SECTION NONREINFORCED CONCRETE SEWER PIPE
|
|
- Joan Fitzgerald
- 8 years ago
- Views:
Transcription
1 SECTION PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Furnishing and installing nonreinforced concrete sewer pipe. Provide concrete sewer pipe less than 12 inches in diameter, and in other sizes when specifically called for, to be nonreinforced concrete pipe. B. Related Work Specified in Other Sections Includes: 1. Section Laying and Jointing Buried Pipelines 2. Section Leakage Tests 1.2 REFERENCES A. Codes and standards referred to in this Section are: 1. ASTM C 14 - Specification for Concrete Sewer, Storm Drain, and Culvert Pipe 2. ASTM C Specification for Joints for Circular Concrete Sewer and Culvert Pipe, Using Rubber Gaskets 3. ASTM C Test Methods for Concrete Pipe, Manhole Sections, or Tile 1.3 SUBMITTALS A. General: Provide all submittals, including the following, as specified in Division 1. B. Shop Drawings: Submit complete shop drawings of all plastic liner, details of installation and joints between pipes and structures, between other pipes and all other joints for approval. C. Samples: Submit samples of the type of sheet and strip plastic liner plate for approval, together with a list of ingredients from which the sheets and strips are to be compounded. Submit the list to show the Page 1 of 6
2 percentage of each ingredient used in the formulation. No changes in formulation are permitted without prior approval. D. Quality Control: Submit certified test results of all shop tests for approval. 1.4 QUALITY ASSURANCE A. General: Provide concrete sewer pipe that is precast or machine made and of the product of a concern that can demonstrate by tests and installation records satisfactory experience in manufacturing concrete pipe of the quality and type specified. B. Provide nonreinforced concrete pipe meeting the requirements of ASTM C 14 for Class 2 or Class 3 nonreinforced concrete pipe. C. Classes: Provide the classes of concrete sewer pipe for the various pipelines as shown or specified. 1.5 DELIVERY, STORAGE AND HANDLING A. Deliver, store and handle all products and materials as specified in Division 1 (and as follows:) PART 2 PRODUCTS 2.1 MATERIALS A. Concrete Pipe: Manufacture all nonreinforced concrete pipe in the longest lengths normally available except where shorter lengths are required for pipeline curves or at junctions with structures whose location cannot be adjusted. 1. Design: Cure all pipe by steam or membrane curing. Water curing is not permitted. a. Do not deliver pipe to the site of the work until it has attained an age of at least 12 days. B. Specials, Fittings and Accessories: Provide specials, fittings, and accessories where shown, specified or required, and manufactured in accordance with the applicable sections of the respective standard of the adjoining pipe. Provide joints the same as in the adjoining pipe. Page 2 of 6
3 Provide the interior surface of bends of the same smoothness and diameter as the adjoining pipe. Provide the center line radius of curvature to be equal, in dimension, to the inside diameter of the pipe. 1. Strength: Design all specials, fittings, and accessories to have the same strength as the class of the adjoining pipe. Submit working drawings in conjunction with those submitted for the entire pipeline. C. Joints: Have nonreinforced concrete pipe manufactured with bell and spigot ends suitable for use with a rubber gasket joint. 1. Gaskets: Provide pipe ends for use with rubber gaskets that are suitably reinforced or of sufficient thickness to withstand the stresses caused by the compression of the gasket without cracking or fracturing, and provide surfaces that are smooth and free from spalls, cracks, fractures, and imperfections that would adversely affect the performance of the joint. 2. Gasket Design: Provide rubber gaskets of the 0-ring type. Provide the composition and physical requirements of the gasket for joints not normally subjected to internal pressure meeting the requirements of ASTM C 443. Do not stretch the gasket more than 20 percent when placed on the spigot of the pipe. Provide the gasket of such size that when the joint is off center sufficiently to cause the outer surface of the spigot end of the pipe and the inner surface of the bell end of the adjacent pipe to come into contact at some portion of their periphery, the deformation of the stretched rubber gasket is not more than 50 percent at the point of contact nor less than 20 percent at any point of the normal diameter or thickness of the gasket before deformation. Provide the gasket to be the sole element depended upon to make the joint watertight. 3. Bell and Spigot: Provide inside surfaces of the bell and outside surfaces of the spigot to be parallel with each other within one degree and, unless otherwise permitted, with an angle of not more than 2 degrees with the longitudinal axis of the pipe. Angles greater than 2 degrees will be approved only if plant or field hydrostatic tests show that the adjacent pipes can be properly joined and that the joint will not leak under a deflection sufficient to open one side of the joint 1/2-inch wider than the fully compressed position. In no case are angles of greater than 5 degrees Page 3 of 6
4 approved. Provide the spigot with a preformed groove of sufficient depth to hold the gasket securely in place and produce the proper compression in the gasket. 4. Grout: Fill the interior annular space of each joint, for pipe sizes 30 inches and larger in diameter, with cement grout as specified in Section SOURCE QUALITY CONTROL A. Tests: Test concrete sewer pipe in accordance with the applicable provisions of ASTM C 497 as required by the ASTM Specification for the pipe. Test not less than three sections of each size and class of pipe. B. Basis of Acceptance: Conform the basis of acceptance for nonreinforced concrete pipe with Section 5.1 of ASTM C 14. C. Results: Have the manufacturer submit certified test results of these tests for approval. Provide the number of pipe tested equal to one percent of the number of pipe manufactured in any one size and class, except that not less than three pipes are to be tested unless otherwise approved. PART 3 EXECUTION 3.1 INSTALLATION A. General: Install all nonconcrete sewer pipe in accordance with the manufacturer's recommendations and approved shop drawings and as specified in Division 1. B. Install nonreinforced concrete sewer pipe in accordance with the requirements of Section FIELD QUALITY CONTROL A. Tests: After installation of the nonreinforced concrete pipe and all appurtenances, subject the pipeline to a field running test, as specified in Division 1, under actual operating conditions. B. Leakage Tests: Test the nonreinforced concrete pipelines for leakage after completion in accordance with Section Page 4 of 6
5 3.3 SCHEDULES A. Refer to the schedules contained in Section Laying and Jointing Buried Pipelines for information on the piping that is to be constructed using the pipe materials and methods specified herein. END OF SECTION Page 5 of 6
6 (NO TEXT FOR THIS PAGE) Page 6 of 6
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
More informationDIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
More informationSECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
More informationSECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
More informationSECTION 33 41 00 REINFORCED CONCRETE PIPE. A. The following is a list of SPECIFICATIONS, which may be related to this section:
SECTION 33 41 00 REINFORCED CONCRETE PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes construction of reinforced concrete pipe for storm drainage, culverts, and sanitary sewer, including
More informationSection 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
More informationDIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
More informationSECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
More informationSECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
More informationSECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
More informationSUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.
SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION
More information32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
More information725-R-599 PIPE LINING. (Revised 05-01-12) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE
PIPE LINING (Revised 05-01-12) The Standard Specifications are revised as follows: SECTION 725, DELETE LINES 1 THRU 317. SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
More informationSECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 41 03 POLYVINYL CHLORIDE (PVC) PIPE PART 1 GENERAL 1.01 SECTION INCLUDES A. This section includes all labor, materials, equipment, and incidentals required and installation of Polyvinyl Chloride
More informationPRE INSTALLATION MANUAL
REINFORCED CONCRETE PIPE PRE INSTALLATION INSPECTION & REPAIR MANUAL Kentucky Transportation Cabinet Kentucky Department of Highways Division of Materials 1227 Wilkinson Boulevard Frankfort, KY 40601 (502)
More informationCCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
More informationSECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent
More informationSECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
More informationSECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
More informationSECTION 03400 PRECAST CONCRETE STRUCTURES
PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, and equipment required to install precast concrete manholes, sanitary leaching rings, pump station, valve chamber, structures, frames,
More informationSECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
More informationA. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
More informationENGINEERED SOLUTIONS. A2 Liner Pipe for Trenchless Technology
ENGINEERED SOLUTIONS A2 Liner Pipe for Trenchless Technology A2 Liner Pipe Restores Deteriorated Sewers Cost-Effective Rehabilitation The increasing rate of sanitary and storm sewer deterioration requires
More informationManufacturing Standards for Precast Concrete Products. March 2009
Manufacturing Standards for Precast Concrete Products March 2009 MANUFACTURING STANDARDS FOR PRECAST CONCRETE PRODUCTS (MSPCP) City of Portland Bureau of Environmental Services Engineering Services Materials
More informationINDEX. Sec. No. Items Page Nos.
INDEX Sec. No. Items Page Nos. 1. Types of Pipe............... MSSP- 2 2. Concrete Pipe............... MSSP- 2 thru MSSP-3 3. ABS and PVC Truss Pipe............... MSSP- 3 4. ABS and PVC Solid Wall Pipe...............
More informationSTANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified
More informationCHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
More informationSECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
More informationGuide Specification Precast Concrete Products
Guide Specification Precast Concrete Products This specificaton should be used only by qualified professionals who are competent to evaluate the significance and limiations of the specification and who
More informationSTANDARD SPECIFICATIONS & CONSTRUCTION DETAILS MANUAL SECTION 5 - STORM DRAINAGE. 5.01 Design
SECTION 5 - STORM DRAINAGE 5.01 Design Storm drainage facilities shall be designed in accordance with the goals and guidelines set forth in the Unified Development Ordinance. The goal shall be to collect
More informationGUIDE SPECIFICATIONS FOR PRECAST CONCRETE PRODUCTS
GUIDE SPECIFICATIONS FOR PRECAST CONCRETE PRODUCTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. This specification covers the materials for and manufacture of precast reinforced concrete units produced in
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationSpecification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
More informationSECTION 15109 PRESTRESSED CONCRETE CYLINDER PIPE
SECTION 15109 PRESTRESSED CONCRETE CYLINDER PIPE PART 1 - GENERAL 1.01 DESCRIPTION A. Work Specified The work specified shall include all labor, materials, tools, equipment, services, and incidentals necessary
More informationSECTION 9.02 BUILDING SUBSURFACE DRAINS (PERIMETER, ETC.)
CHAPTER 9 SEWER / STORM DRAIN / IRRIGATION LINES SECTION 9.01 GENERAL This section covers the requirements for piping materials and installation of Lehi City sewer, storm drainage and irrigation collection
More informationSECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
More informationMeeting the Challenge of Pipeline Emergency Repair
Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider
More informationSECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
More informationNative InDesign 2890 SaniTite Brochure 1/8" 100 300 CMYK April 17, 07
Sanitary Sewer Pipe Tough pipe for a tough environment SaniTite Sanitary Sewer Pipe delivers the features that engineers, contractors and municipalities demand durability, performance, handling, toughness
More informationFlowtite Jacking Pipe
U.S. COMPOSITE PIPE SOUTH, LLC. MEMBER OF KTI PIPE GROUP OF COMPANIES Flowtite Jacking Pipe 18585 Samuels Rd. Zachary, La. 70791 PH. 225-658-6166 Fax 225-658-0947 www.flowtitepipe.com Flowtite GRP Pipe
More informationCity of West Linn Public Works Standard Construction Specifications. Table of Contents
City of West Linn Public Works Standard Construction Specifications Table of Contents DIVISION SIX STORM DRAIN TECHNICAL REQUIREMENTS... 1 601 PIPE AND FITTINGS... 1 601.01 Description...1 601.02 Materials...1
More informationNAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE
NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE GENERAL a. These specifications may be used in whole or in part by any party without
More informationThe Most Advanced Name in Drainage Systems. Sanitary Sewer Pipe
The Most Advanced Name in Drainage Systems Sanitary Sewer Pipe SaniTite Sanitary Sewer Pipe delivers the features that engineers, contractors and municipalities demand durability, performance, handling,
More informationPIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta
PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification Number: 3503-11.2.610 Rev. 2 Rubber Lined Steel Pipe and Fittings Mechanically Coupled Plain End Type System Issued Revised Approved
More informationSECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
More informationInspection Manual for Precast Concrete Pipe and Structures
Inspection Manual for Precast Concrete Pipe and Structures May 2014 Table of Contents Chapter One Precast Concrete Pipe and Structures Certified Precast Concrete Producer.. 1-1 Materials Material Testing
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More informationPrequalification Requirements For Precast Concrete Drainage Products
Prequalification Requirements For Precast Concrete Drainage Products June 2010 Rev. 9, June 2010 Prequalification Requirements For Precast Concrete Drainage Products August 1998; Rev. 1, June 1999; Rev.
More informationDMS - 7310 REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION AND PLANT QUALIFICATION
DMS - 7310 REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION EFFECTIVE DATE: APRIL 2012 7310.1. Description. This specification will govern for the fabrication of machine-made
More informationTABLE OF CONTENTS SECTION 500 SANITARY SEWER AND FORCE MAIN
TABLE OF CONTENTS SECTION 500 SANITARY SEWER AND FORCE MAIN Starts on Page 500 GENERAL... 2 501 MATERIALS... 2 502 CONSTRUCTION PROCEDURES... 7 503 ABANDONMENT OF EXISTING SANITARY SEWER FACILITIES...
More informationThe Manitoba Water Services Board SECTION 027030 Standard Construction Specifications September 2013 Page 1 of 21
September 2013 Page 1 of 21 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of sewers including: the supply and installation of pipe, saddles, tees,
More informationSECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN
S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain
More informationSECTION 9. All sewer laterals shall tie into the sewer main lines unless approved by the City Engineer.
SECTION 9 SEWER/DRAINAGE LINES 9.1 GENERAL This section covers the requirements for piping materials and installation in the Cedar Hills City sewer and drainage collection system. All materials and workmanship
More informationUse of Corrugated HDPE Products
Chapter 3 Use of Corrugated HDPE Products Orin Bennett USE OF CORRUGATED HDPE PRODUCTS Corrugated HDPE Pipe Characteristics High-density polyethylene (HDPE) is a versatile material and has some ideal characteristics
More informationTECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
More informationBEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION
BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION GENERAL Rehabilitation of culverts with pipe liners is one of several methods available for extending the life of an existing culvert. It is often cost
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More information900 SEWERAGE WORK ITEM 901 - PIPE SEWERS COMPLETE IN PLACE
900 SEWERAGE WORK ITEM 901 - PIPE SEWERS COMPLETE IN PLACE 901.01 Description 901.02 Materials and Material Handling 901.03 Excavation 901.04 Limit as to Width of Trench 901.05 Unauthorized Excavation
More informationRoyal Seal Gasketed Sewer Pipe
Royal Seal Gasketed Sewer Pipe Royal Seal Gasketed Sewer Pipe Royal Seal gasketed sewer pipe with our specially designed Double Seal Locked-In (DSLI ) gasket is an extremely durable pipe with a leak proof
More informationASTM C76, Class III, Wall B, except as modified herein. Clean natural sand, ASTM C33. Artificial or manufactured sand will not be permitted.
SECTION 3000 - SANITARY SEWERS 3001 SCOPE. This section applies to sanitary sewer construction and shall consist of furnishing all labor, materials, and equipment for the complete installation of sewers
More informationCW 2130 - GRAVITY SEWERS TABLE OF CONTENTS
August 2010 CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications... 1 1.4 Referenced Standard Details...
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
More informationPRECAST CONCRETE MANHOLES
PRECAST CONCRETE MANHOLES WHY PROVIDE GUIDELINES? Past Problems Was tedious to keep track of variables Was easy to make mistakes Wanted: A design tool to reduce problems TOPICS Overview on Precast Manholes
More informationSECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION
SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density
More informationCity of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS
City of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS Page No. 1.0 INTRODUCTION...2 2.0 PIPE MATERIAL CONSIDERATIONS...3 2.1 RCP...
More informationSPR PE Steel Reinforced Liner
ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has
More informationHDPE PRODUCTS QUALITY, PERFORMANCE AND ECONOMY COMBINED
QUALITY, PERFORMANCE AND ECONOMY COMBINED LANE S HDPE DRAINAGE PIPE Scan for more information on Lane s HDPE product line. Lane provides the complete product line to meet all your HDPE drainage needs -
More informationTECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS
TECHNICAL SPECIFICATIONS GRAVITY AND PRESSURE SEWER LINE AND MATERIALS Scope of Work Work performed under this contract shall consist of furnishing and installing, complete and ready for service, the sewer
More informationStorm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
More informationPIPE REHABILITATION. Industrial Wastewater Municipal Wastewater Drinking Water Pressure Pipes
PIPE REHABILITATION Industrial Wastewater Municipal Wastewater Drinking Water Pressure Pipes About Us An HDPE after mechanical insertion into an egg-shaped brick work sewer sized 1400 x 2100 mm (or 56
More informationSTANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete
More informationSECTION 15105 DUCTILE IRON PIPE AND FITTINGS
SECTION 15105 DUCTILE IRON PIPE AND FITTINGS PART 1 GENERAL.01 COORDINATION OF WORK Connection to existing pipelines may require shutdown of Owner facilities. Closely coordinate construction work and connections
More informationSECTION 02400 - STEEL PIPE, MORTAR LINED AND COATED
SECTION 02400 - STEEL PIPE, MORTAR LINED AND COATED PART 1 - GENERAL 1.1 WORK INCLUDED IN THIS SECTION A. The WORK of this Section includes providing mortar-lined and mortarcoated steel pipe, including
More informationDESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
More informationSECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS
SECTION 33 11 00.15 DUCTILE IRON PIPE AND FITTINGS PART 1: GENERAL 1.01 COORDINATION OF WORK Connection to existing pipelines may require shutdown of AW facilities. Closely coordinate construction work
More informationCITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General
General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling
More informationSECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
More informationAIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
More informationSECTION 200: STORM SEWER CONSTRUCTION STANDARDS
SECTION 200: STORM SEWER CONSTRUCTION STANDARDS Page No. Description 200-2 201 GENERAL 200-2 201.1 SPECIFICATIONS 200-2 201.2 CONNECTION TO EXISTING FACILITIES 200-3 202 MATERIALS 200-3 202.1 PIPES 200-4
More informationSECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
More informationMATERIALS DIVISION MEMORANDUM
MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Precast Concrete SPECIFIC SUBJECT: Quality Control Plan Review Check list; Approved list Nos. 26 and 34; Precast Repair Manual NUMBER: MD 286-06 DATE: December
More informationSTORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES
CITY OF PETALUMA STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES AUGUST 1999 Revised 10/98 City of Petaluma Petaluma, California STORM DRAIN INSTALLATION DETAIL
More informationSECTION 603 SANITARY SEWER FORCE MAINS
SECTION 603 SANITARY SEWER FORCE MAINS 1. GENERAL Pipelines for sanitary sewer force main systems shall conform to the following specifications and shall be installed at the locations indicated on the
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-33 30 00 (April 2008) Change 3-11/14 -------------------------- Preparing Activity: USACE Superseding UFGS-33 30 00 (July 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationSECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL
SECTION 02110 - ASBESTOS CEMENT PIPE REPAIRS, DEMOLITION, AND DISPOSAL PART 1 - GENERAL 1.1 WORK INCLUDED IN THIS SECTION A. The WORK of this Section includes the repair, demolition, and disposal of asbestos
More informationSECTION 02401 - SANITARY SEWER PIPE
PART 1 - GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for furnishing and installing sanitary sewer pipe, in accordance with
More informationSECTION 7- STORM SEWER
SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...
More information550 PIPE CULVERTS, SEWERS AND DRAINS
551.01 550 PIPE CULVERTS, SEWERS AND DRAINS 551 GENERAL 551.01 Description 551.02 Materials 551.03 Excavation 551.04 Protection of Excavation 551.05(a) Bedding for Rigid Pipe 551.05(b) Bedding for Non-Rigid
More informationFoundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
More informationPIPE INSPECTION AND REPAIR. Larry Ritchie
PIPE INSPECTION AND REPAIR Larry Ritchie February 23, 2010 PIPE INSPECTION AND REPAIR The Florida Department of Transportation builds and maintains hundreds of miles of underground infrastructure as part
More informationSANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
More informationITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationSection 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
More informationSection Four: Linings and Coatings
Section Four: Linings and Coatings SPIRALWELD PIPE The majority of steel water pipe furnished today is specified to be provided with both an interior lining and an exterior coating. AMERICAN offers a wide
More informationSECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
More informationSECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.
SECTION 02732 BUILDING SEWERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Lateral piping, fittings, and accessories. B. Connection of building sanitary drainage system to municipal sewers. 1.02 REGULATORY
More informationAPPENDIX K PIPE INSPECTION
APPENDIX K PIPE INSPECTION **Virginia Test Method 123** Post Installation Inspection of Buried Storm Drain Pipe and Pipe Culverts June 25, 2010 SCOPE For all roadway projects that are constructed by private
More informationSECTION 15056 DUCTILE-IRON PIPE AND FITTINGS
SECTION 15056 PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. A written request to use Ductile
More information