Lessons Learned/Best Practices: Case Study- Design-Build at SFO

Size: px
Start display at page:

Download "Lessons Learned/Best Practices: Case Study- Design-Build at SFO"

Transcription

1 Lessons Learned/Best Practices: Case Study- Design-Build at SFO Speaker(s): Clay Paslay Moderator Ivar Satero, SFO Steven Rule, Turner Bill Hooper, Jr., Gensler

2 SFO s Delivery Options SELECTION TYPES Price Definition Designer & Contractor 2 separate contracts 1. Low Bid Total Construction Cost Design-Bid-Build (Lump Sum) NA 2A. 2B. Price and other Qualifications Total Construction Cost Fees, General Conditions, Contingencies Etc. NA CM/GC (Low Bid/Best Value) NA Design-Build (Low Bid/Best Value) 3. Qualifications ONLY Based Selection None NA NA

3 Terminal 2 Renovations $383M Project 10 Gate Int l to 14 Gate Domestic Complete Refurbishment Seismic Upgrade NTP 4/1/08 Substantial Completion 3/2/11

4 Terminal 2 Renovations

5 Terminal 2 Renovations

6 Terminal 2 Renovations

7

8 Terminal 2 Renovations Topics for Discussion Communication Organization/Structure/Roles Design Control/Subs as Designers Out of Sync Drawing Development Budget/Contingency/GMP

9 Lessons Learned from SFO Terminal 2 Communications Contractor needs to provide strong design manager leadership to maintain communications and approvals. Have a planning Summit at start of project where roles and responsibilities and lines of communications are defined. Define communications and approval process up front and keep people working within that structure. SFO established Quick Response Teams (QRT s) made up of users / stakeholders, information developed became program. QRT process in use now for activation planning. Organization / Structure / Roles More specific definition of Roles / Responsibilities required More continuity with original Design Consultants even if EOR is a subcontractor Get CA services from original Design Consultants.

10 Lessons Learned from SFO Terminal 2 Design Control / Subs as Designers SFO is considering master architect and bridging documents with future DB projects. Will keep qualifications based DB selection v. Lump Sum for selection of builder team. Out of Sync Drawing Development SFO will use bridging type Master Architect to get drawings to a point where there is a comfort level that design has considered the stakeholders then use quals based process to select DB team. Team needs to balance design and construction schedule against exposure holds in GMP to account for early packages and continuing design. Budget / Contingency / GMP SFO to look at what point GMP is determined. Would prefer Construction Contingency rather than exposures or allowances shift risk to DB team.

11 Terminal 2 Renovations Q&A

12 Terminal 2 Renovations Reference Slides

13 Design-Build Terminal 2 Renovations - Procurement Process Schedule analysis of delivery options indicates design-build only option for achieving 36-month schedule. Airport to provide conceptual drawings in the Request for Proposals (RFP), based on a previous feasibility study. Airport to initiate Quick Response Team (QRT) process to expedite Program Development. RFP to include SFO s boilerplate for full A/E services, from Programmatic Phase through CA, with all of the same milestone deliverables for r an Airport-controlled design effort. Contract structured as progressive GMP.

14 Design-Build Collaboration Benefits Design-Bid-Build Bid Cost Savings Begin Buyout Design/Build w/gmp GMP Buyout Collaboration Time Savings Time

15 Design-Build Contract/Bidding Process DESIGN Bridging Documents Design Builder Civil Package Structure Package M/E/P Package Systems Package Building Package Final GMP Awarded Cost CONSTRUCTION Final GMP Time

16 Design-Build Terminal 2 Renovations Selection of Design-Builder Best Value selection process, with 40% of evaluation based qualifications and 60% on costs, as required by the pending new ordinance. Qualifications evaluation scored based on: Team Qualifications Key Personnel Experience Management Approach Cost evaluation scored based on: Design Fee General Conditions OH&P Markup Significant issue to bidders in Best Value is cost weighting.

17 Design-Build Terminal 2 Renovations Selection of Design-Builder For Example Firm #1 Firm #2 Design Fee $10,000,000 $12,000,000 General Conditions $20,000,000 $22,000,000 OH&P Markup 10% 12% Estimated Direct Costs $300,000,000 $300,000,000 Overhead & Profit Fee $30,000,000 $36,000,000 Total Cost Evaluation $360,000,000 $370,000,000 Lowest - 60 Points Maximum 60 2 nd Low - % Difference on Cost 60 (.027*60) = 58.38

18 Design-Build Terminal 2 Renovations Selection of Design-Builder Airport received 3 proposals from well-qualified firms. The firm ranked 2 nd in qualifications, but had the lowest cost structure, prevailed. When extended over the anticipated cost of construction, the total forecast cost of the highest ranked proposer resulted in a $22M savings as compared to the 2 nd ranked proposer. NTP was issued on April 1, 2008, with a September 30, 2010 Substantial Completion date. Current date for completion is March 2, 2011

Evaluating Project Delivery Options

Evaluating Project Delivery Options Evaluating Project Delivery Options Scot A. Bini Vice President, URS August 24, 2004 Design-Bid-Build Overview Design Build Construction Management at Risk Owner Representation Terminology Project Manager

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Approved March 23, 2011 Purpose: While the traditional Design-Bid-Build

More information

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield

More information

Construction Delivery Methods for Texas school districts

Construction Delivery Methods for Texas school districts Construction Delivery Methods for Texas school districts Pfluger Associates Architects, P.L.L.C. ARCHITECTS / PLANNING CONSULTANTS History Prior to 1995, public school districts were required to utilize

More information

What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM

What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM Progressive design-build: A better way? Discussion topics: What is progressive design-build?

More information

C.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods

C.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods C.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods Friday, December 3, 2010 9:00 a.m. to 3:00 p.m. Ontario Airport Radisson 2200 East Holt Boulevard

More information

CONSIDERING GC/CM There are some benefits and risks to using GC/CM. Departments should consider these carefully.

CONSIDERING GC/CM There are some benefits and risks to using GC/CM. Departments should consider these carefully. Department of Finance and Administrative Services ALTERNATIVE PUBLIC WORKS GENERAL CONTRACTOR/CONSTRUCTION MANAGER (GC/CM) GENERAL INFORMATION INTRODUCTION This manual provides the policy framework, procedures

More information

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. Terri Mestas Program Director

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. Terri Mestas Program Director Los Angeles Community College District PROGRAM MANAGEMENT SERVICES Terri Mestas Program Director CMAA Southern California Chapter February 13, 2015 1 LACCD Overview Established in 1969 Governed by seven-member

More information

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February

More information

Rebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153

Rebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153 Rebuilding Ohio s Public Construction Law: Construction Reform in House Bill 153 October 2011 E. Rod Davisson, Esq., Schottenstein Zox & Dunn Co., LPA 250 West Street Columbus, Ohio 43215 614.462.2700

More information

Project Delivery Methods & Contract Types CSTM 102 Spring 2013

Project Delivery Methods & Contract Types CSTM 102 Spring 2013 Project Delivery Methods & Contract Types CSTM 102 Spring 2013 Schedule February 16- Building Information Modeling February 21- Midterm Review February 23- Midterm In the industry the term Pre-Construction

More information

ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects

ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical

More information

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

The programming, design

The programming, design Understanding Project Delivery for the Design and Construction of Public Buildings architecture The programming, design and construction of important public buildings require the coordinated efforts of

More information

DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE

DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE ARIZONA DEPARTMENT OF TRANSPORTATION INTERMODAL TRANSPORTATION DIVISION DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE 3rd Edition December 2007 Published by: ADOT Construction Group 206 S. 17 th Ave.,

More information

ANCHORAGE SCHOOL DISTRICT ANCHORAGE, ALASKA. ASD MEMORANDUM #186 (2011-2012) March 22, 2012

ANCHORAGE SCHOOL DISTRICT ANCHORAGE, ALASKA. ASD MEMORANDUM #186 (2011-2012) March 22, 2012 ANCHORAGE SCHOOL DISTRICT ANCHORAGE, ALASKA ASD MEMORANDUM #186 (2011-2012) March 22, 2012 TO: FROM: SUBJECT: SCHOOL BOARD OFFICE OF THE SUPERINTENDENT AWARD OF CONTRACT: IT DATA CENTER MOVE TO KENNEDY

More information

Major Changes to Public Contracting and the CM/GC Delivery Method

Major Changes to Public Contracting and the CM/GC Delivery Method Major Changes to Public Contracting and the CM/GC Delivery Method Jeremy Vermilyea Schwabe Williamson & Wyatt Oregon Public Contracting Code & Model Public Contract Rules Section 137-049-0690 The CM/GC

More information

ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS

ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS ACC REAL ESTATE COMMITTEE PRESENTATION SEPTEMBER 17, 2009 SEAN T. BOULGER, ESQ. WILMER CUTLER PICKERING HALE AND DORR LLP I. Introduction

More information

CAPITAL PROJECT COSTS!!! UNIVERSITY OF CALIFORNIA SANTA CRUZ

CAPITAL PROJECT COSTS!!! UNIVERSITY OF CALIFORNIA SANTA CRUZ INTRODUCTION All Capital Project Budgets have 2 basic components: Construction Fees, Project Management, and Administration This presentation looks at COST DRIVERS that impact these 2 components and COST

More information

Program Management for School Construction

Program Management for School Construction Program Management for School Construction Presented to: Pasadena Unified School District Board of Education January 13, 2009 Project Delivery Options Design Bid Build Design/Build Construction Management

More information

Construction Activity: Audit Strategies

Construction Activity: Audit Strategies Construction Activity: Audit Strategies Capital construction projects can create significant exposure for organizations that are unaware of the risks associated with excessive cost, project delays and

More information

Commissioning Large Public Projects Using Construction Manager at Risk (CM@R)

Commissioning Large Public Projects Using Construction Manager at Risk (CM@R) Commissioning Large Public Projects Using Construction Manager at Risk (CM@R) Greg Cunningham, AIA Enovity, Inc. Synopsis Over the past ten years, an alternative method of project delivery has evolved

More information

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement

More information

AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS

AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS Advancing Professional Construction and Program Management Worldwide ACKNOWLEDGMENTS CMAA gratefully acknowledges the time and efforts of those who served as

More information

Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP

Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting

More information

Design-Build Process for Project Managers

Design-Build Process for Project Managers Vermont Agency of Transportation Design-Build Process for Project Managers This document provides guidance on the preliminary engineering and procurement process and roles and responsibilities of key personnel

More information

How to Write the Construction Management RFQ/RFP

How to Write the Construction Management RFQ/RFP 2011-06-07 How to Write the Construction Management RFQ/RFP Setting Up a Project for Success Today's Objectives The Art of RFQ/RFP writing First things first Determining the optimum Project Delivery Method

More information

Advanced Water Treatment Facility Alternative Project Delivery A Better Way

Advanced Water Treatment Facility Alternative Project Delivery A Better Way Advanced Water Treatment Facility Alternative Project Delivery A Better Way Service Area = 420 Square Miles 43 Cities Population = 4 Million 720,000 acre feet used per year 40% Groundwater from local water

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Elevator Upgrades Response Deadline 9/03/13

More information

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel Page 1 of 6 ALM Properties, Inc. Page printed from: New York Law Journal Back to Article Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel James E. Hughes New York

More information

Construction Management At-Risk

Construction Management At-Risk Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction

More information

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached ADDENDUM #1 RFP: 500 16 Design Build Maintenance & Operations Complex The following changes to the Request for Proposal and clarifications are provided based on questions received and must be added/considered

More information

Building Capital Projects in Tough Times John Lynch, State of Washington

Building Capital Projects in Tough Times John Lynch, State of Washington Building Capital Projects in Tough Times John Lynch, State of Washington Published as a joint effort of the National Association of State Facilities Administrators (NASFA) and the Associated General Contractors

More information

Construction Contract Fundamentals. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,

Construction Contract Fundamentals. Baker Tilly refers to Baker Tilly Virchow Krause, LLP, Construction Contract Fundamentals Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2010 Baker Tilly Virchow Krause, LLP About

More information

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015 PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015 DATE: TO: FROM: Michael Ehl, Director Airport Operations Wayne Grotheer, Director Aviation Project Management

More information

Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2

Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2 The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363

More information

Procurement Guidelines for Non-Profit Housing

Procurement Guidelines for Non-Profit Housing Procurement Guidelines for Non-Profit Housing July 2013 Table of Contents PART 1 INTRODUCTION... 1 1.1 Objectives... 1 1.2 How to Use... 1 PART 2 WORKING WITH BC HOUSING... 3 2.1 Key Stakeholders... 3

More information

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT CRENSHAW/LAX TRANSIT CORRIDOR PROJECT A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies Robert Ball, P.E. and Kimberly Ong, P.E. Los Angeles Metropolitan Transportation

More information

Info for CM at Risk RFP Butterfly Conservatory and Genomics Classroom

Info for CM at Risk RFP Butterfly Conservatory and Genomics Classroom Info for Butterfly Conservatory and Genomics Classroom 1. Introduction to the project The (CSC), located in downtown Hartford, is a non-profit organization dedicated to enhancing science education throughout

More information

RESOLUTION NO. 2012-11

RESOLUTION NO. 2012-11 RESOLUTION NO. 2012-11 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF GARIBALDI ACTING AS CONTRACT REVIEW BOARD APPROVING A REQUEST FOR PROPOSAL DOCUMENT AND SAMPLE CONTRACT FOR THE GARIBALDI FIRE STATION

More information

SAN FRANCISCO AIRPORT COMMISSION MINUTES

SAN FRANCISCO AIRPORT COMMISSION MINUTES SAN FRANCISCO AIRPORT COMMISSION MINUTES July 19, 2011 9:00 A.M. Room 400 - City Hall #1 Dr. Carlton B. Goodlett Place (400 Van Ness Avenue) City and County of San Francisco EDWIN M. LEE, MAYOR COMMISSIONERS

More information

Canadian Evaluation Society. Request for Proposal. Intermediate-Level. Professional Learning Program. (Stage Two)

Canadian Evaluation Society. Request for Proposal. Intermediate-Level. Professional Learning Program. (Stage Two) Canadian Evaluation Society Request for Proposal Intermediate-Level Professional Learning Program (Stage Two) Instructional Designer/Project Manager July 31, 2015 2 1.0 Background The delivery of quality

More information

The Construction Management Delivery System An Architect s Point of View

The Construction Management Delivery System An Architect s Point of View Session 1421 The Construction Management Delivery System An Architect s Point of View Daniel Davis, AIA University of Hartford Abstract There are at least three different building project delivery systems

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Organization Project

More information

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK MD ANDERSON AGREEMENT No. This Agreement is made as of, 20xx (the Effective Date ), by and between The Owner: M D Anderson Cancer Center c/o Sourcing

More information

Getting Connected with the Colorado Department of Transportation (CDOT)

Getting Connected with the Colorado Department of Transportation (CDOT) Getting Connected with the Colorado Department of Transportation (CDOT) INTRODUCTION Who is CDOT? CDOT is responsible for 9,146 miles of highway including 3,447 bridges State government agency with funding

More information

Construction Management and project process

Construction Management and project process Construction Management and project process Presented by: Vourvoutsiotis Apostolos GSO University of Applied Science Nürnberg 06.04.2000 Table of Contents Construction Management and project process Construction

More information

MIAMI BEACH. IN I A Financial Information: AGENDA ITEM

MIAMI BEACH. IN I A Financial Information: AGENDA ITEM COMMISSION ITEM SUMMARY Condensed Title: REQUEST FOR APPROVAL TO ISSUE A REQUEST FOR QUALIFICATIONS (RFQ) 2014-142-ME FOR A DESIGN CRITERIA PROFESSIONAL (DCP) TO PREPARE THE DESIGN CRITERIA PACKAGE FOR

More information

Design Build Institute of America (DBIA)

Design Build Institute of America (DBIA) Design Build Institute of America (DBIA) 1 D E S I G N B U I L D L E S S O N S L E A R N E D J O S É D. N U Ñ E Z, L E E D A P V I C E C H A N C E L L O R F A C I L I T I E S P L A N N I N G, M A I N T

More information

REQUEST FOR QUALIFICATIONS RFP # 1027 CITY OF RIVERSIDE MOBILE APPLICATION. Proposal Due: Before 4:00 PM June 18, 2011. Issued by:

REQUEST FOR QUALIFICATIONS RFP # 1027 CITY OF RIVERSIDE MOBILE APPLICATION. Proposal Due: Before 4:00 PM June 18, 2011. Issued by: REQUEST FOR QUALIFICATIONS RFP # 1027 CITY OF RIVERSIDE MOBILE APPLICATION Proposal Due: Before 4:00 PM June 18, 2011 Issued by: CITY OF RIVERSIDE DEVELOPMENT DEPARTMENT 3900 Main Street, 5 th Floor Riverside,

More information

CDOT Resources for Small Businesses

CDOT Resources for Small Businesses General Information Resources Civil Rights & Business Resource Center is responsible for promoting and maintaining equal opportunity and participation for highway construction contractors and consultants

More information

'rn - _CI ' 0'(. K)Qi

'rn - _CI ' 0'(. K)Qi =04 Los Angeles W o rld Airports Report to the BOARD OF AIRPORT COMMISSIONERS Approved by: 'rn - _CI ' 0'( K)Qi Dominic Nessi, Chief Information Officer ç Meeting Date: December 18, 2014 jf, (,,,,S(n\-_

More information

ORDINANCE NO.------- THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:

ORDINANCE NO.------- THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS: ORDINANCE NO.------- An ordinance authorizing the award of one design-build contract for the decommissioning, disablement, demolition and removal of Scattergood Generating Station Unit 3 pursuant to a

More information

Hard copies should be sent to: The Denver Waldorf School Attn: Lori Pucelik 940 Fillmore St Denver, CO 80206

Hard copies should be sent to: The Denver Waldorf School Attn: Lori Pucelik 940 Fillmore St Denver, CO 80206 April 24, 2013 RE: THE DENVER WALDORF SCHOOL SCHEMATIC DESIGN ARCHITECTURAL SERVICES REQUEST FOR PROPOSAL Dear Contact, Beecher Development Services has been retained by to provide Owners Representation

More information

Oregon Public Contracting Coalition Guide to CM/GC Contracting

Oregon Public Contracting Coalition Guide to CM/GC Contracting NOTE: REFERENCES TO ORS 279 AND BOLI REGULATIONS CONTAINED HEREIN DO NOT REFLECT ANY CHANGES OCCURING SUBSEQUENT TO THE PUBLICATION DATE. THE USER OF THIS DOCUMENT IS RESPONSIBLE FOR USING REGULATIONS

More information

Assessment of Critical Success Factors for Construction Projects in Pakistan

Assessment of Critical Success Factors for Construction Projects in Pakistan First International Conference on Construction In Developing Countries (ICCIDC I) Advancing and Integrating Construction Education, Research & Practice August 4-5, 2008, Karachi,, Pakistan Assessment of

More information

PROPRIETARY MEETINGS. Are they legal in Washington? Robynne Thaxton Parkinson, J.D, DBIA www.rtp-law.com

PROPRIETARY MEETINGS. Are they legal in Washington? Robynne Thaxton Parkinson, J.D, DBIA www.rtp-law.com PROPRIETARY MEETINGS Are they legal in Washington? Robynne Thaxton Parkinson, J.D, DBIA www.rtp-law.com Purpose of Procurement Laws Protection of general public prevent fraud, collusion, favoritism, and

More information

AMENDMENT TO AGREEMENT PARTIES

AMENDMENT TO AGREEMENT PARTIES AMENDMENT TO AGREEMENT PARTIES This [FIRST] Amendment to Agreement ( Amendment ) is entered into between Solano Community College District ( District ) and Swinerton Management and Consulting ( Consultant

More information

REQUEST FOR PROPOSAL. RFP No. 1027 LEAD GENERATION SERVICES. Proposal Due: Before 5:00 PM September 3, 2008. Issued by:

REQUEST FOR PROPOSAL. RFP No. 1027 LEAD GENERATION SERVICES. Proposal Due: Before 5:00 PM September 3, 2008. Issued by: REQUEST FOR PROPOSAL RFP No. 1027 LEAD GENERATION SERVICES Proposal Due: Before 5:00 PM September 3, 2008 Issued by: CITY OF RIVERSIDE DEVELOPMENT DEPARTMENT 3900 Main Street, 5 th Floor Riverside, CA

More information

RFP-00118 ADDENDUM NO. 1

RFP-00118 ADDENDUM NO. 1 INTERNAL SERVICES DEPARTMENT PROCUREMENT MANAGEMENT SERVICES 111 NW 1 ST Street Suite 1300 Miami, Florida 33128-1974 Telephone: 305-375-4725 Fax: (305) 375-5688 RFP-00118 ADDENDUM NO. 1 DATE: March 26,

More information

AN OWNER'S GUIDE TO CONSTRUCTION AND PROGRAM MANAGEMENT. Enabling Project Success Under Any Delivery Method

AN OWNER'S GUIDE TO CONSTRUCTION AND PROGRAM MANAGEMENT. Enabling Project Success Under Any Delivery Method AN OWNER'S GUIDE TO CONSTRUCTION AND PROGRAM MANAGEMENT Enabling Project Success Under Any Delivery Method Acknowledgments CMAA gratefully acknowledges the time and efforts of those who served as contributing

More information

Prequalification Supplement for First Tier Subcontractors under CM at Risk Wake Technical Community College Early Site North Campus Project

Prequalification Supplement for First Tier Subcontractors under CM at Risk Wake Technical Community College Early Site North Campus Project NC General Statue 143-128.1.c states, The construction manager at risk shall contract directly with the public entity for all construction; shall publically advertise as prescribed in G.S. 143-129; and

More information

Office of the Inspector General

Office of the Inspector General Office of the Inspector General Commonwealth of Massachusetts Gregory W. Sullivan Inspector General Experience of Massachusetts Public Agencies with Construction Management at Risk Under M.G.L. c. 149A

More information

Fundamentals of a Construction Audit. August 7, 2014

Fundamentals of a Construction Audit. August 7, 2014 Fundamentals of a Construction Audit August 7, 2014 Agenda Definitions Risk Based Approach What Determines Risk Fraud Construction Risks What to Audit Red Flags Why Audit Prevention Wrap-up 1 Definitions

More information

OBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.

OBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments. OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for administration of construction manager

More information

CM/GC Guidelines FOR PUBLIC OWNERS. A Joint Publication Building Your Quality of Life. AGC Publication Number 2912 NASFA Publication Number F-3007

CM/GC Guidelines FOR PUBLIC OWNERS. A Joint Publication Building Your Quality of Life. AGC Publication Number 2912 NASFA Publication Number F-3007 CM/GC Guidelines FOR PUBLIC OWNERS AGC Publication Number 2912 NASFA Publication Number F-3007 A Joint Publication Building Your Quality of Life Building Your Quality of Life Nothing contained in this

More information

REQUEST FOR QUALIFICATIONS For an AS-NEEDED CONSULTING PROJECT MANAGER(S) With Hospital, Clinical Care and Building Systems Renewal Experience

REQUEST FOR QUALIFICATIONS For an AS-NEEDED CONSULTING PROJECT MANAGER(S) With Hospital, Clinical Care and Building Systems Renewal Experience REQUEST FOR QUALIFICATIONS For an AS-NEEDED CONSULTING PROJECT MANAGER(S) With Hospital, Clinical Care and Building Systems Renewal Experience For the UNIVERSITY OF CALIFORNIA, SAN DIEGO On behalf of FACILITIES

More information

Community Program Directors, All Community Facilities Staff, State Architects and Engineers

Community Program Directors, All Community Facilities Staff, State Architects and Engineers TO: State Directors Rural Development RD AN No. 4794 (1942-A) September 28, 2015 ATTN: Community Program Directors, All Community Facilities Staff, State Architects and Engineers FROM: Tony Hernandez /s/

More information

CM at Risk. process of design-bid-build as an established method of project delivery. a 3D/International essay

CM at Risk. process of design-bid-build as an established method of project delivery. a 3D/International essay a 3D/International essay CM at Risk Management at Risk (CM at Risk), similar to established private sector methods of construction contracting, is gaining popularity in the public sector. It is a process

More information

Project Organization. System and Project Management 1.040/1.401J Nathaniel Osgood

Project Organization. System and Project Management 1.040/1.401J Nathaniel Osgood Project Organization System and Project Management 1.040/1.401J Nathaniel Osgood Center for Construction and Research Education Department of Civil and Environmental Engineering Massachusetts Institute

More information

Lease-Leaseback 201:Lessons Learned in Dancing School. Our Agenda

Lease-Leaseback 201:Lessons Learned in Dancing School. Our Agenda Lease-Leaseback 201:Lessons Learned in Dancing School CASH Annual Conference February 26, 2013 Travis Kirk, Merced Union High School District Mark Quattrocchi, Quattrocchi Kwok Architects Glenn Gould,

More information

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874 ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial

More information

Members, Council of Presidents. Advertisements for Architect/Engineer and Construction Manager Services and Calls for Bid

Members, Council of Presidents. Advertisements for Architect/Engineer and Construction Manager Services and Calls for Bid July, 2003 MEMORANDUM UCF-05.01-07/03 TO: Members, Council of Presidents FROM: SUBJECT: Advertisements for Architect/Engineer and Construction Manager Services and Calls for Bid AUTHORITY: Sections 240.209(3)(p),

More information

Policy Number: 3-804 Policy Name: Professional Services and Construction Services Procurement

Policy Number: 3-804 Policy Name: Professional Services and Construction Services Procurement Page 1 3-804 Professional Services and Construction A. Project Delivery Methods 1. A university may procure design services, construction and construction services, as applicable, under any of the following

More information

Guidelines. for. Construction and Renovation. Parish Facilities

Guidelines. for. Construction and Renovation. Parish Facilities Guidelines for Construction and Renovation of Parish Facilities Building Commission Diocese of Des Moines 2014 Table of Contents Introduction.. 1 Pastoral Planning. 2 Approval of Bishop. 2 Needs Assessment

More information

OREGON PUBLIC CONTRACTING COALITION DESIGN-BUILD WHITEPAPER

OREGON PUBLIC CONTRACTING COALITION DESIGN-BUILD WHITEPAPER NOTE: REFERENCES TO ORS 279 AND BOLI REGULATIONS CONTAINED HEREIN DO NOT REFLECT ANY CHANGES OCCURING SUBSEQUENT TO THE PUBLICATION DATE. THE USER OF THIS DOCUMENT IS RESPONSIBLE FOR USING REGULATIONS

More information

REPORT TO THE UTAH LEGISLATURE. A Performance Audit of School Building Construction. November 2008. Number 2008-14. Audit Performed By:

REPORT TO THE UTAH LEGISLATURE. A Performance Audit of School Building Construction. November 2008. Number 2008-14. Audit Performed By: REPORT TO THE UTAH LEGISLATURE Number 2008-14 A Performance Audit of School Building Construction November 2008 Audit Performed By: Audit Manager Audit Supervisor Audit Staff Tim Osterstock Wayne Kidd

More information

ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER. Occupation Specific Technical Requirements

ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER. Occupation Specific Technical Requirements ENGINEERING COMPETENCIES ENTRY LEVEL ENGINEER Responsible for performing entry level engineering analysis, design, plan, review and inspection for small to medium projects and/or designated segments of

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) Administration of Project: Local Higher Education Project Name FAES- Student Success Center Response Deadline 03/04/2013 4:30 pm local time Project Location

More information

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Shideler Hall Renovation Response Deadline 12/20/13

More information

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR DB-BIM Contract No. 5890 07/14 Project No. 02-3210 AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR 1 DB-BIM Contract

More information

Architectural and Engineering Basic Services Fee Estimating Guidelines

Architectural and Engineering Basic Services Fee Estimating Guidelines Architectural and Engineering Basic Services Fee Estimating Guidelines Basic Services is the design work customary on a typical project to take an established building program, site, and budget, and then

More information

Project success depends on

Project success depends on Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we

More information

DIVISION OF FACILITIES AND CONSTRUCTION MANAGEMENT ARCHITECTURAL/ENGINEER FEES EFFECTIVE DATE: July 13, 2015

DIVISION OF FACILITIES AND CONSTRUCTION MANAGEMENT ARCHITECTURAL/ENGINEER FEES EFFECTIVE DATE: July 13, 2015 I. Purpose DIVISION OF FACILITIES AND CONSTRUCTION MANAGEMENT To provide a standard for a reasonable A/E fee structure on State of Utah Projects II. Background The State Procurement Code requires that

More information

BROWN UNIVERSITY PROJECT DELIVERY PROCESS GUIDELINES D EPARTMENT OF F ACILITIES M ANAGEMENT

BROWN UNIVERSITY PROJECT DELIVERY PROCESS GUIDELINES D EPARTMENT OF F ACILITIES M ANAGEMENT BROWN UNVERSTY PROJECT DELVERY PROCESS GUDELNES D EPARTMENT OF F ACLTES M ANAGEMENT Facilities Management Mission Statement The mission of Facilities Management is to support the University by enhancing

More information

SAN FRANCISCO AIRPORT COMMISSION MINUTES

SAN FRANCISCO AIRPORT COMMISSION MINUTES SAN FRANCISCO AIRPORT COMMISSION MINUTES April 22, 2014 Special Meeting 9:00 A.M. Room 400 - City Hall #1 Dr. Carlton B. Goodlett Place (400 Van Ness Avenue) City and County of San Francisco EDWIN M. LEE,

More information

PROJECT MANAGEMENT BASICS

PROJECT MANAGEMENT BASICS PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the

More information

Notes from National Contract Management Association (NCMA) Panel Understanding the Proposal Bid-No Bid Decision How to Increase Competition

Notes from National Contract Management Association (NCMA) Panel Understanding the Proposal Bid-No Bid Decision How to Increase Competition Panel Members Adelle Pierce President, AM Pierce & Associates Incorporated Dawn Rich President, Amelex Will Weston, President and CEO, Greenfield Engineering Corporation Glen Ives, Group Vice President

More information

Construction Management at Risk: An Innovative Project Delivery Method at Stormwater Treatment Area in the Everglades, Florida

Construction Management at Risk: An Innovative Project Delivery Method at Stormwater Treatment Area in the Everglades, Florida Construction Management at Risk: An Innovative Project Delivery Method at Stormwater Treatment Area in the Everglades, Florida Young H. Kwak, Ph.D. 1 and Randall Bushey, P.E. 2 Abstract The traditional

More information

A Guidebook to Local Government Construction Projects

A Guidebook to Local Government Construction Projects A Guidebook to Local Government Construction Projects Association County Commissioners of Georgia 3rd Edition 2011 Sponsored by A Guidebook to Local Government Construction Projects 3rd Edition March 2011

More information

Maplewood at Cheshire County, Westmoreland, NH CONCEPTUAL PLANS AND COST ESTIMATES Request for Proposals. Design and Engineering

Maplewood at Cheshire County, Westmoreland, NH CONCEPTUAL PLANS AND COST ESTIMATES Request for Proposals. Design and Engineering Maplewood at Cheshire County, Westmoreland, NH CONCEPTUAL PLANS AND COST ESTIMATES Request for Proposals Design and Engineering Issue Date: July 02, 2015 Optional Informational Meeting July 09, 2015 1:00

More information

REQUEST FOR PROPOSAL FOR ARCHITECTURAL DESIGN SERVICES. The Battery Conservancy

REQUEST FOR PROPOSAL FOR ARCHITECTURAL DESIGN SERVICES. The Battery Conservancy REQUEST FOR PROPOSAL FOR ARCHITECTURAL DESIGN SERVICES The Battery Conservancy Issue Date: March 23, 2012 Responses Due: April 20, 2012 Introduction The Battery Conservancy ( TBC ) is a 501(c)(3) not-for-profit

More information

Report on SELECTING THE BEST PROJECT DELIVERY METHOD USING THE ANALYTICAL HIERARCHY PROCESS (AHP)

Report on SELECTING THE BEST PROJECT DELIVERY METHOD USING THE ANALYTICAL HIERARCHY PROCESS (AHP) Report on SELECTING THE BEST PROJECT DELIVERY METHOD USING THE ANALYTICAL HIERARCHY PROCESS (AHP) Prepared for Dr. Soliman Almohawis CEM 520 Construction Contracting & Administration By Abdullah S. Alzouri

More information

Request for Qualifications & Proposal. Architectural Team. Lake County School District R-1. On-Call Services. For

Request for Qualifications & Proposal. Architectural Team. Lake County School District R-1. On-Call Services. For Request for Qualifications & Proposal Architectural Team For Lake County School District R-1 On-Call Services Provided by: Submittal Deadline: April 23, 2015 Time: 5:00 PM 1.0 Introduction On behalf of

More information

Contractor s Estimation of Cost and Bidding Strategy. Construction Project Management_Kumar Neeraj Jha

Contractor s Estimation of Cost and Bidding Strategy. Construction Project Management_Kumar Neeraj Jha 1 Contractor s Estimation of Cost and Bidding Strategy Contents 1.1 Contractor s estimation and bidding process 1.2 Bidding models 1.3 Determination of optimum mark-up level 1.4 Bidding and estimation

More information

How to get value for money from service providers on major projects

How to get value for money from service providers on major projects How to get value for money from service providers on major projects Session Focus Contracting as a relationship Identifying win/win arrangements Procurement & Planning on major projects Understanding the

More information

DESIGN-BUILD IN CALIFORNIA

DESIGN-BUILD IN CALIFORNIA DESIGN-BUILD IN CALIFORNIA 1. Why Design-Build Design Build Drivers, Goals and Challenges (see Reed Construction Data and DGS handouts) 2. Who Can Do Design-Build Design-Build Authorizing Statutes for

More information

Lesson 4: Use of Feasibility Studies and Consultants

Lesson 4: Use of Feasibility Studies and Consultants Lesson 4: Use of Feasibility Studies and Consultants Objectives At the completion of this lesson, students will be able to: 1. Define feasibility study and describe its purpose. 2. Describe the components

More information

BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS

BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS CARROLL COUNTY PUBLIC SCHOOLS ADMINISTRATIVE REGULATIONS BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS Administrative Procedures For Appointment of Architectural, Engineering and Construction

More information