1 Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: E: Last updated 18 June 2012 Will Simpson Senior Manager T: E: Paul Eckersley Manager Technology Risk T: E: Distribution Timetable For action Fieldwork completed 13 April 2012 Daniel Benjamin, Director of Corporate Draft report issued 3 May 2012 Services David Wells Head of IT Management 16/5/2012 comments For information Christopher Graham Information Commissioner Final report issued 16/5/2012

2 Contents Sections 1 Executive Summary 1 2 Detailed Findings 3 A Internal audit approach 12 B Definition of internal audit ratings 14 C Outline Project Timescales 15 Glossary The following terms are used in this report: Capita ICO's current IT service provider GPS Government Procurement Services ICO Information Commissioner's Office IT Information Technology MoJ Ministry of Justice OJEU Official Journal of European Union Options Study review to establish ICO preferred procurement strategy Project Board body responsible for representing ICO, monitoring progress and providing authorisation to project on decision TUPE Transfer of Undertakings (Protection of Employment) Law This report is confidential and is intended for use by the Management and Directors of The Information Commissioner's Office only. It forms part of our continuing dialogue with you. It should not be made available, in whole or in part, to any third party without our prior written consent. We do not accept responsibility for any reliance that third parties may place upon this report. Any third party relying on this report does so entirely at its own risk. We accept no liability to any third party for any loss or damage suffered or costs incurred, arising out of or in connection with the use of this report, however such loss or damage is caused. It is the responsibility solely of The Information Commissioner s Office management to ensure that there are adequate arrangements in place in relation to risk management, governance and control.

3 1 Executive Summary 1.1 Background A significant proportion of the ICO's IT Services are provided under an outsource contract with Capita. This contract was due to expire in July 2012 but was extended to July 2013 in order to allow the ICO more time to consider its overall requirements and other ways in which they could be delivered. An options study was conducted with a recommendation to the Executive Team on how to proceed. The renewal will be undertaken within the framework of the Government strategy on IT procurement and takes into account the requirement for all government departments to identify savings, including opportunities through re-tenders. Key dates for the IT Procurement Project June '11 IT Procurement Project established. Nov '11 Project manager employed to establish the available options to the ICO, determine management priorities and what IT services will be required. May '12 OJEU notice to be published Aug '12 ITT to be issued to suppliers Jan '13 Select successful supplier to be done We have been asked by Senior Management and the Audit Committee to provide assistance at key stages of the process. This is our second review, on progress made and plans for the future as the ICO prepares to publish the public sector tender notice in the Official Journal of European Union (OJEU) in May Note: Management has recognised that it needs additional support to ensure a successful tender and supplier selection. We will provide initial assistance as part of Internal Audit Plan and Grant Thornton's Performance Improvement Team may be commissioned to provide further assistance to management in due course. 1.2 Scope The agreed focus of the second phase was to: review the project governance, management and reporting controls; provide a progress report on the project; review the options under consideration; and confirm that the potential options support the IT Strategy. Further details of our scope and approach can be found in Appendix A. 1.3 Audit Opinion Our focus during this phase of the audit has been to provide assurance over the progress towards the testing phase of the project, and to provide assistance to those preparations. At this stage, it is not possible to assess the operating effectiveness as preparation for the tender has not started. Design effectiveness Overall, we have concluded that in the areas examined the risk management activities and controls are suitably designed to achieve the risk management objectives required by management Management needs to ensure that alternative procurement arrangements are in place if government procurement frameworks are not available and establishing formal terms of reference for the project board. Amber 2012 Grant Thornton UK LLP. All rights reserved. 1

4 The Information Commissioner's Office Internal Audit IT Procurement Review- Phase 2 1. Executive summary Further details of our findings and recommendations are provided in Section Progress since the last internal audit review The contract extension to Capita is now in place and will expire in July The Options Study was being finalised at the time of our latest fieldwork, with the final version expected to be submitted to the Executive Team by end of April We understand that the study is likely to recommend tendering for two lots of services, with existing Government frameworks being used for the remaining services. Final details of the proposals are currently being agreed with the various stakeholders. 2 Organising the tender into separate lots may not support an effective tender process, possibly precluding some suppliers and duplicating some services unnecessarily (i.e hardware support for the servers and desktops required by each lot); and 3 Formal project controls need to be established, including detailing roles, responsibilities and authority of the Project Board, and confirming objectives of the tendering process. 1.6 Acknowledgement We would like to take this opportunity to thank the staff involved in for their co-operation during this internal audit. 1.5 Key findings The following table details the key findings from our review. Further details of our findings and recommendations are provided in Section 2. Risk / Process High Medium Low Improve't Procurement activities Project governance 1 2 Previous IA review Total Refer to Appendix B for definitions of internal audit recommendation ratings. No findings have been rated a high priority. Each of our recommendations aims to help the ICO to establish an appropriate approach to its tendering processes in order to obtain IT services that will best meet its current and future requirements. The three medium rated findings relate to: 1 A key Government framework, web hosting and development, may not be in place by the time that the ICO needs it so those services may need to be tendered separately; 2012 Grant Thornton UK LLP. All rights reserved. 2

5 2 Detailed Findings 2.1 Procurement activities 1. Medium Government procurement framework not in place Finding and Implication Proposed action Agreed action (Date / Ownership) The Project Board identified that there was the opportunity to utilise Management to establish how long the existing frameworks for some of the services currently being provided tendering process for web hosting and [Action as agreed by client]. by Capita or other suppliers. One of those frameworks is for web development services would take, and hosting and web site development. At the time of this review, the work back from July 2013 to establish The web elements have been moved into framework was only at early stages of being drafted by Government when a decision about the tendering the main contract. The contingent option of Procurement Services (GPS), so there is a strong possibility that the process needs to be made. In addition, obtaining the web hosting/services through framework may not be in place when ICO need to procure those preparatory work should be undertaken so a separate procurement exercises was services. that the organisation is fully ready to reviewed. This was considered not to be a commence such alternative tendering viable option as, given the contract value, a Discussion with management has identified that whilst this was a procedures if and when they are needed. full OJEU would be required. known risk, no contingency was in place should the framework not be available to the ICO when it is needed. Framework agreements make Recommend this action is closed procurement a simpler process and organisations benefit from negotiations undertaken by GPS. Therefore, if the framework is not available and ICO have to tender directly for web hosting and development services, consideration needs to be given to when that decision has to be made, in order to allow sufficient time for a separate Date Effective: 10 May 2012 tender to be issued for those services or for web hosting and development services to be included within the Invitation to Tender currently being planned. An outline of project timescales (see Appendix C) has been established, but management have not yet established when such a decision would need to be made Grant Thornton UK LLP. All rights reserved. 3

6 2. Medium Presentation of lots for tender Finding and Implication Proposed action Agreed action (Date / Ownership) ICO has mapped out all the current services being provided by Capita Management to consider re-organising the [Action as agreed by client]. and other third-party suppliers to determine what lots would be offered. lots to ensure similar services are These have packaged into two lots: Hardware Service plus Operating packaged together that maximise supplier's System Service and Applications Service plus Desktops / Office offering, but provides ICO with flexibility As noted in recommendation 1 the web Hardware Service. over the service provided to meet future elements have been brought into the main needs. contract. However, there is duplication between the two lots and it is not clear why the lots are organised as they are. For example, server hardware support and configuration is to be provided as part of the Hardware Service plus Operating System Service lot but desktop hardware support is to be delivered as part of the Applications Service plus Desktops / Office hardware Service. Most suppliers who provide server hardware support also offer desktop support as some of the skills required are common and there are some dependencies on server configuration to how desktops operate. The potential value of each lot is similar and this may be why the lots have been collated as they have been. At the time of the field visit by GT the work to split and define the service was work in progress and based on the options study. Since then more detailed reviews and definitions of the services have been developed and the summary descriptions reviewed to ensure clarity. Recommend this action is closeddate Effective: 10 May 2012 During the review, we discussed with the management the dependency on web hosting and web development government procurement framework. We agreed with management that a contingency will be needed and one such contingency would be to include web hosting and web development, However, web hosting is largely a generic service where capacity and availability of service are the key areas to consider. Web development is much more likely to be closely aligned to the organisation's needs and requires a partnership approach. Management may get better quality bids if these two services are offered separately. If lots are not correctly organised, ICO may not get the best value for the services provided, and different suppliers are providing similar services or not making best use of supplier's specialist services. Lots correctly organised should ensure ICO achieves the objectives of continuity of IT services, clarity over accountability for each service support government procurement objectives and allowing flexibility to 2012 Grant Thornton UK LLP. All rights reserved. 4

7 accommodate future ICO needs. If the lots are not organised effectively, the ICO may receive poor quality bids, supplier bids may overlap resulting in duplication and increased cost or suppliers may not bid at all Grant Thornton UK LLP. All rights reserved. 5

8 2.2 Project Governance 3. Medium Project controls Finding and Implication Proposed action Agreed action (Date / Ownership) Prior to the appointment of the Director of Corporate Services, the IT Project Manager to document the Terms of [Action as agreed by client]. Procurement project had not been managed on a formal basis. The Reference for the Project Board that Director of Operations (acting project sponsor), Head of IT and Head of should include: Finance met as and when required and fulfilled the Project Board A governance paper has been developed, function. However, meetings were not documented, roles and roles and responsibilities of members agreed by Project Board and by the responsibilities were not been formally established and agreed. of the board and, where and when Executive Team Updating the Executive Team on progress is achieved through the additional authority is to be sought Project Sponsor being a member of the Executive Team and not by any frequency of project board meetings No further action proposed formal reporting. authority of the board to make The newly appointed Director of Corporate Services established regular meetings of the project board, which consists of Director of Corporate Services, Director of Operations, Head of Finance Head of IT and Options Study Project Manager. However, the Terms of Reference has not been established that clearly sets out the role and responsibility of the Project Board, what authority it has and when additional authorisation is required. Key decisions need to be appropriately discussed, concluded and communicated. Project Board should formally record key decisions. For example: content of the OJEU notice; agreement over the objectives of the tendering process that support how to organise the lots; and how to select which suppliers to send the ITT to. Project board need to agree with the Executive Team what the priorities are for the procurement of IT service, such as lowest cost or minimal disruption to users. These two examples of objectives may not be complimentary and the ICO may need to prioritise one over the other. decisions Responsibility for updates to the Executive Team prior to any MoJ liaison meetings determine what reporting will be required Project Board to establish the key objectives of the tendering process, in order to prioritise activities to meet those objectives. Project board should also agree what key decisions are required, when the decisions will be made and whether additional authority beyond the Project Board may be necessary, such as the Executive Team. Date Effective: 10 May Grant Thornton UK LLP. All rights reserved. 6

9 3. Medium Project controls Finding and Implication Proposed action Agreed action (Date / Ownership) 4. Low Liaison with Ministry of Justice Finding and Implication Proposed action Agreed action (Date / Ownership) ICO is required to keep the MoJ informed of any significant events and updated on activities, through on-going liaison meetings. These meetings were attended by the Information Commissioner or the Director of Operations. [Action as agreed by client]. Prior to the appointment of the Director of Corporate Services, the Director of Operations was the project sponsor and a member of the Project Board. The Director of Operations also attended some MoJ liaison meetings. Updates to the MoJ on the IT Procurement Project were provided but they were not prepared and agreed by the Project Board. The Director of Corporate Services is now the sponsor for the project and is not expected to attend liaison meetings with MoJ going forward. The IT Procurement Project Manager should obtain the schedule of liaison meetings with MoJ, in order to prepare a formal update report of project progress and raise any issues that MoJ need to be made aware of. Project Board needs to ensure that the Information Commissioner or Director of Operations is appropriately briefed, especially if the Director of Operations is not involved in the liaison meeting. Confirm that Director of Corporate Services attends the quarterly MoJ liaison meetings Dates of next meetings with MoJ have been noted in project calendar. Reporting to MoJ, Management Board and Executive team is detailed in the Governance paper. Recommend this action is closed Date Effective: 10 May Grant Thornton UK LLP. All rights reserved. 7

10 5. Low Complete set of Project Documents Finding and Implication Proposed action Agreed action (Date / Ownership) The Project Manager has established a Project Initiation Document for Project Manager to agree with Project [Action as agreed by client]. IT Procurement but it relates to setting up the project for the Options Sponsor what documentation set is Study and not for the wider project of procuring IT Service. According required for the project and draft those to the ICO Project Management Methodology a number of documents documents for the Project Board's Agreed. Governance paper approved by are expected to be established as part of any major project, including: consideration and approval, where ET. Weekly reporting in place, RAID logs necessary being used. PID final approval target date end May 2012 Project checklist; Project brief; Business case; Recommend this action is closed Issue, risk, action, and decision logs; Project Initiation Document; and Date Effective: 16 May 2012 Project Board meeting minutes. At the time of the review, we had access to a project brief and project time lines which related to the Options Study phase only. The project has progressed sufficiently for plans to be drawn up for the procurement activity. ICO management had recognised this and are now in the process of setting the project on a formal basis, including documentation which will support governance over the project and ensure visibility over decisions made. With a lack of detail over the intention for managing the procurement process, it is possible that: decisions are made without support of the Executive Team, services are procured that do not best support ICO requirements, and project team is unclear on roles and responsibilities. Consequently the lack of clarity may delay elements of the project or key milestones may not be achieved, which if on the critical path, may result in ICO not having continuity of IT services Grant Thornton UK LLP. All rights reserved. 8

11 2.3 Progress on findings from previous review Agreed action Status progress Further agreed action (Date / Ownership) 1. Action: Director of Operations to liaise with MoJ on the issue at regular MOJ liaison meetings and via correspondence and ad-hoc meetings. See finding 2 above The ICO (Director of Operations) will liaise directly with the MoJ as our sponsoring department and primary link to central government. In addition the Head of IT will continue to review government direction using existing sources primarily trade press, websites and press monitoring. These sources have given good coverage since the ICT strategy was launched in March. It is anticipated that there will be a government update on procurement in August Date Effective: Review end of August 2011 Owner: Director of Operations Regular liaison meetings occur with Ministry of Justice, where either the Information Commissioner or the Director of Operations provides updates. Head of IT is attending government procurement conferences to ensure current government strategy is understood in addition to meeting the Ombudsman Association to share best practice. 2. Action a: Agree. Approval has been given for the recruitment of an experienced person on a short fixed term contract to undertake this study. Date Effective: Job description to be agreed and recruitment to start by end of July Action b: A risk register will be created as part of project governance (see 6). Engagement with ET, MB and AC will happen throughout the IT procurement. Risks have been identified through work on the IT strategy and been developed further by Internal Audit. The risks will feed into development of plans and the scoping of the options study. A risk workshop will be run as part of the options study scoping process. Corporate Governance can assist in this. Date Effective: August 2011 Action c: Detailed review of services provided by Capita Bill Ritchie appointed in November 2011 Awaiting risk register being established as part of the Options Study, in draft but not completed. Analysis of services provided by Capita has been completed and chart of those services now exists. This has been used to drive definition of the lots to be tendered. none See finding 4 above 2012 Grant Thornton UK LLP. All rights reserved. 9

12 Agreed action Status progress Further agreed action (Date / Ownership) 3. Action a: Agreed review skills of existing team, to establish the gap for an in-house solution. Date Effective: September 2011 In-house solution is not preferred solution. IT to focus on supplier and contract management skills. Intention is to recruit those skills. None Action b: Agreed review IT policy and procedures gaps between services and what might be brought in-house. Date Effective: November Action a: Current government policy on websites and web development means that the future of the ICO s site is uncertain and subject to the decisions of central government. However any re-procurement will look to align hosting and development if at all possible. We are keeping the situation under review. Date Effective: Review in October 2011 Owner: Head of Corporate Affairs Action b: As above. Date Effective: Review in October a) We recommend early consideration of the TUPE aspects of the contract re-negotiation and suggest all relevant parties are approached early in the process to give an initial indication of the potential costs of the TUPE transfers. Action a: Noted. To be considered in evaluations of options. (Consider TUPE implications if services brought in-house). Date Effective: Review April 2012 b) The Head of IT should develop a Staffing Strategy to consider the impact of the procurement issues such as TUPE, additional skills requirements and succession planning. Whichever option is adopted, there will be a considerable impact on existing IT staff which needs consideration and management. Action b: Agreed. To be considered in evaluations of options with the support of Organisational Development. Will also be included in discussion of risks (see 2c) Date Effective: Review April 2012 No longer necessary as in-house provision is not the preferred option. Management looked into recruiting web developer as part of the IT department. This was unsuccessful (skills required in one person could not be found). Management plans to use existing framework or make part of the tender to procure such a service. In-house proposition not a preferred solution. See finding 1 above None 2012 Grant Thornton UK LLP. All rights reserved. 10

13 The Information Commissioner's Office Internal Audit IT Procurement Review- Phase 2 1. Executive summary Agreed action Status progress Further agreed action (Date / Ownership) 6. Action: Project brief and PID to be developed, a project board will See finding 4 and 5 above be formed. Date Effective: July Action: A gap analysis will be undertaken using the findings from the Internal Audit of BC and the current DR/BC provision. Work has started on a technical evaluation of improvements to the give greater resilience for remote access and regional offices. Government strategy is to consolidate data centres and is the most likely final destination for most of ICO s hardware any such provision would be expected to provide adequate BC and DR. The contract extension must provide maximum flexibility around provision of DR, including possible early termination of Sunguard if required. Date Effective: Review November 2011after Internal audit report received Business Continuity is to be included as part of the tender. The existing DR provision will expire at the end of the current contract in July Grant Thornton UK LLP. All rights reserved. 11

14 A Internal audit approach Approach and Scope The objective of the review was to provide assurance to IT Management and the Business that the IT Procurement project will provide a robust approach to defining requirements and moving to an IT Service provision which is appropriate for the business, following the end of the current contract with Capita. We focussed on the following sub risks: The project may not engage sufficiently with Government stakeholders resulting in a failure to obtain the relevant approvals and expenditure commitments; Project governance structures, planning and reporting may be inadequate to ensure the successful replacement of the existing outsource contract; The options study may not be conducted effectively resulting in a failure to identify all possible solutions or align them properly to the IT Strategy and needs of the ICO in the longer term; Planned implementation timescales may not be achieved leading to a failure to maximise on the benefits identified in the business case. Our internal audit approach is based upon the underlying principles of the UK Corporate Governance Code (2010) guidelines on internal control that require management to identify, assess and manage the risks that are significant to the achievement of the organisation s overall business objectives. Our role as internal auditor is to provide objective and independent assurance to the Audit Committee and management that it is doing this successfully for each of the areas being audited. Our audit was carried out in accordance with the guidance contained within the Government s Internal Audit Standards (2011) and the Auditing Practices Board s Guidance for Internal Auditors. We also have regard to the Institute of Internal Auditors guidance on risk based internal auditing (2005). In accordance with our agreed internal audit plan, we agreed to undertake a review of the Information Commissioner's Office's project to identify options for replacing the existing outsourced IT Contract with Capita. This review will further inform our on-going understanding of ICO's governance and risk management activities. We achieved our audit objectives by: meeting with key staff to gain an understanding of the arrangements in place, building upon the information we have already gained through our audit planning process; assessing the effectiveness of the control mechanisms in place to mitigate identified risks; discussion of key findings with management and preparation of a draft report Grant Thornton UK LLP. All rights reserved. 12

15 The Information Commissioner's Office Internal Audit IT Procurement Review- Phase 2 1. Executive summary The findings and conclusions from this review will support our annual opinion to the Audit Committee on the adequacy and effectiveness of internal control arrangements. Responsibilities It is the responsibility of management to ensure that there are adequate controls and activities in place to ensure that the ICO's business objectives can be met and that the risks to the ICO are minimised. Based on the work we have carried out, we provide an objective assessment of the adequacy and effectiveness of controls and activities established by management to manage the identified risks to the ICO. During the course of our review we have conducted interviews and, where necessary, testing/verification work to support our assessment of the adequacy and effectiveness of current arrangements. Additional information Client staff The following people were consulted as part of this review: Daniel Benjamin, Director of Corporate Services; David Wells, Head of IT; John Rackstraw, Senior IT Service Delivery Manager; Angela Muston, Solicitor; Bill Richie, Options Study Project Manager Andy Cryer, Head of Finance. Locations The following locations were visited during the course of this review: Wilmslow Office It is our reporting protocol to balance our reporting of positive practice with areas for attention. This enables the ICO to build upon its strengths, whilst focusing upon key findings and associated recommendations, which if acted upon, should enhance the control environment and improve the management of key risks. Please refer to our letter of engagement for full details of responsibilities and other terms and conditions Grant Thornton UK LLP. All rights reserved. 13

16 B Definition of internal audit ratings Audit issue rating Within each report, every audit issue is given a rating. This is summarised in the table below. Rating Description Features High Key control not designed or operating effectively Findings that are fundamental to the management of risk Potential for fraud identified in the business area, representing a weakness in control Non compliance with key procedures / standards that requires the immediate attention of management Non compliance with regulation Impact is contained within the department and compensating controls would detect errors Medium Important findings that are to be resolved by line Possibility for fraud exists management. Control failures identified but not in key controls Non compliance with procedures / standards (but not resulting in key control failure) Low Findings that identify non-compliance with established Minor control weakness procedures. Minor non compliance with procedures / standards Improvement Information for department management Items requiring no action but which may be of interest to Control operating but not necessarily in accordance management or best practice advice with best practice 2012 Grant Thornton UK LLP. All rights reserved. 14

17 The Information Commissioner's Office Internal Audit IT Procurement Review- Phase 2 1. Executive summary C Outline Project Timescales Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Authority to issue OJEU Notice 27/04 Publish OJEU Notice 30/05 (Minimum of 37 days from publication of the OJEU notice) Deadline for Expression of Interest Combined OJEU/PQQ 09/07 Prepare & Issue PQQ 30/05 Expression of interest would be evidenced by the return of a completed PQQ PQQ Returns Submission Date 09/07 Review PQQs & agree shortlist Prepare & Issue ITT + Contract 06/08 06/08 (Minimum of 40 days from the issue of the ITT) Clarification & receipt of final tenders 15/10 Evaluation & confirm preferred bidder 09/01 ICO activity Due Diligence Contract Award Supplier activity 07/03 Contract Signed 18/03 Initial Transition (Minimum of 10 days from contract award) Contract Start Date Service Freeze Project Freeze Change Freeze 10/ Grant Thornton UK LLP. All rights reserved. 15

18 Grant Thornton UK LLP. All rights reserved. "Grant Thornton" means Grant Thornton UK LLP, a limited liability partnership. Grant Thornton UK LLP is a member firm within Grant Thornton International Ltd ('Grant Thornton International'). Grant Thornton International and the member firms are not a worldwide partnership. Services are delivered by the member firms independently. This publication has been prepared only as a guide. No responsibility can be accepted by us for loss occasioned to any person acting or refraining from acting as a result of any material in this publication.

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office Internal Audit 2013-14: Follow up Last updated 4 July 2014 Distribution For action Senior Corporate Governance Manager Timetable Fieldwork completed 21 May 2014 Draft

More information

IT Re procurement 2013 project governance

IT Re procurement 2013 project governance ICO IT Re procurement 2013 project governance A summary of the recommended project governance that will be required to deliver the IT re procurement project Bill Ritchie Version 1.0 26 Apr 2012 Contents

More information

Information Commissioner's Office

Information Commissioner's Office Phil Keown Engagement Lead T: 020 7728 2394 E: philip.r.keown@uk.gt.com Will Simpson Associate Director T: 0161 953 6486 E: will.g.simpson@uk.gt.com Information Commissioner's Office Internal Audit 2015-16:

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Internal Audit 2011-12: Business Continuity Review Last updated 6 February 2012 Will Simpson Senior Manager

More information

Information Commissioner's Office

Information Commissioner's Office Information Commissioner's Office Review of the Agile process used to develop the ICE system Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Last updated 15 March 2013 Will Simpson Senior

More information

Cllr Ray Theodoulou. Yes Lead Member report dated 18 th March 2013 Tender documents Draft Contracts from the framework

Cllr Ray Theodoulou. Yes Lead Member report dated 18 th March 2013 Tender documents Draft Contracts from the framework IT Managed Services/SAP Support Services Contract Cabinet Date 10th July 2013 Finance and Change Cllr Ray Theodoulou Key Decision Background Document Location/Contact for inspection of Background Documents

More information

Page 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health

Page 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health Page 5 Agenda Item 5 Report to: The Adult Social Services and Health Committee Date: 20 th November 2012 Report of: The Strategic Director of Adult Social Services, Housing and Health Ward Location: All

More information

Manchester City Council

Manchester City Council Manchester City Council Accounts Audit Plan 2009/10 18 December 2009 Contents Page 1 Introduction 2 2 Approach and audit risks 3 3 Administration 13 4 Planned outputs 16 Appendices A B IFRS Action Plan

More information

Internal Audit - progress report 2015-16 and 2016-17 plan

Internal Audit - progress report 2015-16 and 2016-17 plan Audit Committee, 16 March 2016 Internal Audit - progress report 2015-16 and 2016-17 plan Executive summary and recommendations Introduction Grant Thornton have prepared the attached report which sets out

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support Final Report Version 1.1 Oct 2009 Contents 1. Executive Summary...3 2. Context and Background...3 3. Deliverables and Value Added...

More information

Dacorum Borough Council Final Internal Audit Report

Dacorum Borough Council Final Internal Audit Report Dacorum Borough Council Final Internal Audit Report ICT Change Management Distribution list: Chris Gordon Group Manager Neil Telkman - Information, Security and Standards Officer Gary Osler ICT Service

More information

Central Hosting. Case Study

Central Hosting. Case Study Central Hosting Case Study October, 2014 Central Hosting Case Study Background An Chéim was originally set up to procure, distribute and implement key MIS systems (hardware and software) for the Institutes

More information

Managing ICT contracts in central government. An update

Managing ICT contracts in central government. An update Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government

More information

CRM Phase 3 Development, support and maintenance - Questions and Answers

CRM Phase 3 Development, support and maintenance - Questions and Answers No. Question Answer 1. 2. 3. 4. 5. 6. 7. Are we able to discuss the requirements of this tender with the UKCES prior to submitting our proposal? Can we be placed on a list to be notified of future opportunities

More information

Page 97. Executive Head of Asset Planning, Management and Capital Delivery

Page 97. Executive Head of Asset Planning, Management and Capital Delivery Page 97 Agenda Item 7 Report to: Strategy and Resources Committee Date: 16 December 2013 Report of: Executive Head of Asset Planning, Management and Capital Delivery Ward Location: Not applicable Author

More information

Governance, Risk and Best Value Committee

Governance, Risk and Best Value Committee Governance, Risk and Best Value Committee 2.00pm, Wednesday 23 September 2015 Internal Audit Report: Integrated Health & Social Care Item number Report number Executive/routine Wards Executive summary

More information

Aberdeen City Council

Aberdeen City Council Aberdeen City Council Internal Audit Report Final Contract management arrangements within Social Care & Wellbeing 2013/2014 for Aberdeen City Council January 2014 Internal Audit KPI Targets Target Dates

More information

Digital Inclusion Programme Started. BL2a

Digital Inclusion Programme Started. BL2a PROJECT BRIEF Project Name Digital Inclusion Programme Status: Started Release 18.05.2011 Reference Number: BL2a Purpose This document provides a firm foundation for a project and defines all major aspects

More information

Internal Audit at the University of Cambridge.

Internal Audit at the University of Cambridge. Internal Audit at the University of Cambridge. Contents Introduction to Deloitte 1 Our team 2 What is Internal Audit? 4 Our approach to Internal Audit 5 Authority and reporting lines 7 Planning 8 Ad Hoc

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information

Dacorum Borough Council Final Internal Audit Report. IT Business Continuity and Disaster Recovery

Dacorum Borough Council Final Internal Audit Report. IT Business Continuity and Disaster Recovery Dacorum Borough Council Final Internal Audit Report IT Business Continuity and Disaster Recovery Distribution list: Chris Gordon Group Manager Performance, Policy and Projects John Worts ICT Team Leader

More information

Housing Related Support Contract Management Framework 2009/10

Housing Related Support Contract Management Framework 2009/10 Housing Related Support Contract Management Framework 2009/10 0 If you would like this information in large print, audio tape or in any other format or language please contact the public information officer

More information

CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT

CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT 1 Scope of Internal Audit 1.1 Terms of Reference 1.1.1 Do terms of reference: (a) establish the responsibilities and objectives

More information

Date: 7 February 2013

Date: 7 February 2013 Item No. Report title: Classification: Open Ward(s) or groups affected: From: Date: 7 February 2013 Meeting Name: Deputy Leader and Cabinet Member for Housing Management GW2: Leasehold and Ancillary Properties

More information

Appendix C Accountant in Bankruptcy. Annual report on the 2013/14 audit

Appendix C Accountant in Bankruptcy. Annual report on the 2013/14 audit Appendix C Accountant in Bankruptcy Annual report on the 2013/14 audit Prepared for Accountant in Bankruptcy and the Auditor General for Scotland 6 August 2014 Audit Scotland is a statutory body set up

More information

Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development)

Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development) Meeting: Cabinet Date: 6 October 2005 Subject: Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development) Contact Officer: Portfolio Holder: Key

More information

Capital Projects. Providing assurance over effective delivery of projects

Capital Projects. Providing assurance over effective delivery of projects Capital Projects Providing assurance over effective delivery of projects Governance and oversight Project Scope and change Reporting and communication Project risk and success factors Delivery Major projects

More information

Auditing data protection a guide to ICO data protection audits

Auditing data protection a guide to ICO data protection audits Auditing data protection a guide to ICO data protection audits Contents Executive summary 3 1. Audit programme development 5 Audit planning and risk assessment 2. Audit approach 6 Gathering evidence Audit

More information

Councillor David Chambers Date of Decision/Referral to O & S REPORT OF: STRATEGIC DIRECTOR (CORPORATE) SDC/08/37

Councillor David Chambers Date of Decision/Referral to O & S REPORT OF: STRATEGIC DIRECTOR (CORPORATE) SDC/08/37 REPORT TO INDIVIDUAL CABINET MEMBER FOR FINANCE, LEGAL AND ICT 20 MAY 2008 Key Decision YES Forward Plan Ref No Corporate Priority ALL Cabinet Portfolio Holder : Councillor David Chambers Date of Decision/Referral

More information

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr

More information

ICT Digital Transformation Programme

ICT Digital Transformation Programme Officer and Date Item Cabinet 11 th May 2016 Public ICT Digital Transformation Programme Responsible Officer: Clive Wright, Chief Executive Email: Clive.wright@shropshire.gov.uk Tel: 01743 252007 1.0 Summary

More information

Internal Audit Annual Report 2011/12

Internal Audit Annual Report 2011/12 1 Introduction 1.1 In accordance with the Code of Practice for Internal Audit in Local Government in the United Kingdom, the Internal Audit Annual Report 2011/12 for Cheshire East contains the following:

More information

Disability Employment Services Quality Framework Advice V 2.0

Disability Employment Services Quality Framework Advice V 2.0 Disability Employment Services Quality Framework Advice V 2.0 Disclaimer This document is not a stand-alone document and does not contain the entirety of Disability Employment Services Providers' obligations.

More information

LSE Internal Audit procedures (to be read in conjunction with the attached flowchart)

LSE Internal Audit procedures (to be read in conjunction with the attached flowchart) LSE Internal Audit procedures (to be read in conjunction with the attached flowchart) Audit activity is governed by the HEFCE Code of Audit Practice. 1. Determining audit activity a) Audits will be conducted

More information

PROCUREMENT & LOGISTICS DEPARTMENT

PROCUREMENT & LOGISTICS DEPARTMENT PROCUREMENT & LOGISTICS DEPARTMENT Tender/OJEU Procedure Overview This procedure applies to all purchases over 50,000 not covered by existing contracts and should be followed in conjunction with the Tender/OJEU

More information

Lead Provider Framework Draft Scope. NHS England / 13/12/13 Gateway Ref: 00897

Lead Provider Framework Draft Scope. NHS England / 13/12/13 Gateway Ref: 00897 Lead Provider Framework Draft Scope NHS England / 13/12/13 Gateway Ref: 00897 1 Introduction The commissioning support lead provider framework is being developed in response to requests from CCGs for a

More information

Outsourcing. Knowledge Summary

Outsourcing. Knowledge Summary Knowledge Summary Outsourcing P&SM professionals should have the knowledge and skills required to manage the outsourcing process and to advise colleagues of the most appropriate solution to obtain best

More information

Service Delivery Plan 2007/8 Template 1. Delivery plan

Service Delivery Plan 2007/8 Template 1. Delivery plan Delivery plan Theme Leisure & Environment Clean and safe streets and public places with the Council maintaining and enforcing high standards of cleanliness throughout the borough. 1. Deliver a proactive

More information

Becoming Tender Ready

Becoming Tender Ready Becoming Tender Ready Difference Between Procurement & Tendering Procurement is the process of acquiring goods, works and services, covering both acquisition from third parties and from in-house providers.

More information

SOUTH NORTHAMPTONSHIRE COUNCIL. 11/31 ICT Capacity Management FINAL REPORT. June 2011

SOUTH NORTHAMPTONSHIRE COUNCIL. 11/31 ICT Capacity Management FINAL REPORT. June 2011 SOUTH NORTHAMPTONSHIRE COUNCIL 11/31 ICT Capacity Management FINAL REPORT June 2011 This report and the work connected therewith are subject to the Terms and Conditions of the contract dated 18/06/07,

More information

IT REVIEW OF THE DISASTER RECOVERY ARRANGEMENTS

IT REVIEW OF THE DISASTER RECOVERY ARRANGEMENTS NOTTINGHAM CITY HOMES IT REVIEW OF THE DISASTER RECOVERY ARRANGEMENTS Report issued: February 2011 Audit Plan: The matters raised in this report are only those that came to the attention of the auditor

More information

OUTSOURCING. The Original Agreement provided for an optional 3-year extension to the original 10-year term.

OUTSOURCING. The Original Agreement provided for an optional 3-year extension to the original 10-year term. Filed: -- EB--0 Exhibit C Tab Page of OUTSOURCING.0 BACKGROUND Hydro One Networks Inc. ( Networks ) entered into a -year master services agreement with Inergi LP ( Inergi ) on December, 0 for services

More information

Project Athena Phase 1 Human Resources and Payroll

Project Athena Phase 1 Human Resources and Payroll Executive 14 November 2011 Report from the Director of Finance and Corporate Services Project Athena Phase 1 Human Resources and Payroll Wards Affected: [ALL] 1.0 Summary 1.1 This report concerns the transfer

More information

Employers Liability Registers

Employers Liability Registers Employers Liability Registers Working in partnership with you to perform an independent audit to meet the FSA s requirements on What are the FSA employers liability requirements? The FSA published updated

More information

General Dental Council Website Review: Dental Professionals Survey Invitation to Tender

General Dental Council Website Review: Dental Professionals Survey Invitation to Tender General Dental Council Website Review: Dental Professionals Survey Invitation to Tender Summary 1. The General Dental Council (GDC) invites tender proposals for a research project on the usability of the

More information

ESSEX FIRE AUTHORITY. Internal Audit Progress Report. Audit Sub-Committee Meeting: April 2012

ESSEX FIRE AUTHORITY. Internal Audit Progress Report. Audit Sub-Committee Meeting: April 2012 ESSEX FIRE AUTHORITY Internal Audit Progress Report Audit Sub-Committee Meeting: April Essex Fire Authority CONTENTS Section Page 1 Introduction 1 2 Final reports 1 3 Key Findings from Internal Audit Work

More information

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice Department of Health PFU & PPP Forum Benchmarking and market testing in NHS PFI projects Code of Best Practice This Code of Best Practice provides guidance and advice on good practice to NHS Trusts, Project

More information

Project Management Framework

Project Management Framework Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project

More information

Tender Evaluation and Contract Award

Tender Evaluation and Contract Award Brief 9 January 2011 Public Procurement Tender Evaluation and Contract Award C O N T E N T S Key principles governing the process of evaluation of tenders How does an evaluation panel operate? How does

More information

the role of the head of internal audit in public service organisations 2010

the role of the head of internal audit in public service organisations 2010 the role of the head of internal audit in public service organisations 2010 CIPFA Statement on the role of the Head of Internal Audit in public service organisations The Head of Internal Audit in a public

More information

The Learning Zone - Project Management Arrangements

The Learning Zone - Project Management Arrangements Coleg Gwent Internal Audit Report () 6 June 2012 Overall Opinion The Learning Zone - Project Management Arrangements CONTENTS Section Page Executive Summary 1 Action Plan 4 Findings and Recommendations

More information

Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006

Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006 TUPE Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006... 1 Service Provision Changes... 1 Employer Liability Information... 2 Liability for Failure to Inform and Consult

More information

Business Planning & Budgetary Control 2012/13

Business Planning & Budgetary Control 2012/13 Cymdeithas Tai Cantref Cyf Final Internal Audit Report Business Planning & Budgetary Control 2012/13 Date of fieldwork: October November 2012 Date of draft report: November 2012 Date of final report: November

More information

ESSEX FIRE AUTHORITY Essex County Fire & Rescue Service

ESSEX FIRE AUTHORITY Essex County Fire & Rescue Service ESSEX FIRE AUTHORITY Essex County Fire & Rescue Service MEETING Policy & Strategy Committee AGENDA ITEM 7 MEETING DATE 25 March 2009 REPORT NUMBER SUBJECT REPORT BY Monitoring IT Transformation Progress

More information

LESSONS LEARNED REPORT

LESSONS LEARNED REPORT Demystifying Quality in a Project Environment Best Practice User Group Workshop LESSONS LEARNED REPORT Purpose This document summarises the results of a workshop looking at Quality in a Project Environment,

More information

Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary

Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary Office of the Police and Crime Commissioner for Avon and Somerset and Avon and Somerset Constabulary Internal Audit Report () FINAL Risk Management: Follow Up of Previous Internal Audit Recommendations

More information

To be used in conjunction with the Invitation to Tender for Consultancy template.

To be used in conjunction with the Invitation to Tender for Consultancy template. GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small

More information

Informing the audit risk assessment for West Midlands Integrated Transport Authority Pension Fund

Informing the audit risk assessment for West Midlands Integrated Transport Authority Pension Fund Informing the audit risk assessment for West Midlands Integrated Transport Authority Pension Fund Year ended 31 March 2015 February 2015 John Gregory Engagements Lead T 07880 456 107 E john.gregory@uk.gt.com

More information

CABINET. 24 March 2015

CABINET. 24 March 2015 CABINET 24 March 2015 Title: Procurement of Electricity and Gas Supplies Report of the Cabinet Member for Finance Open Report with Exempt Appendix 4 Wards Affected: All Report Author: Andrew Sivess Group

More information

Internal Audit Strategic and Annual Plans 2015/16

Internal Audit Strategic and Annual Plans 2015/16 Internal Audit Strategic and Annual Plans 2015/16 Financial Scrutiny and Audit Committee 10 February 2015 Agenda Item No 8 Summary: This report provides an overview of the stages followed prior to the

More information

Appendix A Scoring for all Corporate and Project Risks Matrix

Appendix A Scoring for all Corporate and Project Risks Matrix Appendix A Scoring for all and Project s Matrix / Moderate (1) Significant (2) Serious (3) Critical (4) Certain/High (4) Tolerable (4) Moderate (8) Substantial (12) Intolerable (16) Very Likely (3) Tolerable

More information

ABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee

ABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee ABERDEEN CITY COUNCIL Name of Committee : Resources Management Committee Date of Meeting : 29 March 2007 Title of Report : CRM System Procurement Lead Officer : Jacek Nowak, Head of Customer Relations

More information

Aberdeen City Council IT Security (Network and perimeter)

Aberdeen City Council IT Security (Network and perimeter) Aberdeen City Council IT Security (Network and perimeter) Internal Audit Report 2014/2015 for Aberdeen City Council August 2014 Internal Audit KPIs Target Dates Actual Dates Red/Amber/Green Commentary

More information

Financial Operating Procedure: Budget Monitoring

Financial Operating Procedure: Budget Monitoring Financial Operating Procedure: Budget Monitoring Original Created: Jan 2010 Last Updated: Jan 2010 1 Index 1 Scope of Procedure...3 2 Aim of Procedure...3 3 Roles & Responsibilities...3 Appendix A Timetable...7

More information

DRAFT V5. PFSC 16/05/2014 Appendix 1. Outline Plan to deliver the County Council s investment property Strategy

DRAFT V5. PFSC 16/05/2014 Appendix 1. Outline Plan to deliver the County Council s investment property Strategy PFSC 16/05/2014 Appendix 1 Outline Plan to deliver the County Council s investment property Strategy 1. Strategic Drivers 1.1 The County Council s property investment strategy sets out how its property

More information

Vale of Glamorgan. Overview Report: Review of HR and Workforce Planning. November 2011

Vale of Glamorgan. Overview Report: Review of HR and Workforce Planning. November 2011 Vale of Glamorgan Overview Report: Review of HR and Workforce Planning November 2011 Content 1 Introduction 1 2. Review Findings 3 3. The Way Forward 17 2012 Grant Thornton UK LLP. All rights reserved.

More information

Audit Committee, 20 March 2014. Internal Audit Report Partners Expenses. Executive summary and recommendations. Introduction

Audit Committee, 20 March 2014. Internal Audit Report Partners Expenses. Executive summary and recommendations. Introduction Audit Committee, 20 Internal Audit Report Partners Expenses Executive summary and recommendations Introduction Mazars have undertaken a review of the HCPC s controls and processes for ensuring partners

More information

The Annual Audit Letter for West Mercia Police and Crime Commissioner and Chief Constable

The Annual Audit Letter for West Mercia Police and Crime Commissioner and Chief Constable The Annual Audit Letter for West Mercia Police and Crime Commissioner and Chief Constable Year ended 31 March 2015 October 2015 John Gregory Director and Engagement Lead T +44 (0)121 232 5333 E john.gregory@uk.gt.com

More information

South Liverpool Homes. Invitation to Tender. Mobile Phone Contract

South Liverpool Homes. Invitation to Tender. Mobile Phone Contract South Liverpool Homes Invitation to Tender Mobile Phone Contract Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4

More information

SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012

SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012 SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012 INTERNAL AUDIT PLAN Report of the: Director of Finance Contact: John Turnbull or Gillian McTaggart Urgent Decision?(yes/no) No If yes, reason urgent decision required:

More information

Note the Chief Internal Auditor s findings to date and gain assurance from Officers that key issues raised are being addressed.

Note the Chief Internal Auditor s findings to date and gain assurance from Officers that key issues raised are being addressed. Agenda Item No: 9 To: Joint Audit Committee Date: 24 September 2014 By: Chief Internal Auditor Title: Internal Audit Update Report 2014-15 Purpose of Report: The purpose of this report is to give an opinion

More information

Governing Body Organisational Development Programme 2015/16

Governing Body Organisational Development Programme 2015/16 Governing Body Organisational Development Programme 2015/16 Governing Body meeting 5 February 2015 C Author(s) Julie Glossop, Senior Commissioning Manager Sponsor Idris Griffiths, Chief Operating Officer

More information

Avon & Somerset Police Authority

Avon & Somerset Police Authority Avon & Somerset Police Authority Internal Audit Report IT Service Desk FINAL REPORT Report Version: Date: Draft to Management: 19 February 2010 Management Response: 12 May 2010 Final: 13 May 2010 Distribution:

More information

Finance Effectiveness Efficiency

Finance Effectiveness Efficiency Business Unit Finance Effectiveness Efficiency An overview Agenda Page 1 Efficiency - An overview 1 2 Our services 7 3 Case study 14 Section 1 Efficiency - An overview 1 Section 1 Efficiency - An overview

More information

Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS

Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS Table of Contents Contents INTRODUCTION... 2 1. DEFINING MANAGEMENT CONSULTANCY... 2 2. KEY SUCCESS FACTORS... 3 3. THE PROJECT APPROACH

More information

LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY

LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY PacificTA LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY COOK ISLANDS MINISTRY OF INFRASTRUCTURE AND PLANNING NOVEMBER 2013 This report has been prepared for the Ministry of Infrastructure

More information

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010 Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010 This report has been prepared on the basis of the limitations set out on page 16. Contents Page

More information

MONTHLY PROJECT PROGRESS REPORT

MONTHLY PROJECT PROGRESS REPORT MONTHLY PROJECT PROGRESS REPORT Project name: Project description: UCL School of Pharmacy Merger - IT & Data Programme A Programme to ensure all IT & Data elements of the UCL SoP Merger are co-ordinated

More information

Perth & Kinross Council. Risk Assessment, Annual Audit Plan and Fee Proposal for 2007/08. External Audit Report No: 2008/01

Perth & Kinross Council. Risk Assessment, Annual Audit Plan and Fee Proposal for 2007/08. External Audit Report No: 2008/01 Perth & Kinross Council Risk Assessment, Annual Audit Plan and Fee Proposal for 2007/08 External Audit Report No: 2008/01 Draft Issued: 11 February 2008 Final Issued: 29 February 2008 Contents Page Page

More information

Oxford City Council Managing Capital Projects

Oxford City Council Managing Capital Projects www.pwc.co.uk Internal Audit Report 2014/2015 August 2015 Oxford City Council Managing Capital Projects Table of Contents 1. Executive Summary... 3 2. Background and scope... 5 3. Detailed findings...

More information

Statement of responsibilities of auditors and audited bodies: Local authorities, NHS bodies and small authorities.

Statement of responsibilities of auditors and audited bodies: Local authorities, NHS bodies and small authorities. Statement of responsibilities of auditors and audited bodies: Local authorities, NHS bodies and small authorities. 1. This statement serves as the formal terms of engagement between appointed auditors

More information

Growth by acquisition.

Growth by acquisition. Forward thinking Growth by acquisition. A practical guide for owner-managed businesses Acquisitions can be an excellent means of enhancing shareholder value in a privately owned business. However, selecting

More information

WHAT IS PRINCE2? Benefits There are many benefits of using PRINCE2 but primarily it:

WHAT IS PRINCE2? Benefits There are many benefits of using PRINCE2 but primarily it: WHAT IS PRINCE2? Introduction PRINCE2 (Projects in a Controlled Environment) is a structured project management method that can be applied regardless of project scale, type, organisation, geography or

More information

CONSTITUTION PART 4 CONTRACT PROCEDURE RULES

CONSTITUTION PART 4 CONTRACT PROCEDURE RULES CONSTITUTION PART 4 CONTRACT PROCEDURE RULES (last revised January 2016) A Brief Guide to the Contract Procedure Rules These Contract Procedure Rules promote good purchasing practice, public accountability

More information

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT ACCOUNTABLE SIGNATURE AUTHORISED for implementation SIGNATURE On behalf of Chief Executive

More information

Safety Management Systems (SMS) guidance for organisations

Safety Management Systems (SMS) guidance for organisations Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

Tendering Policies and Procedures

Tendering Policies and Procedures Tendering Policies and Procedures Tendering Policies and Procedures Content Pg. Mission Statement..3 Introduction....4 Background to the EPS (formerly Shannon Consortium Procurement Network) 4 The Key

More information

Aberdeen City Council. Performance Management Process. External Audit Report o: 2008/19

Aberdeen City Council. Performance Management Process. External Audit Report o: 2008/19 Aberdeen City Council Performance Management Process External Audit Report o: 2008/19 Draft Issued: 11 February 2009 Final Issued: 6 April 2009 Contents Pages Pages Management Summary Introduction 1 Background

More information

JOB DESCRIPTION. 1. JOB TITLE: Assistant Procurement Officer. 4. DEPARTMENT: Chief Financial Officer/Bursar s Office

JOB DESCRIPTION. 1. JOB TITLE: Assistant Procurement Officer. 4. DEPARTMENT: Chief Financial Officer/Bursar s Office JOB DESCRIPTION 1. JOB TITLE: Assistant Procurement Officer 2. REFERENCE NUMBER: HR13297a 3. ROLE CODE: APOBO 4. DEPARTMENT: Chief Financial Officer/Bursar s Office 5. ORGANISATION CHART: Chief Financial

More information

Non Housing Capital Programme. PROJECT Outline Business Case

Non Housing Capital Programme. PROJECT Outline Business Case Non Housing Capital Programme PROJECT Outline Business Case Originating Service: Continuous Improvement. 1. Part A: Basic Proposal Details A.1 Description of proposal: (Please include details of any premises

More information

2.0 RECOMMENDATIONS Members of the Committee are asked to note the information contained within this report.

2.0 RECOMMENDATIONS Members of the Committee are asked to note the information contained within this report. REPORT TO: SCRUTINY COMMITTEE 25 JUNE 2013 REPORT ON: REPORT BY: INTERNAL AUDIT REPORTS CHIEF INTERNAL AUDITOR REPORT NO: 280-2013 1.0 PURPOSE OF REPORT To submit to Members of the Scrutiny Committee a

More information

1.1 This report updates Members on progress with asset management.

1.1 This report updates Members on progress with asset management. Lake District National Park Authority Agenda Item: Authority: 3 October 0 Page: ASSET MANAGEMENT UPDATE OCTOBER 0 SUMMARY. This report updates Members on progress with asset management. Recommendation

More information

The Scottish Wide Area Network Programme

The Scottish Wide Area Network Programme The Scottish Wide Area Network Release: Issued Version: 1.0 Date: 16/03/2015 Author: Andy Williamson Manager Owner: Anne Moises SRO Client: Board Version: Issued 1.0 Page 1 of 8 16/04/2015 Document Location

More information

Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit

Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit Page 1 Walton Centre Monitoring & Audit Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt Page 2 Table of Contents Section Contents 1 Introduction 2 Responsibilities Within This

More information

West Highland College. Internal Audit 2014/15 Annual Report August 2015

West Highland College. Internal Audit 2014/15 Annual Report August 2015 Internal Audit 2014/15 Annual Report August 2015 TABLE OF CONTENTS Section Page 1. Introduction 3 2. Executive Summary 4 5 3. Audit Findings 6 11 4. Benchmarking 12 5. Key Performance Indicators 13 Appendices

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

The University s responsibilities and its arrangements for internal audit Internal audit protocol 2014/15 to 2016/17

The University s responsibilities and its arrangements for internal audit Internal audit protocol 2014/15 to 2016/17 The University s responsibilities and its arrangements for internal audit Internal audit protocol 2014/15 to 2016/17 Summary This paper sets out the University s current obligations and arrangements for

More information

GUIDELINE ON THE APPLICATION OF THE OUTSOURCING REQUIREMENTS UNDER THE FSA RULES IMPLEMENTING MIFID AND THE CRD IN THE UK

GUIDELINE ON THE APPLICATION OF THE OUTSOURCING REQUIREMENTS UNDER THE FSA RULES IMPLEMENTING MIFID AND THE CRD IN THE UK GUIDELINE ON THE APPLICATION OF THE OUTSOURCING REQUIREMENTS UNDER THE FSA RULES IMPLEMENTING MIFID AND THE CRD IN THE UK This Guideline does not purport to be a definitive guide, but is instead a non-exhaustive

More information