Thanet Offshore Wind Farm www.gl-nobledenton.com Applied Intelligence
Thanet History Crown Estates Round 2 100 x 3MW WTGs to provide 300MW 33kV Array to Substation 132kV to Shore Two Export Cables to Richborough Power Station July 2005 GL commenced engineering for Warwick Energy September 2007 CRC acquired TOW November 2008 Vattenfall Wind Power acquired TOW 11/05/2010 2
Thanet Location 11/05/2010 3
Challenge Financial Closure through Project Execution to Project Completion 11/05/2010 4
Thanet Offshore Wind Farm Vattenfall Wind Power - Client - Principal Contractor GL Noble Denton - Project Management Services - CDM Coordinator - Marine Warranty Surveyor Management - Foundations Installation 11/05/2010 5
CDM 2007 Construction Phase Plan (CPP) CPP Supporting Procedures Principal Contractor CDM Coordinator Procedures and Risk Assessments Authority to Commence Work 11/05/2010 6
Contract Status Form of Contract e.g. Lump Sum HSE Document Control Planning Cost Control Interfaces Risk Management Package management QA / QC 11/05/2010 7
Level 1 Schedule 11/05/2010 8
Project Organogram Project Assistant Hanne Kongstad Steering Group / Sponsor TBA Project Director Ole Bigum Nielsen Client Project Manager Gordon Clark Head of HSE Kevin Lennon Economic Control Thomas Olofsson QHSE Gordon Clark Certification DNV Project Engineer Gordon Clark PR & Communications Mandy Broughton Marine Warranty Noble Denton Consultants Commercial Manager Chris Hughes-Rees Construction Manager Ray Guy O&M Site Manager Jimmy Hansson Legal VAB / ND Consultants Cost / Contracts Engineer Peter Watson Programme HS&E Manager Peter Butler Insurance MARSH Brokers Project Support Sarah Eastmond Quality Steve Mason / Peter McGrath CDM Practitioner Kellie Field Risk Management Chris Hughes-Rees / Peter Watson Interfaces Naval Sondhi/ Andy Reed Consents Royal Haskoning Kit Hawkins Document Control Karolina Kolacynska Risk Management Peter Butler Port of Ramsgate Stephen Reynolds HS&E Andy Walker SAP John Harrison Marine Coordination SeaRoc Port Technicians Wind Turbines Poul-Erik Larsen WTG Installation Find V Poulsen SCADA Lars Højholt Power Plant Control Jesper Runge Kristensen Foundations Naval Sondhi Andy Reed Ramboll Foundations Design Monopiles Transition Pieces Electrical Stig Holm Sørensen Garrad Hassan Terry Foster Cardiff Power Dafydd Rickard Array Cable Reps Polar Prince Cable Installation Stig Holm Sørensen Export Cables David Smail Inter Array Cables Glen Evertsen Foundation Installation Management Garry Blowers Management of all Foundation Installation Management Contracts Offshore Sub-Station Martin Rendell Jacket and Piles Shore End Ops 11/05/2010 Normand Mermaid Subocean Services 9 Site Manager Søren Thor Export Cable Reps UR101 Discoverer Diving & Tower Crews Osiris Topsides Loadout / Transportation Installation and Hook-Up
Current Status Monopiles / TPs 100 Cables 89 WTGs 65 Substations 2 Export Cables 1 of 2 Strings Energised 2 of 10 Contracts Placed 77 Operations Building 1 11/05/2010 10
Monopiles in Fabrication 11/05/2010 11
Sea Jack Used for Monopile and TP Installation 11/05/2010 12
MPs in Installed with Navigation Aids 11/05/2010 13
TPs in Yard 11/05/2010 14
TP Installation 11/05/2010 15
Resolution Used for TP and WTG Installation 11/05/2010 16
Sea Jack installing TPs 11/05/2010 17
Ramsgate Site 11/05/2010 18
Ramsgate Site Layout 11/05/2010 19
Onshore Substation Richborough 11/05/2010 20
Onshore Export Cable Works - A256 11/05/2010 21
Polar Prince DP Vessel for Cable Lay 11/05/2010 22
Normand Mermaid Cable Lay 11/05/2010 23
UR101 Export Cable Lay 11/05/2010 24
Cable Plough 11/05/2010 25
Euro Duct 11/05/2010 26
Offshore Substation Topsides Construction 11/05/2010 27
Offshore Substation Jacket Construction 11/05/2010 28
Stanislav Yudin Offshore Substation Installation 11/05/2010 29
Installation of Offshore Substation by Yudin 11/05/2010 30
Offshore Substation Installation by Yudin 11/05/2010 31
Vessels working in the Field things get busy at times 11/05/2010 32
Offshore Substation Installed 11/05/2010 33
Excalibur Used for Offshore Substation Hook-up 11/05/2010 34
Met Mast Installation on Offshore Substation 11/05/2010 35
Marine Mammal Observation - 11 th April 2009 11/05/2010 36
Installation of WTGs by Resolution 11/05/2010 37
WTG Installation by Resolution 11/05/2010 38
Lessons Learnt Project Management CDM 2007 Contract Status Marine Operations Design Optimisation 11/05/2010 39
Project Management HSE Document Control Planning Cost Control Interfaces Risk Management Package Management QA / QC 11/05/2010 40
Typical Project Management REDS Diving Support OWPMS Crew Vessel Charter ABJV Pile Gripper personnel Gardline Crew Vessel Charter Dutch Heavy Lift Densit Fugro Seacore IHC Hydrohammer IHC Handling NCS Gardline Sea Contractors Refurbishment of Pile Gripper Grouting Services Drilling Hammer Rental Pile Lifting Tool (Rental) Positioning Base Station Marine Mammal Observation Harbour Tug Hire Subacoustech Envrioserve VG Lift Engineering Storm Trinity House Brown and May Jon Ford Arie Dirk Noise Monitoring Guard Vessel Lift Supervisors Weather Forecasting Rental of Marker Buoys Herring Survey Bird Surveyor Bird Surveyor 11/05/2010 41
Cost Forecast Missing Items Accuracy Risk Assessment 11/05/2010 42
Marine Operations Onshore Site and Marine Support CDM-2007 Safety File Construction Vessel Coordination Crew Vessel Coordination Weather 11/05/2010 43
Design Overview and Optimisation String Completion Common Monopile Diameters Design for Installations Cable Installation Methodology 11/05/2010 44
Conclusions Plan the Work Work the Plan Plan Early Appreciate Project Status Do Not Skimp on Project Management Identify and Manage Risk 11/05/2010 45
Thank you for your attention! For further information visit www.gl-nobledenton.com 11/05/2010 46
Thank you for your attention! For further information visit www.gl-nobledenton.com 11/05/2010 47
Thank you for your attention! For further information visit www.gl-nobledenton.com 11/05/2010 48
Thank you for your attention! For further information visit www.gl-nobledenton.com 11/05/2010 49