Control Committee for final vetting prior to implementation of any changes. The cost control system for West Rail has proved effective as it enables the management to identify problem areas early and to initiate timely corrective action so as to maximise the chances of completing the project within the established budget. Programme Management Programme Management in the global sense requires that the individual contracts, most of which are significant projects in their own right, be progressed in a manner that efficiently supports the aims of the scheme as a whole. The parameters of design, construction methods and time must be compatible, and all contract interfaces must be rationalised so that contractors can gain physical access to site areas in a smooth and well-planned manner. To effectively perform the programme management function and ensure that all these interfaces are compatible, KCRC has developed a Master Programme of major activities to be performed (Figure 6). They form a critical path network that relates individual activities of one contract to another through a large number of controlled interfaces. The West Rail Master Programme is a computerised database containing the individual activities forming the execution of the West Rail scope of work. Activity records in the database are described by various attributes that provide planned and actual status of the work represented by the selected records. The information about the relative sequence of activities enables flexibility in analysing the impact of one activity on another. The database also provides the capability of assigning, sorting, summarising and allocating resources needed to perform activities. The software used to develop the West Rail Master Programme is Primavera Project Planner. Each contractor's own programme can be imported into the programme system and assessed for compatibility. The Master Programme spans a period of time beginning with the work included in the preliminary engineering or Technical Studies phase, and continues through to Systems Commissioning and trial running. The Programme is organised into sections and contracts, based upon the way works will be carried out. Major activities, Key Dates, and Key Event Indicators are developed from the Master Programme. Through these interlinked relationships, the impacts of delays are assessed for criticality to the objectives of the West Rail Programme as a whole. Robust systems and procedures are in place to track, control, and adjust activities as needed to achieve the required results. Each year, senior management reviews and assesses Key Event Indicators for the coming year and recommends programme adjustments to reflect the Corporation s long-term objectives for the project. 7

8 Responsibility Development of Master Programme Director, West Rail NO KEIs Approved? Review and approve Key Event Indicators (KEI) YES Project Controls West Rail Functional Organisations West Rail Designated Managers Identify Key Event Indicators & issue for review Review Key Event Indicators Review Key Event Indicators Confirm Key Event Milestones Indicators Develop draft Master Programme & issue for review Review draft Master Programme. Review draft Master Programme. Project Controls conduct working meetings to finalize Master Programme & forward to Approval Authorities for review and aproval. Issue Master Programme using PCN Approval Authorities Review and approve Master Programme through PCN NO Master Programme Approved? YES Figure 6 Development of master programme In addition, three specialised types of programme are being employed to help manage the intricacies of the project. Co-ordinated Installation Programmes (CIPs) are being developed for each distinct facility (e.g. a station, the depot or a ventilation building) to delineate the required sequencing of detailed activities so that project contractors can be well prepared for the window of time that they will have access to specific areas to perform their duties. For example, the civil contractor for a station will provide access to the lifts and escalators contractors who will install their equipment and then hand the areas back to the civil contractor for installation of architectural finishes. The CIP is a composite programme to be prepared by the Engineer. Following the issue of the CIP by the Engineer, the Contractor and the Project Contractors involved are to revise and resubmit their respective programmes accordingly. The Engineer prepares and issues the integrated CIP to the Contractor and may from time to time revise and re-issue the CIP. 8

9 The purpose of the CIP is to facilitate the co-ordination of the delivery, installation, testing and commissioning of the system-wide E&M contract works with the civil construction, building services and architectural, builder's works and finishes. It serves to organise the management of interfaces between the works of the Project Contactors. Similar to the CIPs, the Track Related Installation Programme (TRIP) has been developed for the contractors who are involved with installing trackwork, signalling, traction power, and other equipment along the railway line itself. This is a detailed network of activities that allows shared use of works trains once the initial rail has been installed. The TRIP was implemented in August 2001 and is reviewed weekly. This programme co-ordinates all installation activities along the track, based on the input received from each of the Project Contractors. The allocation of track access and works trains will be in accordance with the overall project sequence and criticality of each work activity. The third special programme being developed for the West Rail project is the Operational Readiness Plan and Programme. This will provide a systematic approach to make sure that West Rail operates smoothly and safely from day one of operation onwards. Activities covered by the Operational Readiness Plan and Programme are essentially all those items necessary for successful Day-One operation which are not part of the project works deliverables. The Operational Readiness Programme was initially developed in late 2000 when the project works were approximately 40% complete, and structural works were in excess of 70% complete. Whilst the critical path to Day-One operations essentially runs through the delivery of the West Rail project works, the non-project activities, relating to approvals by governmental and regulatory bodies and services provided by other activities (e.g. feeder buses to stations), will progressively become more critical to Day-One operations, and it is vital to identify the timing requirements of these issues and to co-ordinate with these bodies to ensure that necessary arrangements are made in time. The first formal operational readiness forum was convened in July 2001 with the senior management of relevant government departments. Detailed working level meetings are now being conducted, and these plenary forum sessions will continue on an ongoing basis until West Rail opening. The management structure of the operational readiness process for West Rail within KCRC comprises a steering committee and a working group. The Operational Readiness Steering Committee oversees and provides high-level coordination of all matters concerning West Rail Day-One operational readiness. It defines the strategy and sets policy with respect to all aspects of operational readiness including any necessary submissions to the Government and outside organisations. The role of the working group is to implement the policies and strategies set by the Steering Committee (Figure 7). Part of the Operational Readiness Programme involves integrating the Light Rail and West Rail Operations organisations and providing a training programme for all those who will be manning the trains, control rooms and station platforms. The organisational structure and training plan are due to be finalised around the end of

10 West Rail Operational Readiness Plan West Rail Operational Readiness Programme Successful Day One operation West Rail Commissioning Plan Figure 7 Operation readiness plan and programme THE CULTURAL AND SOCIAL ASPECTS OF PROJECT MANAGEMENT Building a major railway has never been purely an engineering undertaking. For the implementation of any mega project, the cultural and social aspects of the project have to be taken good care of from the initial planning stage. This is especially so when West Rail is a rail project which cuts through urban centres as well as culturally and environmentally sensitive area in the tranquil setting of the rural New Territories. While no one would ever doubt the value of West Rail, nonetheless significant effort was still required to address community concerns relating to land resumption and traffic diversions required for the construction works, as well as dealing with objections to noise nuisance, shifting of the alignment, naming of stations, etc. Apart from being very vocal and vociferous, some resistance elements were very well-organised and highly politicised. If not handled efficiently and effectively, such resistance and pressure might lead to serious delays in the project in addition to adverse publicity. Hence, community relations has a key role to play in project management. It is of vital importance to establish and sustain a harmonious relation with the community such that the project can proceed smoothly according to programme. A comprehensive community impact assessment had been conducted during the inception stage so that all the potential community impacts and problems could be catered for, as far as possible, and in a practicable manner during the early design stage. It should be understood that not all the community impact issues could be identified prior to actual construction and many unexpected issues will manifest themselves subsequently. Adopting a preventive and proactive attitude helps to reduce considerably many of the potential troubles. Respect for traditional beliefs and culture of the indigenous villagers is a must for any major project in Hong Kong, especially in the rural New Territories. In order to respect Fung Shui, a total of 19 Pai Laus and a Fung Shui Pavilion will have to be built along the West Rail alignment, as well as relocating a Fung Shui Well and reprovisioning many Fung Shui trees. For other Fung Shui cases which cannot be resolved by these options, engineering and technical solutions may be required. On West Rail grave locations necessitated shifting the railway alignment and a village shrine required a redesign of the station structure. 10

11 Comprehensive pre-condition surveys were conducted to cover all the facilities and structures within a reasonable distance of the works, listing out all existing defects in adjacent structures, with photographic records taken and dated. This has facilitated the subsequent handling of claims for compensation for cracks and damage. In order to enlist the support of the community for the West Rail project, community briefings, media briefings, school talks and exhibitions are held regularly to keep the community updated on the development of the project. To maintain close dialogue with residents along the alignment, community liaison offices have been set up to provide a one-stop rapid response facility for complaints and enquiries. A 24-hour complaint and enquiry hotline is operated on West Rail. Working groups with local representatives are set up to deal with specific issues, as and when required. NEW INITIATIVES AND OBSERVATIONS The West Rail project management system has been operating effectively overall. Compared to previous large railway projects in Hong Kong, several new initiatives have been adopted on the West Rail project. Below are some observations that highlight the nature and benefits of the new initiatives and strategies adopted. 1. The strategy of prevention is better than cure has proved successful. The proactive approach adopted on West Rail has resolved numerous concerns long before they ever became serious problems. Consequently it is also considered to be the best approach for other projects. 2. Managing a project under strict budgetary and programme control has proved advantageous. It imposes a discipline that is sometimes lacking on construction projects, resulting in cost escalation and programme over-runs. 3. Value engineering has proved to be beneficial to the project. The change of the West Rail scheme from a 12-car to a less expensive 9-car configuration not only resulted in substantial saving in capital cost but also brought about the inclusion on certain contracts of a value engineering clause to effect shared savings. However, the major review exercise was only completed at a late stage in the design. Had the change been made earlier, there would have been less disruption and greater savings. Figure 8 shows how the opportunity to influence project characteristics decreases over time. 4. The use of interface specifications as a contract requirement detailing the responsibilities between the contractors was provided during the tendering period, to form the basis for understanding the responsibilities of each contractor. The interface management plans developed by the contractors minimise interface inconsistencies and misunderstanding on interface requirements and designs, and will greatly facilitate installation and the overall commissioning process. 5. The cultivation of an informal partnering relationship between client and contractor encourages the willingness to solve problems regardless of who is directly responsible and reinforces the prevention is better than cure strategy. 6. The effort put into community relations has contributed significantly to the smooth implementation of the project programme. By taking good care of the social and cultural aspects of the project, possible resistance and disturbance by the residents along the alignment is minimised. In addition, such efforts have also helped to establish a positive and proactive image for West Rail. 11

12 100% Degree of Influence 0.0% Award of Contracts Day One of Operation Design Period Construction Period Operation Period Decreasing Influence Figure 8 Opportunity to influence project characteristics CONCLUSION The West Rail experience has proved that a robust project management system is essential to the implementation of a project from design, through construction to the commissioning stage and day one operation. KCRC, working together in partnership with the project's contractors and design consultants, has been able to resolve technical and commercial issues to the satisfaction of all parties whilst maintaining the major objectives of meeting time and cost constraints. West Rail is well on schedule to serve the people of Hong Kong by the end of KCRC believes the project management approach developed for West Rail may provide a useful reference for other projects to draw upon. 12

13 List of Major Contracts of the West Rail Phase I Annex 1 Civil Construction Contracts Package Title Contract Number Award Date Contract Sum (HK$ million) Consultant / Contractor Kwai Tsing Tunnels DB-320 Oct ,903 Dragages-Zen Pacific JV Tai Lam Tunnel DB-350 Sep ,790 Nishimatsu-Dragages JV Viaduct-Kam Sheung Road to Tin Shui Wai CC-201 Jun ,213 Maeda-Chun Wo JV Yuen Long and Long Ping Stations CC-202 Sep ,762 AMEC-HK Construction JV Tin Shui Wai Station CC-203 Jul ,126 Chun Wo-Fujita-Henryvicy JV Viaduct-Tin Shui Wai to Siu Hong CC-211 Jun Maeda-Chun Wo JV Siu Hong Station CC-212 Jul ,386 HKACE JV Tuen Mun Station CC-213 Jul ,353 HKACE-JV Tsuen Wan Section CC-300 Sep ,779 Penta Ocean-Kier JV Tsuen Wan Reclamation CC-302 Mar Sino-European JV Nam Cheong Station CC-402 Sep ,238 Balfour Beatty-Zen Pacific JV Tunnel Works-Mei Foo to Nam Cheong CC-403 Jun China State-Zen Pacific JV Mei Foo Station CC-404 Jul ,243 Kier-Zen Pacific JV Civil and Infrastructure Zen Pacific-China State-Ngo CC-601 Jun Works Kee JV Kam Sheung Road Station CC-602 Sep NECSO Entrecanales Cubiertas SA West Rail Headquarters CC-603 Feb Sun Fook Kong JV West Rail Depot CC-604 Dec Costain-China Harbour JV Railway Systems Contracts Train Control and Signalling Alcatel Canada Inc Transport DB-1300 Mar System Automation Traction Power and Overhead Line DB-1400 Sep Siemens-CITIC Consortium Telecommunications Systems DB-1500 Nov Siemens Ltd Main Control System DB-1510 Jul Siemens Ltd Commercial Communications DB-1520 Jul Andrew Corporation Integrated Training System DB-1530 Dec Booz Allen & Hamilton (Australia) Ltd Automatic Revenue Collection DB-1650 Oct Thales e-transaction CGA S.A. Platform Screen Doors DB-1700 Oct Nissho Iwai-Nabco Consortium Escalators SI-1120 Oct Constructions Industrielles De La Mediterranee Lifts SI-1121 Oct Ryoden Lift & Escalator Co Ltd 13

14 Tunnel Ventilation System SI-1200 Jan Shinryo Corporation Electric Multiple Units SP-1900 Mar ,102 IKK Consortium Cab Simulators SP-1901 Feb Mitsubishi Electric (HK) Ltd Diesel Locomotives SP-2100 Jun Shenzhen Sunray Group Co Ltd Works Wagons & Rail Buses SP-2101 Jun LORIC Consortium OHL Maintenance Vehicles SP st Qtr 2002 (F) - - Rail Grinding Vehicle SP st Qtr 2002 (F) - - Track Tamping Vehicle SP st Qtr 2002 (F) - - Viaduct Inspection Unit SP-2105 TBD - - Ladder Trolleys SP-2106 TBD - - Permanent Way - Southern Area CC-1810 Sep Leighton-RSA JV Permanent Way - Northern Area Detailed Design Contracts (Civil) CC-1820 Sep Shun Wo-Henryvicy-China Railway Construction Corporation-Queensland Rail JV Yuen Long Section DD-200 Mar Ove Arup and Partners Hong Kong Ltd Tuen Mun Section DD-210 Mar Maunsell Consultants Asia Ltd Tsuen Wan Section DD-300 Mar Atkins China Ltd Sham Shui Po Section DD-400 Mar Hyder Consulting Ltd West Rail Depot and Station DD-600 Mar Parsons Brinckerhoff (Asia) Ltd F: Forecast TBD: To be determined 14

15

Water Supplies Department Active WSD Capital Works Contracts

Water Supplies Department Active WSD Capital Works Contracts No. Title Active WSD Capital s Location of or Start 17/WSD/14 Improvement to waterworks facilities at Lantau South and Sha Tin Fuk Shing 42.600 16-Nov-15 Nov-18 Lantau South and mainlaying at Keung South

More information

Property Development

Property Development Property Development The Group will continue strengthening its reputation by enhancing the quality of its products and services and branding individual projects. High project marketability and improved

More information

Legislative Council Panel on Transport Subcommittee on matters relating to railways

Legislative Council Panel on Transport Subcommittee on matters relating to railways LC Paper No. CB(1)1023/04-05(01) Legislative Council Panel on Transport Subcommittee on matters relating to railways MTR Performance and Asset Management - Follow up measures to Lloyd's Report by MTRCL

More information

Sponsorship and Exhibition Opportunities. Showcase your brand at the biggest NEC event in Asia Pacific NEC ASIA PACIFIC USERS GROUP CONFERENCE

Sponsorship and Exhibition Opportunities. Showcase your brand at the biggest NEC event in Asia Pacific NEC ASIA PACIFIC USERS GROUP CONFERENCE NEC ASIA PACIFIC USERS GROUP CONFERENCE 10 OCTOBER 2014 I LANGHAM PLACE HOTEL, MONGKOK, HONG KONG Sponsorship and Exhibition Opportunities Showcase your brand at the biggest NEC event in Asia Pacific neccontract.com/apconference14

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

Transit Oriented Development and Value Capture Hong Kong

Transit Oriented Development and Value Capture Hong Kong UNESCAP Regional Expert Group Meeting on Sustainable and Inclusive Transport Development and 2 nd Asia BRTS Conference, 29 Sep 1 Oct 2014, Ahmedabad Transit Oriented Development and Value Capture Hong

More information

Technical Journal. Paper 142

Technical Journal. Paper 142 Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager

More information

1. Senior / Executive Project Engineer (Civil)

1. Senior / Executive Project Engineer (Civil) 1. Senior / Executive Project Engineer (Civil) You will play a lead role in managing the Contractors in the construction of underground MRT stations namely Downtown Line, Thomson Line and enhancement to

More information

Asset Management Policy March 2014

Asset Management Policy March 2014 Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and

More information

Legislative Council Panel on Security

Legislative Council Panel on Security LC Paper No. CB(2)2585/03-04(01) Legislative Council Panel on Security Progress Report on the Implementation of the Drug Dependent Persons Treatment and Rehabilitation s (Licensing) Ordinance (Cap. 566)

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

53km. Deliver the New Era Network. Island Line Extension. will be added to our Hong Kong network. New Railway Projects are in progress

53km. Deliver the New Era Network. Island Line Extension. will be added to our Hong Kong network. New Railway Projects are in progress 53km will be added to our Hong Kong network Deliver the New Era Network 4 New Railway Projects are in progress Island Line Extension opened in December 2014 Executive Management s Report Hong Kong Network

More information

HKCS RESPONSE COMMONLY ACCEPTED AUDIT OR ASSESSMENT MECHANISM TO CERTIFY INFORMATION SECURITY STANDARDS

HKCS RESPONSE COMMONLY ACCEPTED AUDIT OR ASSESSMENT MECHANISM TO CERTIFY INFORMATION SECURITY STANDARDS Hong Kong Computer Society Room 1915, 19/F, China Merchants Tower, Shun Tak Centre, 168 Connaught Road Central, Hong Kong Tel: 2834 2228 Fax: 2834 3003 URL: http://www.hkcs.org.hk Email: hkcs@hkcs.org.hk

More information

Airport Rail Link is gathering speed. Wolfgang Rueprich, Project Manager Airport Rail Link, October 21, 2009

Airport Rail Link is gathering speed. Wolfgang Rueprich, Project Manager Airport Rail Link, October 21, 2009 Airport Rail Link is gathering speed Wolfgang Rueprich, Project Manager Airport Rail Link, October 21, 2009 Integrated Public Transit System for Metropolitan Regions Regional / Long Distance Rail Service

More information

Legislative Council Panel on Environmental Affairs. 209DS Outlying Islands sewerage, stage 1, phase 1 - consultants fees and investigations

Legislative Council Panel on Environmental Affairs. 209DS Outlying Islands sewerage, stage 1, phase 1 - consultants fees and investigations For discussion On 8 May 2001 Legislative Council Panel on Environmental Affairs 209DS Outlying Islands sewerage, stage 1, phase 1 - consultants fees and investigations Purpose This paper seeks Members

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 NCSA 01 Competency Based Assessment in Architecture THE

More information

ANNEX 8 Contract Management Strategy

ANNEX 8 Contract Management Strategy ANNEX 8 Contract Management Strategy Bath & North East Somerset, Bristol, North Somerset and South Gloucestershire Councils working together to improve your local transport Contract Management Strategy

More information

PROVISION OF CYCLE TRACK NETWORK IN THE NEW TERRITORIES. Executive Summary

PROVISION OF CYCLE TRACK NETWORK IN THE NEW TERRITORIES. Executive Summary PROVISION OF CYCLE TRACK NETWORK IN THE NEW TERRITORIES Executive Summary 1. Cycling is one of the popular recreational activities in Hong Kong. Many cyclists ride bicycles on cycle tracks for recreational

More information

STATE TRANSIT POSITION DESCRIPTION

STATE TRANSIT POSITION DESCRIPTION STATE TRANSIT POSITION DESCRIPTION POSITION: DIVISION: REPORTS TO: Manager Operational Support & Infrastructure Fleet Operations and Infrastructure General Manager Fleet Operations and Infrastructure GRADE:

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...

More information

JE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE:

JE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE: 1. JOB TITLE Job Title: Project Manager (Transport Infrastructure) Reports to: Design Programme Manager Service: Highways and Transport Environment & Infrastructure Date: November 2014 2. JOB PURPOSE To

More information

Central Hosting. Case Study

Central Hosting. Case Study Central Hosting Case Study October, 2014 Central Hosting Case Study Background An Chéim was originally set up to procure, distribute and implement key MIS systems (hardware and software) for the Institutes

More information

Construction Procurement Policy Project Implementation Process

Construction Procurement Policy Project Implementation Process Construction Procurement Policy Project Implementation Process Government of South Australia Copyright. January 2015 ISBN 978-0-7590-0217-3 The text in this document may be reproduced free-of-charge in

More information

Delivery Management Guidelines Delivery Process 2 - Project Management

Delivery Management Guidelines Delivery Process 2 - Project Management Delivery Management Guidelines Delivery Process 2 - Project Management Version control Version 9-1 Date 2010-10-18 Status Approved The IDMS Prov Infr Strat DP1: Portfolio Management DP1-1 Infrastructure

More information

LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY

LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY PacificTA LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY COOK ISLANDS MINISTRY OF INFRASTRUCTURE AND PLANNING NOVEMBER 2013 This report has been prepared for the Ministry of Infrastructure

More information

5 th Seminar on Best Practices for Urban Tree Management

5 th Seminar on Best Practices for Urban Tree Management Latest Development of Landscape Architectural Education and Accredited Arboricultural Practitioners Paul Chan Hong Kong Institute of Landscape Architects Milestone Development of Landscape Architectural

More information

Facilities Maintenance Contract

Facilities Maintenance Contract Re-tendering the Facilities Maintenance Contract Asset Management Services UTAS Property Portfolio Total Asset Management Reviewing options and preferences Contract structure & deliverables Tendering process

More information

to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015

to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 D to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 This page has been left blank intentionally Page 2 of 24 Page 3 of 24 This page has been left blank intentionally Page 4 of 24 Strategic

More information

Legislative Council Panel on Health Services Subcommittee on Health Protection Scheme. Role and Development of Public and Private Healthcare Services

Legislative Council Panel on Health Services Subcommittee on Health Protection Scheme. Role and Development of Public and Private Healthcare Services LC Paper No. CB(2)448/12-13(02) For discussion on 14 January 2013 Legislative Council Panel on Health Services Subcommittee on Health Protection Scheme Role and Development of Public and Private Healthcare

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

Procurement & Contracting Division. Request for Information (RFI) Concerning Procurement of Electrified Rolling Stock ("Rolling Stock")

Procurement & Contracting Division. Request for Information (RFI) Concerning Procurement of Electrified Rolling Stock (Rolling Stock) Request for Information (RFI) Concerning Procurement of Electrified Rolling Stock ("Rolling Stock") November 2013 1 Request for Information ( RFI ) Concerning the Procurement of Electrified Rolling Stock

More information

Cost Management Guidelines for. 1 September 2010

Cost Management Guidelines for. 1 September 2010 Cost Management Guidelines for Public Transport Investment Projects 1 September 2010 Table of Contents Foreword iv 1. Introduction 1 1.1 Purpose Of The Guidelines 1 1.2 Applicability 1 1.2.1 Conventionally

More information

Reshaping the urban quality of Hong Kong Using the Mass Transit Railway Networks

Reshaping the urban quality of Hong Kong Using the Mass Transit Railway Networks Reshaping the urban quality of Hong Kong Using the Mass Transit Railway Networks Raymond wai-man, Wong Professor chi-ming, Tam City University of Hong Kong The background Before 2007, HK s railway networks

More information

A Best Practice Guide

A Best Practice Guide A Best Practice Guide Contents Introduction [2] The Benefits of Implementing a Privacy Management Programme [3] Developing a Comprehensive Privacy Management Programme [3] Part A Baseline Fundamentals

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

POSITION DESCRIPTION, PERFORMANCE MEASURES AND TARGETS

POSITION DESCRIPTION, PERFORMANCE MEASURES AND TARGETS POSITION DESCRIPTION, PERFORMANCE MEASURES AND TARGETS Attachment 1 Position Title: Programs & Client Relations Manager Responsible to: Chief Executive Officer Responsibility: Programs Management and Client

More information

TfNSW Standard Requirements TSR T Technical Management

TfNSW Standard Requirements TSR T Technical Management Template Applicable to: Transport Projects Quality Management System Status: Division: Approved Transport Projects Version: 5.0 Desksite No.: 3455797_1 Date of issue: 1 July 2014 Effective date: 1 July

More information

The complete provider for. Gauging Products and Measurement Systems

The complete provider for. Gauging Products and Measurement Systems The complete provider for Gauging Products and Measurement Systems The Gauging Requirement Effective clearance assessment is something that concerns all railways and demands for significantly increased

More information

Legislative Council Panel on Security Creation of a permanent Chief Superintendent of Police post of the Cyber Security and Technology Crime Bureau

Legislative Council Panel on Security Creation of a permanent Chief Superintendent of Police post of the Cyber Security and Technology Crime Bureau LC Paper No. CB(2)1621/13-14(05) For discussion on 3 June 2014 Legislative Council Panel on Security Creation of a permanent Chief Superintendent post of the Cyber Security and Technology Crime Bureau

More information

Overview of Program Management Services and Proposed CIP FY2012-17

Overview of Program Management Services and Proposed CIP FY2012-17 Finance & Administration Committee Item III-A January 13, 2010 Overview of Program Management Services and Proposed CIP FY2012-17 Page 3 of 64 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

More information

www.germanrailgroup.eu

www.germanrailgroup.eu www.germanrailgroup.eu German RailGroup Engineering & Consulting GbR Hilpertstraße 20 64295 Darmstadt, Germany Phone + 49 (6151) 8 85-300 Fax + 49 (6151) 8 85-244 info@germanrailgroup.eu Your network for

More information

DIRECTORATE OF ESTATES & FACILITIES

DIRECTORATE OF ESTATES & FACILITIES DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:

More information

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling

More information

Scrim And Texture Data Collection Contract Management S Chamberlain

Scrim And Texture Data Collection Contract Management S Chamberlain Scrim And Texture Data Collection Contract Management S Chamberlain Introduction Transit New Zealand (Transit) has been successfully managing SCRIM and texture data collection through external suppliers

More information

Capital Works Management Framework

Capital Works Management Framework POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Last updated 18 June 2012 Will Simpson Senior Manager T: 0161 953 6486 E: will.g.simpson@uk.gt.com

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy

Customer requirements. Asset management planning Inspection and assessment Route asset planning Annual work plans Contracting strategy Section 8 Output monitoring Inputs Customer requirements Safety standards Outputs and funding SRA and Government Policy Network stewardship strategy Asset and operational policies Maintenance & renewal

More information

STRATEGY AND RESOURCES COMMITTEE ITEM 14 27 MARCH 2012 FACILITIES MANAGEMENT: FUTURE CONTRACTUAL ARRANGEMENTS

STRATEGY AND RESOURCES COMMITTEE ITEM 14 27 MARCH 2012 FACILITIES MANAGEMENT: FUTURE CONTRACTUAL ARRANGEMENTS FACILITIES MANAGEMENT: FUTURE CONTRACTUAL ARRANGEMENTS Report of the: Contact: Urgent Decision? If yes, reason urgent decision required: Annexes/Appendices: Other available papers: Director of Operations

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM 13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM This ESIA has identified impacts (both positive and negative) to the physical, natural and socio-economic environments, as well as to community and worker

More information

Construction Logistics Plan Guidance

Construction Logistics Plan Guidance Construction Logistics Plan Guidance For planners MAYOR OF LONDON Transport for London Section 1 Introduction Contents Section 1 Introduction 3 Section 2 Policy background 6 Section 3 Typical contents

More information

COWI s Role in the Copenhagen Metro Project

COWI s Role in the Copenhagen Metro Project COWI s Role in the Copenhagen Metro Project On the occasion of the award by the Copenhagen Cultural Foundation for COWI A/S part in the implementation of Phase 1 of the Copenhagen Metro 2 COWI s Role in

More information

CONSTRUCTION SOLUTIONS

CONSTRUCTION SOLUTIONS APA CONSTRUCTION SOLUTIONS ASIA PACIFIC Leading the way in Construction Solutions The outlook of the construction industry within the Asia Pacific region remains strong, however pressures to successfully

More information

Network Certification Body

Network Certification Body Network Certification Body Scheme rules for assessment of railway projects to requirements of the Railways Interoperability Regulations as a Notified and Designated Body 1 NCB_MS_56 Contents 1 Normative

More information

Public Transport Vehicle Management System. Request for Information

Public Transport Vehicle Management System. Request for Information Public Transport Vehicle Management System Request for Information Public Transport Authority Western Australia Page 2 of 11 Table of Contents 1 INTRODUCTION... 3 1.1 Information for Respondents... 3 1.2

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1

DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1 DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1 Guideline: DRAFT Planning the opening of a road project guideline Version: 1.1 Issue: September 2009 Approved By: Phil Margison General Manager,

More information

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words

More information

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012. RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as

More information

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption.

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption. Page 1 of 24 COMMUNITY AND SERVICES SPECIAL COMMITTEE REPORT 9 DECEMBER 2104 AGENDA ITEM 6.1 ASSET MANAGEMENT POLICY 2014 REVIEW Director: Manager: Ian Butterworth Director Infrastructure and Engineering

More information

APPLICATION FOR PERMISSION UNDER SECTION 16 OF THE TOWN PLANNING ORDINANCE (CAP. 131) GUIDANCE NOTES

APPLICATION FOR PERMISSION UNDER SECTION 16 OF THE TOWN PLANNING ORDINANCE (CAP. 131) GUIDANCE NOTES APPLICATION FOR PERMISSION UNDER SECTION 16 OF THE TOWN PLANNING ORDINANCE (CAP. 131) GUIDANCE NOTES INTRODUCTION 1 The following notes give information and guidance on how to apply for permission under

More information

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3 /01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,

More information

Track and Track Drainage Renewals Programme

Track and Track Drainage Renewals Programme Board Date: 26 March 2015 Item 14: Track and Track Drainage Renewals Programme This paper will be considered in public 1 Summary Track and Track Drainage Renewals Programme Existing Estimated Existing

More information

Infrastructure Asset Management Strategy

Infrastructure Asset Management Strategy Infrastructure Asset Management Strategy Strategy Owner Manager Parks and Assets Engineering and Infrastructure Creation Date 27 March 2006 Revision Date 4 March 2015 Please check Council s Intranet to

More information

The HS2 Environmental Minimum Requirements (EMR s) and Code of Construction Practice (CoCP)

The HS2 Environmental Minimum Requirements (EMR s) and Code of Construction Practice (CoCP) The HS2 Environmental Minimum Requirements (EMR s) and Code of Construction Practice (CoCP) January 2015 Leila du Toit Sustainable Construction Manager Environmental Minimum Requirements (EMR s) Environmental

More information

Australian Cost Engineering Society and AACE International. Cost Matters - Vital to Engineering 2015 Seminar Program (Victoria)

Australian Cost Engineering Society and AACE International. Cost Matters - Vital to Engineering 2015 Seminar Program (Victoria) Australian Cost Engineering Society and AACE International Cost Matters - Vital to Engineering 2015 Seminar Program (Victoria) Cost does matter, to all professionals and especially to engineers who have

More information

Environmentally Responsible Development

Environmentally Responsible Development Preamble Environmentally responsible development is about the delivery of a better quality of life for every one of our citizens, for now and for generations to come. We will support environmental protection

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

Procurement requirements for reducing waste and using resources efficiently

Procurement requirements for reducing waste and using resources efficiently Guidance for building and civil engineering projects Procurement requirements for reducing waste and using resources efficiently Model procurement wording for clients and contractors to cut waste on construction

More information

Managing ICT contracts in central government. An update

Managing ICT contracts in central government. An update Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Data Transparency - CRL Employees 58,200-149,999 - Data at 31 March 2014

Data Transparency - CRL Employees 58,200-149,999 - Data at 31 March 2014 3rd Party Agreements This post is critical to managing the risk to the Delivery of Crossrail arising from Third Party interfaces. The central purpose is to put in place the commercial agreements necessary

More information

Management Summary to Final Report Version 2

Management Summary to Final Report Version 2 Report EU Databases and Interfaces Study Management Management to Final Report Version 2.. Document control Superseded documents Version history Version Date Comments 1 14.01.2012 to Final Report 2 10.02.2012

More information

CORPORATE GOVERNANCE REPORT

CORPORATE GOVERNANCE REPORT MISSION STATEMENT OF CORPORATE GOVERNANCE We are delighted to have maintained excellence in corporate governance in order to supply value added PCBs to the market and consider the balance of all the stakeholders

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

NHS BLOOD AND TRANSPLANT MARCH 2009 RESPONDING EFFECTIVELY TO BLOOD DONOR FEEDBACK

NHS BLOOD AND TRANSPLANT MARCH 2009 RESPONDING EFFECTIVELY TO BLOOD DONOR FEEDBACK 09/26 NHS BLOOD AND TRANSPLANT MARCH 2009 RESPONDING EFFECTIVELY TO BLOOD DONOR FEEDBACK EXECUTIVE SUMMARY From April 2009 an NHS wide common approach to complaint handling comes in to effect. This provides

More information

ECONOMIC CONTRIBUTION

ECONOMIC CONTRIBUTION ECONOMIC CONTRIBUTION HKIA works around the clock to support Hong Kong s role as a financial, logistics and transportation hub by connecting the city, the PRD and Southeast Asia through its large network

More information

IT1T Integrated Recruitment Systems 2015

IT1T Integrated Recruitment Systems 2015 UCD IT Services IT1T Integrated Recruitment Systems 2015 Project Initiation Document Version 1.0 2 December 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial Draft

More information

PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS

PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS NORTH LONDON WASTE AUTHORITY Agenda Item No: REPORT TITLE: PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS REPORT OF: HEAD OF WASTE STRATEGY AND CONTRACTS FOR SUBMISSION TO: DATE: AUTHORITY MEETING 11

More information

Development of a Safety Management System in Hong Kong MTR Corporation. Carl Wu, Safety & Quality Support Manager, MTR Corporation, Hong Kong

Development of a Safety Management System in Hong Kong MTR Corporation. Carl Wu, Safety & Quality Support Manager, MTR Corporation, Hong Kong Development of a Safety Management System in Hong Kong MTR Corporation Carl Wu, Safety & Quality Support Manager, MTR Corporation, Hong Kong Abstract: Safety of customers, the public, contractors and staff

More information

Transport for London. Projects and Planning Panel

Transport for London. Projects and Planning Panel Agenda Item 5 Transport for London Projects and Planning Panel Subject: Project Monitoring Project s Date: 9 January 2014 1 Purpose 1.1 To present to the Panel the forward approval programme for projects

More information

THE QUALITY MANAGEMENT SYSTEM IS YOURS UP TO STANDARD?

THE QUALITY MANAGEMENT SYSTEM IS YOURS UP TO STANDARD? THE QUALITY MANAGEMENT SYSTEM IS YOURS UP TO STANDARD? Nigel Anderson, Head of Global Service Delivery Group Corporate Facilities Management, EMEA 1. SETTING THE SCENE Customer service expectations in

More information

MTR Corporation. 2015 Interim Results 13 August 2015

MTR Corporation. 2015 Interim Results 13 August 2015 2015 Interim Results 13 August 2015 Page 1 Forward-looking statements Certain statements contained in this presentation may be viewed as forward-looking statements. Such forwardlooking statements involve

More information

Guideline for Professional Services Contractor Performance Reporting

Guideline for Professional Services Contractor Performance Reporting ` Guideline for Professional Services Contractor Performance Procedure Applicable to: Transport Projects Quality Management System Status: Approved Division: Transport Projects Version: 10 Date of issue:

More information

Legislative Council Panel on Security. Construction of an Ambulance Depot at Choi Shun Street, Sheung Shui

Legislative Council Panel on Security. Construction of an Ambulance Depot at Choi Shun Street, Sheung Shui LC Paper No. CB(2)2452/11-12(03) For discussion on 4 July 2012 Legislative Council Panel on Security Construction of an Ambulance Depot at Choi Shun Street, Sheung Shui PURPOSE This paper consults the

More information

Monitoring Highways England The monitoring framework

Monitoring Highways England The monitoring framework Monitoring Highways England The monitoring framework October 2015 Contents Executive summary 4 Roads reform 4 ORR s role in monitoring Highways England 5 What we will do next 10 1. Overview of this document

More information

London Borough of Bromley COMMISSIONING - PROPOSED TOTAL FACILITY MANAGEMENT CONTRACT

London Borough of Bromley COMMISSIONING - PROPOSED TOTAL FACILITY MANAGEMENT CONTRACT Report No. DRR14/089 London Borough of Bromley PART 1 - PUBLIC Decision Maker: Executive Date: 15 th October 2014 Decision Type: Non-Urgent Executive Key Title: COMMISSIONING - PROPOSED TOTAL FACILITY

More information

How To Write A Contract

How To Write A Contract Commercial Management the NEC Way Hong Kong Institute of Surveyors Ian.Heaphy@turntown.com Mark.Lyddon@turntown.com, July 2014 Turner & Townsend plc July 14 making the difference Health, safety & wellbeing

More information

ata ports & harbours airports railways roads & highways 0333 0112 046 info@ata-recruitment.co.uk www.ata-recruitment.co.uk

ata ports & harbours airports railways roads & highways 0333 0112 046 info@ata-recruitment.co.uk www.ata-recruitment.co.uk TRANSPORT INFRASTRUCTURE RECRUITMENT airports ports & harbours roads & highways railways 0333 0112 046 info@-recruitment.co.uk INTRODUCTION ATA has specialist operating teams who are strategically focussed

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

CABINET. 12 January 2006 PROCUREMENT OF CUSTOMER RELATIONSHIP MANAGEMENT COMPUTER SOFTWARE. Report of the Assistant Chief Executive (CH)

CABINET. 12 January 2006 PROCUREMENT OF CUSTOMER RELATIONSHIP MANAGEMENT COMPUTER SOFTWARE. Report of the Assistant Chief Executive (CH) CABINET 12 January 2006 PROCUREMENT OF CUSTOMER RELATIONSHIP MANAGEMENT COMPUTER SOFTWARE Report of the Assistant Chief Executive (CH) RECOMMENDATION That Cabinet 1 confirm the approach to implementing

More information

Role in the project (e.g. Prime Engineering Consultant or Contractor), and summary of professional Duties : Name Professional Duties Contract Awarded?

Role in the project (e.g. Prime Engineering Consultant or Contractor), and summary of professional Duties : Name Professional Duties Contract Awarded? PROPOSAL FORM FOR SINGLE PROJECT PROFESSIONAL INDEMNITY NOTE: THIS IS A PROPOSAL FOR A CLAIMS MADE POLICY Note : Please provide any necessary explanations or additional details by attachment to this Proposal

More information

Contract Management Guideline

Contract Management Guideline www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract

More information

Hong Kong means business in sustainable development

Hong Kong means business in sustainable development SHOWCASING THE Achievements the Hong Kong Civil Service of Hong Kong means business in sustainable development ENVIRONMENTAL PROTECTION DEPARTMENT Hong Kong s status as Asia s world city is backed by its

More information

PROJECT AGREEMENT FOR THE PLANNING AND DESIGN OF THE COMMON REGISTRY SOLUTIONS

PROJECT AGREEMENT FOR THE PLANNING AND DESIGN OF THE COMMON REGISTRY SOLUTIONS PROJECT AGREEMENT FOR THE PLANNING AND DESIGN OF THE COMMON REGISTRY SOLUTIONS Council of Australian Governments An agreement between the Commonwealth of Australia and the States and Territories, being

More information