Brainstorm. What is Cost and Project Cost Management?



Similar documents
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Chapter 7: Project Cost Management. Munawar

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 3: Project Cost Management

How To Manage Project Cost Management

Chapter 5: Project Cost Management

IST 302 : Project Cost Management

INSE 6230 Total Quality Project Management

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

An introduction to Earned Value Analysis

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

Using Earned Value Management for Improving Processes. By Cynthia K. West

700 Analysis and Reporting

Project Cost Management

Chapter 7. (PMBOK Guide)

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Project Cost Management

Estimating Cost at Completion - Judgment & EV Information

Earned Value Formulae

Introduction to earn value management in Civil Engineering

Module 5 Cost Management PMP Exam Questions

Predicting progress on your project

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Earned Value and Agile Reporting

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

AACE International Recommended Practice No. 86R 14

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Project Cost Control: The Way it Works By R. Max Wideman

Appendix D Glossary Of Terms

Project Cost Management. Richard Boser

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

COINS EVA Earned Value Analysis

How To Manage Project Cost Management

How To Manage A Project

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

CPM -100: Principles of Project Management

Project Cost Management

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Earned Value Management Guidelines

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Project Control with ProTrack

plans based on actual cost, schedule and technical progress of work [1, 9].

PERCEPTION. Tracking Progress & EAC

EVM.01. Earned Value Analysis Why it Doesn't Work

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

L10: Budgeting and Cost Control. Olivier de Weck

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

10.1 Communications Planning 10.2 Information Distribution Figure Performance Reporting 10.1 Communications Planning 10.

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Project Cost Management.

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

Certification Exam Objectives: PK0-003

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT Approval Date:

Simple Earned Value (Using MS Project 2010)

Tracking Budgets and Schedules

Project Management Using Earned Value

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Applied Project Management ( APM )

PROJECT COST MANAGEMENT

Project Management for Scientists

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam

PMI Lexicon of Project Management Terms

PMP Exam Preparation Answer Key

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

Earned Value Management Best Practices

Tracking Software Development Progress with Earned Value and Use Case Point

Project Cost Management

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

Project Management Glossary

Earned Value Management for Enterprise Resource Planning Implementations

State of Michigan (SOM) August Department of Technology, Management & Budget

What is the Health of my Project?

Agile Project Management Controls

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Project Execution - PM Elements

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Is Poor Project Management a Crime?

A Gentle Introduction to Earned Value Management Systems

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

PROJECT SCHEDULING AND TRACKING

Cost management and Control of Construction Project

Project Management: Tracking Progress and Earned Value with MS Project 2003

Earned Value Management System Description

Sample Examination Questions

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

Cost Management. How Much Will This Project Cost?

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

Transcription:

Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations, and so on. How do you estimate the cost of this project? Chapter 7 Project Cost Management November 10, 2008 2 Why Project Cost Management? IT projects have a poor track record for meeting budget goals The CHAOS studies found the average cost overrun (the additional percentage or dollar amount by which actual costs exceed estimates) ranged from 180 percent in 1994 to 43 percent in 2002; other studies found overruns to be 33-34 percent Example: The United Kingdom s National Health Service IT modernization program was called the greatest IT disaster in history by a London columnist, with an estimated $26 billion overrun What is Cost and Project Cost Management? Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange Costs are usually measured in monetary units like dollars Project cost management includes the processes required to ensure that the project is completed within an approved budget 3 4 1

Project Cost Management Processes Cost estimating: developing an approximation or estimate of the costs of the resources needed to complete a project Cost budgeting: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance Cost control: controlling changes to the project budget Project Cost Management Summary 5 6 Basic Principles of Cost Management Most members of an executive board better understand and are more interested in financial terms than IT terms, so IT project managers must speak their language Profits are revenues minus expenditures Profit margin is the ratio of revenues to profits Life cycle costing considers the total cost of ownership, or development plus support costs, for a project Cash flow analysis determines the estimated annual costs and benefits for a project and the resulting annual cash flow Cost of Software Defects Relative cost to repair defects: It is better to find and fix software defects early. 7 8 2

Basic Principles of Cost Management Tangible costs or benefits are those costs or benefits that an organization can easily measure in dollars Intangible costs or benefits are costs or benefits that t are difficult to measure in monetary terms Direct costs are costs that can be directly related to producing the products and services of the project Indirect costs are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project Sunk cost is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs Basic Principles of Cost Management (continued) Learning curve theory states that when many items are produced repetitively, the unit cost of those items decreases in a regular pattern as more units are produced Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict Contingency reserves allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline Management reserves allow for future situations that are unpredictable (sometimes called unknown unknowns) 9 10 Cost Estimating Types of Cost Estimates Project managers must take cost estimates seriously if they want to complete projects within budget constraints ts It s important to know the types of cost estimates, how to prepare cost estimates, and typical problems associated with IT cost estimates 11 12 3

Cost Management Plan A cost management plan is a document that describes how the organization will manage cost variance on the project A large percentage of total project costs are often labor costs, so project managers must develop and track estimates for labor Cost Estimation Tools and Techniques Basic tools and techniques for cost estimates Analogous or top-down estimates: use the actual cost of a previous, similar project as the basis for estimating the cost of the current project Bottom-up estimates: involve estimating individual work items or activities and summing them to get a project total Parametric modeling: uses project characteristics (parameters) in a mathematical model to estimate project costs 13 14 Typical Problems with IT Cost Estimates Estimates are done too quickly Later estimates are the more precise Estimates are done at various stages of the project, and the project manager need to explain the rationale for each estimate. Lack of estimating experience Software developers have less experience with cost estimation. To improve: Good project management technique Develops a history of keeping reliable project information, including estimates Training and mentoring on cost estimating Typical Problems with IT Cost Estimates (continue) Human beings are biased toward underestimation Senior professionals / project manager might make estimates based on their own abilities Forget to allow for extra costs needed for integration and testing on large IT project Management desires accuracy Management want a more accurate estimate to help them create a big to win a major contract or get internal funding To improve: Project manager should help develop good cost and schedule estimates and to use their leadership and negotiation skills to stand by those estimates 15 16 4

Cost Estimate: Practice Before creating an estimate, know what it will be used for, gather as much information as possible, and clarify the ground rules and assumptions for the estimate If possible, estimate costs by major WBS categories Create a cost model to make it easy to make changes to and document the estimate Cost Estimate: Practice 17 18 Software Development Cost Estimate Cost Budgeting Cost budgeting involves allocating the project cost estimate to individual work items over time The WBS is a required input to the cost budgeting process since it defines the work items An important goal is to produce a cost baseline A time-phased budget that project managers use to measure and monitor cost performance 19 20 5

Sample Cost Baseline Cost Control Project cost control includes: Monitoring cost performance Ensuring that only appropriate project changes are included in a revised cost baseline Informing project stakeholders of authorized changes to the project that will affect costs *Numbers are rounded, so some totals appear to be off. It is important for the team to document assumptions they make when developing the cost baseline and have several experts review it. 21 22 Earned Value Management (EVM) EVM is a project performance measurement technique that integrates scope, time, and cost data Given a baseline (original plan plus approved changes), one can determine how well the project is meeting its goals You must enter actual information periodically to use EVM More and more organizations around the world are using EVM to help control project costs Earned Value Management Terms The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date 23 24 6

Rate of Performance Rate of performance (RP) is the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity Cost variance (CV) is the earned value minus the actual cost Schedule variance (SV) is the earned value minus the planned value Cost performance index (CPI) is the ratio of earned value to actual cost Schedule performance index (SPI) is the ratio of earned value to planned value Earned Value Formulas 25 26 Rules of Thumb for Earned Value Numbers Negative numbers for cost and schedule variance indicate problems in those areas CPI and SPI less than 100% indicate problems Problems mean the project is costing more than planned (over budget) or taking longer than planned (behind schedule) The CPI can be used to calculate the estimate at completion (EAC) an estimate of what it will cost to complete the project based on performance to date; the budget at completion (BAC) is the original total budget for the project Earned Value Chart for Project after Five Months 27 28 7

Project Portfolio Management Many organizations collect and control an entire suite of projects or investments as one set of interrelated activities in a portfolio Five levels for project portfolio management 1. Put all your projects in one database 2. Prioritize the projects in your database 3. Divide your projects into two or three budgets based on type of investment 4. Automate the repository 5. Apply modern portfolio theory, including risk-return tools that map project risk on a curve Benefits of Portfolio Management Schlumberger saved $3 million in one year by organizing 120 information technology projects into a portfolio META Group research shows that: Organizations that evaluate information technology projects by what their business impacts are and what their potential business values will be implement projects that result in 25 percent more improvement to the bottom line Business executives state that using project portfolio management allows managers to make decisions faster and with more confidence 29 30 Chapter Summary Project cost management is a traditionally weak area of IT projects, pojects, and project poject managers aages must work to improve pove their ability to deliver projects within approved budgets Main processes include: Cost estimating Cost budgeting Cost control 31 8