Government Contracting and Earned Value Management (EVM)

Size: px
Start display at page:

Download "Government Contracting and Earned Value Management (EVM)"

Transcription

1 Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine Company, LLC a CSC company, and may not be reproduced in any form without express written consent. 1

2 What is Earned Value Management? A project management methodology that integrates scope, cost and schedule Objective measure of progress against the PMB (Performance Measurement Baseline) Traditional way of determining if you are over or under budget is to compare Budget versus Actual Earned Value asks the missing question: What did I get done? Compares Performance against Budget to identify Schedule Variances Compares Performance against Actuals to identify Cost Variances Also identifies Variances at Completion 2

3 Benefits of Earned Value Management Quantifies and objectively measures work accomplished Early warning system regarding deviations from the baseline Use of common metrics and performance indicators Mitigation of risks associated with cost and schedule overruns Analysis of variances Means to forecast final cost and schedule outcomes Provides and improves the accuracy of revenue, profit and billing plans 3

4 History of Earned Value Management Late 1800s: Planned, earned and actual standards terminology used in manufacturing industry 1950s: Cost Variance used by industrial engineers 1962: - Implementation of PERT resulted in 11 reporting formats, including cost of work report PERT = program evaluation and review technique 1967: Cost/Schedule Control Systems Criteria (C/SCSC) Effort led by U.S. Air Force; Department of Defense (DoD) implemented 35 Criteria for work over certain funding thresholds Poor feedback, refusal of private industry to adopt the C/SCSC system 1996 present: Criteria was revised down to 32 and ANSI/EIA-748 officially issued in 1998 Adopted by DoD in

5 What is ANSI/EIA-748? American National Standards Institute/Electronic Industries Alliance It is an industry standard published by the GEIA (Government Electronics and Information Technology Association) Recognized by the DoD since 1999, for use on defense acquisition programs 32 management control guidelines or criteria for an EVMS Best business practices at a high level Each EVMS has to be tailored to the organization s business environment and management style Must still meet the intent of each guideline ANSI clearly states that it is a guide 5

6 EVM vs. EVMS? Earned Value Management (EVM) The methodology of integrating scope, schedule and cost Example: Our company utilizes Earned Value Management. Earned Value Management System (EVMS) Integrated Management System that is compliant with the 32 EVMS Guidelines per ANSI/EIA-748 Processes and procedures, software tools, databases Example: We have a validated EVMS. 6

7 What are the 32 EVMS Guidelines? They fit into five subsystems or processes: Organization Define the contractual scope of work Identify work within the framework of a Work Breakdown Structure (WBS) Authorize the work Planning, Scheduling and Budgeting Plan, schedule and budget the work Authorize the work (can fit into more than one process) Establish the performance measurement baseline (PMB) Manage the control account Accounting Considerations Accumulate costs of work and materials 7

8 What are the 32 EVMS Guidelines? They fit into five subsystems or processes: (Cont d) Analysis and Management Reports Compare planned and actual costs to accomplishments and analyze variances Act on variance analysis Prepare explanations/supporting rationale for variances to management Revisions and Data Maintenance Prepare plans to achieve workarounds due to variances Baseline changes as applicable Update Estimate to Complete (ETC) Incorporate changes and develop an Estimate at Completion (EAC) Note: Some guidelines fit into more than one process! 8

9 How does EVM relate to Project Management? Project Management Cycle: Earned Value Management Processes: Initiate Plan Execute Control Close out Organizing and Authorization Planning, Scheduling and Budgeting Accounting Considerations Analysis and Management Reports EARNED VALUE MANAGEMENT Revisions and Data Maintenance This makes sense since EVM is a project management methodology! 9

10 When and Why is Earned Value Required? When: Dictated by contract, or Could be an internal requirement (management or internal policy) Why: OMB Circular No. A-11 (2004, last updated 09), Part 7 Section 300 Office of Management and Budget (Executive Office of the President of the United States) Policy applies to ALL federal agencies of the Executive Branch of the Government subject to the Executive Branch Review all major acquisitions with development effort (not just DoD) Part of their annual budget submission Section 300-8: Agencies must use a performance-based acquisition management or earned value management system, based on the ANSI/EIA Standard 748, to obtain timely information regarding the process of capital investments 10

11 How do You Know if it s in the Contract? DFARS vs. FAR Clauses Department of Defense: DFARS clauses Notice of Earned Value Management System DFARS Earned Value Management System DFARS Federal Government Agencies: FAR clauses FAR Rule effective July 5, 2006 implement EVMS policy in accordance with OMB Circular A-11 (from 2004) Notice of Earned Value Management System FAR & FAR Earned Value Management System FAR Note: OMB states Agencies can develop own provisions and clauses for their own use as long as they are substantially the same as in the FAR (example, HHS has its own clauses) 11

12 Earned Value Management Application (DoD) Thresholds Thresholds revised 2005 Applies to both Contractor and Subcontractor (Per DoD Instruction , Dec 8, 2008, Page 44 EVM Implementation Policy, regarding Operation of the Defense Acquisition System): Cost/incentive contracts > $50M Compliance with EVM guidelines in ANSI/EIA-748 Formally validated and accepted EVMS CPR (Contract Performance Report) Monthly IMS (Integrated Master Schedule) Monthly CFSR (Contract Funds Status Report) Quarterly CWBS Data Item per DiD DI-MGMT-81334C Subcontractor EVMS Flowdown IBR (Integrated Baseline Review) Within 180 days of Contract Award, exercise of options, and major modifications 12

13 Earned Value Management Application (DoD) Thresholds (cont d) Cost/incentive contracts <$50M but >$20M Compliance with the EVM guidelines in ANSI/EIA-748 but no formal EVM System Validation required CPR, IMS both tailored CFSR and CWBS Subcontractor EVMS flow-down IBRs (same as above) Cost/incentive contracts <$20M Discretion of the government Program Manager (PM) FFP Contracts regardless of $ value Discouraged, limited use Except developmental work where cost/schedule visibility is required, and contract is >$20M Need a waiver from government PM 13

14 EVMS Flowdown to Subcontractors (DoD) DFARS Notice of EVMS Section (c): The offeror shall identify the subcontractors (or the subcontracted effort if subcontractors have not been selected) to whom the EVMS requirements will apply. The offeror and the Government shall agree to the subcontractors or the subcontracted effort selected for application of the EVMS requirements. The offeror shall be responsible for ensuring that the selected subcontractors comply with the requirements of the Earned Value Management System clause of the contract. 14

15 EVMS Flowdown to Subs (DoD) (cont d) DFARS EVMS Section (h): The Contractor shall require its subcontractors to comply with EVMS requirements as follows: (1) For subcontracts valued at $50,000,000 or more, the following subcontractors shall comply with the requirements of this clause: [Contracting Officer to insert names of subcontractors (or subcontracted effort if subcontractors have not been selected) designated for application of the EVMS requirements of this clause.] (2) For subcontracts valued at less than $50,000,000, the following subcontractors shall comply with the requirements of this clause, excluding the requirements of paragraph (b) of this clause: [Contracting Officer to insert names of subcontractors (or subcontracted effort if subcontractors have not been selected) designated for application of the EVMS requirements of this clause.] 15

16 HHS Clauses and Thresholds Acquisition Policy Memorandum No , October 1, 2008: Interim acquisition guidance.specific implementation parameters for the application of EVM to contracts issued by HHS, consistent with the flexibility and discretion allowed by the FAR. Strengthened the existing HHSAR clauses Health and Human Services Acquisition Regulation The EVMS clauses are HHSAR , 2, 3 & 4 Not yet formally incorporated into the HHSAR (as of April 26, 2010) 16

17 Earned Value Management Application Thresholds (HHS) HHS Policy &4 (Full & Partial EVMS): (For major acquisitions per the OMB Circular A-11) Cost reimbursement/fixed Price Incentive Contracts: >$25M: Full EVM required Contractor s EVMS must be validated and accepted by the CFA (Cognizant Federal Agency) = DCMA >$10M: Full EVM required Contractor s EVMS must comply with ANSI/EIA-748 Firm Fixed Price & Time and Material: >$25M: Partial EVM required (Schedule only) Contractor s EVMS must be validated and accepted by the CFA (Cognizant Federal Agency) >$10M: Partial EVM required (Schedule only) Contractor s EVMS must comply with ANSI/EIA-748 Any type contract <$10M: Optional with HCA prior approval (Head of the Contracting Activity) 17

18 HHS Thresholds (cont d) Note that HHS thresholds requiring a validated EVMS are less than the DoD s! $25M versus $50M Look to see which policy or clause is referenced in the RFP Might reference HHS Policy Document Number HHS-OCIO dated 6/11/07 instead of HHSR clauses For HHS IT Contracts (originally established in 2005) Established three (3) tiers for EVMS Tier 1 was >$10M Compliant EVMS (needs to be certified as compliant) but not validated States that when changes occur to the HHSAR, HHS will apply EVM requirements in accordance with the most recent HHSAR rule Reminder: the EVMS HHSAR clauses are not yet formally incorporated into the HHSAR (as of 4/26/10), yet they are official interim acquisition guidance. 18

19 For any RFP and/or Contract from any Government Agency. You need to ensure You understand the government Request for Proposal (RFP) and what is being asked You understand the subcontractor EVMS flowdown requirements Make sure potential subcontractors understand and bid accordingly If the cumulative value over the life of the subcontract breaches a threshold, they automatically fall under those threshold requirements. Final Blanket Ordering Agreements (BOAs) and other subcontractor agreements are worded correctly Incorporate language that indicates the threshold levels for different types of reporting and the requirements 19

20 For any RFP and/or Contract from any Government Agency. (cont d) If an organization does not have a compliant or validated EVMS at the time they bid on an RFP, they need to include a plan for becoming compliant/validated Government may not pay for this expense You also want to ensure the final government contract reads correctly (all clauses are there, etc.) 20

21 Who is responsible for reporting Earned Value? The Contractor Program Manager manages and reports program performance based on input from resources managing the detailed program work Program Manager s name is on the official CDRLs CDRL = Contract Data Requirement List per the contract CAMs are responsible for Cost and Schedule for their assigned Control Accounts CAM = Control Account Manager CAMs are typically assisted by Financial Analysts and/or Project Control Analysts in maintaining the EVMS tool and generate the CDRL s to the government Other organizational functions that have a hand in the Earned Value data? Includes at a minimum: Functional groups Project manager Technical lead 21

22 Government Roles and Responsibilities DoD Contracts: Office of the Under Secretary of Defense Develop, publish and maintain DoD policy and guidance on EVM Changes to the DFARS Oversee DCMA enforcement of EVMS compliance Work with Defense Acquisition University (DAU) regarding training needs and course curricula DCMA Defense Contracting Management Agency Conduct EVMS Surveillance reviews for initial and continued compliance with the ANSI/EIA-748 Formally accept (validate) a compliant EVMS on behalf of DoD Also involved in audits on HHS Contracts (CFA = Cognizant Federal Agency) 22

23 Government Roles and Responsibilities (cont d) DCAA Defense Contracting Audit Agency Periodic reviews of supplier s Accounting Systems and EVMS in support of DCMA EVMS Surveillance Audits 14 of the 32 EVMS Guidelines in the ANSI have to do with indirect cost/accounting, and therefore fall under DCAA Note: The DCMA surveillance audit cannot be completed unless DCAA performs their portion of the audit Other government agencies: Seem to rely on DoD a lot regarding policy, guidance and training DoD has many more years experience with EVMS requirements DAU (Defense Acquisition University) courses Rely on the CFA = Cognizant Federal Agency for compliance validation of Contractors DCMA and DCAA 23

24 System Description Validation System Description explains how an organization interprets and adheres to the 32 EVMS guidelines For a new contract: Contractor develops a draft/preliminary System Description DCMA performs a Pre-Assessment Visit (PAV) approximately 6-8 months after contract start DCMA follows up with a Validation Review (VR) of the System Description During this time, an updated System Description may be issued by the Contractor, and any recommendations/corrective actions are also addressed by the Contractor When a VR has been performed, DCMA issues a letter to the Contractor stating the system is validated DCMA provides an Advance Agreement which identifies which System Description is validated, and establishes the Joint Surveillance Review process Subsequent successful DCMA Surveillance Audits result in a follow-up letter from DCMA stating that the Contractor s EVMS is compliant and valid. 24

25 System Description Validation (cont d) DCMA Surveillance Audit end-of year assessments: Contractor is found to be one of the following: Compliant: The contractor s EVMS is compliant with their System Description on all 32 Guidelines Non-compliant: The contractor s EVMS is non-compliant with their System Description on any of the 32 Guidelines Non-compliance can lead to losing the contract Unassessed: The contractors EVMS is unassessed This means that at least one of the 32 guidelines may not have been audited, resulting in the entire EVMS being considered unassessed Does not mean that the contractor is non-compliant or that there are any issues with the EVMS 25

26 Policies, Processes and Procedures Highly recommended that the organization develop formal processes and procedures for their EVMS System Description can be detailed and contain these processes and procedures, but any change to a small process may then result in a need to update the entire System Description Changes to the System Description require DCMA approval It is recommended that the organization develop Policies and SOPs outside of the System Description Internal change control Quicker and easier to implement Also desktop procedures for step-by-step procedures All processes and procedures are subject to Auditor review DCMA & DCAA Customer review (Joint surveillance involves the customer) 26

27 DynPort s Experience with Biotech Government Contracting and an EVMS Prime contractor since 1997 on a DoD Biotechnology vaccine program requiring a validated EVMS DVC s EVMS was validated in 1999 then again in 2004 In-house EVMS expertise totaling more than 40 years in Earned Value Management Two EVP certified employees EVP: Earned Value Professional Certification issued by AACEI (the Association for the Advancement of Cost Engineering International) Seven-hour, four-part exam On average, only 50% of students pass Total of five DCMA Surveillance Audits on this prime contract and two DCAA System and Surveillance Audits Generation of audit requests for information (RFIs) and data packages 27

28 DynPort s Experience with Biotech Government Contracting and an EVMS (cont d) Ongoing internal Surveillance Audits by the Corporate EVM group System Description generation and updates Internal Policies and Procedures directly related to EVMS processes 10 years experience with the EVMS Software tool MPM (owned by Deltek) Expert knowledge of the 32 Guidelines as described in the ANSI/EIA-748 Industry Standard DVC can assist with financial reporting and requirements for the DoD or other government agencies, including EVMS. 28

29 EVMS: We Can Help DVC can assist with your financial reporting/requirements for government contracts, including EVMS. Ask us how! DVC Communications (we ll connect you with the right person) (April Finnen) Main phone:

July 6, 2015 11(1) CHAPTER 11

July 6, 2015 11(1) CHAPTER 11 July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111

More information

Defense Logistics Agency INSTRUCTION

Defense Logistics Agency INSTRUCTION Defense Logistics Agency INSTRUCTION DLAI 2105 Effective May 13, 2013 SUBJECT: Earned Value Management (EVM) Systems Performance, Oversight, and Governance Referenses: (a) DLA Instruction 2105, Earned

More information

How To Write Ansi/Eia Evm System Acceptanceance Guide

How To Write Ansi/Eia Evm System Acceptanceance Guide National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA 748 Earned Value Management System Acceptance Guide Working Release For User Comment January 23, 2006

More information

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing

More information

FOREWORD. Page 2 of 88

FOREWORD. Page 2 of 88 FOREWORD Earned Value Management (EVM) is one of the DoD s and industry's most powerful program management tools. Government and industry program managers use EVM to assess cost, schedule and technical

More information

NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook

NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook NASA/SP-2012-599 Earned Value Management (EVM) Implementation Handbook National Aeronautics and Space Administration NASA Headquarters Washington, D.C. 20546 February 2013 NASA STI Program... in Profile

More information

IT Baseline Management Policy. Table of Contents

IT Baseline Management Policy. Table of Contents Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...

More information

DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219

DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PSP 730.8.B.1/2010-003 February 18, 2011 11-PSP-003(R) MEMORANDUM

More information

DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System

DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System Breakout Session A Alfred J. Massey, Western Region, Special Programs Manager,

More information

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program

More information

Department of Defense MANUAL

Department of Defense MANUAL Department of Defense MANUAL NUMBER 5000.04-M-1 November 4, 2011 CAPE SUBJECT: Cost and Software Data Reporting (CSDR) Manual References: See Enclosure 1 1. PURPOSE. This Manual: a. Reissues DoD 5000.04-M-1

More information

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor

More information

AF Life Cycle Management Center

AF Life Cycle Management Center AF Life Cycle Management Center Subcontract Pricing Shannon Prince AFLCMC/PZF Wright-Patterson AFB 24 March 2014 Overview Intro to Subcontracts Pertinent Thresholds PCO & Prime Responsibilities Prime Analysis

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)

More information

EVM Contract Requirements Toolkit

EVM Contract Requirements Toolkit Center for Earned Value Management To make Naval Acquisition the Standard of Excellence in Government EVM Contract Requirements Toolkit Director, Center for Earned Value Management March 2008 Notice: The

More information

THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010

THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010 THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010 ACQUlsmON, TECHNOLOGY AND LOG ISTICS AUG 1 0 2011 MEMORANDUM FOR SECRETARIES OF THE MILITARY DEPARTMENTS CHAIRMAN OF THE JOINT

More information

Monitoring Subcontracts. The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations

Monitoring Subcontracts. The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Monitoring Subcontracts The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Subcontracts What should a contractor know about subcontracting:

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Training Seminars. Description. Core Courses: The core courses consist of the following:

Training Seminars. Description. Core Courses: The core courses consist of the following: Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals

More information

STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers

STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers Answers to questions submitted, but not included in this set of Q&As,will be provided in a subsequent posting of Q&As in the near future. As the

More information

Project Reviews Lessons Learned Presented by: Kellie Cloud, PMP, PMI SP, PMI RMP, EVP

Project Reviews Lessons Learned Presented by: Kellie Cloud, PMP, PMI SP, PMI RMP, EVP Project Reviews Lessons Learned Presented by: Kellie Cloud, PMP, PMI SP, PMI RMP, EVP Project Management Institute WDC Chapter Chantilly Luncheon 10 March 2011 Topics of Discussioni Best Practices and

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

CHAPTER 8. Table of Contents

CHAPTER 8. Table of Contents July 29, 2015 8(1) Paragraph CHAPTER 8 Table of Contents 8-000 Cost Accounting Standards Page 8-001 Scope of Chapter... 801 8-100 Section 1 --- Overview - Cost Accounting Standards Board (CASB) Rules and

More information

DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule

DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule DOECAA Spring Conference Presentation Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule Mary Karen Wills, CPA Director/Leader, BRG Government Contracts 2014 Berkeley Research Group

More information

IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?

IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? 1 IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? Presented at The Nexus of Agile Software Development and Earned Value Management, OSD-PARCA, February 19 20, 2015 Institute for Defense Analysis, Alexandria,

More information

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by: Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you

More information

Internal Surveillance

Internal Surveillance Page 1 of 18 Internal Surveillance A contract having Earned Value Management System (EVMS) requires the contractor to maintain an effective management control system consistent with EVM industry standards

More information

DCAA Our Role. Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE. Page 1. DCAA 1965-2015: Celebrating 50 Years of Excellence

DCAA Our Role. Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE. Page 1. DCAA 1965-2015: Celebrating 50 Years of Excellence DCAA Our Role Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE DCAA 1965-2015: Celebrating 50 Years of Excellence Page 1 Topics About DCAA Typical DCAA Audits for Small Businesses Basic Roles of

More information

2014 Technical Data Rights Forum

2014 Technical Data Rights Forum 2014 Technical Data Rights Forum Technical Data Rights Challenges from the Small Business Perspective Moderator: Holly Emrick Svetz, Womble Carlyle Alison Brown, NAVSYS Corporation Devon Elizabeth Hewitt,

More information

PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS

PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS Guiding Principle: Sound planning and management of DOE s contracts for the acquisition of projects are essential to the success of the Department

More information

Earned Value Management Knowledge Sharing

Earned Value Management Knowledge Sharing www.pwc.com Earned Value Management Knowledge Sharing IFS Customer Summit 2011 Laura Ayres April 12, 2011 Agenda - EVM Defined - EVM Regulatory Requirements & Industry Standards - Current EVM Environment

More information

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT 1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between

More information

Master Document Audit Program. Version 1.5, dated September 2015 B-01 Planning Considerations

Master Document Audit Program. Version 1.5, dated September 2015 B-01 Planning Considerations Activity Code 11070 Version 1.5, dated September 2015 B-01 Planning Considerations Accounting System Audit Audit Specific Independence Determination Members of the audit team and internal specialists consulting

More information

Case Study. An example of a new government contract award to a private sector company required to demonstrate ANSI-748 Compliance

Case Study. An example of a new government contract award to a private sector company required to demonstrate ANSI-748 Compliance Case Study An example of a new government contract award to a private sector company required to demonstrate ANSI-748 Compliance Executive Summary Managing a government contract with ANSI-748 Earned Value

More information

Cost and Software Data Reporting Training

Cost and Software Data Reporting Training Cost and Software Data Reporting Training Contracting for CSDRs October 16, 2012 Contracting Begins 60 days prior to RFP release CSDR IPT Contractor Data Reporting Structure Resource Distribution Table

More information

Earned Value Management and Professional Services Automation

Earned Value Management and Professional Services Automation Earned Value Management and Professional Services Automation Prepared by: Frances B. Craig Unanet Technologies www.unanet.com 1 of 5 Earned Value Management and Professional Services Automation Earned

More information

Truth in Negotiations Act (TINA) Essentials

Truth in Negotiations Act (TINA) Essentials Truth in Negotiations Act (TINA) Essentials Brent Calhoon, CPA and Jamie Sybert Date: June 5, 2012 Time: 12pm - 1:30pm Eastern Discussion Topics Introductions Truth in Negotiations Act (TINA) Background

More information

Audit Issues In Government Subcontracting

Audit Issues In Government Subcontracting Audit Issues In Government Subcontracting Breakout Session E Brent A. Calhoon, CPA, Partner, Baker Tilly Virchow Krause, LLP Janie L. Maddox, CPCM, Fellow, Thursday, March 27 1:30pm 2:45pm Agenda 1. Introductions

More information

Accounting System Requirements

Accounting System Requirements Accounting System Requirements Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily

More information

Federal Regulatory Compliance Best Practices Washington Technology Webcast. September 27, 2012

Federal Regulatory Compliance Best Practices Washington Technology Webcast. September 27, 2012 Federal Regulatory Compliance Best Practices Washington Technology Webcast September 27, 2012 Agenda Topic Minutes Regulatory compliance overview 5 Major areas of financial compliance risk 15 Best practices

More information

Earned Value Management: Not Just for the Big Guns Anymore

Earned Value Management: Not Just for the Big Guns Anymore Earned Value Management: Not Just for the Big Guns Anymore January 15, 2008 Aronson & Company Government Contract Solutions Group 805 King Farm Boulevard, Suite 300 Rockville, Maryland 20850 301.231.6200

More information

HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)

HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC) Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise

More information

What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008

What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008 What Does the Government Want from Project Management? DC PMI Chapter Executive Breakfast Series January 16, 2008 The Government Wants from Project Management A project management process and culture in

More information

Current Initiatives May 2015

Current Initiatives May 2015 DHG 20 th Annual Government Contracting Update Current Initiatives May 2015 Mr. Ken Saccoccia Deputy Director Page 1 One Agency One Mission DCAA Overview Priorities and Better Buying Power Small Business

More information

CONTACT: 1. Proposed rule BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE

CONTACT: 1. Proposed rule BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE By Eric Sobota, Kelley Doran and Barron Avery Contractors that work for the Department of Energy (DOE) under agreements

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

What Exactly is an Acceptable Accounting System?

What Exactly is an Acceptable Accounting System? What Exactly is an Acceptable Accounting System? Kristen Soles, CPA Member Stephanie Widzinski, CPA Senior Manager September 27, 2012 Agenda Review DFARS Business System Rule What Agency is Responsible

More information

Risk Mitigation and Subcontract Management

Risk Mitigation and Subcontract Management Risk Mitigation and Subcontract Management Breakout Session # C13 Danielle Carr, MSM Program Acquisitions, HMS Technologies Stacey B. Dey-Foy Director Suspension & Debarment, EPA July 28, 2014 @ 4:00pm

More information

Services Contracts and Earned Value Management (EVM)

Services Contracts and Earned Value Management (EVM) Services Contracts and Earned Value Management (EVM) National Defense Industrial Association 2111 Wils on Blvd, Suite 400 Arlington, VA 22201 www.ndia.org February 17, 2010 www.ndia.org 2010 National Defense

More information

EARNED VALUE MANAGEMENT SYSTEMS (EVMS)

EARNED VALUE MANAGEMENT SYSTEMS (EVMS) NOT MEASUREMENT SENSITIVE DOE G 413.3-10 XX-XX-08 EARNED VALUE MANAGEMENT SYSTEMS (EVMS) [This Guide describes suggested nonmandatory approaches for meeting requirements. Guides are not requirements documents

More information

INSTRUCTION NUMBER 7640.02 August 22, 2008

INSTRUCTION NUMBER 7640.02 August 22, 2008 Department of Defense INSTRUCTION NUMBER 7640.02 August 22, 2008 IG DoD SUBJECT: Policy for Follow-up on Contract Audit Reports References: See Enclosure 1 1. PURPOSE. This Instruction: a. Reissues DoD

More information

Cost and Software Data Reporting (CSDR) Manual

Cost and Software Data Reporting (CSDR) Manual DoD 5000.04 M 1 Cost and Software Data Reporting (CSDR) Manual April 18, 2007 Cost Analysis Improvement Group FOREWORD This Manual reissues DoD 5000.4-M-1 (Reference (a)) pursuant to the authority of DoD

More information

TC-UPDATE (11/10) 52.222-39 252.204-7009. 12. Requirements Regarding Potential Access to Export-Controlled Items

TC-UPDATE (11/10) 52.222-39 252.204-7009. 12. Requirements Regarding Potential Access to Export-Controlled Items TC-UPDATE (11/10) The following updates reflect changes to various provisions and clauses of U.S. Government acquisition regulations, including the Federal Acquisition Regulations (FAR) and the Department

More information

Government Contractor Business Systems and Overview of System Assessments

Government Contractor Business Systems and Overview of System Assessments Government Contractor Business Systems and Overview of System Assessments Agenda Overview of business systems rules and environment today 3 rd party assessments Practical solutions Contractor perspective

More information

Developing Work Breakdown Structures

Developing Work Breakdown Structures Developing Work Breakdown Structures International Cost Estimating & Analysis Association June 2014 Neil F. Albert MCR, LLC nalbert@mcri.com 703-506-4600 2014 MCR, LLC Distribution prohibited without express

More information

Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012

Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012 Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012 1 Panelists Robert A. ( Rob ) Burton, Partner, Venable LLP A 30-year veteran

More information

Scheduling Process Maturity Level Self Assessment Questionnaire

Scheduling Process Maturity Level Self Assessment Questionnaire Scheduling Process Maturity Level Self Assessment Questionnaire Process improvement usually begins with an analysis of the current state. The purpose of this document is to provide a means to undertake

More information

INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7

INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7 INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically

More information

Is Your Accounting System Making the Grade? Attributes of an Acceptable Accounting System April 26, 2012

Is Your Accounting System Making the Grade? Attributes of an Acceptable Accounting System April 26, 2012 Is Your Accounting System Making the Grade? Attributes of an Acceptable Accounting System April 26, 2012 2012 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland 20850 301.231.6200

More information

Department of Defense INSTRUCTION

Department of Defense INSTRUCTION Department of Defense INSTRUCTION NUMBER 3204.01 August 20, 2014 USD(AT&L) SUBJECT: DoD Policy for Oversight of Independent Research and Development (IR&D) References: See Enclosure 1 1. PURPOSE. This

More information

Department of Defense INSTRUCTION

Department of Defense INSTRUCTION Department of Defense INSTRUCTION NUMBER 7640.02 April 15, 2015 IG DoD SUBJECT: Policy for Follow-Up on Contract Audit Reports References: See Enclosure 1 1. PURPOSE. This instruction reissues DoD Instruction

More information

TOPIC 12 CONTRACT COST AND PRICE ANALYSIS

TOPIC 12 CONTRACT COST AND PRICE ANALYSIS CONTRACT AUDIT GUIDE FRAMEWORK TOPIC 12 CONTRACT COST AND PRICE ANALYSIS Objective To determine whether the agency effectively conducts cost or price analysis to arrive at fair and reasonable prices for

More information

PEP TALK. Policy EVMS - PARS. Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition

PEP TALK. Policy EVMS - PARS. Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition 2015 Department of Energy Acquisition and Project Management Workshop Federal Stewardship Providing the Value Proposition PEP TALK Policy EVMS - PARS Melvin Frank Chief, Project Systems Division/MA-632

More information

OMB Uniform Guidance Procurement Standards Pilot Worthy?

OMB Uniform Guidance Procurement Standards Pilot Worthy? Federal Demonstration Partnership May 13, 2014 OMB Uniform Guidance Procurement Standards Pilot Worthy? Prepared by: Office of Naval Research Debbie Rafi, Director, University Business Affairs Abe Sabbag,

More information

INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006

INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 1. MANAGEMENT REVIEWS The contractor should have policies and procedures for periodic monitoring of the billing

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

Pre-Award Accounting Systems

Pre-Award Accounting Systems Pre-Award Accounting Systems 2013 National SBIR Conference Christopher Andrezze, CPA Special Assistant to the Deputy Director May 16, 2013 The views expressed in this presentation are DCAA's views and

More information

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office

More information

How To Audit A Government Contractor

How To Audit A Government Contractor Activity Code 17740 Version 6.11, dated November 2015 B-1 Planning Considerations Preaward Survey of Prospective Contractor Accounting System Audit Specific Independence Determination Members of the audit

More information

The Program Managers Guide to the Integrated Baseline Review Process

The Program Managers Guide to the Integrated Baseline Review Process The Program Managers Guide to the Integrated Baseline Review Process April 2003 Table of Contents Foreword... 1 Executive Summary... 2 Benefits... 2 Key Elements... 3 Introduction... 4 IBR Process Overview...

More information

EDWARDS PROJECT SOLUTIONS NORTH AMERICAN INDUSTRY CERTIFICATION SYSTEM (NAICS) CODES QUALIFICATIONS WITH FULL DESCRIPTIONS

EDWARDS PROJECT SOLUTIONS NORTH AMERICAN INDUSTRY CERTIFICATION SYSTEM (NAICS) CODES QUALIFICATIONS WITH FULL DESCRIPTIONS REVISED: J 5523920 PORTFOLIO MANAGEMENT SIZE STANDARD: $7.0M Edwards Project Solution ( ) provides portfolio management services through building enterprise project management solutions and providing portfolio

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

NCMA MEETING PREPARING FOR A DCAA PRICE PROPOSAL AUDIT JUNE 8, 2011

NCMA MEETING PREPARING FOR A DCAA PRICE PROPOSAL AUDIT JUNE 8, 2011 NCMA MEETING 1 PREPARING FOR A DCAA PRICE PROPOSAL AUDIT JUNE 8, 2011 Denise M. Hunt DCAA LM Mt. Laurel Resident Office Forward Pricing Technical Specialist DCAA OVERVIEW AND PRICE PROPOSAL AUDIT PROCESS

More information

Contractor Purchasing System Reviews (CPSRs)

Contractor Purchasing System Reviews (CPSRs) Contractor Purchasing System Reviews (CPSRs) San Diego Chapter on February 17, 2010 Panel members: Carl DeWoody Dan Kearney Lil Smith Jim Southerland Facilitator: Maurice Caskey 1 Outline Introduction

More information

Accounting System. Page 1 of 9

Accounting System. Page 1 of 9 Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems

More information

Report No. DoDIG-2012-081 April 27, 2012. Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support

Report No. DoDIG-2012-081 April 27, 2012. Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support Report No. DoDIG-2012-081 April 27, 2012 Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support Additional Copies To obtain additional copies of this

More information

Using Earned Value Management Concepts to Improve Commercial Project Performance

Using Earned Value Management Concepts to Improve Commercial Project Performance Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler, LLC www.lewisfowler.com Welcome to the

More information

UNIT 34: COST ACCOUNTING STANDARDS

UNIT 34: COST ACCOUNTING STANDARDS UNIT CERTIFICATION Statement of Completion has satisfactorily completed training in the duty of this Unit under the conditions described below and in accordance with the overall standard(s) for this Unit.

More information

Over Target Baseline and Over Target Schedule Guide

Over Target Baseline and Over Target Schedule Guide Over Target Baseline and Over Target Schedule Guide OUSD AT&L (PARCA) December 5, 2012 1 Table of Contents Section Page No. Introduction 4 Chapter 1. What is Formal Reprogramming? 5 1.1 Formal Reprogramming

More information

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Small Business Process

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Small Business Process DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION Small Business Process Contracts Directorate DCMA-INST 119 OPR: DCMA-AQS 1. PURPOSE. This Instruction: a. Reissues and updates DCMA

More information

GOVERNMENT CONTRACTING MICROSOFT DYNAMICS AX AND

GOVERNMENT CONTRACTING MICROSOFT DYNAMICS AX AND GOVERNMENT CONTRACTING AND MICROSOFT DYNAMICS AX White paper on Government Contracting requirements and considerations in planning for a Dynamics AX implementation. 1 Government Contracting and Microsoft

More information

Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies

Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies Inspector General U.S. Department of Defense Report No. DODIG-2016-001 OCTOBER 1, 2015 Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies INTEGRITY

More information

Property Management System (GPMS)

Property Management System (GPMS) Property Management System (GPMS) Business System Overview Sep 20, 2013 Marcia D. Whitson, CPPM, CF NPMA National President DFARS 252.242-7005 Contractor Business Systems DoD Business Systems Rule - Clarifies

More information

The Changing Government Contractor Environment

The Changing Government Contractor Environment The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.

More information

The Cost Accounting Standards and Consequences of Noncompliance

The Cost Accounting Standards and Consequences of Noncompliance The Cost Accounting Standards and Consequences of Noncompliance Breakout Session E05 Greg Bingham, Vice President, The Kenrich Group LLC Mike LaCorte, Principal, The Kenrich Group LLC Tuesday, December

More information

DCMA EVMS COMPLIANCE REPORT I LOCKHEED MARTIN AERONAUTICS CO.

DCMA EVMS COMPLIANCE REPORT I LOCKHEED MARTIN AERONAUTICS CO. POST ACCEPTANCE REVIEW FOR CAUSE COMPLIANCE REPORT FOR THE LOCKHEED MARTIN AERONAUTICS COMPANY FORT WORTH, TEXAS PREPARED BY: DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) EARNED VALUE MANAGEMENT (EVM) CENTER

More information

Government Contract Accounting Are You DCAA Compliant? Procurement Technical Assistance Program (PTAP)

Government Contract Accounting Are You DCAA Compliant? Procurement Technical Assistance Program (PTAP) Government Contract Accounting Are You DCAA Compliant? Procurement Technical Assistance Program (PTAP) NH Presentation October 20, 2010 Presented by: Fred Kline, MBA, CPA Tom Martin MBA, CPA Malcolm Young,

More information

DEFENSE CONTRACT AUDIT AGENCY 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219. PPS June 26, 2012 INFORMATION FOR CONTRACTORS

DEFENSE CONTRACT AUDIT AGENCY 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219. PPS June 26, 2012 INFORMATION FOR CONTRACTORS DEFENSE CONTRACT AUDIT AGENCY 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 PPS June 26, 2012 DCAA MANUAL NO. 7641.90 INFORMATION FOR CONTRACTORS 1. PURPOSE. This manual supersedes

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security

MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security 1. PURPOSE This memorandum sets forth an understanding of contract audit coverage and related audit

More information

Attachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT

Attachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT Attachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT If the Order involves funds from a Federal government contract or funds from a

More information

DCAA Audit R 4 Rights to Records, Requirements & Remedies

DCAA Audit R 4 Rights to Records, Requirements & Remedies San Diego Chapters Present DCAA Audit R 4 Rights to Records, Requirements & Remedies A Seminar with Panel Discussion and Audience Participation February 18, 2009 This Morning s Agenda 8:30 Introduction

More information

TABLE OF CONTENTS. 1. Understanding 1. 2. Subcontracting Goals 2. 3. Method Used to Develop Subcontracting Goals 2. 4. Master Subcontracting Plan 2

TABLE OF CONTENTS. 1. Understanding 1. 2. Subcontracting Goals 2. 3. Method Used to Develop Subcontracting Goals 2. 4. Master Subcontracting Plan 2 TABLE OF CONTENTS Page 1. Understanding 1 2. Subcontracting Goals 2 3. Method Used to Develop Subcontracting Goals 2 4. Master Subcontracting Plan 2 5. Master Subcontracting Plan Administration 4 6. Opportunities

More information

Inside The Proposed DFARS Business Systems Rule

Inside The Proposed DFARS Business Systems Rule Portfolio Media. Inc. 860 Broadway, 6th Floor New York, NY 10003 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Inside The Proposed DFARS Business s Rule Law360,

More information

Federal Acquisition Certification for Contracting Officer s Representatives (FAC-COR) Handbook

Federal Acquisition Certification for Contracting Officer s Representatives (FAC-COR) Handbook DEPARTMENT OF HEALTH AND HUMAN SERVICES Federal Acquisition Certification for Contracting Officer s Representatives (FAC-COR) Handbook Issued by the Office of the Secretary Office of the Assistant Secretary

More information

Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope

Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope Activity Code 24010 B-1 Planning Considerations Estimating System Survey (ICR) Purpose and Scope The major objectives of this audit are to: Evaluate the adequacy of and the contractor s compliance with

More information

Prepare for Self-Certification of the Government Property Management System

Prepare for Self-Certification of the Government Property Management System Prepare for Self-Certification of the Government Property Management System By Jackie Luo, CEO, E-ISG Asset Intelligence Summary: Government Property Management is one of the 6 mandatory business systems

More information

SMALL BUSINESS JOBS ACT AND NATIONAL DEFENSE AUTHORIZATION ACT FOR FISCAL YEAR 2013 F O R P U B L I C R E L E A S E 1

SMALL BUSINESS JOBS ACT AND NATIONAL DEFENSE AUTHORIZATION ACT FOR FISCAL YEAR 2013 F O R P U B L I C R E L E A S E 1 SMALL BUSINESS JOBS ACT AND NATIONAL DEFENSE AUTHORIZATION ACT FOR FISCAL YEAR 2013 F O R P U B L I C R E L E A S E 1 Overview Small Business Jobs Act of 2010 Pending Regulations Accelerated Payments to

More information

Contractor Purchasing System Review (CPSR) Guidebook

Contractor Purchasing System Review (CPSR) Guidebook DEPARTMENT OF DEFENSE (DOD) Contractor Purchasing System Review (CPSR) Guidebook November 02, 2015 DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) This revision supersedes all previous versions. Table of Contents

More information