1 Questions and Answers RFP NUMBER: RAF/2014/00020 DESCRIPTION: APPOINTMENT OF SERVICE PROVIDERS TO PROVIDE AN ENTERPRISE PROJECT PORTFOLIO MANAGEMENT (EPPM) SOLUTION PUBLISH DATE: 04 July 2014 VALIDIY PERIOD: 90 Days from the closing date CLOSING DATE: 29 July 2014 CLOSING TIME: COMPULSORY BRIEFING SESSION 11:00 AM THE CLOSING TIME WILL BE AS PER THE CLOCK AT THE RAF RECEPTION Date: 15 July 2014 Time: 11h00 to 12h00 Venue: Road Accident Fund 2 Eco Glades Office Park 420 Witch-Hazel Avenue Centurion BID RESPONSES MUST BE HAND DELIVERED / COURIERED TO: Road Accident Fund (RAF) Head Office Eco Glades Office Park, 420 Witch-Hazel Avenue CENTURION (at the reception) ATTENTION: Steve van Huyssteen NB: Bidders must ensure that they sign the register at the reception when delivering their bids BIDDER NAME:
2 QUESTIONS AND ANSWERS QUESTION 1. Referring to pg. 72 par 4.1: The bidder offering the EPPM Solution must: Supply, install, configure, customize and license the EPPM Solution for the RAF. Does RAF have an Enterprise Agreement with Microsoft? Yes, licensing must be done through RAF EA. QUESTION 2. Referring to pg. 72 par 4.1: The bidder offering the EPPM Solution must: Supply, install, configure, customize and license the EPPM Solution for the RAF. If so, should we include Microsoft Licensing costs of our proposed solution? Licensing costs should still be included yes. Additional licensing requirements will have to be added to our EA and costed accordingly. QUESTION 3. Referring to pg. 72 par 3.2: The following are attributes of the required solution: An EPPM solution that is able to seamlessly integrate with the existing database, with SharePoint and MS Projects. What version of SharePoint and MS Project does RAF make use of? SharePoint 2010, and Project 2010 QUESTION 4. Referring to pg. 72 par 3.2: The following are attributes of the required solution: An EPPM solution that is able to seamlessly integrate with the existing database, with SharePoint and MS Projects. What existing database is RAF referring to please provide details of this database and functionality? There is no database besides the cost center data in SAP and project documentation on SharePoint.
3 QUESTION 5. Referring to pg. 72 par 3.2: The following are attributes of the required solution: An EPPM solution that is able to seamlessly integrate with the existing database, with SharePoint and MS Projects. If the existing version of SharePoint is not SharePoint 2013 Enterprise will it be acceptable for the solution to be installed on a separate SharePoint 2013 farm? ANSWER Yes, this will have to be licensed and separately costed. (Including hardware requirements and costs) QUESTION 6. Are all the SAP ERP systems hosted in Midrand? No, plans are in place to move entire SAP environment to Midrand but only GRC and BI hosted in Midrand. ECC, FM, HCM still in Menlyn. QUESTION 7. Can we make the assumption that all required hardware and software licenses are outside of the scope of this proposal and will be provided by RAF? This is in line with the point of integrating to the current environment; my assumption is that RAF already has the relevant licenses and hardware? No, licenses and hardware need to be accounted for in the proposed cost of the solution. If the solution requires storage, hardware or licensing (additional to what RAF currently has in place), this needs to be considered as within scope of this proposal. QUESTION 8. Please confirm if RAF has a Microsoft Enterprise Agreement that covers the following licenses: a. Project Server 2013 b. SharePoint Server Enterprise 2013 c. Project Web App (PWA) Client Access Licenses (CAL s) d. SharePoint CAL s e. Who is the service provider for Microsoft Licenses for RAF?
4 a. Yes b. Yes c. No d. Yes e. External service provider (not Microsoft) Please note that we do have an existing EA, however the cost of additional licenses will form part of the costing for this solution, provision has not been made for this. QUESTION 9. Kindly confirm the version of the following: a. Microsoft Project 2010 or 2013 b. SharePoint 2010 or 2013 c. Microsoft Project Server 2010 or 2013? a. Project b. SharePoint 2010 c. We are not running project server QUESTION 10. Can RAF IT provide a topology of the current environment (Development, Staging, UAT, Production) in which the EPPM needs to be integrated to? a. The above will assist with licensing and sizing of the architecture. For the SAP environment, Dev., QA and prod is in place. QUESTION 11. Hardware Requirements: a. If a topology/current architecture diagram be made available then this will assist with the sizing, pricing of licensing and overall bid price. Architecture diagrams can only be shared once a contract has been entered into, this information cannot be shared outside of a contractual agreement.
5 QUESTION 12. Would notification and alerts and reminders be a requirement as this would entail integration to Exchange? a. What version of Microsoft Exchange Server does RAF utilize? Yes, exchange QUESTION 13. Environmental and Project Office a. Does RAF have an established project office? b. What is the structure of this project office if it exists? c. How many active projects? d. How many Project Managers, Administrators and Team members within this Project Office? e. How many people will need access to the EPPM Solution? The bid document mentioned 30 at first. Of this 30 please indicate number for each specific role: i.) Project Managers ii.) Team members iii.) Administrators iv.) Executives The above number provided will impact the training prices. f. What is the level of skill of the project managers, administrators and team members? i.) Can it be assumed that project managers, administrators and team members, have project management skills relevant to their roles or should this be included in the training? a. Yes b. This information will be provided to the successful bidder. c. This varies. d. At present we have 22 staff members. e. Project Managers: 8 Business Analysts: 6 Coordinators: 4 Executives: All Regional Managers: 5 f. Project Management Skills is not part of the Specification.
6 QUESTION 14. It was mentioned in the briefing that the project should be completed 3 months after awarding/signing the bid to the service provider. What if there are delays from RAF IT with regard to Procurement of hardware and software licenses or any delays from RAF that would impact the schedule? Is the service provider allowed to add penalty clauses for such delays incurred by the bidder/client? Delays by RAF IT emanating from requests that has been submitted in writing and providing reasonable timeframes to submit required information cannot be attributed to the successful service provider. However, I believe these concerns can be addressed via the Contracting process. QUESTION 15. There are other components which extend past the 3 month duration. We see these as: a. Support and Maintenance and b. Ongoing customization Are there any others that we need to take into consideration? ANSWERS: None other than what was specified in the Specification published. QUESTION 16. If the response must be in the format as published how do bidders deal with instances where the space provided for a response is too small? Bidders should print the bid document as provided on the website to preserve page numbering, i.e. do not modify the document as evaluators will expect to find certain information on particular pages. Where there is insufficient space and an additional page must be inserted or where attachments are required these should be placed at the relevant point in the document as additional pages. If attachments are placed in different sections please note where the information may be found at the relevant point in the bid document. QUESTION 17. The document refers to two sets of people to be trained: Skills transfer (on-the-job training) of 15 nominated RAF staff members that will provide first and second line support for a period of three (3) years before go live User training (train-the-trainer) of 30 nominated RAF staff members including provision of training materials for RAF staff to undertake User training before the system go live. What is the actual user base?
7 The user base is the 30 users in the second item. The 15 staff in the first item is IT support staff. QUESTION 18. Does the three-month implementation window include migration of data or will the solution be applied afresh? Data is currently a relatively small amount, held in MS SharePoint, so there should be no difficulty in migrating it within this window. QUESTION 19. Please give further information regarding the functionality required by the Project Management Office (PMO), such as an approved document. What metrics are required by RAF? Is there documentation on the requirements? There is a Board approved document (Framework) that will be made available to the successful bidder. This is a confidential document and cannot be shared during bidding. An approved framework exists, which documents how reporting is done to EXCO. The RAF will consider whether any further information may be made available to bidders. QUESTION 20. The specification calls for SAP integration. For what purpose? What is required? Is this also related to resourcing of projects? The RAF holds financial and HR information in SAP, which must be integrated. QUESTION 21. The specification calls for SAP integration. For what purpose? What is required? Is this also related to resourcing of projects? The RAF holds financial and HR information in SAP, which must be integrated. QUESTION 22. Must cost/time information developed in the solution be pushed back to SAP? RAF would expect this information to be pulled and pushed back, i.e. to perform reconciliations.
8 QUESTION 23. Does the specification assume the future continued use of MS Project and MS SharePoint? Is a MS solution predetermined? Bidders should not assume that RAF will continue in the MS Project / MS SharePoint environment. This is not predetermined. The solution would, however, need to be MS compatible. QUESTION 24. Regarding the 30 system users identified for training, will the solution be rolled out further? What is the location of users? No. The 30 is the total users. These are located at Head Office (Centurion) where the core of users is located, but also at satellite offices throughout South Africa (regional offices and customer service centers). QUESTION 25. Is a multi-platform or a desktop solution required? RAF would prefer a multiplatform solution as the use of tablets is the trend for the PMO staff. QUESTION 26. What is the number of projects being undertaken? RAF is not able to answer this currently. There are a number of projects ranging from values of R100k to several million Rand; some are limited in scope while others are transversal across many departments/regions. QUESTION 27. What auto dashboard reporting is required? There is no information currently available on the requirement. Bidders should frame what is possible and indicate how customization may be allowed. QUESTION 28. If a bidder can provide more than one solution, how should multiple offers be made?
9 Bidders should provide a single submission that outlines the options available. QUESTION 29. Must the solution integrate to MS and SAP? Yes. QUESTION 30. Regarding governance, must this be automated? Is this in reference to governance or compliance? Is this at a macro or micro level? RAF requires an audit trail and workflows. QUESTION 31. Must the solution be able to handle sub-contractor management? Sub-contracting is not usual in this environment however, this functionality will be utilized in certain instances. QUESTION 32. The specification requires customization on an as-and-when-required basis over a period of three years. What is the extent of customization? Bidders should make provision for possible large changes. QUESTION 33. Would RAF consider a Software as a Service model or is the solution to be implemented at RAF datacenters? The solution must be implemented at the RAF datacenter. QUESTION 34. Is the three months implementation window for implementation only or must integration also be undertaken in this three months?
10 Full implementation and integration must be undertaken in three months. QUESTION 35. The response must be in a PDF format but the solution description might be a lot bigger. Can we attach an addendum for that? If you need to attach additional information just attach where it make sense in the document. If files are used just add separates where you can indicate where the contents can be found.where we ask for the substantiation in the technical criteria a place where we say substantiate just annotate there where it can be found in the proposal. QUESTION 36. With regards to the implementation window, do you see that part of that is to migrate all your information from the existing the systems that you use within the new solution as well or will you start out afresh with the new system? The sum total that we use at present is MS Projects in terms of our project scheduling and SharePoint where we currently save or store our documents. In terms of the transfer of data yes the database is not that big. QUESTION 37. Regarding the functionality application methodology etc. that is being used within the PMO, is it available for bidders? RAF does have a Board approved PMO framework which details our processes in terms of the different sizes of projects and we do change request that would be available to the successful bidder. QUESTION 38. What will be your single source of truth by extracting data from SAP financial data into your EPPM solution? Are you looking at then capturing cost time in that solution and then pushing it back into SAP the actual cost or to have SAP as your single source of truth and reflecting the data only in the EPPM solution? Both ways because your budgets sits in SAP but the actual cost is captured somewhere else then we need to do a reconciliation to be able to understand where we at. QUESTION 39. And the recon will it be in the EPPM and then push up?
11 Yes.
11:00 a.m. The closing time will be as per the clock at the RAF reception
RFB NUMBER: RAF/2015/00019 DESCRIPTION: Request for Information: ICT Security Solutions PUBLISH DATE: 18 September 2015 VALIDIY PERIOD: 120 days from the closing date CLOSING DATE: 20 October 2015 CLOSING
More informationRequest for Information: Enterprise scanning and content management solutions, as well as architecture to suit RAF s current and future needs
RFB NUMBER: RAF/2014/00036 DESCRIPTION: Request for Information: Enterprise scanning and content management solutions, as well as architecture to suit RAF s current and future needs PUBLISH DATE: 16 January
More informationREQUEST FOR INFORMATION ON PERFORMANCE TEST TOOLS
RFI NUMBER: DESCRIPTION: RAF/2013/00047 REQUEST FOR INFORMATION ON PERFORMANCE TEST TOOLS PUBLISH DATE: 17 January 2014 VALIDIY PERIOD: 90 Days from the closing date CLOSING DATE: 07 February 2014 CLOSING
More information2.1. Service Providers who do not comply with the mandatory requirements will not be considered for further evaluation.
BID SPECIFICATION Infrastructure as a Service (IaaS) 1. BACKGROUND OF THE ROAD ACCIDENT FUND The Road Accident Fund (RAF) is a statutory body that, in terms of the provisions of the Road Accident Fund
More informationNew Jersey Transportation Authority (NJTA) Request For Proposal And Optional PeopleSoft Financial System
January 14, 2010 TO ALL PROPOSERS: RE: Request for Proposal New Jersey Turnpike Authority The Upgrade and Enhancement of the PeopleSoft Financial System And Optional PeopleSoft Financial System for South
More informationG-Cloud Service Definition Lotus Notes to Microsoft SharePoint Migration Discovery Service
G-Cloud Service Definition Lotus Notes to Microsoft SharePoint Migration Discovery Service Lotus Notes to Microsoft SharePoint Migration Discovery Service This service provides an opportunity to review
More informationREQUEST FOR INFORMATION
REQUEST FOR INFORMATION RFI Ref: VM2013-05-49 SIA Learning Management System (LMS) Page 1 of 13 TABLE OF CONTENTS SECTION 1: INTRODUCTION...3 SECTION 2: BACKGROUND...5 SECTION 3: SUMMARY OF RFI...7 SECTION
More informationRequest for Proposal. Contract Management Software
Request for Proposal Contract Management Software Ogden City Information Technology Division RETURN TO: Ogden City Purchasing Agent 2549 Washington Blvd., Suite 510 Ogden, Utah 84401 Attn: Sandy Poll 1
More informationXBRL-Based Reporting System, Data Warehouse and Business Intelligence Tools
XBRL-Based Reporting System, Data Warehouse and Business Intelligence Tools The Bank of Mauritius (Bank hereafter) held a pre-bid meeting on 9 October 2013 in respect of the invitation for bids for the
More informationResponses to Inquiries RFP 14-15 Software Quality Assurance Managed Services
Responses to Inquiries RFP 14-15 Software Quality Assurance Managed Services 1. Questions with specific reference to documentation in the RFP Question/ Clarification What else does the application environment
More informationREQUEST FOR PROPOSAL ENTERPRISE RESOURCE PLANNING (ERP) BID NUMBER: CLOSING DATE FOR SUBMISSION: TIME:
REQUEST FOR PROPOSAL ENTERPRISE RESOURCE PLANNING (ERP) BID NUMBER: CLOSING DATE FOR SUBMISSION: TIME: 1 Table of Contents 1 Introduction... 5 1.1 Background... 5 1.2 Purpose... 5 2 Scope of Services for
More informationSOLICITATION INFORMATION JANUARY 13, 2015 TITLE: INTEGRATED CIVIL DIVISION CASE MANAGEMENT SYSTEM
SOLICITATION INFORMATION JANUARY 13, 2015 RFP# 7549264 TITLE: INTEGRATED CIVIL DIVISION CASE MANAGEMENT SYSTEM SUBMISSION DEADLINE: FEBRUARY 11, 2015 AT 2:30 PM (ET) QUESTIONS CONCERNING THIS SOLICITATION
More informationChange Management Best Practices
General Change Management Best Practices Practice Area Best Practice Criteria Organization Change management policy, procedures, and standards are integrated with and communicated to IT and business management
More informationCITY OF FRISCO PURCHASING DIVISION
May 31, 2013 Addendum #1 Questions and Answers RFP #1306-059 Enterprise Discovery for Electronic Records Questions and Answers CITY OF FRISCO PURCHASING DIVISION 1. The RFP states to use either AC, FR,
More informationCloud & Datacenter Monitoring with System Center Operations Manager
Page 1 of 5 Overview This course equips students with the skills they require to deploy and configure System Center 2012 R2 Operations. Using hands-on labs, students learn the following: How to architect
More informationDocument Reference. Section Number. Question # Section Heading. The IV&V Contractor will provide. project management services to the III.B.4.
Addendum 1 s and Answers Independent Verification and Validation (IV&V) Services Bureau of Health Services Financing RFP 3000003817 Proposal Due Date/Time: January 6, 2016, 4:00 p.m. CT Heading in 1 RFP
More informationKMS Implementation Roadmap
KMS Implementation Roadmap Sample Excerpt Prepared by: The Knowledge Compass, Inc. TABLE OF CONTENTS 1. EXECUTIVE SUMMARY 5 1.1 Overview 5 1.2 Project Goals & Objectives 5 1.3 Implementation Approach 5
More informationImplementation of Enterprise Resource Planning Application RFP No. 2016-008 Questions & Answers April 28 th, 2016
1. Implementation of Enterprise Resource Planning Application RFP No. 2016-008 Questions & Answers April 28 th, 2016 Is COMPASS looking for replacement of SAP or integration/enhancement of current SAP
More informationEfficiently Automating MDM and Business Process through Winshuttle: The Moen and Rockwell Automation Stories
Efficiently Automating MDM and Business Process through Winshuttle: The Moen and Rockwell Automation Stories Presenter: Lance Yoder, Clear Process Solutions About the Presenter LANCE YODER Case Western
More informationRequest for Proposal Business & Financial Services Department
Request for Proposal Business & Financial Services Department CONTRACT 5118 P Enterprise Project Management Solution Design and Implementation 1. Introduction 1.1 The City of Richmond (the City ) proposes
More information1. PURPOSE 2. BACKGROUND. 2.1 Functionalities of the Current GCIS ECMS. BID SPECIFICATIONS FOR GCIS SHAREPOINT Page 1 of 9
BID SPECIFICATIONS Upgrade and Extend SharePoint as the GCIS Extranet, Enhance, Support and Maintenance of GCIS Enterprise Content Management System (ECMS) for a period of three (3) years Reference: GCIS
More informationClaims Management for the London Market
for the London Market is a complete lifecycle claims solution, driving efficiencies and speed of handling claims. It guides claims handlers through the complex process of dealing with the progress of a
More informatione-gateway SOLUTION OVERVIEW Financials HCM ERP e-gateway Web Applications Mobile Devices SharePoint Portal
e-gateway SOLUTION OVERVIEW In an effort to manage mission critical information better, perform their daily tasks more efficiently, share information to key stakeholders more effectively, and ensure that
More informationTechnology Consulting
Dallas Area Rapid Transit Authority Dallas, Texas EHIBIT H STATEMENT OF WORK Technology Consulting Purpose Dallas Area Rapid Transit (DART) is seeking a master service agreement with two qualified Contractors
More informationModule: Sharepoint Administrator
Module: Sharepoint Administrator Mode: Classroom Duration: 40 hours This course teaches IT Professionals to design and deploy Microsoft SharePoint 2010. Course Outline: Module 1: Designing a Logical Architecture
More informationProsecutorial Case Management System Maintenance/Enhancement Support Services. Request for Proposal: RFP # 7549208
RFP # 7549208 Solicitation Information December 12, 2014 TITLE: Prosecutorial Case Management System Maintenance/Enhancement Support Services Submission Deadline: Wednesday, January 14, 2015 at 2:00 PM
More informationFMPA RFP 2015-205: Intranet Design Services Questions & Answers (December 7, 2015)
FMPA RFP 2015-205: Intranet Design Services Questions & Answers (December 7, 2015) 1. Question: Can companies from outside the USA can apply for this? Yes. 2. Question: Do we need to come there for meetings?
More informationboth the Employer and Contractor teams access and administer contracts in a common environment available 24hrs per day, 365 days per year
CEMAR is a simple to deploy, web-based solution to contract management and reporting with a minimum 99.5% availability. CEMAR achieves compliance through tailored workflow that: covers NEC3 ECC, TSC, PSC,
More informationRequest for Proposal for Project Server 2013, MS SharePoint 2013 Intranet Development and Mobile Application Development Services
Request for Proposal for Project Server 2013, MS SharePoint 2013 Intranet Development and Mobile Application Development Services Solicitation Number: DCRB-14-010 Questions 1. On page 4 of the RFP in the
More informationLaunch of Serena s SharePoint Workflow Solution
Launch of Serena s SharePoint Workflow Solution 1. Overview Serena controls roughly 20% of the market world wide in the Application Lifecycle Management (ALM) space, mainly at the top end of the market
More informationDESKTOP COMPUTER SKILLS
1 Desktop Computer Skills Price List DESKTOP COMPUTER SKILLS Microsoft Office 2010 Microsoft Office 2010: New Features Please note all prices exclude VAT Approx. Learning Hours: 3 Price: 45 Office 2010
More informationCounselorMax and ORS Managed Hosting RFP 15-NW-0016
CounselorMax and ORS Managed Hosting RFP 15-NW-0016 Posting Date 4/22/2015 Proposal submission deadline 5/15/2015, 5:00 PM ET Purpose of the RFP NeighborWorks America has a requirement for managed hosting
More informationCase Management powered by Microsoft Dynamics CRM
- From case capture to resolution powered by Microsoft Dynamics CRM CasePoint is a Solution that combines the best of the Microsoft Dynamics CRM with purpose-built functionality to deliver complete case
More informationKern Health System CORE Software Professional Services RFP Responses to Questions/Request for Explanation
Kern Health System CORE RFP Responses to Questions/Request for Explanation Kern Health Systems (KHS) has prepared the following responses to questions received regarding the CORE Request for Proposal (RFP).
More information10964C: Cloud & Datacenter Monitoring with System Center Operations Manager
10964C: Cloud & Datacenter Monitoring with System Center Course Details Course Code: Duration: Notes: 10964C 5 days Elements of this syllabus are subject to change. About this course This course equips
More informationDigital Signature Application
Department of Science and Technology Republic of South Africa Specification Digital Signature Application 1. INTRODUCTION The Department of Science and Technology (DST) has 100 employees in Pretoria and
More informationFor each requirement, the Bidder should indicate which level of support pertains to the requirement by entering 1, 2, or 3 in the appropriate box.
Annex Functional Requirements for: The integrated reconciliation system of Back-Office and Cash Accounts operations: Instructions: The Required or Desired column represents whether a feature is a business
More informationCan the RFP, or the sections of the RFP that you are requesting responses on, be provided in MS Word so that it is easier to formulate our response?
ADDENDUM NO. ONE February 9, 2015 This Addendum forms a part of the contract Documents and modifies the original RFP dated January 12, 2015. Acknowledge receipt of this Addendum on the Proposal Form. Failure
More informationState of Wisconsin Division of Enterprise Technology (DET) SharePoint 2010 Service Offering Definition (SOD)
State of Wisconsin Division of Enterprise Technology (DET) SharePoint 2010 Service Offering Definition (SOD) 1 Document Revision History Date Version Creator Notes 07/15/2011 1.0 Lisa Jorgensen Initial
More informationNintex Workflow 2013 & InfoPath Form Design workshop
Nintex Workflow 2013 & InfoPath Form Design workshop Duration: 30 Hrs. Course Outline: Module 1: Creating a SharePoint Form with InfoPath Designer Design a SharePoint Form Using the Blank Form Template
More informationHosted Contact Center RFQC 98000-0000001097 Questions and Answers
Hosted Contact Center Q&A s 1-4, Released 4/24/14 1. Appendix A I noticed that on the Appendix A there is only 5 pages and that pages 6 and 7 are not yet provided. Will they be updated soon? 2. Section
More informationMOC 10964C: Cloud and Datacenter Monitoring with System Center Operations Manager
MOC 10964C: Cloud and Datacenter Monitoring with System Center Operations Manager Course Overview This course provides students with the knowledge and skills to deploy and configure System Center 2012
More informationThe Secrets to Using MS Project Server Effectively
The Secrets to Using MS Project Server Effectively About the Presenter: David Mack 16+ years Microsoft Project experience Instructor and mentor to several Fortune 500 companies Federal deliveries to VA,
More information2011 NASCIO Nomination Business Improvement and Paperless Architecture Initiative. Improving State Operations: Kentucky
2011 NASCIO Nomination Business Improvement and Paperless Architecture Initiative Improving State Operations: Kentucky Kevin Moore 6/1/2011 Executive Summary: Accounts Payable was a time consuming, inefficient
More informationWebsite Maintenance Services RFP Questions & Answers
Website Maintenance Services RFP Questions & Answers Summary 8 companies submitted an Intent to Bid. 5 companies submitted questions. 109 questions were submitted. Questions & Answers 1. We plan to use
More informationImprove Project Team Collaboration Using Microsoft Project Online
Improve Project Team Collaboration Using Microsoft Project Online Presented by Steven Vowles, PMP, CISA, MCTS Senior Program Director, Infor Consulting Services Global PMO April 29, 2016 1 Discipline!
More informationDallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010
Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning
More informationState of Louisiana Division of Administration / Office of Technology Services
State of Louisiana Division of Administration / Office of Technology Services REQUEST FOR INFORMATION (RFI) RELATED TO ENTERPRISE DOCUMENT CAPTURE (EDC) July 1, 2015 This Request for Information (RFI)
More informationREQUEST FOR PROPOSAL (RFP) for Provide Document Imaging & Archiving Solution And Develop Application Process Workflow on MS SharePoint
REQUEST FOR PROPOSAL (RFP) for Provide Document Imaging & Archiving Solution And Develop Application Process Workflow on MS SharePoint May 2016 Housing Development Finance Corporation Plc. Information
More informationElectoral Commission. Auction # 10220790. Active Directory Management Software
Electoral Commission Auction # 10220790 Active Directory Management Software IMPORTANT NOTICE Failure to comply with the completion of the auction conditions and the required information (i.e. Make, model
More informationPhase Name 1 Initiation. 2 Requirements. 3 Design
No Phase Name 1 Initiation 2 Requirements 3 Design 4 Pre-Migration 5 Pre-Migrate 6 Pre-Migrate 7 Migrate 8 Migrate 9 Migrate 10 Migrate 11 Post-Migrate 12 Post-Migrate 13 Post-Migrate 14 Post-Migrate 15
More informationImplementing Project Server 2010
Implementing Project Server 2010 Course ISI-1327 4 Days Instructor-led, Hands-on Course Description This instructor-led course will provide you with the knowledge and skills to effectively install and
More informationSolicitation No. 8004853 - Oracle Enterprise Content Management System Services
DALLAS/FORT WORTH INTERNATIONAL AIRPORT July 17, 2013 CLARIFICATIONS Re: - Oracle Enterprise Content Management System Services Please be advised of the following clarifications to the above referenced
More informationMinnesota Department of Employment and Economic Development (DEED) Project: Web Application Security Assessment. DEED Answers to Vendor s Questions
Minnesota Department of Employment and Economic Development (DEED) Project: Web Application Security Assessment DEED Answers to Vendor s Questions Friday, 10 September 2010 1. Has data classification been
More informationREQUEST FOR PROPOSALS CUSTOMER SERVICE TRACKING SYSTEM THE CITY OF CHARLOTTETOWN CHARLOTTETOWN PEI PROPOSALS ARE TO BE SUBMITTED PRIOR TO
REQUEST FOR PROPOSALS CUSTOMER SERVICE TRACKING SYSTEM THE CITY OF CHARLOTTETOWN CHARLOTTETOWN PEI PROPOSALS ARE TO BE SUBMITTED PRIOR TO 12:00:00 NOON LOCAL TIME on FRIDAY DECEMBER 9th, 2011 TABLE OF
More informationCloud Services Catalog with Epsilon
Cloud Services Catalog with Epsilon Modern IT enterprises face several challenges while building a service catalog for their data center. Provisioning with a cloud management platform solves some of these
More informationCRM Request for Proposal. Rhode Island Economic Development Corporation. Request for Proposal for a CRM System. July 3, 2013
CRM Request for Proposal Rhode Island Economic Development Corporation Request for Proposal for a CRM System July 3, 2013 Page 1 of 10 Table of Contents 1 STATEMENT OF WORK... 3 1.1 PURPOSE... 3 1.2 COVERAGE
More informationTown of Needham Document Management Storage and Retrieval Solution RFP14NEE272G
Notice to All Prospective Bidder Deadline for written questions 4:00 p.m. Friday, May 9, 2014 ADDENDUM #2 RELEASED (WEDNESDAY, MAY 14, 2014) We are issuing this addendum to provide more information with
More informationSECTION C SCHEDULE A: PROJECT BRIEF PART 1: SCOPE OF SERVICES
Table of Contents Page C1/ 1 Statement of Work and Business Requirements... 2 1.1 Objective... 2 1.2 General Requirements... 2 1.3 Technical Requirements... 2 1.4 Services List... 4 1.5 Implementation
More informationRFP# 027-1516. ADDENDUM No. 1 Questions and Answers
SPECIAL ADMINISTRATIVE BOARD OF THE TRANSITIONAL SCHOOL DISTRICT OF THE CITY OF ST. LOUIS Purchasing Department 801 North 11th Street Saint Louis, Missouri 63101 RFP# 027-1516 Website and Mobile App Development
More informationAsset management guidelines
Asset management guidelines 1 IT asset management (ITAM) overview Objective Provide a single, integrated view of agency assets in order to allow agencies to identify the asset location and assess the potential
More informationTENDER NUMBER: ITT/SACU/015/2015/O Information and Communication Technology (ICT) Audit IT Effectiveness Review
TENDER NUMBER: ITT/SACU/015/2015/O Information and Communication Technology (ICT) Audit IT Effectiveness Review CLOSING DATE & TIME FRIDAY, 23 JANUARY 2015 17H00 (Namibian Time) POSTAL & PHYSICAL ADDRESS
More informationPlanning an ERP Implementation Project @ Small and Medium Enterprises
Planning an ERP Implementation Project @ Small and Medium Enterprises 27 th Regional WIRC Conference 31 August 2012 Table of Contents What is an SME and ERP Why an ERP for the SME segment Assessing the
More informationJacada Automation for Citrix Enabled BPOs
Customer Experience. Simplified. Jacada Automation for Citrix Enabled BPOs Karnail Jita Pre-Sales Manager, EMEA & APAC 29 Jan 2014 [ ] Current Problem Manual Data Entry Start Process Open Email Update
More informationFor windows erver, Which edition of Windows server 2008 is required ( i. e. Web / Standard / Enterprise )?? Kindly suggest.
Clarifications/Responses for Notice Inviting Tender From Companies/Agencies for Hiring Four Dedicated Servers (3 - Linux & 1 - Windows) Sr. No. Page No. Clause in Tender Clarification/Suggestion Sought
More informationWhat s New in Sage 100 ERP
Date What s New in Sage 100 ERP Lori Maloof, Product Manager CPE Credit In order to receive CPE credit for this session, you must be present for the entire session. Recommended CPE Credit = 1 Delivery
More informationLONDON BOROUGH OF WALTHAM FOREST
LONDON BOROUGH OF WALTHAM FOREST Meeting / Date Cabinet 13 th November 2012 Agenda Item 10 Report Title Cabinet Portfolio Report Author/ Contact details Wards affected Public Access Appendices OneSAP ERP
More information2003 Patricia Ensworth Page 1
1 1 Sample software development project 2 1.1 Start project 3 1.2 Initiation phase 4 1.2.1 Develop project charter 5 1.2.2 Project charter approved 6 1.3 Planning phase 7 1.3.1 Product activities 8 1.3.1.1
More informationTENDER NO: BS2015RFB361
TENDER NO: BS2015RFB361 TENDER DESCRIPTION: APPOINTMENT OF A SERVICE PROVIDER TO PROVIDE AX ACCOUNTING SCM AND PROJECTS SOFTWARE PACKAGE FOR THE BANKSETA FOR THE PERIOD OF TWO YEARS, SIX MONTHS (30 MONTHS)
More informationEvolutyz Corp. is a future proof evolution of endless opportunities with a fresh mind set in Technology Consulting and Professional Services.
Evolutyz Corp. is a future proof evolution of endless opportunities with a fresh mind set in Technology Consulting and Professional Services. Who we are? In order to remain competitive, enterprises today
More informationHow To Write An Oor Ebusiness Ebusiness Solution
Q1. Is it a mandatory requirement to be an Oracle ebusiness Certified Partner or will you accept proof of successful implementations with Oracle, i.e., can use pre-existing setups and application security
More informationecms Document Management Request for Proposal: Questions & Responses
The State Bar of California ecms Document Management Request for Proposal: Questions & Responses August 6, 2015 1. What do you consider to be the top three critical success factors for this project? i.e.,
More information<workers> Online Claims and Injury Management
Global Resources... Local Knowledge With over 30 years experience in workers compensation, our claims management systems have been adopted by Self-Insured Organisations, Third Party Administrators and
More informationELVIS ENTERPRISE LEVEL VALUE INTEGRATION SYSTEM. Toronto Washington, DC Vancouver tel. 1.866.517.1088 www.lynxsystemsinc.com
Strategy ENTERPRISE LEVEL VALUE INTEGRATION SYSTEM Lynx Systems is a powerful and dynamic software application built on the SharePoint platform. It is designed for use by senior executives, and the operational
More informationHow To Manage A System Center 2012 R2 Operation Manager
CÔNG TY CỔ PHẦN TRƯỜNG CNTT TÂN ĐỨC TAN DUC INFORMATION TECHNOLOGY SCHOOL JSC LEARN MORE WITH LESS! Course 10964B: Length: Cloud & Datacenter Monitoring with System Center Operations Manager Audience:
More informationMS 20467: Designing Business Intelligence Solutions with Microsoft SQL Server 2012
MS 20467: Designing Business Intelligence Solutions with Microsoft SQL Server 2012 Description: This five-day instructor-led course teaches students how to design and implement a BI infrastructure. The
More informationMigrating Within the Cloud, SaaS to SaaS
Migrating Within the Cloud, SaaS to SaaS A Real World Experience COLLABORATIVE WHITEPAPER SERIES COLLABORATIVE WHITE PAPER SERIES: Migrating Within the Cloud, SaaS to SaaS How do you know when a technology
More informationAsset and Lifecycle Management
Campbell Robertson, Worldwide Public Sector Solution Leader, IBM ECM August 2014 Asset and Lifecycle Management With enterprise content management from IBM The asset lifecycle Concept Design Tender Build
More informationmiletone as suggested below:
Response to Queries by Bidders for Tender "RFP for Design, Development, Hosting and Maintenance of Website/Portal for MMRC for 2 years." Sr. No. Clause Ref. No. Original Clause Query Proposal by Bidder
More informationTHIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION.
Denver Public Schools Purchasing Department 900 Grant Street, Room 301 Denver, Colorado 80203 Request for Proposal BD1354 ADDENDUM NUMBER ONE THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME
More informationTask Management. JobTraQ Core Features
Task Management JobTraQ automates human to human workflow and simplifies hierarchical team management of collaborative tasks. JobTraQ also ensures that the correct data is collected and displayed through
More informationOverview Of The. For The. Management Of IT Business
Overview Of The ALERT System Specifically Developed For The Management Of IT Business Contents CONTENTS THE OBJECTIVE 3 APPLICATION SCOPE 4 KEY SYSTEM FEATURES 5 THE COMPANY BEHIND ALERT 6 ALERT FUNCTION
More informationSPECIAL CONDITIONS FOR THE UPGRADE OF EXISTING MICROSOFT EXCHANGE SERVER 2003 TO MICROSOFT EXCHANGE SERVER 2010
SPECIAL CONDITIONS FOR THE UPGRADE OF EXISTING MICROSOFT EXCHANGE SERVER 2003 TO MICROSOFT EXCHANGE SERVER 2010 1.0 Scope of Tender These specifications and conditions detail the basic requirements for
More informationTemplate K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
More informationPUR1308/12 - Service Management Tool Minimum Requirements
PUR1308/12 - Service Tool Minimum Requirements No. General Requirements The Supplier organisation must have 10 years or more experience in 1. developing Service software. 2. 3. 4. 5. 6. 7. 8. The Supplier
More informationProject and Resource Management: A Do-it-Yourself guide
Project and Resource Management: A Do-it-Yourself guide By Shyam Kapoor Prisio Technologies LLC Introduction As per Gartner about one third of the projects are never complete and more than half exceed
More information<risk> Enterprise Risk Management
Global Resources... Local Knowledge is vital in supporting business continuity across diverse and challenging environments and operating models. By consolidating risk management activities into a single,
More informationCurrent Challenges in Managing Contract Lifecycle Management
Current Challenges in Managing Lifecycle Management s are the bloodline of your business. Due to increased pressure in volume, complexity and regulatory compliance, contracts have evolved from a simple
More information3. Will we be able to submit both CPF Payment Advice(s) and IRAS submissions one PAT Is integrated with my payroll software?
INTEGRATING PAT WITH PAYROLL SOFTWARE FAQs General: 1. What is Payroll software integration with PAT system about? Companies will be able to submit CPF monthly contributions directly to PAT system via
More informationAddendum #4 to Spotsylvania County RFP #15-10-36 for Enterprise Asset Management System Software June 10, 2015
Addendum #4 to Spotsylvania County RFP #15-10-36 for Enterprise Asset Management System Software June 10, 2015 Addendum #4 for Request for Proposal #15-10-36 is issued in accordance with the RFP Terms
More informationADDENDUM B January 10, 2014
Finance Department Purchasing Division Dear Proposer: REQUEST FOR PROPOSALS (RFP) Specification No. 14-10809-C FOR ECMS/AGENDA/RECORDS MANAGEMENT SOFTWARE PROPOSALS WILL NOT BE OPENED AND READ PUBLICLY
More informationGlendale Community College Microsoft Office SharePoint Server 2007 Initiative Vision/Scope Document. Version 1.0
ware Architects, Inc. Proposal to XXXXX Date Glendale Community College Microsoft Office SharePoint Server 2007 Initiative Vision/Scope Document Software Architects, Inc. Proposal to XXXXX Date Version
More informationAdvanced Solutions of Microsoft SharePoint Server 2013
Course 20332B: Advanced Solutions of Microsoft SharePoint Server 2013 Course Details Course Outline Module 1: Understanding the SharePoint Server 2013 Architecture This module introduces the architectural
More informationContiki Sourcing and Enterprise Contract Management overview
Contiki Sourcing and Enterprise Contract Management overview www.cmacontiki.com Page 1 Contents About CMA Contiki... 3 About Contiki Enterprise Contract Management suite... 3 Contiki ECM supports business
More informationwww.pwc.com Leveraging Continuous Auditing / Continuous Monitoring in internal audit April 10, 2012
www.pwc.com Leveraging Continuous Auditing / Continuous Monitoring in internal audit April 10, 2012 Agenda 1. Introductions to DA, CA & CM [] 2. Inventory management continuous monitoring [The Gap] 3.
More informationManaging Complex Capital Portfolio using PPM integration with PS, CATS & FICO. Session: 2804. Sanjaya Una
Managing Complex Capital Portfolio using PPM integration with PS, CATS & FICO Session: 2804 Sanjaya Una Agenda 1. About GyanSys 2. Overview - PPM 5.0 Technical Architecture 3. Case Study Managing Complex
More informationTAHOE REGIONAL PLANNING AGENCY REQUEST FOR PROPOSAL FOR SOFTWARE CONSULTANT
TAHOE REGIONAL PLANNING AGENCY 128 Market Street P.O. Box 5310 Phone: (775) 588-4547 Stateline, NV 89449 Stateline, Nevada 89449-5310 Fax (775) 588-4527 www.trpa.org Email: trpa@trpa.org REQUEST FOR PROPOSAL
More informationRSA Identity Management & Governance (Aveksa)
RSA Identity Management & Governance (Aveksa) 1 RSA IAM Enabling trusted interactions between identities and information Access Platform Authentication Federation/SSO Employees/Partners/Customers Identity
More informationWelcome to Metafile. Solving document issues for over 30 years. Matt Akin msa@metafile.com 800-638-2445 x 301
Welcome to Metafile Solving document issues for over 30 years Matt Akin msa@metafile.com 800-638-2445 x 301 Janine Peck jgp@metafile.com 800-638-2445 x 303 Metafile helps many companies with their AP,
More informationTerms of Reference For developing Enterprise Electronic File Management and its post-development support service.
Terms of Reference For developing Enterprise Electronic File Management and its post-development support service. Access to Information - II Prime Minister s Government of Bangladesh 1. Introduction E-Governance
More information