Building New Generation Nuclear Plants Worldwide : AREVA's Experience

Size: px
Start display at page:

Download "Building New Generation Nuclear Plants Worldwide : AREVA's Experience"

Transcription

1 Building New Generation Nuclear Plants Worldwide : AREVA's Experience Philippe Guay Senior Vice President, New Builds Offers AREVA 37 th WNA Symposium September 2012 LONDON

2 Projects status The value of experience Conclusion WNA Symposium September 2012 p.2

3 AREVA is deploying the world s first advanced fleet of Gen III NPPs with 4 EPR reactor units under construction Percentage of completion (AREVA scope) Olkiluoto 3 82 % Complete (Supply of a turnkey Power Plant) Flamanville 3 60 % Complete (Supply of a Nuclear Steam Supply System) Taishan 1&2 70% Complete (Supply of 2 nuclear islands) WNA Symposium September 2012 p.3

4 Olkiluoto 3 Major Milestones Reactor Building Containment Line -7 m to +16 m Delivery of the Reactor Pressure Vessel Lifting of the Reactor Dome Reactor Pressure Vessel introduced All primary loop components installed WNA Symposium September 2012 p.4

5 Olkiluoto 3 moving towards completion: water intake structure flooding, fuel handling equipment installation July 12 Refueling machine installed July 12 Filling of the cooling water Pumping Station WNA Symposium September 2012 p.5

6 Olkiluoto 3 moving towards completion: Turbine island commissioning February 12 Turbine island connected to local 110 kv network WNA Symposium September 2012 p.6

7 Flamanville 3 Major Milestones Copyright EDF Signature of the contract First concrete pouring Installation of the pressurizer relief tank Welding of first supports in safeguard buildings EBS pumps installed Installation of Safeguard system piping Delivery of the first embedded tank (RPE) First safety pump in the safeguard building Start of Piping Erection WNA Symposium September 2012 p.7

8 Flamanville 3 Nuclear Building installation works ongoing June 12 RPV Support Ring Installation July 12 Installation of RCP and Steam Generators vertical supports WNA Symposium September 2012 p.8

9 Taishan 1&2 EPR Project Major Milestones Copyright TNPJVC Signature of the Contract Excavation Ceremony First Concrete TS1 TS1 1st liner lifted TS2 1st liner lifted TS1: polar crane delivered RPV installed Start of the Self Reliance program LOI to create a JV in Nuclear Reactor Engineering First Concrete TS2 TS1: Dome lifted WNA Symposium September 2012 p.9

10 Taishan 1 Dome poured, RPV installed June 12 Reactor Vessel installation July 12 Dome pouring WNA Symposium September 2012 p.10

11 Projects status The value of experience Conclusion WNA Symposium September 2012 p.11

12 EPR lessons learned Olkiluoto 3 Flamanville 3 Taishan 1&2 Future EPR Four ongoing EPR projects Two countries with licensing process underway Two approaches to improve EPR competitiveness A centralized integration of EPR optimizations Finland, France, China USA, UK Bottom up & top down Standard EPR design AREVA s Target: Certainty to build EPR on time and on budget to minimize risks and ensure profitability of the investment WNA Symposium September 2012 p.12

13 The value of Experience: Knowledge management A mature field experience consolidation process A systematic process There are more than 1600 Experience feedbacks in the data base coming from current projects and our work on currently operating plants well established in the company: In 2011 alone, around 1 Experience feedback per day have been captured This unique project delivery experience has allowed AREVA to improve on all aspects of project execution Project management and organization 18% Engineering Procurement Construction 44% Engineering Construction 11% 6% Procurement Others Experience feedbacks by Discipline 21% Project management WNA Symposium September 2012 p.13

14 The value of Experience: Project organization Generic organization leveraging experienced teams Organization Experienced teams Worldwide PM support organization Project Management Office Risk & Opportunity Management Contract Management Proposals COMPETENT RESOURCES STANDARDS, METHODS, TOOLS Projects CGNPC For the Taishan projects: 50% Management Directors & Managers, 50% Engineering staff, 90% Procurement workforce, Schedule Management Estimating CROSS-FERTILIZATION have worked on the OL3 or FA3 projects Lessons Learned Worldwide project support organization WNA Symposium September 2012 p.14

15 The Value of Experience: Supply chain Manufacturing of heavy components Tube sheet and lower shell Y1 Y2 Y3 Y4 Y5 (# months) 70 ~5y 60-40% OL3 Shells subassembly Pressure boundary & lower part sub-assembly Hydraulic tests & preparation OL3 ~3y TSN 0 Tube sheet and lower shell TS1 Shells subassembly Pressure boundary & lower part sub-assembly Hydraulic tests & preparation Source : AREVA, average of the four Steam Generators for each unit WNA Symposium September 2012 p.15 Apr 12 First two steam generators delivered on Taishan site

16 The value of experience: Construction Illustration: Concrete slab one-step pouring Improvement Illustration Context Thick concrete slab (4m at FA3 and TSN) One-step pouring challenging Improvement One-step pouring method validated at Taishan thanks to temperature control Use of ice Use of integrated piping Use of a heating cover CGNPC One-step pouring Gain Construction schedule: 1 month shorter Concrete temperature check This improvement was made possible thanks to our Chinese partners CGNPC WNA Symposium September 2012 p.16

17 The value of experience: Construction Illustration, from OL3 to TSN: first main milestones Construction duration (# months) Dome lifting Slab +1,5m Start of inner containment Gusset pouring 1 st concrete OL TSN1 WNA Symposium September 2012 p.17

18 Developing AREVA Gen III+ reactors offering AREVA strongly engaged in the UK market with The ongoing Hinkley Point C project with NNB co The Horizon Nuclear Power development The NuGen project for the Moorside project Bids submitted since Jan to the Finnish utility Fennovoima for an EPR and the Czech utility CEZ for two EPRs Bilateral negotiations to sell EPR units in China and India 3rd phase of the licensing process for the EPR in the USA Creation of a joint offer team with EDF in Poland Opening of a joint office with EDF in Riyadh (Kingdom of Saudi Arabia) French safety authority has issued a favorable opinion on ATMEA1 ATMEA1 reactor technology short listed for the Jordan New Build program ATMEA1 reactor is pre-qualified in Argentina WNA Symposium September 2012 p.18

19 Projects status The value of experience Conclusion WNA Symposium September 2012 p.19

20 Conclusion After the Fukushima accident, the fundamentals of the world energy market remain the same : Important growth in electricity need Geopolitics factors, security of supply and pressure on fossil energy Environmental issues and need to reduce CO 2 emissions in energy production In this context, low-carbon energies such as nuclear power and renewable energies will play a key role in the energy mix AREVA offers a complete range of Gen III + Reactors, offering both increased efficiency and a level of safety complying with the most stringent safety requirements and meeting our customers needs for a safe and competitively priced electricity AREVA is capturing a unique project delivery experience and best practices from past and on-going projects for the benefit of customers needs The Fukushima accident raises legitimate questions and concerns. The nuclear industry needs to give appropriate answers to these concerns. We need to dialogue with our stakeholders in order to restore trust and strengthen nuclear public acceptance WNA Symposium September 2012 p.20

AREVA, an unparalleled experience in building nuclear reactors

AREVA, an unparalleled experience in building nuclear reactors AREVA, an unparalleled experience in building nuclear reactors Frank APEL Senior Vice President Sales Central Europe and Nordic Countries AREVA, International Commercial Organisation 9 th Annual European

More information

The EPR design: the European reference

The EPR design: the European reference The EPR design: the European reference Jean-Bernard Ville Executive Vice-President, New Builds June 25 th, London 1 EPR Design safety 2 EPR project delivery 3 A partnership-based approach Platts 7 th European

More information

US EPR nuclear technology and market outlook

US EPR nuclear technology and market outlook US EPR nuclear technology and market outlook Bruno Blotas Vice-President, Business Development 29 May 2013 Mexico City Conference The future of nuclear energy AREVA at a glance The US-EPR Status of ongoing

More information

AREVA: supply chain network principles and company s vision

AREVA: supply chain network principles and company s vision AREVA: supply chain network principles and company s vision Virginie MOUCQUOT-LAIHO AREVA Finland Communications Director & Vice Country Manager Oulu, Finland 18.09.2012 1 AREVA & nuclear industry The

More information

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011 Olkiluoto 3 Project AREVA Suppliers Day Warsaw October 4, 2011 Virginie MOUCQUOT-LAIHO AREVA OL3 Project Management Office & Communications Manager AREVA Reactor & Services - New Builds EPR Project Fleet

More information

Olkiluoto 3 Project June 2010

Olkiluoto 3 Project June 2010 Olkiluoto 3 Project June 2010 Author: R&S Communications Department, La Défense, France. The reproduction, transmission or use of this document or its contents is not permitted without express written

More information

New nuclear project financing Warsaw, June 26, 2013 p. 1

New nuclear project financing Warsaw, June 26, 2013 p. 1 New nuclear project financing Warsaw, June 26, 2013 p. 1 The EPR design: a reference technology Loïc ELOY Director of New Builds Offers Poland Platts Conference Warsaw, 26 June 2013 EPR reactor design

More information

AREVA Advanced nuclear power plants

AREVA Advanced nuclear power plants AREVA Advanced nuclear power plants Bernard Bastide AREVA Brazil and South America VP University of Rio de Janeiro III Semana da Engenharia Nuclear UFRJ August 2013 AREVA presentation AREVA EPR projects

More information

The EPR reactor the reference for New Build

The EPR reactor the reference for New Build The EPR reactor the reference for New Build The reference for New Build The Reference for Safety The EPR design offers the highest level of safety: Already licensed in France, Finland and China Strong

More information

A Nuclear New Deal. Jacques Besnainou. President, AREVA Inc. AREVA

A Nuclear New Deal. Jacques Besnainou. President, AREVA Inc. AREVA AREVA Building Energy Certainty: A Nuclear New Deal Jacques Besnainou President, AREVA Inc. AREVA EnergyBiz Leadership Forum, Session Two: Resource Review Washington, D.C. March 9, 2009 Three ways forward

More information

NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012

NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012 NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012 Tanhua Jarmo Teollisuuden Voima Oyj 2 EU ENERGY ROADMAP 2050 NUCLEAR POWER IN ALL SCENARIOS Consumption of electricity

More information

Structural Integrity and NDE Reliability II

Structural Integrity and NDE Reliability II Structural Integrity and NDE Reliability II Preparing for EPR TM Reactor Vessel Inspection J. Laube, AREVA NDE Solutions / intelligendt, Germany Y. Bouveret, AREVA NDE Solutions / Intercontrole, France

More information

AREVA: Global leader in low-carbon power generation

AREVA: Global leader in low-carbon power generation AREVA: Global leader in low-carbon power generation Premium Review Société Générale Paris, November 29 th, 2012 Agenda AREVA overview Strategy & performance Financial Outlook AREVA Presentation November

More information

Join the UK Nuclear Renaissance. Procurement & Quality Process

Join the UK Nuclear Renaissance. Procurement & Quality Process Join the UK Nuclear Renaissance Procurement & Quality Process 1 AREVA NP UK Supplier Day, March 16th Birmingham EPR is a trademark of the AREVA Group 1 The Process: AREVA Supply Chain Strategy Didier David

More information

AREVA. Solutions for Nuclear & Renewable Power Generation

AREVA. Solutions for Nuclear & Renewable Power Generation AREVA Solutions for Nuclear & Renewable Power Generation 1 AREVA Group Arlit, Niger Melox, France La Hague, France Lynchburg, U.S.A. Alpha Ventus, Germany 2 AREVA Group 2011 Key Figures 8.872Bn in Annual

More information

What Are Vendors Looking for in NPP Finance?

What Are Vendors Looking for in NPP Finance? NEA Workshop 19 September 2013 The Role of Electricity Price Stability and Long Term Financing for Nuclear New Build What Are Vendors Looking for in NPP Finance? Jean-Hugues Perréard, Vice President Project

More information

Nuclear Consultancy & Engineering Services

Nuclear Consultancy & Engineering Services Insert a caption to go with the photograph in here ITER, France Wednesday, 14 December 2011 Nuclear Consultancy & Engineering Services T H E N U C L E A R A T K I N S A S S Y S T E M A L L I A N C E CONSTRUCTION

More information

Paris, April 26, 2012

Paris, April 26, 2012 At March 31, 2012: 2.4% revenue growth to 2.026bn (+1.3% like for like) Backlog growth year on year to 45.1bn (+3.7%), down slightly over 3 months (-1.0%) Paris, April 26, 2012 AREVA generated consolidated

More information

Physics and Engineering of the EPR

Physics and Engineering of the EPR Physics and Engineering of the EPR Keith Ardron UK Licensing Manager, UK Presentation to IOP Nuclear Industry Group Birchwood Park, Warrington UK, November 10 2010 EPRs in UK EPR is Generation 3+ PWR design

More information

Solutions for Nuclear & Renewable Power Generation

Solutions for Nuclear & Renewable Power Generation Solutions for Nuclear & Renewable Power Generation Integrated Business Model Luc Oursel AREVA CEO AREVA has become the undisputed global leader in low carbon power generation solutions through its unique

More information

Nuclear Design Practices and the Case of Loviisa 3

Nuclear Design Practices and the Case of Loviisa 3 Nuclear Design Practices and the Case of Loviisa 3 Harri Tuomisto Fortum Power, Finland Third Nuclear Power School, 20-22 October 2010, Gdańsk, Poland 22 October 2010 Harri Tuomisto 1 Objectives The objective

More information

Swiss media visit to Olkiluoto August 15, 2014

Swiss media visit to Olkiluoto August 15, 2014 Swiss media visit to Olkiluoto August 15, 2014 Käthe Sarparanta Senior Adviser, Project Department Teollisuuden Voima Oyj NUCLEAR POWER PLANTS IN FINLAND Olkiluoto, Eurajoki Population 5.4 million Power

More information

Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants

Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants Westinghouse Electric Company & The Nuclear Fuel Cycle Royal Commission - South Australia November 4, 2015 1 AP1000 is a trademark

More information

Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland

Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland IAEA Technical meeting on Safety culture in pre-operational

More information

Drivers and approach for the design of the EPR reactor

Drivers and approach for the design of the EPR reactor Drivers and approach for the design of the EPR reactor Martine Mayousse Reactor & Services / Safety & Licensing IAEA Vienna June 27, 2013 1 Agenda 1. Introduction 2. EPR design objectives and principles

More information

U.S. EPR Design Overview

U.S. EPR Design Overview U.S. EPR Design Overview Brian A. McIntyre U.S. EPR Design Certification Project Manager WM2009 Conference March 4, 2009 The EPR Story 1989: Agreement between Framatome and Siemens on development of common

More information

The World Nuclear Supply

The World Nuclear Supply The World Nuclear Supply Chain An Overview Greg KASER Staff Director NEA International WPNE Workshop Paris 11 March 2014 Outline of Presentation 1. About WNA 2. Value of: New construction Early dismantlement

More information

May 23, 2011 Tokyo Electric Power Company

May 23, 2011 Tokyo Electric Power Company Analysis and evaluation of the operation record and accident record of Fukushima Daiichi Nuclear Power Station at the time of Tohoku-Chihou-Taiheiyou-Oki-Earthquake (summary) May 23, 2011 Tokyo Electric

More information

Advanced Construction Methods for New Nuclear Power Plants

Advanced Construction Methods for New Nuclear Power Plants Advanced Construction Methods for New Nuclear Power Plants A. Introduction Relative to coal fired and natural gas fired power plants, nuclear power plants are more expensive to build but less expensive

More information

Flamanville 3 Nuclear Power Plant

Flamanville 3 Nuclear Power Plant Flamanville 3 Nuclear Power Plant Prepared by: Giorgio Locatelli (University of Lincoln) and Mauro Mancini (Politecnico di Milano) Contacts: Giorgio Locatelli University of Lincoln Lincoln School of Engineering

More information

AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH

AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH Thomas M. Williamson, P.E. VP, New Plant Market Strategy AREVA Inc. Introduction AREVA Overview Nuclear

More information

Q1 2013 Q1 2012 1 Change Change LFL

Q1 2013 Q1 2012 1 Change Change LFL At March 31, 2013: Strong revenue growth of 12.5% to 2.279bn (+15.5% like for like) Stable backlog year on year: 44.9bn (-1.0% over the quarter) Paris, April 25, 2013 Luc Oursel, Chief Executive Officer,

More information

AP1000 Technology: Passive & Proven

AP1000 Technology: Passive & Proven AP1000 Technology: Passive & Proven The Right Fit for Brazil Jeff Benjamin Senior Vice President Nuclear Power Plants (NPP) AP1000 is a trademark or registered trademark of Westinghouse Electric Company

More information

The ACR : Advanced Design Features for a Short Construction Schedule

The ACR : Advanced Design Features for a Short Construction Schedule Transactions of the 17 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 17) Prague, Czech Republic, August 17 22, 2003 Paper # S01-3 The ACR : Advanced Design Features for

More information

An overview of available reactor designs 2012 Jim Thomson

An overview of available reactor designs 2012 Jim Thomson An overview of available reactor designs 2012 Jim Thomson The main designs worldwide are: 1. Areva EPR 2. (Areva Kerena BWR) 3. Areva-Mitsubishi Atmea 4. Atomstroyexport VVER-1200 5. CNGPC CPR-1000 6.

More information

Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build

Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build John H. Moore Nuclear Power Division j.h.moore@iaea.org Paris, France March 11, 2014 (OECD Workshop) International

More information

DESIGN OF EPR. Bernard DEBONTRIDE France, bernard.debontride @framatome-anp.com. AREVA FRAMATOME ANP Plants Sector Nuclear Engineering

DESIGN OF EPR. Bernard DEBONTRIDE France, bernard.debontride @framatome-anp.com. AREVA FRAMATOME ANP Plants Sector Nuclear Engineering DESIGN OF EPR Bernard DEBONTRIDE France, bernard.debontride @framatome-anp.com AREVA FRAMATOME ANP Plants Sector Nuclear Engineering Key Words: EPR, Design Abstract: At the origin was the common decision

More information

Olkiluoto 3 Experience

Olkiluoto 3 Experience Olkiluoto 3 Experience CNRA International Workshop on New Reactor Siting, Licensing and Construction Experience Hosted by the State Office for Nuclear Safety Prague, Czech Republic 15-17 September 2010

More information

SPANISH NUCLEAR INDUSTRY. Antonio Cornadó Quibus President Spanish Nuclear Industry Forum

SPANISH NUCLEAR INDUSTRY. Antonio Cornadó Quibus President Spanish Nuclear Industry Forum SPANISH NUCLEAR INDUSTRY Antonio Cornadó Quibus President Spanish Nuclear Industry Forum WHAT IS SPANISH NUCLEAR IDUSTRY FORUM? An association of companies that support activities related to nuclear energy:

More information

Olkiluoto 3 Basic Facts

Olkiluoto 3 Basic Facts Olkiluoto 3 Basic Facts TVO a world-class nuclear power company Teollisuuden Voima Oy (TVO) is a Finnish limited liability company established in 1969. The operating idea of the Company is to produce electricity

More information

Nuclear Safety First POWER

Nuclear Safety First POWER Nuclear PRoduct SOLUTIONS Emergency Diesel Generators Nuclear Safety First POWER Welcome to Alstom Power Alstom is a global leader in power generation with a portfolio of products covering all fuel types.

More information

The Essential Guide to the new build nuclear supply chain

The Essential Guide to the new build nuclear supply chain The Essential Guide to the new build nuclear supply chain Opportunities, routes to market, codes and quality arrangements for nuclear new build in the UK Stage One February 2011 Created by: Endorsed by:

More information

Office for Nuclear Regulation

Office for Nuclear Regulation Office for Nuclear Regulation ASSESSMENT REPORT Civil Nuclear Reactors Programme NNB GenCo: Hinkley Point C Pre-Construction Safety Report 2012 Assessment Report for Severe Accident Work Stream (B20) Assessment

More information

Teollisuuden Voima Oyj - General Presentation January 2009. Ilkka Mikkola Senior Adviser (Former Fuel Manager) Teollisuuden Voima Oyj

Teollisuuden Voima Oyj - General Presentation January 2009. Ilkka Mikkola Senior Adviser (Former Fuel Manager) Teollisuuden Voima Oyj Teollisuuden Voima Oyj - General Presentation January 2009 Ilkka Mikkola Senior Adviser (Former Fuel Manager) Teollisuuden Voima Oyj Nuclear Power Plants in Finland in 2008 Olkiluoto OL1 BWR 860 MW 1978

More information

HINKLEY POINT C: THE LONG MARCH TO FID

HINKLEY POINT C: THE LONG MARCH TO FID HINKLEY POINT C: THE LONG MARCH TO FID ELECTRIC POWER SPECIAL REPORT JULY 216 Benjamin Leveau, Editor, France and Belgium, Platts nuclear publications Oliver Adelman, Managing Editor, EMEA, Platts nuclear

More information

Global Nuclear Power Developments Asia Leads The Way

Global Nuclear Power Developments Asia Leads The Way Global Nuclear Power Developments Asia Leads The Way Edward Kee Nuclear Energy Asia 2010 - Hong Kong (1400 1430) Global Nuclear Power Developments - Asia Leads The Way What is the competitive global position

More information

NEW NUCLEAR POWER PLANTS FOR ONTARIO - THE CONTENDERS - 2008 October

NEW NUCLEAR POWER PLANTS FOR ONTARIO - THE CONTENDERS - 2008 October NEW NUCLEAR POWER PLANTS FOR ONTARIO - THE CONTENDERS - 2008 October (THIS OVERVIEW IS AN UPDATED VERSION OF AN EARLIER ONE THAT WAS PUBLISHED IN THE BULLETIN OF THE CANADIAN NUCLEAR SOCIETY, MARCH 2008,

More information

POWER & RENEWABLE ENERGY SERVICES

POWER & RENEWABLE ENERGY SERVICES POWER & RENEWABLE ENERGY SERVICES Siting - Assistance to permitting Environmental Impact Assessment Safety and environmental audits Construction code compliance and design review Supplier Technical Assessment

More information

Best Practices and Approaches to Supply Chain Management

Best Practices and Approaches to Supply Chain Management Best Practices and Approaches to Supply Chain Management ATOMEX Forum 2012 Moscow 12.12. 14.12.2012 AF-Consult Switzerland Ltd Jan Kocourek 1 Objectives Provide information available regarding both the

More information

Boiling Water Reactor Systems

Boiling Water Reactor Systems Boiling Water (BWR) s This chapter will discuss the purposes of some of the major systems and components associated with a boiling water reactor (BWR) in the generation of electrical power. USNRC Technical

More information

Workshop GESEL - UFRJ: O presente e o futuro da energia nuclear no Brasil

Workshop GESEL - UFRJ: O presente e o futuro da energia nuclear no Brasil Workshop GESEL - UFRJ: O presente e o futuro da energia nuclear no Brasil Jürgen Czech Diretor Técnico AREVA NP Johannes Höbart Diretor Presidente AREVA Brasil Rio de Janeiro - Dezembro/2009 Introduction

More information

KERNREACTOREN EEN OVERZICHT VAN GENERATIE III+ KERNREACTOREN

KERNREACTOREN EEN OVERZICHT VAN GENERATIE III+ KERNREACTOREN KERNREACTOREN EEN OVERZICHT VAN GENERATIE III+ KERNREACTOREN Frank Bertels Tractebel Engineering (GDF Suez) KVAB debatavond: Nieuwe generatie kernreactoren 13 november 2014 CHOOSE EXPERTS, FIND PARTNERS

More information

POWER & RENEWABLE ENERGY SERVICES

POWER & RENEWABLE ENERGY SERVICES POWER & RENEWABLE ENERGY SERVICES Nuclea Siting - Assistance to permitting Environmental Impact Assessment Safety and environmental audits Construction code compliance and design review Supplier Technical

More information

Safety of New Nuclear Power Plants

Safety of New Nuclear Power Plants Safety of New Nuclear Power Plants Example: VVER-1200/V491 H. Hirsch A. Y. Indradiningrat Workshop on the Paks II NPP Project Budapest, Energiaklub, 08.10.2014 New NPP in Paks: Reactor Type In the EIA

More information

Nuclear Safety. Policy 2013-2016

Nuclear Safety. Policy 2013-2016 Nuclear Safety Policy 2013-2016 Nuclear Safety Policy 2013-2016 T he organisational principles and actions defined in the Nuclear Safety Charter and applied within the group have achieved significant improvements

More information

Fukushima 2011. Fukushima Daiichi accident. Nuclear fission. Distribution of energy. Fission product distribution. Nuclear fuel

Fukushima 2011. Fukushima Daiichi accident. Nuclear fission. Distribution of energy. Fission product distribution. Nuclear fuel Fukushima 2011 Safety of Nuclear Power Plants Earthquake and Tsunami Accident initiators and progression Jan Leen Kloosterman Delft University of Technology 1 2 Nuclear fission Distribution of energy radioactive

More information

AP1000 Overview. 2011 Westinghouse Electric Company LLC - All Rights Reserved

AP1000 Overview. 2011 Westinghouse Electric Company LLC - All Rights Reserved AP1000 Overview AP1000 is a registered trademark in the United States of Westinghouse Electric Company LLC, its subsidiaries and/or its affiliates. This mark may also be used and/or registered in other

More information

PRESS RELEASE. At September 30, 2015: Progress on the transformation plan in the third quarter:

PRESS RELEASE. At September 30, 2015: Progress on the transformation plan in the third quarter: At September 30, 2015: Rise in revenue to 2.947bn: +10.3% vs. September 2014 (+8.7% like for like) Backlog of 31.595bn Discontinued operations, including AREVA NP: Revenue of 2.732bn: -7.5% vs. September

More information

First half 2009 results and outlook. Monday, August 31, 2009

First half 2009 results and outlook. Monday, August 31, 2009 First half 2009 results and outlook Monday, August 31, 2009 Notice Forward-looking statements This document contains forward-looking statements and information. These statements include financial forecasts

More information

HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT. New Reactor Build. EDF/AREVA EPR Step 2 PSA Assessment

HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT. New Reactor Build. EDF/AREVA EPR Step 2 PSA Assessment HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT New Reactor Build EDF/AREVA EPR Step 2 PSA Assessment HM Nuclear Installations Inspectorate Redgrave Court Merton Road Bootle Merseyside

More information

Accenture Utilities Podcast Series A perspective on enterprise asset management in the power generation sector

Accenture Utilities Podcast Series A perspective on enterprise asset management in the power generation sector Accenture Utilities Podcast Series A perspective on enterprise asset management in the power generation sector An interview with Todd Knapp, Accenture s Enterprise Asset Management Lead in Accenture Utilities

More information

Rosatom Investment Projects. Perspective in Europe and in the world

Rosatom Investment Projects. Perspective in Europe and in the world ROSATOM Rosatom Investment Projects Perspective in Europe and in the world Ivo Kouklík Vice-President, Rusatom Overseas June 13, 013 Rauma PRESENTATION CONTENT ROSATOM - Introduction ROSATOM Investment

More information

Operational Reactor Safety 22.091/22.903

Operational Reactor Safety 22.091/22.903 Operational Reactor Safety 22.091/22.903 Professor Andrew C. Kadak Professor of the Practice Lecture 19 Three Mile Island Accident Primary system Pilot operated relief valve Secondary System Emergency

More information

XA0302230 EVALUATION OF TRAINING ACTIVITIES IN ARGENTINA

XA0302230 EVALUATION OF TRAINING ACTIVITIES IN ARGENTINA XA0302230 EVALUATION OF TRAINING ACTIVITIES IN ARGENTINA Alejandro D. SANDA ATUCHANPP ARGENTINA I came from Argentina. Do you know where Argentina is? Argentina is in South America, below Brazil. The area

More information

February 19, 2014. Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company

February 19, 2014. Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company JAPAN-U.S. DECOMISSIONING AND REMEDIATION FUKUSHIMA RECOVERY FORUM February 19, 2014 Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company Toshiba global formation Information

More information

Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions. Nici Bergroth, Fortum Oyj FORS-seminar 26.11.

Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions. Nici Bergroth, Fortum Oyj FORS-seminar 26.11. Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions Nici Bergroth, Fortum Oyj FORS-seminar 26.11.2009, Otaniemi Loviisa 3 CHP Basis for the Loviisa 3 CHP alternative Replacement

More information

Fact Sheet on China s energy sector and Danish solutions

Fact Sheet on China s energy sector and Danish solutions Fact Sheet on China s energy sector and Danish solutions 1. EXPANSION WITH RENEWABLE ENERGY: China focuses on a massive expansion with non fossil energy that is renewable energy and nuclear energy. The

More information

First Quarter 2014 Earnings Conference Call. New Nuclear Presentation Section. April 24, 2014 First Quarter 2014 Earnings Conference Call 1

First Quarter 2014 Earnings Conference Call. New Nuclear Presentation Section. April 24, 2014 First Quarter 2014 Earnings Conference Call 1 First Quarter 2014 Earnings Conference Call New Nuclear Presentation Section April 24, 2014 1 Safe Harbor Statement/Regulation G Information Statements included in this presentation which are not statements

More information

Nuclear Education & Training in France. Support to Newcomer and Expanding Countries

Nuclear Education & Training in France. Support to Newcomer and Expanding Countries Nuclear Education & Training in France Support to Newcomer and Expanding Countries H.E. Ms. Marion Paradas Permanent Representative of France to the IAEA Mr. Yves Fanjas Academia & Research: Mr. François

More information

Public SUMMARY OF EU STRESS TEST FOR LOVIISA NUCLEAR POWER PLANT

Public SUMMARY OF EU STRESS TEST FOR LOVIISA NUCLEAR POWER PLANT 1 (8) SUMMARY OF EU STRESS TEST FOR LOVIISA NUCLEAR POWER PLANT 1 LOVIISA NUCLEAR POWER PLANT Loviisa town is located approximately 90 km eastwards from Helsinki at the coast of Gulf of Finland. Loviisa

More information

ANCHOR BOLTS FOR NUCLEAR POWER PLANT APPLICATIONS

ANCHOR BOLTS FOR NUCLEAR POWER PLANT APPLICATIONS ANCHOR BOLTS FOR NUCLEAR POWER PLANT APPLICATIONS EXPERIENCE FROM DESIGN AND CONSTRUCTION OF OLKILUOTO UNITS 2015-11-03 Kukkola Timo 2 OL1 AND OL2 CROSS-SECTION 3 OL1 AND OL2 OL1 and OL2 continuous improvement

More information

We endorse a comprehensive approach to address all greenhouse gas emissions. We recognise the importance of increasing energy efficiency

We endorse a comprehensive approach to address all greenhouse gas emissions. We recognise the importance of increasing energy efficiency JOINT STATEMENT BY THE G8 ENERGY MINISTERS, THE EUROPEAN ENERGY COMMISSIONER, THE ENERGY MINISTERS OF BRAZIL, CHINA, EGYPT, IN- DIA, KOREA, MEXICO, SAUDI ARABIA, AND SOUTH AFRICA The Energy Ministers of

More information

PGE - Polish Energy Group. Nuclear power development in Poland - we need decision today. Organisation of the Polish Power Sector After Consolidation

PGE - Polish Energy Group. Nuclear power development in Poland - we need decision today. Organisation of the Polish Power Sector After Consolidation Nuclear power development in Poland - we need decision today Hanna Trojanowska Director of International Affairs and New Technologies Department PGE Polska Grupa Energetyczna S.A. Organisation of the Polish

More information

Introduction of the education and training courses to support emerging countries

Introduction of the education and training courses to support emerging countries Introduction of the education and training courses to support emerging countries Kazuo KISHIDA (JICC) IAEA TM to Prepare Guidance Documents for Capacity Building in Vienna, Austria on February 23-27, 2015

More information

Course available 24/7 for up to six months from the date of purchase or until completion

Course available 24/7 for up to six months from the date of purchase or until completion SPED ONLINE COURSE TRAINING Piper BootCamp and Process Plant Layout BOTH Piper BootCamp and Process Plant Layout online courses contain: Approximately 25 hours of online videos Printable notes Links to

More information

The Supply Chain for a UK Nuclear New Build Programme

The Supply Chain for a UK Nuclear New Build Programme The Supply Chain for a UK Nuclear New Build Programme A report submitted to the Department for Business Enterprise & Regulatory Reform (BERR) by the National Metals Technology Centre (NAMTEC) Updated February

More information

Building on +60 GW of experience. Track record as of 31 December 2013

Building on +60 GW of experience. Track record as of 31 December 2013 Building on +60 GW of experience Track record as of 31 December 2013 Can data and analysis make a difference on turbine performance? Proven technology. For Vestas, it is more than a saying it is something

More information

Lessons Learned from past NPP Construction Technology/Management

Lessons Learned from past NPP Construction Technology/Management Lessons Learned from past NPP Construction Technology/Management 19 March 2014 Ki Sig Kang Nuclear Power Division International Atomic Energy Agency Trend in Construction Starts Rabidly changed the No.

More information

Procurement, Inventory Management and Supply Chain solutions for the Petrochemicals sector

Procurement, Inventory Management and Supply Chain solutions for the Petrochemicals sector Procurement, Inventory Management and Supply Chain solutions for the Petrochemicals sector 1 2 About us Saudi Maintenance and Supply Chain Management Company (SMSCMC) is a top-tier integrated supply chain

More information

Construction automation and productivity - Industry perspective

Construction automation and productivity - Industry perspective Construction automation and productivity - Industry perspective Vice President R&D, Ilkka Romo Skanska Oy 22.1.2013 1 22.1.2013 Ilkka Romo Skanska in short One of the world s leading companies in construction

More information

4 3 Divisional update

4 3 Divisional update 4 3 Divisional update Industry Denis Gasquet Water Jean-Michel Herrewyn Environmental Services Jérôme Le Conte Energy Services Franck Lacroix Transport Jérôme Gallot 99 Veolia Energy: key figures 900 urban/

More information

Piping Systems for Nuclear Power Industry. Prague, October 2011

Piping Systems for Nuclear Power Industry. Prague, October 2011 Piping Systems for Nuclear Power Industry Prague, October 2011 Introduction of the company Leading Czech supplier of piping systems for power engineering 60 years of experience in the field of power industry

More information

GE Oil & Gas. Air cooled heat exchangers Robust and reliable for all loads and applications

GE Oil & Gas. Air cooled heat exchangers Robust and reliable for all loads and applications GE Oil & Gas Air cooled heat exchangers Robust and reliable for all loads and applications What it is Air cooled heat exchangers are commonly used in industrial applications where a reliable source of

More information

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Published in the Official State Gazette (BOE) No 283 of November 24 th 2009 Nuclear Safety Council Instruction

More information

The Essential Guide for the nuclear new build supply chain

The Essential Guide for the nuclear new build supply chain The Essential Guide for the nuclear new build supply chain STAGE TWO MARCH 2013 Contents Introduction P. 02 1 Project Certainty and Timeline P. 04 Developers Planning to Build New Nuclear Power Stations

More information

Conventional Energy Sources

Conventional Energy Sources 9.2 Conventional Energy Sources Key Question: What benefits and problems come with common sources of energy? Hints The word plant here is not the kind that grows out of the ground. In this section, plants

More information

Nuclear power is part of the solution for fighting climate change

Nuclear power is part of the solution for fighting climate change Nuclear power is part of the solution for fighting climate change "Nuclear for Climate" is an initiative undertaken by the members of the French Nuclear Energy Society (SFEN), the American Nuclear Society

More information

U.S. ENGAGEMENT WITH INTERNATIONAL PARTNERS

U.S. ENGAGEMENT WITH INTERNATIONAL PARTNERS U.S. ENGAGEMENT WITH INTERNATIONAL PARTNERS Dr. Alex R. Burkart Deputy Director Office of Nuclear Energy, Safety and Security U.S. Department of State Co-Chair IFNEC Infrastructure Development Working

More information

Financing Nuclear Power Projects: Challenges and IAEA Assistance in Capacity Building

Financing Nuclear Power Projects: Challenges and IAEA Assistance in Capacity Building Financing Nuclear Power Projects: Challenges and Assistance in Capacity Building International Framework for Nuclear Energy Cooperation Finance Workshop London, 9-10 May 2012 Nadira Barkatullah International

More information

Russian approach to organization of international cooperation in the field of nuclear infrastructure (NI)

Russian approach to organization of international cooperation in the field of nuclear infrastructure (NI) STATE NUCLEAR ENERGY CORPORATION ROSATOM Russian approach to organization of international cooperation in the field of nuclear infrastructure (NI) A. E. Sitnikov Rosatom/ Rosenergoatom Russia Atomex-Asia

More information

Pocket Guide 2012. Pocket Guide 2012 1

Pocket Guide 2012. Pocket Guide 2012 1 Pocket Guide 2012 Pocket Guide 2012 1 2 Pocket Guide 2012 04 11 Teollisuuden Voima Oyj Olkiluoto nuclear power plant 4 Company 5 Shareholders and holdings 6 Important dates 10 Key figures 10 Nuclear Waste

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides

More information

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS Presented by W.J. (Chris) Zhang University of Saskatchewan Saskatoon, Canada Email: chris.zhang@usask.ca Outline 1. Modularization in NPP 2. Comparison

More information

The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station

The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station May 2012 Government and TEPCO s Mid-to Long Term Countermeasure Meeting Management Council Outline

More information

Benefits of Geothermal Energy By Dr. Silas Simiyu

Benefits of Geothermal Energy By Dr. Silas Simiyu Benefits of Geothermal Energy By Dr. Silas Simiyu Introduction Geo means Thermal means Intoduction The Earth Crust Mantle Outer core Inner core Is renewable and sustainable Reservoir managed well (Re-injection)

More information

Introductions: Dr. Stephen P. Schultz

Introductions: Dr. Stephen P. Schultz Introductions: Dr. Stephen P. Schultz Vienna, Austria 1 3 September 2015 Work Experience Current Member Advisory Committee on Reactor Safeguards, U.S. Nuclear Regulatory Commission, 12/2011 Chair, Fukushima

More information

ELEKTROBUDOWA SA for 15 years listed on WSE ELEKTROBUDOWA SA POLISH LEADER IN POWER ENGINEERING. 4th October 2011. www.elbudowa.com.

ELEKTROBUDOWA SA for 15 years listed on WSE ELEKTROBUDOWA SA POLISH LEADER IN POWER ENGINEERING. 4th October 2011. www.elbudowa.com. ELEKTROBUDOWA SA POLISH LEADER IN POWER ENGINEERING 4th October 2011 Agenda GENERAL INFORMATION ABOUT COMPANY BUSINESS SEGMENTS ELEKTROBUDOWA FOR NUCLEAR PP ELEKTROBUDOWA SA GROUP FINANCIAL STATEMENTS

More information

Overview on DHC pricing and regulations in Europe-

Overview on DHC pricing and regulations in Europe- Overview on DHC pricing and regulations in Europe- Challenges and need of development Birgitta Resvik, Corporate Relations Sweden, Vice President, Fortum Our geographical presence today Nr 3 Nr 1 Nr 1

More information

Alstom Power in Chattanooga, USA Bringing State-of-the-Art Engineering & Manufacturing Capabilities to the North American Market POWER

Alstom Power in Chattanooga, USA Bringing State-of-the-Art Engineering & Manufacturing Capabilities to the North American Market POWER POWER Alstom Power ramps up its presence in North America Alstom Power has opened a new manufacturing and engineering facility in Chattanooga, on the banks of the Tennessee river, to serve both new and

More information

Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director

Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director Seminar FPGA-based I&C Systems in Nuclear Applications February 4, 2015, Energiforsk,

More information