Delivering Major Crown Projects Long Term Vision and Plan for the Parliamentary Precinct

Size: px
Start display at page:

Download "Delivering Major Crown Projects Long Term Vision and Plan for the Parliamentary Precinct"

Transcription

1 Delivering Major Crown Projects Long Term Vision and Plan for the Parliamentary Precinct November 2014

2 Long Term Vision and Plan The main focus of the LTVP is the rehabilitation of the Centre, West and East Blocks. Major Crown Projects is responsible for the implementation of these projects. In order to empty the Centre Block of all occupants and functions, a series of projects to create permanent and interim accommodation have been undertaken. 2

3 Valour Building (151 Sparks) Valour Building (151 Sparks) Édifice La Bravoure

4 Long Term Vision and Plan Developed in 2001 and updated in 2007 and A guide for change for the Parliamentary Precinct and for future designers and decision makers. The LTVP is comprised of three components: 1. The Vision and Principles 2. The Demonstration Plan 3. The Implementation framework approvals sought for rolling 5 year programs of work Implementation has three components: Major Capital Program focus of this presentation Recapitalization Program Planning Program 4

5 1,127,260? Number of interior bricks laid, West Block 5

6 LTVP implementation The 5-year rolling plan provides: Flexibility in responding to government priorities, and More accuracy in developing functional requirements and establishing project costs and schedules. The opportunity to construct four committee rooms in the former Canadian Museum of Contemporary Photography allowed the West Block to begin construction 4 years early. 6

7 Flexibility Another opportunity led to the revision of the LTVP. The Government Conference Centre was selected to provide interim accommodation for the Senate while Centre Block undergoes rehabilitation. 7

8 Current MCP Projects MCP Projects TB Project Approval Construction Start Scheduled Completion West Block Rehabilitation $863 M Mar Wellington Building $425 M Apr Sir John A. Macdonald Building $ 99.5 M Dec Visitor Welcome Centre Phase 1 $109 M Jan Government Conference Centre $190 M Jul East Block Rehabilitation, Phase 1 $167 M Jan

9 44,000 cubic meters? Volume of rock to be excavated for West Block Construction 9

10 Current MCP Projects 10

11 Nature of MCP Projects Complex: Heritage (masonry, sculptural elements, decorative ironwork) Located in the Parliamentary Precinct (security, tourists, traffic, lay down areas) Seismic upgrades within a heritage building Mechanical /Electrical/Multimedia upgrades within a heritage building Special Purpose Space (House of Commons Chamber, Committee Rooms, MP suites) Oversight (internal, external, public interest) Security The adaptive re-use of a former Banking Hall to be used for Parliamentary business and Ceremonial events requiring significant mechanical, electrical, multimedia and security upgrades 11 11

12 Nature of MCP Projects, continued Project Cost is typically greater than $100 M: Treasury Board approves all LTVP contracting and expenditure authorities Attestation of substantive estimates by CFO, PWGSC Multiple Stakeholders: Parliamentary Partners (House of Commons, Senate of Canada, Library of Parliament) National Capital Commission (NCC), Federal Heritage Buildings Review Office (FHBRO) RCMP, other PWGSC Branches, City of Ottawa, etc. Must not impact the Operations of Parliament: Noise control Traffic control Careful coordination and ongoing communications 12

13 Implementation The implementation approach is tailored to the location, schedule and funding. Design/Bid/Build General Contractor Construction Management Design/Build Valour Building West Block, Wellington, SJAM, GCC Food Production Facility (not on the Hill) Construction Management is used for most LTVP projects as the optimal model. Proven track record Allows for schedule acceleration Provides off ramps 1 Rideau Start construction in parallel with design Options exercised when funding becomes available Balances risk, flexibility and efficiency for large complex projects 13

14 13,090 square meters? Area of West Block exterior masonry 14

15 West Block as-found conditions LTVP projects often require hazardous material abatement & structural investigations prior to completing full tender documents. CM fast tracking provides schedule benefits. Unit prices are at times used when precise quantities cannot be determined prior vacating building. Precise scope of work is progressively defined on site (measured, recorded and validated) Fox and Barrett floor assemblies, from 1865 construction, are found and replaced Unused fireplaces and chimneys are uncovered and the brick consolidated. Fresh air intake tunnels, from 1865 construction, are discovered below grade. 15

16 Oversight of CM Contract The CM contract is service based, remunerated as a monthly fee + % fee of Cost of Work The CM is responsible to issue and award contract packages by sub-trade Crown requires the CM to follow open, fair and transparent tendering practices (twostage public tender process for larger than $100K, 3 bids for less than $100K) Any planned expenditure against the contract needs authorization by PWGSC (multiparty review ) Continuous review of work on site to ensure value and quality of work Clerk of Works Prime Consultant full-time on site representatives PWGSC and private sector project management support specialists 16

17 Managing the Schedule Pre-Design: Initial schedule is prepared by PWGSC based on previous project experience, lessons learned PWGSC schedule consultant engaged to validate activity durations and logic (updated monthly) Design: Prime Consultant scheduler provides detailed design and preliminary construction schedule PWGSC schedule consultant reviews and challenges Construction: Construction Manager or General Contractor is responsible for preparing a detailed construction schedule and monthly schedule report. PWGSC schedule consultant reviews and challenges Schedule is reviewed monthly as a minimum 17

18 Managing Risk Risk is managed and monitored throughout the project Developed based on previous projects & Lessons Learned database Quantified by a Risk Matrix, validated through Monte Carlo simulation Varies due to the nature of the project Heritage designation, masonry deterioration, hazardous material abatement, challenging site conditions & fit-up of ceremonial spaces. Carried as part of budget for each project 18

19 3,485 square meters? Area of new copper roof, West Block 19

20 Program Oversight Fairness Monitoring All major procurements are monitored by an independent Fairness Monitor. Audit Regime The Auditor general audited the rehabilitation of the Parliament buildings in 2010 and concluded that PWGSC has put in place generally sound project management practices. An independent 3rd party assessed project management practices in the Precinct in 2012 concluding that sound project management systems, controls, outputs and practices are in place for the West Block, Wellington and other projects. PricewaterhouseCoopers conducted audits of the West Block, Wellington and Sir John A. Macdonald construction management contracts, issuing clean audit reports for all three projects. 20

21 Innovation The use of lasers to clean masonry Partnering with the University of Calgary to test seismic resistance of load bearing masonry 21

22 West Block Rehabilitation Includes: Demolition and abatement of hazardous materials Rehabilitation of masonry and heritage interiors Construct Interim HoC Chamber in the courtyard Structural/Seismic upgrades New Mechanical/Electrical/Life Safety systems Updated IT/Multi-media & Security systems 22

23 West Block Interim HoC Chamber 23 23

24 West Block Excavation 24

25 approximately 1000? Total number of workers West Block, Wellington, Sir John A. Macdonald & Government Conference Centre construction sites 25

26 Visitor Welcome Centre Phase1 The Visitor Welcome Centre Ph1 will provide a new visitor entrance to the West Block (outside the footprint of the heritage building) containing security screening services and Shipping & Receiving. It will later become the West Entrance to the future Visitor Centre, after the Centre Block rehabilitation is complete. Before any construction can occur, underground utilities and infrastructure must be relocated. Ph1 Concept for the final VWC 26

27 Wellington Building Includes: Heritage Rehabilitation 70 MP office units 10 Committee Rooms New Mechanical/Electrical/Life Safety systems Green Globes Sustainability Targets Updated IT/Multimedia/Security systems 27

28 Sir John A. Macdonald Includes: Excavation of the adjacent site and the basement for construction of an addition Interior selective demolition and hazardous materials abatement Exterior and interior heritage rehabilitation 28 Updated IT/Multimedia/Security systems

29 Government Conference Centre Includes: Selective demolition and abatement of hazardous materials Seismic upgrades Interior and exterior heritage rehabilitation Fit-up for Interim Senate Chamber, office units and support space New Mechanical/Electrical/Life Safety systems Updated IT/Multi-media & Security systems 29

30 ? Number of heritage masons on site daily at West Block 30

Examination of Construction Management Contract for West Block Rehabilitation Project

Examination of Construction Management Contract for West Block Rehabilitation Project Examination of Construction Management Contract for West Block Rehabilitation Project PCL Invoices #1 to 18 for the period from June 30, 2011 to December 21, 2012 June 18, 2013 To the Parliamentary Precinct

More information

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL Prepared for: Public Works and Government Services Canada Parliamentary Precinct Branch Prepared by: Halsall Associates 210 Gladstone

More information

Notice. Carling Campus - Consulting Services for Carling Campus. (Closed)

Notice. Carling Campus - Consulting Services for Carling Campus. (Closed) Notice (Closed) Solicitation Number Carling Campus Title Consulting Services for Carling Campus Basic Information Reference Number 0000003274 Issuing Organization Brookfield Global Integrated Solutions

More information

Financial Statements of the. Office of the Secretary to the Governor General

Financial Statements of the. Office of the Secretary to the Governor General Financial Statements of the Office of the Secretary to the Governor General For the Year Ended March 31, 2014 Statement of Management Responsibility Including Internal Control Over Financial Reporting

More information

July 2015. Oklahoma Capitol Restoration Project. Interior Rehabilitation Monthly Progress Report

July 2015. Oklahoma Capitol Restoration Project. Interior Rehabilitation Monthly Progress Report July 2015 Oklahoma Capitol Restoration Project Interior Rehabilitation Monthly Progress Report TABLE OF CONTENTS Design-Builder Progress Summary... TAB 1 Design Progress Summary... TAB 2 Project Schedule...

More information

Strategic Outlook for the 39th Parliament. House of Commons Administration

Strategic Outlook for the 39th Parliament. House of Commons Administration Strategic Outlook for the 39th Parliament House of Commons Administration The central column of Confederation Hall, located in the main foyer of Parliament s Centre Block, supports a beautiful vaulted

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

County Of Sonoma Agenda Item Summary Report

County Of Sonoma Agenda Item Summary Report County Of Sonoma Agenda Item Summary Report Department: General Services Contact: Rob Kambak Phone: (707) 565-3211 Board Date: 10/27/2009 4/5 Vote Required Deadline for Board Action: AGENDA SHORT TITLE:

More information

5047P Architectural and Engineering Services for the Cambie Fire Hall and Ambulance Station Project- Addendum #2

5047P Architectural and Engineering Services for the Cambie Fire Hall and Ambulance Station Project- Addendum #2 January 23, 2013 Business and Financial Services Department Finance Division Telephone: 604-276-4218 Fax: 604-276-4162 Attention: To All Proponents Dear Bidders: Re: 5047P Architectural and Engineering

More information

MILWAUKEE CITY HALL FOUNDATION RESTORATION. Project Update November 12, 2014

MILWAUKEE CITY HALL FOUNDATION RESTORATION. Project Update November 12, 2014 MILWAUKEE CITY HALL FOUNDATION RESTORATION Project Update November 12, 2014 Milwaukee City Hall Building History/Fast Facts - City Hall is a masonry and iron superstructure - Originally constructed from

More information

4.3.2 Contaminated Sites

4.3.2 Contaminated Sites PERFORMANCE MEASUREMENT STRATEGY 4.3.2 Contaminated Sites Strategic Outcome: The North Date: Approved September 2014 Sector: Northern Affairs Organization Measurement (PM) Strategies are required by Treasury

More information

Utilities and existing services

Utilities and existing services Construction Services Building standards for mechanical and electrical installations Utilities and existing services October 2012 Directorate: Environment Construction Services - Building standards for

More information

CAPITAL PROJECT COSTS!!! UNIVERSITY OF CALIFORNIA SANTA CRUZ

CAPITAL PROJECT COSTS!!! UNIVERSITY OF CALIFORNIA SANTA CRUZ INTRODUCTION All Capital Project Budgets have 2 basic components: Construction Fees, Project Management, and Administration This presentation looks at COST DRIVERS that impact these 2 components and COST

More information

Angelo State University Construction Report

Angelo State University Construction Report May 12, 2009 Angelo State University Construction Report Modular buildings will temporarily house ASU staff during the Hardeman renovation starting this fall. Prepared for: John Russell, Director of Planning

More information

Arts Revitalisation Projects and the Planning System. January 2010 Guideline

Arts Revitalisation Projects and the Planning System. January 2010 Guideline Arts Revitalisation Projects and the Planning System January 2010 Guideline Photography credits: courtesy http://www.flickr.com/groups/renewnewcastle/ Arts Revitalisation Projects and the Planning System

More information

ACT ACCOUNTING POLICY. Capital Works

ACT ACCOUNTING POLICY. Capital Works ACT ACCOUNTING POLICY Capital Works FOR REPORTING PERIODS ENDING ON OR AFTER 30 JUNE 2006 TABLE OF CONTENTS 1 Introduction... 3 1.1 APPLICATION... 3 1.1.1 This Policy... 3 1.1.2 Relationship to International

More information

Business Case. Ottawa Public Library Main Library Facility May 2015

Business Case. Ottawa Public Library Main Library Facility May 2015 Business Case Ottawa Public Library Main Library Facility May 2015 The information contained in this document is proprietary to the Ottawa Public Library and the City of Ottawa. Unauthorized distribution

More information

The work has continued on final Phase 4 and is nearing completion.

The work has continued on final Phase 4 and is nearing completion. Updates-January 22, 2013 29369-Rehab Plaza Deck/Drainage Budget: $18,000,000, constr. Start 8/2009 The work has continued on final Phase 4 and is nearing completion. The main plaza area of phase 4 is now

More information

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. Terri Mestas Program Director

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. Terri Mestas Program Director Los Angeles Community College District PROGRAM MANAGEMENT SERVICES Terri Mestas Program Director CMAA Southern California Chapter February 13, 2015 1 LACCD Overview Established in 1969 Governed by seven-member

More information

Vision Home Inspection

Vision Home Inspection Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the

More information

Sacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project March, 2015

Sacramento Municipal Utility District Headquarters Building and Site Rehabilitation Project March, 2015 Addendum 1: Changes to the Draft IS/MND Text and Figures Introduction This summary presents minor corrections and revisions made to the Draft IS/MND initiated by the public, staff and/or consultants based

More information

Report of the Auditor General of Canada to the Board of Internal Economy of the House of Commons

Report of the Auditor General of Canada to the Board of Internal Economy of the House of Commons June 2012 Report of the Auditor General of Canada to the Board of Internal Economy of the House of Commons Administration of the House of Commons of Canada Office of the Auditor General of Canada The Report

More information

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES CAPITAL ASSET MANAGEMENT PROJECT PROCUREMENT PROCEDURES AND GUIDELINES June 2003 Updated June 20, 2003 Ministry of Education Province of British Columbia TABLE OF CONTENTS EXECUTIVE SUMMARY... iii 1.0

More information

Comparative Study of Guidelines and Practices for Building Infrastructure Asset Management. Summary. 1. Introduction. 2. Australian Practices

Comparative Study of Guidelines and Practices for Building Infrastructure Asset Management. Summary. 1. Introduction. 2. Australian Practices Comparative Study of Guidelines and Practices for Building Infrastructure Asset Management Mr. Ashish SHAH B.E. (Civil), M.E. (I.T.) Researcher, RMIT University, Australia Research interests in Infrastructure

More information

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Internal Controls Over Financial Reporting.

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Internal Controls Over Financial Reporting. Aboriginal Affairs and Northern Development Canada Internal Audit Report Audit of Internal Controls Over Financial Reporting Prepared by: Audit and Assurance Services Branch Project #: 14-05 November 2014

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: 1 DISCUSSION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: 1 DISCUSSION ITEM GB3 Office of the President TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: 1 For Meeting of July 21, 2015 DISCUSSION ITEM PRELIMINARY PLANS FUNDING, MISSION BAY EAST CAMPUS PHASE 1 (BLOCK 33) BUILDING,

More information

Corporate Plan 2015-19

Corporate Plan 2015-19 Corporate Plan 2015-19 i ii Serving the Australian Parliament The DPS Corporate Plan 2015-2019 This corporate plan lays out the strategic direction for the Department of Parliamentary Services for the

More information

Audit of Procurement Practices

Audit of Procurement Practices Audit Report Audit of Procurement Practices Audit and Evaluation Directorate April 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 INTRODUCTION... 5 Background... 5 Risk Assessment... 5 Objective and Criteria...

More information

On June 15, 2015, the Board received the Ernst and Young report on the Special Advisor s review of the Vancouver Board of Education.

On June 15, 2015, the Board received the Ernst and Young report on the Special Advisor s review of the Vancouver Board of Education. Date: September 25, 2015 ITEM 3 To: From: Committee II - Planning and Facilities Jim Meschino, Director of Facilities Re: Ernst & Young Report s INTRODUCTION This report contains recommendations. BACKGROUND

More information

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter.

Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. SCHEDULE OF CONSULTANT S SERVICES Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. Project (Insert name and description

More information

Developing a Public-Private Partnership Framework: Policies and PPP Units

Developing a Public-Private Partnership Framework: Policies and PPP Units Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework

More information

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,

More information

QA/QC, Project Updates & Procurement

QA/QC, Project Updates & Procurement Construction Institute The Changing State of the State October 16, 2015 QA/QC, Project Updates & Procurement Laura A. Cruickshank, FAIA University Master Planner and Chief Architect Planning, Architectural

More information

A Residential Owner s Guide to PERMITS. Elgin CITY OF PLANNING & NEIGHBORHOOD SERVICES

A Residential Owner s Guide to PERMITS. Elgin CITY OF PLANNING & NEIGHBORHOOD SERVICES A Residential Owner s Guide to PERMITS CITY OF Elgin PLANNING & NEIGHBORHOOD SERVICES CITY OF Elgin A Residential Owner s Guide Welcome! This booklet has been prepared to provide residential property owners

More information

Measuring, Estimating and Tendering Processes in Construction and the Built Environment

Measuring, Estimating and Tendering Processes in Construction and the Built Environment Unit 9: Measuring, Estimating and Tendering Processes in Construction and the Built Environment NQF Level 3: Guided learning hours: 60 BTEC National Unit abstract Estimating is concerned with the processes

More information

House of Commons Corporate Governance Framework

House of Commons Corporate Governance Framework House of Commons Corporate Governance Framework What is Corporate Governance? 1. Good corporate governance is fundamental to any effective organisation and is the hallmark of any well-managed corporate

More information

Construction Projects Status Report

Construction Projects Status Report Construction Projects Status Report Date October 28, 2014 Meeting Type To From Purpose 2222222 Originator Governance Policy Reference Resource Person(s) Regular Meeting, Public Agenda Board of Trustees

More information

City of Kingston Information Report to Municipal Heritage Committee Report Number MHC-15-067

City of Kingston Information Report to Municipal Heritage Committee Report Number MHC-15-067 To: From: Resource Staff: Date of Meeting: November 2, 2015 Subject: Executive Summary: City of Kingston Information Report to Municipal Heritage Committee Report Number MHC-15-067 Chair and Members of

More information

Agency Management of Software Licensing

Agency Management of Software Licensing The Auditor-General Audit Report No.27 2001 2002 Assurance and Control Assessment Audit Agency Management of Software Licensing Australian National Audit Office Commonwealth of Australia 2001 ISSN 1036-7632

More information

Board of Regents Meeting June 16-17, 2005 Agenda Item #11 Arizona State University EXECUTIVE SUMMARY Page 1 of 5

Board of Regents Meeting June 16-17, 2005 Agenda Item #11 Arizona State University EXECUTIVE SUMMARY Page 1 of 5 EXECUTIVE SUMMARY Page 1 of 5 ACTION ITEM: Academic Renovations and Deferred Maintenance Phase I, Revised Revised Project Implementation Approval, (ASU). ISSUE: ASU requests Revised Revised Project Implementation

More information

Newsletter: Construction Information, No. 1 28 June 2010

Newsletter: Construction Information, No. 1 28 June 2010 1 ( 6 ) Newsletter: Construction Information, No. 1 28 June 2010 Premiere for the newsletter about construction and disruption In connection with the start of the construction of the New Karolinska Solna

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides

More information

The University of Akron Main Campus Biennium 1 July 2016- June 2018. Priority Project Budget Description 1 Electrical Infrastructure Loop

The University of Akron Main Campus Biennium 1 July 2016- June 2018. Priority Project Budget Description 1 Electrical Infrastructure Loop The University of Akron Main Campus Biennium 1 July 2016- June 2018 1 Electrical Infrastructure Loop $2,400,000 Scope: Replace center campus deteriorated 4,160 volt cable and duct bank with 23,000 volt

More information

Auditor General of Canada to the House of Commons

Auditor General of Canada to the House of Commons 2010 Report of the Auditor General of Canada to the House of Commons FALL Chapter 1 Canada s Economic Action Plan Office of the Auditor General of Canada The Fall 2010 Report of the Auditor General of

More information

Contract Management Guideline

Contract Management Guideline www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract

More information

PROJECT MANAGEMENT FRAMEWORK AUDIT AUDIT REPORT. Project # 13/14 01-03

PROJECT MANAGEMENT FRAMEWORK AUDIT AUDIT REPORT. Project # 13/14 01-03 PROJECT MANAGEMENT FRAMEWORK AUDIT AUDIT REPORT Project # 13/14 01-03 Prepared by Audit and Evaluation Directorate MARS 2014 Table of Contents 1.0 SUMMARY... 5 1.1 OBJECTIVE OF THE AUDIT... 5 1.2 OPINION

More information

Article 5: Building Regulations

Article 5: Building Regulations Article 5: Building Regulations Division 37: Additional Building Regulations for Archaic Materials and Methods of Construction (Added Additional Building Regulations for Archaic Materials and Methods of

More information

4.3 Project Construction

4.3 Project Construction 4.3 Project Construction 4.3.1 Contract Management Contract management practices may vary depending on the type of construction delivery method (e.g. Design-Bid-Build, Stipulated Sum, Construction Management).

More information

Electricity Market Reform:

Electricity Market Reform: Electricity Market Reform: Consultation on Low Carbon Contracts Company s and Electricity Settlements Company s operational costs 2015/16 Government Response January 2015 Crown copyright 2015 URN 15D/001

More information

MILTON HALL BCO AWARDS 2014 THE WORKSPACE CONSULTANTS LLP

MILTON HALL BCO AWARDS 2014 THE WORKSPACE CONSULTANTS LLP MILTON HALL BCO AWARDS 2014 EXTERNAL ELEVATIONS MILTON HALL THE EAST WING THE LINK BUILDING NORTH - WEST ELEVATION (1:200@A3) MILTON HALL THE LINK BUILDING THE NORTH WING SOUTH - EAST ELEVATION (1:200@A3)

More information

Vendor Performance Evaluation

Vendor Performance Evaluation Vendor Performance Evaluation Canadian Public Procurement Council Oct. 27-29, 2014 Agenda 1) Objectives and 2) Evaluation 3) Evaluation Templates and 4) Use of Vendor Score 2 13:00 14:00 1 Objectives and

More information

Project Management Manual Update 2006. Transportation Department City of Edmonton

Project Management Manual Update 2006. Transportation Department City of Edmonton Project Management Manual Update 2006 Transportation Department City of Edmonton Project Management Manual for Transportation Projects EXECUTIVE SUMMARY This document has been updated to fulfill the requirements

More information

RESIDENTIAL COURSE OF CONSTRUCTION QUESTIONNAIRE

RESIDENTIAL COURSE OF CONSTRUCTION QUESTIONNAIRE RESIDENTIAL COURSE OF CONSTRUCTION QUESTIONNAIRE Residential Course of Construction policies, also known as Builder s Risk, are designed to cover the property owner for potential loss while the property

More information

Centinela Valley Union High School District. Measure CV Program Update July 23, 2012

Centinela Valley Union High School District. Measure CV Program Update July 23, 2012 Centinela Valley Union High School District Measure CV Program Update July 23, 2012 Site Construction Progress Site Updates Hawthorne High School Lawndale High School Leuzinger High School 2 Hawthorne

More information

Audit of Construction Contracts

Audit of Construction Contracts National Research Council Canada Audit of Construction Contracts Internal Audit, NRC January 2009 TABLE OF CONTENTS 1.0 Executive Summary... 1 2.0 Introduction... 6 2.1 Background and context... 6 2.2

More information

Internal Audit. Audit of the Inventory Control Framework

Internal Audit. Audit of the Inventory Control Framework Internal Audit Audit of the Inventory Control Framework June 2010 Table of Contents EXECUTIVE SUMMARY...4 1. INTRODUCTION...7 1.1 BACKGROUND...7 1.2 OBJECTIVES...7 1.3 SCOPE OF THE AUDIT...7 1.4 METHODOLOGY...8

More information

Construction Management Thesis Requirements: Fall 2008 Department of Architectural Engineering

Construction Management Thesis Requirements: Fall 2008 Department of Architectural Engineering Construction Management Thesis Requirements: Fall 2008 Department of Architectural Engineering AE 481W: Senior Thesis Faculty Consultants Michael Horman, Ph.D. (Spring Only) 211 Engineering Unit A 863

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM GB3 Office of the President TO MEMBERS OF THE COMMITTEE ON : For the Meeting of ACTION ITEM APPROVAL OF PARTIAL PRELIMINARY PLANS FUNDING, LOWER SPROUL PROJECTS, BERKELEY CAMPUS CAMPUS PROJECT PROJECT

More information

Capital Projects Town Hall Meeting

Capital Projects Town Hall Meeting Capital Projects Town Hall Meeting Planning, Architectural & Engineering Services September 15, 2014 Agenda Project Updates Recently Completed and in Construction Projects in Design Projects in Planning

More information

BUILDING MOVE PROCESS INSIDE CITY LIMITS

BUILDING MOVE PROCESS INSIDE CITY LIMITS To move a building from outside or within the City to a site within City limits, the following STEPS must be taken before the move can take place: 1. A written request to relocate a dwelling must be provided

More information

construction management Customized Approach, Global ExpErience, Innovative Delivery

construction management Customized Approach, Global ExpErience, Innovative Delivery program and construction management Customized Approach, Global ExpErience, Innovative Delivery Proven Solutions for Smooth, Successful Project Delivery Capital projects, by their nature, can be highly

More information

Friends Seminary Presentation to NYC Landmarks Preservation Commission 21 April 2015 Kliment Halsband Architects

Friends Seminary Presentation to NYC Landmarks Preservation Commission 21 April 2015 Kliment Halsband Architects Presentation to NYC Landmarks Preservation Commission 21 April 2015 Kliment Halsband Architects FRIENDS SEMINARY RE-DEVELOPMENT PROJECT NYC LPC SUBMISSION 16 APRIL 2015 INDEX 1 Project Description 2 Stuyvesant

More information

Pumphouse Museum at the Historic Ottawa Beach Parks Park Township

Pumphouse Museum at the Historic Ottawa Beach Parks Park Township Pumphouse Museum at the Historic Ottawa Beach Parks Park Township Project Description: Wedged between Ottawa Beach Road and the Lake Macatawa Shoreline, the historic red brick industrial building commonly

More information

Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL?

Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? Why does the renovation and expansion of an EXISTING SCHOOL sometimes cost about the SAME or MORE than the construction of a NEW SCHOOL? 1. BASIC FACTS: The current Abington High School building is 111,831

More information

ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE

ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE For discussion (date to be confirmed) PWSC(2015-16)6 ITEM FOR PUBLIC WORKS SUBCOMMITTEE OF FINANCE COMMITTEE HEAD 703 BUILDINGS Government Office Intra-governmental services 120KA Building a government

More information

KBC Chapter 34 : Applying the Kentucky Building Code to Existing and Historic Buildings

KBC Chapter 34 : Applying the Kentucky Building Code to Existing and Historic Buildings KBC Chapter 34 : Applying the Kentucky Building Code to Existing and Historic Buildings Presented by: Kentucky Department of Housing, Buildings, and Construction Kentucky Heritage Council Louisville Metro

More information

Government of Canada Transformation of Pay Administration Initiative. Presentation to Financial Management Institute

Government of Canada Transformation of Pay Administration Initiative. Presentation to Financial Management Institute Government of Canada Transformation of Pay Administration Initiative Presentation to Financial Management Institute Presented By: Brigitte Fortin, Associate Assistant Deputy Minister Accounting, Banking

More information

3. HERITAGE GRANT APPROVAL 192 MOORHOUSE AVENUE, CHRISTCHURCH

3. HERITAGE GRANT APPROVAL 192 MOORHOUSE AVENUE, CHRISTCHURCH 3. HERITAGE GRANT APPROVAL 192 MOORHOUSE AVENUE, CHRISTCHURCH General Manager responsible: General Manager, Strategy and Planning Group, DDI: 941-8281 Officer responsible: Author: PURPOSE OF REPORT Programme

More information

The Role of Independent Fiscal Institutions. Lisa von Trapp Budgeting and Public Expenditures Organisation for Economic Cooperation and Development

The Role of Independent Fiscal Institutions. Lisa von Trapp Budgeting and Public Expenditures Organisation for Economic Cooperation and Development The Role of Independent Fiscal Institutions Lisa von Trapp Budgeting and Public Expenditures Organisation for Economic Cooperation and Development Luxembourg, 7 June 2011 What is an Independent Fiscal

More information

@hba_sudbury. Buying A New Home. Presented in Partnership with. Greater Sudbury Public Library PHONE SDHBA: 705 671 6099

@hba_sudbury. Buying A New Home. Presented in Partnership with. Greater Sudbury Public Library PHONE SDHBA: 705 671 6099 Buying A New Home Presented in Partnership with Greater Sudbury Public Library PHONE SDHBA: 705 671 6099 1 Four Month Series DATES: Sept 13: Underground / Cash Deal Oct 11: Talking with Builder / Renovator

More information

Lindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1

Lindsay Thurber Comprehensive High School Red Deer School District No. 104 School Facilities Evaluation Project Page 1 School Facilities Evaluation Project Page 1 Executive Summary In November 1999, Alberta Infrastructure, School Facilities Branch engaged Stephens Kozak Carr and Brown Architects to conduct evaluations

More information

Commercial Building Program (CBP)

Commercial Building Program (CBP) Commercial Building Program (CBP) Rehabilitation or Demolition Schuyler, Nebraska {previously titled, Commercial Building Rehabilitation Program } Aging commercial buildings require timely maintenance

More information

Contractor Safety Management Procedure

Contractor Safety Management Procedure IDM UID Q2GBJF VERSION CREATED ON / VERSION / STATUS 02 Apr 2015 / 1.2 / Approved EXTERNAL REFERENCE Notice to Proceed Contractor Safety Management Procedure The purpose of this instruction is to describe

More information

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT

THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT ACCOUNTABLE SIGNATURE AUTHORISED for implementation SIGNATURE On behalf of Chief Executive

More information

Q. Please provide resumes for Gary L. Murray, Sean LaCour, Glenn Samms, Trina L. Troke, Trina Cormier.

Q. Please provide resumes for Gary L. Murray, Sean LaCour, Glenn Samms, Trina L. Troke, Trina Cormier. Requests for Information CA-47.0 NP NP 2007 CBA 1 2 3 4 5 6 Q. Please provide resumes for Gary L. Murray, Sean LaCour, Glenn Samms, Trina L. Troke, Trina Cormier. A. The resumes of Mr. Gary L. Murray,

More information

This scheme is entirely free and has the security of Waterford Council behind it.

This scheme is entirely free and has the security of Waterford Council behind it. LANDLORD INFORMATION VACANT PREMISES SCHEME (City Arts Spaces) With the success of the new visitor attractions to Waterford and an increase in tourist numbers, Waterford Council is again taking applications

More information

Budget development and management within departments

Budget development and management within departments V I C T O R I A Auditor General Victoria Budget development and management within departments Ordered to be printed by Authority. Government Printer for the State of Victoria No. 39, Session 2003-2004

More information

Article 11. Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools

Article 11. Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools Article 11 Window Replacement Project Norman E. Day & Col. John Robinson Elementary Schools MSBA Accelerated Repair Program Program targets replacement of roofs, windows, doors, and boilers Goal is to

More information

Health PEI Business Plan: April 1, 2010-March 31, 2011

Health PEI Business Plan: April 1, 2010-March 31, 2011 ONE ISLAND FUTURE ONE ISLAND HEALTH SYSTEM Business Plan: April 1, 2010-March 31, 2011 Published by: Health PEI PO Box 2000 Charlottetown PEI Canada, C1A 7N8 September 2010 Cover: Strategic Marketing and

More information

MULTI-RESIDENTIAL BUILDING SOLUTIONS

MULTI-RESIDENTIAL BUILDING SOLUTIONS MULTI-RESIDENTIAL BUILDING SOLUTIONS OUR EXPERTISE AT YOUR SERVICE Canam has been offering owners, real estate developers, architects, engineers and contractors an array of construction solutions since

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Project Management of the Canadian High Arctic Research Station

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Project Management of the Canadian High Arctic Research Station Aboriginal Affairs and Northern Development Canada Internal Audit Report Audit of Project Management of the Canadian High Arctic Research Station Prepared by: Audit and Assurance Services Branch Project

More information

CONSTRUCTION RISK MANAGEMENT. TABLE of CONTENTS:

CONSTRUCTION RISK MANAGEMENT. TABLE of CONTENTS: CONSTRUCTION RISK MANAGEMENT TABLE of CONTENTS: 1. Introduction 2 2. Project Start Up Risk Exposure Analysis 3 3. Insurance 5 4. Additional Advice 8 5. Bonding 9 6. Subcontractor Default Insurance 11 1

More information

January 31, 2003. Members of the Legislative Audit Committee:

January 31, 2003. Members of the Legislative Audit Committee: Lawrence F. Alwin, CPA State Auditor An Audit of The Administrative Expenses the National Heritage Insurance Company Charged to the Health and Human Services Commission January 31, 2003 Members of the

More information

HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION

HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION HAZELWOOD HIGH SCHOOLS SCHEMATIC DESIGN PRESENTATION 1 AGENDA Hazelwood 1 st Planning Process High School Program Schematic Designs Schedule 2 HAZELWOOD 1 ST GOALS Life, health and safety improvements

More information

CITY OF SANTA MONICA RESIDENTIAL REHABILITATION PROGRAM GUIDELINES

CITY OF SANTA MONICA RESIDENTIAL REHABILITATION PROGRAM GUIDELINES CITY OF SANTA MONICA RESIDENTIAL REHABILITATION PROGRAM GUIDELINES Proposed June 2014 TABLE OF CONTENTS Page l. MULTIFAMILY REHABILITATION... 1 II. OWNER-OCCUPIED REHABILITATION... 2 III. ELIGIBLE REPAIRS/IMPROVEMENTS...

More information

WELCOME PROPOSALS FOR PENTAVIA RETAIL PARK WELCOME TO OUR EXHIBITION WHICH SETS OUT OUR PLANS TO DEVELOP THE PENTAVIA RETAIL PARK SITE.

WELCOME PROPOSALS FOR PENTAVIA RETAIL PARK WELCOME TO OUR EXHIBITION WHICH SETS OUT OUR PLANS TO DEVELOP THE PENTAVIA RETAIL PARK SITE. WELCOME WELCOME TO OUR EXHIBITION WHICH SETS OUT OUR PLANS TO DEVELOP THE PENTAVIA RETAIL PARK SITE. The purpose of the exhibition is to provide the community with the opportunity to view our initial ideas

More information

Request for Proposal No. RFP02658. Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition

Request for Proposal No. RFP02658. Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 contractingservices@seattleschools.org Request for Proposal No. RFP02658

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

Travaux publics et Services gouvernementaux Canada. Public Works and Government Services Canada. our portfolio. our story 2008-2009

Travaux publics et Services gouvernementaux Canada. Public Works and Government Services Canada. our portfolio. our story 2008-2009 Public Works and Government Services Canada Travaux publics et Services gouvernementaux Canada our portfolio our story 2008-2009 REAL PROPERTY BRANCH Disponible en français Contact Us We welcome your comments

More information

Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents

Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents Primary Author: Laura McCluskey 4801 N Career Ave Sioux Falls, SD

More information

York Comprehensive. A Case Study. York comprehensive high school auditorium

York Comprehensive. A Case Study. York comprehensive high school auditorium York Comprehensive High School A Case Study York comprehensive high school auditorium York Comprehensive High School Exterior Imagine three individual schools in one district each representing a community

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM GB2 OFFICE OF THE PRESIDENT TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: For the Meeting of May 15, 2013 ACTION ITEM APPROVAL OF THE BUDGET AND APPROVAL OF DESIGN FOLLOWING ACTION PURSUANT TO

More information

EA@GC. Enterprise Architecture at the Government of Canada

EA@GC. Enterprise Architecture at the Government of Canada EA@GC Enterprise Architecture at the Government of Canada Gary Doucet Chief Architect, Government of Canada Treasury Board Secretariat Vice President, Association of Enterprise Architects April 2008 Lets

More information

Putting your business into motion

Putting your business into motion Putting your business into motion Monitoring Systems MONITORING IS ONE OF THE FASTEST GROWING DISCIPLINES IN SURVEYING THE WORLD IN MOTION Demand for monitoring is on the rise. Around the world, new monitoring

More information

Transport for London. Projects and Planning Panel

Transport for London. Projects and Planning Panel Agenda Item 5 Transport for London Projects and Planning Panel Subject: Project Monitoring Project s Date: 9 January 2014 1 Purpose 1.1 To present to the Panel the forward approval programme for projects

More information

Term Sheet for Lease in Cambridge, Massachusetts

Term Sheet for Lease in Cambridge, Massachusetts 1/22/15 Term Sheet for Lease in Cambridge, Massachusetts D A T E D A S O F : J A N U A R Y X X, 2015 PREAMBLE: Landlord and Tenant (each as defined below) hereby enter this Term Sheet (this Term Sheet

More information

Supply Chain Stream. Innovation Procurement The Made in Canada Approach to Vendor Credentialing

Supply Chain Stream. Innovation Procurement The Made in Canada Approach to Vendor Credentialing Supply Chain Stream Innovation Procurement The Made in Canada Approach to Vendor Credentialing Why Supply Chain Matters Improves clinical and fiscal outcomes in any health care organization From the basement

More information

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention

More information

TD AMERITRADE Park Omaha

TD AMERITRADE Park Omaha TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment

More information