1 How to Estimate and Bid Design Build Projects September 13, 2016

2 Agenda Description of Central 70 Project Who are Kiewit-Meridiam Partners Description and benefits of the Design-Build Delivery Method Guiding principles, tools and processes for estimating Group exercise - mock estimate/bid Bid results Bidding strategies and philosophies Design Management / Review Process KMP process moving forward 2

3 Description of Central 70 Project 3

4 Central 70 Project Restripe Lowered Section Full Reconstruct Widening w/ mill and overlay O&M Limits Beyond Construction I-25 to Brighton ~1.25 Miles Brighton to Colorado ~1.5 Miles Colorado to Quebec ~2 Miles Quebec to Chambers ~5 Miles Chambers to Tower ~2.2 Miles 4

5 Who are Kiewit-Meridiam Partners 5

6 Team Organization Project Agreement Developer Equity Members 60% 40% DB Contract O&M Contract Self-Perform Lead Contractor Interface Agreement Lead Operator Life cycle responsibilities Design Contract Lead Engineer Design Sub 6

7 Who is meridiam? Meridiam: A global investor and asset manager Has a business model built exclusively on equity financing of projects Meridiam develops, finances, builds and manages various types of projects: Transport infrastructure Social infrastructure Public buildings Utility networks and services 7

8 Who are PB, Jacobs and Jorgensen 8

9 Who is Kiewit? One of North America s largest and most admired engineering and construction companies Consistently among the top 10 of Engineering News-Record s Top 400 Contractors FORTUNE 500 company with revenues over $9 billion 9

10 International Presence but Locally Centered Central District Heavy Civil Mass grading Drainage Bridge construction Paving Rail Current Local Projects I-225 Rail Line Denver VA Medical Center US 34 Permanent Repairs WISE Water Treatment RiNo IC Contract Kiewit Building Group Commercial Buildings Medical Office Buildings Special Use Facilities Higher Education Office Current Local Projects I-225 Rail Line Denver VA Medical Center Olde Town Transit Hub SCL Hospital Aurora SCL Hospital Northglenn UCCS Mass Electric Transit /Light Rail Signal, overhead contact systems (catenary) Traction power Communications systems Current Local Projects I-225 Light Rail RTD On Call Services 10

11 Description and Benefits of the Design- Build Delivery Method 11

12 Why Do a Workshop? Market is trending towards Design-Build Project Delivery Method 87% of Kiewit s current backlog of work are Design- Build Projects We need subs/suppliers to work with us on these projects We want to provide training to help small subcontractors build capacity to become more competitive We have received feedback that subs/suppliers are not comfortable with Design-Build estimating Goal - Understand the Design-Build estimating and bid process 12

13 What is a DBFOM? Overview DBFOM: Design Build Finance Operate and Maintain CDOT maintains ownership of the Project All aspects of procurement are transferred to the private sector During Construction, the Developer is paid milestone payments for a portion of construction costs Over the remaining life of the Project, the Developer is paid performance payments (i.e. fixed yearly fee) 13

14 What is a DBFOM? Benefits Single point of procurement Budget certainty for the State: CDOT knows exactly how much the payments are for the life of the Project Workforce Opportunities: The Developer will utilize many services from local businesses and provides hundreds of jobs over the 30 year term Cost Certainty: The Developer has increased responsibilities for design, construction, maintenance, and rehabilitation limiting the risk of cost overrun 14

15 Team Organization Project Agreement Developer Equity Members 60% 40% DB Contract O&M Contract Self-Perform Lead Contractor Interface Agreement Lead Operator Life cycle responsibilities Design Contract Lead Engineer Design Sub 15

16 Types of Project Delivery Methods - DBB Traditional - Design Bid Build Separate design and construction firms Projects are fully designed before released for bid Bids are on known scope of work Construction schedule already determined 16

17 Types of Project Delivery Methods DB Design-Build Design-Build: a single entity is responsible for both designing and building the project Projects are designed to initial levels usually 30% Bids are made on projected design Construction schedule determined as design is developed 17

18 Why Do Owners Use Design Build? Traditional Design- Bid-Build Benefits Orderly progression of work Multiple, competitive procurements Substantial design control by Owner Risk/Disadvantage Increased project delivery time Final total cost uncertainty Multiple contracts managed by Owner Design- Build Faster completion schedule Project risks assumed by designbuilder Innovation through designer / constructor cooperation Cost savings - constructability and value engineering Improved Quality and Project Performance schedule and budget 18 Limited design control by Owner Fixed project definition early

19 Guiding Principles, Tools and Processes for Estimating 19

20 Design-Build Estimate Tools / Processes Know what you are estimating Have the plans and a clear understanding of the scope Have your estimating data ready Direct labor costs / labor escalation Staff / overhead / office storage Insurance / contingency / bonding Material pricing / escalation / sales tax Risk analysis Equipment pricing / taxes Fuel / taxes Other subcontractors 20

21 Group Exercise 21

22 Estimating / Bid Exercise Estimating Wall at 30% Design As a team develop estimate Drawings and takeoffs provided Pre-Bid Meeting after 15 minutes Use provided sample estimating reference information Submit Bid in 55 minutes! 22

23 Estimating / Bid Exercise 23

24 Bid Results 24

25 RFC Drawing Review / Estimate Review What additional/different questions would you have asked at the pre-bid conference? Did you miss something? Did you include items you did not need? Did you include the appropriate amounts for Contingency Escalation Profit 25

26 Bidding Strategies and Philosophies 26

27 Bidding Strategies / Philosophies Bid from accurate past costs Best value vs. low price Risk sharing Escalation tied to applicable indexes Early procurement of materials or equipment Knowing the market How much fee to apply How many other bidders there are Who is your competition Bring your Resume sell yourself Safety record Quality program Schedule performance history Tenure of team Level of commitment to job 27

28 Design Management / Review Process 28

29 Design Management / Review Process Post Bid Design review process Constructability reviews Attend pre-bid meetings and open houses Attend task force meetings with Designer+Owner+City+GC Provide input that will facilitate your work Provide comments on drawings and specification progress packages at 60% and 90% Review quantity takeoff of drawings to ensure design growth is controlled Review specified products to ensure you budgeted for them Provide pricing for change orders 29

30 KMP process moving forward 30

31 CDOT s Current Project Schedule Fourth Draft RFP, October 2016 ROD, January 2017 Final RFP, March 2017 Technical Proposal Due, May 2017 Financial Proposals Due, July

32 KMP s Projected Timeline 32

Getting Connected with the Colorado Department of Transportation (CDOT)

Getting Connected with the Colorado Department of Transportation (CDOT) Getting Connected with the Colorado Department of Transportation (CDOT) INTRODUCTION Who is CDOT? CDOT is responsible for 9,146 miles of highway including 3,447 bridges State government agency with funding

More information

Construction Delivery Methods for Texas school districts

Construction Delivery Methods for Texas school districts Construction Delivery Methods for Texas school districts Pfluger Associates Architects, P.L.L.C. ARCHITECTS / PLANNING CONSULTANTS History Prior to 1995, public school districts were required to utilize

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing.

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing. COLORADO DEPARTMENT OF TRANSPORTATION CONTRACTOR PREQUALIFICATION STATEMENT (EXPERIENCE, EQUIPMENT AND FINANCIAL) Return to: Contracts & Market Analysis Prequalification Unit 4201 E. Arkansas,4th Floor

More information

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Approved March 23, 2011 Purpose: While the traditional Design-Bid-Build

More information

Claret Consulting 18 December 2015

Claret Consulting 18 December 2015 The Denver-based Regional Transport District (RTD) 2004 FasTracks program is a multi-billion dollar regional transportation expansion plan that was designed to meet the Denver metro area s infrastructural

More information

INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS

INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS INTRODUCTION TO PUBLIC-PRIVATE PARTNERSHIPS WITH AVAILABILITY PAYMENTS Dr. Silviu Dochia, Senior Associate Michael Parker, Managing Director SUMMARY Public-private partnerships ( P3s ) can provide the

More information

Lessons Learned/Best Practices: Case Study- Design-Build at SFO

Lessons Learned/Best Practices: Case Study- Design-Build at SFO Lessons Learned/Best Practices: Case Study- Design-Build at SFO Speaker(s): Clay Paslay Moderator Ivar Satero, SFO Steven Rule, Turner Bill Hooper, Jr., Gensler SFO s Delivery Options SELECTION TYPES Price

More information

Public/Private Partnerships and the Public Procurement Process

Public/Private Partnerships and the Public Procurement Process ELEVATING OUR PROFESSIONALISM 48 TH ANNUAL CONFERENCE MAY 17-20, 2015 ORLANDO, FLORIDA Public/Private Partnerships and the Public Procurement Process By Roman Martinez, MPA, CPPO, CPPB DEFINITION OF P3S

More information

DOING BUSINESS WITH CDOT

DOING BUSINESS WITH CDOT DOING BUSINESS WITH CDOT Who is CDOT? CDOT is responsible for 9,146 miles of highway including 3,447 bridges One of the largest state government agencies with an annual budget of $1.2 billion Primarily

More information

Public-Private Partnerships Forum PPP Law, Structures and Contracting

Public-Private Partnerships Forum PPP Law, Structures and Contracting Public-Private Partnerships Forum PPP Law, Structures and Contracting AGC California Fall Conference 2010 Hyatt Grand Champions, Indian Wells November 4, 2010 MAKING IT HAPPEN. Overview California PPP

More information

Infrastructure Banking

Infrastructure Banking Public-Private Partnership Structures May 2013 Edward Fanter Managing Director 212-605-1614 edward.fanter@bmo.com Infrastructure Banking June 2011 0 Infrastructure Banking Leading P3 Platform BMO Capital

More information

Surety Bond Associates. Understanding Contract Surety Bonding: An Orientation for Veteran Owned Small Contractors

Surety Bond Associates. Understanding Contract Surety Bonding: An Orientation for Veteran Owned Small Contractors Surety Bond Associates Understanding Contract Surety Bonding: An Orientation for Veteran Owned Small Contractors Contract Surety Bonds Bid Bond Performance Bond Payment Bond Who Requires Bonds? Public

More information

IDOT Chicago - St. Louis High-Speed Rail Program Management

IDOT Chicago - St. Louis High-Speed Rail Program Management 1 www.idothsr.org www.connectthemidwest.com IDOT Chicago - St. Louis High-Speed Rail Program Management Lessons Learned: Sealing the Corridor For 110 MPH Operations Thomas W. Hunter Parsons Brinckerhoff

More information

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices : A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it

More information

Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery

Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery Comparison of Design Bid Build and Design Build Finance Operate Maintain Project Delivery By Bob Prieto Design Bid Build (DBB) and Design Build Finance Operate Maintain (DBFOM) project delivery differ

More information

REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE

REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE Our Commitment: Increasing Investment Despite Lean Times Even while facing a $277M deficit, we are finding ways to rebuild

More information

Pricing Your Work (Overhead Recovery Review)

Pricing Your Work (Overhead Recovery Review) Pricing Your Work (Overhead Recovery Review) To accurately price your work, you need to be aware of three main factors: 1. The Estimate these costs are the direct costs of labor, equipment, materials,

More information

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

St. Vrain Watershed Master Plan Thursday, January 23 10:00 a.m. 12:15 p.m.

St. Vrain Watershed Master Plan Thursday, January 23 10:00 a.m. 12:15 p.m. St. Vrain Watershed Master Plan Thursday, January 23 10:00 a.m. 12:15 p.m. City Council Study Session Room City of Longmont Civic Center, 350 Kimbark Street, Longmont Minutes 1. Introductions a. Jeff Crane

More information

Lease-Leaseback 201:Lessons Learned in Dancing School. Our Agenda

Lease-Leaseback 201:Lessons Learned in Dancing School. Our Agenda Lease-Leaseback 201:Lessons Learned in Dancing School CASH Annual Conference February 26, 2013 Travis Kirk, Merced Union High School District Mark Quattrocchi, Quattrocchi Kwok Architects Glenn Gould,

More information

Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships

Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships Massachusetts Public-Private Partnership Infrastructure Oversight Commission Introduction to Public-Private Partnerships May 29, 2013 Introduction With you today from KPMG Years of Experience: 30+ Tim

More information

RTD S SUBCONTRACTOR PERFORMANCE SELF-INSURED PROGRAM. Presenter: Marla Lien, General Counsel Regional Transportation District Denver, Colorado

RTD S SUBCONTRACTOR PERFORMANCE SELF-INSURED PROGRAM. Presenter: Marla Lien, General Counsel Regional Transportation District Denver, Colorado RTD S SUBCONTRACTOR PERFORMANCE SELF-INSURED PROGRAM Presenter: Marla Lien, General Counsel Regional Transportation District Denver, Colorado PURPOSE OF THE PROGRAM To eliminate bonding as an obstacle

More information

District of Columbia Department of Transportation Traffic Services Administration Lighting Asset Management Program

District of Columbia Department of Transportation Traffic Services Administration Lighting Asset Management Program District of Columbia Department of Transportation Traffic Services Administration Lighting Asset Management Program A. Introduction The District of Columbia Department of Transportation Traffic Services

More information

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Phase 1 Phase 1 Project Status Closeout Status Completing Closeout of Remaining Elements of Work Final As-Builts nearing completion

More information

DESIGN-BUILD IN CALIFORNIA

DESIGN-BUILD IN CALIFORNIA DESIGN-BUILD IN CALIFORNIA 1. Why Design-Build Design Build Drivers, Goals and Challenges (see Reed Construction Data and DGS handouts) 2. Who Can Do Design-Build Design-Build Authorizing Statutes for

More information

Annual Meeting of Senior PPP Officials 2010

Annual Meeting of Senior PPP Officials 2010 Paris _ 12th of April 2010 PPP Risk Pricing PPPs Vs Traditional Procurement PPPs Strengths PPPs around the World Best PPPs Practices PPP Risk Pricing DESIGN DIFFERENT PPP DELIVERY MODELS BOT BUILD FINANCE

More information

Construction Management Functions CMGT 500/700

Construction Management Functions CMGT 500/700 Construction Management Functions CMT 500/700 Project Planning and Design Master Planning Planning Phase Designer Selection Design Phase Bid Phase Award Phase Construction Phase Master Planning AKA Capital

More information

225 statewide business consultants, 15 transportation consultants and 8 former CDOT engineers available to help you immediately!

225 statewide business consultants, 15 transportation consultants and 8 former CDOT engineers available to help you immediately! SUBCONTRACTING ON CDOT CONSTRUCTION PROJECTS Ramp Up Ridgway! Connect2DOT Colorado Small Business Development Center Network (SBDC) program funded by CDOT Free training, consulting, and resources for small

More information

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel Page 1 of 6 ALM Properties, Inc. Page printed from: New York Law Journal Back to Article Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel James E. Hughes New York

More information

Preliminary Value for Money Analysis

Preliminary Value for Money Analysis Preliminary Value for Money Analysis Comparison of Project Delivery Methods and Financing Options C-470 ExpressLanes November 2014 Outline Executive Summary Comparison of Delivery Options Base Case Plan

More information

Bonding and Insurance Requirements. Economic Development Committee 04/7/08

Bonding and Insurance Requirements. Economic Development Committee 04/7/08 Bonding and Insurance Requirements Economic Development Committee 04/7/08 Purpose To provide information related to the purpose and use of bid security, performance bond, and payment bond on City solicitations

More information

Evaluating Project Delivery Options

Evaluating Project Delivery Options Evaluating Project Delivery Options Scot A. Bini Vice President, URS August 24, 2004 Design-Bid-Build Overview Design Build Construction Management at Risk Owner Representation Terminology Project Manager

More information

PPPs: INSIGHTS FROM NORTH AMERICA. Presenter: Brian Middleton. www.jacobs.com worldwide

PPPs: INSIGHTS FROM NORTH AMERICA. Presenter: Brian Middleton. www.jacobs.com worldwide PPPs: INSIGHTS FROM NORTH AMERICA Presenter: Brian Middleton AGENDA Overview of US PPP market Case studies of sample projects Summary/Conclusions PPPs: An insight from North America SUMMARY OF PPPs IN

More information

Introduction to Public-Private Partnerships (P3s)

Introduction to Public-Private Partnerships (P3s) Introduction to Public-Private Partnerships (P3s) Today s Instructor Patrick DeCorla-Souza P3 Program Manager Office of Innovative Program Delivery Program Development Team Course Outline Slide 2 Lesson

More information

Public Private Partnership in Hospitals

Public Private Partnership in Hospitals Public Private Partnership in Hospitals Presentation to the International Health Seminar Brazil - Canada October 20, 2010 2008 The Canadian Council for Public-Private Partnerships Overview Healthcare in

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

Building Capital Projects in Tough Times John Lynch, State of Washington

Building Capital Projects in Tough Times John Lynch, State of Washington Building Capital Projects in Tough Times John Lynch, State of Washington Published as a joint effort of the National Association of State Facilities Administrators (NASFA) and the Associated General Contractors

More information

CDOT Resources for Small Businesses

CDOT Resources for Small Businesses General Information Resources Civil Rights & Business Resource Center is responsible for promoting and maintaining equal opportunity and participation for highway construction contractors and consultants

More information

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding

Bonding P3 Projects. Frequently Asked Questions about P3s and Bonding Bonding P3 Projects Government entities in the United States have understood the importance of surety bonds and have required bonds for over a century to provide performance and payment assurance for the

More information

EXHIBIT A Accessible Truck Routes Map

EXHIBIT A Accessible Truck Routes Map EXHIBIT A Accessible Truck Routes Map ASHEVILLE, NORTH CAROLINA ROUTE: A ROUTE: B ROUTE: C ROUTE: D ROUTE: E EXHIBIT A EXHIBIT B Craven Street Improvements Map ASHEVILLE, NORTH CAROLINA EXHIBIT B EXHIBIT

More information

CONSIDERING GC/CM There are some benefits and risks to using GC/CM. Departments should consider these carefully.

CONSIDERING GC/CM There are some benefits and risks to using GC/CM. Departments should consider these carefully. Department of Finance and Administrative Services ALTERNATIVE PUBLIC WORKS GENERAL CONTRACTOR/CONSTRUCTION MANAGER (GC/CM) GENERAL INFORMATION INTRODUCTION This manual provides the policy framework, procedures

More information

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS Construction/Maintenance Contracts and Design/Build Low Bid Contracts 1. Districts are responsible for reviewing their work program and identifying contracts that are good candidates for the Business Development

More information

GUIDELINES FOR RECRUITMENT AND SELECTION OF MINORITY BUSINESSES FOR PARTICIPATION IN STATE CONSTRUCTION CONTRACTS

GUIDELINES FOR RECRUITMENT AND SELECTION OF MINORITY BUSINESSES FOR PARTICIPATION IN STATE CONSTRUCTION CONTRACTS GUIDELINES FOR RECRUITMENT AND SELECTION OF MINORITY BUSINESSES FOR PARTICIPATION IN STATE CONSTRUCTION CONTRACTS In accordance with G.S. 143-128.2 (effective January 1, 2002) these guidelines establish

More information

Major Changes to Public Contracting and the CM/GC Delivery Method

Major Changes to Public Contracting and the CM/GC Delivery Method Major Changes to Public Contracting and the CM/GC Delivery Method Jeremy Vermilyea Schwabe Williamson & Wyatt Oregon Public Contracting Code & Model Public Contract Rules Section 137-049-0690 The CM/GC

More information

Denver Union Station. Regional Transportation District Denver, Colorado

Denver Union Station. Regional Transportation District Denver, Colorado Denver Union Station Regional Transportation District Denver, Colorado Regional Transportation District Created in 1969 Eight-county service area Service area: 2,340 sq. miles 2.8 million population 15

More information

February 4, 2016. Estimate

February 4, 2016. Estimate Wrentham, MA February 4, 2016 Architect: Turowski2 Architecture, Inc. P.O. Box 1290 313 Wareham Road Marion, MA 02738 (508) 758-9777 Cost Estimator: Miyakoda Consulting 300 Black Mallard Road Bridgewater,

More information

How to Write the Construction Management RFQ/RFP

How to Write the Construction Management RFQ/RFP 2011-06-07 How to Write the Construction Management RFQ/RFP Setting Up a Project for Success Today's Objectives The Art of RFQ/RFP writing First things first Determining the optimum Project Delivery Method

More information

CONTRACTOR QUALIFICATION APPLICATION for

CONTRACTOR QUALIFICATION APPLICATION for BOARD OF WATER COMMISSIONERS 1600 WEST 12TH AVENUE DENVER, COLORADO 80204 CONTRACTOR QUALIFICATION APPLICATION for South Boulder Diversion Canal Access Bridge for Ralston Landslide Repair General Contractor

More information

STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR

STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR REBECCA OTTO STATE AUDITOR STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR SUITE 500 525 PARK STREET SAINT PAUL, MN 55103-2139 (651) 296-2551 (Voice) (651) 296-4755 (Fax) state.auditor@osa.state.mn.us (E-mail)

More information

Non-Merchant Independent Power Projects: An Excellent Source of Yield and Duration for a De-risking Strategy

Non-Merchant Independent Power Projects: An Excellent Source of Yield and Duration for a De-risking Strategy Non-Merchant Independent Power Projects: An Excellent Source of Yield and Duration for a De-risking Strategy Louis Bélanger, CFA, FRM Managing Director, Stonebridge Infrastructure Debt Fund The Stonebridge

More information

City of Aurora Council Agenda Commentary

City of Aurora Council Agenda Commentary Item #: SS: 1st: 2nd: 9d City of Aurora Council Agenda Commentary Item Title: Consideration to AWARD A CHANGE ORDER TO THE COMPETITIVELY BID CONTRACT with Western Summit Constructors, Inc., Englewood,

More information

PROJECT COST ESTIMATES & FEASIBILITIES

PROJECT COST ESTIMATES & FEASIBILITIES PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed

More information

Supplier Performance Management Program. CEA Edmonton Buildings Committee November 13, 2012

Supplier Performance Management Program. CEA Edmonton Buildings Committee November 13, 2012 Supplier Performance Management Program CEA Edmonton Buildings Committee November 13, 2012 Supplier Performance Management Program - Background Consulting Services Review (Dec 14, 2009): The Office of

More information

MANTON CONSOLIDATED SCHOOLS. REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS. On a PERFORMANCE CONTRACTING BASIS

MANTON CONSOLIDATED SCHOOLS. REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS. On a PERFORMANCE CONTRACTING BASIS MANTON CONSOLIDATED SCHOOLS REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS On a PERFORMANCE CONTRACTING BASIS July 16, 2010 1 NOTICE IS HEREBY GIVEN THAT THE BOARD OF EDUCATION OF MANTON

More information

Cost Controls and Safe Harbor Standards for Homeownership Development Effective April 1, 2004

Cost Controls and Safe Harbor Standards for Homeownership Development Effective April 1, 2004 Cost Controls and Safe Harbor Standards for Homeownership Development Effective April 1, 2004 To expedite the homeownership review process, HUD is instituting safe harbor and maximum fee ranges for a number

More information

Community Program Directors, All Community Facilities Staff, State Architects and Engineers

Community Program Directors, All Community Facilities Staff, State Architects and Engineers TO: State Directors Rural Development RD AN No. 4794 (1942-A) September 28, 2015 ATTN: Community Program Directors, All Community Facilities Staff, State Architects and Engineers FROM: Tony Hernandez /s/

More information

Rebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153

Rebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153 Rebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153 October 2011 E. Rod Davisson, Esq., Schottenstein Zox & Dunn Co., LPA 250 West Street Columbus, Ohio 43215 614.462.2700

More information

NOTICE TO CONTRACTORS

NOTICE TO CONTRACTORS NOTICE TO CONTRACTORS Notice is hereby given that San Luis Obispo County Community College District, ( District ) is accepting sealed Informal Bidding Prequalification Applications and Formal Bidding Prequalification

More information

BOND MEASURE E CONTRACTOR OUTREACH

BOND MEASURE E CONTRACTOR OUTREACH FREMONT UNIFIED SCHOOL DISTRICT BOND MEASURE E CONTRACTOR OUTREACH May 4, 2015 INTRODUCTIONS Therese Gain, Director of Facilities, Fremont Unified School District Carol Lemos, Administrative Assistant

More information

Infrastructure Contract Management: Key Issues and Best Practices

Infrastructure Contract Management: Key Issues and Best Practices Infrastructure Contract Management: Key Issues and Best Practices Kevin Sampson OAA/EGAT Fred Guymont EGAT/I & E USAID Infrastructure Workshop Washington, DC December, 2009 What is contracting? con tract

More information

MOHAMMAD I CHAUDHRY, P.E. A CONSTRUCTION PROJECT MANAGER Specialized in Highways, Bridges and Infrastructures construction & Maintenance

MOHAMMAD I CHAUDHRY, P.E. A CONSTRUCTION PROJECT MANAGER Specialized in Highways, Bridges and Infrastructures construction & Maintenance MOHAMMAD I CHAUDHRY, P.E. A CONSTRUCTION PROJECT MANAGER Specialized in Highways, Bridges and Infrastructures construction & Maintenance SUMMARY: Mr. Chaudhry, a decisive, innovative leader with a demonstrated

More information

Request for Proposal CONSTRUCTION MANAGEMENT/GENERAL CONTRACTOR (CM/GC) SERVICES. For. City of Cripple Creek

Request for Proposal CONSTRUCTION MANAGEMENT/GENERAL CONTRACTOR (CM/GC) SERVICES. For. City of Cripple Creek Request for Proposal CONSTRUCTION MANAGEMENT/GENERAL CONTRACTOR (CM/GC) SERVICES For City of Cripple Creek Bennett Avenue Street Improvements and Enhancements January 13, 2014 City of Cripple Creek Request

More information

MEMORANDUM. 4201 E. Arkansas Ave., Room 262, Denver, CO 80222 P 303.757.9204 F 303.757.9656 www.coloradodot.info

MEMORANDUM. 4201 E. Arkansas Ave., Room 262, Denver, CO 80222 P 303.757.9204 F 303.757.9656 www.coloradodot.info 4201 E. Arkansas Ave., Room 262 Denver, CO 80222 MEMORANDUM TO: TRANSPORTATION COMMISSION FROM: JOSH LAIPPLY, CHIEF ENGINEER SCOTT RICHRATH, CHIEF FINANCIAL OFFICER DATE: SEPTEMBER 17, 2014 SUBJECT: PROGRAM

More information

I-66 Pavement Rehabilitation

I-66 Pavement Rehabilitation I-66 Pavement Rehabilitation Fall Asphalt Conference Richmond, VA David Shiells, P.E. Virginia Department of Transportation David White Superior Paving Corporation October 2, 2012 Project Location 2 Goal

More information

TAPPAN ZEE HUDSON RIVER CROSSING PROJECT

TAPPAN ZEE HUDSON RIVER CROSSING PROJECT New York State Department of Transportation New York State Thruway Authority TAPPAN ZEE HUDSON RIVER CROSSING PROJECT DESIGN-BUILD PROJECT RESPONSES TO PROPOSERS S REFERENCE NUMBER: This page is intentionally

More information

Construction Surety Bonds

Construction Surety Bonds Construction Surety Bonds September 17, 2014 Presented by: Walt Caldwell Walt.Caldwell@willis.com What is a Surety Bond An instrument where one party (Surety) guarantees the obligations of a second party

More information

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield

More information

Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2

Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2 The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ 508.7 Million

More information

Contractors Surety Briefing for 2011. Presented By: Nick J. Rutigliano, President

Contractors Surety Briefing for 2011. Presented By: Nick J. Rutigliano, President Contractors Surety Briefing for 2011 Presented By: Nick J. Rutigliano, President Table of Contents 1. Surety Industry Status 2. What Drives Your Bonding Capacity 3. Communicating Your Financial Conditions

More information

A P3 is Just Another Method to Finance and to Deliver a Public Works Project.

A P3 is Just Another Method to Finance and to Deliver a Public Works Project. Federal Highway Administration Docket FHWA 2014-0006 Draft Toll Concession Public-Private Partnership (P3) Model Contract Guide Addendum Comments from the American Subcontractors Association (ASA), Surety

More information

LEASE LEASE BACK TRAINING AND LA TRADE TECH CULINARY ARTS SMALL CONTRACTOR OPPORTUNITY FORUM PROGRAM AGENDA

LEASE LEASE BACK TRAINING AND LA TRADE TECH CULINARY ARTS SMALL CONTRACTOR OPPORTUNITY FORUM PROGRAM AGENDA LEASE LEASE BACK TRAINING AND LA TRADE TECH CULINARY ARTS SMALL CONTRACTOR OPPORTUNITY FORUM I. Welcome Thursday, February 12, 2015 1:00 PM to 3:00 PM PROGRAM AGENDA II. LACCD Build Program Mission & Goals

More information

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES

REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES Big Rapids Public Schools Building Program 2005 OWNER Big Rapids Public Schools 21034 15-Mile Road Big Rapids, Michigan 49307 PHONE: (231) 796-2627

More information

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK November 1990 Transport No. PS-2 THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE John R. Lethbridge The use of outside

More information

Colorado Department of Health Care Policy and Financing

Colorado Department of Health Care Policy and Financing Colorado Department of Health Care Policy and Financing Colorado MMIS and Fiscal Agent Operations Services Draft RFP Release Response and Pre-RFP Bidder s Conference Announcement Details Colorado Medicaid

More information

photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada

photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada photos.com Cost, Quality and Accountability Public Tendering versus Self-Performance for Municipal Infrastructure Delivery in Canada For more than 200 years and with few exceptions, Canada s municipal

More information

Project Management Oversight Services

Project Management Oversight Services Solicitation Number: Reference-Number-FTA-08-PMOC Project Management Oversight Services Federal Transit Administration Our fundamental business strategy is forging strong, long-term relationships with

More information

SPECIFICATION COMPLIANCE MATRIX SPECIFICATION PARAGRAPH TITLE STATEMENT

SPECIFICATION COMPLIANCE MATRIX SPECIFICATION PARAGRAPH TITLE STATEMENT 5.30 Scope of Services Proposed Including Design Compliance: The committee evaluation will include the proposer s overall scope of services proposed. The committee will assign up to 25 points based on

More information

Franklin L. Burns School of Real Estate & Construction Management

Franklin L. Burns School of Real Estate & Construction Management University of Denver 1 Franklin L. Burns School of Real Estate & Construction Management Office: Daniels College of Business, Room 380 Mail Code: 2101 S. University Blvd. Denver, CO 80208 Phone: 303-871-3432

More information

I-25/ARAPAHOE INTERCHANGE RECONSTRUCTION PROJECT

I-25/ARAPAHOE INTERCHANGE RECONSTRUCTION PROJECT MANDATORY PRE-BID SIGN IN CDOT Carrie DeJiacomo, Program Engineer John Hall, Resident Engineer Telecia McCline, Project Manager Tammy Maurer, Assistant Project Manager David Evans/Hartwig Design Consultant

More information

Subcontractor Involvement Project Tracking Progress Curves. CSTM 462 Fall 2012

Subcontractor Involvement Project Tracking Progress Curves. CSTM 462 Fall 2012 Subcontractor Involvement Project Tracking Progress Curves CSTM 462 Fall 2012 Subcontractor Involvement into the Critical Path Many building contractors get very little input into the schedule from their

More information

Program Management for School Construction

Program Management for School Construction Program Management for School Construction Presented to: Pasadena Unified School District Board of Education January 13, 2009 Project Delivery Options Design Bid Build Design/Build Construction Management

More information

ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects

ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical

More information

A Guidebook to Local Government Construction Projects

A Guidebook to Local Government Construction Projects A Guidebook to Local Government Construction Projects Association County Commissioners of Georgia 3rd Edition 2011 Sponsored by A Guidebook to Local Government Construction Projects 3rd Edition March 2011

More information

NEGAUNEE PUBLIC SCHOOLS. REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS. On a PERFORMANCE CONTRACTING BASIS

NEGAUNEE PUBLIC SCHOOLS. REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS. On a PERFORMANCE CONTRACTING BASIS NEGAUNEE PUBLIC SCHOOLS REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS On a PERFORMANCE CONTRACTING BASIS July 26, 2010 NOTICE IS HEREBY GIVEN THAT THE BOARD OF EDUCATION OF NEGAUNEE

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

452 S. Saginaw, 2 nd Floor Flint, MI 48502 810.257.3088

452 S. Saginaw, 2 nd Floor Flint, MI 48502 810.257.3088 452 S. Saginaw, 2 nd Floor Flint, MI 48502 810.257.3088 September 2, 2015 The Genesee County Land Bank is soliciting proposals from qualified firms of Certified Public Accountants to audit its financial

More information

NIGP Career Seminar Series II Workshop I Bonds (Bid, Performance, and Payment) Bond Excerpts from ARS Title 34

NIGP Career Seminar Series II Workshop I Bonds (Bid, Performance, and Payment) Bond Excerpts from ARS Title 34 NIGP Career Seminar Series II Workshop I Bonds (Bid, Performance, and Payment) Bond Excerpts from ARS Title 34 34-201. Notice of intention to receive bids and enter contract; procedure; doing work without

More information

The Vermont Agency of Transportation Small Business Element of the Disadvantaged Business Enterprise (DBE) Program

The Vermont Agency of Transportation Small Business Element of the Disadvantaged Business Enterprise (DBE) Program The Vermont Agency of Transportation Small Business Element of the Disadvantaged Business Enterprise (DBE) Program Introduction and Overview of the Small Business Element: The Vermont Agency of Transportation

More information

Construction Management for Owners

Construction Management for Owners Construction Management for Owners General, Critical, and Future Trends 19 February 2010 Larry J. Smith, P.E. CCM, F.SAME Agenda Change General Trends Four Critical Trends Future Trends Professional Construction

More information

For more information, please contact: W. David Lee, Administrator, Statewide Planning and Policy Analysis Florida Department of Transportation 605

For more information, please contact: W. David Lee, Administrator, Statewide Planning and Policy Analysis Florida Department of Transportation 605 For more information, please contact: W. David Lee, Administrator, Statewide Planning and Policy Analysis Florida Department of Transportation 605 Suwannee Street MS 28 Tallahassee, Florida 32399 (850)

More information

Jamaica School Rehabilitation Project and Maintenance Plan

Jamaica School Rehabilitation Project and Maintenance Plan Jamaica School Rehabilitation Project and Maintenance Plan Jacob Greenstein Daniel Hollander Sophie Taintor Jessica Tulodo October 2009 Outline Impacts of Tropical Storm Gustav USAID School Rehabilitation

More information

NOW, THEREFORE, THE BOARD OF COMMISSIONER FOR THE COUNTY OF ALAMANCE DOTH ORDAIN:

NOW, THEREFORE, THE BOARD OF COMMISSIONER FOR THE COUNTY OF ALAMANCE DOTH ORDAIN: ORDINANCE FOR THE ESTABLISHMENT OF ALAMANCE COUNTY MINORITY BUSINESS ENTERPRISE (MBE) OUTREACH PLAN AND GUIDELINES FOR RECRUITMENT AND SELECTION OF MINORITY BUSINESSES WHEREAS, the Board of Commissioners

More information

Chicago Transit Authority Open Standards Fare System Overview. David Faust Chicago Transit Authority Senior Project Manager Chicago, IL

Chicago Transit Authority Open Standards Fare System Overview. David Faust Chicago Transit Authority Senior Project Manager Chicago, IL Chicago Transit Authority Open Standards Fare System Overview David Faust Chicago Transit Authority Senior Project Manager Chicago, IL KEY OBJECTIVES Greater customer convenience Private financing of equipment

More information

Building the right customer relationships:

Building the right customer relationships: Building the right customer relationships: Predictive analytics and requests for proposals. Get in touch. Call us at 1.866.963.6941 or write us at info@canworksmart.com. What if you could determine what

More information

RFP VOICE OVER IP PHONE SYSTEM BID: #14-012- BOE

RFP VOICE OVER IP PHONE SYSTEM BID: #14-012- BOE SPECIFICATIONS AND BID FORMS FOR RFP VOICE OVER IP PHONE SYSTEM BID: #14-012- BOE Due on or before 11:00 A.M. ON FRIDAY, MARCH 7, 2014 at the: OFFICE OF THE PURCHASING COORDINATOR CENTRAL OFFICE WESTON

More information

PRE BID MEETING AGENDA

PRE BID MEETING AGENDA PRE BID MEETING AGENDA Project Name: UCHC Academic Bldg. Addition & Renovation Meeting Location: UCHC, Farmington, CT Campus Project #: 901729 Meeting Date: December 10, 2014 1. Team Introductions: Construction

More information

PUBLIC CONSTRUCTION PROJECTS AND THE COLORADO PUBLIC WORKS ACT

PUBLIC CONSTRUCTION PROJECTS AND THE COLORADO PUBLIC WORKS ACT PUBLIC CONSTRUCTION PROJECTS AND THE COLORADO PUBLIC WORKS ACT John W. Mill Sherman & Howard L.L.C. PUBLIC WORKS [T]he construction, erection, repair, maintenance, or improvement of any building, road,

More information

DBE/SBE Let s Connect

DBE/SBE Let s Connect First Quarter 2012 IN THIS ISSUE Off to a Great Start! Supportive Services Denver Transit Partners will use this quarterly newsletter to keep the DBE/SBE community up-to-date on our progress in implementing

More information