1 State Revolving Fund Project Plan Overview Public Meeting June 10, 2009
2 What is the OMI? The OMI is the Oakland Macomb Interceptor Sewer. The OMI transports much of the sanitary sewage from Oakland and Macomb Counties to the Detroit Water & Sewerage Department (DWSD) for treatment. The OMI is a 21 mile long pipe tunnel. The OMI is between 3 0 and 12 9 in diameter (mostly over 8 ) The OMI is buried up to 100 deep. The OMI serves about 830,000 people.
3 What is the OMI Service Area?
4 Who does the OMI Service? City of Auburn Hills City of Clarkston City of Rochester City of Rochester Hills Independence Township Oakland Township Orion Township Oxford Township West Bloomfield Township Waterford Township Village of Lake Orion Village of Oxford City of Fraser City of Sterling Heights City of Utica Chesterfield Township Clinton Township Harrison Township Lenox Township Macomb Township Shelby Township Washington Township Village of New Haven
5 Where is the OMI located? Begins at Dequindre and Avon Roads An arm follows M-59 Follows Clinton River and Utica Road to Dodge Park Road. Follows Dodge Park Rd. to 15 Mile Road. Follows 15 Mile Rd, to the ITC (Edison) Corridor Follows the ITC Corridor to 9 Mile Road. Follows the Railroad ROW to just south of Eight Mile Road.
6 What is the History of the OMI? Built in the early 1970s by Detroit Water and Sewerage Department Series of Construction Contracts Included the 15 Mile and Romeo Arms in Macomb County Three Collapses on15 Mile 1978, 1980, 2004 Major Disruption Occurred Loss of Service Environmental Impairment Surface Disruption $200,000,000 in Repair Costs (current dollars) INSERT FIG 4
7 What Disruption is Caused by a Collapse?
8 What is the OMI s Current Condition? The OMI was inspected in 2007 and Visual inspection was conducted by staff and by using CCTV. Much of the pipe exhibited moderate to severe deterioration. Voids were detected above the pipe in a number of areas. Infiltration through cracks will continue to deteriorate the pipe. Projecting Reinforcing Steel Crown of Pipe Severely Deteriorated
9 Why is the Project Needed? The OMI was constructed using the same design, materials and contractors in the same soil conditions and at the same time as the 15 Mile Road Interceptor. The 15 Mile Road Interceptor has failed three times with catastrophic results. Rehab will prevent environmental impairment. Rehab of the OMI will prevent collapse at costs far less than future repairs.
10 Where are the Problem Areas? High Distress Areas Avon Arm (M 59) 2 areas 15 Mile west of corridor Corridor south of 15 Mile Corridor at I 696 Corridor at 10 ½Mile Corridor south of 10 Mile Medium Distress Areas Utica south of M 59 Dodge Park south of 18 Mile Dodge Park south of 16 Mile Corridor north of 12 Mile Corridor south of 11 ½Mile Localized Distress Throughout INSERT FIG 8
11 What are the Alternatives? Three Alternatives were analyzed The first is the No Action Alternative The second is the Replacement Alternative The third is the Rehabilitation Alternative
12 What is the No Action Alternative? THE OMI would remain in service with no repair or rehabilitation. Structural defects would remain and expand. Pipe failure collapse could be anticipated at some unknown time. Initial Capital cost would be Zero. Additional user cost would be Zero. Future Repair cost could be Significant. Potential Environmental Impact is Severe.
13 What is the Replacement Alternative? The existing pipe would be replaced in a tunnel roughly paralleling the current route. Construction would disrupt many neighborhoods. Initial Capital Cost would be $499,000,000. Additional User Cost would be about $103 per year per customer over 20 years. INSERT FIG 7
14 What is the Rehabilitation Alternative? Control Structures would be constructed to allow work inside the tunnel while maintaining service to customers. Structural lining would be constructed in severely deteriorated areas. Cracks and leaks would be sealed to prevent further deterioration. Initial Capital Cost would be about $160,000,000. Additional User Cost would be about $35 per year per customer over 20 years.
15 How do the Alternative Costs Compare? ALTERNATIVES No Action Replacement Rehabilitation Estimated Capital Cost $ $ 499,000,000 $ 160,068,220 SRF Interest Rate 2.50% 2.50% 2.50% Term in years Estimated Annual Payment $ $ 32,009,417 $ 10,267,917 Estimated Annual O&M Cost $ 832,529 $ 832,529 $ 832,529 Estimated Total Annual Cost $ 832,529 $ 32,841,946 $ 11,100,446 Service Area Population 832, , ,902 Average Household Size Number of Customers 319, , ,120 Estimated Annual Cost per Customer over 20 years $ 2.61 plus potential repair costs $ $ 34.78
16 What Alternative has been selected? The Rehabilitation Alternative provides for construction leading to a tunnel with a useful life of at least 20 years. The alternative does not require area wide disruption that Replacement would. The alternative will protect against catastrophic collapse that is a potential of No Action. The annual user cost of about $35.00 (over 20 years) will be much less than potential repair costs and is a reasonable addition to current rates.
17 When will the Work Take Place? Design Efforts: Construction Efforts: Year Quarter Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Project Component Hydraulic Study Modify Corridor Gate Supplimental Geotech PCI 5 Gate PCI 5 Rehab PCI 5 Grouting PCI 8 New Gate PCI 9 Temp fix of hole PCI 8 New Access Shaft PCI 8 Rehab PCI 7 Corridor Bypass PCI 7 Rehab PCI 7 Grouting PCI 11A Rehab PIC 6 New Gate PCI 6 Rehab PCI 6 Groutimg PCI 9 Control Structure PCI 9 Rehab PCI 10B Rehab PCI 10A Rehab
18 What are the Social & Environmental Impacts? Without Replacement or repair collapse of the OMI could cause up to 83 million gallons of raw sewage to be discharged by tributary communities per day. During Rehabilitation surface disruption to open space and parkland may take place that will be mitigated upon completion. Minor construction related impacts will also occur. These impacts include additional noise, dust, sediment and traffic. These will be minimized by staging construction and implementing best management practices. No Historical or Archeological sites will be disturbed as part of the Rehabilitation.
19 Any Questions or Comments?
20 Thank You for Your Interest!
MACOMB COUNTY NEIGHBORHOOD STABILIZATION PROGRAM HOMEBUYER ASSISTANCE FOR VACANT FORECLOSED PROPERTIES
MACOMB COUNTY HOMEBUYER ASSISTANCE OVERVIEW and GUIDELINES OVERVIEW Macomb County s Homebuyer Program for Vacant Foreclosed Properties is part of the Neighborhood Stabilization Program (NSP) created by
More informationAfter the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service.
After the Flush Published: July 14, 2011 Sewage or wastewater is something we rarely think or talk about. The wastewater from our toilets, showers, washing machines and dishwashers quickly departs our
More informationPurpose and Approach. Introduction
City of Ann Arbor Sanitary Sewer Wet Weather Evaluation Project Best Practices Sub- Group of the Citizens Advisory Committee Examples of Wet Weather Improvements from Other Communities December 5, 2013
More informationDEPARTMENT OF ENVIRONMENTAL QUALITY
PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized
More informationBRUCE TOWNSHIP 32 MILE ROAD VILLAGE OF ROMEO 30 MILE ROAD CENTRAL SANITARY SEWER DISTRICT CAMPGROUND ROAD 28 MILE ROAD MOUND ROAD VAN DYKE AVENUE
26 MILE ROAD M-53 M-53 OWNER ENGINEER N TRUNKLINE SEWER AND SECTIONS 27, 34, 35, & 36 OF THE CENTRAL SANITARY SEWER DISTRICT T-4-S R-12-E,, SRF NO. 5623-01 BRUCE TOWNSHIP 32 MILE ROAD VILLAGE OF ROMEO
More informationTerry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson Engineering
DON T JUST REHAB IT, RENEW IT! WATERFORD TOWNSHIP, MICHIGAN IMPROVEMENTS TO A 3.0 MGD SEWAGE PUMPING STATION Terry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson
More informationRehabilitation or Replacement? That Is The Question
Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections
More informationDry Weather Flow from Footing Drains and Service Connections
Wastewater Master Plan DWSD Project No. CS-1314 Dry Weather Flow from Footing Drains and Service Connections Technical Memorandum Original Date: May 2, 2002 Revision Date: September 2003 Author: CDM Table
More informationSewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority
More informationSANITARY SEWER BACKUP. Causes & Prevention
SANITARY SEWER BACKUP Causes & Prevention A. PURPOSE The purpose of this publication is twofold: 1. It provides homeowners with basic information on the causes of sanitary sewer backups. 2. It provides
More informationSPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
More informationStorm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
More informationMIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.
MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade
More informationCity of Mill Valley Sewer Capital Improvement Plan 2012 2016
City of Mill Valley Sewer Capital Improvement Plan 2012 2016 I. BACKGROUND Between December 2004 and February 2008, the ed States Environmental Protection Agency (EPA) conducted inspections of the SASM
More informationTECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
More informationSanitary Sewer Master Plan
, Illinois Sanitary Sewer Master Plan EXECUTIVE SUMMARY Prepared by September 9, 2010 1670 South Taylorville Road Decatur, Illinois 62521 www.bgmengineering.com Sanitary Sewer Master Plan A. SCOPE OF STUDY
More informationRepair or Replacement - Band-Aids vs. Surgery
Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing
More informationFY15 Gravity Sewer and Manhole Rehabilitation
Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE
More informationZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022
ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 Town of Zionsville, Indiana December 19, 2012 PREPARED BY BEAM, LONGEST & NEFF, LLC. 8126 Castleton Road Indianapolis, Indiana
More informationAlphington sewer replacement
Alphington sewer replacement Frequently asked questions We understand you might have some questions for us so here are a few to provide you with more information. You are also welcome to call us on 1800
More informationBRANDYWINE HUNDRED SEWER REHABILITATION LYNNFIELD WEBSTER FARMS
BRANDYWINE HUNDRED SEWER REHABILITATION PROGRAM ND13 GREEN ACRES GREEN ACRES LYNNFIELD WEBSTER FARMS OBJECTIVES OF MEETING Review Why in Brandywine Hundred Explain County obligations regarding laterals
More informationQuantifying Inflow and Infiltration via Dyed Water Flooding
Quantifying Inflow and Infiltration via Dyed Water Flooding Prepared by Anna Kesler, E.I.T. Catherine Morley, P.E. Overview Historical background to City of Elmhurst I/I issues What Is Dye Flooding? What
More informationWater Main Lining A Sustainable Alternative to Open Cut Replacement
Water Main Lining A Sustainable Alternative to Open Cut Replacement Sean O Dell, PE Baxter & Woodman, Inc. B&W Client Seminar, Crystal Lake May 1, 2014 Agenda Why, What, When, Where, Who, How Reduction
More informationINTRODUCTION. WASTEWATER MANAGEMENT PLAN MAY 2009 Metropolitan North Georgia Water Planning District 7-1
INTRODUCTION There are approximately 16,000 miles of sewers and more than 450,000 manholes within the Metro Water District. Sewers and manholes within the Metro Water District range in age from new to
More informationSEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
More informationAlmonte Sanitary District Sewer System Management Plan Adopted by the ALMONTE Board of Directors on_08/28/06
Almonte Sanitary District Sewer System Management Plan Adopted by the ALMONTE Board of Directors on_08/28/06 1. Goals The goal of this SSMP is to provide a plan and schedule to properly manage, operate,
More informationFISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN WASTEWATER TREATMENT FACILITIES
FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN WASTEWATER TREATMENT FACILITIES 1 FISCAL YEAR 2014-2018 CAPITAL IMPROVEMENT PLAN Wastewater Treatment Facilities The Wastewater Treatment System (System)
More information53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:
Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections
More informationSEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER
Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating
More informationDRAFT Public Outreach Document for What s an SSMP?
DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials
More informationCHARTER TOWNSHIP OF FENTON SEWER SYSTEM FINANCIAL OVERVIEW JANUARY, 2014
CHARTER TOWNSHIP OF FENTON SEWER SYSTEM FINANCIAL OVERVIEW JANUARY, 2014 Fenton Township receives numerous inquiries regarding the relatively high sewer use fees that Township residents have been paying
More informationPhased Assessment Strategy for Sewers
Phased Assessment Strategy for Sewers A plan for understanding sewer system condition quicker, with fewer resources. Venay Sehgal Bhatia Digital Marketing Manager Envirosight Are deteriorating infrastructure
More informationCHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall
CHELTENHAM TOWNSHIP SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall 1 SANITARY SEWER UPDATE 1. Overview a. The Problem b. Pennsylvania Department of Environmental Protection
More informationTownship of Enniskillen. Asset Management Plan
Township of Enniskillen Asset Management Plan 2014 1 TABLE OF CONTENTS Page A. Introduction 3 B. State of Local Infrastructure 4 C. Desired Levels of Service 7 D. Asset Management Strategy 8 E. Financing
More informationTOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion Project Overview Sanitary Sewer System 2 Town of Surfside Project Overview Potable Water System 3 Town of Surfside Project Overview Storm Water
More informationMAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT
Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public
More informationSummary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort
Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort June 25, 2012 Thomas Gossiaux, PE (AECOM) Matt Raysin, PE (GCDC-WWS) Dave Barnas, PE (AECOM) Ed Tharp, PE (AECOM) Summary
More informationTransportation Options
Transportation Options For patients of Crittenton Hospital Medical Center Table of Contents For assistance in finding transportation 3 Wheelchair Van Transportation AmbuTrans 3 Angel Healthcare Express
More informationSewer Pipe & Manhole Rehab. Jack Keys Collection System & Inspection Services Supervisor Southern Clinton County Municipal Utilities Authority
Sewer Pipe & Manhole Rehab Jack Keys Collection System & Inspection Services Supervisor Southern Clinton County Municipal Utilities Authority Past & Present There Are Times It Feels Like This 10 DIP WITH
More informationBefore H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe September 11, 2012 NEWEA Collection Systems Conference Presented by: Laurie L. Perkins, PE Dennis A. Dievert, PE C. Frederick
More information2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES
2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES The Wastewater Treatment System (System)
More informationEstimating Stormwater System Annual Maintenance and Repair Costs - A GIS Approach
October 5 2011 Estimating Stormwater System Annual Maintenance and Repair Costs - A GIS Approach 2011 SESWA Annual Conference 2011 Southeast Stormwater Associated Annual Conference Presentation Overview
More informationRepairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses
Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses They also give the community a built-in re-entry system for future monitoring and repair. BY BRETT HANES According to
More informationSewer systems: Failures and rehabilitation
Water Utility Journal 8: 17-24, 2014. 2014 E.W. Publications Sewer systems: Failures and rehabilitation C. N. Damvergis Hellenic Association of Hydraulic Works and Water Resources Management Consulting
More informationForce Main Condition Assessment: New Technologies & Case Studies
Force Main Condition Assessment: New Technologies & Case Studies Andy Dettmer, Ph.D., P.E. CMOM Workshop August 19, 2014 2 1 Three takeaways 1. Most of your force mains are good 2. We can pinpoint the
More informationFor Asset Management
For Asset Management By: Larry Weiss SDLTAP It Begins with Accurate Inventory Inventory of existing system: The Local Roads Needs Study conducted in Aug/Sept of 08 indicated by it s results and from LTAP
More informationUsing Frequent Sewer Inspection to Prioritize Asset Management. May 1, 2014. John Schroeder, P.E., BCEE Drew Richards, EI Tim Fallara, P.E.
Using Frequent Sewer Inspection to Prioritize Asset Management May 1, 2014 John Schroeder, P.E., BCEE Drew Richards, EI Tim Fallara, P.E. Agenda Rationale and Goals for Sewer Re-inspection How and why
More informationSECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
More informationIS THAT LINER THICK ENOUGH?
IS THAT LINER THICK ENOUGH? Philip McFarlane, Opus International Consultants Ltd ABSTRACT The amount of pipeline rehabilitation being undertaken in New Zealand is increasing each year. Larger diameter
More informationMeeting the Challenge of Pipeline Emergency Repair
Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider
More informationWorking together to improve beach water quality. Fixing our. public and private. sewers
Working together to improve beach water quality Fixing our public and private sewers May 2004 FIND FIX DECIDE Narrow Neck Beach on a summer day As part of Project CARE, our long-term project to improve
More informationUtilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets
*Jessica Brown, P.E., Freese and Nichols, Inc., (817) 312-6980; Jessica.Brown@freese.com Mazen Kawasmi, Freese and Nichols, Inc. ABSTRACT The City of Fort Worth s wastewater collection system includes
More informationNON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES
North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES Brad Jenson
More informationCoxwell Sanitary Trunk Sewer Emergency Repair: By-pass Sewer Tunnel Construction Final Report
STAFF REPORT ACTION REQUIRED Coxwell Sanitary Trunk Sewer Emergency Repair: By-pass Sewer Tunnel Construction Final Report Date: July 28, 2014 To: From: Public Works and Infrastructure Committee General
More informationSTANDARD SPECIFICATIONS SECTION 02959 SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT
STANDARD SPECIFICATIONS SECTION 02959 SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for rehabilitation of defective mainline
More informationA Comprehensive Approach to Storm Water Asset Management Planning. City of Virginia Beach Public Works Operations
A Comprehensive Approach to Storm Water Asset Management Planning City of Virginia Beach Public Works Operations Steve McLaughlin, PE April 2016 Agenda City of Virginia Beach, VA Population: 450,000 250
More informationRouge River Watershed, MI Region 5. Community Case Study ROU-1. Number of CSO Outfalls. Combined Sewer Service Area. Wastewater Treatment Capacity
Community Case Study Rouge River Watershed, MI Region 5 Number of CSO Outfalls 168 Combined Sewer Service Area 93 square miles Wastewater Treatment Capacity 1,700 mgd (primary) 930 mgd (secondary) Receiving
More informationSee Appendix A for additional information, or contact ASTM directly.
DEFINITIONS Wherever used in these specification guidelines, the following words and terms have the meanings indicated. AREAWAY: A paved surface, serving as an entry area to a basement or subsurface portion
More informationCOMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary
CITY OF LAKEWOOD COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary MAY 2006 storage conveyance treatment performance Prepared for: City of Lakewood, Ohio Prepared by: Metcalf & Eddy of Ohio,
More informationTHE BIG FIX: Public works administration would be easy if infrastructure. San Diego s Sewer Renewal Program. By Steve Gibbs
THE BIG FIX: San Diego s Sewer Renewal Program By Steve Gibbs Public works administration would be easy if infrastructure lasted forever. It does not. Roads, bridges and sewers eventually wear out. Even
More informationREVISED SHORT TERM AND LONG TERM SEWER PIPE INSPECTION AND CONDITION ASSESSMENT PROGRAM SOUTH COAST WATER DISTRICT. June 2005
REVISED SHORT TERM AND LONG TERM SEWER PIPE INSPECTION AND CONDITION ASSESSMENT PROGRAM SOUTH COAST WATER DISTRICT FOR SOUTH COAST WATER DISTRICT Prepared with the requirements identified in the United
More informationCOMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY
COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY Revised: April 2014 Village of Wilmette, Illinois NPDES CSO Permit No. ILM580012 Chapter 1 Introduction This Operational and Maintenance
More informationCOLLECTION SYSTEM SETTLEMENT AGREEMENT
COLLECTION SYSTEM SETTLEMENT AGREEMENT Wastewater Collection System Rehabilitation and Replacement Report and Plan A deliverable of the Settlement Agreement and Final Order between the city of Los Angeles
More informationComponents of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000
Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 SEMCOG 2000 Prepared
More informationBridges & Culverts Condition by Quantity
3.4.3 What condition is it in? Approximately 93% of the municipality s bridge structures are in good to excellent condition, with the remaining 7% in fair condition. As a result, the municipality received
More informationFirst in Service First in Safety
7840 Nagle Avenue Morton Grove, Illinois 60053 847-470-5235 Fax - 847-965-9511 Wind Damage; Frequently Asked Questions: What can I do with branches that fall in my yard? Bring them out to the parkway;
More informationOVER-HEAD SEWER ASSISTANCE GRANT
OVER-HEAD SEWER ASSISTANCE GRANT The Village of North Aurora has a vested interest in the proper operation of the North Aurora sanitary system. Understanding that some residential users of the sanitary
More informationUndergrounding high voltage electricity transmission. The technical issues
Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.
More informationSPR PE Steel Reinforced Liner
ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has
More informationBEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK
BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD Re Application of the Philadelphia Water Department for Increased Rates and Related Charges Fiscal Years 2017-2018 DIRECT TESTIMONY OF STEPHEN
More informationThe Metropolitan St. Louis Sewer District. Sewer Overflows In Our Community
The Metropolitan St. Louis Sewer District Sewer Overflows In Our Community March 2012 About MSD Formed in 1954, the Metropolitan St. Louis Sewer District (MSD) is the governmental agency that provides
More informationSource Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water
United States Office of Water EPA 916-F-01-032 Environmental Protection (4606) July 2001 Agency Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows
More informationInteractive Decision Tree Automates Sewer Rehabilitation Planning
Interactive Decision Tree Automates Sewer Rehabilitation Planning IWPCA Annual Conference June 5, 2008 Rodney Moeller, P.E., John Schroeder, P.E. BCEE, C. Timothy Fallara, P.E. & Mel Meng, P.E. Agenda
More informationSmall Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C.
Small Dam Repair The Stone Lake Dam Story Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. 29601 1 Historical background of Stone Lake A series of three
More informationAmendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling
Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation
More informationCondition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049
Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049 EPA New England Water Infrastructure Outreach provides tools,
More informationSECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE
SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final
More informationSanitary Sewer Smoke Testing
Sanitary Sewer Smoke Testing Beginning March 31, 2014 The City of Brunswick will be conducting smoke testing on the City s sanitary sewer system beginning March 31, 2014. Smoke testing will occur over
More informationCLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
More informationWastewater Collection and Treatment Systems For Small Cities
Page 1 of 13 FISCAL SUSTAINABILITY PLAN For the, Wastewater Collection and Treatment System This plan outlines a (FSP) for the City of Small Town, County of Xxxxx, State of Kansas, as required by the Kansas
More informationCondition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel
OAWWA 73 rd Annual Conference Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel By Jason DeLaet, P.E. Supervising Engineer Greater Cincinnati Water Works & Michael J. Livermore
More informationTRANSPORTATION RESOURCES for Livingston County Macomb County Oakland County Wayne County
TRANSPORTATION RESOURCES for Livingston County Macomb County Oakland County Wayne County Description Page Senior Center Transportation - Oakland County 3,4 Senior Center Transportation - Livingston County
More informationSewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
More informationReview of Footing Drain Disconnection Projects
Wastewater Master Plan DWSD Project No. CS-1314 Review of Footing Drain Disconnection Projects Technical Memorandum Original Date: August 8 2002 Revision Date: September 2003 Author: CDM Table of Contents
More informationAmbulatory Surgery Centers
Ambulatory Surgery Centers List of Ambulatory Surgery Facilities That Meets Certain QUALITY Standards (set forth by ASC Quality Collaboration & CMS) University of Michigan - East Ann Arbor Ambulatory Surgery
More informationSIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS Introduction City of Tacoma property owners are responsible for the construction, maintenance and repair of private side sewers, which connect
More informationBACKUPS! Solving the Problem in a Seattle Neighborhood
BACKUPS! Solving the Problem in a Seattle Neighborhood MARTHA BURKE SEATTLE PUBLIC UTILITIES A ND A NDY BEHNKE HERRERA ENVIRONMENTAL CONSULTANTS PNCWA 2 009 BOISE, IDAHO Broadview Area Project Study Area
More informationSession: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University
More informationPlatte River Interceptor Slipline Rehabilitation
Platte River Interceptor Slipline Rehabilitation Owner: Metro Wastewater Reclamation District Contractor: American West, Denver CO Slipline Pipe Manufacturer : Hobas Pipe USA Presented by: Tom Furie, Area
More informationSEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
More informationS-16 Sewer Pump Station Improvements
S-16 Pump Station Improvements Status: Ongoing Location: Pump stations throughout the Utility s service area Budget 20,600,491 12,181,491 512,000 1,340,000 2,310,000 1,075,000 1,097,000 1,090,000 995,000
More informationIndustrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems.
Industrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems. Aging pipeline infrastructure and industry s inability to evaluate and inspect has left many engineers and plant managers
More informationPREVENTING GROUNDWATER POLLUTION: SECONDARY CONTAINMENT
PREVENTING GROUNDWATER POLLUTION: SECONDARY CONTAINMENT PREVENTING GROUNDWATER POLLUTION IS EVERYONE S JOB! Even if our drinking water comes from rivers, lakes, or reservoirs, we need to be mindful of
More informationSan Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION
ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,
More informationAnnular Space Grouting of Slipline Products
Annular Space Grouting of Slipline Products by David Gellings(, M.APWA & John Jurgens(, M.WWCPA Traditional methods of using neat cement slurries, (Portland cement and water, cement with fly ash or cement
More informationTask F: Financial Plan
Task F: Financial Plan Comprehensive Water Master Plan DWSD Contract No. CS-1278 Final Report For Submittal to Detroit Water and Sewerage Department June 2004 IN ASSOCIATION WITH CDM Task F: Financial
More informationAppendix J: Pipe Evaluation and Replacement Options and Costs
Appendix J: Pipe Evaluation and Replacement Options and Costs STORMWATER SYSTEM INVENTORY The City of Olympia has an extensive stormwater conveyance system. As a matter prudent management of the Stormwater
More informationUsing StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System
Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System Luis Aguiar Miami-Dade Water & Sewer Department Anna Pridmore, PhD Structural Technologies PROJECT BACKGROUND Miami-Dade Water & Sewer Department
More informationCURED-IN-PLACE PIPE MINIMIZING RISK BY DEFECT CODING
North American Society for Trenchless Technology 2007 No-Dig Conference & Exhibition San Diego, California April 16-19, 2007 CURED-IN-PLACE PIPE MINIMIZING RISK BY DEFECT CODING Robert K. Lee, P.E. 1 1
More informationBeechmont Park Project
Beechmont Park Project Foundation Drain Project Why pre -1972 homes are chosen in your neighborhood? Results of pilot study in your area showed the majority of homes built prior to 1972 within your neighborhood
More information