1 Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler, LLC Welcome to the PMI Houston Conference & Expo and Annual Job Fair 2015 Please put your phone on silent mode Q&A will be taken at the close of this presentation There will be time at the end of this presentation for you to take a few moments to complete the session survey. We value your feedback which allows us to improve this annual event. 1

2 EV Within PMI Project Cost Management Knowledge Area Controlling and Monitoring Process Group Reference: PMI PMBOK and PMI 2

3 EV Within PM Methodology As an analytical technique for assessing progress of technical maturity through cost and schedule Performance Measurement Reference: PMI PMBOK 3

4 Capabilities of EV Management Objective, measurable metrics Informs the organization decision making process Supports project controls to enable successful project execution through Performance Measurement Relevant to internally driven business efficiency requirements for commercial programs 4

5 Why EV Was Developed Late 1800s Optimize performance of factories 1950s and 1960s Navy developed into PERT/Cost techniques Cost/Schedule Control Systems Criteria (C/SCSC) guidelines in ANSI/EIA-748 by NDIA Performance Measurement as a means to make better business decisions 5

6 What s In A Name Historically driven and mandated within the defense industry Perception of being operationally burdensome Uncomfortable Involves a priori planning and periodic reporting Requires root cause analysis and mitigation Drives accountability and active management Reference: Earning Value from Earned Value Glen Alleman, Aug

7 What EV Isn t or Won t Do Performance Measurement Will not ensure project success by itself Is not a one size fits all strategy Does not make up for a bad plan, incomplete requirements, or poor project management Is not just a government reporting requirement Performance Measurement is not a solution as much as it is an efficiency enabling methodology 7

8 Here s The Value Success enabler Element of PM fundamentals Disciplined project controls and performance monitoring Performance Measurement enhances program management capability through insight Increase the probability of program success Equally applicable in commercial business 8

9 Cost of EVM Process Author (Year) Source of Estimate Cost Range Kouts (1978) MITRE Corp. (1982) DOD IG (1984) Decision Planning Corp. (c1992) Humphreys and Assoc. (c1992) Lampkin (1992) Survey of Industry 0.5% to 5% Survey of Industry 0.1% to 0.2% Survey of DoD Experts 5.0% Industry Cost Estimating Model 0.6% to 1.0% Consultant Experience 0.5% to 4.0% Average of Five Studies Above 0.4% to 1.63% Reference: The Costs and Benefits of the EVM Process D. Christensen, Fall

10 Program Customer Satisfaction Best Worst Minimal Capability Qualified Performer Composite World Class Program Management Capability Reference: DCMC Conference, March

11 When to Consider EV High value programs Long duration programs Progress payment programs Contract types: Firm Fixed, Cost Plus, T&M In support of broader corporate mission to drive efficiency and effectiveness in program execution and utility of organizational resources 11

12 Performance Measurement In support of objective technical maturity Objectively validated and measured timephased cost and schedule performance Alerts program to potential execution problems Absolute or trend measures Enables problem diagnosis by variance analysis that leads to active program risk management 12

13 Why Measure Performance? To further increase the probability of program success through: Risk and opportunity management Program governance and controls Answer the questions Is the program performing according to plan? Are there performance trends emerging? How does this program relate to corporate success? 13

14 Concepts Validate the technical scope Establish The Plan What scope, by when, for how much Measure performance and assess variance Analyze to reveal root cause Implement corrective actions Inform the organization Project and Portfolio levels 14

15 Concept as a System Scope Schedule Cost / Resources Program Funding Earned Value Management System Portfolio Dashboard Performance Analysis Root Cause Determination Corrective Action Planning Performance Measurement/Analysis Cost and Schedule Performance Data Collection 15

16 Performance Measures Cost Measures: CV = EV AC ; CPI = EV / AC Schedule Measures: SV = EV PV ; SPI = EV / PV Estimate-at-Complete (EAC): Various Estimate-to-Complete (ETC): ETC = EAC - AC Reference: PMI PMBOK, Table

17 Establish the Plan Plan what you know in objective terms Entire plan, Rolling Wave Don t create variances during planning Reference: Scott Adams, Inc 17

18 Measure Performance Collect cost and schedule data based on predefined, objective, measureable criteria Scope management through governance Reference: Jorge Cham

19 Assess Variance Mechanical process of determining performance as compared to The Plan Provides visibility in objective terms Focus on primary drivers of plan variance Absolute and relative measures 19

20 Root Cause Meaningful level of detail Ask Why more than once Recommend and implement solutions Capture in risk action register Informs the program of risks and opportunities Reference: MindTools 20

21 Implement Corrective Action Supports the program controls function Assess cost and schedule impacts Baseline program governance Log, track, and report Archive 21

22 Broader Context Risk and opportunity management Dashboard reporting Project portfolio management Projects Programs Portfolios Supportive of enterprise strategic objectives and Value Chain of the organization 22

23 Deploy Incrementally Reconcile objective sources of performance information for cost and/or schedule Measure performance period-over-period Allow the variance analysis to inform next steps in evolving measurement maturity Rigorous management of baseline plan Reveal need for scope management through governance 23

24 Tailored Solution ANSI/EIA 748: Compliant versus Certified Begin with cost or schedule performance Reference: Earning Value from Earned Value Glen Alleman, Aug

25 Overhead Burdens Training and education Stakeholders, PMO Team, Project Managers Supporting IT infrastructure Cost and schedule information collection Excel spreadsheets to enterprise solutions Reporting and analysis time In comparison to value of improved performance and project delivery 25

26 Frame the Conversation Speak in terms of Performance Measures Recognize the value of performance insight Recognize performance data as a corporate asset Value of improved probability of program success outweighs organizational cost factors Improved internal/external customer satisfaction Align to corporate objectives 26

27 Prepare for Implementation Shared vision of what success looks like Stakeholder alignment and visible support Project identity and organizational brand Motivated, capable, and visionary team Integrated governance, change management Build open cross functional relationships 27

28 Company Return On Sales +15% +10% +5% 0% -5% -10% -15% Minimal Capability Qualified Performer Composite World Class Program Management Capability Reference: DCMC Conference, March

29 Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler 383 Inverness Parkway, Suite 475 Englewood, CO Phone: LinkedIn: 29

30 30

31 31

32 32

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

A Framework for Project Metrics

A Framework for Project Metrics A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of

More information

Project Cost Management

Project Cost Management Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Agile Project Management Controls

Agile Project Management Controls 0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,

More information

Training Seminars. Description. Core Courses: The core courses consist of the following:

Training Seminars. Description. Core Courses: The core courses consist of the following: Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 [email protected]

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

EDWARDS PROJECT SOLUTIONS NORTH AMERICAN INDUSTRY CERTIFICATION SYSTEM (NAICS) CODES QUALIFICATIONS WITH FULL DESCRIPTIONS

EDWARDS PROJECT SOLUTIONS NORTH AMERICAN INDUSTRY CERTIFICATION SYSTEM (NAICS) CODES QUALIFICATIONS WITH FULL DESCRIPTIONS REVISED: J 5523920 PORTFOLIO MANAGEMENT SIZE STANDARD: $7.0M Edwards Project Solution ( ) provides portfolio management services through building enterprise project management solutions and providing portfolio

More information

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Expert Reference Series of White Papers. Importance of Schedule and Cost Control Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project

More information

Young Hoon Kwak Associate Professor School of Business The George Washington University

Young Hoon Kwak Associate Professor School of Business The George Washington University Project Management in Government: An Introduction to Earned Value Management (EVM) Improving Performance Series Young Hoon Kwak Associate Professor School of Business The George Washington University Frank

More information

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

The Two Most Useful Earned Value Metrics: the CPI and the TCPI PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was

More information

Scheduling Process Maturity Level Self Assessment Questionnaire

Scheduling Process Maturity Level Self Assessment Questionnaire Scheduling Process Maturity Level Self Assessment Questionnaire Process improvement usually begins with an analysis of the current state. The purpose of this document is to provide a means to undertake

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by: Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you

More information

David S. Christensen, Ph.D.

David S. Christensen, Ph.D. The Costs and Benefits LESSONS of the Earned LEARNED Value Management Process THE COSTS AND BENEFITS OF THE EARNED VALUE MANAGEMENT PROCESS David S. Christensen, Ph.D. Up to now assessments of the earned

More information

Module 5 Cost Management PMP Exam Questions

Module 5 Cost Management PMP Exam Questions Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional

More information

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT OFFICES A PRACTICAL GUIDE TO SETTING UP A PMO (WITH EXAMPLES)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT OFFICES A PRACTICAL GUIDE TO SETTING UP A PMO (WITH EXAMPLES) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT OFFICES A PRACTICAL GUIDE TO SETTING UP A PMO (WITH EXAMPLES) Developed by the Department of Health Informatics Directorate Informatics Capability Development

More information

IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?

IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? 1 IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? Presented at The Nexus of Agile Software Development and Earned Value Management, OSD-PARCA, February 19 20, 2015 Institute for Defense Analysis, Alexandria,

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111

More information

Project Management Office Charter

Project Management Office Charter Old Dominion University Office of Computing and Communication Services Project Management Office Charter Version: 1.0 Last Update: February 18, 2010 Created By: Anthony Fox, PMP OCCS Project Management

More information

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program

More information

Earned Value Management Guidelines

Earned Value Management Guidelines Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application

More information

Project Management Certificate (IT Professionals)

Project Management Certificate (IT Professionals) Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.

More information

PROJECTS SCHEDULING AND COST CONTROLS

PROJECTS SCHEDULING AND COST CONTROLS Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to

More information

Project Management Improving Performance with KPIs Shelia Darby, MBA, PMP Darby Consulting www.darbyconsulting.com

Project Management Improving Performance with KPIs Shelia Darby, MBA, PMP Darby Consulting www.darbyconsulting.com Project Management Improving Performance with KPIs Shelia Darby, MBA, PMP Darby Consulting www.darbyconsulting.com Welcome to the PMI Houston Conference & Expo and Annual Job Fair 2015 Please put your

More information

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT 1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

Project Risk Management

Project Risk Management Project Risk Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Risk Management

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

Building for the future

Building for the future Building for the future Why predictive analytics matter now William Gaker Goals for today Growth and establishment of the people analytics field Best practices for building a people analytics function

More information

Atern The latest version of the DSDM approach which makes DSDM appropriate to all types of project.

Atern The latest version of the DSDM approach which makes DSDM appropriate to all types of project. THE AGILE PROJECT LEADER S DICTIONARY This dictionary attempts to de-mystify the jargon around the world of Agile projects. Part 1 translates common Agile terms into more traditional words. Part 2 translates

More information

Government Contracting and Earned Value Management (EVM)

Government Contracting and Earned Value Management (EVM) Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine

More information

Strategic PMOs Play A Vital Role In Driving Business Outcomes A Part Of PMI s Thought Leadership Series

Strategic PMOs Play A Vital Role In Driving Business Outcomes A Part Of PMI s Thought Leadership Series A Forrester Consulting Thought Leadership Paper Commissioned By Project Management Institute (PMI) November 2013 Strategic PMOs Play A Vital Role In Driving Business Outcomes A Part Of PMI s Thought Leadership

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin

More information

Program Management Professional (PgMP) Examination Content Outline

Program Management Professional (PgMP) Examination Content Outline Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)? Due to the often complex and risky nature of projects, many organizations experience pressure for consistency in strategy, communication,

More information

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information

THE COSTS AND BENEFITS OF THE EARNED VALUE MANAGEMENT PROCESS

THE COSTS AND BENEFITS OF THE EARNED VALUE MANAGEMENT PROCESS THE COSTS AND BENEFITS OF THE EARNED VALUE MANAGEMENT PROCESS David S. Christensen, Ph.D. College of Business Southern Utah University Cedar City, Utah 84720 E-mail: [email protected] Phone: (435)865-8058

More information

Principles of IT Governance

Principles of IT Governance Principles of IT Governance Governance of enterprise IT focuses on delivering services to support top line growth while moving operational savings to the bottom line. The management of IT services has

More information

Assessing the Appropriate Level of Project, Program, and PMO Structure

Assessing the Appropriate Level of Project, Program, and PMO Structure PMI Virtual Library 2011 Daniel D. Magruder Assessing the Appropriate Level of Project, Program, and PMO Structure By Daniel D. Magruder, PMP Executive Summary Does your organization have in-flight projects

More information

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

Presented By: Leah R. Smith, PMP. Ju ly, 2 011

Presented By: Leah R. Smith, PMP. Ju ly, 2 011 Presented By: Leah R. Smith, PMP Ju ly, 2 011 Business Intelligence is commonly defined as "the process of analyzing large amounts of corporate data, usually stored in large scale databases (such as a

More information

CVR/IT Consulting LLC

CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com [email protected] Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value

More information

performance management system that is based on Earned Schedule Management.

performance management system that is based on Earned Schedule Management. The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created

More information

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management

More information

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP Frequently Asked Questions What is the PMP credential? The PMP (Project Management Professional) credential is a globally recognized certification for

More information

Chapter 7. (PMBOK Guide)

Chapter 7. (PMBOK Guide) Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:

More information

Predicting progress on your project

Predicting progress on your project www.nonsuch.co [email protected] Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

Driving PPM Adoption Through Effective Change Management

Driving PPM Adoption Through Effective Change Management Driving PPM Adoption Through Effective Change Management Presenters: David Boghossian, Founder, PowerSteering Software Jay Hoskins, PowerSteering Business PPM Consultant Welcome! Thank you for joining

More information

Chapter 7: Project Cost Management. Munawar [email protected]

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

Earned Value Management Best Practices

Earned Value Management Best Practices Division of Information Technology Investment Management Enterprise Architecture & Strategy Group Office of Information Services Earned Value Management Best Practices Version 2.2 Last Modified: 19 November

More information

Measures and Metrics for PMO Success

Measures and Metrics for PMO Success Project Management Office Summit Measures and Metrics for PMO Success Jim Kendrick, PMP, CMC President and Practice Leader 2009 P2C2 Group, Inc. [email protected] 301-942-7985 Also See Related Blog

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

Principles of Project Management

Principles of Project Management IPM 2012 Conference Principles of Project Management David Radkovich, PMP, EVP Subsystem Technologies [email protected] Karen Jordan, PMP Subsystem Technologies [email protected]

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,

More information

5 Signs You Might Need a Service Management Framework (SMF) Assessment

5 Signs You Might Need a Service Management Framework (SMF) Assessment 5 Signs You Might Need a Service Management Framework (SMF) Assessment White Paper Terry Daffin Visionary Integration Professionals (1) To say running a large IT shop is challenging is an understatement.

More information

ITPMG. February 2007. IT Performance Management: The Framework Initiating an IT Performance Management Program

ITPMG. February 2007. IT Performance Management: The Framework Initiating an IT Performance Management Program IT Performance Management: The Framework Initiating an IT Performance Management Program February 2007 IT Performance Management Group Bethel, Connecticut Executive Summary This Insights Note will provide

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

Software Performance Evaluation Maturity Model (SPE-MM)

Software Performance Evaluation Maturity Model (SPE-MM) Software Performance Evaluation (SPE-MM) Users Group Conference 20 July 1999 Guy Mercurio Defense Contract Management Command Software Center Agenda Introduction Development Goals Structure Pilot Test

More information

Enterprise PMO is a key enabler and foundation for effective enterprise portfolio management.

Enterprise PMO is a key enabler and foundation for effective enterprise portfolio management. Enterprise Program Management Office (EPMO): "Best Practices and PMOs" Stephen C. Hawald - CISM, PMP Our EPMO Ship Has Been Selected For Our Journey! Our PMO is shipworthy and ready to sail across complex

More information

Assessment of NCTD Program Management Framework for Positive Train Control Program

Assessment of NCTD Program Management Framework for Positive Train Control Program Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation

More information

Collaborative Project Management in a DevOps Culture

Collaborative Project Management in a DevOps Culture Collaborative Project Management in a DevOps Culture Speaker: Dennis Baldwin Company: Experis Website: www.experis.com Welcome to the PMI Houston Conference & Expo and Annual Job Fair 2015 Please put your

More information

Tracking Budgets and Schedules

Tracking Budgets and Schedules Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is

More information

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the

More information

Introduction to OpenPPM

Introduction to OpenPPM 0 Introduction to OpenPPM Content Table Introduction to OpenPPM... 1 0.1. OpenPPM: A tool thought by and for Project Managers... 2 0.2. Project, Program and Portfolio Management... 3 0.3. What is not OpenPPM?...

More information

The new licensing model increases the flexibility of organizational use and reduces total cost of ownership.

The new licensing model increases the flexibility of organizational use and reduces total cost of ownership. NEW in CA Clarity PPM v12 In its new Version 12, CA Clarity PPM v12 has been greatly enhanced and now meets the requirements of its target markets such as IT, product development as well as research and

More information

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3 /01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,

More information

MGMT 4135 Project Management. Chapter-16. Project Oversight

MGMT 4135 Project Management. Chapter-16. Project Oversight MGMT 4135 Project Management Chapter-16 Project Oversight Project Oversight: defined as a set of principles and processes to guide and improve the management of projects. Ensures projects meet the needs

More information

Project Control with ProTrack

Project Control with ProTrack Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern

More information

October 7, 2011. Presented to. The PMI Washington DC Chapter. Pedro Agosto. Director of Client Services, XA Systems, LLC. pedro.agosto@xasystems.

October 7, 2011. Presented to. The PMI Washington DC Chapter. Pedro Agosto. Director of Client Services, XA Systems, LLC. pedro.agosto@xasystems. October 7, 2011 Presented to The PMI Washington DC Chapter By Pedro Agosto Director of Client Services, XA Systems, LLC [email protected] Introduction Re-evaluating IT Services Today s Challenges

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

Earned Schedule Leads to Improved Forecasting

Earned Schedule Leads to Improved Forecasting Lipke, Walt Norman, Oklahoma, USA Earned Schedule Leads to Improved Forecasting Abstract For project cost, analysts can predict the final value with some confidence using the Independent Estimate at Completion

More information

Chapter 4. The IM/IT Portfolio Management Office

Chapter 4. The IM/IT Portfolio Management Office Chapter 4 The IM/IT Portfolio Management Office Learning Objectives Identify some of the primary causes of IM/IT project failures. Describe the main differences between IM/IT project management, IM/IT

More information

Michael Landry, MBA, PMP Chief Project Controller

Michael Landry, MBA, PMP Chief Project Controller Artistry of Project Management The Artistry Michael Landry, MBA, PMP Chief Project Controller Leadership is the art of accomplishing more than the science of management says is possible Colin Powell is

More information

Project Cost Management - 2 Days

Project Cost Management - 2 Days Project Cost Management - 2 Days Course Description: The Cost Management course addresses the identification, elaboration, planning, and management of the project budget. Including selected processes from

More information

How To Manage A Project

How To Manage A Project Project Management Framework U.S. Department of the Interior Bureau of Reclamation Technical Service Center September 2012 Mission Statements The U.S. Department of the Interior protects America s natural

More information