1 January 27, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PARKS, RECREATION, AND CULTURAL SERVICES DEPARTMENT ON WESTSYDE POOL AND COMMUNITY CENTRE ROOF REPAIR OPTIONS UPDATE PURPOSE To provide Council with the options from the City's prime consultant, Read Jones Christoffersen Engineers Ltd. (RJC), for the Westsyde Pool and Community Centre (WPCC) repair project and to seek direction to undertake a Recreation Facility and Services Review and Feasibility Study for Westsyde, North Kamloops, and Brocklehurst. SUMMARY In January 2015, there was an interior roof leak at WPCC that was caused by excessive amounts of moisture in the building, which resulted in the partial collapse of a section of the interior roof. The pool operation was temporarily closed, Council and the community were alerted, and a repair plan was developed. Under the guidance of RDH Building Engineering Ltd. (RDH), a company specializing in building envelope restoration, a repair plan was developed and implemented. The temporary fix was completed at a cost of $30,000, and the pool reopened in March 2015 and continued operating until its normal shutdown period on June 1, The pool normally reopens in September each year, but it has remained closed during the wait for the permanent roof repair. The WPCC fitness facility has remained open on a limited schedule. As part of RDH's investigation, it was discovered that a failure of the original vapour barrier system had caused excessive moisture to erode the roof support beams and ceiling materials, which resulted in unsafe conditions. Even though temporary support beams were installed in 2015, a permanent fix is necessary for the pool portion to be safely operated over the long term, as the existing pool roof cannot safely support excessive wind or snow loads. In September 2015, Administration updated Council on the next steps toward a permanent repair solution. Council authorized transferring existing capital funds from Capital Project No Canada Games Aquatic Centre Building Envelope Repair ($2,867,360) to the WPCC Roof Repair Project. At that time, Council directed Administration to apply for the Canada 150 Federal Infrastructure Grant Program for the maximum amount of $500,000. The application was unsuccessful. Administration will review the status of the Canada Games Aquatic Centre Building Envelope Repair that is currently scheduled for 2017, and Administration will bring forward recommendations to the 2017 Budget discussions once the WPCC Roof Repair Project has been completed. S:\DCS\Jobs (c3)\236529_wpcc Roof Repair Options_REP\WPCC Roof Repair Options_REP.docx 27
2 WESTSYDE POOL AND COMMUNITY CENTRE January 27, 2016 ROOF REPAIR OPTIONS Page 2 Subsequently, RJC was engaged to prepare a detailed feasibility study and options review for Council's consideration. The options presented include a variety of scopes of work, depending on the total facility use and programming desired. All options include hazardous materials abatement, soft design costs, permit fees, and design contingencies. Option Description Cost Option 1A Basic Repair $3,080,000 Option 1B Outdoor Pool $4,200,000 Option 2 Modernization $4,930,000 Option 3 Toward Net Zero $12,974,000 Option 4 As the construction repair costs significantly exceed the original estimate of $2.1 million, Administration suggests a fourth option be considered. In light of a recent ice rink closure and other recreation building maintenance needs, and to further support Council's desire to provide efficient and cost-effective services, Administration suggests undertaking a Recreation Facility and Services Review and Feasibility Study for Westsyde, North Kamloops, and Brocklehurst prior to investing additional capital in these aging facilities. In 2005, the Kamloops Joint Aquatic Facility and Services Review was completed. It examined three indoor pools (YMCA-YWCA, Canada Games Aquatic Centre, and Westsyde) and two outdoor pools (Brocklehurst and McDonald Park). This review recommended that a phased approach to consolidating and repurposing existing aquatic facilities and investing in new pools on the North Shore and downtown should be undertaken, which would result in a new pool at McArthur Island and downtown. In keeping with Council's strategic goals of good governance and fiscal responsibility, an updated Recreation Facility and Services Review and Feasibility Study would provide an opportunity to maximize the use of recreation facilities as core community assets in the Brocklehurst, North Kamloops, and Westsyde neighbourhoods. Kamloops is served by three indoor pools (YMCA-YWCA, Westsyde, and Canada Games Aquatic Centre) and two seasonal outdoor aquatics facilities (Brocklehurst Recreation Centre and McDonald Park Pool). For comparative purposes, in 2014, the combined annual subsidy investment to operate the Westsyde, Brocklehurst, and McDonald Park pools was $714,000 and the Tournament Capital Centre/Canada Games Pool annual subsidy investment was $726,000. These facilities are aging and reflect the design and building practices of earlier years. Subsequently, they are less efficient to operate and less effective in their ability to respond to the public's recreation needs and interests. A Recreation Facility and Services Review and Feasibility Study would also provide Council with the opportunity to review emerging recreational concerns such as: The loss of the Ice Box arena; The growth of pickleball and demand for services from active agers; A conversation with the community on recreation facility use and needs; A summary of results of any previous studies and research completed; An overview of existing facilities and operating costs; S:\DCS\Jobs (c3)\236529_wpcc Roof Repair Options_REP\WPCC Roof Repair Options_REP.docx 28
3 WESTSYDE POOL AND COMMUNITY CENTRE January 27, 2016 ROOF REPAIR OPTIONS Page 3 A review of future trends and recreation needs that are not currently served; A review of feasibility and cost options, which may include alternate community use of existing facilities, including: - Converting WPCC to a community centre and multi-purpose gymnasium with programming that is targeted to active agers, such as pickleball; - Adding an additional ice rink at Brocklehurst Recreation Centre; - Converting the outdoor pool at McDonald Park to a water spray park; and An opportunity to explore the feasibility and cost of constructing a leisure pool aquatic facility at McArthur Island Sport and Event Centre. RECOMMENDATION: That Council either: a) Authorize staff to pursue Option 4 to conduct a Recreation Facility and Services and Review Feasibility Study for Westsyde, North Kamloops, and Brocklehurst and authorize Administration to: OR i) undertake a Recreation Facility and Services Review and Feasibility Study for Westsyde, North Kamloops, and Brocklehurst at a cost of $100,000, with funding provided from the Gaming Reserve Fund; ii) provide a report to Council with results of the feasibility concept plan and recommendations on next steps; and ii) update the Financial Plan to reflect this cost; b) Authorize Administration to: i) undertake Option 2 - Modernization for Westsyde Pool and Community Centre (WPCC) at a total cost of $4,930,000 with funding from the Community Works Reserve Fund; ii) increase Capital Project No WPCC Pool Repair by $2,062,640, with funding from the Community Works Reserve Fund; and iii) include the WPCC Project in the Financial Plan. COUNCIL POLICY The Council Strategic Plan identifies good governance, livability, and fiscal responsibility as key objectives, which support the study of recreation facility and programming opportunities in Westsyde, Brocklehurst, and North Kamloops from a long-term perspective. S:\DCS\Jobs (c3)\236529_wpcc Roof Repair Options_REP\WPCC Roof Repair Options_REP.docx 29
4 WESTSYDE POOL AND COMMUNITY CENTRE January 27, 2016 ROOF REPAIR OPTIONS Page 4 To provide historical context, the City's most recent recreation master plan, the Kamloops Joint Aquatic Facility and Services Review, was undertaken in Prior to that, the 2003 Parks and Recreation Master Plan was implemented and then updated as the "Oasis of Activity: City of Kamloops Parks Master Plan" in Recreation and health and wellness are also key components of the Sustainable Kamloops Plan (2010). DISCUSSION To provide Council with a full range of potential costs and improvement benefits, RJC was directed to consider several unique options ranging from basic, targeted repairs to just the roof structure to a complete facility refresh and amenity enhancement. Each of the four options provides Council with a unique and realistic approach to repairing the pool roof over the short- and long-term. A full, detailed breakdown is provided in Attachment "A". Attachment "B" contains illustrations and floor plans for each option. Option 1A - Basic Repair $3,080,000 This option is $212,640 higher than current funding levels and may achieve the original time frame for completion of September 1, It proposes replacing the roof structure completely and providing an improvement in insulation R-value in the roof area only. The mechanical and HVAC systems will remain the same, but the dehumidification system will be improved. RJC states the existing dehumidification system is under capacity for a building of this size, and it is the primary reason for the moisture-related repair issues at present. It is RJC's opinion that this option does not adequately address the long-term issue of the existing inefficient HVAC and mechanical systems or the eventual need to replace this infrastructure to ensure the longevity and integrity of the building envelope (the existing air handling system has three to five years of useful life remaining). The estimated construction time is six months, with an additional two to three months for detailed design and tendering, for a total of eight to nine months. Option 1B - Outdoor Pool $4,200,000 This option is $1,332,640 higher than current funding levels and may achieve the original time frame for completion of September 1, It proposes eliminating the existing roof structure completely and building three new walls to separate the rest of the facility from the outdoor pool deck. The mechanical and HVAC systems would require reconfiguration, but the dehumidification system is less robust due to less interior space. This option presents some interesting opportunities for year-round use and programming; however, the winter months will significantly impact energy costs due to outside temperatures and heat loss from the pool. As well, the pool deck will require heat tracing throughout to make it comfortable and safe for public use in cold months. This option eliminates the need for a new HVAC and dehumidification system; however, the long-term utility costs are substantial, and the public acceptance of an outdoor pool in the winter months is a concern. The estimated construction time is six months, with an additional two to three months for detailed design and tendering, for a total of eight to nine months. S:\DCS\Jobs (c3)\236529_wpcc Roof Repair Options_REP\WPCC Roof Repair Options_REP.docx 30
5 WESTSYDE POOL AND COMMUNITY CENTRE January 27, 2016 ROOF REPAIR OPTIONS Page 5 Option 2 - Modernization $4,930,000 This option is $2,062,640 higher than current funding levels and requires an additional construction time frame of three months (December 1, 2016, estimated completion). This option proposes a complete replacement of the HVAC, mechanical, and dehumidification systems, as well as improvements to the R-value of the building envelope's insulation. The existing air handling system has three to five years of useful life remaining, so RJC recommends full replacement. An exterior finish and additional window glazing will create a modern, attractive look and provide natural light and improved energy efficiency throughout. This option will provide fully balanced mechanical and HVAC systems that will minimize future energy costs and humidity impacts on the building envelope. Also included in this option is the ability to pre-wire for the installation of solar panels for future use and to plan for the roof to be strong enough to hold the additional weight of those panels. The estimated construction time is nine months, with an additional two to three months for detailed design and tendering, for a total of 11 to 12 months. Option 3 - Toward Net Zero $12,974,000 This option is $10,100,400 higher than current funding levels and will require an additional construction time frame of six to nine months (June 1, 2017, estimated completion). This option provides the most complete refresh of WPCC. It includes geothermal heating and cooling, envelope upgrades, and a solar array help the building achieve net zero emissions. The interior amenity space will be significantly expanded, with a second floor area that would allow expansion of the fitness facility and programming. Space for an additional leisure pool and hot tub is included in this design option. This option also includes the demand for 55 additional parking spaces due to expected higher use. Parking is a limiting factor since the City does not have any other land parcels in the immediate area that could be used for surface parking. The parking capacity may not be an issue in summer months or during school holidays. The estimated construction time is 12 to14 months, with an additional three to four months for detailed design and tendering, for a total of 15 to17 months. Option 4 - Conduct a Recreation Facility and Services Review and Feasibility Study As the construction repair costs significantly exceed the original estimate of $2.1 million, and in support of Council's desire to provide recreation services as efficient and cost-effective as possible, Administration proposes a fourth option, which is to conduct a Recreation Facility and Services Review and Feasibility Study for Westsyde, Brocklehurst, and North Kamloops prior to investing additional capital in these aging facilities. For Council information, since McDonald Park Pool closed for the season in September 2015, it has experienced a failure with its hot water boiler ($65,000 replacement cost) and main pool drain ($150,000 cost estimate), which are both required for normal pool operations prior to its reopening in June These costs are not in the 2016 Financial Plan. Administration will be bringing this information forward to Council for direction once the final cost estimate is completed for the main pool drain issue. McDonald Park Pool was constructed in S:\DCS\Jobs (c3)\236529_wpcc Roof Repair Options_REP\WPCC Roof Repair Options_REP.docx 31
6 WESTSYDE POOL AND COMMUNITY CENTRE January 27, 2016 ROOF REPAIR OPTIONS Page 6 In 2005, a collaborative research study, the Kamloops Joint Aquatic Facility and Services Review, was conducted by the City and the Kamloops YMCA-YWCA. The study examined three indoor pools (the YMCA-YWCA downtown pool, the Canada Games Aquatic Centre, and Westsyde Pool) and two outdoor pools (Brocklehurst and McDonald Park). The intent of the report was to "review and analyze Kamloops' current aquatic service and facilities and make recommendations to ensure the communities continued support of the service" and "to determine the future needs and preferences and recommend the type of services, facilities, or renovations to facilities that are required to meet those needs in a cost-effective manner." The collaborative review discussed the need for improvements to existing pools, possible new pools, and a number of phasing options in order to ensure that the City has an appropriate amount of water to meet community needs beyond In summary, the report suggested a reconfiguration involving the following phases: Phase One (2012) - The construction of a new indoor/outdoor pool multi-purpose community leisure pool on the North Shore and closure of the YMCA-YWCA pool (Administration does not support the recommendations regarding the YMCA-YWCA pool). No significant improvements should be made to the two outdoor pools. Phase Two (2017) - The closure of McDonald Park and Brocklehurst outdoor pools. Phase Three (2022) - A major renovation to the Canada Games Aquatic Centre to improve leisure amenities to allow more visits and the construction of a new urban pool in the downtown area. With reference to Westsyde Pool, the collaborative review states: A decision could be made that because of its very low attendance, and the fact it has reached middle age, that no improvements should be undertaken, and that it should be closed when the proposed North Shore facility is built, and converted to some other type of multi-purpose recreation facility. A decision could be made for a small number of leisure facilities such as a hot tub, a larger fitness area, a warm teaching pool, and several interactive features that appeal to young children. A renovation of this type which renovation of this type, which would include improvements to mechanical systems would extend the life of the facility and in all likelihood the number of visitors. It is in the consultant's opinion, however, that attendance figures would not increase dramatically. Based on these conclusions, Administration suggests that Council consider an additional option to conduct a Recreation Facility and Services Review and Feasibility Study for Westsyde, North Kamloops, and Brocklehurst, which would provide the opportunity to maximize the use of recreation facilities as core community assets over the longer term. SUSTAINABILITY IMPLICATIONS Options 2 and 3 provide the best overall building energy efficiency improvements for WPCC, as the mechanical and air handling systems would be modernized to today's standards. Also, both options include the opportunity to install solar panels on the new roof structure. S:\DCS\Jobs (c3)\236529_wpcc Roof Repair Options_REP\WPCC Roof Repair Options_REP.docx 32
7 WESTSYDE POOL AND COMMUNITY CENTRE January 27, 2016 ROOF REPAIR OPTIONS Page 7 FINANCIAL IMPLICATIONS All estimated costs of Options 1A, 1B, 2, and 3 are based on Class "C" probability levels and include all contingencies for soft and construction costs (+10%). Administration does not recommend the lowest price Option1A - Basic Repair because, in RJC's opinion, the existing air handling and mechanical system will eventually require complete replacement due to its age and lack of capacity and may be more expensive to update and repair in future years. The WPCC, when in full operation, has an annual operating budget of $547,000. Under normal activity levels, the admissions and programming revenue is $130,000, with a net cost to operate of $417,000. It is anticipated the facility will be closed for normal operations until September 2016, which has reduced the net tax subsidy required by $70,000 and is reflected in the 2016 Financial Plan. Depending on which option Council chooses, any further construction closure times beyond September 1, 2016, will result in net operational cost reductions of $35,000 per month. For example, based on Option 2 - Modernization, the estimated completion time is December 2016, which will reduce the net operating cost by an additional $105,000 ($175,000 total reduction in net tax subsidy for 2016). The Community Works Reserve Fund currently has an uncommitted balance of $2.7 million. If Council chooses Option 2 - Modernization, the uncommitted balance will be $637,360. For Council information, the Canada Games Aquatic Centre Building Envelope Repair project is currently in the 2017 Financial Plan, with funding provided by the Community Works Fund ($3 million). PERSONNEL IMPLICATIONS Although the gym facility is currently open on a limited schedule, depending on which repair option Council chooses, the gym will need to be closed for the duration of the construction period for safety reasons. Administration reviewed options of transferring fitness equipment and staff from WPCC to the nearby Westsyde Community Centre gymnasium, but the existing programming demand for that gym space and the cost of setting up a registration desk do not make that plan feasible. If the Recreation Facility and Services Review and Feasibility Study is undertaken, the gymnasium facility can remain open according to its current schedule. IMPLEMENTATION PLAN If Option 4, Recreation Facility and Services Review and Feasibility Study is undertaken, to provide certainty for all stakeholders, the goal is to complete the scope of work as quickly as possible to provide the community and Council with an opportunity to review the results within 90 days. S:\DCS\Jobs (c3)\236529_wpcc Roof Repair Options_REP\WPCC Roof Repair Options_REP.docx 33
8 WESTSYDE POOL AND COMMUNITY CENTRE January 27, 2016 ROOF REPAIR OPTIONS Page 8 COMMUNICATIONS PLAN The Parks, Recreation, and Cultural Services Department has been in regular contact with the Westsyde Community Development Society on the project status. Arrangements will be made to conduct a public open house to announce Council's course of action. There will be a communications fund allowance of $10,000 included in the construction budget for each of the options provided. B. J. McCorkell Parks, Recreation, and Cultural Services Director Approved for Council Consideration: Concurrence: K. Humphrey, CPA, CA, Finance Director J. Fretz, P.Eng., Public Works and Utilities Director Author: J. T. Putnam, B.Comm., Parks and Civic Facilities Manager Reviewed by: B. Berger, Recreation, Social Development, and Culture Manager JTP/dla/lm/kjm Attachments S:\DCS\Jobs (c3)\236529_wpcc Roof Repair Options_REP\WPCC Roof Repair Options_REP.docx 34
9 Westsyde Pool - Total Cost for Options Attachment "A" 1a - Targeted Repair 1b - Outdoor Pool Hard Costs (From LEC Reports) Architectural Building Envelope $ 369, , Projections $ 16, Finishes / Interior $ 60, , Structural $ 316, Mechanical $ 314, , Electrical $ 162, , Sitework $ 100, , Ancilliary Work $ 262, , Overhead $ 240, , Profit $ 93, , Design Contingency $ 315, , Sub-Total Hard Costs $ 2,249, ,760, Amenities Additional Cost Allowance Allowance for Leisure Pool + Hot Tub or Slide Replacement $ 150, , Allowance for Adding Parking $ - 300, Total with Allowances $ 2,399, ,320, Option 2 - Envelope and HVAC Modernization Option 3 - toward net zero $ $ 674, $ 1,233, $ $ 31, $ 93, $ $ 156, $ 1,349, $ $ 316, $ 1,098, $ $ 528, $ 1,846, $ $ 305, $ 724, $ $ 100, $ 285, $ $ 291, $ 556, $ $ 360, $ 1,078, $ $ 138, $ 413, $ $ 447, $ 1,346, Leisure Pool and Hot Tub Included in $ $ 3,350, $ 10,025, Option 3 Scope Pricing Allowance for parking assumes: $ $ 260, $ - No parking requirements for Option 1a $ $ 300, $ 450, parking stalls for Options 1b and 2 $ $ 3,910, $ 10,475, parking stalls for Option 3. Soft Costs Owner Side City of Kamloops $ 100, $ 100, $ 100, $ 100, Permitting 0.500% $ 11, $ 13, $ 16, $ 50, Testing $ 10, $ 25, $ 15, $ 25, Geotechnical $ 25, $ 30, $ 25, $ 30, Subtotal, Owner $ 146, $ 168, $ 156, $ 205, Existing Consultant Side ACEC BC Guideline Building Factor Percentage Extension Extension Extension Extension Prime Consultant 1.4% % $ 53, $ 65, $ 79, $ 238, Envelope 2.8% % $ 17, $ 14, $ 32, $ 58, Architect 4.0% % $ 30, $ 29, $ 58, $ 182, Structural 6.0% % $ 32, $ - $ 32, $ 112, Mechanical 7.0% % $ 37, $ 50, $ 62, $ 219, Electrical 7.5% % $ 20, $ 22, $ 38, $ 92, Fees on Allowances 8.0% $ 66, $ 150, $ 111, $ 211, Subtotal Consultants $ 257, $ 332, $ 416, $ 1,114, Consulting Fee % (Total) 11.47% 12.04% 12.43% 11.12% Sub-totals $ 2,803, $ 3,821, $ 4,483, $ 11,794, Construction Contingency (10%) $ 280, $ 382, $ 448, $ 1,179, Project Totals $ 3,084,027 $ 4,203,363 $ 4,931,510 $ 12,974,032 35
10 Attachment "B" Westsyde Pool 2015 Feasibility Study Options Review Monday, January 11, 2016 Read Jones Christoffersen Ltd. Creative Thinking Practical Results 36
11 37
12 ORIGINAL BUILDING FOOTPRINT 38
13 2015 Envelope Study 39
14 2015 Feasibility Study 40
15 Site and Amenities The options presented include a variety of scopes of work and allowances depending on the total program considered. Amenity work typically includes replacement of the waterslide. Some options include a leisure pool and new hot tub. Options 1b, 2 and 3 include allowances for adding parking to meet current Development Bylaw requirements. Each option includes hazardous materials abatement. Each option includes some landscaping, scope varies. 41
16 Option 1a: basic repair 42
17 Option 1a: basic repair Approximately 6 months Total Hard plus Soft Cost Est. $3,080,000 43
18 Option 1b: outdoor pool 44
19 Option 1b: outdoor pool Approximately 6 months Total Hard plus Soft Cost Est. $4,200,000 45
20 Option 2: modernization 46
21 Option 2: modernization Approximately 9 months Total Hard plus Soft Cost Est. $4,930,000 47
22 Option 3: toward net zero 48
23 Option 3: toward net zero Approximately months Total Hard plus Soft Cost Est. $12,974,000 49
24 Energy / GHG Emissions 50
25 Building Life Cycle 51
26 Scopes Not Addressed 1a basic repair Pool Tank Pool Apron Pool Equipment Amenity Structure Foundations Amenity Building Joists Amenity Building Envelope Amenity Building Interiors Air Handling Equipment 1b - Outdoor Pool Pool Tank Pool Apron Pool Equipment Amenity Structure Foundation Amenity Building Interiors 2 - modernization Pool Tank Pool Apron Pool Equipment Amenity Structure Foundations Amenity Building Joists Amenity Building Interiors 3 toward net zero Pool Tank Pool Apron Pool Equipment Amenity Structure (partial) Foundation 52
27 Sustainability 53
28 Summary Our study presents four options of unequal performance for Westsyde Pool. Option 1a is intended to meet the identified budget by addressing the structural deterioration and envelope of the pool building (Natatorium). Option 1b is a second approach to a full building upgrade but changes the functionality of the pool by removing the enclosure. Option 2 address the building envelope, mechanical and electrical of the full building. Option 3 provides the most complete refresh of Westsyde Pool, although some systems remain untouched. It includes geothermal, envelope upgrades and solar PV to help the building toward net zero energy targets 54
Before You Start an Energy Efficiency Retrofit The Building Envelope
ABOUT YOUR HOUSE Before You Start an Energy Efficiency Retrofit The Building Envelope The building envelope is the outer layer of the building that separates the indoor living space from the outdoor environment,
More informationresearch highlight Highly Energy Efficient Building Envelope Retrofits for Houses
research highlight June 2012 Technical Series 12-103 Highly Energy Efficient Building Envelope Retrofits for Houses introduction In Canada approximately 30% of all energy is consumed in buildings, with
More informationPROSPECTUS ALTERATION DENVER FEDERAL CENTER BUILDING 53 LAKEWOOD, CO
FY2015 Project Summary The General Services Administration (GSA) proposes a repair and alteration project to undertake system and architectural repairs as well as alteration of existing space at the Denver
More informationROGER WEETMAN RESORT MUNICIPALITY OF WHISTLER IAN ROSS MCDONALD BRUCE CARSCADDEN ARCHITECT MICHAEL BLACKMAN RJC
ROGER WEETMAN RESORT MUNICIPALITY OF WHISTLER IAN ROSS MCDONALD BRUCE CARSCADDEN ARCHITECT MICHAEL BLACKMAN RJC ROGER WEETMAN RESORT MUNICIPALITY OF WHISTLER Process for Feasibility & Life Cycle Studies
More informationWhy does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL?
Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? 1. BASIC FACTS: The current Abington High School building is 111,831
More informationSchedule B to By-law 33-2009
Amended by By-law 8-2016 Note: This consolidation is prepared for convenience only. For accurate reference the original by-laws should be reviewed. Floor Area Calculation Floor area shall: Schedule B to
More informationMinneapolis Community Planning and Economic Development Department Planning Division Report. Capital Improvements Location and Design Review
Minneapolis Community Planning and Economic Development Department Planning Division Report Capital Improvements Location and Design Review Date: April 11, 2013 Authority for Review: City Charter: Chapter
More informationRepair Project for April 7, 2009
Repair Project for April 7, 2009 Scope of the Project HVAC Upgrades Roof Replacement Window Replacement/Exterior Openings Science Lab Renovations New Fire Alarm/Electrical AAB (accessibility) Upgrades
More informationbout your HOUSE before you start Renovating Your Basement Moisture Problems
A bout your HOUSE before you start Renovating Your Basement Moisture Problems CE 28 c Condensation of cold surfaces, efflorescence Water leak in corner on floor Mold and decay on floor joists and sill
More informationbout your house before you start Renovating Your Basement Moisture Problems
A bout your house CE 28c before you start Renovating Your Basement Moisture Problems Mold and decay on floor joists and sill plates Stuffy air, high humidity, poor air circulation Water draining in from
More informationGreenhouse Gas Implications of HVAC Upgrades in Multi-Unit Residential Buildings
Greenhouse Gas Implications of HVAC Upgrades in Multi-Unit Residential Buildings J A NUARY 2015 INTRODUCTION This Research Report explores best practices and approaches for reducing greenhouse gas (GHG)
More informationNatatorium Building Enclosure Deterioration Due to Moisture Migration
Buildings 2012, 2, 534-541; doi:10.3390/buildings2040534 OPEN ACCESS buildings ISSN 2075-5309 www.mdpi.com/journal/buildings/ Case Study Natatorium Building Enclosure Deterioration Due to Moisture Migration
More informationBUILDING SAFETY UNIT
POLICY Page 1 of 5 SUBMITTAL REQUIREMENTS FOR ONE AND TWO FAMILY DWELLINGS, ADDITIONS AND RENOVATIONS All submittals shall be site specific and designed to the provisions of the 2012 International Residential
More informationMolds and mildew are fungi that grow
Appendix C: Moisture, Mold and Mildew Molds and mildew are fungi that grow on the surfaces of objects, within pores, and in deteriorated materials. They can cause discoloration and odor problems, deteriorate
More informationKey energy-efficient features of your new home
Key energy-efficient features of your new home Your thermal envelope The thermal envelope, or shell, of your home (walls, roof and floor) is designed to keep you dry and comfortable. It protects you from
More informationSchedule B to By-law 33-2009 Part A Fees Payable for Permits
Floor Area Calculation Floor area shall: Part A Fees Payable for Permits (Effective January 1, 2015) a) be calculated by measuring to the outer face of exterior walls and to the centre of party walls or
More informationLEED PRESENTATION OUTLINE
16902 BOLSA CHICA STREET, SUITE 101 HUNTINGTON BEACH, CA 92649 TELEPHONE (714) 840-8230 FACSIMILE (714) 840-2490 LEED PRESENTATION OUTLINE I. Overview of Green Building and Risks Involved with Sustainability
More informationSchool Board Proposed Capital Improvements Program. Fiscal Years 2014-2023
School Board Proposed Capital Improvements Program Fiscal Years 2014-2023 TABLE OF CONTENTS Summary Page 1 Capital Projects Pages 2-6 Capital Projects Description Pages 7-14 SCHOOL BOARD PROPOSED CAPITAL
More informationabout your house Before You Start Renovating Your Basement Moisture Problems Figure 1 Moisture problems to solve
about your house CE 28 c Before You Start Renovating Your Basement Moisture Problems Mold and decay on floor joists and sill plates Stuffy air, high humidity, poor air circulation Water draining in from
More informationWP5_D.19 Skills Profile SUMMARY REPORT
WP5_D.19 Skills Profile SUMMARY REPORT 1. The aim of the WP5 was to prepare Skills profile files for the detected new employment opportunities. The Skills profiles developed by Green Skills partnership
More informationbout your HOUSE before you start Renovating Your Basement Structural Issues And Soil conditions
A bout your HOUSE before you start Renovating Your Basement Structural Issues And Soil conditions CE 28 b Ground slopes towards window well No granular fill or connection to footing drain Ground floor
More informationbout your house before you start Renovating Your Bathroom
A bout your house CE 28e before you start Renovating Your Bathroom Inadequate lighting Water-wasting showerhead Renovating your bathroom is a great way to add value to your home both for your family s
More informationNational Building Code of Canada 2010
National Building Code of Canada 2010 Emergency Change Issued by the Canadian Commission on Building and Fire Codes The table that follows lists two emergency changes that apply to the National Building
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationLindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1
School Facilities Evaluation Project Page 1 Executive Summary In November 1999, Alberta Infrastructure, School Facilities Branch engaged Stephens Kozak Carr and Brown Architects to conduct evaluations
More informationSUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER
NOTICE TO PROPERTY OWNER Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. If your home or business is below
More informationChignecto-Central Regional School Board. Highland Consolidated Middle School. Indoor Air Quality Issues Mechanical Systems
Chignecto-Central Regional School Board Highland Consolidated Middle School Mechanical Systems Prepared by: Neil Van Rossum, P.Eng. CJ MacLellan & Associates Antigonish, Nova Scotia November 2012 CJM File:
More informationWATER. Water Management Protect your building from water damage. Intent. Information & Tips
Water Management Protect your building from water damage If not managed properly, rain can drain into unwanted areas damaging your roof, windows, walls and facade. Eliminate water damage to your property
More informationEstimated Cost of Repair
1 Applicant: Property: Home: Business: Assessor: Applicant Number: Type of Loss: Hurricane Date Contacted: 1/18/2014 Date of Loss: 10/29/2012 Date Received: 1/14/2014 Date Inspected: 2/4/2014 Date Entered:
More informationHOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY
HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY Benson Kwong, CVS, PE, CEM, LEED AP, CCE envergie consulting, LLC Biography Benson Kwong is an independent consultant providing
More informationAchieving Net Zero. Bradley Berneche, President Alouette Homes. National Marketing Committee Canadian Home Builders Association Ottawa, June 6, 2008
Achieving Net Zero Bradley Berneche, President Alouette Homes National Marketing Committee Canadian Home Builders Association Ottawa, June 6, 2008 Overview Who Is Alouette Homes? The EQuilibrium Initiative
More informationELIGIBLE REPAIR PROJECT PARAMETERS
THE DISTRICT MUNICIPALITY OF MUSKOKA ONTARIO RENOVATES PROGRAM FOR HOMEOWNERS ELIGIBLE REPAIR PROJECT PARAMETERS 1. To have your project considered and payment processed, all projects requiring a Building
More informationCONDENSATION IN REFRIDGERATED BUILDINGS
CONDENSATION IN REFRIDGERATED BUILDINGS By: Steve Salisbury Nov. 10, 2010 (revised Nov. 14, 2013) Introduction The following discussion reviews the basic causes of condensation in refrigerated buildings
More informationulletin Canada Mortgage and Housing Corporation
B ulletin Canada Mortgage and Housing Corporation Replacement Reserve Guide WHAT IS THE REPLACEMENT RESERVE? The replacement reserve is a fund kept by each housing sponsor under the terms of its operating
More informationORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT
1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.2 Water damage in many classrooms. Replace tiles. 1.1.3 Cabinets, Equipment 1.1.4 Portables
More informationD 4.4 Activity Report Technical support during the planning phase of new buildings
Grant agreement no. IEE/11/981/SI2.615956 MLEI BEAM-Graz City of Graz (AT) Boosting Energy Efficiency Actions in the Municipal Buildings of the City of Graz D 4.4 Activity Report Technical support during
More informationHow To Manage A Building
Protecting your property s safety and performance with comprehensive, strategic solutions. Program Management Raba Kistner Facilities, Inc. provides a specialized offering of services that ultimately creates
More information2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT
Presentation Synopsis Heating, Ventilating and Air Conditioning Building Condition Assessment Vancouver, B.C. Prepared for: EPIC Prepared by: Douglas Spratt, P.Eng Douglas Spratt & Associates Ltd. www.dspratt-associates.com
More informationSolving Persistent Moisture Problems and Moisture Damage
B etter buildings Solving Persistent Moisture Problems and Moisture Damage Summary This three-storey, 15-unit, 1,300 square metre (13,993 sq. ft) walk-up was built in 1958. In the 1980s, the building started
More informationHigh Performance School Buildings Resource and Strategy Guide
High Performance School Buildings Resource and Strategy Guide Published by: Sustainable Buildings Industry Council With support from: California Energy Commission National Concrete Masonry Association
More informationResidential HVAC Load Sizing Training October 14, 2015. David Kaiser Green Code Plan Reviewer
Residential HVAC Load Sizing Training October 14, 2015 David Kaiser Green Code Plan Reviewer DCRA - Green Building Division Regulations of green codes including: Green Building Act Green Construction Code
More informationInfrared Moisture Detection
What it can do for you... what it can t and why 1. Infrared camera basics 2. Examples Lew Harriman MoistureDM.com 3. Summary - The 4 most important facts about infrared moisture detection 1 of 19 Infrared
More informationAttached is a link to student educational curriculum on plug load that provides additional information and an example of how to estimate plug load:
Energy Conservation Tip #1 Always turn off all lights when you leave a room or when they are not needed. It is estimated that 26% of a building s electricity is used for lighting. For D-11 this equals
More informationPOMONA COLLEGE Sustainability Integration Office Facilities and Campus Services
POMONA COLLEGE Sustainability Integration Office Facilities and Campus Services May 200 Table of Contents NEW CONSTRUCTION/MAJOR RENOVATION Process... Design... 3 MINOR RENOVATIONS/PROJECTS Process...
More informationSpringfield Township Board of Education March 10, 2015 Referendum Questions and Answers (updated 2/19/2015)
Springfield Township Board of Education March 10, 2015 Referendum Questions and Answers (updated 2/19/2015) What is a referendum? New Jersey school districts hold public referendum votes to seek approval
More informationKlosterenga, Oslo, Norway, 1998-2000 page - 1
Klosterenga, Oslo, Norway, 1998-2000 page - 1 Introduction Klosterenga is an urban revitalisation project close to the city centre of Oslo. The 3 apartments were built with a focus on energy saving. Next
More informationEnergy efficiency building standards in Japan
www.asiabusinesscouncil.org Energy efficiency building standards in Japan Japan s regulation of building energy efficiency falls under the Energy Conservation Law that was first adopted in 1979. Subsequently
More information1..GENERAL DATA 2. CLIMATIC DATA. Location
1..GENERAL DATA Location Szentendre, Downtown, Hungary Property Community centre of Szentendre, Public, Municipality of Szentendre Year of Building: End of 19th Century Present use (1) Community centre
More informationPolicy on Repair and Renovation Funding
Policy on Repair and Renovation Funding I. POLICY STATEMENT Auburn University s (the University s) Policy on Repair and Renovation Funding provides guidance and direction regarding the use of Repair and
More informationU.S. Department of Housing and Urban Development Office of Public and Indian Housing. A Good Place to Live!
U.S. Department of Housing and Urban Development Office of Public and Indian Housing A Good Place to Live! Introduction Having a good place to live is important. Through your Public Housing Agency (or
More informationSigns of insulation problems In the winter. In the summer. conditioning system
about your house CE 19 While previous generations may have been content to live in drafty houses, most people now want comfortable warm houses. A healthy house today is well sealed, well insulated and
More informationIntroduction to Energy Codes & Green Building Programs
Introduction to Energy Codes & Green Building Programs David Neiger B.S. Arch, LEED AP Homes, Certified HERS Rater Principal Populus Sustainable Design Consulting Why green homes? The Building Sector:
More informationSoils, Foundations & Moisture Control
Soils, Foundations & Moisture Control Soil The top loose layer mineral and/or organic material on the surface of the Earth that serves as a natural medium for the growth of plants and support for the foundations
More informationYour Personal Home Energy Action Plan
www.centralvalleyenergytuneup.org g Your Personal Home Energy Action Plan 123 Sample Street Fresno, Ca 93710 Home Energy Rater Name Company Evaluation Date Joe Rater Rater Services, Inc. 9/1/2013 This
More informationPreventing Ice Dams on Roofs
Preventing Ice Dams on Roofs Facility Manager November/December 2005 When a roof leaks, facility managers inevitably receive complaints from building occupants. If it is winter, ice dams are often the
More informationFoundation. Foundation
Moisture Aside from structural concerns, the most important consideration for foundation design is moisture. No client wants a wet basement. No client wants a damp basement. No client wants mold in their
More informationBEST 3, Atlanta, April 2012 Grahame E. Maisey, P.E.
A Methodology to Develop a Sustainable, High Performance Building Envelope BEST 3, Atlanta, April 2012 Grahame E. Maisey, P.E. We re Going To Reveal New Sustainable Truths and Expose Old Bogus Truths We
More informationFishermen s Market. Indoor Public Space. Shipping Container Follies. Under the Steps Gallery. Beach
1- Little Forest 2- Big Slide 3- Under the Steps Gallery 4- Green Slope 5- Swimming Pool 6- Hot Tub 7- Wood Beach 8- Bio Swale 9- Big Screen 10- Amphitheatre 11- Rocky Beach 12- Playground 13- Shipping
More informationMUNICIPALITY OF THAMES CENTRE COMMUNITY SERVICES AND DEVELOPMENT RECREATION
REPORT NO. PR-019-15 MUNICIPALITY OF THAMES CENTRE COMMUNITY SERVICES AND DEVELOPMENT RECREATION TO: Mayor and Members of Council FROM: Liz Murray Recreation and Facilities Manager DATE: July 13, 2015
More informationNumber Northern Arizona University Facility Services Section Page. Effective April 1, 2011
Facility Services Section Page Recharge Services, Maintenance and Construction PURPOSE 1 of 6 The purpose of this policy is to set forth standards for chargeable services for maintenance and construction
More informationORANGE UNIFIED SCHOOL DISTRICT SCHOOL FACILITIES MASTER PLAN NEEDS ASSESSMENT
1. SAFETY, HEALTH, CODE 1.1 Structural Requirements, Seismic Stability 1.1.1 Primary Structure 1.1.2 Ceilings 1.1.3 Cabinets, Equipment 1.1.4 Portables 1.2 Fire / Life Safety 1.2.1 Corridor, Separation
More informationSchool of Veterinary Medicine Second Floor Student Clinical/Instructional Space
REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES School of Veterinary Medicine Second Floor Student Clinical/Instructional Space For Enumeration in the 2015-17 Capital Budget March 2014 Project
More informationAngelo State University Construction Report
May 12, 2009 Angelo State University Construction Report Modular buildings will temporarily house ASU staff during the Hardeman renovation starting this fall. Prepared for: John Russell, Director of Planning
More informationTHE IC Y N E N E AD V A N T A G E
THE IC Y N E N E AD V A N T A G E APP L I C A T I O N CA S E ST U D Y : CO M M E R C I A L BUILDING IN S U L A T I O N Condensation Control with ICYNENE LD-C-50 Synopsis: Icynene solved the condensation
More informationFirst Time Home Buyers Energy Efficiency Workshop Guide
First Time Home Buyers Energy Efficiency Workshop Guide Why is efficiency important when buying a home? Affordability: lower utility bills Environmental responsibility: reduces your carbon footprint and
More informationRFI Response RFP: HSCG88-16-R-PQQ015 Replace HVAC Bldg A & C San Diego, CA.
1. There is verbiage in the hazardous material report referring to a state licensed abatement contractor. Within the recommendations part of the report (page 64 of 111 of the specification pdf) is the
More informationPoints of Construction
Points of Construction BCB Homes builds the best homes in America. Period. The physics of building in the South Florida hot, humid climate are hard enough on their own, but BCB executes the details better
More informationCode Requirements for Existing Buildings
Code Requirements for Existing Buildings Kevin S. Hastings, P.E., LEED AP R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS)
More informationThe District Energy Manager and Classroom Heating
Mt. Carmel Area School District Energy Conservation Policy Adopted 6/19/06 These guidelines supersede all previous instructions. It is crucial that these energy guidelines be observed in the operation
More informationSustainable Design and Energy-Efficient Building Techniques for Existing Housing
Sustainable Design and Energy-Efficient Building Techniques for Existing Housing PATH Energy Retrofit Project Henderson, Nevada NREL Research Site, Lebanon NJ Energy Retrofit Goals PROJECT GOALS Identify,
More informationRESIDENTIAL COURSE OF CONSTRUCTION QUESTIONNAIRE
RESIDENTIAL COURSE OF CONSTRUCTION QUESTIONNAIRE Residential Course of Construction policies, also known as Builder s Risk, are designed to cover the property owner for potential loss while the property
More informationThe Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE
The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE BUILDING SERVICES DEPARTMENT 789 Broadway Street, Box 3000 Wyoming, ON N0N 1T0 Telephone: 519 845-0801 Toll-free: 1-866-324-6912 Fax: 519
More informationNotice to Property Owners
Modification or Repair of your Flood Prone Property Notice to Property Owners Rebuilding or Remodeling Your Home If your home or business sustained damage, or if you are making improvements to the structure
More information@hba_sudbury. Buying A New Home. Presented in Partnership with. Greater Sudbury Public Library PHONE SDHBA: 705 671 6099
Buying A New Home Presented in Partnership with Greater Sudbury Public Library PHONE SDHBA: 705 671 6099 1 Four Month Series DATES: Sept 13: Underground / Cash Deal Oct 11: Talking with Builder / Renovator
More informationRepair of Spalling and Leaking Clay Brick Building Walls
B etter buildings Repair of Spalling and Leaking Clay Brick Building Walls Overview A few years after being built in Waterloo in 1980, a condominium of three, six-storey buildings showed severe spalling
More informationTsawwassen BC Arena Before & After installation of the Low-E ceiling
LOW EMISSIVITY CEILINGS Emissivity- Describes the ability of a certain material to radiate heat rather then absorb it. Materials that radiate 100% have an (EM) of 1.0, while materials that radiate no heat
More informationPUBLIC MINUTES PROPERTY MAINTENANCE APPEALS BOARD. Wednesday, November 25, 2015, 3:46 p.m. Committee Room B, City Hall
PUBLIC MINUTES PROPERTY MAINTENANCE APPEALS BOARD Wednesday,, 3:46 p.m. Committee Room B, City Hall PRESENT: Mr. Ian Oliver, Chair Mr. Michael Brockbank, Vice-Chair Mr. Roy Fleming, Member Mr. Donald Stiller,
More informationOakland County Executive Department of Facilities Management. Energy Management Procedures October 5, 2009
Oakland County Executive Department of Facilities Management Energy Management Procedures October 5, 2009 1. Goal The acquisition and management of energy is fundamental to the mission and operation of
More information3. HERITAGE GRANT APPROVAL 192 MOORHOUSE AVENUE, CHRISTCHURCH
3. HERITAGE GRANT APPROVAL 192 MOORHOUSE AVENUE, CHRISTCHURCH General Manager responsible: General Manager, Strategy and Planning Group, DDI: 941-8281 Officer responsible: Author: PURPOSE OF REPORT Programme
More informationHome inspectors are not mold inspectors, however they do inspect for defects that
CONDENSATION IN THE WALLS Home inspectors are not mold inspectors, however they do inspect for defects that can result in mold. Mold grows in wet or damp environments. Defects that result in a wet or damp
More informationBuilding Condition Assessment Report
Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.
More informationProject Management Division
CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT February 2015 Project Management Division BELOW: Collins Construction crews complete recent exterior work and await delivery of exterior siding. Collins
More informationMURCH ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1929 BUILDING AREA 47,700 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 491 WARD 3 PROPOSED PROGRAM CAPACITY 500 Site Plan MURCH - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationAPPENDIX E: CAPITAL NEEDS SUMMARY
APPENDIX E: CAPITAL NEEDS SUMMARY Building A Foundation Hall Building to be replaced ARCHITECTURAL Roof Repair North Structural Wall Repair Flooring Repairs Ceiling Repairs Lighting Repairs Lighting Repairs
More informationBPC Green Builders. Green building for new and existing homes. Health Comfort Energy
BPC Green Builders Green building for new and existing homes Health Comfort Energy Mechanical Systems Installed HVAC Systems Primary energy source large, roof mounted, solar thermal array (AET flat plate)
More informationIECC Compliance Guide for Homes in Virginia
IECC Compliance Guide for Homes in Virginia Amended Version of 2012 International Energy Conservation Code July 14, 2014 Climate Zone Since the entire state of Virginia falls in the IECC Climate Zone 4,
More informationD Sample Notices to Property Owners, Sample Affidavits, and Other Material
D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully
More informationBUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES
Department of Health and Human Services, Division of Public Health Occupational and Environmental Epidemiology Branch 1912 Mail Service Center, Raleigh, North Carolina 27699-1912 BUILDING ASSESSMENT QUESTIONNAIRE
More informationDRAPER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More informationCAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT. January 2014. Project Management Division
CAPITAL PROJECTS DEPARTMENT MONTHLY ACTIVITY REPORT RIGHT: the proposed conceptual profile of the new Joe Redington Sr. JR/SR High School January 2014 Project Management Division New Knik Area Middle/High
More informationAnswers to Your Questions from the Webinar
2008 Desert Aire and USA Swimming. Used by permission. Desert Aire & USA Swimming - Aquatics Webinar - Answers to Your Questions Answers to Your Questions from the Webinar Thank you for your interest in
More informationAIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries
AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries Hot tips and cool ideas to save energy and money! Air conditioning units or systems are often used by foundries
More informationA Guide to Green Roofs on Existing School Buildings
A Guide to Green Roofs on Existing School Buildings What is a Green Roof? What does it do? Green Roofs can mean different things. It can include vegetative plantings, solar thermal installations, solar
More informationHybrid heat pumps. saving energy and reducing carbon emissions
Hybrid heat pumps saving energy and reducing carbon emissions Bart Aspeslagh Product planning and new technology manager, Daikin Europe NV. aspeslagh.b@daikineurope.com Stefanie Debaets Design engineer,
More informationThe Orange County Farmers Museum Emergency Preparedness Plan
The Orange County Farmers Museum Emergency Preparedness Plan TABLE OF CONTENTS Section Page Introduction. 2 1. Coordination with an Emergency Response Agency. 2 2. Policies of the Board 2 3. Procedures
More informationABOVE ALL, IT S A ROOF SERVICED BY THE JAMES MYERS COMPANY
ABOVE ALL, IT S A ROOF SERVICED BY THE JAMES MYERS COMPANY BEAM A Premiere Roof Asset Management Program WITH BEAM WE CAN HELP YOU MAINTAIN AND PROTECT THE ROOF THAT PROTECTS YOU. A FRAGILE BARRIER Consider
More informationInspecting to a higher standard.
Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com rob@protec-inspections.com
More informationThink Of Us First! When It s Time to Distribute Your Plans
Think Of Us First! When It s Time to Distribute Your Plans CONSTRUCTION NOTEBOOK WILL LIST YOUR PLANS AND SPECS FREE CALL TODAY FOR DETAILS 702-876-8660 Why use Experience We have over 60 years of experience
More informationRoss River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis
DNA project managers planners architects engineers David Nairne + Associates Ltd Suite 250 171 W Esplanade North Vancouver British Columbia Canada V7M 3J9 T 604 984 3503 F 604 984 0627 E dna@ davidnairne.com
More informationSchool Facilities Referendum Recommendations
Haddonfield Public School District LONG RANGE PLANNING COMMITTEE School Facilities Referendum Recommendations NOVEMBER 19, 2015 School Facilities Referendum Recommendations Tonight s goals Presentation
More information