1 : It Just Sucks! Presented by: Darryl Cloud Concrete Sealants, Inc. Learning Objectives In this course, you will learn: Terminology for Watertightness Equipment Tips, Tricks, and FAQ s History of Vacuum Testing for Precast Manufacturers of products depend on a number of quality control methods to ensure performance. One method available to the manufacturers of concrete products is vacuum testing. Vacuum testing is an easy and quick method of offering a high degree of reasonableness to the quality, watertighness, and structural integrity to a host of products of varying geometrical configurations. Not that long ago Effective August 1,1960 Deduct $15.00 if Ordered without bottom Terminology and purpose NPCA 1
2 Terminology Definition of a vacuum: According to the definition of the American Vacuum Society (1958) the term "vacuum" refers to a given space filled with gas at pressures below atmospheric. In other words, a vacuum is the state of a gas where the density of the particles is lower than atmospheric pressure at the earth's surface. Terminology Inches of Mercury (in/hg) This is a unit of measure for pressure; it is the measure used by most barometers to measure atmospheric pressure Negative Pressure A pressure that is less than atmospheric, also referred to as a vacuum Watertight Construction such that water cannot pass through except under significant pressure Low Pressure System Vacuum Conversion 1000 = 1 bar = Hg So Why Vacuum Test? To eliminate: Structures: Vacuum testing is performed on: Septic Tanks Manholes Pipe NPCA 2
3 Purpose: Because it improves the seal! Before Vacuum After Vacuum Purpose! Vacuum Force ASTM Specification References C 1214 Concrete Pipe Sewer lines (Field) C 1227, Section 9 Proving water tightness in septic tanks (Plant) C 1244 Concrete Sewer Manholes (Field) C 1618 Concrete Sanitary Sewer Pipe (Plant) Performance Test Methods Test procedures should be clearly defined prior to tank fabrication and installation... Consideration should be given to whether tests will be conducted in the plant or on-site (prior to or after backfilling). ASTM C-1227: Section Vacuum Testing Seal the empty tank and apply a vacuum to 4 inches (100MM) of mercury. The tank is approved if 90% of vacuum is held for 2 minutes. NPCA Best Practice Manual: Introduce a vacuum of 4 inches of mercury. Hold this pressure for five minutes. The tank must have no loss of pressure during the duration of the test. NPCA 3
4 The Precast Show 2014 Alternative Materials Verifying Watertightness in wastewater tanks Orenco literature states that tanks should always be water tested Note: Vacuum testing is not acceptable, as it will not adequately test the flange joint and will not easily reveal very small leaks or leaks created by capillary action. (Orenco assembly instructions NIN-TNK-4) Septic tanks can be tested for water tightness using: The water method Negative pressure / vacuum method WATERTEST vs. VACUUM TEST This is rhetoric! Let see why. Watertight Testing Water Water Column Water Test per ASTM C 1227 Fill tank to the invert of the outlet Let stand for 24 hours Refill the tank Tank passes if water level does not drop within 1 hour ' The force of water is a linear relationship to the height of the column. The force increases by psi per foot. STANDPIPE ' ' ' Local Code Requirement Fill the tank completely into the riser ' 13 30' Hydrostatic Cautions Before Vacuum 1 of water into the riser creates 62 lb/ft2 of lift this will displace a top seal lid Use additional weight when necessary Don t do it if you don t have to! NPCA Before Vacuum A vacuum pulls After thevacuum same at all heights After Vacuum Vacuum Force Vacuum Force ~26 Hg ~30 Hg 4
5 Draw a vacuum on the tank of 4 + Hg Allow tank to settle Return vacuum to 4 Hg Shut valve and hold the vacuum Tank is watertight if there is no loss of vacuum after 5 minutes Watertight Testing: In Field Verifying Watertightness in manholes / pipe Watertight Testing In Plant Manholes and Pipe can be tested for water tightness in the plant with automated equipment. Watertight Testing In Field Manholes and Pipe can be tested for water tightness in the field using a vacuum pump or venturi. NPCA 5
6 Minimum Test Times C a Diameter (in) Depth Time (s) Caution!!!! The negative internal pressure may cause the casting to implode. Alternative Materials This imploded at 11.5 of Hg (800 lb/ft 2 ) Orenco brags about this!!! In there literature, they state that this is substantially higher than the worst-case load =094e0b5cb1b01d712f70 Equipment Vacuum Test Equipment Cherne Vacuum Test Equipment Plug-It NPCA 6
7 Equipment Home made Equipment Alternatives Tips and tricks 1. Use the rubber gasket as supplied 2. Us a small diameter of butyl sealant 3. Use a metal vacuum test lid w/ foam NPCA 7
8 1. Duct tape yea, it can be used for everything! 2. External Joint Warp 3. Expansion pipe plugs 1. Listen shhhh! You ll hear the hissing. 2. Use a power audio detection device. 3. Use water / soapy water 1. Cement slurry 2. Caulking 3. Epoxy sealers 4. Butyl sealant / butyl wrap NPCA 8
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
More informationSEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
More informationSpecifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
More informationSECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
More informationSECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
More informationGrade Level Spill Containment Manholes
Grade Level Spill Containment Manholes Installation Instructions 705-5 Gallon 715-15 Gallon 725-25 Gallon Manual # Revision Date Changes from Previous Revision F-1307 7 Mar. 2012 Removed reference to pipe
More informationCITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General
General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling
More information32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
More informationSANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
More informationSUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.
SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION
More informationDIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
More informationSECTION 03400 PRECAST CONCRETE STRUCTURES
PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, and equipment required to install precast concrete manholes, sanitary leaching rings, pump station, valve chamber, structures, frames,
More informationFY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
More informationSECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationWastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
More informationSection 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
More informationSECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
More informationCity of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING
1.0 GENERAL 1.1 Scope 2.0 PRODUCTS 1.1.1 The work shall consist of testing wastewater and/or storm mains to ensure construction conforms to the proper line, grade, cross section and performance. 2.1 The
More informationFY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
More informationSECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
More informationCLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
More informationSECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
More informationDIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
More informationSECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More informationSECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
More informationBUILDING SEWER CONNECTION REQUIREMENTS
BUILDING SEWER CONNECTION REQUIREMENTS ANY PERSON DESIRING TO MAKE A NEW OR REVISED SEWER INSTALLATION MUST FIRST MAKE APPLICATION WITH THE NORTHERN GILA COUNT SANITARY DISTRICT FOR A PERMIT BEFORE STARTING
More informationGUIDE SPECIFICATIONS FOR PRECAST CONCRETE PRODUCTS
GUIDE SPECIFICATIONS FOR PRECAST CONCRETE PRODUCTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. This specification covers the materials for and manufacture of precast reinforced concrete units produced in
More informationExhibit A. Rules and Regulations for House Connections and Sewer Extensions
The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and
More informationBelow Grade Spill Containment Manholes 705-5 Gallon 715-15 Gallon 725-25 Gallon. Installation Instructions
Below Grade Spill Containment Manholes 705-5 Gallon 715-15 Gallon 725-25 Gallon Installation Instructions Warning Application and use of this product should be in compliance with local, state, and federal
More informationDESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
More informationChecklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System
Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System An application for the construction or alteration of an individual subsurface sewage disposal system shall
More information53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:
Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections
More informationCCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
More informationStormwater/Wetland Pond Construction Inspection Checklist
: Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials
More informationSANITARY GRAVITY SEWER LINE TESTING. B. Section 02732 CCTV Inspection of Gravity Sewer Lines
PART 1 GENERAL 1.1 SECTION INCLUDES A. Low Pressure Air Test B. Deflection Test 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02732 CCTV Inspection of Gravity Sewer Lines
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
More information1. General...1. 1.1 General Requirements... 1. 2. Gravity Sanitary Sewer Testing Requirements...3
Table of Contents 1. General...1 1.1 General Requirements... 1 2. Gravity Sanitary Sewer Testing Requirements...3 2.1 General Requirements... 3 2.2 Test Method & Sequence... 3 2.3 Exfiltration Test - Low
More informationCONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements
16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications
More informationEmerging Technologies in Wastewater Collection Systems
Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation
More informationSeptember 2012 Brunswick County Engineering Department Revision 1.0. Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM
1.0 General Technical Specification 020.01 GRAVITY SANITARY SEWER SYSTEM a) It is the intent of this specification to ensure that all gravity sewer system infrastructure constructed within the service
More information08003-1 WATER SERVICE 2
08003_Mar08_2011.pdf Page 1 of 7 INDEX Page 08003-1 WATER SERVICE 2 1.1 Pipe 2 1.1.1 Copper 2 1.1.2 Polyethylene 2 1.2 Valves and Fittings 2 1.2.1 Main Stops 3 1.2.2 Curb Stops 3 1.2.3 Curb Box 3 1.2.4
More informationGuide Specification Precast Concrete Products
Guide Specification Precast Concrete Products This specificaton should be used only by qualified professionals who are competent to evaluate the significance and limiations of the specification and who
More informationINDEX. Sec. No. Items Page Nos.
INDEX Sec. No. Items Page Nos. 1. Types of Pipe............... MSSP- 2 2. Concrete Pipe............... MSSP- 2 thru MSSP-3 3. ABS and PVC Truss Pipe............... MSSP- 3 4. ABS and PVC Solid Wall Pipe...............
More informationSECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
More informationPRECAST CONCRETE MANHOLES
PRECAST CONCRETE MANHOLES WHY PROVIDE GUIDELINES? Past Problems Was tedious to keep track of variables Was easy to make mistakes Wanted: A design tool to reduce problems TOPICS Overview on Precast Manholes
More informationSECTION 02612 NONREINFORCED CONCRETE SEWER PIPE
SECTION 02612 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Furnishing and installing nonreinforced concrete sewer pipe. Provide concrete sewer pipe less than 12 inches in diameter, and in other sizes
More informationCHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
More informationWastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
More informationSEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
More informationMorrison Bros. Co. General Product Specifications
Morrison Bros. Co. General Product Specifications Tank Mounted Spillbox The spill containment device is manufactured to contain spills and drips that may occur at the fill point on aboveground storage
More informationSeptic Tank Use & Maintenance Tips
Yellowhead County Hamlet of Cadomin Septic Tank Use & Maintenance Tips This guide gives an overview of the responsibilities for property owners in Cadomin. For Seasonal, Permanent & Vacationing Cadomin
More informationThe Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21
September 2013 Page 1 of 21 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of sewers including: the supply and installation of pipe, saddles, tees,
More informationSECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)
CHAPTER 9 SEWER / STORM DRAIN / IRRIGATION LINES SECTION 9.01 GENERAL This section covers the requirements for piping materials and installation of Lehi City sewer, storm drainage and irrigation collection
More informationSECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent
More information3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
More informationSECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
More informationGuidelines for Precast Concrete Grease Interceptors
Guidelines for Precast Concrete Grease Interceptors Purpose Provide an overview of the basic design principals that govern why gravity grease interceptors work Provide a forum for discussion of common
More informationSection 3: Septic Tanks. 3. Septic Tanks
Section 3: Septic Tanks 3. Septic Tanks 3. Septic Tanks 3.1 Design...28 3.2 Installation...29 3.3 Testing...37 3.4 Inspection...37 3.5 Operation...37 3.6 Common technical issues...41 3.7 Case study...41
More informationOnsite Wastewater Concepts, Materials, Regulations & The Application Process Part I
Onsite Wastewater Concepts, Materials, Regulations & The Application Process Part I B Onsite Sewage System Materials Instructors: Bart Harriss, RS, Environmental Manager Florida Department of Health Division
More informationWAVELET WATER QUALITY MONITORING KIT
AYYEKA Rethink Water Monitoring WAVELET WATER QUALITY MONITORING KIT ON OFF QUICK START GUIDE AYYEKA IMPORTANT! Use with pressure applications up to 145 PSI. Contact AYYEKA SUPPORT center for technical
More informationSPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
More informationSTANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete
More informationINSTALLATION OF INSITUFORM LINER
PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationSERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS
1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General
More informationSECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS
SECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS PART 1: GENERAL 1.01 COORDINATION OF WORK Connection to existing pipelines may require shutdown of AW facilities. Closely coordinate construction work
More informationHYLINER AKS HDPE LINING
HYLINER AKS HDPE LINING FOR CONCRETE PIPE Manufactured from HDPE Available in white and black Sheets up to 3 m width D1.12 HyLiner AKS HDPE Lining for Concrete Pipe October 2013 0800 WE PIPE (93 7473)
More informationSeptic System Owner s Manual
Septic System Owner s Manual Sponsored by: copyright 2013 No part of this publication may be reproduced without our consent. www.callbrownies.com Brownie s Septic and Plumbing has provided quality service
More informationENGINEER S LIST OF APPROVED ITEMS POTABLE WATER SYSTEM
ENGINEER S LIST OF APPROVED ITEMS POTABLE WATER SYSTEM General 1. All products must be NSF 61 approved for potable water service 2. All products with brass or bronze must be lead free 3. Advanced written
More information31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE
31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE Edited 21/12/01 Wyong Shire Council has many non sewered areas that
More informationARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.
ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of
More informationOverview PARTS LIST. B. Lever mounting base C. Flush handle assembly D. Grey/Blue float stop E. Grey float (Full Flush) F. Flush valve washer
Overview READ ENTIRE INSTRUCTIONS BEFORE STARTING INSTALLATION PARTS LIST A. Flush valve B. Lever mounting base C. Flush handle assembly D. Grey/Blue float stop E. Grey float (Full Flush) F. Flush valve
More informationSEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER
Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating
More informationSECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to
More informationSEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
More informationOPERATING INSTRUCTIONS AND PARTS LIST FOR U075075 U100058 UNDERGROUND HOSE REELS
OPERATING INSTRUCTIONS AND PARTS LIST FOR U075075 U0005 FORM NO.: 3-00 REV: RAIN BIRD CORPORATION ONE REELCRAFT CENTER COLUMBIA CITY, IN 675 (00) -33 / (60) - FAX: (60) -605 U0005 MODEL NUMBER SIGNIFICANCE
More informationSTANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY
STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water
More informationEXHIBIT "A. Technical Specifications for Water and Sewer Service Lines
EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding
More informationITEM II - SANITARY GRAVITY SEWER PIPE, FITTINGS, & ACCESSORIES
ITEM II - SANITARY GRAVITY SEWER PIPE, FITTINGS, & ACCESSORIES 2.01 General (c) All sanitary gravity sewers shall be constructed of either PVC or Ductile Iron unless otherwise specified in the Special
More informationNational Precast Concrete Association
National Precast Concrete Association NOTES 1. This manual does not claim or imply that it addresses any safety-related issues associated with its use. Operation and maintenance of precast concrete grease
More informationSECTION 33 01 30.13 ACCEPTANCE TESTING FOR SANITARY SEWERS
SECTION 33 01 30.13 ACCEPTANCE TESTING FOR SANITARY SEWERS PART 1: GENERAL 1.01 PERFORMANCE REQUIREMENTS A. Gravity flow sanitary sewers are required to have straight alignment and uniform grade between
More informationSECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES
1.00 PART 1 GENERAL 1.01 SCOPE A. It is the intent of this contract to install a 100% solids epoxy monolithic coating to the walls, benches and inverts of all manholes and the specified surfaces of other
More informationTECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS
TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS Scope of Work Work performed under this contract shall consist of furnishing and installing, complete and ready for service, the sewer
More informationOperating and Maintaining Sewer Systems I Technical Nole No. SAN. 2.0.4 I I
:..-..._ --. Operating and Maintaining Sewer Systems I Technical Nole No. SAN. 2.0.4 I I.-j - / A sewer system Is a self-operating network of underground pipes that carries sewage by gravity flow from
More informationKnowledge Domain: Plumbing Unit: Leaking Skill: Epoxy
Knowledge Domain: Plumbing Unit: Leaking Skill: Epoxy Tools and Parts Required: 1) Jar 2) Oversized lid 3) Epoxy 4) Rubber tube 5) Soapy water 6) Safety goggles 7) Latex gloves 8) Scrap stick to mix epoxy
More informationSECTION 221413 FACILITY STORM DRAINAGE PIPING
SECTION 221413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
More informationSECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
More informationSECTION 02401 - SANITARY SEWER PIPE
PART 1 - GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for furnishing and installing sanitary sewer pipe, in accordance with
More informationSECTION 16402 UNDERGROUND ELECTRIC SERVICE
SECTION 16402 UNDERGROUND ELECTRIC SERVICE PART 1 GENERAL 1.1 SUMMARY A. Description of System 1. Furnish all labor, materials, and equipment for below grade work external to buildings as required, and
More informationSewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority
More informationSECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
More informationGRAVITY SEWER REPAIR MARINE DRIVE CONSTRUCTION COMPLETION REPORT
GRAVITY SEWER REPAIR MARINE DRIVE CONSTRUCTION COMPLETION REPORT PREPARED OCTOBER 9, 2001 PREPARED BY: CITY OF BLAINE, PUBLIC WORKS DEPARTMENT 1200 YEW AVENUE BLAINE, WA 98230 Introduction This completed
More informationWaterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries
Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Introduction Wastewater of petrochemical industries and refineries contains high amounts of emulsified aliphatic or
More informationMinimum Design Criteria for the permitting of Gravity Sewers
Minimum Design Criteria for the permitting of Gravity Sewers Adopted by the Division of Water Quality on February 12, 1996 Updated to 15A NCAC 2T Regulations on March 2008 1,400 copies of this document
More informationSECTION 603 SANITARY SEWER FORCE MAINS
SECTION 603 SANITARY SEWER FORCE MAINS 1. GENERAL Pipelines for sanitary sewer force main systems shall conform to the following specifications and shall be installed at the locations indicated on the