1 1 IDOT Chicago - St. Louis High-Speed Rail Program Management Lessons Learned: Sealing the Corridor For 110 MPH Operations Thomas W. Hunter Parsons Brinckerhoff

2 Agenda AGENDA 2» Overall Program Description» Background Data» Crossing Treatment Types» Lessons Learned

3 3 Overall Program Description

4 The Chicago to St. Louis Corridor OVERVIEW: CHICAGO TO ST. LOUIS PROGRAM 4» HSR development on the corridor since 1980 s» Previously completed studies (2004 ROD)» Sizeable ridership at intermediate stations

5 Why Not Faster? 110 MPH VS. 220 MPH 5» Jog, Run, Sprint Philosophy Jog mph Run mph Sprint mph

6 Program is Comprised of Multiple Projects (FRA Contributions Indicated) OVERVIEW: CHICAGO TO ST. LOUIS PROGRAM 6

7 Initial Program Budget: $1.2 Billion OVERVIEW: CHICAGO TO ST. LOUIS PROGRAM 7» Track & Structures $558 million» Real Estate $ 15 million» Stations $ 40 million» Rolling Stock / Equipment $211 million» Signaling & Communications $153 million» Miscellaneous $ 50 million (Grade Crossing Approaches, Bridges, Fencing, etc)» Professional Services $175 million (Program Management, Environmental / Design, Construction Oversight) Total: $1,202 million Additional Supplemental (under negotiation): $248 million

8 Key Program Milestones MILESTONES 8

9 Who s Involved? OVERVIEW: CHICAGO TO ST. LOUIS PROGRAM 9 Elected Officials Regional Agencies Transportation Providers Business Community General Public & Interest Groups City/County Technical Staff Project Partners Illinois Department of Transportation (IDOT) Federal Railroad Administration (FRA) Union Pacific Railroad (UPRR) UPRR Contractors/Consultants Amtrak: Service Provider Illinois Commerce Commission (ICC) Stakeholders Project Management Consultant (PMC) Parsons Brinckerhoff (PB) Additional Consultants

10 Background Data

11 Construction Coordination CONSTRUCTION 11» UP responsible for track/signal/bridge delivery Six weeks from 2010 agreement to construction» PMC field team focus on oversight and verification» Invoicing meeting FRA requirements a critical task» IDOT will contract stations, equipment, etc

12 Construction Overview CONSTRUCTION 12» One of the first construction projects in the HSIPR Program» In 2010, upgraded 76.5 miles of existing main line track» Continued in 2011 upgrading miles of existing main line track

13 Interim Grade Crossing Improvements CONSTRUCTION 13 Before» Road Crossings» Road Crossings After

14 New Construction 14» Next Priorities Complete design work Drainage structure work on existing main line Siding re-construction» Complete TRT work in 2012 Signal & crossing upgrades Reconstruct existing sidings Construct 32 miles of 2 nd main line Reconstruct interlockers

15 Crossing Treatment Types

16 Crossing Treatment CROSSING TREATMENT 16» Safety Public road crossing warning: four quadrant gates and pedestrian gates as required Private crossing enhancements: four quadrant gates at private crossings with special treatment at farm crossings Implementation of cab signaling on limited segment, and PTC

17 Crossing Treatment CROSSING TREATMENT 17» Collaborative Decision Process Involvement of all stakeholders Based on FRA HSR Guidelines ICC Regulations and requirements IDOT, UP and local input

18 Diagnostic Inspections CROSSING TREATMENT 18» Field Data Collection Use a standard measurement Involve all stakeholders Determines the base line for future design

19 Grade Crossing Diagnostic Review CROSSING TREATMENT 19

20 Determination on Treatments CROSSING TREATMENT 20» Stakeholder Involvement in Design Extensive discussions with ICC, FRA, IDOT and UPRR Novel ways to meet requirements Required FRA review for approval still underway

21 Grade Crossing 30% Design CROSSING TREATMENT 21 COLLABORITVE PROCESS WITH MULTI-AGENCY REVIEW AND APPROVAL

22 Lessons Learned

23 Start Early on Discussions LESSONS LEARNED 23» Involved IDOT, UP, FRA, Amtrak» Initial focus was IDOT, UP, ICC FRA brought into discussions after consensus made» Groundbreaking nature of agreements meant numerous obstacles

24 Coordinate Planning and Design LESSONS LEARNED 24 The Players:» UP and UP contractors» IDOT, Program Management Consultant (PMC), and additional support consultants» Local agencies General Coordination:» IDOT deals with PE (parties agree scope/budget)» UP completes design

25 LESSONS LEARNED Special Features Required for 110mph Running 25» 20-mile test segment planned for 2012 supported by cab signal installation» PTC by 2015 to be delivered by UP» Curve/spiral designs selected for high ride quality while accommodating balanced condition for freight at 60 mph» FRA Class 6 standards

26 Get Your Information from the Source GET INVOLVED 26» For additional information: Visit for specific information and to comment on the Illinois High-Speed Rail project. Visit for Midwest High-Speed Rail information. Project Hotline IDOT-HSR ( ).

27 Questions?

Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873

Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873 Legislative Fiscal Bureau One East Main, Suite 301 Madison, WI 53703 (608) 266-3847 Fax: (608) 267-6873 February 16, 2010 TO: FROM: Members Joint Committee on Finance Bob Lang, Director SUBJECT: Governor's

More information

SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development

SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development Draft 06162009 SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development The Minnesota Department of Transportation (Mn/DOT) requires the services of

More information

Performance Goals and Objectives:

Performance Goals and Objectives: Online Briefing Winter 2011 2012 Purpose: The purpose of the Project is to examine and recommend ways of introducing higher passenger train speeds on the Empire Corridor and ways to improve reliability,

More information

USA: INFRASTRUCTURES DAY

USA: INFRASTRUCTURES DAY USA: INFRASTRUCTURES DAY Business Opportunities for Infrastructures in the US Market Business Conference 21th November 2014 Auditório do Banco Popular Rua Ramalho Ortigão, 51 Lisboa Organização: Patrocinadores:

More information

Section ALTERNATIVES. 3. Alternatives

Section ALTERNATIVES. 3. Alternatives Section 3 ALTERNATIVES 3. Alternatives 3.0 Alternatives The Springfield Rail Improvements Project Build Alternatives would utilize different routes. The No Build Alternative includes the continuation of

More information

Utah Transit Authority

Utah Transit Authority Utah Transit Authority Overview The Utah Transit Authority (UTA) is submitting its 2012 FrontRunner South Safety and Activation Program for consideration for an APTA Rail Safety & Security Excellence Award.

More information

Introduction to Station Area Planning The Charlotte Story

Introduction to Station Area Planning The Charlotte Story Introduction to Station Area Planning The Charlotte Story Boston 2009 Steve Hamwey - Sasaki Associates, Inc. Troy Russ - Glatting Jackson, Inc. October 31 st, 2009 Station Area Planning October 15th History

More information

ACQUISITION AND PROCUREMENT: NEW JERSEY HIGH-SPEED RAIL IMPROVEMENT PROGRAM HAS COST AND SCHEDULE RISKS

ACQUISITION AND PROCUREMENT: NEW JERSEY HIGH-SPEED RAIL IMPROVEMENT PROGRAM HAS COST AND SCHEDULE RISKS ACQUISITION AND PROCUREMENT: NEW JERSEY HIGH-SPEED RAIL IMPROVEMENT PROGRAM HAS COST AND SCHEDULE RISKS Audit Report OIG-A-2015-012 June 17, 2015 DRAFT REPORT Page intentionally left blank NATIONAL RAILROAD

More information

Midwest Regional Rail Initiative Phase 7. South of the Lake Route Alternatives Analysis Report

Midwest Regional Rail Initiative Phase 7. South of the Lake Route Alternatives Analysis Report South of the Lake Alternatives Analysis Report Table of Contents Midwest Regional Rail Initiative Phase 7 South of the Lake Route Alternatives Analysis Report Prepared for: Indiana Department of Transportation

More information

Safety Engineering Policy Memorandum

Safety Engineering Policy Memorandum Safety Engineering Policy Memorandum SAFETY 2-13 Automated Traffic Law Enforcement Systems: Red Light Running (RLR) Camera Enforcement Systems and Automated Railroad Grade Crossing (RGC) Enforcement Systems

More information

Doing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs

Doing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs Doing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs W. T. "Bill" Farquhar Trinity Railway Express Irving, TX Abstract The Trinity Railway Express (TRE)

More information

Cisco Positive Train Control: Enhancing End-to-End Rail Safety

Cisco Positive Train Control: Enhancing End-to-End Rail Safety Solution Overview Cisco Positive Train Control: Enhancing End-to-End Rail Safety What You Will Learn Positive Train Control (PTC), one of many new safety measures mandated by the U.S. Federal Government,

More information

MINUTES OF A PUBLIC MEETING OF THE METRA BOARD SAFETY COMMITTEE OF THE COMMUTER RAIL DIVISION OF THE REGIONAL TRANSPORTATION AUTHORITY

MINUTES OF A PUBLIC MEETING OF THE METRA BOARD SAFETY COMMITTEE OF THE COMMUTER RAIL DIVISION OF THE REGIONAL TRANSPORTATION AUTHORITY MINUTES OF A PUBLIC MEETING OF THE METRA BOARD SAFETY COMMITTEE OF THE COMMUTER RAIL DIVISION OF THE REGIONAL TRANSPORTATION AUTHORITY The Metra Board Safety Committee of the Commuter Rail Division of

More information

METROLINK SAFETY PEER REVIEW PANEL FINAL REPORT

METROLINK SAFETY PEER REVIEW PANEL FINAL REPORT METROLINK COMMUTER RAIL SAFETY PEER REVIEW PANEL SIX-MONTH REPORT CARD ON THE SCRRA S S PROGRESS ON THE PANEL S RECOMMENDED METROLINK ENHANCED SAFETY ACTION PLAN FINAL REPORT DECEMBER 31, 2009 Prepared

More information

Wilmington to Newark Commuter Rail Improvement Project

Wilmington to Newark Commuter Rail Improvement Project Wilmington to Newark Commuter Rail Improvement Project The Delaware Transit Corporation (DTC), a subsidiary of the Delaware Department of Transportation (DelDOT), is undertaking a rail capacity expansion

More information

Briefing On New Jersey High Speed Rail Improvement Program. October 10, 2012

Briefing On New Jersey High Speed Rail Improvement Program. October 10, 2012 Briefing On New Jersey High Speed Rail Improvement Program October 10, 2012 Limits Of Work: Trenton To New Brunswick I Ladder In Pennsylvania Station New York New Frequency Converter At Metuchen Amtrak

More information

Comprehensive Railroad Liability Coverage

Comprehensive Railroad Liability Coverage Comprehensive Railroad Liability Coverage APPLICANTS ARE ADVISED TO READ THE POLICY FORM BEFORE COMPLETING THIS APPLICATION AS THE FORM, SUBJECT TO WHATEVER AMENDMENTS TO THE TERMS, CONDITIONS AND EXCLUSIONS

More information

Dallas-Fort Worth Area Major Transportation Projects

Dallas-Fort Worth Area Major Transportation Projects Dallas-Fort Worth Area Major Transportation Projects Presented by: Jeffrey C. Neal Program Manager Transportation North Central Texas Council of Governments (NCTCOG) August 14, 2014 Texas Society of Professional

More information

Department of Transportation, Rail Division Records Retention Schedule 2002-0018 Effective Date: June 2003 Table of Contents. Rail Safety...

Department of Transportation, Rail Division Records Retention Schedule 2002-0018 Effective Date: June 2003 Table of Contents. Rail Safety... Department of Transportation, Rail Division Records Retention Schedule 2002-0018 Effective Date: June 2003 Table of Contents Crossing Safety... 4 Rail Planning, Projects, and Operations... 5 Rail Safety...

More information

Virginia s Approach to Intercity Passenger Rail Development

Virginia s Approach to Intercity Passenger Rail Development Virginia s Approach to Intercity Passenger Rail Development Kevin B. Page Chief Operating Officer Virginia Department of Rail and Public Transportation June 14, 2013 www.drpt.virginia.gov High Speed Rail

More information

Office of Safety and Compliance

Office of Safety and Compliance The Federal Railroad Administration (FRA) was created by the Department of Transportation Act of 1966. It is one of ten agencies within the U.S. Department of Transportation concerned with intermodal transportation.

More information

Risk Management in the Development of a Penta-P Project

Risk Management in the Development of a Penta-P Project Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don

More information

FLC 4th Annual Summer Research Symposium: Planes, Trains, Ports & Highways What Keeps Florida Moving?

FLC 4th Annual Summer Research Symposium: Planes, Trains, Ports & Highways What Keeps Florida Moving? FLC 4th Annual Summer Research Symposium: Planes, Trains, Ports & Highways What Keeps Florida Moving? Jose Gonzalez SVP - Florida East Coast Industries Wednesday, August 12, 2015 1 Florida East Coast Industries

More information

REAL PROPERTY MANAGEMENT: Applying Best Practices Can Improve Real Property Inventory Management Information

REAL PROPERTY MANAGEMENT: Applying Best Practices Can Improve Real Property Inventory Management Information REAL PROPERTY MANAGEMENT: Applying Best Practices Can Improve Real Property Inventory Management Information Report No. OIG-A-2013-015 June 12, 2013 NATIONAL RAILROAD PASSENGER CORPORATION The Inspector

More information

Metrolink Positive Train Control Program May 2012

Metrolink Positive Train Control Program May 2012 Metrolink Positive Train Control Program May 2012 Metrolink s aggressive Positive Train Control (PTC) program calls for installing a back-office system, replacing the current computeraided dispatch system,

More information

UNITED STATES SENATE COMMITTEE ON COMMERCE, SCIENCE AND TRANSPORTATION HEARING ON THE FUTURE OF INTERCITY RAIL PASSENGER SERVICE AND AMTRAK

UNITED STATES SENATE COMMITTEE ON COMMERCE, SCIENCE AND TRANSPORTATION HEARING ON THE FUTURE OF INTERCITY RAIL PASSENGER SERVICE AND AMTRAK UNITED STATES SENATE COMMITTEE ON COMMERCE, SCIENCE AND TRANSPORTATION HEARING ON THE FUTURE OF INTERCITY RAIL PASSENGER SERVICE AND AMTRAK Testimony of HERZOG TRANSIT SERVICES, INC. Tuesday April 29,

More information

Experts in Rail Maintenance and Infrastructure

Experts in Rail Maintenance and Infrastructure Experts in Rail Maintenance and Infrastructure It is with great people and pride, rooted in a culture of safety, D that Transdev delivers systems, technologies, and business processes to strengthen rail

More information

AMTRAK UNVEILS ADVANCED TECHNOLOGY LOCOMOTIVES FOR NORTHEAST SERVICE Siemens-built equipment to improve reliability, efficiency and mobility

AMTRAK UNVEILS ADVANCED TECHNOLOGY LOCOMOTIVES FOR NORTHEAST SERVICE Siemens-built equipment to improve reliability, efficiency and mobility FOR IMMEDIATE RELEASE: May 13, 2013, 5 AM ET ATK-13-039 Media Contact: Amtrak: 202 906.3860 Siemens: 917 622.2413 AMTRAK UNVEILS ADVANCED TECHNOLOGY LOCOMOTIVES FOR NORTHEAST SERVICE Siemens-built equipment

More information

VRE SYSTEM PLAN SUMMARY

VRE SYSTEM PLAN SUMMARY VRE System Plan Summary January 2014 VRE SYSTEM PLAN SUMMARY VRE A Cost-Effective Contributor to Regional Mobility During the last decade, VRE has demonstrated its ability to accommodate a rapid and substantial

More information

Stouffville Corridor Rail Service Expansion

Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Class Environmental Assessment Study WELCOME PUBLIC INFORMATION CENTRE #2 Tuesday January 28, 2014 Agincourt Recreation

More information

Why NEC FUTURE? 457 MILES LONG 2,200 DAILY TRAINS 750,000 DAILY PASSENGERS. Study Partners. Key Needs

Why NEC FUTURE? 457 MILES LONG 2,200 DAILY TRAINS 750,000 DAILY PASSENGERS. Study Partners. Key Needs 457 MILES LONG 2,200 DAILY TRAINS 750,000 DAILY PASSENGERS THE NEC IS THE BUSIEST RAIL CORRIDOR IN THE NATION, AND IS VITAL TO THE ECONOMY AND CITIES OF THE NORTHEAST. Why NEC FUTURE? The Northeast United

More information

An Interim Assessment of Achieving Improved Trip Times on the Northeast Corridor

An Interim Assessment of Achieving Improved Trip Times on the Northeast Corridor An Interim Assessment of Achieving Improved Trip Times on the Northeast Corridor Prepared by Amtrak Under Section 212(d) of the Passenger Rail Investment and Improvement Act of 2008 (Public Law 110-432)

More information

Owner s Procurement Forum

Owner s Procurement Forum Washington Metropolitan Area Transit Authority Construction Management Association of America National Capitol Chapter Owner s Committee Owner s Procurement Forum February 24, 2015 OVERVIEW of WMATA INFRASTRUCTURE:

More information

Project Management Manual. Volume 1: PM Desk Book

Project Management Manual. Volume 1: PM Desk Book Project Management Manual Volume 1: PM Desk Book Revision 0: July 15, 2011 THE PROJECT MANAGER S TEN COMMANDMENTS PROJECT MANAGERS SHALL: 1. Draft the Project Charter to define the scope, schedule, budget,

More information

CalMod Design-Build Electrification Services

CalMod Design-Build Electrification Services SECTION 01800 SYSTEMS INTEGRATION AND INTEGRATOR REQUIREMENTS PART 1 GENERAL DESCRIPTION A. This section specifies the system-wide integration requirements for the Caltrain Electrification system, i.e.

More information

L E G I S L A T I V E A N A L Y S T S O F F I C E

L E G I S L A T I V E A N A L Y S T S O F F I C E November 29, 2011 High-Speed Rail Authority: The Draft 2012 Business Plan and Funding Plan L E G I S L A T I V E A N A L Y S T S O F F I C E Presented to: Assembly Transportation Committee Hon. Bonnie

More information

Questions and Answers about the Orange Bus/Rail Investment Plan

Questions and Answers about the Orange Bus/Rail Investment Plan Why are transit improvements needed? Questions and Answers about the Orange Bus/Rail Investment Plan The Triangle Region is now home to 1.5 million people. The U.S. Census and the 2035 Joint Long Range

More information

Rail Automation. What is ACSES? usa.siemens.com/rail-automation

Rail Automation. What is ACSES? usa.siemens.com/rail-automation Rail Automation What is ACSES? usa.siemens.com/rail-automation What is ACSES? Siemens, a specialist in the area of US Cab Signal design, offers a carborne product that provides both Civil Speed Enforcement

More information

APPLICATION FOR COMPREHENSIVE LIABILITY INSURANCE - RAILROADS

APPLICATION FOR COMPREHENSIVE LIABILITY INSURANCE - RAILROADS STEADFAST INSURANCE COMPANY APPLICATION FOR COMPREHENSIVE LIABILITY INSURANCE - RAILROADS THE COMPLETION OF AND SUBMISSION TO THE STEADFAST INSURANCE COMPANY OF THIS APPLICATION DOES NOT CONSTITUTE A BINDER

More information

RAIL HANDBOOK EXECUTIVE SUMMARY

RAIL HANDBOOK EXECUTIVE SUMMARY Rail Handbook Last Updated: January 2012 RAIL HANDBOOK EXECUTIVE SUMMARY PURPOSE The purpose of the Rail Office Programs Handbook (Rail Handbook) is to identify and designate responsibility for rail processes

More information

When is BRT the Best Option? 1:30 2:40 p.m.

When is BRT the Best Option? 1:30 2:40 p.m. TRB/APTA 2004 Bus Rapid Transit Conference When is BRT the Best Option? 1:30 2:40 p.m. Paul Larrousse Director, National Transit Institute (NTI) (Moderator) TRB/APTA 2004 Bus Rapid Transit Conference Session

More information

Word Count= 4,708 (+ 2 images) ABSTRACT

Word Count= 4,708 (+ 2 images) ABSTRACT HIGH SPEED RAIL IN NEW JERSEY Alfred E. Fazio, PE Deputy Chief Engineer, Section Improvements, Amtrak 2955 Market St Philadelphia, PA 19104 215.219.2185 [email protected] Theresa Impastato Program

More information

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements Presentation July 23, 2014 A. Morton Thomas and Associates, Inc. 800 King Farm Boulevard, 4 th Floor Rockville, Maryland 20850

More information

DECEMBER 10, 2014 FINAL AGENDA PUBLIC COMMENTS ON AGENDA ITEMS AND OTHER MATTERS

DECEMBER 10, 2014 FINAL AGENDA PUBLIC COMMENTS ON AGENDA ITEMS AND OTHER MATTERS NEW JERSEY TRANSIT CORPORATION NJ TRANSIT BUS OPERATIONS, INC. NJ TRANSIT RAIL OPERATIONS, INC. NJ TRANSIT MERCER, INC. NJ TRANSIT MORRIS, INC. REGULARLY SCHEDULED BOARD OF DIRECTORS MEETINGS CALL TO ORDER

More information

ICN National Passenger Rail Alliance, www.npra.icn.org.au, Transport Sector Opportunities

ICN National Passenger Rail Alliance, www.npra.icn.org.au, Transport Sector Opportunities ICN National Passenger Rail Alliance, www.npra.icn.org.au, Transport Sector Opportunities Stephan van der Lit Programme Manager, ICN National Passenger Rail Alliance m: +61 447 888 005 e: [email protected]

More information

National Railroad Passenger Corporation AMTRAK. Fiscal Years 2013 2017 Five Year Plan. May 2013

National Railroad Passenger Corporation AMTRAK. Fiscal Years 2013 2017 Five Year Plan. May 2013 National Railroad Passenger Corporation AMTRAK Fiscal Years 2013 2017 Five Year Plan May 2013 Table of Contents Introduction... 4 Background... 4 PRIIA Sections 209 and 212... 5 Amtrak s Strategic Plan...

More information

Power Point Presentation

Power Point Presentation Good Morning Chairman Evans and members of the Committee on Finance and Revenue. I am Jack Requa, Interim General Manager and CEO of the Washington Metropolitan Area Transit Authority (WMATA), commonly

More information

Environmental Impact Statement for the Washington Union Station Expansion Project

Environmental Impact Statement for the Washington Union Station Expansion Project This document is scheduled to be published in the Federal Register on 11/04/2015 and available online at http://federalregister.gov/a/2015-28079, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION

More information

Illinois Tollway and Chicago Department of Transportation Construction Networking Event. March 13, 2015

Illinois Tollway and Chicago Department of Transportation Construction Networking Event. March 13, 2015 Illinois Tollway and Chicago Department of Transportation Construction Networking Event March 13, 2015 Today s Agenda Welcome Illinois Tollway projects Chicago Department of Transportation (CDOT) projects

More information

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37

More information

Lincoln Downtown Master Plan Update

Lincoln Downtown Master Plan Update Lincoln Downtown Master Plan Update Table of Contents Executive Summary........................................... 1 Complete Streets Framework.................................... 3 Promenade Creating

More information

SYSTEMWIDE REQUIREMENTS

SYSTEMWIDE REQUIREMENTS SYSTEMWIDE REQUIREMENTS for the Peninsula Rail Program San Francisco to San Jose on the Caltrain Corridor Description of the Systemwide Context for the High Speed Train Project This document provides a

More information

The Gateway Program and Hudson Tunnel Project

The Gateway Program and Hudson Tunnel Project The Gateway Program and Hudson Tunnel Project Presented to: NJ State Senate Oversight Committee Stephen Gardner Executive Vice President NEC Business Development August 10, 2015 1 The Need for Gateway

More information

8 IMPLEMENTATION PLAN. 8.1 Introduction

8 IMPLEMENTATION PLAN. 8.1 Introduction 8 IMPLEMENTATION PLAN 8.1 Introduction An implementation plan for the Illinois Statewide ITS Strategic Plan is the next step of the project planning process. This plan provides a strategy for implementing

More information

Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012

Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012 Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 6:00 6:30 p.m. Open House 6:30 7:00 p.m. Presentation 7:00 8:00 p.m. Open House 2 Project Overview Carla

More information

MOTION NO. M2016-76 Contingency Increase for Flatiron West, Inc. Construction Contract for Tacoma Trestle Track & Signal Project

MOTION NO. M2016-76 Contingency Increase for Flatiron West, Inc. Construction Contract for Tacoma Trestle Track & Signal Project MOTION NO. M2016-76 Contingency Increase for Flatiron West, Inc. Construction Contract for Tacoma Trestle Track & Signal Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board 7/14/2016

More information

Project Management Oversight Services

Project Management Oversight Services Solicitation Number: Reference-Number-FTA-08-PMOC Project Management Oversight Services Federal Transit Administration Our fundamental business strategy is forging strong, long-term relationships with

More information

Passenger & Freight Rail = Less Energy & More Choices. NATIONAL CONFERENCE of STATE LEGISLATURES

Passenger & Freight Rail = Less Energy & More Choices. NATIONAL CONFERENCE of STATE LEGISLATURES Passenger & Freight Rail = Less Energy & More Choices 2011 ENERGY POLICY SUMMIT FUELING TOMORROW S TRANSPORTATION Presentation to NATIONAL CONFERENCE of STATE LEGISLATURES San Antonio, TX August, 2011

More information

AnNual Audit, Inspection, and

AnNual Audit, Inspection, and Amtrak Amtrak Office of Inspector General www.amtrakoig.gov AnNual Audit, Inspection, and Evaluation Plan Fiscal Year 2013 OIG-AIE Sept. 30, 2012 Amtrak Office of Inspector General I Semiannual Report

More information