1 COMPARATIVE LIFE-CYCLE ANALYSIS OF ENERGY-EFFICIENCY MEASURES AT TVA S CHATTANOOGA OFFICE COMPLEX: PHASE II RESULTS & FINAL DESIGN Umesh Atre Innovative Design Inc 850 W Morgan St Raleigh, NC umesh@innovativedesign.net Michael Nicklas Innovative Design Inc 850 W Morgan St Raleigh, NC nicklas@innovativedesign.net David Zimmerman Tennessee Valley Authority 1101 Market St Chattanooga, TN drzimmerman@tva.gov ABSTRACT This paper presents the second phase of the daylighting & building energy simulation work conducted for Tennessee Valley Authority s 1.3 million sf Chattanooga Office Complex (COC). Once the base daylighting and building energy models were validated for one building (as part of the first phase), energy simulation models were developed and validated for the entire complex, this expanded scope now involving 4 office buildings and data center served by a central chilled water & hot water plant. A 3-step validation had to be performed since the data center was metered separately but still shared the same central plant. equest (DOE-2.2) & Daysim 3.0 (Radiance) software were used for energy modeling & daylighting analysis respectively. The new models for the entire complex were modified to analyze effects of the following energy-efficiency measures: atrium & office daylighting, lighting, plug loads, chilled water & cooling water ΔT, VFDs, reduced outside air, BAS & improved AHU operation, atrium heat recovery & destratification, new chillers, water-source heat pumps, and exhaust air energy recovery systems. The final proposed design is expected to reduce existing building energy consumption by 33%. Daylighting, improved lighting, and plug load optimization represents 58% of the total energy savings. Detailed cost-benefitanalyses suggest a 13-year payback on all measures excluding daylighting, lighting, and plug loads, and a 17- year combined payback. The expected energy savings would help TVA achieve/exceed their rigorous internal energy goals while complying with federal mandates. HVAC and lighting upgrades, combined with other design changes, could qualify this facility for a possible LEED-CI rating. North South Fig. 1: Site Plan of the TVA COC showing buildings A,B,C,D,E,F, and the Computer/Data Center

2 1. BASECASE MODEL VALIDATION The first step involved in the building energy modeling and validation process included getting together relevant information on the following items. Requests were made to the building design team and the building management teams, depending on data classifications. Data requested from the Architects of Record on the COC and/or TVA included the following: Architectural drawings and building assemblies information Mechanical drawings and HVAC zoning Electrical drawings Interior design/furniture layouts Data requested from the Engineering/Building Management teams and/or TVA included the following: Mechanical drawings and HVAC zoning Electrical drawings Occupancy and schedules Lighting schedules Building management schedules Building energy consumption (utility bills) Interior equipment and schedules A 3-step model validation had to be performed for accuracy: was established using the individual building area fractions in comparison to the totals. Though the Monteagle Place (MP) building has an actual (measured) base performance of 250+ Kbtu/sf/yr, it only accounts for 11% of the combined square footage of all the buildings. The actual base performance of the rest of the COC is 58 Kbtu/sf/yr, and the energy performance for the combined model was thus determined to be 79.8 Kbtu/sf/yr, which matches pretty closely with the simulation results for the combined model. Step 1: Validation of the Chattanooga Office Complex model, excluding Monteagle Place (data center) Step 2: Validation of the model for Monteagle Place Step 3: Validation of the combined model for Chattanooga Office Complex, including Monteagle Place Steps 1 and 2 were possible and essential since TVA has been keeping separate utility bill records for Monteagle Place (data center) and the rest of the COC. Fig. 3: Basecase Model Validation Results 2. ENERGY-EFFICIENCY MEASURES 2.1 Summary Of Past Analysis And Current Process Fig. 2: Building Energy Model for the entire TVA COC Since the COC and Monteagle Place models had to be combined, a baseline building energy performance target The past analysis (published in the 2011 ASES Proceedings) for the TVA COC focused on evaluating only one building Lookout Place (LP) to understand the effects of daylighting, lighting, and interior equipment modifications on the existing building s energy performance. Other measures were studied, with the intention of having a more detailed analysis in the future. The current phase of analysis was begun with a model built for the COC (set of 5 buildings), excluding the data center (Monteagle Place). The same first sets of recommendations

3 (daylighting, lighting, and interior equipment) were evaluated for this complex. With the inclusion of the Monteagle Place building to the COC model, it was decided that the COC model (excluding Monteagle Place) not be used to study the further new set of recommendations received from the engineering team, since all of these buildings share the same central plant. Beyond the New Basecase model, a revised model for the entire COC+MP was developed. The following description of runs refers to this revised model. A later portion of the analysis compared the original Lookout Place model, the later COC model, and the final COC+MP model for reference purpose. 2.2 Description Of Runs Baseline Model The baseline model represents the Existing buildings. All as-built architectural, mechanical, and electrical drawings and supporting documentation was used in this run. An image of the baseline building energy model is shown in Fig. 2., and the baseline model validation results for the TVA COC and TVA COC + MP are presented in Fig Daylighting Design This run focused on studying the effects of daylighting on the building energy consumption. Of particular interest was the effect on the interior lighting and cooling energy consumption. Hourly daylighting schedules generated using separate daylighting analysis software (Daysim) were incorporated into the previously validated baseline building energy model. This revised building energy model represents the effect of using the following daylighting design recommendations in existing spaces: Interior fabric baffles in the perimeter spaces, Translucent glazing system in the atrium skylights, High reflectance ceilings, New, reflective surfaces in the light scoops located at every floor level in the atrium, and Interior fabric baffles in the spaces adjoining the atrium A daylighting analysis report was created as a separate document for details on each of the recommended options for the office and atrium spaces. All the other simulation parameters were kept the same as the original model Interior Lighting This run focused on studying the effects of improved, energy-efficient lighting on the building energy consumption. The average ambient lighting intensity used in this analysis is set at 0.8 w/sf, which follows in line with the lighting design that is currently being proposed by the architectural team on this project. The ambient lighting set point for both the daylighting and the interior lighting is set at 35 fc, with supplemental task lighting as required Interior Plug Load Equipment This run included studying the effect of reducing the installed w/sf on the plug load equipment in the COC workstations. Average savings from the Workstation Occupancy Sensors Study and Workstation Occupancy Survey conducted by the TVA s Building Management personnel were used in the office spaces to estimate savings. After discussion with TVA personnel and the architectural and mechanical teams, the three strategies mentioned above (namely, daylighting, interior lighting, and plug load management) were considered to be a definite current or future implementation at the COC. A combined model including these 3 strategies was renamed as the New Basecase, and all future energy measures were then compared against this new model. Note: All the runs beyond this point were based on HVAC recommendations by the PME engineering team (local firm from Chattanooga, TN) working on this project. The following descriptions were summarized from an original HVAC report titled Energy Modeling Packages developed by this engineering team Increase Chilled Water Temperature Difference on Existing Chillers This strategy proposes to increase the chilled water temperature differentials on the existing chillers. Current Lookout Place differential is 14 deg. F., and current Monteagle Place differential is 11 deg. F. This model evaluated the effect of increasing these existing differentials to 16 deg. F. Chillers were modeled be operated at 42 deg. F. chilled water temperature in conjunction with VFDs on the chilled water pumps. Results of this run should be compared to the New Basecase. This is referred to as Run 1 and the Alternate as Alt 1* in Fig.4 and/or Fig.5. Alternate: Results from the run mentioned above show a reduction in pumping energy as expected, but also shows a reduction in cooling energy and cooling tower energy, which are unexpected savings resulting from this measure. One possible reason could be that with reduced pumping, the heat generated by the pump motor is reduced and thus less of it gets transferred into the chilled water loop. The chillers see less heat as compared to the basecase, resulting in cooling savings and lower heat rejection. Though this could be a possible reason, the magnitude of cooling savings is not proportionate to the reduced heat generated by the pumps.

4 Fig. 4: Integrated Energy Saving Sets for the COC+MP, COC, and the original LP (Lookout Place) models Fig. 5: Building Energy Performance of Individual Runs (beyond New Basecase) for the COC+MP model Hence an Alternate was presented assuming no cooling or tower savings are achieved in this run. This was intended to provide a best and worst case scenario and determine a range on the savings. Note: Alternates were also presented for all the future runs that feature either a change in the chilled water temperature differential and/or the cooling tower water temperature differential.

5 2.2.6 Increase Cooling Tower Water Temperature Differences on Existing Cooling Towers This strategy proposes to increase the cooling tower water differentials on the existing cooling towers. Current cooling tower differentials are 10 deg. F. This model evaluated the effect of increasing these existing differentials to 14 deg. F. Cooling Tower pumps were modeled with VFDs. Results of this run should be compared to the new basecase. This is referred to as Run 2 and the Alternate as Alt 2* in Fig.4 and/or Fig Cooling Tower Fans VFD Controls This strategy proposes to install variable frequency drives on the cooling tower fan motors. The basecase model was modified to include VFD controls on the pumps. Results of this run should be compared to the new basecase. This is referred to as Run 3 in Fig.4 and/or Fig.5. Note: A combined simulation of runs 2 and 3 was run to see the effect of both these applications together. This is referred to as Run 2&3 and the Alternate as Alt 2&3* in Fig.4 and/or Fig Reduction In Outside Air Quantity This strategy proposes to reduce outside air quantity by improved particulate filtration and cleaning of air stream gas contamination using Bi-Polar Ionization method. The outside air target reduction is from 15 cfm per person to 5 cfm per person. Air handlers would also be upfitted with MERV 6 (30%) prefilters followed by MERV 13 (85%) final filters to arrest particulates. Bi-Polar Ionization hardware would be installed between the final filters and coil bank. This model evaluated the energy savings resulting from the reduced outside air conditioning. Data received from the engineering team suggested that no additional static would need to be added due to these modifications. This is referred to as Run 4 in Fig.4 and/or Fig.5. reduction in fan horsepower requirements associated with all core area air handlers operating under a full DDC controlled duct pressure optimization in a True VAV mode. This is referred to as Run 5 in Fig.4 and/or Fig Atrium Heat Recovery and Destratification This strategy proposes evaluation of the heat recovery opportunities in the atriums. Heat trapped below the skylights can be captured and used during the heating season (October-March). Large-blade fans would be installed in the atrium that could induce enough ventilation to drive the stratified air from the upper levels of the atrium to occupied zones. This modeling package could not be evaluated using the building energy analysis software and savings were calculated using a custom excel spreadsheet. Hourly temperature reports were generated to estimate the amount of usable heat. This is referred to as Run 6 in Fig.4 and/or Fig.5. Note: These fans could also be operated during the summer seasons to allow for a small increase (2-4 deg. F) in thermostat cooling set-points thus taking advantage of the ventilation leading to cooling savings. The savings are currently limited to heat recovery in the heating season only. Comparison between the existing condition and the proposed daylighting design in the atrium spaces (one of the large blade fans is seen in the proposed image) is shown in Fig. 6. The current primary issue of direct beam radiation is mitigated through the use of translucent skylight glazing. Note: This particular strategy is still under consideration due to influence of LEED modeling guidelines BAS/Improved Air Handler Operation This combination of strategies proposes to evaluate energy savings associated with a full conversion to a micro-processor based Variable Air Volume (VAV) HVAC system. The savings would also be extended to all of the system hydronic equipment components. Currently pneumatic thermostats control ceiling diffuser vanes in the core spaces. Air valves located at branch take-offs of each duct adjust static pressure above the diffusers, but there is no direct communication/signaling between all the branch ducts. This model evaluates Fig. 6: Comparing Existing and Proposed Daylighting in the Atrium space at COC Integrated Set 1-6 Runs of combination strategies allowed the design team to understand and compare the effects of individual

6 strategies versus overall effects. The following 2 sets were considered: 7A: Integrated Set of 1-6 runs with 5 and without run 4 (reduced OA), and 7B: Integrated Set of 1-6 runs with 5 and with run 4 (reduced OA). These are referred to as Run 7A and 7B, and the Alternates as Alt 7A* and Alt7B* in Fig.4. The reason for the two different sets was due to the fact that the reduced outside air strategy was still under consideration, as mentioned earlier New Chillers This strategy proposes evaluating replacement of 2 of the existing Lookout Place chillers with cooling-only type high-efficiency machines. All 3 chillers in Monteagle Place were modeled as existing without any modifications. Data obtained for the Trane CenTraVac machines was used in this analysis. This modeling run was further improved upon in the next package with the integration of a water source heat pump. This is referred to as Run 8 in Fig.4 and/or Fig Water Source Heat Pump This strategy proposes evaluating integration of a high water temperature water source heat pump in the Monteagle/Lookout Place chiller mix to reduce heat recovery cost. A 350 ton heat pump has been evaluated based upon the hot water and efficiency parameters received from the engineering team. This run was combined with the earlier run (run 8), and the results for run 8 include savings from this recommendation. strategies versus overall effects. The following set was considered: Integrated Set of 1-10 runs with 7B as the final option selected from the series 7 runs. These are referred to as Run 11D and the Alternate as Alt 11D* in Fig.4 and/or Fig.5 The energy savings from these final simulation models should give an idea of the combined potential of all the strategies listed above. 3. CONCLUSIONS A holistic approach to the problem is an essential step towards understanding the complex relationships between architectural, mechanical, and other design disciplines that play a role in building design. The paybacks of each evaluated measure, if viewed independently, suggests a much different answer than a combination of measures, either in combinations of two or more. The final proposed design is expected to reduce existing building energy consumption by 33%. Daylighting, improved lighting, and plug load optimization represents 58% of the total energy savings. Detailed cost-benefit-analyses suggest a 13-year payback on all measures excluding daylighting, lighting, and plug loads, and a 17-year combined payback Building Exhaust Energy Recovery This strategy proposes to evaluate the effect of using a water-to-air run-around cycle for recovering energy from the building exhaust stream. The energy recovered would be used to pre-cool outside air during the summer seasons and pre-heat during the winter seasons. This model should have been an add-on to #4 Reduction in Outside Air Quantity, but as that strategy is currently on hold, the current model should be compared against the new basecase. This is referred to as Run 10 in Fig.4 and/or Fig Integrated Set 1-10 Runs of combination strategies allowed the design team to understand and compare the effects of individual

Commissioning - Construction Documents (Page 1 of 6)

Commissioning - Construction Documents (Page 1 of 6) Commissioning - Construction Documents (Page 1 of 6) A. General Information Climate Zone: Building Type: Conditioned Area (sf): Reviewer's Name: Reviewer's Agency: Note: Design Review for each system/subsystem

More information

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01 GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per

More information

REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS

REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS Ken L. Hansen P.E. University of Nebraska Medical Center hansenkl@unmc.edu 402-559- 5301 402-630-

More information

The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.

The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building. MSV: Square Footage: 24,844 No. of Floors: 1 Year Built: 1963 Type of Use: Lounge and dining area open all night for snacks Steam Water-cooled condenser, 50-Ton York unit with a 6 cylinder-reciprocating

More information

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks Presentation Outline Common Terms / Concepts HVAC Building Blocks Plant Level Building Blocks Description / Application Data Green opportunities Selection Criteria Air Distribution Building Blocks same

More information

HVAC Systems: Overview

HVAC Systems: Overview HVAC Systems: Overview Michael J. Brandemuehl, Ph.D, P.E. University of Colorado Boulder, CO, USA Overview System Description Secondary HVAC Systems Air distribution Room diffusers and air terminals Duct

More information

Topics for Today. Order of Magnitude Mechanical Estimating. Order of Magnitude Estimate Goal. Project Delivery Methods. Questions for Client

Topics for Today. Order of Magnitude Mechanical Estimating. Order of Magnitude Estimate Goal. Project Delivery Methods. Questions for Client Order of Magnitude Mechanical Estimating Justin Apprill, P.E. Topics for Today Estimate Goals A Concept for Accurate Conceptual Estimating HVAC Systems Common System Types and Rules of Thumb Pricing Example

More information

SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP

SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP research journal 2013 / VOL 05.01 www.perkinswill.com SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP ARCHITECTURE AND ENGINEERING OF SUSTAINABLE BUILDINGS Current Trends in Low-Energy HVAC Design

More information

for K-12 School Buildings

for K-12 School Buildings Advanced Energy Design Guide for K-12 School Buildings HVAC Section John Murphy Applications Engineer, LEED AP Trane La Crosse, Wisconsin jmurphy@trane.com www.trane.com AEDG-K12 HVAC Subcommittee John

More information

HVAC Processes. Lecture 7

HVAC Processes. Lecture 7 HVAC Processes Lecture 7 Targets of Lecture General understanding about HVAC systems: Typical HVAC processes Air handling units, fan coil units, exhaust fans Typical plumbing systems Transfer pumps, sump

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-23 09 93 (November 2015) ----------------------------- Preparing Activity: USACE Superseding UFGS-23 09 23 (May 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

Comparing Energy Savings of Different VAV Systems

Comparing Energy Savings of Different VAV Systems Comparing Energy Savings of Different VAV Systems Prepared By: Martyn Dodd mart@energysoft.com EnergySoft LLC 1025 5th Street, Suite A Novato, CA 94945 415-897-6400 www.energysoft.com Last Modified: March

More information

CHAPTER 8 HVAC (Heating, Ventilation, and Air-Conditioning)

CHAPTER 8 HVAC (Heating, Ventilation, and Air-Conditioning) CHAPTER 8 HVAC (Heating, Ventilation, and Air-Conditioning) Objectives Survey current HVAC system(s), operating procedures, and maintenance schedule. Analyze results of energy audit for HVAC system(s)

More information

Preliminary Final Proposal

Preliminary Final Proposal 1 Butler Memorial Hospital New Inpatient Tower Senior Capstone Project Mechanical Option Preliminary Final Proposal Mechanical System Re-design and Breadth Topics Butler Memorial Hospital New Inpatient

More information

for Plans Examiners and Building Inspectors

for Plans Examiners and Building Inspectors Building Technologies Program HVAC Controls Guide for Plans Examiners and Building Inspectors September 2011 Authors: Eric Makela, PNNL James Russell, PECI Sarah Fujita, PECI Cindy Strecker, PECI Prepared

More information

CONTROL STRATEGIES FOR HVAC SYSTEMS

CONTROL STRATEGIES FOR HVAC SYSTEMS CONROL SRAEGIES FOR HVAC SYSEMS ZBIGNIEW POPIOLEK Department of Heating, Ventilation and Dust Removal echnology Silesian University of echnology, Poland 1 Definition of control: to apply a regulating influence

More information

Example Retrocommissioning Measure: Opening Throttled Discharge Valves

Example Retrocommissioning Measure: Opening Throttled Discharge Valves Opening Throttled Discharge Valves This 21-story building, constructed in 1997, is located in Oregon and contains 589,000 gross square feet of mostly office occupancy. The HVAC system includes six large

More information

AIR COOLED CHILLER CHILLED WATER PUMP CONTROL: The chilled water pump with the lowest runtime will automatically start when the outside air temperature rises above the system enable setpoint. When the

More information

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues Design Guide Retrofitting Options For HVAC Systems In Live Performance Venues Heating, ventilation and air conditioning (HVAC) systems are major energy consumers in live performance venues. For this reason,

More information

1.2 Refrigerant Equipment. General

1.2 Refrigerant Equipment. General Part 1 General 1.1 Summary.1 Unless otherwise indicated, follow the standards below when specifying heating, ventilation and air conditioning (HVAC) work. These standards are not intended to restrict or

More information

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings Advanced Energy Design Guide LEED Strategies for Schools and High Performance Buildings Today s Presenters Stephen Koontz, LEED AP Energy Services Leader Tampa Bay Trane Allen Irvine General Sales Manager

More information

NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES

NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES 8.1 INTRODUCTION Testing, adjusting, and balancing of HVAC systems can best be accomplished by following a series of systematic procedures. The NEBB TAB

More information

SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION

SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION The purpose of this guide specification is to assist the specifier in correctly specifying Mechanical System Testing

More information

SIMULATION OF RADIANT COOLING PERFORMANCE WITH

SIMULATION OF RADIANT COOLING PERFORMANCE WITH SUMMARY REPORT MAY 2008 SIMULATION OF RADIANT COOLING PERFORMANCE WITH EVAPORATIVE COOLING SOURCES Timothy Moore Center for the Built Environment (CBE) University of California, Berkeley May 2008 EXECUTIVE

More information

Impact of Control System Technologies on Industrial Energy Savings

Impact of Control System Technologies on Industrial Energy Savings Impact of Control System Technologies on Industrial Energy Savings Priyam Parikh Industrial Assessment Center Texas A&M University Bryan P. Rasmussen Industrial Assessment Center Texas A&M University http://farolconsulting.com/?page_id=110

More information

Element D Services Heating, Ventilating, and Air Conditioning

Element D Services Heating, Ventilating, and Air Conditioning PART 1 - GENERAL 1.01 OVERVIEW A. This section supplements Design Guideline Element D3041 on air handling distribution with specific criteria for projects involving design of a Data Center spaces B. Refer

More information

Building Energy Systems. - HVAC: Heating, Distribution -

Building Energy Systems. - HVAC: Heating, Distribution - * Some of the images used in these slides are taken from the internet for instructional purposes only Building Energy Systems - HVAC: Heating, Distribution - Bryan Eisenhower Associate Director Center

More information

HVAC Checklist - Long Form

HVAC Checklist - Long Form HVAC Checklist - Long Form Page 1 of 14 Appendix B discusses HVAC system components in relation to indoor air quality. utside Air Intake Location pen during occupied hours? Unobstructed? Standing water,

More information

Tips and Tricks for Estimating Energy Savings. Celeste Cizik, P.E. Project Manager E M C Engineers, Inc.

Tips and Tricks for Estimating Energy Savings. Celeste Cizik, P.E. Project Manager E M C Engineers, Inc. Tips and Tricks for Estimating Energy Savings Celeste Cizik, P.E. Project Manager E M C Engineers, Inc. AIA Quality Assurance Learning Objectives 1. Understand the pros and cons of various energy calculation

More information

Printing and Publishing Energy Savings Guide

Printing and Publishing Energy Savings Guide Printing and Publishing Energy Savings Guide Oregon printing and publishing plants face challenges of rising operating costs, environmental and other regulations, outdated equipment and customer demand

More information

Mechanical Systems Proposal revised

Mechanical Systems Proposal revised Mechanical Systems Proposal revised Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option

More information

EnergyPro Building Energy Analysis. Assisted Living Building

EnergyPro Building Energy Analysis. Assisted Living Building EnergyPro Building Energy Analysis Assisted Living Building EnergyPro Building Energy Analysis for an assisted living building Project Scope The purpose of the EnergyPro energy model was to evaluate the

More information

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM AIR HANDLING UNITS... 1 CHILLERS... 2 COOLING TOWERS... 2 CLOSED LOOP COOLERS... 2 MISCELLANEOUS SUPPLY FANS...

More information

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Prepared for the U.S. Department of Energy s Federal Energy Management Program

More information

Rev. No. 0 January 5, 2009

Rev. No. 0 January 5, 2009 ENERGY & ENVIRONMENTAL ENERGY ISSUES COMMITTEE 415 Main Building Telephone (574) 631-6666 Notre Dame, Indiana Facsimile (574) 631-5883 46556 USA Energy Conservation Plan For HVAC Systems Rev. No. 0 January

More information

newsletter engineers energy-saving strategies for Water-Source Heat Pump Systems volume 36 2 providing insights for today s hvac system designer

newsletter engineers energy-saving strategies for Water-Source Heat Pump Systems volume 36 2 providing insights for today s hvac system designer engineers volume 36 2 newsletter providing insights for today s hvac system designer energy-saving strategies for Water-Source Heat Pump Systems from the editor... Water-source heat pump (WSHP) systems

More information

Raising the Bar: A Comparison Study of Iowa s Current and Proposed Energy Code

Raising the Bar: A Comparison Study of Iowa s Current and Proposed Energy Code Raising the Bar: A Comparison Study of Iowa s Current and Proposed Energy Code Julia Gauthier, LEED AP BD+C Jeanne Huntsman, AIA, LEED Green Associate The Weidt Group Raising the Bar Special statements

More information

SYSTEMS INTEGRATION SYSTEMS INTEGRATION. Air handler uses heat recovery on exhaust air to temper incoming ventilation air Oxbow skylight

SYSTEMS INTEGRATION SYSTEMS INTEGRATION. Air handler uses heat recovery on exhaust air to temper incoming ventilation air Oxbow skylight 100% outside air intake Air handler uses heat recovery on exhaust air to temper incoming ventilation air Oxbow skylight Smoke evacuation Natural convection exhaust Atrium skylight Phase change material

More information

Energy Efficiency Opportunities in Federal High Performance Computing Data Centers

Energy Efficiency Opportunities in Federal High Performance Computing Data Centers Energy Efficiency Opportunities in Federal High Performance Computing Data Centers Prepared for the U.S. Department of Energy Federal Energy Management Program By Lawrence Berkeley National Laboratory

More information

Continuous Energy Management at UC San Diego. Anna Levitt, P.E. Assistant Energy Manager June 13, 2013

Continuous Energy Management at UC San Diego. Anna Levitt, P.E. Assistant Energy Manager June 13, 2013 Continuous Energy Management at UC San Diego Anna Levitt, P.E. Assistant Energy Manager June 13, 2013 UC San Diego: A 42 megawatt Microgrid With a daily population of over 45,000, UC San Diego is the size

More information

Subtropical Cities September 2006. Design for Energy Efficiency in Commercial Buildings in Queensland

Subtropical Cities September 2006. Design for Energy Efficiency in Commercial Buildings in Queensland Subtropical Cities September 2006 Design for Energy Efficiency in Commercial Buildings in Queensland Contents Typical Building Constraints & Requirements Understanding Energy Consumption in Buildings HVAC

More information

CONCEPTUALIZATION OF UTILIZING WATER SOURCE HEAT PUMPS WITH COOL STORAGE ROOFS

CONCEPTUALIZATION OF UTILIZING WATER SOURCE HEAT PUMPS WITH COOL STORAGE ROOFS CONCEPTUALIZATION OF UTILIZING WATER SOURCE HEAT PUMPS WITH COOL STORAGE ROOFS by Dr. Bing Chen and Prof. John Bonsell Passive Solar Research Group University of Nebraska-Lincoln Omaha campus and Richard

More information

Methods for Effective Room Air Distribution. Dan Int-Hout Chief Engineer, Krueger Richardson, Texas

Methods for Effective Room Air Distribution. Dan Int-Hout Chief Engineer, Krueger Richardson, Texas Methods for Effective Room Air Distribution Dan Int-Hout Chief Engineer, Krueger Richardson, Texas Agenda Overview LEED issues and Update Perimeter Acoustics Thermal Comfort IAQ / Standard 62.1 Update

More information

Scope of Work. See www.sei.ie for resources available

Scope of Work. See www.sei.ie for resources available HVAC SWG Summary Background Pool energy-efficiency knowledge Increase cost-competitiveness Develop resources aimed at assisting in reducing HVAC energy consumption Address barriers to energy-saving HVAC

More information

Energy Efficiency HOSPITALITY. www.energia.ie

Energy Efficiency HOSPITALITY. www.energia.ie Energy Efficiency HOSPITALITY www.energia.ie Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could make a real

More information

CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS

CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS By: Michael J. Bitondo, Mark J. Tozzi Carrier Corporation Syracuse, New York August 1999 INTRODUCTION In December of 1998, the American Refrigeration Institute

More information

Commercial & Municipal Retrofit 2015 VFD Rebate

Commercial & Municipal Retrofit 2015 VFD Rebate 2015 VFD Rebate Section A: MEMBER INFORMATION Member Name Electric Account Number Rate Number Facility Address City State Zip Code Service Location Identification Email Mailing Address (if different from

More information

Enclosed Football Stadium Design History and Lessons Learned

Enclosed Football Stadium Design History and Lessons Learned Enclosed Football Stadium Design History and Lessons Learned Robert L. Towell, P.E., LEED AP, QCxP btowell@cxegroup.com CxE Group LLC St. Louis, Missouri 314-436-6543 With thanks to the St. Louis Convention

More information

Automated Commissioning for Energy (ACE) Platform for Large Retail Property. Overview

Automated Commissioning for Energy (ACE) Platform for Large Retail Property. Overview Automated Commissioning for Energy (ACE) Platform for Large Retail Property $62,900 dollars of energy savings identified during the first 6 weeks Overview The ability to pull large amounts of complex data

More information

Circuit breaker panel. Power supply for condensing unit. Power supply for furnace. Air handler (Furnace)

Circuit breaker panel. Power supply for condensing unit. Power supply for furnace. Air handler (Furnace) UNIT OBJECTIVES Describe the concept of year-round air conditioning List three typical year-round air conditioning system types List the five ways to condition the air Determine airflow for a cooling system

More information

HVAC Technologies for Building Energy Efficiency Improvements 2013 National Symposium on Market Transformation. Richard Lord Carrier Fellow

HVAC Technologies for Building Energy Efficiency Improvements 2013 National Symposium on Market Transformation. Richard Lord Carrier Fellow HVAC Technologies for Building Energy Efficiency Improvements 2013 National Symposium on Market Transformation Richard Lord Carrier Fellow HVAC Industry Challenges and Issues Ozone Deletion Global Warming

More information

Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues

Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues LBNL-6129E ERNEST ORLANDO LAWRENCE BERKELEY NATIONAL LABORATORY Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues Liping Wang, Tianzhen Hong Environmental

More information

Section 2: Estimating Energy Savings and Incentives

Section 2: Estimating Energy Savings and Incentives Section 2: Estimating Energy Savings and Incentives 2.1 Estimating Energy Savings and Incentives... 2 2.2 Customized Measures - Estimation Software... 2 2.2.1 AC&R I - High Efficiency Chiller... 3 2.2.2

More information

ENERGY SAVING STUDY IN A HOTEL HVAC SYSTEM

ENERGY SAVING STUDY IN A HOTEL HVAC SYSTEM ENERGY SAVING STUDY IN A HOTEL HVAC SYSTEM J.S. Hu, Philip C.W. Kwong, and Christopher Y.H. Chao Department of Mechanical Engineering, The Hong Kong University of Science and Technology Clear Water Bay,

More information

SAM HOUSTON STATE UNIVERSITY

SAM HOUSTON STATE UNIVERSITY PART 1: GENERAL 1.01 General Requirements A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the

More information

State of the Art Energy Efficient Data Centre Air Conditioning

State of the Art Energy Efficient Data Centre Air Conditioning - White Paper - State of the Art Energy Efficient Data Centre Air Conditioning - Dynamic Free Cooling - Release 2, April 2008 Contents ABSTRACT... 3 1. WHY DO I NEED AN ENERGY EFFICIENT COOLING SYSTEM...

More information

Basics of HVAC Cleaning

Basics of HVAC Cleaning Basics of HVAC Cleaning Seminar Outline Residential 1. Types of systems used and why 2. Types of air distribution systems 3. System components 4. Determining the need for cleaning (ACR2002) 5. Project

More information

CTBUH Copyright. What every tenant wants. Chairman, Jones Lang LaSalle. Dan Probst

CTBUH Copyright. What every tenant wants. Chairman, Jones Lang LaSalle. Dan Probst What every tenant wants Dan Probst Chairman, Jones Lang LaSalle Chicago, USA Industry drivers Converging forces Mass acceptance of global warming, climate change Rising energy prices Widely accepted green

More information

HEATING, VENTILATION & AIR CONDITIONING

HEATING, VENTILATION & AIR CONDITIONING HEATING, VENTILATION & AIR CONDITIONING as part of the Energy Efficiency Information Grants Program Heating and cooling can account for approximately 23 % of energy use in pubs and hotels 1. Reducing heating

More information

Leveraging the Power of Intelligent Motor Control to Maximize HVAC System Efficiency

Leveraging the Power of Intelligent Motor Control to Maximize HVAC System Efficiency Leveraging the Power of Intelligent Motor Control to Maximize HVAC System Efficiency Because HVAC systems comprise a large amount of a building s operating costs, it makes sense to ensure these systems

More information

Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA

Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA Boggarm S. Setty, P.E., Fellow ASHRAE Setty & Associates, Ltd. 3040 Williams Drive, Suite 600, Fairfax,

More information

Cover Page page 1. Table of Contents page 2. Section 1 Introduction page 3. Section 2 Variable Air Volume System Components page 4

Cover Page page 1. Table of Contents page 2. Section 1 Introduction page 3. Section 2 Variable Air Volume System Components page 4 How to Estimate the Cost of a VAV Reheat HVAC System Table of Contents: Cover Page page 1 Table of Contents page 2 Section 1 Introduction page 3 Section 2 Variable Air Volume System Components page 4 Section

More information

University of Maryland s Gossett Field House College Park, MD

University of Maryland s Gossett Field House College Park, MD Presentation Outline Project Background Existing Mechanical System Mechanical Redesign Structural Redesign Electrical Redesign Conclusions & Recommendations Acknowledgements Questions Project Team Owner:

More information

ASTACEA4 Inspect complex/central air conditioning systems

ASTACEA4 Inspect complex/central air conditioning systems Overview This Unit covers the competences required to inspect complex/central air conditioning systems as defined by the CIBSE TM 44 Figure 1.1: Summary of system types and their component parts. The air

More information

Energy Efficiency Tips for Businesses

Energy Efficiency Tips for Businesses Energy Efficiency Tips for Businesses Top 10 Tips Lighting Tips Heating and Cooling Temperature Control Office Equipment Laundry Service Refrigeration Equipment Food Service Equipment Employee Involvement

More information

DIABLO VALLEY COLLEGE CATALOG 2015-2016

DIABLO VALLEY COLLEGE CATALOG 2015-2016 HEATING, VENTILATION, AIR CONDITIONING, REFRIGERATION - HVACR Tish Young, Dean Physical Sciences and Engineering Division Physical Sciences Building, Room 263 Possible career opportunities Upon successful

More information

Heating, Ventilation & Air Conditioning Equipment

Heating, Ventilation & Air Conditioning Equipment FinAnswer Express Utah Incentive Catalog Effective as of May 19, 2012 Heating, Ventilation & Air Conditioning Equipment Rocky Mountain Power provides incentives for many types of energy-efficient technologies.

More information

Energy Efficiency: Integrated Design and HVAC Systems HEALTHCARE - TOP 5 GREEN BUILDING STRATEGIES

Energy Efficiency: Integrated Design and HVAC Systems HEALTHCARE - TOP 5 GREEN BUILDING STRATEGIES EPA Publication 909-F-07-001 What? Energy use in healthcare facilities is higher than nearly all other building types. With rising energy costs and climate change concerns energy efficiency is financially

More information

ASHRAE Student System Selection Competition New Office Building - Nashville, Tennessee Spring 2009

ASHRAE Student System Selection Competition New Office Building - Nashville, Tennessee Spring 2009 ASHRAE Student System Selection Competition New Office Building - Nashville, Tennessee Spring 2009 Kansas State University Department of Architectural Engineering and Construction Science 240 Seaton Hall

More information

HVAC Simplified Approach Option

HVAC Simplified Approach Option HVAC Simplified Approach Option Part I Project Address: City: HVAC System Designer of Record: Date: Zip: Qualification The building is 2 stories or less in height and has a gross floor area is less than

More information

Energy Efficiency in Industrial HVAC Systems

Energy Efficiency in Industrial HVAC Systems Energy Efficiency in Industrial HVAC Systems Heating, ventilation and air conditioning (HVAC) constitutes up to 35 percent of energy used in manufacturing facilities. This fact sheet is geared towards

More information

Riverside City College. Math & Science Building HVAC Investigation. May 23, 2013

Riverside City College. Math & Science Building HVAC Investigation. May 23, 2013 May 23, 2013 Prepared by: P2S Engineering, Inc. 5000 East Spring St, Eighth Floor Long Beach, CA 90815 T 562.497.2999 F 562.497.2990 www.p2seng.com Table of Contents Executive Summary... 2 Background...

More information

Fundamentals of HVAC Control Systems

Fundamentals of HVAC Control Systems ASHRAE Hong Kong Chapter Technical Workshop Fundamentals of HVAC Control Systems 18, 19, 25, 26 April 2007 2007 ASHRAE Hong Kong Chapter Slide 1 Chapter 5 Control Diagrams and Sequences 2007 ASHRAE Hong

More information

HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY

HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY Benson Kwong, CVS, PE, CEM, LEED AP, CCE envergie consulting, LLC Biography Benson Kwong is an independent consultant providing

More information

White Paper #10. Energy Efficiency in Computer Data Centers

White Paper #10. Energy Efficiency in Computer Data Centers s.doty 06-2015 White Paper #10 Energy Efficiency in Computer Data Centers Computer Data Centers use a lot of electricity in a small space, commonly ten times or more energy per SF compared to a regular

More information

Deep Energy Savings in Existing Buildings

Deep Energy Savings in Existing Buildings Case Study Deep Energy Savings in Existing Buildings Overview Site Details Owner: Alliance for Sustainable Colorado Location: Denver, CO Building Type: Office Project Description: Major Renovation Size

More information

Santa Ana College Central Heating & Cooling

Santa Ana College Central Heating & Cooling Santa Ana College Central Heating & Cooling Plant Project # 5807 P2S Engineering, Inc. T 562.497.2999 5000 East Spring Street, 8th Floor F 562.497.2990 Long Beach, CA USA 90815-5218 www.p2seng.com Table

More information

MEETING AGENDA. Project Administrator:

MEETING AGENDA. Project Administrator: MEETING AGENDA Project Administrator: To: Ann Green M. Baker, SLCS C. Bullinger, SLCS R. Clark, SLCS Board C. Cox, SLCS S. Dotinga, Granger J. Graham, SLCS J. Gusick, SLCS, Board C. Hanshaw, SLCS Board

More information

Energy Efficient HVAC-system and Building Design

Energy Efficient HVAC-system and Building Design Energy Efficient HVAC-system and Building Design Maija Virta 1, Harri Itkonen 1, Panu Mustakallio 1, Risto Kosonen 1 1 Halton Oy, Finland Corresponding email: maija.virta@halton.com SUMMARY This paper

More information

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations MECHANICAL SYSTEMS DESIGN STANDARDS Appendix A RECOMMENDED HVAC SYSTEMS BY TYPE OF SPACE Matt Higgins Valentin Lucero

More information

Outline. CC objectives Site and building description Typical data floor overview CC measures Results Lessons learned

Outline. CC objectives Site and building description Typical data floor overview CC measures Results Lessons learned Outline CC objectives Site and building description ypical data floor overview CC measures Results Lessons learned 2 CC Objectives Identify and solve existing operating problems Improve building thermal

More information

Building Performance Evaluation Guide Version 1.7

Building Performance Evaluation Guide Version 1.7 Building Performance Evaluation Guide Version 1.7 Prepared by Center for Energy and Environment January 2014 Minnesota Sustainable Building 2030: Building Performance Evaluation Guide p 1 1. Schematic

More information

NYC Department of Education Building Condition Assessment Survey 2014-2015 BROADWAY EDUCATION CAMPUS - MANHATTAN, 26 BROADWAY, MANHATTAN, NY, 10004

NYC Department of Education Building Condition Assessment Survey 2014-2015 BROADWAY EDUCATION CAMPUS - MANHATTAN, 26 BROADWAY, MANHATTAN, NY, 10004 School: InspectionId Asset Data Inspection Type Building Assessment Survey 204-205 BROADWAY EDUCATION CAMPUS - MANHATTAN, 26 BROADWAY, MANHATTAN, NY, 0004 Time In Last Edited 255 MECHANICAL 205-05-8 09:00AM

More information

DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER

DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER DATA CENTERS 2009 IT Emissions = Aviation Industry Emissions Nations Largest Commercial Consumers of Electric Power Greenpeace estimates

More information

ULTRA-EFFICIENT HVAC DESIGN AND CONTROL

ULTRA-EFFICIENT HVAC DESIGN AND CONTROL CASE STUDY ULTRA-EFFICIENT HVAC DESIGN AND CONTROL MAJOR HEATING, VENTILATING AND AIR- CONDITIONING REPLACEMENT AT THE COUNTY OF SAN DIEGO CRIME LAB December 30, 2005 8520 Tech Way, Suite 110 San Diego,

More information

Energy Efficiency. Bars & RestauRants. www.energia.ie

Energy Efficiency. Bars & RestauRants. www.energia.ie Energy Efficiency Bars & RestauRants www.energia.ie 2 Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could

More information

Dehumidification Design

Dehumidification Design Dehumidification Design Using Data-Center Heat Utilizing free heat from a server room was the concept behind an air-handling system in a college-campus building Considerable energy savings are possible

More information

Lesson 36 Selection Of Air Conditioning Systems

Lesson 36 Selection Of Air Conditioning Systems Lesson 36 Selection Of Air Conditioning Systems Version 1 ME, IIT Kharagpur 1 The specific objectives of this chapter are to: 1. Introduction to thermal distribution systems and their functions (Section

More information

1. What percent of a commercial business s energy usage comes from their HVAC system? A. 13% B. 23% C. 33% D. 43% E. 53%

1. What percent of a commercial business s energy usage comes from their HVAC system? A. 13% B. 23% C. 33% D. 43% E. 53% 1 1. What percent of a commercial business s energy usage comes from their HVAC system? A. 13% B. 23% C. 33% D. 43% E. 53% 2. How much money do commercial facilities spend per square foot on energy costs

More information

In the compression-refrigeration loop (air conditioning), which is likely to be warmer? 1. Condenser coil 2. Evaporator coil

In the compression-refrigeration loop (air conditioning), which is likely to be warmer? 1. Condenser coil 2. Evaporator coil In the compression-refrigeration loop (air conditioning), which is likely to be warmer? 1. Condenser coil 2. Evaporator coil Answer: (1) Condenser coil See the video. A.R.E. Building Systems Study Guide

More information

BSD Technical Standard Division 23: HVAC

BSD Technical Standard Division 23: HVAC Division 23: HVAC I. PURPOSE This technical standard is a narrative describing Beaverton School District s (BSD s) Basis of Design for mechanical systems and heating, ventilation, and air conditioning

More information

Defining Quality. Building Comfort. Precision. Air Conditioning

Defining Quality. Building Comfort. Precision. Air Conditioning Defining Quality. Building Comfort. Precision Air Conditioning Today s technology rooms require precise, stable environments in order for sensitive electronics to operate optimally. Standard comfort air

More information

Air Conditioning. The opportunity for energy efficiency. Low cost actions to reduce energy usage now

Air Conditioning. The opportunity for energy efficiency. Low cost actions to reduce energy usage now Fact Sheet #6 Air Conditioning In this fact sheet you will discover: The opportunity for energy efficiency How air conditioning works Low cost actions to reduce energy usage now Investments to reduce costs

More information

Bring the fresh in. Dedicated Outside Air Systems

Bring the fresh in. Dedicated Outside Air Systems Bring the fresh in. Dedicated Outside Air Systems The inside story on outside air. On average, we breathe in 3,400 gallons of air each day. Ambient indoor air pollution is a major problem, affecting health

More information

HVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget

HVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget A PRIMER Educational HVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget Contents: Introduction: The best HVAC system is durable, reliable

More information

Tim Sisson - Trane HVAC OVERVIEW

Tim Sisson - Trane HVAC OVERVIEW Tim Sisson - Trane HVAC OVERVIEW HVAC Systems System Types Acoustics Controls Modernization more than one Down to the Studs Opportunity for new System Type Renovation Possible opportunity for new System

More information

Energy-Efficient Laboratory Design

Energy-Efficient Laboratory Design 2005, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Reprinted by permission from ASHRAE Journal, (Vol. 47, No. 5, May 2005). This article may not be

More information

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT Presentation Synopsis Heating, Ventilating and Air Conditioning Building Condition Assessment Vancouver, B.C. Prepared for: EPIC Prepared by: Douglas Spratt, P.Eng Douglas Spratt & Associates Ltd. www.dspratt-associates.com

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

The sample report format is applicable to many different building types and systems and the examples provided cover a variety of applications.

The sample report format is applicable to many different building types and systems and the examples provided cover a variety of applications. Purpose Power Smart s Minimum Requirements for an Energy Study (see Appendix) provides a comprehensive list of the basic elements which must be included in an Energy Study Report. The intent of this sample

More information