Scheduling is Not about Chronology; it s about

Size: px
Start display at page:

Download "Scheduling is Not about Chronology; it s about"

Transcription

1 Scheduling is Not about Chronology; it s about Logic! Table of Contents Intro 1 Current Issues in Scheduling 2 Activity Sequencing versus Determining Causality 3 Sequencing Relationships in the Wiki-Website Schedule 4 Cause-And-Effect Relationships in the Wiki-Website Schedule 5 What Future Scheduling Software Should Do in the Wiki-Website Schedule 6 All Our Current Dependencies are Later-Than Dependencies! 6 Why Are Causal Relationships Important? 7 Other Issues That Will Be Resolved With Causal Relationships 8 Integration of Critical Path and Critical Chain Scheduling 8 What Scheduling Terminology Can Stay For Causal Dependencies? 9 What Scheduling Terminology Should Change For Causal Dependencies? 9 Changes Needed in CPM and in Scheduling Software 10 Conclusion 12 Intro Definition of the terms: Scheduling is the act of determination of dates for project deliverables, activities and milestones. Note that the term itself is not defined in the PMBOK or the Practice Standard for Scheduling; I had to derive this definition from the definition of the term project schedule that is defined in those documents. Chronology is the arrangement of events in their occurrence order (Wikipedia). Logic is the study of the principles of valid demonstration (proof) and inference (deriving a conclusion from premises) (Wikipedia). In this article, we would like to discuss if scheduling is a matter of determining chronology or a matter of determining logic. Some terms used in scheduling imply scheduling is a matter of determining chronology, e.g. terms like activity sequencing, predecessor, successor, lag and lead. Other terms used in scheduling imply scheduling is a matter of logic, e.g. terms like network logic and modeling. It appears to me that the scheduling profession is at a cross-road where it needs to decide whether scheduling should be a matter of chronology or a matter of logic or both but each in their own school of thought. In this article, we will argue that scheduling should be a matter of logic; we think schedules will be better if they are logical models of projects. ProjectPro Corp Page 1

2 Current Issues in Scheduling A successor often does not succeed in time. For example, tasks involved in the following relationships do not succeed each other chronologically: start-to-start, finish-to-finish, finish-to-start with a lead time. Similarly, predecessors hardly ever precedes (entirely)! The terms are hard to understand and therefore hard to use. Activity sequences often change. Schedulers cannot rely blindly on their network logic to produce viable scenarios of their schedule when they enter progress. When schedulers use dependencies as activitysequencers, their dependencies are often arbitrary and will often change. Ideally, when schedule updates are entered, the network logic always produces a schedule that makes sense from a practical point of view. Current schedules are too maintenance hungry. Schedulers often create network logic that is very maintenance hungry. Ideally, you create the network of dependencies once and you don t need to change it (other than refining it). Current scheduling software does not allow dynamic due dates. Our schedule software does not allow us to create dynamic due dates. Have you ever been saved when a team member who works on a critical tasks announced (s)he will slip their deliverable? If programmers deliver the source code late, the documentation people suddenly also have more time to complete their deliverables and we will end up moving due dates often, spending a lot of time on maintaining our schedule. Current scheduling software does not allow dynamic windows of opportunity. Our schedule software does not allow us to create dynamic windows of opportunity for tasks. Many tasks of secondary importance have a window of opportunity that should shift when the Critical Path shifts. For example, software documenters can start when the software screens are finalized, but have to be finished when the software is implemented. This window of opportunity shifts constantly as progress is ahead or behind on the programming, testing or debugging tasks. Scheduling software does not allow you to schedule part of your schedule backward. Your entire schedule is scheduled forward or backward. Often a milestone is an event from which certain activities need to be scheduled backward. Often the chains of tasks that are of secondary importance need to be scheduled backwards from a critical milestone on the Critical Path. As one life-long scheduler, Ralph Kuhn PMP, puts it: Ten years ago, I had no Start-to-Finish dependencies to speak of in my schedules, now I sometimes set up to 5% of my dependencies as Start-to-Finish dependencies in my construction schedules! ProjectPro Corp Page 2

3 Activity Sequencing versus Determining Causality To introduce the issue with a simple example, consider you have two tasks: Prepare for exam and Take the exam. In which way would you schedule these two tasks; in way A or in way B as shown below: A Prepare for exam FS Dependency Take exam B Prepare for exam SF Dependency Take exam ProjectPro Corp. If you choose A, you take the process Activity Sequencing from the PMBOK (3 rd Edition) literally, and tend to determine chronology between their tasks: You prepare before taking exam, so the finish of preparing should be linked to the start of take exam. The result is a Finish-to-Start (FS) relationship. The predecessor task precedes the successor in terms of chronology, which makes sense. If you choose B, you treat dependencies to model cause-and-effect relationships between tasks (logic): The start date of the exam should drive where the preparation task is scheduled, so the start of Take exam should be linked to the finish of Prepare for exam. The result is a Start-to-Finish (SF) relationship. The predecessor actually succeeds the successor in terms of chronology, which does NOT make sense. The successor actually precedes. Which schedule is better? In our view, schedule B is more accurately reflects reality. There are several reasons for this: 1. In schedule A, the finish-to-start dependency implies that if you need more time for prepare for exam, you will (and can) postpone the exam. Only some exams can be rescheduled; the PMP-exam and the driver s license exam. In schedule B, the exam date drives when you need to be finished with the preparation, which is valid for most other exams. ProjectPro Corp Page 3

4 2. Schedule A suggests that if prepare for exam will take less time, you will reschedule the exam to an earlier date. In schedule B, the exam date will stay where it is. 3. In schedule A, if the exam is rescheduled, the preparation task stays scheduled where it is, whereas in schedule B the task prepare for exam would be rescheduled accordingly. As you can see, schedule B is able to withstand real-life changes much better than schedule A and is in our view a better schedule of the situation. Schedule B is a dynamic model of the situation and will need less maintenance and provide forecasts that are more accurate. Over the years, we have made some observations: Most people have difficulties with dependencies as sequencing relationships because when they sometimes see that the successor precedes and that the predecessor succeeds, it does not make sense to them (in terms of chronology). It does not make sense to me either. Many people struggle with the process of Activity Sequencing because it is arbitrary and subject to change. Sequence relationships are not stable relationships; they simply ask you to express your personal preference. When the schedule shifts, the sequencing relationships often need to be changed. The sequencing relationships are very maintenance hungry. The PMBOK calls for sequencing the activities by calling the process Activity Sequencing. We can see here that some terminology used and defined in the PMBOK does not support thinking of dependencies as cause-and-effect relationships. In my view, this process should call for Determining Causality between activities instead. We will now explore these concepts in a larger, more realistic schedule situation, the creation of a wiki-based website. Sequencing Relationships in the Wiki-Website Schedule If you create a small schedule in terms of Activity Sequencing the following would result: Explanation: The task write documentation can start as soon as the screens of the computer software application are completed. The task write documentation has 5 days of total slack, because it is scheduled to be started very early. The problem with this schedule is that documentation is scheduled too early in the project; documentation is seldom completed before the feature is entirely coded. ProjectPro Corp Page 4

5 Cause-And-Effect Relationships in the Wiki-Website Schedule If you create the schedule in terms of cause-and effect or impact relationships (causality), the following schedule would result. The task write documentation is now scheduled backward from when the feature is expected to be completed using a Start-to-Finish relationship: Explanation: The way the current scheduling software Microsoft Project handles this situation is: The startto-finish relationship from feature completed to write documentation overrides the dependency from screens completed to write documentation because the start-to-finish dependency tells the software that it should schedule the finish of task write documentation at or after the start of feature completed. We don t agree that write documentation should be allowed to finish after feature completed, but that makes it end up scheduled close to the feature completed milestone. The start-to-finish dependency does not have an Earlier-Than attribute, neither Microsoft Project nor Oracle s Primavera has Earlier-Than dependencies as a feature. The strength of this schedule is that the schedule is more realistic in terms of the dates for the task write documentation. It is scheduled to be done as late as possible and does not finish before the features are coded (code feature). The problem with this schedule is that the Total Slack on the task write documentation is calculated to be 7 days; it can slip to May 30 th. The total slack should be only 5 days, the window of opportunity from May 8 until May 21 minus two weekends and minus the duration of the task: 13 2*2 4 = 5 days. You can see here that the current scheduling software does not support thinking of dependencies in terms of cause-and-effect and entering them as such. The software does not have earlier-than dependencies. By the way, the screen shots are made in Microsoft Project, but Primavera calculates the Total Slack (Total Float) in this project exactly the same; it is how the Critical Path Method and algorithm are defined. The task write documentation is now an open end (loose end) in the network of dependencies; its finish date is not constrained by anything but the project finish date. Technically, this is wrong, because you cannot still be writing your documentation while you are implementing the feature; you need the documentation in order to implement the feature! Of course, master schedulers have worked around this by setting an extra Finish-to-Start dependency from write documentation to implement feature to bring the total Slack down and tie up the loose end. If the Start-to-Finish dependencies were treated by the scheduling software as an Earlier-Than relationship, there would not be less slack on task write documentation, because with the Start-to-Finish-Earlier dependency, we are telling the software that the start of the milestone Feature Completed should cause write documentation to end. We would have a perfect, logical model of the situation. ProjectPro Corp Page 5

6 What Future Scheduling Software Should Do in the Wiki-Website Schedule Scheduling software should allow us to model the wiki-project in terms of cause-and-effect logic: 4 d 0 d Finish-to-Start-Later Start-to-Finish-Earlier Finish-to-Start-Later (FS Later) dependency from screens completed to write documentation. Start-to-Finish-Earlier (SF Earlier) dependency from feature completed to write documentation. The total slack on write documentation is calculated as the window of opportunity that the two dependencies on the task provide. The task is currently scheduled to finish just before the milestone feature completed but could move up to 5 days earlier: Total Slack = 5 days. This schedule is able to withstand almost any type of change or progress that you throw at it without having to revise the dependencies: If the first five tasks slip, the window of opportunity for write documentation will slip accordingly. If code feature or test feature takes longer the window of opportunity for write documentation expands; the documentation specialist will have more time. If they take shorter, it shrinks. This is often what happens in practice. Write documentation is cut off when the feature completed occurs, which is often what happens with documentation in practice. The documentation is shipped as-is. All Our Current Dependencies are Later-Than Dependencies! The four types of dependencies, we currently have, are all Later-Than dependencies: If you set a Finish-to-Start dependency without any lag or lead, it means that the start of the driven task (dependent) cannot be earlier than, but can slip later than the finish of the driver task (independent). If you set a Start-to-Start dependency without any lag or lead, it means that the start of the driven task cannot be earlier than, but can slip later than the start of the driver task. If you set a Finish-to-Finish dependency without any lag or lead, it means that the finish of the driven task cannot be earlier than, but can slip later than the finish of the driver task. If you set a Start-to-Finish dependency without any lag or lead, it means that the finish of the driven task cannot be earlier than, but can slip later than the start of the driver task. ProjectPro Corp Page 6

7 In the case of the exam, we concluded that the Start-to-Finish dependency was the better type of dependency in most cases, but we still have a problem. The Start-to-Finish dependency between these tasks allows the Prepare for Exam task to extend its duration and to slip its finish date past the start date of the Take Exam task, which of course does not make sense in this situation as shown in the next illustration: Start-to-Finish-Later (existing dependency): prepare for exam take exam Start-to-Finish-Earlier (new dependency): prepare for exam take exam ProjectPro Corp. What we need to model this situation properly is a new type of dependency, a Start-to-Finish-Earlier dependency. If we could make the Start-to-Finish of the Earlier-Than character as shown in the illustration, we could tell our scheduling tool that the Prepare for Exam task should always finish before the Take Exam task. This would also restrict the Total Slack for the task, which the current Start-to-Finish dependencies don t do. Do we need all four types of dependencies to provide an Earlier-Than and a Later-Than variety? Yes, all dependencies should allow you to indicate if it is an Earlier-Than or Later-Than relationship because more types of dependencies provide more flexibility to model a wide variety of project situations. Specifically: Earlier-than dependencies give us the possibility of dynamic due dates. Dynamic due dates are rescheduled automatically when the network moves and it recalculates the slack (float) of each task constantly. Dynamic due dates are a very useful feature that cannot be found in any scheduling software currently, as far as we are aware of. Earlier-than dependencies give us the possibility to model dynamic windows of opportunity. Why Are Causal Relationships Important? There are several reasons: Cause-and-effect relationships make it easier to analyze how a network updates the scheduled dates. Each arrow will be treated as an impact relationship, and in order to understand how the impact will flow through the schedule, you just need to follow the arrows in the direction that they point with cause- and effect relationships. ProjectPro Corp Page 7

8 Cause-and-effect relationships in combination with Earlier-Than dependencies allow you to create: Dynamic due dates: The date when you need to be ready is often dependent on when other people will be ready with their work. If we had earlier-than dependencies, we could say if this milestone slips, extend the time allocated for that task (earlier-than relationship). This is a useful concept in many situations. Dynamic windows-of-opportunity: The period in which a task can take place can shift through dependencies. You will be able to give a task a later-than relationship with an early task as well as an earlier-than relationship with a later task, which creates a window-of-opportunity for the task. This is a useful concept in many situations. Other Issues That Will Be Resolved With Causal Relationships Backward scheduling from a fixed finish date does not work well in current scheduling software: If all tasks are scheduled as late as possible, there are no buffers in the schedule and the project will be late. An ALAP task may have total slack (total float), but if you start work on the day the task is scheduled and enter the actual start date, the total slack suddenly disappears. If you do want to schedule as late as possible, you have to build buffers into the schedule in appropriate places, which is exactly what Critical Chain schedulers do. Nobody understands Start-to-Finish relationships currently. Nobody can produce an example in which to use them. The Start-to-Finish dependency is hardly ever used in schedules, because it is hard to come up with an example where the start of one task should drive the finish date of another task. If you can create a Start-to-Finish-Earlier relationship, it will have utility and application in practice. Primavera already has a solid hammock task feature, but Microsoft Project does not. The new Earlier-Than attribute of dependencies will allow us to create hammock tasks where needed that fluctuate in duration as the network shrinks or expands. We can then constrain a hammock task, like Manage the project, to start Later-Than contract award and simultaneously, we can force the task to finish Earlier-Than the project finish milestone. If the task can also automatically stretch or shrink driven by its dependencies, we have a real hammock task feature in Microsoft Project. Earlier-than dependencies will allow you to create dynamic buffers on tasks in secondary chains. This will allow us to do traditional Critical Path scheduling or Critical Chain scheduling with a single scheduling application. We will explain this in more detail. Integration of Critical Path and Critical Chain Scheduling In current scheduling software you have to choose between scheduling your project in either the Critical Path way or the Critical Chain way and the resulting schedules cannot be converted back and forth. A Critical Chain schedule with buffers is essentially a different schedule than a Critical Path schedule, because of: The time buffers that need to be inserted in every chain The ALAP scheduling ProjectPro Corp Page 8

9 The tight estimates The resource-critical path The avoidance of multi-tasking Particularly, the buffers make a Critical Chain schedule different from its Critical Path brother. With the new type of dependency that we propose in this article, we think it will be possible to switch back and forth between a Critical Path view of the schedule and a Critical Chain view of the schedule. What Scheduling Terminology Can Stay For Causal Dependencies? Terms that can stay the same or that can keep their current definition: The terms that characterize the different kinds of dependencies can stay the same: Finish-to-Start: creates an impact from the finish of the driver task to the start of the driven task; if the finish date of the driver task moves, the start date of the driven task will move with it. When the driver finishes, the driven task is triggered to start. Finish-to-Finish: creates an impact from the finish of the driver task to the finish of the driven task. When the driver finishes, the driven task is forced to finish. Start-to-Start: creates an impact from the start of the driver task to the start of the driven task. When the driver starts, the driven task will be triggered to start. Start-to-Finish: creates an impact from the start of the driver task to the finish of the driven task. When the driver starts, the driven should finish. When there are multiple dependencies, the most constraining dependency will take effect. The term Network Logic is ok. The term Network Diagram is ok. What Scheduling Terminology Should Change For Causal Dependencies? Terms that need to change or that need to be redefined in our standards: We need to remove the terms Predecessor and Successor from the PMBOK and from our vocabulary and replace them with the words Driver and Driven or Independent and Dependent task. The word Predecessor implies that this task always precedes, which is often not the case, for example in a Start-to-Start dependency. The word Successor implies that this task always succeeds which is often not the case, for example in a Start-to-Start dependency. Note that, even if we decide not to start treating dependencies as cause-and-effect relationships, we need to find better terminology for Predecessor and Successor. We need to rename the PMBOK process Activity Sequencing to something else, like Determine Causality or Determine Relationships. A lag is defined in the PMBOK (3 rd Edition) as that it directs a delay in the successor. The words lag and delay imply sequencing and chronology and are confusing when you treat dependencies as cause-and-effect. The term lag should be dropped; the term lag is ProjectPro Corp Page 9

10 not appropriate any longer in that case, because the driven task is not necessarily lagging the driver task, for example in a Start-to-Start relationship. The term lag needs to be replaced by the term dependency duration, gap or time-spacer. The term lag relates to time and chronology and is no longer appropriate. If a dependency has a duration, it will naturally create a gap between the ends of the driver and driven tasks that are linked (FS, SS, FF and SF relationship). If you add a positive lag of 2 days (dependency duration) onto the Start-to-Finish dependency (Later-than), the driven task write documentation will go to the right (later) in current scheduling software (Microsoft Project and Oracle s Primavera) as in the following screen shot: Instead, in this situation the lag should be treated by scheduling software as a duration on the dependency and should go to the left (earlier). An Earlier-Than dependency will do this (We tricked the software to make the following screen shot). You can see why terms like gap or dependency duration are more appropriate: A lead is defined in the PMBOK (3 rd Edition) as that it allows an acceleration of the successor (PMBOK, 3 rd Edition). The word lead can be dropped entirely if the field dependency duration ( gap or time spacer ) in scheduling software allows entering negative values (even though for activities, negative durations do not make sense). Changes Needed in CPM and in Scheduling Software The most important change is that in the Critical Path Method (CPM), the Critical Path algorithm needs to be enhanced so it can process the new Earlier-Than dependencies. The algorithm needs to calculate Early Start, Early Finish, Late Start and Late Finish dates correctly when the scheduler uses Earlier-Than dependencies. The current generation of scheduling software treats dependencies exclusively that the independent (driver) task imposes a Later-Than constraint on the dependent (driven) task. In addition to this type of relationship between tasks, the next generation of scheduling software also needs Earlier-Than dependencies. Therefore, in scheduling software we need the following change. The dialog box in which you specify the type of dependencies should provide the following options: ProjectPro Corp Page 10

11 Existing dependency relationships: FS: Start driven task after Finish task driver = Finish-to-Start-Later (FSL) SS: Start driven task after Start task driver = Start-to-Start-Later (SSL) FF: Finish driven task after Finish task driver = Finish-to-Finish-Later (FFL) SF: Start driven task after Finish task driver = Start-to-Finish-Later (SFL) New dependency relationships: Start driven task before Finish task driver = Finish-to-Start-Earlier (FSE) Start driven task before Start task driver = Start-to-Start-Earlier (SSE) Finish driven task before Finish task driver = Finish-to-Finish-Earlier (FFE) Start driven task before Finish task driver = Start-to-Finish-Earlier (SFE) The new thing here is that these options allow you to create dependencies that kick back in time (earlier) instead of dependencies that can only kick forward (later). Graphically, we should be able to see immediately if a dependency is of the later-than or earlier-than type. We can accomplish this if we use the following depiction for the later-than and earlier-than dependencies: Finish-to-Start-Later Finish-to-Start-Earlier ProjectPro Corp. As you can see, you just have to look at the direction of the arrowhead to understand in which direction the impact will happen. If the arrow points to the right, it is a later-than relationship. If it points to the left, it is an earlier-than relationship. ProjectPro Corp Page 11

12 Conclusion In this article, we proposed to change the paradigm of scheduling from determining chronology to determining causality. This requires us to see scheduling as creating a dynamic model of the project that needs little maintenance and that produces forecasts that are accurate under most circumstances that can occur. For this, we need a new type of dependency relationship, the earlier-than dependencies that currently do not exist in scheduling software. Author of Dynamic Scheduling with Microsoft Office Project 2003 President ProjectPro Corp. Ottawa, ON, Canada Tel EricU@ProjectProCorp.com ProjectPro Corp Page 12

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Precedence Diagram Method. CSTM 462 Planning & Scheduling Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Basic CPM Calculations

Basic CPM Calculations Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.

More information

Scheduling Best Practices

Scheduling Best Practices In a continuing series of articles on specific aspects of critical path method (CPM) scheduling, Warner examines various facets of the process of preparing, analyzing and utilizing schedules in project

More information

Project Management. Week 4- Project Planning and Network Diagrams 2012-13

Project Management. Week 4- Project Planning and Network Diagrams 2012-13 Project Management Week 4- Project Planning and Network Diagrams 2012-13 Last Week Project Appraisal Techniques Scoping Tools-Breakdown Structures Estimation This Week What is Planning? Purpose of Planning

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method

More information

Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them

Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Sponsored by Is Your Schedule Correct? Common Scheduling Mistakes and How to Avoid Them Joseph A. Lukas PMP, CSM, CCP, PE White Paper 1-888-762-3683 www.pmcentersusa.com Joe Lukas & PM Centers USA, LLC

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Scheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group

Scheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group Scheduling Best Practices Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group Paul Brough has experience in multiple phases of project management, including

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective 1. Abstract PM WORLD TODAY FEATURED PAPER MARCH 2009 Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective By Satya Narayan Dash, PMP, MCP and Uttam Kumar Singh, PMP, PAHM MS Project

More information

Chapter-6. Developing a Project Plan

Chapter-6. Developing a Project Plan MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies

More information

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment // Taming an Unruly Schedule Using the 14-Point Schedule Assessment Dr. Dan Patterson, PMP CEO & President, Acumen February 2010 www.projectacumen.com Table of Contents Introduction... 3 The 14-Point Assessment...

More information

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP PMBOK Guide 5 th Edition and MS Project 2010: A Practical Step-by-Step Approach 1. Abstract By Satya Narayan Dash, PMP, CSM, MCP Project Management Body of Knowledge (PMBOK) Guide, from PMI, comes with

More information

Problems, Methods and Tools of Advanced Constrained Scheduling

Problems, Methods and Tools of Advanced Constrained Scheduling Problems, Methods and Tools of Advanced Constrained Scheduling Victoria Shavyrina, Spider Project Team Shane Archibald, Archibald Associates Vladimir Liberzon, Spider Project Team 1. Introduction In this

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added. Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

Information Technology Project Management

Information Technology Project Management Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

The Project Planning Process Group

The Project Planning Process Group 3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity

More information

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP

SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP SCHEDULING AND TIME MANAGEMENT Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS

More information

Project Initiation and Revision Training Manual. Table of Contents

Project Initiation and Revision Training Manual. Table of Contents for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...

More information

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and

More information

CALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS

CALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS CALCULATION DIFFERENCES WHEN IMPORTING FROM MICROSOFT PROJECT 2003-2010 INTO ORACLE PRIMAVERA P6 VERSION 7 BY PAUL E HARRIS OF EASTWOOD HARRIS TABLE OF CONTENTS 1 INTRODUCTION 3 2 AIM 3 3 SUMMARY 3 4 LEVELS

More information

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0 ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The

More information

DCMA 14-Point Assessment Metrics

DCMA 14-Point Assessment Metrics DCMA 14-Point Assessment Metrics The integrity of a CPM schedule is one of the critical factors in improving a project s likelihood of success 1! There is a well-established correlation between the quality,

More information

Microsoft Project 2010 Advanced

Microsoft Project 2010 Advanced Microsoft Project 2010 Advanced Table Of Contents SECTION 1 - REFRESH OF THE BASICS... 3 GUIDE INFORMATION... 4 Introduction... 4 How To Use This Guide... 4 Objectives... 4 Instructions... 4 PROJECT INFORMATION

More information

Project Management Dashboard Pro v5 Documentation

Project Management Dashboard Pro v5 Documentation Project Management Dashboard Pro v5 Documentation Installation There is NO installation required. It s just a macro enabled excel file that opens if you have Excel 2007, 2010, 2013 and 2016 on your Windows

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

Introduction. http://www.alexsbrown.com/ Page 1

Introduction. http://www.alexsbrown.com/ Page 1 Modeling Tough Scheduling Problems with Project Management Software Alex S. Brown, PMP, Strategic Planning Manager, Mitsui Sumitomo Marine Management (U.S.A.), Inc. Introduction Despite year-over-year

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Activity Definition Input Work Breakdown Structure Scope Statement Historical Information

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle. Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

Introduction to Project Management

Introduction to Project Management L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You

More information

Scheduling Best Practices

Scheduling Best Practices In this article, as part of a continuing series of articles regarding critical path method (CPM) scheduling, Warner reviews various facets of the process of preparing, analyzing and utilizing schedules

More information

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

Importance of Finish to Start Successors

Importance of Finish to Start Successors Importance of Finish to Start Successors Jim Aksel, PMP, PMI SP Director of Project Management Celeris Systems, Inc. In addition to creating schedule logic the way workers ordinarily perform their business

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

Computer Training Centre University College Cork

Computer Training Centre University College Cork Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2007 Level 1: Creating Project Tasks Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.

More information

Microsoft Project Dissected

Microsoft Project Dissected Microsoft Project Dissected by Ron Winter, PSP Schedule Analyzer Software Copyright 2012 Third Annual Construction CPM Conference Introduction Although Oracle/Primavera P6 is dominant Many contracts specify/allow

More information

Lecture 26 CPM / PERT Network Diagram

Lecture 26 CPM / PERT Network Diagram Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review

More information

Project Time Management

Project Time Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-981-3 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-981-3 The material contained within

More information

Chapter 6: Project Time Management

Chapter 6: Project Time Management CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD jwoo5@calstatela.edu California State University, LA Computer and Information System Department Chapter 6: Project Time Management

More information

How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)

How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows) Project management M project tutorial Part 1: Project beginning and the Gantt chart Purpose Project management by using Microsoft Project software Introduction Project management is a process of organizing,

More information

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1 IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break

More information

CPM-200: Principles of Schedule Management

CPM-200: Principles of Schedule Management CPM-: Principles of Schedule Management Lesson B: Critical Path Scheduling Techniques Instructor Jim Wrisley IPM Fall Conference PMI-College of Performance Management Professional Education Program Copyright

More information

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E. Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June

More information

Network Planning and Analysis

Network Planning and Analysis 46 Network Planning and Analysis 1. Objective: What can you tell me about the project? When will the project finish? How long will the project take (project total duration)? 2. Why is this topic Important

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT PROJECT TIME MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_time_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

Chapter 4: Project Time Management

Chapter 4: Project Time Management Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan. 2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone

More information

Scheduling Best Practices

Scheduling Best Practices RECOVERY SCHEDULES By Mark I. Anderson, Executive Vice President and Chief Operating Officer of Warner Construction Consultants, Inc. In this article, as part of a continuing series of articles regarding

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project

More information

powerproject 24 REASONS TO USE ASTA POWERPROJECT RATHER THAN PRIMAVERA FOR MANAGING CONSTRUCTION PROJECTS www.astadev.com

powerproject 24 REASONS TO USE ASTA POWERPROJECT RATHER THAN PRIMAVERA FOR MANAGING CONSTRUCTION PROJECTS www.astadev.com powerproject 24 REASONS TO USE ASTA POWERPROJECT RATHER THAN PRIMAVERA FOR MANAGING CONSTRUCTION PROJECTS www.astadev.com 1 FAMILIAR, powerproject 24 REASONS TO USE ASTA POWERPROJECT RATHER THAN PRIMAVERA

More information

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards... SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement

More information

Project Scheduling. with Primavera P6. Training Manual

Project Scheduling. with Primavera P6. Training Manual Project Scheduling with Primavera P6 Training Manual Development History June 2003, CPM Scheduling with SureTrak training materials developed by URS Corporation for Caltrans. SureTrak is a registered trademark

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide

Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide Health Check Summary Reports Performance Trend Schedule Trace Schedule Compare Margin Tracker Health Check Indicators Missing Predecessors

More information

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List

More information

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead

More information

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING MICROSOFT PROJECT SOFTWRE FOR THE PROJECT SCHEDULING ŠÁRK ČEMERKOVÁ Silesian University in Opava School of usiness dministration in Karviná Department of Mathematical Methods in Economics Czech Republic

More information

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

Real-Life MS Project: Dependencies and Leveling

Real-Life MS Project: Dependencies and Leveling http://www.alexsbrown.com/ Microsoft Project is a widely-used scheduling tool. Its quirks and complications are a huge drain of time on the Project Management community. This series will go beyond tips

More information

CHAPTER 1. Basic Concepts on Planning and Scheduling

CHAPTER 1. Basic Concepts on Planning and Scheduling CHAPTER 1 Basic Concepts on Planning and Scheduling Scheduling, FEUP/PRODEI /MIEIC 1 Planning and Scheduling: Processes of Decision Making regarding the selection and ordering of activities as well as

More information

ME 407 Mechanical Engineering Design Spring 2016

ME 407 Mechanical Engineering Design Spring 2016 ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,

More information

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL

More information

Basic Schedule Analysis

Basic Schedule Analysis Basic Schedule Analysis Topics Why are Schedules Important Scheduling Basics Attributes of a Valid Schedule Scheduling Best Practices Basic Schedule Analysis Tools and Techniques Sources: NASA Schedule

More information

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John

More information

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules

Learning Objectives. Learning Objectives (continued) Importance of Project Schedules Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities

More information

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

Project Time Management

Project Time Management Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules

More information

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management

MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Winter : Lecture # Project Time Management Homework Discussion Homework

More information

Almost everyone in the planning and scheduling profession

Almost everyone in the planning and scheduling profession PS.02 The Great Negative Lag Debate Mr. Edward E. Douglas III CCC PSP, Mr. Timothy T. Calvey PE PSP, Mr. Donald F. McDonald Jr. PE CCE PSP, and Mr. Ronald M. Winter PSP Almost everyone in the planning

More information

PMBOK GLOSSARY. Activity Duration Estimating. Estimating the number of work periods which will be needed to complete individual activities.

PMBOK GLOSSARY. Activity Duration Estimating. Estimating the number of work periods which will be needed to complete individual activities. PMBOK GLOSSARY Accountability Matrix. See responsibility assignment matrix. Activity. An element of work performed during the course of a project. An activity normally has an expected duration, an expected

More information

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4

Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4 MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking

More information

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition

Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project

More information