1 The Olkiluoto 3 project Virginie Moucquot-Laiho OL3 Project Communications Manager Warsaw, 29 September 2010

2 Structure of the OL3 Consortium (CFS) TVO Plant Contract FramatomeANP AREVA Consortium Agreement Siemens AG SAS France GmbH Germany AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.2 AREVA Proprietary

3 OL3 Turnkey Scope Turnkey, firm-price contract for: Design, procurement, construction and commissioning Siemens PG TI including Civil Work (CW): Turbine + Generator Balance of TI AREVA NP NI including Civil Work (CW): NSSS Balance of NI (BNI) Operational I&C BOP (Balance-of-Plant) Access Building, Waste Building Training of Operators Overall project coordination TI CW TI NI CW NI Siemens PG AREVA NP AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.3 AREVA Proprietary

4 Buildings of Nuclear Island - NI NI/TI Buildings Buildings of Turbine Island - TI Waste Building Auxiliary Building Fuel Building Diesel Buildings 3+4 Access Building Electrical Building Safeguard Building 4 Reactor Building Safeguard Building 1 Turbine Building Diesel Building 1+2 Safeguard Buildings 2+3 Circulating Water Pump Building Ducts & channels Essential Service Water Pump Building AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.4 AREVA Proprietary

5 CHALLENGE SAFETY IS OUR UPPERMOST PRIORITY AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.5 AREVA Proprietary

6 40,00 35,00 30,00 25,00 20,00 15,00 10,00 5,00 0,00 FREQUENCY Lost Time Accidents / million worked hours CFS Safety Indicators August 2010 General 319 accidents 3,465 days lost 1 fatal accident 26,150,000 Man-hours août-06 oct-06 déc-06 févr-07 avr-07 juin-07 août-07 oct-07 déc-07 févr-08 avr-08 juin-08 août-08 oct-08 déc-08 févr-09 avr-09 juin-09 août-09 oct-09 déc-09 févr-10 avr-10 juin-10 août-10 0,40 0,35 0,30 0,25 0,20 0,15 0,10 0,05 0, GRAVITY - Days lost per thousand worked hours Safety indicators Frequency = 12.2 since 01/02/ in Finland, 50 in France Gravity = 0.13 since 01/02/2005 ~ 2 in Finland and in France 0.13 août-06 oct-06 déc-06 févr-07 avr-07 juin-07 août-07 oct-07 déc-07 févr-08 avr-08 juin-08 août-08 oct-08 déc-08 févr-09 avr-09 juin-09 août-09 oct-09 déc-09 févr-10 avr-10 juin-10 août-10 AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.6 AREVA Proprietary

7 CHALLENGE SAFETY OUR UPPERMOST PRIORITY AT ALL TIME AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.7 AREVA Proprietary

8 CFS Site Manpower August 2010 About 55 nationalities working at once CFS ~ 4, NI = 3, TI ~ /09/06 25/11/06 25/01/07 25/03/07 25/05/07 25/07/07 25/09/07 25/11/07 25/01/08 25/03/08 25/05/08 25/07/08 25/09/08 25/11/08 25/01/09 25/03/09 25/05/09 25/07/09 25/09/09 25/11/09 25/01/10 25/03/10 25/05/10 25/07/10 NI TI Total AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.8 AREVA Proprietary

9 Nuclear Safety Culture Continuous development A strong implication of subcontractors Regular meetings at all levels Daily involvement of Areva supervisors Language mapping Trainings Dedicated training for each worker Direct awareness actions for workers Information panels at site Safety culture minute : on-the-spot short sessions AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.9 AREVA Proprietary

10 Nuclear Safety Culture CHALLENGE Site Campaign NUCLEAR SAFETY CULTURE A COMMON LANGUAGE FOR THE BEST QUALITY RESULT AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.10 AREVA Proprietary

11 Olkiluoto Project Progress targets Civil Work completed Nuclear Island: >95% completed = 11/12 buildings (Only outer dome Spring 2011) Turbine Island completed NI Electro-mechanical installation full speed installation progress full speed Piping activity in progress: >600 people Electrical installation works in progress: >150 km of cables pulled Primary system: Civil Work completed Commissioning started for NI/TI Reactor Pressure Vessel installed in Reactor Building Main Coolant Lines introduction andwelding launched Turbine Island ready for tests and commissioning Commissioning start for NI/TI AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.11 AREVA Proprietary

12 Nuclear Island General view AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.12 AREVA Proprietary

13 Turbine Island AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.13 AREVA Proprietary

14 Inner Containment Dome pouring completed in July Preparation for the outer dome under progress Reactor Building Dome AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.14 AREVA Proprietary

15 Reactor Building Pre-stressing Pre-stressing of the inner containment under progress AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.15 AREVA Proprietary

16 IRWST (In-containment Refueling Water Storage Tank) Filling test for leaktightness In containment Refueling Water Storage Tank (IRWST) Test of leaktight ness: First filling Mid July 2010 Spreading area Discharge Melt Channel week 40, D view of IRWST and Spreading Area AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.16 AREVA Proprietary

17 Steam pipe Interfaces NI/TI AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.17 AREVA Proprietary

18 Electro-mechanical installations Electrical activities Introduction of the cabinets week 3, 2010 AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.18 AREVA Proprietary

19 Electro-mechanical activities Pipes installation AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.19 AREVA Proprietary

20 Electro-mechanical installation Stainless steel pipes AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.20 AREVA Proprietary

21 Heavy Components Introduction of the RPV June 18, 2010 AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.21 AREVA Proprietary

22 Heavy Components Main Coolant Lines Welding of primary circuit Alignment and welding of Main Coolant Lines using special equipment AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.22 AREVA Proprietary

23 EPR Next PROJECTS Steps End of NI Civil Works activities (12 buildings) Peak of NI Electromechanical installation activities (~2.000 workers) TECHNICAL Piping, ventilation, electrical installation progress FEEDBACK EXPERIENCE Primary circuit welding completed Electrical Completion of installation of switchgears NI/TI tests and Commissioning ramping-up AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.23 AREVA Proprietary

24 I&C Architecture accepted by STUK with application of conditions Systems independency for safety and process functions Hardwire Back-up System (HBS) Overall test concept Test Bay, engineering simulator, test on site Equipment qualification program Teleperm XP/XS Sensors, instrumentation Local platforms on site for modifications during Commissioning Full scope simulator for operators training AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.24 AREVA Proprietary

25 Relationship EPR withprojects the Client To favor the proximity and help the client relationship thanks to the Project organization implementation on site ORGANIZATIONAL FEEDBACK EXPERIENCE Fully associate the client to all commissioning phases Respect our commitment Safety Quality Fuel loading end 2012 AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.25 AREVA Proprietary

26 Typical Project organization structure (CFS/NI) Organization Qualified mix of know-how and experiences from the Group Transferring of the Project organization on OL3 site (about 700 people) including: Engineering staff at site Construction on a typical base organization including a strong technical coordination management team for works preparation Commissioning team ramping up and including in the near future an embedded TVO team (about 75 people) Transfer from Construction to Commissioning Back Office for supporting the Project activities on site: France/Germany Full support to site activities For example: modifications support on major topics Progressive demobilization Switch to system-based organization in Fall 2010 AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.26 AREVA Proprietary

27 AREVA asset: 3D model - Reactor Building UJB 3D view Metallic platforms UJB 3D view Primary system AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.27 AREVA Proprietary

28 From 3D model to an isometric drawing AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.28 AREVA Proprietary

29 OL3 experience for COMMITMENTS future EPR Executed Detailed Design Computerized 3D model Standardized Primary Components SAFETY Internal manufacturing & QUALITY facilities = our priorities On the shelf components Globalized supply chain FUEL Qualification LOADING for hundreds of 2012 suppliers -= gaining our experience target Understanding of production ratios Improvement for next projects Internal feedback experience process implemented on OL3 All parties committed to the nuclear industry renaissance at the required safety level AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.29 AREVA Proprietary

30 Thank you! AREVA - Virginie Moucquot-Laiho AREVA Day Warsaw - 29 September p.30 AREVA Proprietary

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011 Olkiluoto 3 Project AREVA Suppliers Day Warsaw October 4, 2011 Virginie MOUCQUOT-LAIHO AREVA OL3 Project Management Office & Communications Manager AREVA Reactor & Services - New Builds EPR Project Fleet

More information

Olkiluoto 3 Project June 2010

Olkiluoto 3 Project June 2010 Olkiluoto 3 Project June 2010 Author: R&S Communications Department, La Défense, France. The reproduction, transmission or use of this document or its contents is not permitted without express written

More information

AREVA, an unparalleled experience in building nuclear reactors

AREVA, an unparalleled experience in building nuclear reactors AREVA, an unparalleled experience in building nuclear reactors Frank APEL Senior Vice President Sales Central Europe and Nordic Countries AREVA, International Commercial Organisation 9 th Annual European

More information

AREVA: supply chain network principles and company s vision

AREVA: supply chain network principles and company s vision AREVA: supply chain network principles and company s vision Virginie MOUCQUOT-LAIHO AREVA Finland Communications Director & Vice Country Manager Oulu, Finland 18.09.2012 1 AREVA & nuclear industry The

More information

Swiss media visit to Olkiluoto August 15, 2014

Swiss media visit to Olkiluoto August 15, 2014 Swiss media visit to Olkiluoto August 15, 2014 Käthe Sarparanta Senior Adviser, Project Department Teollisuuden Voima Oyj NUCLEAR POWER PLANTS IN FINLAND Olkiluoto, Eurajoki Population 5.4 million Power

More information

Building New Generation Nuclear Plants Worldwide : AREVA's Experience

Building New Generation Nuclear Plants Worldwide : AREVA's Experience Building New Generation Nuclear Plants Worldwide : AREVA's Experience Philippe Guay Senior Vice President, New Builds Offers AREVA 37 th WNA Symposium 12-14 September 2012 LONDON Projects status The value

More information

The EPR design: the European reference

The EPR design: the European reference The EPR design: the European reference Jean-Bernard Ville Executive Vice-President, New Builds June 25 th, London 1 EPR Design safety 2 EPR project delivery 3 A partnership-based approach Platts 7 th European

More information

New nuclear project financing Warsaw, June 26, 2013 p. 1

New nuclear project financing Warsaw, June 26, 2013 p. 1 New nuclear project financing Warsaw, June 26, 2013 p. 1 The EPR design: a reference technology Loïc ELOY Director of New Builds Offers Poland Platts Conference Warsaw, 26 June 2013 EPR reactor design

More information

Join the UK Nuclear Renaissance. Procurement & Quality Process

Join the UK Nuclear Renaissance. Procurement & Quality Process Join the UK Nuclear Renaissance Procurement & Quality Process 1 AREVA NP UK Supplier Day, March 16th Birmingham EPR is a trademark of the AREVA Group 1 The Process: AREVA Supply Chain Strategy Didier David

More information

Olkiluoto 3 Basic Facts

Olkiluoto 3 Basic Facts Olkiluoto 3 Basic Facts TVO a world-class nuclear power company Teollisuuden Voima Oy (TVO) is a Finnish limited liability company established in 1969. The operating idea of the Company is to produce electricity

More information

U.S. EPR Design Overview

U.S. EPR Design Overview U.S. EPR Design Overview Brian A. McIntyre U.S. EPR Design Certification Project Manager WM2009 Conference March 4, 2009 The EPR Story 1989: Agreement between Framatome and Siemens on development of common

More information

The EPR reactor the reference for New Build

The EPR reactor the reference for New Build The EPR reactor the reference for New Build The reference for New Build The Reference for Safety The EPR design offers the highest level of safety: Already licensed in France, Finland and China Strong

More information

NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012

NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012 NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012 Tanhua Jarmo Teollisuuden Voima Oyj 2 EU ENERGY ROADMAP 2050 NUCLEAR POWER IN ALL SCENARIOS Consumption of electricity

More information

Best Practices and Approaches to Supply Chain Management

Best Practices and Approaches to Supply Chain Management Best Practices and Approaches to Supply Chain Management ATOMEX Forum 2012 Moscow 12.12. 14.12.2012 AF-Consult Switzerland Ltd Jan Kocourek 1 Objectives Provide information available regarding both the

More information

DESIGN OF EPR. Bernard DEBONTRIDE France, bernard.debontride @framatome-anp.com. AREVA FRAMATOME ANP Plants Sector Nuclear Engineering

DESIGN OF EPR. Bernard DEBONTRIDE France, bernard.debontride @framatome-anp.com. AREVA FRAMATOME ANP Plants Sector Nuclear Engineering DESIGN OF EPR Bernard DEBONTRIDE France, bernard.debontride @framatome-anp.com AREVA FRAMATOME ANP Plants Sector Nuclear Engineering Key Words: EPR, Design Abstract: At the origin was the common decision

More information

Teollisuuden Voima Oyj - General Presentation January 2009. Ilkka Mikkola Senior Adviser (Former Fuel Manager) Teollisuuden Voima Oyj

Teollisuuden Voima Oyj - General Presentation January 2009. Ilkka Mikkola Senior Adviser (Former Fuel Manager) Teollisuuden Voima Oyj Teollisuuden Voima Oyj - General Presentation January 2009 Ilkka Mikkola Senior Adviser (Former Fuel Manager) Teollisuuden Voima Oyj Nuclear Power Plants in Finland in 2008 Olkiluoto OL1 BWR 860 MW 1978

More information

Structural Integrity and NDE Reliability II

Structural Integrity and NDE Reliability II Structural Integrity and NDE Reliability II Preparing for EPR TM Reactor Vessel Inspection J. Laube, AREVA NDE Solutions / intelligendt, Germany Y. Bouveret, AREVA NDE Solutions / Intercontrole, France

More information

US EPR nuclear technology and market outlook

US EPR nuclear technology and market outlook US EPR nuclear technology and market outlook Bruno Blotas Vice-President, Business Development 29 May 2013 Mexico City Conference The future of nuclear energy AREVA at a glance The US-EPR Status of ongoing

More information

Olkiluoto 3 Experience

Olkiluoto 3 Experience Olkiluoto 3 Experience CNRA International Workshop on New Reactor Siting, Licensing and Construction Experience Hosted by the State Office for Nuclear Safety Prague, Czech Republic 15-17 September 2010

More information

Physics and Engineering of the EPR

Physics and Engineering of the EPR Physics and Engineering of the EPR Keith Ardron UK Licensing Manager, UK Presentation to IOP Nuclear Industry Group Birchwood Park, Warrington UK, November 10 2010 EPRs in UK EPR is Generation 3+ PWR design

More information

Flamanville 3 Nuclear Power Plant

Flamanville 3 Nuclear Power Plant Flamanville 3 Nuclear Power Plant Prepared by: Giorgio Locatelli (University of Lincoln) and Mauro Mancini (Politecnico di Milano) Contacts: Giorgio Locatelli University of Lincoln Lincoln School of Engineering

More information

Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland

Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland IAEA Technical meeting on Safety culture in pre-operational

More information

ELEKTROBUDOWA SA for 15 years listed on WSE ELEKTROBUDOWA SA POLISH LEADER IN POWER ENGINEERING. 4th October 2011. www.elbudowa.com.

ELEKTROBUDOWA SA for 15 years listed on WSE ELEKTROBUDOWA SA POLISH LEADER IN POWER ENGINEERING. 4th October 2011. www.elbudowa.com. ELEKTROBUDOWA SA POLISH LEADER IN POWER ENGINEERING 4th October 2011 Agenda GENERAL INFORMATION ABOUT COMPANY BUSINESS SEGMENTS ELEKTROBUDOWA FOR NUCLEAR PP ELEKTROBUDOWA SA GROUP FINANCIAL STATEMENTS

More information

Electrical Systems. Emergency Diesel Generator Solutions

Electrical Systems. Emergency Diesel Generator Solutions Electrical Systems Emergency Diesel Generator Solutions AREVA Competence in Emergency Power Supply Emergency Diesel Generators (EDGs) Business Areas e Modernization of existing EDGs p Customer support

More information

How To Understand And Understand Tvo

How To Understand And Understand Tvo Nuclear Power Plant Unit Olkiluoto Contents TVO a pioneer in its own field Olkiluoto One unit, many buildings n PRIMARY CIRCUIT Reactor pressure vessel and internal structures Reactor core and fuel Reactor

More information

Public SUMMARY OF EU STRESS TEST FOR LOVIISA NUCLEAR POWER PLANT

Public SUMMARY OF EU STRESS TEST FOR LOVIISA NUCLEAR POWER PLANT 1 (8) SUMMARY OF EU STRESS TEST FOR LOVIISA NUCLEAR POWER PLANT 1 LOVIISA NUCLEAR POWER PLANT Loviisa town is located approximately 90 km eastwards from Helsinki at the coast of Gulf of Finland. Loviisa

More information

Advanced Construction Methods for New Nuclear Power Plants

Advanced Construction Methods for New Nuclear Power Plants Advanced Construction Methods for New Nuclear Power Plants A. Introduction Relative to coal fired and natural gas fired power plants, nuclear power plants are more expensive to build but less expensive

More information

AREVA Advanced nuclear power plants

AREVA Advanced nuclear power plants AREVA Advanced nuclear power plants Bernard Bastide AREVA Brazil and South America VP University of Rio de Janeiro III Semana da Engenharia Nuclear UFRJ August 2013 AREVA presentation AREVA EPR projects

More information

Q1 2013 Q1 2012 1 Change Change LFL

Q1 2013 Q1 2012 1 Change Change LFL At March 31, 2013: Strong revenue growth of 12.5% to 2.279bn (+15.5% like for like) Stable backlog year on year: 44.9bn (-1.0% over the quarter) Paris, April 25, 2013 Luc Oursel, Chief Executive Officer,

More information

Drivers and approach for the design of the EPR reactor

Drivers and approach for the design of the EPR reactor Drivers and approach for the design of the EPR reactor Martine Mayousse Reactor & Services / Safety & Licensing IAEA Vienna June 27, 2013 1 Agenda 1. Introduction 2. EPR design objectives and principles

More information

Boiling Water Reactor Systems

Boiling Water Reactor Systems Boiling Water (BWR) s This chapter will discuss the purposes of some of the major systems and components associated with a boiling water reactor (BWR) in the generation of electrical power. USNRC Technical

More information

Paris, April 26, 2012

Paris, April 26, 2012 At March 31, 2012: 2.4% revenue growth to 2.026bn (+1.3% like for like) Backlog growth year on year to 45.1bn (+3.7%), down slightly over 3 months (-1.0%) Paris, April 26, 2012 AREVA generated consolidated

More information

First Quarter 2014 Earnings Conference Call. New Nuclear Presentation Section. April 24, 2014 First Quarter 2014 Earnings Conference Call 1

First Quarter 2014 Earnings Conference Call. New Nuclear Presentation Section. April 24, 2014 First Quarter 2014 Earnings Conference Call 1 First Quarter 2014 Earnings Conference Call New Nuclear Presentation Section April 24, 2014 1 Safe Harbor Statement/Regulation G Information Statements included in this presentation which are not statements

More information

ANCHOR BOLTS FOR NUCLEAR POWER PLANT APPLICATIONS

ANCHOR BOLTS FOR NUCLEAR POWER PLANT APPLICATIONS ANCHOR BOLTS FOR NUCLEAR POWER PLANT APPLICATIONS EXPERIENCE FROM DESIGN AND CONSTRUCTION OF OLKILUOTO UNITS 2015-11-03 Kukkola Timo 2 OL1 AND OL2 CROSS-SECTION 3 OL1 AND OL2 OL1 and OL2 continuous improvement

More information

This document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and

This document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and This document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and suppliers. It is transmitted to you in confidence and trust,

More information

Gas turbine power plants

Gas turbine power plants Gas turbine power plants A global challenge Apart from other sources of energy such as water, coal and uranium, the use of natural gas and fuel oil is an important factor in assuring a reliable supply

More information

February 19, 2014. Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company

February 19, 2014. Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company JAPAN-U.S. DECOMISSIONING AND REMEDIATION FUKUSHIMA RECOVERY FORUM February 19, 2014 Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company Toshiba global formation Information

More information

POWER & RENEWABLE ENERGY SERVICES

POWER & RENEWABLE ENERGY SERVICES POWER & RENEWABLE ENERGY SERVICES Siting - Assistance to permitting Environmental Impact Assessment Safety and environmental audits Construction code compliance and design review Supplier Technical Assessment

More information

May 7, 2008. SUBJECT: NRC INSPECTION REPORT FOR AREVA-NP GmbH 99901371/2008-201, NOTICE OF VIOLATION, AND NOTICE OF NONCONFORMANCE

May 7, 2008. SUBJECT: NRC INSPECTION REPORT FOR AREVA-NP GmbH 99901371/2008-201, NOTICE OF VIOLATION, AND NOTICE OF NONCONFORMANCE May 7, 2008 Mr. Hans-Joachim Nisslein QEM Liaison Officer AREVA-NP GmbH Paul-Gossen-Strasse 100 91001 Erlangen, Germany SUBJECT: NRC INSPECTION REPORT FOR AREVA-NP GmbH 99901371/2008-201, NOTICE OF VIOLATION,

More information

Nuclear Safety. Policy 2013-2016

Nuclear Safety. Policy 2013-2016 Nuclear Safety Policy 2013-2016 Nuclear Safety Policy 2013-2016 T he organisational principles and actions defined in the Nuclear Safety Charter and applied within the group have achieved significant improvements

More information

CITY OF LOS ANGELES PERSONNEL DEPARTMENT CAREER OPPORTUNITIES FOR MECHANICAL HELPER

CITY OF LOS ANGELES PERSONNEL DEPARTMENT CAREER OPPORTUNITIES FOR MECHANICAL HELPER CITY OF LOS ANGELES PERSONNEL DEPARTMENT CAREER OPPORTUNITIES FOR MECHANICAL HELPER This information is being given to you to describe potential opportunities as a Helper. The career ladders that Helpers

More information

POWER & RENEWABLE ENERGY SERVICES

POWER & RENEWABLE ENERGY SERVICES POWER & RENEWABLE ENERGY SERVICES Nuclea Siting - Assistance to permitting Environmental Impact Assessment Safety and environmental audits Construction code compliance and design review Supplier Technical

More information

Nuclear Design Practices and the Case of Loviisa 3

Nuclear Design Practices and the Case of Loviisa 3 Nuclear Design Practices and the Case of Loviisa 3 Harri Tuomisto Fortum Power, Finland Third Nuclear Power School, 20-22 October 2010, Gdańsk, Poland 22 October 2010 Harri Tuomisto 1 Objectives The objective

More information

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1]

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1] Nuclear Safety Council Instruction number IS-22, of July 1st 2009, on safety requirements for the management of ageing and long-term operation of nuclear power plants Published in the Official State Gazette

More information

Nuclear Energy: Nuclear Energy

Nuclear Energy: Nuclear Energy Introduction Nuclear : Nuclear As we discussed in the last activity, energy is released when isotopes decay. This energy can either be in the form of electromagnetic radiation or the kinetic energy of

More information

AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH

AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH Thomas M. Williamson, P.E. VP, New Plant Market Strategy AREVA Inc. Introduction AREVA Overview Nuclear

More information

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS Presented by W.J. (Chris) Zhang University of Saskatchewan Saskatoon, Canada Email: chris.zhang@usask.ca Outline 1. Modularization in NPP 2. Comparison

More information

EDUCATION AND TRAINING OF OPERATORS AND MAINTENANCE STAFF AT COMMERCIAL NUCLEAR POWER STATIONS IN JAPAN

EDUCATION AND TRAINING OF OPERATORS AND MAINTENANCE STAFF AT COMMERCIAL NUCLEAR POWER STATIONS IN JAPAN IAEA-CN-73/42 EDUCATION AND TRAINING OF OPERATORS AND MAINTENANCE STAFF AT COMMERCIAL NUCLEAR POWER STATIONS IN JAPAN M.TAKAHASHI Chubu Electric Power Co., Inc. XA9847813 H. KATAOKA Kansai Electric Power

More information

The World Nuclear Supply

The World Nuclear Supply The World Nuclear Supply Chain An Overview Greg KASER Staff Director NEA International WPNE Workshop Paris 11 March 2014 Outline of Presentation 1. About WNA 2. Value of: New construction Early dismantlement

More information

XA0302230 EVALUATION OF TRAINING ACTIVITIES IN ARGENTINA

XA0302230 EVALUATION OF TRAINING ACTIVITIES IN ARGENTINA XA0302230 EVALUATION OF TRAINING ACTIVITIES IN ARGENTINA Alejandro D. SANDA ATUCHANPP ARGENTINA I came from Argentina. Do you know where Argentina is? Argentina is in South America, below Brazil. The area

More information

Introductions: Dr. Stephen P. Schultz

Introductions: Dr. Stephen P. Schultz Introductions: Dr. Stephen P. Schultz Vienna, Austria 1 3 September 2015 Work Experience Current Member Advisory Committee on Reactor Safeguards, U.S. Nuclear Regulatory Commission, 12/2011 Chair, Fukushima

More information

DOCUMENTATION FOR QUALIFICATION SYSTEM

DOCUMENTATION FOR QUALIFICATION SYSTEM DOCUMENTATION FOR QUALIFICATION SYSTEM MATERIAL GROUP: PRESSURE EQUIPMENT MAINTENANCE, REPAIR INTERNAL CODE OF MATERIAL GROUP: MM10300 New code according the registration on myhome: MMGV03 CPV CODE: 45259000-7,

More information

7.1 General 5 7.2 Events resulting in pressure increase 5

7.1 General 5 7.2 Events resulting in pressure increase 5 GUIDE YVL 2.4 / 24 Ma r ch 2006 Primary and secondary circuit pressure control at a nuclear power plant 1 Ge n e r a l 3 2 General design requirements 3 3 Pressure regulation 4 4 Overpressure protection

More information

BWR Description Jacopo Buongiorno Associate Professor of Nuclear Science and Engineering

BWR Description Jacopo Buongiorno Associate Professor of Nuclear Science and Engineering BWR Description Jacopo Buongiorno Associate Professor of Nuclear Science and Engineering 22.06: Engineering of Nuclear Systems 1 Boiling Water Reactor (BWR) Public domain image by US NRC. 2 The BWR is

More information

External Interface Risk

External Interface Risk External Interface Risk External risks result from circumstances, conditions or events that are not under the direct control of facility management. Contingency plans will be developed for systems determined

More information

Government Degree on the Safety of Nuclear Power Plants 717/2013

Government Degree on the Safety of Nuclear Power Plants 717/2013 Translation from Finnish. Legally binding only in Finnish and Swedish. Ministry of Employment and the Economy, Finland Government Degree on the Safety of Nuclear Power Plants 717/2013 Chapter 1 Scope and

More information

Nuclear power plant systems, structures and components and their safety classification. 1 General 3. 2 Safety classes 3. 3 Classification criteria 3

Nuclear power plant systems, structures and components and their safety classification. 1 General 3. 2 Safety classes 3. 3 Classification criteria 3 GUIDE 26 June 2000 YVL 2.1 Nuclear power plant systems, structures and components and their safety classification 1 General 3 2 Safety classes 3 3 Classification criteria 3 4 Assigning systems to safety

More information

Tank Terminals Proven Solutions for Liquid Bulk Storage and Distribution Terminals

Tank Terminals Proven Solutions for Liquid Bulk Storage and Distribution Terminals Tank Terminals Proven Solutions for Liquid Bulk Storage and Distribution Terminals Industrial Technologies Liquid bulk storage and distribution terminals: Safe and future-proof solutions from Siemens 2

More information

Qualification of In-service Inspections of NPP Primary Circuit Components

Qualification of In-service Inspections of NPP Primary Circuit Components Qualification of In-service Inspections of NPP Primary Circuit Components ABSTRACT Matija Vavrouš, Marko Budimir INETEC Institute for nuclear technology Dolenica 28, 10250 Zagreb, Croatia matija.vavrous@inetec.hr,

More information

Generic PCSR Sub-chapter 15.4 : Electrical Equipment

Generic PCSR Sub-chapter 15.4 : Electrical Equipment Form10/00 Document ID : GA91-9101-0101-15004 Document Number : EE-GDA-C284 Revision Number : A Generic Design Assessment Generic PCSR Sub-chapter 15.4 : Electrical Equipment Hitachi-GE Nuclear Energy,

More information

Siemens Hybrid Power Solutions. Cost and emission reduction by integrating renewables into diesel plants

Siemens Hybrid Power Solutions. Cost and emission reduction by integrating renewables into diesel plants Siemens Hybrid Power Solutions Cost and emission reduction by integrating renewables into diesel plants Instrumentation, Controls & Electrical Complete, optimized solutions that minimize your risk One-stop

More information

Solutions for Nuclear & Renewable Power Generation

Solutions for Nuclear & Renewable Power Generation Solutions for Nuclear & Renewable Power Generation Integrated Business Model Luc Oursel AREVA CEO AREVA has become the undisputed global leader in low carbon power generation solutions through its unique

More information

NEW NUCLEAR POWER PLANTS FOR ONTARIO - THE CONTENDERS - 2008 October

NEW NUCLEAR POWER PLANTS FOR ONTARIO - THE CONTENDERS - 2008 October NEW NUCLEAR POWER PLANTS FOR ONTARIO - THE CONTENDERS - 2008 October (THIS OVERVIEW IS AN UPDATED VERSION OF AN EARLIER ONE THAT WAS PUBLISHED IN THE BULLETIN OF THE CANADIAN NUCLEAR SOCIETY, MARCH 2008,

More information

Pocket Guide 2012. Pocket Guide 2012 1

Pocket Guide 2012. Pocket Guide 2012 1 Pocket Guide 2012 Pocket Guide 2012 1 2 Pocket Guide 2012 04 11 Teollisuuden Voima Oyj Olkiluoto nuclear power plant 4 Company 5 Shareholders and holdings 6 Important dates 10 Key figures 10 Nuclear Waste

More information

Power Island. Industrial Power Plants. www.siemens.com / energy

Power Island. Industrial Power Plants. www.siemens.com / energy Power Island Industrial Power Plants www.siemens.com / energy Flexible combined-cycle power plants With today s increasing demands for flexible power plants, intensified by the increased amount of electricity

More information

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,

More information

Workshop GESEL - UFRJ: O presente e o futuro da energia nuclear no Brasil

Workshop GESEL - UFRJ: O presente e o futuro da energia nuclear no Brasil Workshop GESEL - UFRJ: O presente e o futuro da energia nuclear no Brasil Jürgen Czech Diretor Técnico AREVA NP Johannes Höbart Diretor Presidente AREVA Brasil Rio de Janeiro - Dezembro/2009 Introduction

More information

Preliminary validation of the APROS 3-D core model of the new Loviisa NPP training simulator

Preliminary validation of the APROS 3-D core model of the new Loviisa NPP training simulator Preliminary validation of the APROS 3-D core model of the new Loviisa NPP training simulator Anssu Ranta-aho, Elina Syrjälahti, Eija Karita Puska VTT Technical Research Centre of Finland P.O.B 1000, FI-02044

More information

ADMINISTRATIVE SERVICES MANUAL

ADMINISTRATIVE SERVICES MANUAL Purpose Responsibilities Proper Storage and use of flammable liquids can significantly reduce the possibility of accidental fires and injuries. To minimize risk to life and properly, the requirements of

More information

The OL3 Nuclear Power Plant Construction Project. A Learning Experience

The OL3 Nuclear Power Plant Construction Project. A Learning Experience The OL3 Nuclear Power Plant Construction Project A Learning Experience OL3 One of the biggest construction sites in Europe Begun 2005 ready in 2016? Cost 8,5 billion original estimate 3,5 billion > 2000

More information

This is a Master s degree level apprenticeship which includes academic learning combined workplace learning and training.

This is a Master s degree level apprenticeship which includes academic learning combined workplace learning and training. Power Engineer Degree Apprenticeship The UK s energy sector is integral to the prosperity and stability of the UK economy as a whole, delivering an absolutely fundamental service for all its citizens.

More information

Decommissioning situation of Nuclear Power Plant in Japan

Decommissioning situation of Nuclear Power Plant in Japan Decommissioning situation of Nuclear Power Plant in Japan April, 2015 The Japan Atomic Power Co. The Kansai Electric Power Co., Inc. General Description 1 Operational years of commercial NPP in Japan 40

More information

Waste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010

Waste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010 Waste Volume Reduction by Studsvik Nuclear AB Anders Stenmark and Bo Wirendal September 16th, 2010 Waste Streams from Industry The Nuclear Industry generates operational waste during its lifetime as well

More information

EXCHANGE OF STEAM GENERATORS IN PRESSURIZED WATE R REACTOR POWER PLANT S ABSTRACT

EXCHANGE OF STEAM GENERATORS IN PRESSURIZED WATE R REACTOR POWER PLANT S ABSTRACT PAPER 9. 3. EXCHANGE OF STEAM GENERATORS IN PRESSURIZED WATE R REACTOR POWER PLANT S C. Hillrichs, Dipl.-Ing. (FH ) Siemens AG, KWU, Erlangen, West Germany) ABSTRACT As a result of problems experienced

More information

AREVA Learning Solutions - English version -

AREVA Learning Solutions - English version - AREVA Learning Solutions - English version - CoNTeNT 1 Foreword 2 Nuclear Energy Framework 3 Radioactive materials transport 4 Reactors and fuel cycle General knowledge of reactors technology TELEPERM

More information

Information Technology Solutions

Information Technology Solutions S AV E S M O N E Y Can reduce water consumption and waste disposal costs. Wastewater treatment with Vacuum Evaporation Systems Water treatment made easy! E NV IR O N ME NT F R IE N DLY Recycle water and

More information

Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions. Nici Bergroth, Fortum Oyj FORS-seminar 26.11.

Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions. Nici Bergroth, Fortum Oyj FORS-seminar 26.11. Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions Nici Bergroth, Fortum Oyj FORS-seminar 26.11.2009, Otaniemi Loviisa 3 CHP Basis for the Loviisa 3 CHP alternative Replacement

More information

A Nuclear New Deal. Jacques Besnainou. President, AREVA Inc. AREVA

A Nuclear New Deal. Jacques Besnainou. President, AREVA Inc. AREVA AREVA Building Energy Certainty: A Nuclear New Deal Jacques Besnainou President, AREVA Inc. AREVA EnergyBiz Leadership Forum, Session Two: Resource Review Washington, D.C. March 9, 2009 Three ways forward

More information

How To Clean Up A Reactor Water Cleanup

How To Clean Up A Reactor Water Cleanup General Electric Systems Technology Manual Chapter 2.8 Reactor Water Cleanup System TABLE OF CONTENTS 2.8 REACTOR CLEANUP SYSTEM... 1 2.8.1 Introduction... 2 2.8.2 System Description... 2 2.8.3 Component

More information

Fact sheet: Olkiluoto 3

Fact sheet: Olkiluoto 3 March 3, 2008 Fact sheet: Olkiluoto 3 Contact: Lauri Myllyvirta, Energy Campaigner (Helsinki): +358 50 3625 981, firstname.surname@nordic.greenpeace.org World s largest, first-of-a-kind nuclear reactor

More information

Outlook for RWE s nuclear operations. Prof. Dr. Gerd Jäger London, 16 January 2012

Outlook for RWE s nuclear operations. Prof. Dr. Gerd Jäger London, 16 January 2012 Outlook for RWE s nuclear operations Prof. Dr. Gerd Jäger London, 16 January 2012 Overview of German nuclear power plants Power plant Net capacity MW Commercial commissioning Shutdown German nuclear power

More information

Safety assessment of the Loviisa nuclear power plant

Safety assessment of the Loviisa nuclear power plant / OCTOBER 2007 B Safety assessment of the Loviisa nuclear power plant Statement regarding the licence application by Fortum Power and Heat Oy concerning the operation of the Loviisa nuclear power plant

More information

NUCLEAR NEW BUILD Presentation to NucSIG December 9 th,2009

NUCLEAR NEW BUILD Presentation to NucSIG December 9 th,2009 NUCLEAR NEW BUILD Presentation to NucSIG December 9 th,2009 Gautier COSSART Quality Assurance / Safety & Regulations Division ADD PRESENTATION TITLE HERE (GO TO: VIEW / MASTER / SLIDE MASTER TO AMEND)

More information

SINGLE SOURCE CAPABILITY, RESPONSIBILITY, ACCOUNTABILITY.

SINGLE SOURCE CAPABILITY, RESPONSIBILITY, ACCOUNTABILITY. NUCLEAR Services Black & McDonald Limited was founded in 1921 as a partnership between William J. McDonald and William R. Black; they established the company s long-standing commitment to fairness, quality,

More information

May 23, 2011 Tokyo Electric Power Company

May 23, 2011 Tokyo Electric Power Company Analysis and evaluation of the operation record and accident record of Fukushima Daiichi Nuclear Power Station at the time of Tohoku-Chihou-Taiheiyou-Oki-Earthquake (summary) May 23, 2011 Tokyo Electric

More information

Solutions for nuclear technology

Solutions for nuclear technology Solutions for nuclear technology Corrosion resistant pipes Clad pipes Special pipes and components ready for installation Prefabricated piping / spools Vessels, tanks and columns Assemblies 2 NUCLEAR TECHNOLOGY

More information

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Published in the Official State Gazette (BOE) No 283 of November 24 th 2009 Nuclear Safety Council Instruction

More information

HOW DOES A NUCLEAR POWER PLANT WORK?

HOW DOES A NUCLEAR POWER PLANT WORK? HOW DOES A NUCLEAR POWER PLANT WORK? O n t a r i o P o w e r G e n e r a t i o n P U T T I N G O U R E N E R G Y T O U S G O O D E O N T A R I O P O W E R G E N E R A T I O N What a Nuclear Reactor Does

More information

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Nuclear Power in Pakistan Nuclear Power Plants Capacity (MWe) Year of Commissioning In

More information

Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director

Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director Seminar FPGA-based I&C Systems in Nuclear Applications February 4, 2015, Energiforsk,

More information

Fukushima 2011. Fukushima Daiichi accident. Nuclear fission. Distribution of energy. Fission product distribution. Nuclear fuel

Fukushima 2011. Fukushima Daiichi accident. Nuclear fission. Distribution of energy. Fission product distribution. Nuclear fuel Fukushima 2011 Safety of Nuclear Power Plants Earthquake and Tsunami Accident initiators and progression Jan Leen Kloosterman Delft University of Technology 1 2 Nuclear fission Distribution of energy radioactive

More information

Progress and Quality Assurance Regime at the EPR Construction at Olkiluoto Safety Implications of Problems Encountered

Progress and Quality Assurance Regime at the EPR Construction at Olkiluoto Safety Implications of Problems Encountered G Progress and Quality Assurance Regime at the EPR Construction at Olkiluoto Safety Implications of Problems Encountered Authors: H. Hirsch W. Neumann Report prepared for Greenpeace Nordic Hanover, May

More information

INTRODUCTION. Three Mile Island Unit 2

INTRODUCTION. Three Mile Island Unit 2 INTRODUCTION here was an accident at Three Mile Island Unit 2 on March 28,1979. It caused extensive damage to the plant's nuclear fuel core. Most of the plant's major systems were relatively undamaged.

More information

A seismic switch. Certified switchgear for nuclear power plants is providing a critical link in the chain

A seismic switch. Certified switchgear for nuclear power plants is providing a critical link in the chain A seismic switch Certified switchgear for nuclear power plants is providing a critical link in the chain Renato Piccardo, Annunzio Regantini, Davide Cattaneo, Luciano Di Maio A nuclear power plant must

More information

Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build

Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build John H. Moore Nuclear Power Division j.h.moore@iaea.org Paris, France March 11, 2014 (OECD Workshop) International

More information

Boiling Water Reactor Basics

Boiling Water Reactor Basics Boiling Water Reactor Basics Larry Nelson November 2008 Overview Big Picture - BWR Plants Major Components BWR Evolution BWR Features vs. PWR Features Electrochemical Potential (ECP) Concept ECP Monitoring

More information

AP1000 Overview. 2011 Westinghouse Electric Company LLC - All Rights Reserved

AP1000 Overview. 2011 Westinghouse Electric Company LLC - All Rights Reserved AP1000 Overview AP1000 is a registered trademark in the United States of Westinghouse Electric Company LLC, its subsidiaries and/or its affiliates. This mark may also be used and/or registered in other

More information

ENVIRONMENTAL IMPACT ASSESSMENT REPORT

ENVIRONMENTAL IMPACT ASSESSMENT REPORT ENVIRONMENTAL IMPACT ASSESSMENT REPORT for Investment Proposal: BUILDING A NEW NUCLEAR UNIT OF THE LATEST GENERATION AT THE KOZLODUY NPP SITE CHAPTER 2: ALTERNATIVE LOCATIONS AS ASSESSED BY THE CLIENT

More information

2. System Based Design Descriptions and ITAAC AP1000 Design Control Document

2. System Based Design Descriptions and ITAAC AP1000 Design Control Document 2.3.2 Chemical and Volume Control System Design Description The chemical and volume control system (CVS) provides reactor coolant system (RCS) purification, RCS inventory control and makeup, chemical shim

More information

Testing and Utilization of Loviisa Full Scope Apros Model in Engineering and Development Simulator

Testing and Utilization of Loviisa Full Scope Apros Model in Engineering and Development Simulator IYNC 2010 Cape Town, South Africa, 12 18 July 2010 Paper No. 237 Testing and Utilization of Loviisa Full Scope Apros Model in Engineering and Development Simulator Jussi Näveri, Topi Tahvonen 1, Petri

More information