DRAFT PATTULLO BRIDGE ALIGNMENT ASSESSMENT OCTOBER 2011 SW1146SWU

Size: px
Start display at page:

Download "DRAFT PATTULLO BRIDGE ALIGNMENT ASSESSMENT OCTOBER 2011 SW1146SWU"

Transcription

1 DRAFT PATTULLO BRIDGE ALIGNMENT ASSESSMENT OCTOBER 2011 SW1146SWU

2 TABLE OF CONTENTS SECTION 1 INTRODUCTION Objectives Background... 1 SECTION 2 ALIGNMENT OPTIONS... 4 SECTION 3 ASSESSMENT FRAMEWORK & METHODOLOGY Financial Customer Service Other Criteria... 8 SECTION 4 ALIGNMENT OPTION ASSESSMENT Financial Customer Service Other Criteria Summary i Pattullo Bridge Alignment Assessment

3 SECTION 1 INTRODUCTION As part of the decision to replace the existing Pattullo Bridge, there is a need to identify the preferred alignment for the new bridge across the Fraser River, the level of connectivity to the existing road networks in the adjoining municipalities, and the number of bridge lanes required to safely provide sufficient mobility for the forecasted travel demand. This document summarizes the assessment of the two key alignment alternatives identified in the previous study, with the evaluation of the connectivity and number of bridge lanes to follow in subsequent reports. 1.1 OBJECTIVES With the objectives of the previous study being primarily related to identifying the need to replace the existing bridge or retain the existing bridge, a full investigation of the bridge alignments and connection options was not warranted. However, the primary objective of this assessment is to identify the preferred alignment, from the two short listed options. Other key objectives of this alignment assessment study are: Conduct a high level financial assessment of the benefits and costs of the replacement options Develop appropriate criteria to assess the bridge alignment options to assist in identifying a preferred alignment with less impacts and potentially higher benefits. Document the results of the assessment in a brief summary report. 1.2 BACKGROUND In the previous Pattullo Corridor Study (Delcan / TransLink - May, 2008), two alignment options were retained for further consideration. The preferred of these two alignments was identified as Alignment 3 and is located downstream of the existing Pattullo Bridge with an offset of approximately 50 metres to avoid impacts to the existing river structures during construction. The other retained option, previously identified as Alignment 1, is located upstream of the rail bridge, with an offset of approximately 50 metres, again to avoid impacts to the existing river structures. Both of these alignments were assumed to be parallel to the existing bridges as shown in Figure 1. 2 Pattullo Bridge Alignment Assessment

4 Figure 1 Recent transportation planning work conducted in 2011 and related to the North Fraser Perimeter Road in New Westminster resulted in a decision to not to construct the United Boulevard Extension due in large part to the lack of support in the local community. In not constructing this vital link in the North Fraser Perimeter Road west corridor, this decision has placed the entire west corridor upgrade in jeopardy. As such, a previous recommendation from the Pattullo Corridor Study to connect the new Pattullo Bridge to the North Fraser Perimeter Road at the Front Street segment is no longer valid. Without the proposed upgrades to the entire North Fraser Perimeter Road corridor, connections to the Front Street corridor are impractical. Therefore, any connections to the new Pattullo Bridge on the north side of the river will remain as per the current conditions with the primary connection remaining along McBride Boulevard and the secondary connections to Royal Avenue and Columbia Street East, both Major Road Network Elements. The exact configuration of these connections to the Major Road Network elements on the north end of the new bridge will be investigated in later stages of the functional planning for the new bridge. On the south side of the river, the previous assumptions to provide the primary connections between the new bridge and King George Boulevard remain valid as no changes to the transportation network on the south side of the river have taken place to supersede the previous assumptions. Secondary connectivity to Scott Road and possibly to the South Fraser Perimeter Road (under construction) also remain valid and will be explored in more detail in subsequent reports. 3 Pattullo Bridge Alignment Assessment

5 SECTION 2 ALIGNMENT OPTIONS The Pattullo Corridor Study recommended that the new replacement bridge alignment be retained in the existing corridor. However, the level of analysis of this previous study could not accurately differentiate between a parallel upstream alignment and a parallel downstream alignment. Further work was subsequently undertaken in this study to examine the two alignment options in more detail and to determine the preferred alignment. Alignment Refinement Building upon the planning level findings from the previous study, the alignment of the new bridge is also determined by the level of connectivity to the municipal road networks and the likely bridge types and the associated span arrangement that are the most practical for this section of the Fraser River given the navigational channel requirements, river hydraulics, geotechnical, and environmental constraints. Together, these three aspects of the new bridge (alignment, connectivity, and bridge type / span arrangement) will need to be combined and evaluated together to accurately define the new bridge alignment. However, the analysis of the level of connectivity and specifically the connection configurations and related property impacts at either end of the new bridge is deferred to further studies which will be undertaken in later stages of the functional planning activities. Therefore, to allow for future modifications or refinements to the two alignment options, an alignment band for each option has been developed. The width of the bands depend upon a number of further assumptions including the retention of the primary connection to McBride Boulevard and the secondary connections to Royal Avenue (to / from the west) and Columbia Street (to / from the east) on the north side. How and where these connections between the new bridge and Major Road Network occur represents some level of variability in the actual bridge alignment. Furthermore, connections to McBride Boulevard involve two potential corridors on either side of the existing residential island located south of Royal Avenue, between McBride Boulevard and the approach to the existing bridge. These additional alignment variations are represented in the two alignment options as described below and shown in Figure 2: 4 Pattullo Bridge Alignment Assessment

6

7 DOWNSTREAM ALIGNMENT This alignment is located approximately 50 metres downstream from the existing Pattullo Bridge. This alignment remains parallel to the existing bridge as this represents the most efficient roadway geometry due to the need to tie back into the main roadway corridors on the north and south side of the Fraser River. Due to the required roadway geometry to provide connectivity between the downstream alignment and the existing McBride Corridor, this alignment logically follows the approach to the existing bridge located on the west side of the residential island. This alignment represents Alignment 3 from the previous study. UPSTREAM ALIGNMENT This alignment is located approximately 50 metres upstream from the existing New Westminster Rail Bridge. As noted above in Section 1, this alignment represents Alignment 1 from the previous study. Two variations of this upstream alignment were developed to examine alternate means of connecting to the McBride Boulevard corridor. The first alternative includes a connection to the McBride Boulevard corridor west of the residential neighbourhood island and largely following the approach or connection to the existing Pattullo Bridge. Conversely, the second alternative includes a connection to the McBride Boulevard corridor east of the residential neighbourhood island, in the existing right-of-way of the local segment of McBride Boulevard. The connection to the King George Boulevard corridor is similar between the two upstream alignment variations with the actual connection being offset slightly to the east of the existing south bridge (approach structure) abutment. 5 Pattullo Bridge Alignment Assessment

8 SECTION 3 ASSESSMENT FRAMEWORK & METHODOLOGY Two alignment options, downstream and upstream, have been identified as candidates for the preferred alignment for the new Pattullo Bridge. The following section provides a high level comparative assessment of these two alignments using a set of the evaluation criteria previously derived and applied in both the Pattullo Corridor and the Pattullo Bridge Option Assessment studies. However, due to the high level nature of this assessment, only a subset of the previous criteria was used in this assessment with a focus on those criteria providing a clear difference between the options being assessed. The evaluation criteria are presented in three categories: Financial, Customer Service, and Other. A brief description of each of these categories is provided below. 3.1 FINANCIAL Four sub criteria are included under the financial evaluation category: capital cost; salvage value; property cost, and maintenance costs. Where applicable, an analysis period of 25 years has been applied and present value (PV) costs in 2011 dollars were generated by summing the costs over this analysis period. CAPITAL COSTS The capital costs evaluation represents the planning level / class C cost estimates using the elemental parametric cost estimating methodology. In addition to actual construction costs, these project cost estimates include values for future planning, design, project management, construction administration, and contingencies. SALVAGE COSTS The salvage value accounts for project elements that have not yet reached their full life at the end of the planning horizon / life cycle, and it is based on the initial cost, the service life, and the remaining life of the facility. The salvage value has been calculated with respect to the facility components within the jurisdiction of TransLink (e.g. key bridge structural elements). 6 Pattullo Bridge Alignment Assessment

9 PROPERTY Based on the conceptual design drawings prepared in the previous studies, a number of property impacts were identified for each alignment option. Costs have been estimated based on the full and partial takes of the property impacted, recognizing industrial, residential, and other land uses. These cost estimates include contingencies to account for expropriation settlements and business losses. MAINTENANCE Maintenance cost estimates for the TransLink facility components have been applied to the alignments options over the entire planning / analysis period, such as all of the key structural components situated between the bridge abutments. 3.2 CUSTOMER SERVICE The Customer Service category consists of quantitative indicators which include travel time savings, vehicle operating savings, and traffic safety. Based on these indicators, user benefit / cost ratios are generated for each alignment option. TRAVEL TIME SAVINGS Travel time savings estimates are based on outputs from a version of the regional travel demand forecasting model, namely the Gateway Sub Area Model State 4 with the GMS 5.0 Draft 2 revised land use. The AM and PM peak hour output has been expanded to estimate annual travel time savings. The estimates, which include value of time, are calculated by summing the travel time savings over the entire analysis period assuming constant savings throughout. For the purposes of this study, travel time savings were calculated against a base case where the existing bridge would be rehabilitated and operated as a three lane bridge with a reversible centre lane as per the findings in the Pattullo Bridge Option Assessment Study (Delcan 2011). 7 Pattullo Bridge Alignment Assessment

10 VEHICLE OPERATING COSTS Vehicle operating cost estimates are based on the vehicle kilometres travelled output from the travel demand forecasting models. The output from the AM and PM peak hours has been expanded to estimate annual vehicle operating costs. These estimates include an average operating cost per kilometre and a summation of vehicle operating costs over the entire analysis period. TRAFFIC SAFETY IMPROVEMENTS Traffic safety is quantified by summing collision costs over the analysis period of 25 years. The expected number of collisions per annum was estimated using collision prediction models, collision rates, and collision modification factors where applicable. The evaluation considers only incremental differences (Δ) between the key alignment options rather than relative to the base case (which has not been estimated). It is anticipated that the difference between the base case and the two alignment options would be higher than the incremental difference between the two alignment options. Therefore, the current methodology is considered conservative. 3.3 OTHER CRITERIA Other criteria included in the assessment include pedestrian and cyclist accommodation, vehicle connections to the Major Road Network, property impacts, river navigation, and environmental impacts. PEDESTRIAN AND CYCLIST ACCOMMODATION The provision of appropriate pedestrian / cycling facilities on the bridge and the level of connectivity to the existing pedestrian and cycling facility network on both sides of the river has been evaluated qualitatively. The evaluation includes factors such as increased travel lengths, circuitous routing, and grades. VEHICLE CONNECTIONS TO THE MAJOR ROAD NETWORK (MRN) The vehicle connections to the MRN are evaluated based on the complexity of the connection which in turn relates to operational issues, property impacts, and construction costs. 8 Pattullo Bridge Alignment Assessment

11 PROPERTY IMPACTS Property impacts are estimated by the number of property takings associated with each alignment option. Reasonable estimates have been made in terms of the number of actual properties impacted. Though the impacts have been further categorized in previous studies, only an aggregation of the number of takings is presented due to the lack of detail being considered in this study with respect to the configurations of the various connections. RIVER NAVIGATION Improvements to navigation along the Fraser River have been evaluated qualitatively by comparing the achieved navigational clearance (vertical and horizontal) for each of the options. This evaluation is based on a high level assessment of bridge types and span arrangements (pier locations). ENVIRONMENTAL IMPACTS The environmental impacts include three sub categories: terrestrial impacts, aquatic impacts, and archaeological impacts. The two alignment options have been ranked according to low, moderate, or high impact ratings on terrestrial and aquatic features; and a relative ranking of higher or lower impacts on archaeological features. 9 Pattullo Bridge Alignment Assessment

12 SECTION 4 ALIGNMENT OPTION ASSESSMENT Each of the two alignment options has been assessed against the various criteria and the results are presented in Table 1. It is noted that the results are primarily based on those presented in the Pattullo Corridor Study and the Pattullo Bridge Option Assessment Study. Table 1 Evaluation Results for the Downstream and Upstream Alignments CRITERIA FINANCIAL UNIT DOWNSTREAM UPSTREAM Alignment 1 Alignment 3 Capital Cost - Facility $M Salvage Value $M Property $M Maintenance and Operations $M Total Cost (PV) $M CUSTOMER SERVICE Travel Time Savings $M Vehicle Operating Savings $M Traffic Safety (Δ) $M 0 7 Benefit / Cost (B/C) OTHER Pedestrian & Cyclist Accommodation Vehicle Connections to MRN Property Impacts (displacement) Significant Improvement over existing conditions More complex connectin to MRN on thenorth side of the river 7 in New Westminster 9 in Surrey Two parks impacted directly Significant Improvement over existing conditions Less compex connection to MRN at the north approach to the bridge 7 in New Westminster 9 in Surrey No parks impacted River Navigation Moderate Improvement Moderate Improvement Environmental Impact Low to potentially moderate impact on terrestrial (vegetation, wildlife) Moderate impact on aquatic (vegetation, fish, wildlife) Lower anticipated archaeological impacts Low impact on terrestrial (vegetation, wildlife) Low to moderate impact on aquatic (vegetation, fish, wildlife) Higher anticipated archaeological impacts 10 Pattullo Bridge Alignment Assessment

13 4.1 FINANCIAL As can be seen from Table 1 under the financial category, the total cost of the downstream alignment option is higher than that of the upstream alignment option by a magnitude of approximately $46 million (PV). The total cost includes the capital cost, salvage value, property cost, maintenance and operational costs. From the information presented in the Pattullo Bridge Option Assessment Study, a Base Case was identified which consisted of a rehabilitated three lane bridge with a centre reversible lane with a total cost of approximately $139 million (PV). For comparative assessment purposes, the total cost of this Base Case reversible lane option can be discounted from the implementation costs for the two alignment options to achieve the incremental cost for each option. The incremental costs for the two options are summarized below: Downstream Alignment Upstream Alignment $455 Million $409 Million 4.2 CUSTOMER SERVICE Several criteria were evaluated under the customer service category including travel time savings, vehicle operating savings, and traffic safety. Incremental Benefit to Cost ratios were then generated for each of the two alignment options. Based on the results presented in Table 1, the two alignment options show identical travel time savings and vehicle operating costs with a minor difference in the traffic safety improvements. The similarity in travel time and vehicle operating cost savings is due to the fact that both the downstream and upstream options were assessed using the same alignment in the travel demand forecasting model. The slight difference in the location of the two alignments would not result in significant travel time differences given the level of accuracy involved in using the macro level travel demand forecasting model. This information was extracted from that presented previously in the Pattullo Bridge Option Assessment Study. Similar to the total cost under the financial category, the travel time and vehicle operating savings for the Base Case has been discounted from the benefits estimated for each of the two alignment option. The travel time savings, vehicle operating savings, and traffic safety measures altogether yield total benefits of $448 Million for the downstream alignment and $455 million for the upstream alignment. 11 Pattullo Bridge Alignment Assessment

14 The resulting benefits to cost ratios (B/C) for the downstream and upstream options were estimated to be 0.98 and 1.11, respectively. Based on this benefit to cost ratio analysis, the upstream option is performs slightly better financially when compared to the downstream option. 4.3 OTHER CRITERIA This category includes a number of qualitative evaluation criteria: pedestrian and cyclist accommodation, vehicle connections to the Major Road Network, property impacts, river navigation, and environmental impacts. As depicted in Table 1, both the downstream and upstream option are considered to provide significant improvements in pedestrian and cyclist accommodation, similar impacts in the number of properties affected, as well as moderate improvement in river navigation (based on the proposed pier placement associated with a cable stay bridge with a main span of 350 metres see Figure 3). A summary of the assessment of each option with respect to these criteria is provided below: PEDESTRIAN AND CYCLING ACCOMMODATION For the purposes of this study, one way pedestrian / cycling facilities have been assumed to be located on both sides of the new bridge. In both alignment options, the connections to the existing cycling network on the north and south side of the river would be similar in that direct connections to the BC Parkway (south side) and the Central Valley Greenway along Columbia Street remain the primary objective. In both options, connections to the BC Parkway in New Westminster and the Brunette Fraser Greenway would be provided indirectly via the Central Valley Greenway. VEHICLE CONNECTIVITY TO MAJOR ROAD NETWORK With regards to the vehicle connections to the major road network, the upstream alignment has somewhat less complex connections to the MRN whereas the downstream option has more complex connections which also lead to higher construction costs. In the downstream alignment, the further offset of the bridge alignment downstream of the existing bridge alignment results in the required geometry for the roadways connecting to the existing road network to be more constrained and thus complex. It is anticipated that connections to the road network in New Westminster and Surrey for the upstream alignment will be more direct. 12 Pattullo Bridge Alignment Assessment

15

16 PROPERTY IMPACTS Based on the assessments conducted in the previous reports and assuming similar levels of connectivity to the identified Major Road Network elements, a similar number of properties are impacted in both alignment options. However, downstream alignment affects park land (Brownsville Bar Park) on the south side of the river and potentially some park land (Albert Crescent Park) on the north side of the river depending upon the final configuration of the bridge connections. The upstream alignment is anticipated to have minimal to no impacts on any park land. RIVER NAVIGATION Additional analysis was conducted to identify areas where the placement of additional bridge piers in the river would potentially result in river bed scour issues. These scour issues, if significant, could potentially affect the stability of the foundations for the two existing bridges. To this end, a number of no pier zones were identified as shown on Figure 3. Also, further analysis was conducted to identify the navigation channels for this section of the Fraser River. Through discussions with Navigable Waters Protection Division (Transport Canada), Port Metro Vancouver, and the Council of Marine Carriers, a primary / deep sea channel 225 metres wide and 45 metres in height (vertical clearance) was identified along with a secondary / domestic channel of 60 metres. These channels are also shown on Figure 3. Assuming a 350 metre cable stay bridge in both alignments, the approximate location of the main bridge piers have been located on these two figures. As can be seen, in both alignments, placement of the bridge piers avoids the no pier zones and thus the associated river bed scour issues. The bridge pier locations also span the two navigation channels, therefore avoiding any impacts to future river navigation. With the removal of the existing Pattullo Bridge, the number of piers in the Fraser River will be less than today. 13 Pattullo Bridge Alignment Assessment

17 ENVIRONMENTAL EFFECTS In terms of the environmental category, most of the assessed criteria for the two alignment options have similar rankings that range from low to moderate. A brief summary is provided below: Downstream Alignment: Terrestrial Impacts Vegetation: New Westminster connections will affect bluff and park vegetation; significant impacts to heritage chestnut tree between Wellington Street and Columbia Street may not be avoidable due to alignment. Low to Potentially Moderate Impacts Terrestrial Impacts Wildlife / Habitat: Limited wildlife habitat capability / suitability associated with bluff and park vegetation. Low Impacts Aquatic Impacts Vegetation: Potential for bridge pier on Surrey shoreline would affect riparian vegetation. Potential for bridge pier on New Westminster shoreline would affect limited riparian vegetation. Connection to King George Highway will displace Pattullo Channel riparian vegetation. Moderate Impacts Aquatic Impacts Fish / Habitat: Potential for bridge pier on Surrey shoreline affects intertidal zone. Potential for bridge pier on New Westminster shoreline affects limited intertidal zone. River piers and associated armouring will displace subtidal substrates. Connection to King George Highway will displace Pattullo Drainage Channel with Class A fish habitat. Moderate Impacts Aquatic Impacts Wildlife / Habitat: Limited wildlife habitat capability / suitability associated with riparian vegetation if bridge pier located on New Westminster shoreline. Potential for bridge pier on Surrey shoreline affects riparian vegetation. Connection to King George Highway will displace Pattullo Channel & riparian vegetation. Moderate Impacts Archaeological Impacts: In New Westminster, there is no preferred option. In Surrey, the alignment is in close proximity to archaeological site DhRr-002; the highest archaeological potential is beneath and adjacent to the CN Rail ROW between sites DhRr- 002 and DhRr-074. The alignment is also located within site DhRr-064, formerly the BCER Interurban Line ROW. Lower Anticipated Impacts 14 Pattullo Bridge Alignment Assessment

18 Upstream Alignment: Terrestrial Impacts Vegetation: New Westminster connections will affect bluff and park vegetation; impacts to heritage chestnut tree between Wellington Street and Columbia Street can likely be minimized due to simplified connection configuration. Low Impacts Terrestrial Impacts Wildlife / Habitat: Limited wildlife habitat capability / suitability associated with park & bluff vegetation. Low Impacts Aquatic Impacts Vegetation: Potential for bridge pier on Surrey shoreline affects limited riparian vegetation. Connection to King George Highway to cross over railway and Musqueam Drainage Channel. Moderate Impacts Aquatic Impacts Fish / Habitat: Potential for bridge pier on Surrey shoreline affects limited intertidal zone. Potential for bridge pier on New Westminster shoreline affects limited intertidal zone. River piers and associated armouring will displace subtidal substrates. Moderate Impacts Aquatic Impacts Wildlife / Habitat: Limited wildlife habitat capability / suitability associated with riparian vegetation if bridge pier located on New Westminster or Surrey shoreline. Low Impacts Archaeological Impacts: In New Westminster, there is no preferred option, however the upstream alignment is in closer proximity to designated historic building Dh-Rr-048 (the Woodland s Nurses Lodge). In Surrey, the upstream alignment is located within the boundaries of Dh-Rr-074, an area of significant archaeological potential, and crosses the CN Rail ROW, an area of heightened archaeological potential. The alignment also crosses the boundary of Dh-Rr-064, the former BCER Interurban Line ROW. Higher Anticipated Impacts 4.4 SUMMARY From the information presented in Table 1, it can be seen that the upstream alignment possesses higher benefits with lesser impacts. Based on these findings, it is recommended that the further transportation planning work continue with the upstream alignment with further refinement of this alignment dependent on the assessment of the bridge connection options (north and south) as well as any further effects to river navigation, environmental, geotechnical, and river hydraulic characteristics. 15 Pattullo Bridge Alignment Assessment

19 CRITERIA UNIT DOWNSTREAM UPSTREAM Alignment 1 Alignment 3 FINANCIAL Capital Cost - Facility $M Salvage Value $M Property $M Maintenance and Operations $M Total Cost (PV) $M CUSTOMER SERVICE Travel Time Savings $M Vehicle Operating Savings $M Traffic Safety (Δ) $M 0 7 Benefit / Cost (B/C) OTHER Pedestrian & Cyclist Accommodation Vehice Connections to MRN Property Impacts (displacement) Significant Improvement over existing conditions More complex connecton to MRN on the north side of the river 7 in New Westminster 9 in Surrey Park land impacts Significant Improvement over existing conditions Less compex connection to MRN at the north approach to the bridge 7 in New Westminster 9 in Surrey River Navigation Moderate Improvement Moderate Improvement Environmental Impact Low to potentially moderate impact on terrestrial (vegetation, wildlife) Moderate impact on aquatic (vegetation, fish, wildlife) Lower anticipated archaeological impacts Low impact on terrestrial (vegetation, wildlife) Low to moderate impact on aquatic (vegetation, fish, wildlife) Higher anticipated archaeological 16 Pattullo Bridge Alignment Assessment

3 Tappan Zee Bridge Rehabilitation Options

3 Tappan Zee Bridge Rehabilitation Options 3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:

More information

1. REPORT CONTEXT Description of the development (include all of the following that are known at the time of the application):

1. REPORT CONTEXT Description of the development (include all of the following that are known at the time of the application): Transportation Assessment and Management Study Guidelines for Consultants INTRODUCTION This document is intended to provide guidelines for transportation consultants who produce Transportation reports

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

Evergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by

Evergreen Line Rapid Transit Project Business Case Executive Summary. February 2008. Reviewed by Evergreen Line Rapid Transit Project Business Case Executive Summary February 2008 Reviewed by Recommendation and Executive Summary The business case for the Evergreen Line Rapid Transit Project (the Project)

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

Stouffville Corridor Rail Service Expansion

Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Class Environmental Assessment Study WELCOME PUBLIC INFORMATION CENTRE #2 Tuesday January 28, 2014 Agincourt Recreation

More information

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City

Mayors Welcome Strong Surrey Votes Yes Coalition Support. Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City Mayors Welcome Strong Surrey Votes Yes Coalition Support Yes Vote Would Vastly Improve Transit and Transportation in Fast Growing City February 11, 2015 Vancouver, BC The Mayors Council on Regional Transportation

More information

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project. The purpose of this meeting is inform the public of the updates the project, and get input before the finalization of the project. The following panels describe the purpose and hisry of the project, along

More information

FLOOD PLAIN DESIGNATION AND PROTECTION

FLOOD PLAIN DESIGNATION AND PROTECTION CITY OF RICHMOND FLOOD PLAIN DESIGNATION AND PROTECTION BYLAW NO. 8204 EFFECTIVE DATE - SEPTEMBER 8, 2008 CONSOLIDATED FOR CONVENIENCE ONLY This is a consolidation of the bylaws listed below. The amendment

More information

GTA Cordon Count Program

GTA Cordon Count Program Transportation Trends 2001-2011 Executive Summary Project No. TR12 0722 September 2013 1.0 Introduction The Cordon Count program was established to collect traffic data as a tool for measuring travel trends

More information

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year Appendix C1 Surface Water Modelling 1 Overview 1.1 The Drain London modelling was designed to analyse the impact of heavy rainfall events across each London borough by assessing flow paths, velocities

More information

Informational Workshop Public Meeting Kanawha Falls Bridge Project

Informational Workshop Public Meeting Kanawha Falls Bridge Project Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal

More information

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013. Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013 Rationale Underground infrastructure may be at risk from valley, streambank

More information

Presentation to Community Task Force July 9, 2007

Presentation to Community Task Force July 9, 2007 Alternative Evaluation Results Presentation to Community Task Force July 9, 2007 Outline of Presentation Overview of alternative evaluation Alternative evaluation methodology Process and assumptions General

More information

Phases 2 & 3, & Addendum Urban Structure Plan Options for West Whitby

Phases 2 & 3, & Addendum Urban Structure Plan Options for West Whitby 7. 5 A d v a n t a g e s a n d D i s a d v a n t a g e s Table 22 summarizes the advantages and disadvantages of each option based on the evaluation of Table 16. Dillon Consulting Limited Page 75 Table

More information

West London Dyke Flood Control Structure Master Plan Appendix A

West London Dyke Flood Control Structure Master Plan Appendix A West London Dyke Flood Control Structure Master Plan Appendix A Introduction The West London Dyke runs along the west bank of the North Branch of the Thames River from Oxford Street to the forks of the

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580

More information

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

Executive Summary. Transportation Needs CHAPTER. Existing Conditions CHAPTER 1 Executive Summary The City of Forest Grove Transportation System Plan (TSP) was updated to keep it consistent with recent growth trends in the city and other transportation planning efforts in

More information

COPCUT RISE COPCUT RISE DROITWICH SPA CONSULTATION STATEMENT. November 2010. Prepared by Capita Lovejoy on behalf of William Davis Limited

COPCUT RISE COPCUT RISE DROITWICH SPA CONSULTATION STATEMENT. November 2010. Prepared by Capita Lovejoy on behalf of William Davis Limited COPCUT RISE DROITWICH SPA CONSULTATION STATEMENT COPCUT RISE November 2010 Prepared by Capita Lovejoy on behalf of William Davis Limited Copcut Rise Land north of Copcut Lane, Droitwich Spa: Consultation

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

October 15, 2013. Mayor and Council City of New Westminster 511 Royal Avenue New Westminster, BC V3L 1H9

October 15, 2013. Mayor and Council City of New Westminster 511 Royal Avenue New Westminster, BC V3L 1H9 October 15, 2013 Mayor and Council City of New Westminster 511 Royal Avenue New Westminster, BC V3L 1H9 RE: Business Plan Advancing a Collaborative, Regional Approach to Flood Management in BC s Lower

More information

TRANSPORTATION MODELLING IN CALGARY

TRANSPORTATION MODELLING IN CALGARY TRANSPORTATION MODELLING IN CALGARY Why Do We Use Transportation Models? There are three approaches that can be used for proceeding to develop a transportation system for Calgary s future. One approach

More information

Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES

Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES Township of Georgian Bluffs POLICY USE OF UNOPENED ROAD ALLOWANCES 1.0 Background An unopened road allowance as defined by the Municipal Act is a public highway that has not been opened and assumed for

More information

Median Bus Lane Design in Vancouver, BC: The #98 B-Line

Median Bus Lane Design in Vancouver, BC: The #98 B-Line Li 1 Median Bus Lane Design in Vancouver, BC: The #98 B-Line Simon Li, P.Eng. PTOE Acting Program Manager, Road and Bridge Projects TransLink (Greater Vancouver Transportation Authority) 1600 4720 Kingsway

More information

Section ALTERNATIVES. 3. Alternatives

Section ALTERNATIVES. 3. Alternatives Section 3 ALTERNATIVES 3. Alternatives 3.0 Alternatives The Springfield Rail Improvements Project Build Alternatives would utilize different routes. The No Build Alternative includes the continuation of

More information

The Corporation of the TOWN OF MILTON

The Corporation of the TOWN OF MILTON The Corporation of the TOWN OF MILTON Report to: From: Mayor G. A. Krantz & Members of Council M. Paul Cripps, P. Eng., Director, Engineering Services Date: November 11, 2013 Report No. ENG-039-13 Subject:

More information

Newsletter Jumbo Glacier Alpine Resort Proposal

Newsletter Jumbo Glacier Alpine Resort Proposal Newsletter Jumbo Glacier Alpine Resort Proposal August 1995 - Number 1 - Environmental Assessment Office Province of British Columbia The Jumbo Glacier Alpine Resort Proposal Pheidias Project Management

More information

5.14 Floodplains and Drainage/Hydrology

5.14 Floodplains and Drainage/Hydrology I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important

More information

Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents

Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents Port Mann/Highway 1 Project Request For Proposals Volume 1 Instructions to Proponents August 7, 2007 PAGE 1 OF 57 Table of Contents 1. Introduction... 5 1.1 Project Scope Overview... 5 1.2 Short-listed

More information

Transitways and the RouteAhead for Calgary Transit

Transitways and the RouteAhead for Calgary Transit Transitways and the RouteAhead for Calgary Transit Chris Jordan, P.Eng., M.Sc., Manager, Strategic Planning, Calgary Transit, Transportation, City of Calgary Jen Malzer, P.Eng., M.Sc., Senior Transit Planner,

More information

Seagull Intersection Layout. Island Point Road - A Case Study. Authors: John Harper, Wal Smart, Michael de Roos

Seagull Intersection Layout. Island Point Road - A Case Study. Authors: John Harper, Wal Smart, Michael de Roos Seagull Intersection Layout. Island Point Road - A Case Study Authors: John Harper, Wal Smart, Michael de Roos Presented by Mr John Harper, Road Safety and Traffic Services Manager Phone: 4221 2456 Mobile:

More information

EXPENDITURES SUMMARY 2014 2015 INCREASE BUDGET BUDGET (DECREASE) (Restated) Over 2014

EXPENDITURES SUMMARY 2014 2015 INCREASE BUDGET BUDGET (DECREASE) (Restated) Over 2014 EXPENDITURES SUMMARY 2014 2015 INCREASE (Restated) Over 2014 Mayor and Council 879,500 900,000 20,500 Office of Chief Administrative Officer 577,500 598,500 21,000 Clerks 1,727,500 1,635,000 (92,500) Legal

More information

Planning Railway Safety in Canada

Planning Railway Safety in Canada Planning Railway Safety in Canada Mike Lowenger Vice President, Operations and Regulatory Affairs Railway Association of Canada July 10, 2014 ABOUT THE RAC 50+ members Represents virtually all railways

More information

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014 Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,

More information

TOWN OF NEW HAVEN ROAD PLAN

TOWN OF NEW HAVEN ROAD PLAN 1 TOWN OF NEW HAVEN ROAD PLAN BACKGROUND The Town of New Haven, Vermont consists of 42 square miles of land and a population of approximately 1400 people. At the start of the 21 st century, it is served

More information

Alternatives Evaluation Overview

Alternatives Evaluation Overview Alternatives Evaluation Overview 124 Alternatives were analyzed against the evaluation criteria Criteria and criteria weighting were set by the Community Task Force Ratings were quantitative and qualitative

More information

How To Protect A Floodplain From Flooding

How To Protect A Floodplain From Flooding EXECUTIVE SUMMARY This Class Environmental Assessment (Class EA) was undertaken to examine alternative flood protection systems, and their environmental effects, for the elimination of the flood risk on

More information

DRAFT Policy to Guide Discretion on Proposed Relaxations to Minimum Parking Requirements in Commercial Districts City-Wide 2014 June 05

DRAFT Policy to Guide Discretion on Proposed Relaxations to Minimum Parking Requirements in Commercial Districts City-Wide 2014 June 05 PARKING INITIATIVES Attachment I Corridor Program Descriptions Corridor Program Pilot Though the Corridor Program will officially launch in the fall, this summer, The City will pilot the first phase of

More information

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation Position Statement regarding Offshore Wind Proposals on Lake Huron Lake Huron Centre for Coastal Conservation June 2010 Lake Huron Centre for Coastal Conservation (LHCCC) Corporate Position related to:

More information

Cellular Antenna Proposal Form

Cellular Antenna Proposal Form Cellular Antenna Proposal Form Islands Trust, Northern Office 700 North Road, Gabriola Island, BC V0R 1X3 Phone: 250-247-2063 Fax: 250-247-7514 www.islandstrust.bc.ca northinfo@islandstrust.bc.ca Be sure

More information

Alternatives Presentation Meeting Middlebury WCRS(23)

Alternatives Presentation Meeting Middlebury WCRS(23) Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College

More information

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

Penticton Creek May 4, 2015 Council Meeting

Penticton Creek May 4, 2015 Council Meeting Penticton Creek May 4, 2015 Council Meeting Penticton Creek Council Meeting May 4, 2015 Penticton Creek in the Early Years Penticton Creek Council Meeting May 4, 2015 Penticton Creek Today Penticton Creek

More information

Nashville Area MPO Regional Freight Study fast action projects

Nashville Area MPO Regional Freight Study fast action projects Project #1 Beechcroft road (sr 247) at csx crossing Motor carrier survey location Maury County (Spring Hill, Tn) / City of Spring Hill Current at-grade railway crossing causes traffic delays as a result

More information

Lawson Outline Plan External Traffic Analysis Working Paper

Lawson Outline Plan External Traffic Analysis Working Paper Total Lawson Development ACTPLA 16 January 2009 Document No.: Prepared for ACTPLA Prepared by Maunsell Australia Pty Ltd Level 2, 60 Marcus Clarke Street, Canberra ACT 2600, Australia T +61 2 6201 3000

More information

Sector Design Concepts

Sector Design Concepts Section C Sector Design Concepts C7 Sector 7 Great North Road Underpass 6 6 6 C7. Existing situation Sector 7 refers to the cut and cover section of the project linking the northern end of the deep tunnels

More information

Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas

Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas Transportation Association of Canada Primer on Transportation Funding and Governance in Canada s Large Metropolitan Areas The transportation funding and governance frameworks of Canada s metropolitan regions

More information

APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY

APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY ALAMEDA POINT MASTER INFRASTRUCTURE PLAN March 31, 2014 APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY Carlson, Barbee & Gibson, Inc. Backbone Infrastructure Engineer

More information

Evaluation of the Shared-Use Arrow

Evaluation of the Shared-Use Arrow Evaluation of the Shared-Use Arrow Table of Contents Page Evaluation of the Shared-Use ARROW Background... 1 ARROW Design... 1 ARROW Placement... 2 Wayne E. Pein William W. Hunter J. Richard Stewart Report

More information

Arkansas River Corridor Vision & Master Plan

Arkansas River Corridor Vision & Master Plan A r k a n s a s R I v e r C o r r I d o r P l a n Arkansas River Corridor Vision & Master Plan July 2005 Indian Nations Council of Governments A r k a n s a s R I v e r C o r r I d o r P l a n Partnership

More information

Stone Way N Rechannelization: Before and After Study. N 34th Street to N 50th Street

Stone Way N Rechannelization: Before and After Study. N 34th Street to N 50th Street City of Seattle Department of Transportation Stone Way N Rechannelization: Before and After Study N 34th Street to N 50th Street May, 2010 INTRODUCTION Population density in Seattle is increasing within

More information

CHAPTER 8 CIVIL DESIGN

CHAPTER 8 CIVIL DESIGN CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical

More information

INFRASTRUCTURE POLICIES

INFRASTRUCTURE POLICIES PART 7 INFRASTRUCTURE POLICIES 7.1 INTRODUCTION This Section sets out policies related to the development of services and utilities which are essential to the proper functioning and well being of the municipality.

More information

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future

More information

US 51 Ohio River Bridge Engineering and Environmental Study

US 51 Ohio River Bridge Engineering and Environmental Study US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS. 1-100.00 & 1-1140.00 Prepared by: Michael Baker Jr., Inc. 9750 Ormsby Station Rd Louisville, KY 40223 August 16, 2013 Table of Contents

More information

Manitoba Infrastructure and Transportation. Guide for Establishing Reduced-Speed School Zones

Manitoba Infrastructure and Transportation. Guide for Establishing Reduced-Speed School Zones Overview Guide for Establishing Reduced-Speed School Zones The Highway Traffic Act authorizes local governments, such as municipalities, Northern Community Councils and First Nation Band Councils, to make

More information

Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts. Design and Development Guidelines. Part Two.

Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts. Design and Development Guidelines. Part Two. Revere Beach Transit-Oriented Development Parcels Revere, Massachusetts Design and Development Guidelines Request for Qualifications and Expressions of Interest with Preliminary Development Plans Part

More information

Region of Durham Basement Flooding Prevention Study. Public Information Centre #2

Region of Durham Basement Flooding Prevention Study. Public Information Centre #2 Region of Durham Basement Flooding Prevention Study Public Information Centre #2 October 27, 2009 Welcome Today is an opportunity for you to hear about and offer input on the Annes Street Basement Flooding

More information

Executive Director s Recommendation Commission Meeting: March 5, 2015

Executive Director s Recommendation Commission Meeting: March 5, 2015 Executive Director s Recommendation Commission Meeting: March 5, 2015 PROJECT Curseen-Morris Processing and Distribution Center Parking Lot 900 Brentwood Avenue NE Washington, DC SUBMITTED BY United States

More information

MANAGEMENT REPORT. Alternatives to New Secondary North

MANAGEMENT REPORT. Alternatives to New Secondary North MANAGEMENT REPORT Alternatives to New Secondary North School District 68 (Nanaimo-Ladysmith) October 2004 School District 68 (Nanaimo-Ladysmith) Management Report Alternatives to New Secondary North Three

More information

Nepean River Bridge. The NSW Government is building a new pedestrian and cyclist bridge over the Nepean River to connect Penrith and Emu Plains.

Nepean River Bridge. The NSW Government is building a new pedestrian and cyclist bridge over the Nepean River to connect Penrith and Emu Plains. Nepean River Bridge May 2016 The NSW Government is building a new pedestrian and cyclist bridge over the Nepean River to connect Penrith and Emu Plains. The new bridge will provide a safe crossing for

More information

San Diego Integrated Regional Water Management Implementation Grant Proposal Economic Analysis Flood Damage Reduction Costs and Benefits

San Diego Integrated Regional Water Management Implementation Grant Proposal Economic Analysis Flood Damage Reduction Costs and Benefits Attachment 9 San Diego Integrated Regional Water Management Economic Analysis Flood Damage Reduction Costs and Benefits Attachment 9 consists of the following items: Flood Damage Reduction Costs and Benefits.

More information

Cathkin Relief Road Planning Statement

Cathkin Relief Road Planning Statement Cathkin Relief Road Planning Statement The Proposal This statement sets out the background to the Cathkin Relief Road project currently being progressed by South Lanarkshire Council. The project will provide

More information

Consultation on integrating flood defence consents into the Environmental Permitting regime in England and Wales

Consultation on integrating flood defence consents into the Environmental Permitting regime in England and Wales www.gov.uk/defra www.wales.gov.uk Consultation on integrating flood defence consents into the Environmental Permitting regime in England and Wales Annex 2; Proposed exclusions Emergencies and licensable

More information

Intersection Cost Comparison Spreadsheet User Manual ROUNDABOUT GUIDANCE VIRGINIA DEPARTMENT OF TRANSPORTATION

Intersection Cost Comparison Spreadsheet User Manual ROUNDABOUT GUIDANCE VIRGINIA DEPARTMENT OF TRANSPORTATION Intersection Cost Comparison Spreadsheet User Manual ROUNDABOUT GUIDANCE VIRGINIA DEPARTMENT OF TRANSPORTATION Version 2.5 i Virginia Department of Transportation Intersection Cost Comparison Spreadsheet

More information

Screening Transportation Assets for Vulnerability

Screening Transportation Assets for Vulnerability Screening Transportation Assets for Vulnerability Impacts of Climate Change and Variability on Transportation Systems & Infrastructure (Gulf Coast Study, Phase 2) FHWA Office of Planning Environment and

More information

ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS

ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County,

More information

5.0 ENVIRONMENTAL IMPACT ASSESSMENT METHODS

5.0 ENVIRONMENTAL IMPACT ASSESSMENT METHODS 5.0 ENVIRONMENTAL IMPACT ASSESSMENT METHODS The methods that are used to conduct the environmental impact assessment (EIA) of the Project are described in this section. The EIA uses a methodological framework

More information

Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014)

Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014) Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 15.7 Miles, 17 Stations

More information

Public Information & Public Scoping Meeting

Public Information & Public Scoping Meeting Public Information & Public Scoping Meeting William F. Cribari Memorial Bridge Route 136 over the Saugatuck River Review of Rehabilitation Study Report Public Scoping for the gathering and analysis of

More information

GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold

GLOSSARY OF TERMS CHAPTER 11 WORD DEFINITION SOURCE. Leopold CHAPTER 11 GLOSSARY OF TERMS Active Channel The channel that contains the discharge Leopold where channel maintenance is most effective, sediment are actively transported and deposited, and that are capable

More information

Financial Analysis for the Ambleside Centre Zoning Districts

Financial Analysis for the Ambleside Centre Zoning Districts Financial Analysis for the Ambleside Centre Zoning Districts July 2013 Prepared for: The District of West Vancouver By: Coriolis Consulting Corp. Table of Contents 1.0 Introduction... 1 1.1 Purpose...

More information

Transportation Impact Assessment Guidelines

Transportation Impact Assessment Guidelines Transportation Impact Assessment Guidelines Preface The following TIA Guidelines have been developed jointly by the City s Planning and Growth Management and Public Works and Services departments in an

More information

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

City of Auburn Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN

City of Auburn Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN December 21, 2009 Public Works Department 171 N. Ross Street, Suite 200 Auburn,

More information

4.5 TRANSPORTATION - YEAR 2025 TRAFFIC CONDITIONS WITH PROPOSED TIMP 4.5-1 ESTIMATION OF TRIP REDUCTIONS WITH TIMP TRANSIT AND TDM PROGRAMS

4.5 TRANSPORTATION - YEAR 2025 TRAFFIC CONDITIONS WITH PROPOSED TIMP 4.5-1 ESTIMATION OF TRIP REDUCTIONS WITH TIMP TRANSIT AND TDM PROGRAMS Draft Environmental Impact Report State Clearinghouse No. 2002061090 City of LA EIR No. 2003-1922-EIR CPC No. 98-0010 (CPU) 4.5 TRANSPORTATION - YEAR 2025 TRAFFIC CONDITIONS WITH PROPOSED TIMP This chapter

More information

Gold Ray Dam Interagency Technical Team Meeting

Gold Ray Dam Interagency Technical Team Meeting Gold Ray Dam Interagency Technical Team Meeting Agenda Public Outreach, Funding, Monitoring EA/BA/Permit Updates Deconstruction Plans Fish Passage & Salvage Plan Hydraulic Modeling Next Steps Public Outreach,

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Chapter 5: Working with contours

Chapter 5: Working with contours Introduction Contoured topographic maps contain a vast amount of information about the three-dimensional geometry of the land surface and the purpose of this chapter is to consider some of the ways in

More information

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the

More information

APPENDIX G. California Coastal Commission & Conservancy Accessibility Standards

APPENDIX G. California Coastal Commission & Conservancy Accessibility Standards APPENDIX G California Coastal Commission & Conservancy Accessibility Standards STANDARDS AND RECOMMENDATIONS FOR ACCESSWAY LOCATION AND DEVELOPMENT These standards provide guidelines for the location,

More information

HIGHLANDS NEIGHBORHOOD STUDY AREA PARKING ANALYSIS

HIGHLANDS NEIGHBORHOOD STUDY AREA PARKING ANALYSIS HIGHLANDS NEIGHBORHOOD STUDY AREA PARKING ANALYSIS Prepared for: City and County of Denver Department of Public Works, Engineering Division Traffic Engineering Services Parking Operations 201 W. Colfax

More information

SCHNEIDER CREEK REMEDIATION CLASS ENVIRONMENTAL ASSESSMENT ADDENDUM

SCHNEIDER CREEK REMEDIATION CLASS ENVIRONMENTAL ASSESSMENT ADDENDUM SCHNEIDER CREEK REMEDIATION CLASS ENVIRONMENTAL ASSESSMENT ADDENDUM PUBLIC MEETING FEBRUARY 8 TH, 2012 The City of Kitchener and Grand River Conservation Authority (GRCA) are undertaking an Environmental

More information

Development Brief for New Lodge, Bank Mill Lane Berkhamsted. Adopted November 2007

Development Brief for New Lodge, Bank Mill Lane Berkhamsted. Adopted November 2007 Development Brief for New Lodge, Bank Mill Lane Berkhamsted Adopted November 2007 This publication seeks your opinions about the design, layout and requirements for new housing development at New Lodge,

More information

TERMINAL 91 2011 TRAFFIC MONITORING STUDY

TERMINAL 91 2011 TRAFFIC MONITORING STUDY DRAFT TERMINAL 91 2011 TRAFFIC MONITORING STUDY Prepared for: Port of Seattle Prepared by: 6544 NE 61st Street, Seattle, WA 98115 ph: (206) 523-3939 fx: (206) 523-4949 NOVEMBER 4, 2011 TABLE OF CONTENTS

More information

Executive Director s Recommendation Commission Meeting: July 11, 2013

Executive Director s Recommendation Commission Meeting: July 11, 2013 Executive Director s Recommendation Commission Meeting: July 11, 2013 PROJECT Russell Road Widening Phase 2 United States Marine Corps Base Quantico Prince William County, Virginia SUBMITTED BY United

More information

SECTION 2 CORRIDOR A

SECTION 2 CORRIDOR A SECTION 2 CORRIDOR A 2.1 CORRIDOR A (HILLSBOROUGH RIVER TO 40 TH STREET IN TAMPA) The boundaries for Corridor A can be seen in Figure 2-1. They are as follows: North: I-4 South: Crosstown Expressway (now

More information

Optimum proportions for the design of suspension bridge

Optimum proportions for the design of suspension bridge Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering

More information

CITY OF TRAIL MEMORANDUM

CITY OF TRAIL MEMORANDUM 0 C CITY OF TRAIL MEMORANDUM DATE: TO: FROM: SUBJECT: March 24, 2011 FILE NO. 5400-02 DAVID PEREHJJDOFF, CHIEF ADM1NTSTRATIVE OFFICER WARREN PROULX, ENGINEERING TECHMCIAN OLD TRAIL BRIDGE With the interest

More information

Stop The stop sign, a red octagon with white lettering, means come to a full stop and be sure the way is clear before proceeding.

Stop The stop sign, a red octagon with white lettering, means come to a full stop and be sure the way is clear before proceeding. Tr a f f i c S i g n s 7 7. TRAFFIC SIGNS Many collisions and near crashes occur as a result of drivers who ignore or fail to respond appropriately to traffic signs. It is essential that the meaning of

More information

Background Information: The Mamquam River Floodplain Restoration Project

Background Information: The Mamquam River Floodplain Restoration Project Background Information: The Mamquam River Floodplain Restoration Project The Mamquam River Floodplain Restoration project is being undertaken in partnership with the Squamish River Watershed Society, Fisheries

More information

Railway Crossing Information System

Railway Crossing Information System Railway Crossing Information System ITS Canada Presentation June 2, 2014 Ian Steele, P.Eng Agenda Click to edit Master title style RBRC Program Project Background Concept of Operations Design Process Design

More information

Why build the Silvertown Tunnel?

Why build the Silvertown Tunnel? Why build the Silvertown Tunnel? Over the last 30 years east London has changed with the redevelopment of former industrial areas into major commercial and residential districts. The development of Canary

More information

Based on the above, it is recommended that Lift Stations #1 and #3 be abandoned and their flows be diverted to the regional Lift Station #8.

Based on the above, it is recommended that Lift Stations #1 and #3 be abandoned and their flows be diverted to the regional Lift Station #8. Lakeside; Clairmont Heights; Portion of Clairmont currently serviced to Pump Station #2; Crossroads North and Crossroads South portion of flows that are diverted to Lakeside Trunk. It is understood that

More information

DESIGN ASSISTANCE APPLICATION

DESIGN ASSISTANCE APPLICATION DESIGN ASSISTANCE APPLICATION for FY 2016 NEW RIVER MULTI USE PATH: PINNACLE PEAK ROAD TO HAPPY VALLEY ROAD CITY OF PEORIA APPLICATIONS ARE DUE VIA ONLINE SUBMITTAL BY 10:00 AM ON MONDAY, JUNE 29, 2015

More information