ROCHANA TECHNICAL SERVICES L L C METHOD STATEMENT
|
|
- Leslie Campbell
- 7 years ago
- Views:
Transcription
1 Prepared by ROCHANA TECHNICAL METHOD STATEMENT Page No : 1 / 9 Title: METHOD STATEMENT FOR GYPSUM PARTITIONS, LINING AND CEILINGS REVISION STATUS Revision No Date Revision Description Gypsum partitions and lining. SW
2 Page No : 2 / 9 CONTENTS 1. Purpose 2. Principles 3. References 4. Personnel and Responsibilties 5. Method of Construction 6. Codes and Standards related to this section 7. Pre Construction Activities 8. Delivery, Storage and Handling 9. Construction 10. Cleaning & Handing over 11. Temporary works 12. Tolerance for Partition and lining works 13. Inspections 14. MEP conduits, AC duct Openings, Grills etc 15. Materials,Equipment and Plant 16. Manpower to be used 17. Supervision Arrangement 18. Temporary works 19. Health,safety and envioronment requirement 20. Security Arrangement 21. QC Approvals & other documentations 22. Records to be produced 23. Site safety Engineers approval 24. Attachments
3 Page No : 3 / Purpose:- This method statement provides the control sequence and methodology that will be used for the construction of Gypsum Partition, Lining and Ceiling in order to achieve compliance with the Contract Specifications and Drawing. 2.0 Principles:- The principle of this document is to ensure that all methods and stages for the construction of gypsum partition and ceiling is detailed for smoooth progress of the work. This method statement is prepared in general for all types of Gypsum partition, lining and ceiling as detailed on Contract Drawings and approved Shop Drawings encompassing: Materials Construction Inspection & Testing Final Approvals Risk Management 3.0 References:- Contract specifications for gypsum partition and ceiling. All related codes and standards referenced in the Contract specifications. Contract drawings. Approved workshop drawings. Approved MEP builders work drawings. Approved material submittals. Program of works. Project Quality Plan Approved project safety plan and procedures. 4.0 Responsibilities Preparation of Procedure Review of Procedure Review of Procedure Approval Of Procedure Implementation - QA/QC Engineer - Construction Manager - Safety Engineer - Project Director - As described in the procedure The Construction Manager will be responsible for the delegation to designate persons as well as the QA/QC department the responsibility for the inspection and acceptance of any work. 5.0 Method of Construction
4 Page No : 4 / 9 Preliminary Activities/ Approvals 5.1 Submit to the Engineer for approval, samples of the required components and related accessories of the partition framing material, ceiling framing material and different types of gypsum boards and insulation. 5.2 Submit for approval of shop drawings detailing sections of different types of partitions, lining and ceiling with junction details, floor and soffit fixing deatil etc. 5.3 Build sample partition, ceiling and mock ups to a minimum size 3000mmx3000mm and provide a schedule of materials used in the samples/mock up for approval of the Engineer. 5.4 Submit Method Statement, Inspection & Test Plan to the Engineer for approval Prepare and submit for approval Temporary Works shop. Codes and Standards related to this section 6.1 As per specifications 7.0 Pre Construction Activities 7.1 Ensure all required document and material approvals have been obtained. 7.2 Inspect and ascertain conformance of existing base structures and preceding trade works done by others. 7.3 Ensure materials have been obtained from approved suppliers. 7.4 Ensure MEP co ordination function takes place and all relevant personnel are aware of requirements prior to commencing of work in each work zone. 7.5 Ensure work area is clear and safe. 7.6 Ensure all constraints on operations have been identified and precautions are taken. 7.7 Ensure QC and HSE monitoring documents and procedures are established and approved. 7.8 Arrange all necessary personnel, equipment and services as required for the works and ensure adequate water, lighting, power and access arrangements are in place. 7.9 Where further information/ clarification in respect of Contract drawings are required the matter shall be referred to the Engineer by means of a request for information. (RFI) 7.10 Implement Employee induction procedures and Tool Box Talks for ongoing risk assessment and identification of hazards Ensure the structure is not overloaded when materials are distributed within the structure Erect scaffold and access platforms in accordance with approved temporary works documents and safety procedures. 8.0 DELIVERY,STORAGE AND HANDLING Gypsum Partition and lining material (Gypsum boards, insulation and framing components) accompanied by delivery notes, to be delivered to site palletized, and stored in fully enclosed, conditioned space, protected against damage from moisture, humidity, temperature extremes, direct sunlight, surface contamination, and other causes.
5 Page No : 5 / Construction 9.1 Layout marking or setting out A team of surveyors and his gang allocated specifically for layout marking are given an orientation about the site requirement by Site Engineer. This team will carry out layout marking as per approved drawing in concurrence with the schedule of work. The layout would be marked with chalk line on the floor. These lines will get transferred to the slab with the help of Laser/plumb to maintain the verticality of Partition. Once the setting out is completed the end points will be marked with permanent markers. The type of partition as per wall key will be marked alongside the marking, for easy reference. The level and line for setting out would be taken from the authenticated bench mark and grid lines given by the Main Contractor at site. The layout will be cross-checked by Site Supervisor before proceeding with installation. 9.2 Frame work for partitions and lining Top tracks will be fixed onto the soffit as per the particular wall type. The tracks will be fixed securely with wall plug & self taping screws, at a maximum spacing of 600mm centre in staggered manner. The floor tracks will also be fixed in the same manner with same hardware. The studs will be installed as per approved shop drawing between the top and bottom tracks. The frame work will be inspected by ROCHANA TECHNICAL SERVICES supervisor and Site Engineer against shop drawing details and discrepancy, if any will be rectified prior to proceeding further. Frame work for ceilings All hangers are fixed to the soffit of slab with the help of anchor nails at a maximum spacing of 1200 mm centre to centre. After hangers are fixed then the wall angles are fixed to the walls at the perimeter of ceiling area.then the main channels are fixed to these hangers also at a maximu spacing of 1200 mm centre to centre with the help of channel screws. After fixing main channels then the furring channels (Hat Sections) are fixed to the bottom of main channels in perpendicular direction at a maximum spacing of 600 mm centre to centre with the help of channel screws. The frame work will be inspected by ROCHANA TECHNICAL SERVICES supervisor and Site Engineer against shop drawing details and discrepancy, if any will be rectified prior to proceeding further. 9.3 Boarding for partitions After the inspection of frame work by ROCHANA TECHNICAL SERVICES Site Engineer, one side boarding will be done. Boards will be installed along the stud direction with plaster board screws at 3000mm C/C distance in the middle and 200 mm c/c at ends. The screw heads will be driven 2-3mm from the external face to allow for the filling of screw heads. After frame work and one side boarding is done, an inspection request (IR) will be raised to get frame work approval & MEP clearance. The other side boarding will be commenced only Upon receipt of written approval for framework & MEP Clearance. Boarding for ceilings After receiving approval from contractor/consultant for framing and the clearance from MEP contractor to board then the boarding will be done. Boards will be installed with plaster board screws at 300mm C/C distance in the middle and 200 mm c/c at ends. The screw heads will be driven 2-3mm from the external face to allow for the filling of screw heads.
6 Page No : 6 / Insulation:- The approved insulation material will be inserted inside the partition as per the wall key reference. Adhesive/pin will be used to hold the insulation from slipping off from its position. 9.5 Door / Window openings: 10.0 For doors and window openings, as per the approved drawing and door opening schedule, frame work would be done as shown in the shop drawing details. Particular attention would be given for squareness of openings. 9.6 Taping & Jointing: The following coat will be applied over the board joints: a) First coat/jointing coat b) Second coat c) Third coat First coat is the initial jointing process where the joint tape is fixed over the thin jointing compound applied over the joints. Another layer of jointing compound application would be done over the tape. This would be approximately 100mm wide. Screw heads also will be covered by the application of the joint compound. Second and third coats will be applied successively after having dried each previous coats, feathered 50mm beyond the limits of previous coats. This would be sanded smooth, after drying to receive decoration. Cleaning & Handing Over When all the activities are completed, the area will be thoroughly cleaned. The area will then inspected by ROCHANA TECHNICAL SERVICES Site Engineer. An inspection request will be raised (IR) to facilitate Main Contractor s & Consultant s inspection Temporary Works 11.1 Temporary works will be only Working platform and scaffolds Tolerance for Partition and ceiling works 12.1 Tolerance to partition and ceiling works shall be as per specification Sudden Irregularities: Not permitted 12.3 Joint Deviations: Measure ftrom faces of adjacent boards with straight edges (450 mm long with feet pads) to BS 8212, clause Tapered edge Joints: Permissible deviation maximum 3 mm with feet resting on boards External Angles: Permissible deviation 4mm for both faces 12.6 Internal Angles: Permissible deviation 5mm for both faces 13.0 Inspections 13.1 Stage 1 inspection will be done when the framing of partition is done and one side boarding is completed, ready for MEP to satrt their works Stage 2 and inspection will be done when the MEP have completed their part of the works and the insulation is fixed and the partition is ready to receive the second side boarding. The inspection of the MEP services will be raised by the MEP subcontractor.
7 Page No : 7 / Stage 3 and final inspection is done after the partition is boarded and the joints treated to receive the skim coat/following trade works Extent of area for one inspection may be divided into floor or zone or one typical apartment/typical floor MEP conduits, AC duct Openings, Grills etc Openings required for MEP services penetrations will be incorporated as per the site MEP works executed Partition will be handed over to MEP contractor for conduit marking,fixing of box outs etc after first side boarding is done to the parttion Materials,Equipment and Plant 15.1 Materials to be used mm regular gypsum boards mm wide studs for 100 mm wide gypsum dry wall and 70 mm wide studs for 120 mm wide gypsum dry wall mm wide tracks for 100 mm wide gypsum dry wall and 72 mm wide tracks for 120 mm wide gypsum dry wall x23x0.5mm thick wall angle for hangers and perimeter angle to ceilings x0.5 mm thick main channel for ceilings Furring channel for ceilings Insulation- 14 Kg/m3, 50 mm thick Glass wool for partitions Joint Compound Self Tapping Screw & fissure Plug Fibre Tape Corner Tape Channel Screw 12.5mm Gypsum Screw 25mm 15.2 Equipment & Tools Screw Machine Drill Machine Carpenter s Saw Hand Cutter Chalk Line Hacksaw Frame set Plumb Measuring Tape Spirit level Scrapper Scrapper Scrapper 24
8 Page No : 8 / Manpower to be used a. Engineering Staff : The Engineering and Supervisory personnel allocated for PARTITION WORK work will be as follows - 4 Engineer - 4 Foreman - 12 Chargehand - 1 Safety Officer - 1 QA/QC 17.0 Supervision arrangement 17.1 Supervision arrangement will be lead by Site Enginner who will be assisted by Foreman and Charge hands Surveyor will be responsible for setting out from the main grid lines issued by the main contractor MEP requirement will be co-ordinated with MEP Contractor by MEP Co-ordinator Temporary works 18.1 Temporary works includes Scaffolding with working platforms,toe board etc Double Volume areas to be staged by main contractor and certified by the main contractor safety Health, safety and envioronment requirement 19.1 Workers will adhere to proper PPE during the work All tools will be checked for safe performance and maintenance records 19.3 Site house keeping will be maintained properly. All construction debris shall be taken off the work spot/floor and disposed through the chutes availed in every floor by main contractor Security arrangement 20.1 Ingress of unauthorised people to the site will be controlled by site gate keepers on both entrance to the site by main contractor QC Approvals and other documents used at site Approved Project Specific Quality Plan 21.2 Project HSE Plan 21.3 All necessary drawings shall be approved 21.4 All relevant material approval shall be obtained Inspection request shall be raised for stage 1 inspection and Stage 3 inspection MEP subcontractor shall raise stage 2 inspection Records to be produced 22.1 Records mentioned as below are to be produced 22.1 Work Notification
9 Page No : 9 / Inspection and approval Check sheet 22.4 Clearance sheets from MEP/CIVIL trades approved by main contractor Site Safety Engineers approval Approved Approved subject to following : Not Approved : Reasons : 24.0 Attachments 24.1 Risk Assessment
NATIONAL INSTITUTE OF BIOLOGICALS
Short Term Notice Inviting Quotations Quotations No. S.1-36/07/NIB/Engg. (Civil) Invitation to short term quotations for Repairing of damaged gypsum board false ceiling and painting with epoxy paint in
More informationMETHOD STATEMENT FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER
Page 1 of 6 FOR INSTALLATION OF CABLE TRAY/TRUNKING/LADDER 0 Issued for Review & Comments Rev. Date Description Eng. A.H Prepared by Checked by Approved by Page 2 of 6 REVISION CONTROL SHEET REV. NO. DATE
More informationPANELIZED HOME INSTALLATION GUIDELINE
PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.
More informationCEILING SYSTEMS. Between us, ideas become reality. Installing. Suspended Ceilings. North America Version
CEILING SYSTEMS Between us, ideas become reality Installing Suspended Ceilings North America Version 1 Installing Armstrong Suspended Ceilings An Armstrong suspended mineral fiber ceiling is functional,
More informationPART 1 GENERAL 1.1 SECTION INCLUDES
J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including
More informationVA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD
SECTION 09 29 00 GYPSUM BOARD PART 1 - GENERAL 1.1 DESCRIPTION This section specifies installation and finishing of gypsum board, vapor retarder and air and moisture barrrier. 1.2 RELATED WORK A. Installation
More informationHOW TO INSTALL A BEAUTIFUL NEW KITCHEN
HOW TO INSTALL A BEAUTIFUL NEW KITCHEN Easy to follow step-by-step kitchen cabinet installation TOOL AND MATERIAL LIST Hammer Pry bar Screwdriver Phillips Flathead Level Tape measure Pencil Straight edge
More informationEucaboard / Eucaplac/ Eucatile paneling is intended for dry interior use only and requires care in handling.
i This instruction sheet describes the proper methods for installing Eucatex decorative wall paneling. Eucaboard / Eucaplac/ Eucatile paneling is intended for dry interior use only and requires care in
More informationINSTALLATION RECOMMENDATIONS. Outdoor Rubber Tiles
INSTALLATION RECOMMENDATIONS Outdoor Rubber Tiles Prior to Installation: The Outdoor Rubber Tiles and accessory transition pieces intended for this installation have been shipped to you via a freight carrier
More informationSECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront
PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system
More informationManual lifting and handling
Manual lifting and handling When installing British Gypsum products and systems care should be taken to ensure that appropriate methods of handling and lifting are adopted. The following guidance details
More informationAsbestos Abatement Work Plan for the Carter Carburetor Superfund Site
for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project
More informationWindow Installation Instructions
Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for
More informationRACQUETBALL, HANDBALL OR SQUASH COURTS AND GYMNASIUM WALL SURFACES
1807 Elmwood Avenue, Suite 275 Buffalo, New York 14207 (800) 543-5155 RACQUETBALL, HANDBALL OR SQUASH COURTS AND GYMNASIUM WALL SURFACES Fiberesin Wall System Provide materials and labor to complete courts
More informationFireWall. High performance fireresistant. FireWall. www.british-gypsum.com
FireWall FireWall High performance fireresistant wall system FireWall is a non-loadbearing wall which provides up to 240 minutes fire resistance. It is used in certain ground floor basement situations
More informationHow To Level A Subfloor
Skill Level: INTERMEDIATE Give these projects a try if you're a confident DIYer with a good working knowledge of a variety of tools. They can take a day or more to complete. If you can build a birdhouse
More informationDE Frame with C Series Sidelight
TOOLS REQUIRED Tape measure 6' magnetic level 3' magnetic level Screw gun with clutch adjusted #2 phillips tip #3 phillips tip Screwdriver (used to adjust frame on will using oval slots) Pry Bar Powder
More informationSITE SPECIFIC FALL PROTECTION PLAN
1 THIS PLAN IS SPECIFIC TO: PROJECT & ADDRESS 1.1 THIS PLAN IS SPECIFIC TO THE FOLLOWING AREA(S) ON SITE: Parkade level: Typical level: Other: Between G/L: 1.2 THIS PLAN IS APPLICABLE TO THE FOLLOWING
More informationGYPSUM AREA SEPARATION FIREWALLS GA-620-2011
GYPSUM AREA SEPARATION FIREWALLS GA-620-2011 GA-620-2011 Copyright 2011 Gypsum Association All rights reserved. Printed in U.S.A. Characteristics, properties, or performance of materials or systems herein
More informationGuide Specifications for Maple Flooring Systems
Guide Specifications for Maple Flooring Systems MFMA Guide Specification for Resilient Pre-Engineered Fixed Panel System Purpose This Guide Specification is designed to assist in the production of actual
More informationEnergy Company Obligation (ECO): Technical Monitoring Questions
Energy Company Obligation (ECO) Technical Monitoring Questions v1 30/05/2013 Energy Company Obligation (ECO): Technical Monitoring Questions Under ECO suppliers are required to instruct suitably qualified
More informationPlease calculate with around 5% more square meters than needed because you will have material loss due to cutting and sorting.
1. TEKA Soft Loc Installation Guide Thank you for having chosen TEKA Parquet. To guarantee a constant quality product TEKA engineered hardwood flooring is made out of selected wood species and runs only
More informationH-Stud Area Separation Wall System
12 TH EDITION 09 21 16.33/NGC H-Stud Area Separation Wall System 09 21 16.33 139 H-STUD AREA SEPARATION WALL SYSTEM The fire-protection of gypsum-based Area Separation Walls is demonstrated in dramatic
More informationRESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS
RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS The following guidelines are intended to assist with the permit acquisition process with regard to Plumbing Alterations. Not all information, or additional
More informationfirst look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel
first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders
More informationHanson Building Products. precast basement solutions
Hanson Building Products precast basement solutions Hanson Building Products Basement Systems Add an extra dimension and combine the inherent flexible, structural and waterproof properties of concrete
More informationWASHROOM UPGRADE SIR CHARLES TUPPER BUILDING 2250 RIVERSIDE DRIVE, OTTAWA, ON SIR CHARLES TUPPER BUILDING A0.0 COVER SHEET / DRAWING LIST
0 RIVERSIDE DRIVE, OTTAWA, ON A0.0 COVER SHEET / DRAWING LIST A0. LEGEND AND GENERAL NOTES A0. GENERAL NOTES A0. GENERAL NOTES A0. TYPICAL WASHROOM WALL/SINK SECTION A0. DETAIL - CONTROL JOINT A0. DETAIL
More informationGuidelines for Earthquake Bracing of Residential Water Heaters
Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)
More informationSECTION 11 78 13 MORTUARY REFRIGERATORS
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 11 78 13 MORTUARY REFRIGERATORS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in
More informationComposite Stone Veneer
Composite Stone Veneer Installation Guide Ver 1 Jun 2015 www.compstone.com Composite Stone Veneer Installation Guide Contents Introduction & Overview 3 Required Tools 4 Optional Tools 4 Attachment Guidelines:
More informationCertainTeed. Shaftliner For A rea Separation Firewalls
CertainTeed Shaftliner For A rea Separation Firewalls M2Tech Shaftliner Type X for Area Separation M2Tech Shaftliner is a specially formulated product for applications where enhanced mold resistance is
More informationINSTRUCTION FOR ASSEMBLY. 150x180 v Traditional sauna cabin
INSTRUCTION FOR ASSEMBLY 150x180 v Traditional sauna cabin 1. SAUNA PLAN 1800 LIGHT UNDER THE BENCH VENTILATION OUTLET UPPER BENCH 600 1500 LOWER BENCH 400 700 1656 956 HEATER 366 381 690 815 Light switch
More informationDUCT CLEANLINESS FOR NEW CONSTRUCTION GUIDELINES
DUCT CLEANLINESS FOR NEW CONSTRUCTION GUIDELINES Sheet Metal and Air Conditioning Contractors National Association, Inc. 4201 Lafayette Center Drive Chantilly, VA 20151-1209 DUCT CLEANLINESS FOR NEW CONSTRUCTION
More informationGigaCrete Specification PlasterMax
GigaCrete Inc. 6775 Speedway Blvd. Suite M105 Las Vegas, NV 89115 Ph (702) 643-6363 Fax (702) 643 1453 www.gigacrete.com GigaCrete Specification PlasterMax PlasterMax : Fire Rated Plaster for Direct Application
More informationGuidelines for Earthquake Bracing Residential Water Heaters
Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the
More informationMarch 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
More informationPatio Covers / Carports
Patio Covers / Carports Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
More informationHVAC Vents & Diffusers
2 HVAC Vents & Diffusers Drywall, Stone, & Wood Applications TRUFIG can be installed in a variety of finishes and surfaces. This guide will detail the install of HVAC vents and diffusers in drywall, stone,
More informationINSTALLATION INSTRUCTIONS for Bifold Doors (JII103)
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for premium composite, hollow and solid core molded Bifold Doors. Bifolds are designed for fast
More informationDesign and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities
At Macau International Airport (RFQ-198) Section 6 Bill of Quantities Bill Nr. 1 Preliminaries Bill Nr. 1 PRELIMINARIES NOTES : (1) The work shall be done during day time and night time according to CAM/ADA
More informationActive and Passive Sash Replacement
for Andersen Gliding Windows Read all instructions carefully before attempting this procedure. If you have any questions about your ability to complete the procedure, call Andersen at 1-888-888-7020 for
More informationInstallation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details
D Installation Details D1 General D2 Walls D3 Ceilings D4 Reference D Installation Details D Contents D1 General Installation and Fastening Sequence for Steel Studs D1.1 Fastener Selection D1.3 D2 Walls
More informationKnauf Aquapanel Interior. Tile Backing. Cement board for wet areas. Will not deteriorate in water. Easy to score and snap
Tile Backing Will not deteriorate in water Easy to score and snap Resistant to mould and mildew Knauf Aquapanel Interior Cement board for wet areas Knauf Aquapanel Interior Cement Board Drywall for Wet
More informationELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1
KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1
More informationCITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT
Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide
More informationTechnical Services. Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking)
INSTALLATION INSTRUCTIONS FOR GTI CONNECT TILES This document refers to the following products: Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking) 635 X 635 mm 25.5 x 25.5
More informationHerringbone Pattern Flooring
Herringbone Pattern Flooring If it s not marked NOFMA, it s not certified. Handling, Storage, Installation and Tips Herringbone is generally manufactured from 3/4 x 2 ¼ or ¾ x 1-1/2 standard tongue & groove
More informationCanvas Office Landscape Wall Strip Installation and Disassembly for Recycling Instructions
Y Parts Included: Canvas Office Landscape Wall Strip Installation and Disassembly for Recycling Instructions Tools Required: Power Driver Drill Bit (Determined by fastener) Driver Bit (Determined by fastener)
More informationNEW ELECTRICAL SUBSTATION Building 300 SECTION 07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK
ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within
More informationSTANDARD OPEN PATIO COVER
STANDARD OPEN PATIO COVER BUILDING & SAFETY DIVISION 201 E. LA HABRA BLVD. LA HABRA, CA 90631 62-90-9710 Call Before You Dig 1-800-227-2600 PLEASE NOTE: This information Bulletin is made available to assist
More informationIMPORTANT INSTALLATION GUIDE VALENCIA SQUARE CORNER SHOWER READ ALL INSTRUCTIONS CAREFULLY BEFORE STARTING THE INSTALLATION
INSTALLATION GUIDE VALENCIA SQUARE CORNER SHOWER SEALANT REQUIRED TO COMPLETE THIS INSTALLATION: (Not supplied) Sika Sikasil NG (Arctic White) To seal the WHITE shower door and returns to the shower tray.
More informationCITY OF SELMA, TEXAS Inspection Checklist: Commercial
Rev Y71004 The Permits and Inspections Department welcomes you to the City of Selma. The following information is provided to you as guidance through the inspection process. The City of Selma provides
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More informationSchlüter -KERDI-BOARD Substrate, structural panel, bonded waterproofing
Substrate, structural panel, bonded waterproofing The universal substrate for tiles Perfect covering No matter whether you work with mosaics or large format tiles, an absolutely level substrate with straight
More informationBest Barns USA Assembly Book
Best Barns USA Assembly Book Revised November 27, 2013 the Easton - R 12'x 20' Manufactured by Reynolds Building Systems, Inc. 205 Arlington Drive Greenville, PA 16125 724-646-3775 This manual is copyrighted.
More informationInstallation Instructions
Installation Instructions 1. Position the unit onto bridging packers. These keep the unit away from any water sitting inside the frame. 2. Centralise the unit within the frame and pack the edges with appropriate
More informationwww.suttonhousingpartnership.org.uk Asbestos
www.suttonhousingpartnership.org.uk Asbestos images courtesy of www.sxc.hu and/or www.morguefile.com Asbestos Asbestos was widely used until the 1980 s to improve the performance of materials and to provide
More informationFREEPHONE: 0800 059 9112 EMAIL: admin@a1demolitionukltd.com. Asbestos Awareness. Toolbox Talk
FREEPHONE: 0800 059 9112 EMAIL: admin@a1demolitionukltd.com Asbestos Awareness Toolbox Talk ASBESTOS AWARENESS Why is it a Problem Asbestos was extensively used as a building material in the UK from the
More informationStandard from CSI Part Section Format. 06212 For Wood Framing 05160 For Metal Framing 09226 For Gypsum Sheathing
Standard from CSI Part Section Format. 06212 For Wood Framing 05160 For Metal Framing 09226 For Gypsum Sheathing Specifications for SURE-BOARD Series 200 and 200W Panel for shear PART 1.0 GENERAL 1.01
More informationPolicy for the Management of Asbestos in Buildings
in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably
More information7. Installation. installation 7.1.1. CAST-IN WINDOW SYSTEM 7.1. INSTALLATION OF WINDOW MAIN FRAME
7. Installation Window involves the fixing of window frame at an earlier construction stage and subsequent of the window sashes. This is a highly workmanship dependent process. Only trained and approved
More informationINSTALLATION INSTRUCTIONS for Vinyl Windows without Nailing Fin (JII011) ImPOrTANT INFOrmATION & GlOssAry. rough OPeNINGs
Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for vinyl windows without a nailing fin (including finless, flush fin and flange). Read these instructions
More information12.1 Schlüter -KERDI-BOARD
I n n o v a t i v e p r o f i l e s 12.1 Schlüter -KERDI-BOARD S u b s t r a t e U N I V E R S A L S T R U C T U R A L P A N E L, B O N D E D W A T E R P R O O F I N G Application and Function Schlüter
More informationDIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP
DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP CONTENTS WHAT IS RISING DAMP STEP 1 SURVEY STEP 2 METER READINGS STEP 3 CONCLUSION STEP 4 PREPARATION FOR TREATMENT STEP 5 TYPE OF TREATMENT STEP 6
More informationBuilt to Last. Built for Beauty. Good. Solid. Logix. TM
Built to Last. Built for Beauty. Good. Solid. Logix. TM Quality, Value and Service Introducing LOGIX Insulated Concrete Forms. Based on the simple concept of interlocking blocks, LOGIX ICF gives you a
More informationFinishing guide. For Thistle plaster and Gyproc plasterboard. Telephone: 08705 456123 Fax: 08705 456356 Email: bgtechnical.enquiries@bpb.
BUSINESS SUPERBRAND SINCE 008 Gyproc, Thistle, Gypframe and Glasroc are all registered trade names of BPB United Kingdom Limited. Isover is a registered trade name of Saint-Gobain. Proprietor: BPB United
More informationRooflight INSTALLATION INSTRUCTIONS
INSTALLATION INSTRUCTIONS Rooflight These instructions should be used for: Installing Permanent Trickle Ventilation: Constructing & Waterproofing a Timber Upstand Curb: Installing & Waterproofing Proprietary
More informationDivision 9. SignaFlor Pad and Pour Flooring System
Division 9 SignaFlor Pad and Pour Flooring System SPECIFICATIONS Page 1. General... 2 1.1 Description 2 1.2 Quality Assurance 2 1.3 Submittals 2 1.4 Delivery and Storage 3 1.5 Warranty 3 1.6 Working Conditions
More informationAsbestos Management Program
Asbestos Management Program Facilities and Operations Revision #4: February 17, 2012 Page IMPORTANT Asbestos related incidents must be reported IMMEDIATELY to your supervisor Emergency Contacts During
More informationSECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)
SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2
More informationCOMPANY ESTIMATOR BID DAY PHONE NO.
COMPANY ESTIMATOR BID DAY PHONE NO. Work Package: Structural Steel Fabrication & Erection The work in each bid package shall include but shall not be limited to all labor, burden, fringe benefits, materials,
More informationLAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
More informationUFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.20 (April 2006) Change 2-11/14 ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-02362 (August 2004) UNIFIED FACILITIES
More informationK. D. FRAME ASSEMBLY FOR CLOSED STEEL STUD WALLS...Ins 10. FRAME INSTALLATION DETAILS FOR CLOSED STEEL STUD WALLS...Ins 11
K. D. FRAME ASSEMBLY FOR MASONRY WALLS...........................Ins 2 FRAME INSTALLATION DETAILS FOR MASONRY WALLS......................Ins 3 INSTALLING EXISTING MASONRY WALL ANCHORS IN FRAME..................Ins
More informationCode of Standard Practice for Timber Frame Structures
TFEC 2-2013 Code of Standard Practice for Timber Frame Structures August 2013 Preface This Code is intended to represent a reasonable consensus of what constitutes ordinary and acceptable practice within
More informationTHIRD PARTY INSPECTION GUIDELINES FOR OWNERS AND GENERAL CONTRACTORS/CONSTRUCTION MANAGERS DS150
THIRD PARTY INSPECTION GUIDELINES FOR OWNERS AND GENERAL CONTRACTORS/CONSTRUCTION MANAGERS DS150 SECTION ONE A. Objective The objective of this guide is to provide Owners and General Contractors/Construction
More informationServices Enclosures and Protected Shafts - Maintaining Compartmentation
Introduction When a fire resisting element is used to provide fire compartmentation, every opening that allows services to pass through the element must be adequately protected by sealing, or fire stopping
More informationCONTROL METHODS. There are five ways to control the release of asbestos fibers:
Control Methods CONTROL METHODS When asbestos containing materials are found in a building, the owner must decide which method or methods will be used to deal with the asbestos. The decision will be based
More informationCeilings without fi ller. VoglFuge / VoglJoint. Acoustic design ceilings
Technical information VoglFuge / VoglJoint Ceilings without fi ller With air purification as standard Create perfect acoustic designer ceilings with the VoglFuge / VoglJoint system Perforation patterns
More informationINSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
More informationConstruction. SikaProof A-08 Edge, A-12 Edge. Fully bonded FPO sheet membrane in L-shape for the SikaProof A waterproofing system. Product Description
Product Data Sheet Edition 15/10/2014 Identification no: 02 07 04 10 300 0 000002 SikaProof A Edge SikaProof A-08 Edge, A-12 Edge Fully bonded FPO sheet membrane in L-shape for the SikaProof A waterproofing
More informationFIRESTOPPING & SMOKE SEALS
SPECIFICATION SECTION 07 84 00 FIRESTOPPING & SMOKE SEALS 1 GENERAL 1.1 SECTION INCLUDES 1.1.1 Comply with Division 1, General Requirements and Documents referred to therein. 1.1.2 It is the intent of
More informationSchluter -KERDI-BOARD Substrate, building panel, bonded waterproofing
Schluter -KERDI-BOARD Substrate, building panel, bonded waterproofing Schluter -KERDI-BOARD The universal substrate for tiles Flat. Level. Plumb. Square. No matter the quality, cost, or extravagance of
More informationBENTLEY ELEMENTS COLLECTION LVT
This document refers to the following products: Product Size Installation direction Seams treatment Elements Tiles See specifications 90 None Elements Planks See specifications Stair Step None Note: This
More informationThese instructions will show you how to install an internal door into a non-loadbearing partition wall. The instructions are split into three parts.
No 8 in the series of 'How to' brochures produced by PlaceMakers, New Zealand How to Frame and Hang a Door These instructions will show you how to install an internal door into a non-loadbearing partition
More informationHow to Install Hardwood Flooring Over a Sub Floor
How to Install Hardwood Flooring Over a Sub Floor Installation Preparation Instructions Read the entire instructions before starting your project. 1) INSPECT EACH PLANK (see fig. a) Wood is a natural product
More informationDucoterra Radiant Heating Panel Installation Manual
Ducoterra Radiant Heating Panel Installation Manual 1. Introduction Your new radiant heating panels are designed to heat living and working spaces rapidly and efficiently by radiant heating. Like the sun,
More informationKITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS
St. Louis County Department of Public Works Division of Code Enforcement KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS This guideline is intended to provide the homeowner/contractor with the
More informationnecessary for years of satisfactory service. SmartBlock insulating form concrete walls share the
Chapter 7 PLUMBING AND ELECTRICAL 7.1 Introduction to Plumbing and Electrical Consideration of support services such as plumbing and electrical systems from the preliminary schematics phase through final
More informationSash Replacement Guide
for Andersen 200/400 Series Awning Windows Read all instructions carefully before attempting this procedure. If you have any questions about your ability to complete this procedure, call Andersen at 1-888-888-7020
More informationPackaged Terminal Air Conditioner Wall Sleeve Installation
Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation
More informationIN00378 (rev A) Corner Entry
IN00378 (rev A) Corner Entry Before You Start Check that the tray has been installed correctly and that it is level (Fig. A), tiled down onto and sealed to the manufacturer s guidelines. Please Note: All
More informationREDI-EXIT COMMERCIAL FIRE DOOR AND EXTERIOR DOOR KITS INSTALLATION GUIDELINES
REDI-EXIT COMMERCIAL FIRE DOOR AND EXTERIOR DOOR KITS INSTALLATION GUIDELINES Tools Required Tape Measure Hammer Slotted Screw Driver #2 & #3 Philips Screw Driver 3-4 Foot Level 12 Pry Bar Cold Chisel
More informationCORNER FRIDGE REFRIGERATION UNIT INSTALLATION AND OPERATION INSTRUCTIONS
CORNER FRIDGE REFRIGERATION UNIT INSTALLATION AND OPERATION INSTRUCTIONS D E F Y I N G C O N V E N T I O N Congratulations on your new Corner Fridge Your new corner fridge may have different functions
More informationA. Work on this project shall consist of, but is not limited to, the following:
PART 1 - GENERAL CLEANING AND RESTORATION OF SECTION 05900-1 1.1 SUMMARY A. Work on this project shall consist of, but is not limited to, the following: 1. Clean and treat all exposed anodized architectural
More informationAll work shall comply with applicable codes and ordinances. Work shall comply with the BOCA National Plumbing Code, latest edition.
DIVISION 15 MECHANICAL SECTION 15100 - PLUMBING PART 1 - GENERAL SCOPE Plumbing work includes all domestic water, gas, and sanitary sewer systems as shown on plans. Also all fixtures and equipment which
More informationWet Area Construction. Carpentry - Residential Construction. Product Code: 5603
E PL SA M Wet Area Construction Carpentry - Residential Construction Product Code: 5603 Publishing details: Second Edition 2012 TAFE NSW Training and Education Support, Industry Skills Unit Orange and
More informationNCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
More informationSECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
More information